HomeMy WebLinkAboutIR 7334 INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 7334
Miw.c+eta
fir►
is mp� To the Mayor and Members of the City Council November 10. 19$8
l� o
U ��
Subject: UPDATE ON PESSES CHEMICAL COMPANY SUPERFUND BITE
The U.S. Environmental Protection Agency Region VI announced November 2. 1988,
they had completed their remedial investigation and feasibility study of the
Pesses Chemical Company Superfund Site. They will be conducting a public hearing
at 7p.m. . November 16. 1988 to receive comments on this study and will discuss
their perferred remedy for the site.
The Pesses Chemical Company (PCC) Superfund Site is an abandoned metals recycling
facility located at 2301 South Main Street. A drug rehabilitation center with
outdoor facilities adjoins the Pesses Site to the north. There are two hospitals
and five schools located within one mile of the site.
This facility opened in December. 1978 to recover cadmium and nickel from
batteries and sludge, a process which produced high level cadmium emissions.
The plant closed in January of 1981 due to financial problems. They left behind
several hundred 55-gallon drums of process material in an unprotected storage
area in the southern portion of the four-acre site. Most of the drums were
opened and/or deteriorating, exposing contents to the weather, and some were
leaking contents on the ground.
In March of 1983 a grass fire occurred at this site where several of the
responding firemen were overcome by noxious cadmium fumes. This resulted in
the Environmental Protection Agency conducting a prelimary assessment to
determine the potential threat the site posed to human health and the
environment. The result of this study recommended an immediate removal of
drums and soil. Pesses ultimately agreed to remove these materials but failed
to complete the entire removal . With the abandonment by the company the
Environmental Protection Agency assumed responsibility of the site and began
the clean-up process in April , 1983. Analysis of the site revealed heavy metals
(Cadmium, Nickel , Lead. Copper) contamination onsite. The Environmental
Protection Agency- removed 3400 cubic yards of contaminated soil along with
drums, wastes and debris. A two to six inch cap of clean fill material was
installed over the southern fenced portion of the site and seeded with grass.
This action was completed in July. 1983 for a total cost to the Environmental
Protection Agency of $337.876.
This particular. process alleviated many of the short term problems associated
with this site. However, potential long term risks from the site were unknown
and remained to be addressed. In October. 1984 the Pesses Chemical Site was
placed on the National Priorities List. The List comprises the most serious
uncontrolled or abandoned hazardous waste sites requiring long term attention
to protect the public health and environment. Under the Comprehensive
Environmental Response. Compensation and Liability Act of 1980, commonly known
as Superfund, the Envionmental Protection Agency began an extensive remedial
investigation study in 1987 thru most of 1988. This investigation determined
the extent of the contamination remaining at the site and the risk associated
with the contamination, along with potential remedies. The Environmental
Protection Agency has proposed several alternatives to cleaning the Pesses
Site. They have also identified their preferred remedy from those proposed.
ISSUED BY THE CITY MANAGER FORT WORTH, TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 7334
N^•T•,f Page 2
cos 40Rr To the Mayor and Members Of the City Council November 10. 1988
�'� �` • Subject: UPDATE ON PESSES CHEMICAL COMPANY SUPERFUND SITE
i 73
A brief description of those alternatives are as follows:
1) NO ACTION: Under the Superfund Law this alternative must be evaluated and
serves as a base line for other alternatives. This would involve fencing
the entire site and restricting future 'land use. This alternative provides
no long term protection from the risks posed from this site. Cost estimated
at $60,000.
2) IN-SITU CAPPING: This would provide a clay cap to be constructed in the
south area and a concrete cap installed in the operating area near the
warehouse. This alternative prevents contact with the contaminants. Site
restriction would be imposed. Cost estimated at $940,000.
3) IN-SITU VITRIFICATION WITH CAPPING: This is a technique which requires
melting the soil in place by the use of electricity. The contaminated soil
would be turned into a block in place and capped as in #2. Site restriction
would be imposed. Cost estimated at $3.8 million.
4) IN-SITU STABILIZATION WITH CAPPING: The wastes would be stabilized in place
by the use of concrete and then capped as in alternative #2 & #3. Site
restriction would be imposed. Cost estimated at $1.2 million.
5) EXCAVATION, ONSITE STABILIZATION WITH CONSOLIDATION IN SOUTH FIELD AND CAPPED:
This alternative includes stabilizing waste and consolidating this waste
in the south field and capping with a clay cap. The north portion of the
site would not have restrictions while the south area would have restrictions.
Estimated cost is from $1.4 million to $6.3 million depending on stabilization
technique.
6) ONSITE STABILIZATION WITH OFFSITE REMOVAL: Soils would be stabilized and
disposed at an approved hazardous waste (RCRA) landfill . Total clean up
of site is accomplished with no land use restrictions. Estimated cost $3.5
- $8.2 million depending on stabilization technique.
7) IN-SITU CAPPING WITH BUILDING DEMOLITION: This is the same as alternative
2 with the addition of demolishing t e building and removing the building
to an off-site area landfill . Site restrictions would be imposed. Estimated
cost $1.1 million.
Staff has reviewed these alternatives and while alternative #6 is the ultimate
recommended outcome for usage of the site the process does not satisfy the
preference in the Superfund Law for onsite remedies and the projected costs
are unreasonable to support such an alternative.
Staff however does support alternative #5 which will allow the north portion
of the site to have no restriction placed on building and will consolidate
all the contaminated material on the south portion of the site which currently
has no buildings nor does it appear large enough to support future development.
ISSUED BY THE CITY MANAGER FORT WORTH, TEXAS--
INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 7334
M�►rt^ra Page 3
#4oPP To the Mayor and Members of the City Council November 10. 1988
u1`t�f)sue
�rexh�. subject: UPDATE ON PESSES CHEMICAL COMPANY SUPERFUND SITE
Staff does not agree with EPA's preferred remedy which is alternative #4. This
may limit future development of this site due to site restriction requirements.
Should Council concur with staff's recommendations, we will present this as
the City's position on clean-up of the Pesses Site at the Public Hearing
scheduled on November 16, 1988 at 7p.m.
Sincerely,
/S,,
RH:lmt --Douglas Harman
City Manager
OW
ISSUED BY THE CITY MANAGER FORT WORTH, TEXAS --
way
W
m
a
�s� W S L
W
a
U9
z
a
ci
39UJ
ce
N
LV
Li
H
N
x
t!�
C2 A3SI M
x
n
0
3MWUS53P z ,
F1 W
J