HomeMy WebLinkAboutIR 7242 INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 7242
To the Mayor and Members of the City Council December 18, 1987
vz
Subject: 1-30/1-35 INTERCHANGE PROJECT IN DOWNTOWN FORT WORTH
Isis
At the 1-30 Working Group meeting on December 16, 1987, the
Consultants for the State Department of Highways and Public
Transportation passed out and explained the attached information.
At the conclusion of their explanation, the Consultants stated
that they tentatively recommend to the State Department of
Highways and Public Transportation that they believe the Vickery
alternative is the preferred alternative and should be selected.
The staff plans a full presentation of the alternatives for the
City Council at the January Worksession.
If there are any questions, we will respond upon request.
� uglas ma
Ci
Wty Manager
DH/sf
nnn
Attachments (3)
ISSUED BY THE CITY MANAGER FORT WORTH, TEXAS
1— >rr
~
W
�
_ F 4
IL
r
if
•y r��fy a II 3I sa -. � 33 # i �p§33ag-• 8
.rj88��
r J
a# 3:4 a �II _.0 ,# {««� 88�.`8"a 8g &
+' I# "if 1,11T f'3 1
'a' ist s ' I 1�E1IHP i4 �1i3 st '��#
a 4gs t'�x8�" la,'a
!jy:1 I
�-IR,
w t o� °:z. �rtJl$�Yl _i. 1 _•.laid ;.._ , ', {s
ui
cc
WE
I: . a +'y1i as i a 'ri '•o
W
v V1
lu
IWi
zz
O
Vi
iC
O C
JOL
W LC '
� to
s<o
z
Ow
W W
ATTACHMENT "B"
O► SECTION 8 - EVALUATION OF FINALIST ALTERNATIVES 8-1
The final evaluation of five alternatives is presented in this section. The five
alternatives evaluated are as follows.
• Expanded Elevated (Figures 8-2 through 8-6)
• Modified Expanded Elevated (Figures 8-7 through 8-11)
• Depressed (Figures 8-12 through 8-16)
• Vickery Alignment (Figures 8-17 through 8-21)
• Do Nothing
Each of these alternatives has been described in a previous section (Description
of Alternatives 3.0). Each alternative was evaluated as to its ability to achieve
the goals and objectives set forth in the Evaluation Matrix, and the results of
this evaluation are summarized in Figure 8-1. The following narrative presents
the factors considered in each row of the Evaluation Matrix as well as the rela-
tive strengths and weaknesses of each alternative.
8.1 SUMMARY OF FINALIST ALTERNATIVES EVALUATION MATRIX
8.1.1 Design 1.1
OW Goal: Adequate to Meet 2010 Traffic Demand
Objective: Achieve Level of Service C
Based upon the traffic forecasts for the year 2010 for each alternative,
peak-hour demands were estimated for morning and afternoon peaks. These esti-
mated peak-hour demands included consideration of the traffic flow characteristics ,
into and out of the central business district (CBD). Operational analyses were
then performed to determine the resulting level of service during peak hours in
the design year (2010).
None of the alternatives were found to totally meet the objective of
operating at or above Level of Service C. In most instances, the lower level of
service resulted from weaving problems on the outside lane between an on-ramp
and an off-ramp. In order to show a meaningful comparison of the different
alternatives, the percentage of total lane-miles of the project which would
operate at conditions Level of Service C or better during the average peak hour
were calculated. The resulting comparison is as follows.
Expanded Elevated 82 percent
Modified Expanded Elevated 83 percent
Depressed 80 percent
Vickery Alignment 93 percent
Do Nothing 42 percent
8.1.2 Design 2.2
op` Goal: Facility Reliability
Objective: Minimize Operating Constraints
The five alternatives were evaluated concerning their relative suscep-
tibility to flooding, icing, spills, fires, and accidents that might disrupt or
8-2
close the freeway. All of the alternatives have long structures in the inter-
change area which will be subject to icing. Those portions of the facilities
going under the railroads or depressed through downtown will be subject to
possible flooding during heavy rains. The constrained-width roadway sections,
whether elevated or depressed, are susceptible to closure due to hazardous spills
or fires. In short, none of the alternatives score very well toward meeting this
objective, and there are no significant differences in the susceptibility of the
"build" alternatives to operating constraints.
All four "build" alternatives were assigned a rating of "Fair" for this objective.
The No-Build Alternative, however, is more susceptible to closure due to accidents
because of its narrow width and the severe traffic congestion that it will experi-
ence, Therefore, the No-Build Alternative was assigned a score of "Poor" for this
objective.
8.1.3 Design 2.2A
Goal: Facility Reliability
Objective: Emergency Detour Capability
The alternatives were rated on the availability and accessibility of
emergency detour roadways. Lancaster Avenue can be used as a detour for the
IH-34 mainlanes on any of the alternatives. Detours for the IR--35W mainlanes
will be equally as circuitous for all alternatives. Only two of the alternatives,
the Modified Expanded Elevated and the Vickery Alignment, have full-width inside
shoulders which can be used as detours around stalled vehicles and minor acci-
dents. The existing facility, which will remain under the Do Nothing Alternative,
is only two lanes wide in many places and has narrow shoulders that cannot serve
as a detour lane. The Do Nothing Alternative offers virtually no detour capa-
bility on the facility itself. The resulting ratings for the five alternatives'
ability to provide emergency detour capability is as follows.
Expanded Elevated Fair
Modified Expanded Elevated Good
Depressed Fair
Vickery Alignment Good
Do Nothing Poor
8.1.4 Design 3.3
Goal: Facility Safety
Objective: Minimize Accident Potential
Freeways are inherently safer than other traffic facilities because all
crossing traffic and driveways have been eliminated. Differences in accident
rates between freeways can usually be attributed to geometric design deficien-
cies, signing problems, or traffic congestion. These factors were considered
OW in evaluating how effective each of the alternatives would be in minimizing
accident potential. The Vickery Alignment scored the best of all alternatives
because it has the fewest number of design variances, it offers better opportuni-
ties for signing because of the greater distances between decision points, and
8-3
it will have the best overall traffic flow. The Modified Expanded Elevated and
the Depressed alternatives score slightly lower than the Vickery Alternative on
all three counts. The Expanded Elevated Alternative has three times as many
design variances as the Vickery Alignment and almost twice as many as the other
two "build" alternatives, so it has a slightly higher accident potential.
Finally, the Do Nothing Alternative scores the poorest of all on accident poten-
tial because of its numerous design variances, poor signing, and severe conges-
tion. The resulting scores of all alternatives on minimizing accident potential
is as follows.
Expanded Elevated Fair
Modified Expanded Elevated Good
Depressed Good
Vickery Alignment Excellent
Do Nothing Poor
8.1.5 Design 4.4
Goal: Economical Design
Objective: Economical Materials and Construction Techniques
For the most part, all of the "build" alternatives use standard freeway
construction materials and techniques. All of them will require some longer
than usual spans over the railroads and in the interchange area, but these spans
are no longer than those in many other freeway interchange projects. The Modi-
fied Expanded Elevated design, however, incorporates a very unusual structural
support to achieve a long cantilever of the elevated roadway over Lancaster
Avenue. Also, the depressed design includes some highly unusual structural
design for the retaining walls and suspension of Lancaster Avenue over the main-
lanes. Because of these highly unusual design features, the Modified Expanded
Elevated and the Depressed alternatives are considered complex, while the Vickery
Alignment and the Expanded Elevated alternatives are considered to be standard.
No construction activity is involved with the Do Nothing Alternative, so this
objective is not applicable.
8.1.6 Design 4.4A
Goal: Economical Design
Objective: Ease of Maintenance
Factors considered in evaluating the various alternatives on ease of
maintenance included accessibility for maintenance vehicles and room for per-
forming maintenance operations. All of the "build" alternatives are very similar
in these attributes with many elements on which maintenance vehicles will have
to be located on the roadway itself during maintenance operations. All "build"
alternatives were assigned a rating of "Fair." The existing facility has already
deteriorated to the point that it needs frequent and extensive maintenance, and
it is so narrow that maintenance operation results in a virtual closing of the
freeway. Hence, the Do Nothing Alternative was assigned a rating of "Poor."
e"` 8-4
8.1.7 Design 5.5
Goal: Maximize Operating Performance
Objective: Maximize Average Vehicle Speeds
Traffic operational analyses were performed for all alternatives to
ascertain the speeds that vehicles will be able to travel along the mainlanes
during the average peak hour in the year 2010. Speeds along IH-30 were calcu-
lated between Riverside Drive and Forest Park Boulevard. The section evaluated
on IR-35W was between Hattie Street and Luella Street. The calculated speeds
were then weighted in proportion to length of segment and averaged together.
The resulting estimated average peak-hour speed for each alternative in the
year 2010 is as follows.
Expanded Elevated 49 mph
Modified Expanded Elevated 49 mph
Depressed 48 mph
-Vickery Alignment 51 mph
Do Nothing 32 mph
8.1.8 Design 6.6
Goal: Improve Mobility and Accessibility
Objective: Activity Center Access/Interchange Movements
Two factors were considered in evaluating this objective: (1) access
opportunities between IH-30 and the CBD and (2) turning movements provided in
the IH-35W/IH-30 interchange. The existing facility has more access ramps than
will be provided by any of the "build" alternatives. Of course, many of these
existing ramps are so closely spaced that they cause operational and safety
problems. Nevertheless, the Do Nothing Alternative ranks the highest for this
objective. The total number of ramps provided by each alternative is as follows.
Expanded Elevated 19
Modified Expanded Elevated 19
Depressed 19
Vickery Alignment 18
Do Nothing 25
8.1.9 Design 6.6A
Goal: Improve Mobility and Accessibility
Objective: Integrate to Arterial System
Each of the "build" alternatives provide a total of 23 ramps between the
mainlanes and various arterial streets in the project area. This number of
ramps provides excellent integration between the freeway system and the arterial
op", street system. The existing facility, however, has a total of 27 access points
between the mainlanes and arterials. So, the No-Build Alternative ranks the
highest for this objective.
O. 8-5
8.1.10 Design 6.6B
Goal: Improve Mobility and Accessibility
Objective: Minimize Impact to Arterial System
Two factors were considered in evaluating the alternatives under this
objective. First, the changes in arterial street continuity resulting from the
project were identified. All of the "build" alternatives sever Vickery Boulevard
between Henderson Street and University Drive, but they create a new connection
between Summit Avenue and 8th Street so that their net impact on arterial con-
tinuity is zero. Second, the number of signalized intersections that would be
overloaded by the volume of traffic exiting at a specific freeway ramp were
identified for each alternative. The Expanded Elevated, the Modified Expanded
Elevated, and the Depressed alternatives each overload two signalized inter-
sections. The Vickery Alignment overloads one signalized intersection. The
No-Build Alternative also overloads one intersection.
8.1.11 Design 7.7
Goal: High Level of Design Aesthetics
Objective: Combine Engineering Requirements and Physical Appearance
Every effort will be made to design the selected alternative as aestheti-
cally pleasing as possible. However, certain constraints are inherent to some
alternatives which will limit just how aesthetically pleasing they can be. Both
elevated alternatives will be massive structures which will dominate their imme-
diate environs; hence, despite all efforts to design an attractive structure,
the net aesthetic appearance of these alternatives will be "Fair." The Depressed
Alternative will require safety treatments along Lancaster Avenue to prevent
vehicles and pedestrians from falling onto the mainlanes, but these constraints
should not prevent the achievement of a "Good" aesthetic appearance. The Vickery
Alignment has fewer constraints on its design, so a "Good" aesthetic appearance
should be easily achievable with this alternative. The No-Build Alternative is
rated as "Fair" in aesthetics.
8.1.12 Level of Service/Operations 1.1
Goal: Improve Mobility/Reduce Delay
Objective: Minimize Average Travel Times
In order to evaluate the five alternatives under this objective, the time
required to make certain trips during peak hours in the year 2010 were estimated
for each alternative. The following three types of movements were evaluated and
assigned the relative weightings shown.
o Cross-town movements along IH-30 between Riverside Drive and Forest
Park Boulevard (60 percent).
o Interchange movements between IH-30 and IH-35W (25 percent) .
o CBD to IH-30 movements (15 percent) .
8-6
The average peak-hour design year travel times were calculated and then
summed in accordance with the weighting factors for each movement. The resulting
composite travel times in minutes are as follows.
Expanded Elevated 5.8 minutes
Modified Expanded Elevated 5.8 minutes
Depressed 5.8 minutes
Vickery Alignment 5.8 minutes
Do Nothing 8.3 minutes
8.1.13 Level of Service/Operations 2.2
Goal: Achieve "User-Friendly" Facility
Objective: Signing/Clear Decision Points
Most drivers establish a priority among their various driving functions.
If they are busy trying to avoid collisions with merging vehicles or controlling
their vehicle on steep grades or tight curves, they do not bother to try to read
informational signs. Therefore the opportunity to provide effective signing on
an urban freeway is severely constrained by the geometric attributes of that
facility. The five alternatives were evaluated for their potential to be ade-
OP161 quately signed primarily on their geometric layouts. The highest rating was
given to the Vickery Alignment because its decision points are separated by
greater distances. The three "build" alternatives along the existing corridor
received lower ratings because of the shorter spacings between decision points
and tighter curves involved. The No-Build Alternative received the lowest rating
because of its even shorter spacings and sharper curves. The resulting ratings
are as follows.
Expanded Elevated Fair
Modified Expanded Elevated Fair
Depressed Fair
Vickery Alignment Good
Do Nothing Poor
8.1.14 Level of Service/Operations 2.2A
Goal: Achieve "User-Friendly" Facility
Objective: Geometric Attributes
Current design standards for freeways have evolved over the four decades
of freeway use. These standards have been modified to increase safety and
improve the comfort of the driving public. Maximum allowable grades have been
reduced, minimum radii curves have been improved, convergence/divergence angles
for ramps have been modified for better visibility, spacing between ramps has
been increased to reduce weaving problems, and sag and crest vertical curves
have been smoothed to reduce the roller-coaster effect, thus improving sight
OP► distances. Indeed, if a facility could be designed without a single variance
from the "desirable" guidelines in the current State Department of Highways and
Public Transportation (SDHPT) Design Manual, it would be a very "user-friendly"
facility.
OPOI 8-7
The geometric attributes of these five alternatives were evaluated by
counting the number of design variances that each alternative has from the latest
SDHPT Design Manual guidelines. In this rating, the lower the number of vari-
ances, the better the resulting geometric design. The resulting number of vari-
ances for each alternative is as follows.
Expanded Elevated 68
Modified Expanded Elevated 35
Depressed 37
Vickery Alignment 23
Do Nothing 200+
8.1.15 Level of Service/Operations 3.3
Goal: Provide Cost-Effective Facility
Objective: Cost-Effectiveness Index
The cost-effectiveness index used for this evaluation is a simplified
benefit/cost ratio. The only benefits considered were the savings due to reduced
delay time and reduced fuel consumption. The value of time assumed in this
analysis was a minimum wage equivalent of $3.35/hour for individuals and an
average cost of $35.00/hour for commercial vehicles on business trips. It was
further assumed that the cost of fuel would average $1.25/gallon in 1987 dollars
over the 20-year design life of the project. The total savings accrued over the
20-year life of the project were then divided by the implementation costs to
yield the cost-effectiveness index. The resulting ratings for each alternative
in dollars saved/dollars spent are as follows.
Expanded Elevated 3.1
Modified Expanded Elevated 2.7
Depressed 2.5
Vickery Alignment 2.5
Do Nothing N/A
8.1.16 Level of Service/Operations 3.3A and 3.3B
An evaluation of these two parameters concerning minimizing operating
costs for trucks and passenger cars would be based on the same factors used in
evaluating several other parameters in the Evaluation Matrix (Level of Service,
Average Speeds, and Delay Time). Ratings of these parameters would be redundant
and offer no different information; therefore, these two parameters will not be
rated as a part of this evaluation.
8.1.17 Cost/Construction 1.1
Goal: Lowest Cost Facility Achievable
Objective: Minimize Implementation Cost
A detailed cost estimate was prepared for each of the "build" alterna-
tives. The unit costs used in these estimates are based on the latest average
bid prices received for highway construction in the Fort Worth District. These
Opk 8-8
unit prices are considerably lower than those used in previous cost estimates
for this project. The total implementation (construction costs + right-of-way
costs + engineering costs + contingency) costs for the various alternatives are
as follows.
Expanded Elevated $103 million
Modified Expanded Elevated $119 million
Depressed $127 million
Vickery Alignment $138 million
Do Nothing N/A
8.1.18 Cost/Construction 2.2
Goal: Available Funding
Objective: Identify Funding Availability/Eligibility
This project involves two Interstate Highway facilities, which qualifies
it for 90 percent federal funding. The only difference in the funding for the
different alternatives is in how much of the project will be eligible for "new"
Interstate funding and how much will have to be constructed with 4R funds. In
all alternatives the interchange portion and the eastern portion will qualify
Opl► for Interstate funds, while the western portion will only qualify for 4R funding.
There may be slight differences between alternatives in precisely where the
dividing line between 1 and 4R funding occurs. However, with the new funding
levels based on increased gasoline taxes (now at $0.09 federal and $0.15 state
tax/gallon), adequate funds should be available from both 1 and 4R sources to
fund this project.
8.1.19 Cost/Construction 3.3
Goal: Ease of Implementation
Objective: Phased Construction
A detailed plan has been developed for the sequence of construction and
traffic handling during construction for each of the "build" alternatives. Two
lanes of freeway traffic in each direction can be kept open during the construc-
tion process for each alternative. However, the complexity of phasing construc-
tion varies significantly between the alternatives. The Modified Expanded
Elevated is rated as "Very Complex" because of the problems associated with the
new alignment crossing the existing alignment and the construction of unusual
structural bents. The Depressed Alternative is also rated as "Very Complex" due
to the need to excavate below existing facilities within the right-of--way. The
Expanded Elevated is rated as "Complex" due to the problems of widening an exist-
ing structure in a narrow right-of-way with heavy street traffic underneath the
structure. The Vickery Alignment is rated as "Normal" in phasing complexity
because much of it is constructed on a new alignment without the constraints of
the Lancaster Avenue corridor. Since no construction is involved with the Do
OW Nothing Alternative, a rating for it is not applicable under this objective.
" 8-9
8.1.20 Cost/Construction 3.3A
Goal: Ease of Implementation
Objective: Minimize Utility Relocation Problems
Originally, it was thought that one of the major problems associated with
utility relocations would be a delay in implementation time. Further analyses,
however, indicate that utility relocation activities are not on the critical
path for any of the alternatives. Other utility relocation problems considered
in rating the various alternatives included costs, disruption of traffic during
relocation, and impacts on utility system networks. The resulting ratings of
utility relocation problems for the five alternatives are as follows.
Expanded Elevated Minimal
Modified Expanded Elevated Moderate
Depressed Severe
Vickery Alignment Moderate
Do Nothing None
8.1.21 Cost/Construction 4.4
Goal: Minimal Inconvenience to Public
oplk Objective: TCP Convenience to Public
Any roadway construction will present some inconvenience to the travel-
ing public. Every effort was made in the development of detailed sequence of
construction/traffic handling plans for each alternative to minimize this
inconvenience. Nevertheless, the different alternatives will result in varying
degrees of inconvenience for the traveling public. A rating of "Severe" was
assigned to the Depressed Alternative because of the longer construction period
(6 years), shifting of Lancaster Avenue traffic from one side of the excavation
to the other, and numerous shifts in mainlane traffic to narrow temporary lanes.
The level of inconvenience was considered "High" for both of the Elevated alter-
natives because of the numerous detours of freeway traffic involved. The Vickery
Alignment is considered to impose only a "Moderate" level of inconvenience on the
traveling public because it has the shortest duration of construction (4.5 years)
and much of that construction can be accomplished without detouring freeway
traffic. The Do Nothing Alternative involves no construction, so it has no
resulting inconvenience to the public during construction.
8.1.22 Cost/Construction 4.4A
Goal: Minimal Inconvenience to Public
Objective: Minimize Duration of Implementation
The existing facility experiences severe congestion during numerous hours
of each day. Therefore, the sooner that an expanded facility can be provided, the
O. less time that the traveling public will have to suffer the inconvenience of the
current congestion. The ratings of the various alternatives under this objective
are based on the total implementation time required. Of course, the Do Nothing
OW 8-10
Alternative involves no implementation time, but neither does it provide any
benefits in reduced congestion, so a rating for it is not applicable under this
objective. Total implementation times for the alternatives are as follows.
Expanded Elevated 6.5 years
Modified Expanded Elevated 9.5 years
Depressed 10.0 years
Vickery Alignment 8.5 years
Do Nothing N/A
8.1.23 Cost/Construction 4.48
Goal: Minimal Inconvenience to Public
Objective: Minimize Fire/Police Reroutes/Detours
For this objective, the alternatives were rated on the disruption to
typical fire and police routes that would be necessary during construction. The
Depressed Alternative results in major reroutings because each of the north-south
streets will have to be closed at some time for construction of bridges over the
depressed freeway. The other "build" alternatives will have minimal impacts on
police and fire routes. The Do Nothing Alternative will have no impacts.
8. 1.24 Cost/Construction 4.4C
Goal: Minimize Inconvenience to Public
Objective: Minimize Residential Impacts
This objective concerns the impacts of construction traffic, noise, dust,
vibration, etc. on residential units in close proximity to the construction site.
The number of residential units in close proximity is the same for all "build"
alternatives. A total of 509 residential units (414 apartments near the west
segment of the project and 95 low-income housing units near the east segment of
the project) will experience some impacts during construction. A rating for the
Do Nothing Alternative is not applicable under this objective.
8.1.25 Cost/Construction 4.4D
Goal: Minimal Inconvenience to Public
Objective: Minimize Business Impacts
This objective concerns the impacts of construction traffic, noise, dust,
vibration, etc. on commercial establishments in close proximity to the construc-
tion site. All three "build" alternatives using the existing corridor will have
some impacts on 63 commercial buildings along the Lancaster Avenue corridor.
The Vickery Alignment will also impact these buildings during the removal of the
existing elevated and it will impact an additional 12 businesses along the new
alignment, for a total of 75 businesses. A rating for the Do Nothing Alternative
OW is not applicable under this objective.
8-11
8.1.26 Socioeconomic Impacts 1.1
Goal: Minimize Effects on Protected Property
Objective: Minimize Impacts Parks
All potential proximity effects of the various alternatives on the Water
Garden were considered under this objective. The noise study indicates that
there is no measurable difference in noise between any of the alternatives.
The Air Quality report shows that the concentration of vehicle emissions will
be slightly greater for the Depressed Alternative, but that none of the result-
ing concentrations will approach the maximum guidelines established by EPA.
Construction activities for the three "build" alternatives in the Lancaster
Avenue corridor will have significant temporary impacts of a similar nature.
The Vickery Alignment will impose minimal construction impacts on the Water
Garden. The most apparent proximity effect for any of the alternatives will be
the visual impact. Based upon all of the considerations mentioned above, the
following ratings were assigned to the various alternatives for their impacts on
the Water Garden.
Expanded Elevated Poor
Modified Expanded Elevated Poor
Depressed Fair
opbl Vickery Alignment Good
Do Nothing Fair
8.1.27 Socioeconomic 1.1A
Goal: Minimize Effects on Protected Properties
Objective: Minimize Effects on Historic Structures
There are four historic structures to be considered in the evaluation of
alternatives under this objective. The T&P Passenger Terminal, the U.S. Post
Office Building, and the T&P Freight Terminal are all located on the south side
of Lancaster Avenue in the center portion of this project. The Public Market
Building is located in the western portion of the project. Because all of
these buildings are currently being used for commercial activities, the most
significant proximity effects are those associated with the construction process.
The convenient access that these buildings currently enjoy will be reduced during
construction. Other proximity effects on these buildings will be very similar
to those discussed for the Water Garden. The Vickery Alignment, however, will
still be in close proximity to the Public Market Building as it crosses over the
railroad tracks behind the Public Market. The Vickery Alignment results in a
shifting of the heavily traveled mainlanes from immediately in front of the
Public Market to a slightly more distant location in the rear of the building,
a change which should have an overall beneficial effect on the commercial via-
bility of the building. The resulting ratings assigned to the various alterna-
tives after consideration of all proximity factors are as follows.
` 8-12
Expanded Elevated Poor
Modified Expanded Elevated Poor
Depressed Poor
Vickery Alignment Fair
Do Nothing Fair
8.1.28 Socioeconomic 1A.1
Goal: Achieve Least Adverse Visual Impacts
Objective: Maximize Compatibility With Adjacent Structures
The adjacent structures considered under this objective include the com-
mercial office buildings, public buildings, and hotel located along the existing
facility. For the Vickery Alignment, the adjacent structures include railroad
yards on the north and light industrial buildings on the south. The ratings
assigned to the various alternatives for their compatibility with adjacent struc-
tures are as follows.
Expanded Elevated Poor
Modified Expanded Elevated Poor
Depressed Fair
Vickery Alignment Good
Do Nothing Poor
8.1.29 Socioeconomic 2.2
Goal: Reduce Traffic Congestion
Objective: Reduce Delay Time
The total number of vehicle hours of delay time that will be experienced
by the traveling public over a 20-year period was estimated for each alternative.
These estimates are based on a correlation of the density of traffic on a segment
of urban freeway and the corresponding congestion experienced on that segment.
The resulting estimates of millions of vehicle-hours of delay time for each
alternative are as follows.
Expanded Elevated 2.7
Modified Expanded Elevated 2.3
Depressed 2.3
Vickery Alignment 0.0
Do Nothing 36.7
8.1.30 Socioeconomic 3.3 to 3.3C
Goal: Improve Air Quality
Objective: Reduce Emissions
001, The analyses included in the air quality report show that vehicular
emissions will be reduced by any of the "build" alternatives over the Do Nothing
Alternative. However, even the volume of emissions that would result from the
8-13
Do Nothing Alternative would not cause any concentrations of pollutants that
would even approach the maximum allowable guidelines established by EPA. For
example, the concentration of carbon monoxide in the Water Garden is estimated
to vary from a low of 1.8 ppm for the Vickery Alignment to a high of 3.0 ppm for
the Do Nothing Alternative. EPA's maximum allowable guideline for carbon monoxide
is 35.0 ppm. The analyses for other emissions show similar results; consequently,
all "build" alternatives could be considered to be "Good," while the Do Nothing
Alternative would rate a "Fair."
8.1.31 Socioeconomic 4.4
Goal: Mitigate Noise/Vibration
Objective: Minimize Noise Levels
The noise studies indicate that there is no measurable difference between
the noise levels resulting from any of the alternatives. The measurements of
existing noise along the corridor, however, indicate that noise levels exceed
the maximum allowable under DOT guidelines. Therefore, noise mitigation measures
will have to be considered for all alternatives. All alternatives were assigned
a rating of "Fair" for this objective.
op,. 8.1.32 Socioeconomic 4.4A
Goal: Mitigate Noise/Vibration
Objective: Minimize Vibration
No information had yet been received from the subconsultant charged with
performing detailed vibration analyses when this evaluation was performed. In
the absence of more definitive information, it is assumed that all of the alter-
natives will have very similar vibration characteristics except the Depressed
Alternative. It seems logical that somewhat higher levels of vibration affecting
adjacent buildings could occur during the excavation of portions of the rock
strata under Lancaster Avenue. Accordingly, a rating of "Poor" was assigned to
the Depressed Alternative, and all other alternatives were assigned a rating of
"Fair."
8.1.33 Socioeconomic 5.5
Goal: Minimum Acquisitions
Objective: Minimize Business Displacements
The total number of existing business operations that will be displaced
by each of the alternatives is as follows.
Expanded Elevated 2
Modified Expanded Elevated 3
Depressed 4
► Vickery Alignment 7
Do Nothing 0
OW 8-14
8.1.34 Socioeconomic 5.5A
Goal: Minimum Acquisitions
Objective: Minimize Residential Displacements
All of the "build" alternatives will displace a trotal of 124 low-income
housing units located in the northeast quadrant of the interchange between IH-30
and IH-35W. The Do Nothing Alternative displaces no residences.
8.1.35 Socioeconomic 5.58
Goal: Minimum Acquisitions
Objective: Minimize New Right-of-Way Acquisition
In evaluating this objective, the amount of new right-of-way (exclusive
of railroad agreements) was estimated for each alternative. The number of acres
of new right-of-way required for each alternative is as follows.
Expanded Elevated 6.0 acres
Modified Expanded Elevated 6.4 acres
Depressed 7.7 acres
Vickery Alignment 26.1 acres
Do Nothing 0.0 acres
8.1.36 Socioeconomic 6.6
Goal: Maintain Water Quality
Objective: Minimize Impact to Existing Drainage System
All of the "build" alternatives will have some impact on existing drain-
age systems. However, the project is located in the midst of dense commercial
development where most of the land is already covered with buildings or parking
lots, so the increases in water runoff will be minimal. Also, the Trinity River
crosses the project on either end so that outfall locations are close to the
project. For these reasons, all of the "build" alternatives will have only
minimal impacts on the existing drainage systems. The Do Nothing Alternative
will not affect the existing drainage system.
8.1.37 Socioeconomic 6.6A
Goal: Maintain Water Quality
Objective: Minimize Impacts on Receiving Waters/Water Quality
The initial wash of roadway systems removes an accumulation of particles
of rubber, spilled oil and fuel, and some sediments from vehicular emissions
that are considered pollutants. However, by the time that the stormwaters from
roadways reach an outfall location, this initial wash is diluted by water from
+,, other sources and additional rainfall so that it rarely causes any problem to
R� , aquatic life. During the construction period, appropriate measurer: will be taken
to control erosion and protect water quality. There are no apparent differences
1p. 8-15
between the various alternatives in their impacts on water quality; therefore,
all alternatives are assigned a rating of "Fair."
8.1.38 Socioeconomic 7.7
Goal. Enhance Local Economy
Objective: Provide Construction Jobs
The average number of construction jobs that would be created in the
Fort Worth area due to the construction of this project were estimated for each
alternative using typical econometric multipliers. The total employment gener-
ated will be directly proportional to the construction cost for each alternative,
but the average number of jobs varies inversely with the construction period.
The resulting average number of jobs that will be created by each alternative is
as follows.
Expanded Elevated 362
Modified Expanded Elevated 322
Depressed 297
Vickery Alignment 405
Do Nothing 0
8.1.39 Socioeconomic 7.7A
Goals Enhance Local Economy
Objectives Provide Opportunity for Future Development/Redevelopment
All of the "build" alternatives will improve traffic flow in the project
area and to the CBD. This improved accessibility will encourage new development
in the area. The differences in the stimulus provided by the "build" alterna-
tives for redevelopment lies in the relative attractiveness of specific sites.
Either of the Elevated alternatives will continue to present a psychological
barrier between the property on the south side of Lancaster Avenue (north of
the railroad) and the CBD. Both the Depressed Alternative and the Vickery
Alignment would remove this psychological barrier, thereby making this property
more attractive to investors for redevelopment. Additionally, the location of
the Vickery Alignment through the area that is currently light industrial in
nature might encourage some redevelopment of land on the south side of the rail-
road to higher and better uses. The ratings assigned to the various alternatives
concerning their potential to stimulate new development and redevelopment are as
follows.
Expanded Elevated Fair
Modified Expanded Elevated Fair
Depressed Good
Vickery Alignment Excellent
Do Nothing Poor
8-lb
8.1.40 Socioeconomic 8.8
Goal: Avoid Sensitive Areas
Objective: Preserve Schools, Hospitals, Churches, and Natural Habitat
None of the remaining alternatives come close to schools, hospitals, or
churches. Neither do they disturb any natural habitat. Therefore, all five
alternatives are assigned a rating of "Good" under this objective.
8.1.41 Socioeconomic 9.9
Goal: Maintain Consistency With Local Plans
Objective: Consistent With Local Plans, Policies, Programs
All plans developed by any local agency for roadway improvements in the
Fort Worth area during the past 15 years have included an expansion of capacity
along IH-30 and IH-35W. Therefore, the Do Nothing Alternative is inconsistent
with local plans. The Vickery Alignment is slightly different than the location
shown for expanding IH-30 on previous plans, but it is compatible with all other
elements of local plans, policies, and programs. The remaining three alterna-
tives are totally consistent with local plans.
8.1.42 Socioeconomic 10.10
Goal: Maintain Neighborhood Cohesion
Objective: Minimize Neighborhood Traffic/Does Not Isolate
None of the remaining five alternatives being evaluated will divide a
neighborhood or generate unwanted traffic through a neighborhood. All alterna-
tives are assigned a rating of "Good" under this objective.
Attachment "C"
SUMMARY OF RELATIVE STRENGTHS AND WEAKNESSES
Expanded Elevated
Strengths Weaknesses
Construction Mtrls & Technique Emergency Detour Capability
Cost Effectiveness Index Accident Potential
Cost to Implement Aesthetics
Utility Relocation Problems Geometric Attributes
Implementation Time Parklands
Business Displacements Compatibility with Surroundings
R.O.W. Acquisition Delay Time
Future Development
Modified Expanded Elevated
Strengths Weaknesses
Emergency Detour Capability Construction Mtrls & Techniques
Aesthetics
Phased Construction
Parklands
Compatibility with Surroundings
Future Development
Depressed
Strengths Weaknesses
Aesthetics Level of Service
Emergency Detour Capability
Construction Mtrls & Techniques
Average Speed
Phased Construction
Utility Relocation Problems
TCP Convenience
Implementation Time
Fire/Police Detour
Vibration
Construction Jobs
Vickery Alignment
Strengths Weaknesses
Level of Service Activity Center Access
Emergency Detour Capability Cost Effectiveness Index
Accident Potential Cost to implement
Construction Mtrls & Techniques Business Impacts/Construction
Average Speed Business Displacements
Impacts to Arterial System R.O.W. Acquistion
Aesthetics
Signing
Geometric Attributes
Construction Phasing
TCP Convenience
Parklands
Historic Structures
r_ozpatibilitY %tth Surroundings
Delay Time
COt�BLtuctiou Sobs
Future Development
I