HomeMy WebLinkAboutIR 7246 INFORMAL REPORT 70 CITY COUNCIL MEMBERS No. 7246
10*,- To the Mayor and Members of the City Council
January 5, 1988
ux
�raX Subject: STATUS REPORT ON DESIGN, CONSTRUCTION AND
NAINTENANCE PROCESS FOR CITY BUILDINGS
Recently, questions have arisen com-rning the condition of City buildings.
The following is a summary of the design, construction and maintenance pro-
cess currently in effect for City buildings. Councilman Gilley has
recamerded that the City explore the desirability of reorganizing the City
facilities function into a new department devoted strictly to building
design, construction, inspection and maintenance. This report provides
background information as we begin work on Mr. Gilley's request.
Building Design and Construction
Building design and construction has been the responsibility of public works
officials for as long as records indicate. In 1981, the Transportation and
the Public Works Departments were combined into a single department but the
duties remained within the department. Prior to 1981, public building
construction projects were administered by an Assistant Public Works Director
and staff who monitored contracts between the City and
architectural/engineering consultants and construction contractors. City
staff was responsible for interviewing and recommending
architectural/engineering consultants for project design and administration
00p, for City Council approval. After the project was designed, bids were let and
a contract awarded. During the construction phase, the
architectural/engineering consultant represented the City on the job and was
responsible for recommending change orders and resolving problems involving
the construction contractor. City staff would visit the job site
occasionally but did not make formal inspections of the work in progress.
When conflicts between the construction contractor and the architectural/
engineering consultant could not be resolved, City staff became involved.
These conflicts and the lack of real inspection services indicated a need to
revise the established procedures. As a result, organizational and
procedural changes were first implemented in 1980, with additional changes
made in 1981, 19$5, 1986. The procedures currently in effect are described
below:
1. Architectural/engineering consultants are interviewed by a selection
committee comprised of representatives of the operating department,
any appropriate City Board or Commission, the City Manager's Office,
the MBE/WBE Office and the Transportation/Public Works Department.
After evaluating the proposals submitted, the selection committee
makes a recommendation to the City Council. The contract with the
consultant usually includes project design and limited construction
period services. These contracts are administered by a section of
the Transportation and Public Works Department which includes the
City Architect and an Engineering Technician.
OWL
[ISSUED BY THE CITY MANAGER FORT WORTH, TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS No, 7246 2
To the Mayor and Members of the City Council January 5, 1988
'rax Subject: STATUS REPORT ON DESIGN, CONSTRUCTION AND
tells MAINTENANCE PROCESS FOR CITY BUILDINGS
2. During the design phase, the operating department, various City
agencies and other appropriate groups, are consulted to ensure proper
design.
3. When plans have been completed, review and approval by the City
Architect, City Engineer, City Traffic Engineer, City Building Offi-
ial , Deputy Water Director, Building Maintenance Superintendent,
Assistant Construction Engineer for Public Buildings and the
operating department head is required before the plans can be
advertised. Though this procedure is time-consuming, it is
considered to be necessary as it establishes checks and balances,
reduces future problems, and actually saves time in the long run.
4. Prior to 1981, the City normally did not obtain building permits for
City building projects. In retrospect, this practice was short-
sighted, since many of the problems that the City must now correct
might have been avoided had building permits been issued since it
excluded review by the City Development Department's building
inspectors. Since 1981, building permits have been required for all
new building projects and for all major building remodeling/repair
projects.
5. Inspections currently are performed by our in-house inspection per-
sonnel or by an independent inspection consultant. The City's
In-House Inspection Section was established in 1986 and has five
employees currently assigned to it which includes an Assistant
Construction Engineer for Public Buildings and f our Senior
Construction Inspectors. The use of necessary checks and balances
of City Inspectors or inspection consultants provides the
necessary checks and balances needed to insure a quality construction
product.,
6. Currently contracts are let to a general contractor or, in some
instances, a construction manager is retained and the City contracts
for the individual trades. If a construction manager is retained,
that contract is awarded as soon as possible in order to have input
and suggestions from the construction manager during the design
process.
7. When the construction bids are received, City staff evaluates both
the individual bid and the construction company. The evaluation team
consists of the architectural/engineering consultant, the City Archi-
tect, the City Attorney's Office, the MBE/WBE Office, the Construc-
tion Manager (if retained) , the Assistant Construction Engineer and
the Assistant Transportation and Public Works Director. Based on
0101 this review, City staff recommends the contract be awarded to the
k lowest qualified bidder.
[ISSUED BY THE CITY MANAGER FORT WORTH, TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 7246 •3
'OLPT140
"I I J?*'
-.0
To the Mayor and Members of the City Council January 5, 1988
.*
Subject: STATUS REPORT ON DESIGN, CONSTRUCTION AND
to 3
MAINTENANCE PROCESS FOR CITY BUILDINGS
8. Prior to construction, the City also retains an independent testing
laboratory to provide testing services on materials, soils, welding,
etc. By utilizing an independent laboratory for these services, more
checks and balances are incorporated into the building design and
construction procedures.
9. During construction, City staff routinely administers and monitors
all contracts and provides detailed inspection services on assigned
projects.
10. Prior to project completion, City staff performs a final inspection,
and as part of the contract, the architectural/engineering consultant
and the construction manager, prepare a "punch list". Only after
$$punch list" items and other administrative matters have been
completed is the project accepted as complete and the Mayor and
Council Communication for final pay submitted to the City Council for
approval .
11. The City's Internal Audit staff helps to pinpoint any problems and
recommend corrective action both during construction and after
project completion.
At the center of the most recent concerns regarding City buildings are three
facilities: the Municipal Office Building (City Hall ), the Southside
Multi-Purpose Center, and the new Equestrian Center. The Municipal Office
Building was designed and constructed during the early 1970s and the
Southside Multi-Purpose Center was designed and constructed in 1980-81. Both
of these facilities utilized an architectural/engineering consultant to
design the project and to provide construction supervision/inspection
services. No City staff or independent consultant inspected either of these
projects, no building permit was obtained for either project, and only
limited plan review was conducted by City staff.
The new Equestrian Center currently under construction, utilizes the
procedures described above. The City has retained an independent consultant,
Muckelroy Construction, to provide inspection services for this project and
an independent testing lab, Terra-Mar Testing Labs, to provide testing
services of concrete, soils, welds, and other materials. After allegations
of sub-standard work were made by a former Equestrian Center sub-contractor,
the design architect, the independent inspector, City staff and another
independent building contractor were asked to review the construction
procedures. This review team was unable to verify any instances of
sub-standard construction practices and concluded that all allegations of
deficient construction were unfounded.
[ISSUED BY THE CITY MANAGER FORT WORTH, TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 7246 - UA
To the Mayor and Members of the City Council January 5, 1988
OW
Subject: STATUS REPORT ON DESIGN, CONSTRUCTION AND
MAINTENANCE PROCESS FOR CITY BUILDINGS
Building Maintenance
The City of Fort Worth has 427 facilities classified as "buildings" with an
estimated replacement value of $240,378,450. This classification includes
park shelters, pump houses, libraries, and a variety of other buildings. The
General Services Division of Transportation/Public Works provides a minimal
level of routine maintenance on 112 buildings with an annual maintenance
budget of approximately $2 million. The General Services Division does not
maintain the Will Rogers Complex, Meacham Field, the Health Center, the
Museum of Science and History, and Water Department facilities; however, the
Transportation/Public Works Department is often called on to assist with
emergency repairs and other specialized projects.
The General Services Division has completed a detailed building-by-building
inspection of the buildings that they maintain and has developed a detailed
five-year program of work. Priority projects were identified for attention
in FY 1987-88. The priorities were developed, in consultation with user
departments; however, the technical evaluation and analysis was performed by
personnel from the General Services Division.
Over the past four years, the General Services Superintendent -and the staff
► of the General Services Division have expanded the areas of expertise of City
building maintenance crews. Recent examples include adding of the second
floor and remodeling of the Construction/Surveying Building, remodeling of
the Real Property Department offices, the manufacturer's certification of the
City roofing crew, the boiler and air conditioning installation and
replacement projects of the City's HVAC crew, and the use of advanced
infrared testing of major electrical components to detect hot spots and to
allow repairs prior to failure. The basic problem surrounding the
maintenance of qxisting buildings is not one of expertise or training, but
one of money.
Though significant improvements have been made in the building design,
construction and maintenance procedures, we will continue to strive for
additional funding, additional training for personnel and a responsive
organizational structure.
I have requested David Ivory coordinate a staff task force to review Mr.
Gilley's suggestions regarding new organizational arrangements concerning
Public facilities. The task force will review organizational structures in
other comparable cities as well as examine the financial requirements to
assure adequate, on-going maintenance of City-owned buildings.
[ISSUED BY THE CITY MANAGER FORT WORTH, TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 7246 - p.5
To the Mayor and Members of the City Council January 5, 1988
x Subject: STATUS REPORT ON DESIGN,, CONSTRUCTION AND
MAINTENANCE PROCESS FOR CITY BUILDINGS
Since facility issues are of on-going importance, staff thought that this
status report would be useful information for Council . After staff completes
further analysis of organizational issues, a report will be presented to
Council with recommendations regarding organizational changes.
If additional information is desired, it will be furnished upon request.
Douglas man
v
City Manager
DH/kc:n
ISSUED BY THE CITY MANAGER FORT WORTH, TEXAS