HomeMy WebLinkAboutContract 57045-CO2FORTV\TORTH •• City of Fort Worth Change Order Request CSC No. 57045-CO2 Project Name: I ICAP Contract Part 1 (M·458-A) Project No.(s): I 59607-0700430-101339-01780 DOENo. I N/A I City Sec No.: I 57045 :=::=====::::: I City Proj. No.: I 101339 Project Description: Installation of30-inch Sanitary Sewer Line and Cured-ln-P1ace Pipe for ICAP Contract Part I (M-458A) WillCo Underground, LLC City Project Mgr.! Scott Taylor �==�====: A'lone Number: I 817-392-7240 Enter Department(s) to the Right OriQinal Contract Amount Extras to Date Credits to Date I PendinQ ChanQe Orders (in M&C Process) Contract Cost to Date I Amount of Prooosed Cha nae Order .. Revised Contract.Amount Oriqinal Funds Available for ChanQe Orders RemaininQ Funds Available for this CO r,,.,� Additional Fundinq (ifnecessarv) " . ., - ,I f Change Order# I 2 Date: City Inspector: I Stepehn Martinez A'lone Number: I 817-392-6051 Sewer Totals $2,099,800.00 -$2 099,800.00 $199,972.98 $199 972.98 --- i,. $2 299 772.98 $2 299 772.98 $61.407.38 $61 407.38 $2 361,180.36 $2,361,180.36 $104,990.00 � $104 990.00 :, $61.407.38 . $61407.38 CHANGE ORDERS to DATE (INCLUDING THIS ONE} AS% OF ORIGINAL CONTRACT 12.45% MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%} $2,624 750.00 6/25124 Contract Time (Calender d:IV!I\ 210 060 - i� 270 ".! C 270 (. ·:-1. . _ . _ :·lJUSTJflCATI0N <REASONSJ FOR CHANGSiORDER�l: ,,;,''-';';, .. ···~· .. ··-. , .. Change Order No. 2 provides compensation to the contractor having to return to the job site to complete installation of the project30-inch sanitary sewer main pending relocation of a conflicting power line by Oncor. In addition, by pass pumping will be necessary in order to make the final connection to the downstream manhole. It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents enfin full b • � M&cNumber oaa Jul25,2024 Fc �-�• _„_Wc� •i• H �� City of Fort Worth Change Order Additions f�ojectName ICAP Contract Part 1 M-458-A City Sec No.: 57045 Project No.(s): 59607-0700430-101339-01780 DQE No. N A City Proj. No.: 101339 Project Description Installation of 30-inch Sanitary Sewer Line and Cured-In-Place Pipe for ICAP ConVact Part I(M-458A) Contractor WiIICo Under round, LLC Change Order: U Date: 524 Ciry Project Mgr. Scott Ta or City Inspector Ste ehn Martinez ADDITIONS ss Sewer Sewer .38 Page 1 of 1 FURT WORTH Project Name ICAP Contract Part 1(M-458-A) Project No.(s): 59607-O7d0430-t Ot 339-01780 C ity of Fort Worth Change Order Deletions City Sec No : 57045 DOE No. N/A City Proj. No.: 101339 Project Desc.�ip6on Installation of 36•inch Sanitary Sewer Line and Cured-In-Place �ipe for ICAP Contract Part I(M-458A) I Contractor WiIICo Underground, LlC Change Order: � Date 6R5�14 CiryProjectMgr. ScottTayfor Citylnspector: StepehnMartinez DELETIONS REM OESCRIPTlQN DEPT Qtv Unit Un� Cost Total Sewer Dele6ons Sub Total Page 1 of 1 Page 1 of 1 6/25/2024 ICAP Contract art 1 (M-458-A) CPN 101339 Change Order 2 Notes Staff has reviewed the requested prices and considers them to be fair and reasonable. .Contract Compliance Manager By signing I acknowledge that I am the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements. Signature Scott Taylor, P.E. Name of Employee Project Manager Title ATTEST: Jannette Goodall City Sec re ta ry