HomeMy WebLinkAboutContract 56985-FP2FORT WORTH,
PARK & RECREATION DEPARTMENT
NOTICE OF PROJECT COMPLETION
-FP2
City Secretary No: 56985
Date Received: 8/25/2024
Ballfield Lighting Improvements at Harmon Field City Project Ns: 102961 / 102962
Regarding contract 56985 and Rolling Hills Soccer Complex for as required by the PARK & RECREATION
DEPARTMENT as approved by City Council on 11/30/2021 through M&C 21-0s26 the director of the PARK &
RECREATION DEPARTMENT upon the recommendation of the Assistant Director of the Park& Recreation
Department has accepted the project as complete.
Original Contract Prices:
Amount of Approved Change Orders:
Revised Contract Amount:
Total Cost Work Completed:
Less Deductions:
Liquidated Damages:
Pavement Deficiencies:
Total Deduction Amount:
Total Cost Work Completed:
Less Previous Payments:
Final Payment Due
C�
Recommended for Acceptance Asst. Director,
PARK & RECREATION DEPARTMENT
Accepted
Director, PARK & RECREATION DEPARTMENT
Asst. City Manager
$ 1,832,140.00
$ 368,000.00 No 1
$ 2,200,140.00
$ 2,148,140.00
Days @ $650.00/ Day
$ 2,148,140.00
$ 2,040,733.00
$ 107,407.01
Aug 18, 2024
Date
Aug 20, 2024
Date
Aug 25, 2024
Date
Comments: OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
C-620 Signature Page
Contractor's Application for Payment Invoice No. FINAL
To (Owner) City of Fort Worth Invoicing Period (From - To): Invoice Date:
11/1/2023
P. O. FW080-00000010406 From (Contractor): Remit to ( If Not Automatic Deposit ):
Number: GROVES ELECTRICAL SERVICE INC
Project: 102961 / 102962 Contractor's CFW Vendor No.:
0000038362 Groves Electrical Service, Inc. 2410 Squire Place, Farmers Branch, Tx 75234
City Secretary u56985 cn°
Number: tract Harmon Field and Rolling Hills Athlete Lighting Project
mber: Name:
Application For Payment
Change Order Summary
(Approved Change Orders
1. ORIGINAL CONTRACT PRICE..........................................................
$ $1,832,140.00
Number
Additions Deletions
2. Net change by Change Orders.................................................................
$ $368,000.00
1
$368,000.00
3. Current Contract Price (Line 1+2)........................................................
$ $2,200,140.00
2
4. TOTAL COMPLETED AND STORED TO DATE
3
(Progress Estimate, Construction Allowance and Change Orders)......
$ $2,148,140.00
4
5. RETAINAGE:
5
a. X $2,148,140.00 Work Completed.........
$
6
b. X Not Used
$
7
c. Total Retainage (Line 5a + Line 5b) ...............................
$
8
6. AMOUNT ELIGIBLE TO DATE (Line 4 - Line 5c).............................
$ $2,148,140.00
TOTALS
$368,000.00
7. LESS PREVIOUS PAYMENTS (Line 6 from prior Application)........
$ $2,040,733.00
NET CHANGE BY
$368,000.00
8• AMOUNT DUE THIS APPLICATION .................................................
$ $107,407.00
CHANGE ORDERS
9. BALANCE TO FINISH, PLUS RETAINAGE
(Column G on Progress Estimate+ CA + COs + Line 5 above) ..............
$ $52,000.00
Contractor's Certification 10. CONTRACT TIME:
The Contractor certifies with the submittal of this document and associated Payment Request Submittal
on the City of Fort Worth Buzzsaw system that to the best of their knowledge: (1) all previous progress
payments received from Owner on account of Work done under the Contract have been applied on
account to discharge Contractor's legitimate obligations incurred in connection with Work covered by
prior Applications for Payment; (2) title of all Work, materials and equipment incorporated in said
Work or otherwise listed in or covered by this Application for Payment will pass to Owner at time of
payment free and clear of all Liens, security interests and encumbrances (except such as are covered by
a Bond acceptable to Owner indemnifying Owner against any such Liens, security interest or
encumbrances); and (3) all Work covered by this Application for Payment is in accordance with the
Contract Documents and is not defective.
a, Days Awarded 200
b. Days Added by CO 60
C. Total Days 260
d. Days Charged
e. Days Remaining 260
8 a2D Consent of Surety
Affidavit of Bills Paid
This document has been modified from its original form as an EJCDC document and the user did not highlight the
modifications. You are encouraged to read the document carefully and consult Legal Counsel prior to its execution.
C-620 Unit Price Pragresa Estimate
Progress Estimate
For (0Ot1mact)'
Harmon Field and Rolling Hills Athlete Lighting Project
Application Period,
Item
But Item No.
UNIT I BASE BID ITEMS - HARMON FIELD PARK
1-01
Project Sign
1-02
Construction Staking
1-03
Excavation, trenching, and backfill
1-04
Conductors
1-05
Conduit and boxes
1-06
Wire devices
1-07
Light fixgtur7,, y91es, andyont gls.
1-08
Switchgear inc, pane(', enclosures, etc
1-09
Grassing
1-10
Chain Link Fencing
1-11
Concrete Pad
1-12
Concrete Lightpole Piers Purchase & Installation
UNIT 2 BASE BID ITEM - ROLLING HILLS SOCCER
COMPLEX
2-01
Proiect Spn
2-02
Construction Staking
2-03
Excavation, trenching, and backfill
2-04
Conductors
2-05
Conduit and boxes
2-06
Wire devices
2-07
Light fixgtures, gFles, andyont gls.
2-08
Switchgear incffumg pane(', enclosures, etc
2-09
Grassing
2-10
Concrete Pad
2-11
I
Concrete Lightpole Piers Purchase & Installation
UNIT I ALTERNATE BID - HARMON FIELD PARK
1-01
Security Lighting
1-02
Branch circuit wiring and conduit
I
UNIT 2 ALTERNATE BID -ALLOWANCE
1-01
Harmon Field Park Allowance
1-02
Harmon Field Park Allowance
1-03
Harmon Field Park Allowance
1-04
Harmon Field Park Allowance
1-05
Harmon Field Park Allowance
1-06
Rolling Hills Soccer Complex Allowance
1-07
Rolling Hills Soccer Complex Allowance
1-08
Rolling Hills Soccer Complex Allowance
1-08
Rolling Hills Soccer Complex Allowance
1-08
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Rolling Hills Soccer Complex Allowance
City Secretary
56985
Cuntractur's Application
Contract Num:
Application Numb
5
Application Date.
09/23/2022
B
C
D
E
F
G
Matenals
tnaa % Balance
to Finish
Specifioabon
Unit of
Bid Quantity
Unit Price
Estimated
Bid Value
Quantity
Value
Previously Installed
Value This Period
Presently Stored
Completed and
(F)
(B - F)
Section No.
Measure
Installed
Value
(not m C)
Stored to Date B
F,
015813
EA
1.000000
$1,200.00
$1,200.00
1.00000000
$1,200.00
$1,200.00
$1,200.00 100.0%
01 71 23
LS
1.000000
$2,750.00
$2,750.00
100000000
$2,750.00
$2,75000
$2,750.00 100.0°%JJ
260500
LS
1.000000
$35,158.00
$35,158.00
1.00000000
$35,158.00
$35,158.00
$35,158.06100.0%JJ
1
26 05 19
LS
1 000000
$39,267.00
$39,267.00
1.00000000
$39,267.00
$39,267.00
$39,267.00 100.26J
260533
LS
1.000000
$49,560.00
$49,560.00
100000000
$49,560.00
$49,56000
$49,560.00 100.0%J
262726
LS
1.000000
$17600
$17600
100000000
$17600
$17600
$176.00 100.0%J
265668
LS
1000000
$267,054.00
$267,054.00
1.00000000
$267,054.00
$267,054.00
$267,054.06100.0.6
1
LS
1.000000
$30,845.00
$30,845.00
100000000
$30,845.00
$30,84500
$30,845.00 100.0 y.
329213
LS
1.000000
$8,56200
$8,56200
100000000
$8,56200
$8,56200
$8,562.00 1002.1
3231 19
LS
1 000000
$5,415.00
$5,415.00
1.00000000
$5,415.00
$5,415.00
$5,415.06 100.01.J
1
033000
LS
1000000
$4,929.00
$4,929.00
1.00000000
$4,929.00
$4,929.00
$4,929.00 100t,
033413
EA
8.000000
$4,95300
$39,624.00
800000000
$39,624.00
$39,62400
$39,624.00 100.0%
I
015813
EA
1000000
$1,200.00
$1,200.00
1.00000000
$1,200.00
$1,200.00
$1,200.00 100.0°°
017123
LS
1.000000
$3,85600
$3,85600
100000000
$3,85600
$3,85600
$3,856.00 100.01
260500
LS
1000000
$35,193.00
$35,193.00
1.00000000
$35,193.00
$35,193.00
$35, 193.0610021
1
260919
LS
1000000
$163,327.00
$163,327.00
1.00000000
$163,327.00
$163,327.00
$163,327.00 100.0%
260533
LS
1.000000
$89,74300
$89,74300
100000000
$89,74300
$89,74300
$89,743.00 100.0%J
262726
LS
1.000000
$17600
$17600
100000000
$17600
$17600
$176.00 100.0°oJ
265668
LS
1.000000
$802,422.00
$802,422.00
1.00000000
$802,422.00
$802,422.00
$802,422.06100.21
1
LS
1.000000
$47,27300
$47,27300
100000000
$47,27300
$47,27300
$47,273.00 100.0%,
329213
LS
1.000006
$8,56200
$8,56200
100000000
$8,56200
$8,56200
$8,562.00 100.0°oJ
033000
EA
1.000000
$15,94200
$15,94200
100000000
$15,94200
$15,94200
$15,942.00 100.2.1
033413
LS
16.000000
$6,726.00
$107,616.00
16.00000000
$107,616.00
$107,616.00
$107,616.06100.0°
I
EA
2000000
$6,446.00
$12,892.00
2.00000000
$12,892.00
$12,892.00
J
$12,892.06100.0°�
I
1
LS
1.000000
$7,39800
$7,39800
100000000
$7,39800
$7,39800
$7,398.00 100.0%
I
LS
1.000000
$1,000.00
$1,000.00
$1,000.00l
LS
1.000000
$2,500.00
$2,500.00
$2,500.001
LS
1.000000
$5,00000
$5,00000
$5,000.00l
LS
1.000000
$7,500.00
$7,500.00
$7,500.001
LS
1.000000
$10,00000
$10,00000
$10,000.00l
LS
1000000
$1,000.00
$1,000.00
$1,000.001
LS
1.000000
$2,500.00
$2,500.00
$2,500.001
LS
1.000000
$5,000.00
$5,000.00
$5,000.001
LS
1.000000
$7'50000
$7,50000
$7,500.00
LS
1000000
$10,000.00
$10,000.00
$10,000.001
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
This dacumem has been.odflied fin. ns ongnial form as an E1CDC document and the user did not foghhds the
modificndons. Youare°nconrngcd 0read the docum°ot—follyand c°n o L°gal Counsel poor tons°—rco.
C-620 Unit Price Prcgress Estimate
Progress Estimate
Per (cmitract)' Harmon Field and Rolling Hills Athlete Lighting Project
Application Period,
A
I Item
Bid ItcmNo.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
City Secretary 56985
Contract Nam:
B C D
Specification unit of Bid Quantity unit Price Bid value Installed Estimated Quantityaloe
Section No. Measure
Contractor's Application
Application Numb 5 1
Application Date. 09/23/2022
E F G
Mat "a tit % Balance to Finish
Previously Installed Completed and
Value Value Thie Period P (oe1�5�red Stored 1n Date Bj �B
I
I I
I I
I I
I I
I I
I I
I I
I I
I
I I
I I
I I
I
I I
I I
I I
I
I I
I I
I I
I
I I
I I
I I
I
I I
I I
I I
I
I I
I I
I I
I
I I
I I
I I
I
I I
I I
I I
I
I I
I I
I I
I
I I
I I
I I
I
I I
I I
I I
I
I I
I I
I I
I
I I
I I
I I
I
I I
I I
I I
I
I I
I I
I I
I
I I
I I
I I
I
I I
I I
This dacumem has been moddlid firm it, ong 11orth as an UCDC document and the user did not highlight the
modificedons. You are encouraged 0 read the document—cholly and coneolt Legal Counsel poor tons execution.
C-620 Unit Price Prcgress Estimate
Progress Estimate
Per (cmitract)' Harmon Field and Rolling Hills Athlete Lighting Project
Application Period.
A
� Item
Bid ItcmNo.
City Secretary 56985
Contract Nam:
B C D
Specification unit of Bid Quantity unit Price Bid value Installed Estimated Quantityaloe
Section No. Measure
Contractor's Application
Application Numb 5 1
Application Date. 09/23/2022
E F G
Mat "a tit % Balance to Finish
Previously Installed Completed and
Value Value Thie Period P (oe1�5�red Stored 1n Date Bj �B
m ci
This dacumem has been moddlid firm it, ong 11orth as an UCDC document and the user did not highlight the
modificedons. You are encouraged 0 read the document—cholly and coneolt Legal Counsel poor tons execution.
C-620 Unit Price Prcgress Estimate
Progress Estimate
Per (0Ot1tract)' Harmon Field and Rolling Hills Athlete Lighting Project
Application Period.
A
� Item
Bid ItcmNo.
City Secretary 56985
Contract Num
B
Specification unit of Bid Quantity unit Price Bid Value
Section No. Measure
C
Estimated Quantity
Installed
D
Value
Previously Installed
Value
Contractor's Application
Application Numb 5
Application Date. 09/23/2022
E F G
Matmals tcualeted % Balance to Finish
Value This Period Presently Stored Compand (F) (B F)
(not m C) Smmd+,Date B
This dacumem has been moddlid firm it, ong 11orth as an UCDC document and the user did not highlight the
modificedons. You are encouraged 0 read the document—cholly and ccneolt Legal Counsel pnor tons execution.
C-620 Unit Price Prcgress Estimate
Progress Estimate
Per (cmitract)' Harmon Field and Rolling Hills Athlete Lighting Project
Application Period.
A
� Item
Bid ItcmNo.
City Secretary 56985
Contract Nam:
B C D
Specification unit of Bid Quantity unit Price Bid value Installed Estimated Quantityaloe
Section No. Measure
Contractor's Application
Application Numb 5 1
Application Date. 09/23/2022
E F G
Mat "a tit % Balance to Finish
Previously Installed Completed and
Value Value Thie Period P (oe1�5�red Stored 1n Date Bj �B
m ci
This dacumem has been moddlid firm it, ong 11orth as an UCDC document and the user did not highlight the
modificedons. You are encouraged 0 read the document—cholly and coneolt Legal Counsel poor tons execution.
C-620 Unit Price Prcgress Estimate
Progress Estimate
Per (cmitract)' Harmon Field and Rolling Hills Athlete Lighting Project
Application Period.
A
� Item
Bid ItcmNo.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
City Secretary 56985
Contract Nam:
B C D
Specification unit of Bid Quantity unit Price Bid value Installed Estimated Quantityaloe
Section No. Measure
Contractor's Application
Application Numb 5 1
Application Date. 09/23/2022
E F G
Mat "a tit % Balance to Finish
Previously Installed Completed and
Value Value Thie Period P (oe1�5�red Stored 1n Date Bj �B
m ci
I I
I I
I
I I
I I
I I
I
I I
I I
I I
I
I I
I I
I I
I
I I
I I
I I
I I
I I
I I
I I
I I
I I
I I
I I
This dacumem has been moddlid firm it, ong 11orth as an UCDC document and the user did not highlight the
modificedons. You are encouraged 0 read the document—cholly and coneolt Legal Counsel poor tons execution.
C-620 Unit Price Prcgress Estimate
Progress Estimate
Per (cmitract)' Harmon Field and Rolling Hills Athlete Lighting Project
Application Period,
A
I Item
Bid ItcmNo.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
City Secretary 56985
Contract Nam:
B C D
Specification unit of Bid Quantity unit Price Bid value Installed Estimated Quantityaloe
Section No. Measure
Contractor's Application
Application Numb 5 1
Application Date. 09/23/2022
E F G
Mat "a tit % Balance to Finish
Previously Installed Completed and
Value Value Thie Period P (oe1�5�red Stored 1n Date Bj �B
I
I I
I I
I I
I I
I I
I I
I I
I I
I
I I
I I
I I
I
I I
I I
I I
I
I I
I I
I I
I
I I
I I
I I
I
I I
I I
I I
I
I I
I I
I I
I
I I
I I
I I
I
I I
I I
I I
I
I I
I I
I I
I
I I
I I
I I
I
I I
I I
I I
I
I I
I I
I I
I
I I
I I
I I
I
I I
I I
I I
I
I I
I I
I I
I I
I I
This dacumem has been moddlid firm it, ong 11orth as an UCDC document and the user did not highlight the
modificedons. You are encouraged 0 read the document—cholly and coneolt Legal Counsel poor tons execution.
C-620 Unit Price PrcOrssa Estimate
Progress Estimate
Per (cmdract)' Harmon Field and Rolling Hills Athlete Lighting Project
Application Period,
A
Item
Btd ItcmNo.
Totals
City Secretary 56985
Contract Num:
B C
Specification unit of Bid Quantity unit Price Bid Value Estimated Quantity
Section No. Measure Installed
Contractor's Application
Application Numb 5
Application Date. 09/23/2022
D B F G
Matmals t�ua % Balance to Finish
Previously Installed Completed and
Value Value Value This Period P (oely Sin tated Stored to Date B) (B F)
ii,
$1,780,140.00 97.2%
$52,000.001
This dacumem has been moddlid firm it, onl forth as an UCDC document and the user did not highlight the
modificedons. You are encouraged 0 read the document —drolly and ccneolt Legal Counsel pnor tons execution.
C-620 Change Order
Progress Estimate
Change Order Number I
1
Contractor's Application
ADDITIONS
(For (contract).
Z961/ 10V Harmon Field and Rolling
Hills .Athlete Lighting Project
City Secretary
56985
Application Number:
FINAL
Contract Num:
(Application Period:
Application Date:
11/1/2023
A
B
C
D
E
F
Item
Addition
Total Completed
Balance to Fmosh
Change Order Item
Specification
CO Quantity ro Add
Uni[ Price
Change Order
Estimated Quantity
Value
Prevmusly
Value This Matevals Presently
and Stored to Dale
(F) (B - F)
No
Descvphon
Section No. Unrt of Measure
Value
Installed
Installed Valne
Period Stared (not in C)
(D I E)
B
3_01
CONSTRUCTION STALKING
LS
1.00000000
$10,000.00
$10,000.00
1.00000000
$10,000.00
$10,000.00
$10,000.00
100.0%
3_02
( EXCAVATION, TRENCHING AND BACKFILL
LS
1.00000000
$20,263.00
$20,263.00
1.00000000
$20,263.00
$20,263.00
$20,263.00
100.0%
3_03
ICONDUCTORS
LS
1.00000000
$14,679.00
$14,679.00
1.00000000
$14,679.00
$14,679.00
$14,679.00
100.0%
3_04
I CONDUIT AND BOXES
LS
1.00000000
$30,247.00
$30,247.00
1.00000000
$30,247.00
$30,247.00
$30,247.00
100.0%
3_05
(WIRE DEVICES
LS
1.00000000
$176.00
$176.00
1.00000000
$176.00
$176.00
$176.00
100.0%
3_05
I LIGHT FIXTURES, POLES AND CONTROLS
LS
1.00000000
$241,218.00
$241,218.00
1.00000000
$241,219.00
$241,218.00
$241,219.00
100.0%
3_06
15" CONCRETE PAD 10'X4'
LS
1.00000000
$12,849.00
$12,849.00
1.00000000
$12,949.00
$12,849.00
$12,949.00
100.0%
3_07
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I SWITCH GEAR INCLUING PANELS, ENCLOSURES, ETC. LS
I I
I I
I I
I I
I I
I I
I I
I I
I I
I I
I I
I I
I I
I I
I I
I I
I I
I I
1.00000000
$38,568.00
$38,568.00
0.77300000
$38,569.00
$38,568.00
$38,569.00
100.0%
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
This document has bcen modified from its original farm as an E]CDC document and the user did not highlight the
modifications. You are encouraged to read the document carefully and consult Legal Counsel prior torts execution.
C-620 Change Order
Tntals
$368,000.00
$368,000.00 $368,000.00
$368,000.00 100.0%
Progress Estimate Change Order Number 1
Contractor's Application
DELETIONS
For(.. -et): Z961 / 10V Harmon Field and Rolling Hills Athlete Lighting Project
Application Norther.
FINAL
Application Pend
Application Date:
ll/l/2023
A
B C
D E
F
I'm CO Quantity to
Deletion
Change Order Item Description Spec,ficatmn Unit Measure Delete
Unit Price Change Order Not Used
Net Used Not Used Not Used Not Used
Not Used Not Used Not Used
of
No. Section No.
Value
This document has been modified from its original farm as an EJCDC document and the user did not highlight the
modifications. You are encouraged to read the document carefully and consult Legal Counsel prior torts execution.
C-620 Change Order
Totals
This document has been modified from its original form as an EJCDC document and the user did not highlight the
mrshficatmns. You are encouraged to read the document carefully and consult Legal Counsel poor to rts execution.
City Secretary Contract Num: I 56985
Application Period:
Funding Identification (FID)
Original Contract
1 34018-0800450-5740010-101768-004380-9999-18020102
1 34018-0800450-5740010-101768-c04380-9999-18020102
I0
I0
I0
I0
I0
I0
I0
I0
I0
Change Order 1
1 34018-0800450-5740010-101768-004380-9999-18020102
1 34018-0800450-5740010-101768-c04380-9999-18020102
I0
I0
I0
I0
I0
I0
I0
I0
I0
Change Order 2
1 34018-0800450-5740010-101768-004380-9999-18020102
1 34018-0800450-5740010-101768-c04380-9999-18020102
I0
I0
I0
I0
I0
I0
I0
I0
I0
Change Order 3
1 34018-0800450-5740010-101768-004380-9999-18020102
1 34018-0800450-5740010-101768-c04380-9999-18020102
City of Fort Worth Summary of Charges
Harmon Field and Rolling Hills Athlete Lighting Project I P. 0.: FW080-00000010406
0 Application I FINAL
Number:
Total Completed Amt Remaining Gross
$504,830.00
$1,275,310.00
$368,000.00
$26,000.00
$26,000.00
Project Number: 102961 / 102962
Application Date: 11/1/2023
Retainage Net
City of Fort Worth Summary of Charges
City Secretary Contract Num: 56985 Harmon Field and Rolling Hills Athlete Lighting ProjApplicaect I P. O.: FW080-00000010406 Project Number: 102961 / 102962
tion
Application Period: 0 Number: FINAL Application Date: 11/1/2023
Funding Identification (FID) Total Completed Amt Remaining Gross Retainage Net
Change Order 4
1 34018-0800450-5740010-101768-004380-9999-18020102
1 34018-0800450-5740010-101768-c04380-9999-18020102
10
10
10
10
10
10
10
10
10
Change Order 5
1 34018-0800450-5740010-101768-004380-9999-18020102
1 34018-0800450-5740010-101768-c04380-9999-18020102
10
10
10
10
10
10
10
10
10
Change Order 6
1 34018-0800450-5740010-101768-004380-9999-18020102
1 34018-0800450-5740010-101768-c04380-9999-18020102
10
10
10
City of Fort Worth Summary of Charges
City Secretary Contract Num: 56985 Harmon Field and Rolling Hills Athlete Lighting ProjApplicaect I P. O.: FW080-00000010406 Project Number: 102961 / 102962
tion
Application Period: 0 Number: FINAL Application Date: 11/1/2023
Funding Identification (FID) Total Completed Amt Remaining Gross Retainage Net
Change Order 7
1 34018-0800450-5740010-101768-004380-9999-18020102
1 34018-0800450-5740010-101768-c04380-9999-18020102
10
10
10
10
10
10
10
10
10
Change Order 8
1 34018-0800450-5740010-101768-004380-9999-18020102
1 34018-0800450-5740010-101768-c04380-9999-18020102
10
10
10
10
10
10
10
10
10
Totals
1 34018-0800450-5740010-101768-004380-9999-18020102
1 34018-0800450-5740010-101768-c04380-9999-18020102
10
10
10
10
10
10
$872,830.00 $26,000.00
$1,275,310.00 $26,000.00
City of Fort Worth Summary of Charges
City Secretary Contract Num: 56985 Harmon Field and Rolling Hills Athlete Lighting ProjApplicaect I P. O.: FW080-00000010406 Project Number: 102961 / 102962
tion
Application Period: 0 FINAL Application Date: 11/1/2023
Number:
Funding Identification (FID) Total Completed Amt Remaining Gross Retainage Net
10 1.00 $0.00 0.00 $0.00
10 .00 H $0.00 ).00 Qn nn
10 .00 $0.00 ).00
Grand Total $2,148,140.00 $52,000.00 1 1 $0.00 1 1 ($107,407.00)1 1 $107,407.00
G
4 1 34018
C
2060000 102961
5 1 102962
RETAIN
RETAIN
G I H
(77,123.12) (77,123.12)
(9,599.70) (30,283.89)
CSC No. 56985-COl
Fox,.,,
Project Name Athletic Field Lighting at 101961,101962
Client Project #(s)� 101961,101962
Project
Description
Contractor Groves Electrical Service, Inc.
City Project Mgr.1 Helen Florez
Dept. PARD
Original Contract Amount $1,832,140.00
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
City of Fort Worth
Change Order Request
Athletic Field Lighting
I� Change Order#1 1
I
I City Sec # 1 56985
I Datel 8/3/2022
City Inspector Tolliver Lipka / Ron Cordova
Contract Time
Totals (CD)
$1,832,140.00 200
Contract Cost to Date
$1,832,140.00
$1,832,140.00 200
Amount of Proposed Change Order
$368,000.00
$368,000.00 60
Revised Contract Amount
$2,200,140.00
$2,200,140.00 260
Original Funds Available for Change Orders
$368,000.00
$368,00.00
Remaining Funds Available for this CO
$368,000.00
$368,000.00
Additional Funding (if necessary)
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
20.09%
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%)
$2,290,175.00
JUSTIFICATION (REASONS) FOR CHANGE ORDER
On November 30, 2021, City Council authorized the execution of a construction contract with Groves Electrical Service, Inc., in the amount of $1,832,140.00 for the
installation of atheltic field lighting at Harmon Field and Rolling Hills Park (MC-21-0926). After the award of the contract it was determined there were still funds available for
additional lighting at Rolling Hills Park.The additional scope of work will increase the contract time from 200 calendar days to 260 calendar days. The Change Order was
authorized by M&C 22-0474.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in
full (both time and money) for all costs arising out of, or incidental to, the above Change Order. The Project/Program Manager signing below acknowledges
that he/she is the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting
requirements.
Groves Electrical Service, Inc.
William H. Groves
8/4/2022
Inspector/Inspection Supervisor
M
Project and Contract Compliance Manager
o.+cwaco,:a:zw�.con
Aug 4, 2022
'J�tjl'
8/3/22
Program Manager
Date
Senior Capital Project 0 icer
Aug 11, 2022
Assistant Director (Dept)
Date
Director, Contracting Department (Dept)
Aug 15, 2022
061,e
Aug 15, 2022
Assistant City Attorney
Date
Assistant City Manager
Date
�P ^
Aug 24, 2022
4a5n W —2 o9 s o.,
Aug 25, 2022
Council Acti
M&C Number 22-0474 l M&C Date Approved 6/28/20221
ATTEST:
Jannette Goodall, City Secretary
FORTWORTH City of Fort Worth
—�'V`— Change Order Additions
Project Name I Athletic Field Lighting at 101961,101962 City Sec # I 56985
Client Project# 1 101961,101962 1
Contractoi Groves Electrical Service, Inc. PMJ Helen Florez Inspecto ' u"u'i'� P"nr.�n
Change Order Submittal # O1 Date 1 7/19/2022
ADDITIONS
HEM
UES(;RIP 1IUN
UEP I
Uty
Unit
Unit Cost
I otal I
J_U1
U1 /1 2J Construction Staking
PAKU
1.000000U(
LS
$10,000.UI,
$10,000.0UI
3_02
26 05 00 Excavation, trenching, and backfill
PARD
1.00000004
LS
$20,263.OL
$ZU,ZbJ.UU1
3_03
26 09 19 Conductors
PARD
1.0000000(
LS
$14,679.0L
$14,b/9.UUI
3_04
26 05 33 Conduit and boxes
PARD
1.0000000(
LS
$30,247.OL
$JU,Z4/.UUI
3_05
26 27 26 Wire devices
PARD
1.0000000(
LS
$176.01L
$1 /b.UU1
305
26 56 68 Light fixtures, poles, and controls
PARD
1.0000000E
LS
$241,218.UL
$241,216.0UI
3_05
5' Concrete Pad 10'x4'
PARD
1.0000000U
LS
$12,849.01L
$12,849.0UI
3_07
Switchgear incluing panels, enclosures, etc.
PARD
1.00000000
LS
$38,568.01L
$Jb,bb8.UU1
I
I
1
PARD $368,000.00
Sub Total Additions $358:000.00
Change Order Additions Page 3 of 4
FORT WaRTH City of Fort Worth
7' Change Order Deletions
Project Name Athletic Field Lighting at 101961,101962 City Sec # 1 56985
Client Project# 101961, 101962
Contractor Groves Electrical Service, Inc. I PMI Helen Florez Inspector u wl r An RUU
Change Order Submittal # Date j 7/19/2022 j
DELETIONS
11 LM ULSGKII I IUN ULV I Uty Unit Unit GOst I otal
PAIMAD $0.00
Sub Total Deletions $0.00
Change Order Deletions Page 1 of 4
M/SBE for this Change Order
M/SBE Sub Type of Service Amount for this CO
maintaining commitment on origninal agreement of 13%
Total $0.00
Previous Change Orders
CO# DATE I AMOUNT
Total I $0.00 I
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 06/28/22 M&C FILE NUMBER: M&C 22-0474
LOG NAME: 80ATHLETIC FIELD LIGHTING HARMON FIELD AND ROLLING HILLS PARK*
SUBJECT
(CD 8) Authorize Change Order No. 1 to a Construction Contract with Groves Electrical Service, Inc., to the Athletic Field Lighting for Harmon Field
and Rolling Hills Park Project in the Amount of $368,000.00 for a Total Contract Value of $2,200,140.00 (2018 Bond Program)
RECOMMENDATION:
It is recommended that the City Council authorize Change Order No. 1 to the construction contract with Groves Electrical Service, Inc., (City
Secretary No. 56985) to the Athletic Field Lighting for Harmon Field and Rolling Hills Park Project (City Project No. 102962) in the Amount of
$368,000.00 for a Total Contract Value of $2,200,140.00 (2018 Bond Program)
R1411*1 [a]ZF
The purpose of this Mayor and Council Communication (M&C) is to authorize Change Order No. 1 to the construction contract with Groves
Electrical Service, Inc., (City Secretary No. 56985) to the Athletic Field Lighting for Harmon Field and Rolling Hills Park Project in the amount of
$368,000.00 for a total contract value of $2,200,140.00.
On November 30, 2021 the City Council authorized execution of a construction contract (M&C 21-0926, City Secretary Contract No. 56985) with
Groves Electrical Service, Inc., in the amount of $1,832,140.00 for the installation of athletic field lighting at Harmon Field and Rolling Hills Park. Of
this award amount $1,301,310.00 was allocated for lighting at Rolling Hills Park.
On September 23, 2021 bids were received for the installation of athletic field lighting, including 6 ball fields at Rolling Hills Park. Groves Electrical
Services, Inc., accepted bid was $498,690.00 below budget for improvements. Change Order No. 1 in the amount of $368,000.00 will fund the
lighting of an additional ball field at Rolling Hills Park.
This project is included in the 2018 Bond Program. Available resources within the general fund will be used to provide interim financing until debt is
issued. Once debt associated with the project is sold, bond proceeds will reimburse the general fund in accordance with the statement expressing
official Intent to Reimburse that was adopted as part of the ordinance canvassing the bond election (Ordinance No. 23209-05-2018) and
subsequent actions taken by the Mayor and Council.
Construction of this project began in April 2022 and completion is projected to be in August 2022.
The impact of the additional project scope on the Park & Recreation Department's annual operating budget when the project is completed will be
$5,000.00. As of April 30, 2022, the cumulative total of all previously approved M&C's increased the department's estimated annual maintenance
by $418,331.00 beginning in FY2023.
Compliance with the City's Business Equity Ordinace has been achieved by the following method: Groves Electrical Service, Inc., is in compliance
with the City's Business Equity Ordinance by committing to 13% participation on this project's base bid. The City's Business Equity goal for this
project is 11 %.
Rolling Hills Park is located in COUNCIL DISTRICT 8.
FISCAL INFORMATION / CERTIFICATION:
The Director of Finance certifies that funds are available in the 2018 Bond Program Fund for the Rolling Hills Athletic Field Lighting project to
support the approval of the above recommendations and execution of the amendment. Prior to an expenditure being incurred, the Park &
Recreation Department has the responsibility of verifying the availability of funds.
Submitted for Citv Manaaer's Office bv: Valerie Washington 6192
Oriainatina Business Unit Head: Richard Zavala 5704
Additional Information Contact: David Creek 5704
FORT WOR"iN
—T— City of Fort Worth
ACCEPTANCE OF PREVIOUS M/WBE COMMITMENT FORM
(for use with CHANGE ORDERS or AMENDMENTS greater than $100,000)
To be Completed by City Project Manager
Amendment (for Contractual Services Agreement)
Project Name: City Project Number
ATHLETIC FIELD LIGHTING HARMON FIELD AND 102962
ROLLING HILLS PARK City Project Manager
Contractor: Helen Florez
Groves Electrical Service, Inc. City's M/WBE Project Goal
Original Amount of Agreement: $1,759,850.00 Accepted M/WBE Commitment:
Total of Previous Amendments: Date of Last M/WBE Report:
Amount for this Amendment: $400,000.00 Amendment #: 1
Revised Amount of Agreement: $2,159,850.00 Date: 4/27/2022
Language to be inserted in the M&C for this Agreement
11 %
13 %
Groves Electrical Service, Inc. agrees to maintain its initial M/WBE commitment of 13% that it
made on the original agreement and extend and maintain that same M/WBE commitment of 13%
to this first amendment. Therefore Groves Electrical Service, Inc. remains in compliance with the
City's M/WBE Ordinance and attests to its commitment by its signature on the Acceptance of
Previous M/WBE Commitment form executed by an authorized representative of its company.
To be Completed by the Representative of the Change Order (for Construction Contract)
William H. Groves President ,���" 1�
Printed Name Title A thorized Signature/Date
Groves Electrical Service, Inc.
Company Name
2410 Squire Place
Address
Farmers Branch, Texas 75234
City/State/Zip
Billy Brown
Contact Name (if different)
billvPk-roveselectric.com
E-mail address
972-484-2717
Phone number
0% as of 4/29/2022
M/WBE % Paid to Date Date
972-484-2263
Fax Number
City Project Manager has reviewed the work associated with this Amendment,
considers it the same or similar to work in the original Agreement, and recommends that the
Change Order (for Construction Contract) have the option to retain and confirm its existing M/WBE
commitm�I^, .
Helen Florez _, / �1en 5/2/22
City Project Manager City Project Manager gnature Date
Walter K. Newman 0
M/WBE Compliance Staff ID # M/WBE Current % Level via Last Report Rec'd
ltl)O�Z�4f 1 05/11 /2022
M/WBE Signature Date
FORTWORTH.
M"
TRANSPORTATION AND PUBLIC WORKS
October 10, 2023
Groves Electrical Service Inc
2410 Squire PI.
Farmers Branch TX 75234
RE: Acceptance Letter
Project Name: Athletic Field Lighting
Project Type: Lighting
City Project No.: 102961 & 102962
To Whom It May Concern:
On July 26, 2023 a final inspection was made on the subject project. There were punch list items
identified at that time. The punch list items were completed on October 4, 2023. The final inspection
and the corrected punch list items indicate that the work meets the City of Fort Worth specifications and
is therefore accepted by the City. The warranty period will start on October 4, 2022, which is the date of
the punch list completion and will extend of two (2) years in accordance with the Contract Documents.
If you have any questions concerning this letter of acceptance, please feel free to contact me at Helen
Florea (817)392-7372.
Sincerely,-- //
��nn
Helen Florez, Project Manager
Cc: Travis Strang, Inspector
Don Watson, Inspection Supervisor
Aaron Ybarra, Senior Inspector
Victor Tornero, Program Manager
Boydston Designs, Consultant
Cates, Courtney & Roebuck, Inc, Contractor
5707 Horne st LLC, Developer
File
E-Mail: TPW_Acceptance@fortworthtexas.gov
Rev. 8/20/19
CONSENT OF
SURETY COMPANY
TO FINAL PAYMENT
AIA DOCUMENT G707
OWNER
X
ARCHITECT
❑
CONTRACTOR
❑
SURETY
❑
OTHER
❑
Bond # TXC614092
PROJECT: ATHLETIC FIELD LIGHTING AT: HARMON FIELD PARK AND ROLLING HILLS SOCCER
COMPLEX - City Project No.:102961 & 102962
TO (Owner):
City of Fort Worth
1000 Throckmorton Street
Fort Worth, TX 76102
CONTRACTOR:
Groves Electrical Service, Inc.
CONTRACT FOR: Construction
CONTRACT DATE:
In accordance with the provisions of the Contract between the Owner and the Contractor as indicated above, the
Merchants Bonding Company
6700 Westown Parkway
Des Moines, IA 50266-1158 , SURETY COMPANY,
on bond of
Groves Electrical Service, Inc.
2410 Squire Place
Farmers Branch, TX 75234
,CONTRACTOR,
hereby approves of the final payment to the Contractor, and agrees that final payment to the Contractor shall not relieve
the Surety Company of any of its obligations to
City of Fort Worth
1000 Throckmorton Street
Fort Worth, TX 76102 OWNER,
As set forth in the said Surety Company's bond
IN WITNESS WHEREOF,
the Surety Company has hereunto set its hand this 14th day of November. 2023.
Attest: _
(Seal) Eric Lesch, Witness
Merchants Bonding; Company
Surety
Signature of ut� preserftative
Felix Navejar, Attorney -In -Fact ; :1=G G G,-,"'-
Name & Title y
,
y
I
AIA DOCUMENT G707 - CONSENT OF SURETY COMPANY TO FINAL PAYMENT - APRIL 1970 EDITION • A[At
0 1970 • T"E AMERICAN INSTITUTE OF ARCHrFECTS, 1735 NEW YORK AVE., NW, WASHINGTON, D.C. 20006
Obligee; City LE Fort Worth 1 � EL�� �7
Project: ATHLETIC FIELD LIGHTING AT: HARMON FIELD PARK AND ROLLING HILLS SOCCER ,J[�`//�L
COMPLEX - City Project No.:102961 & 102962
Principal: Groves Electrical Service. Inc. BONDING COMPANY,
Bond No.: TXC614092
POWER OF ATTORNEY
Know All Persons By These Presents, that MERCHANTS BONDING COMPANY (MUTUAL) and MERCHANTS NATIONAL BONDING, INC.,
both being corporations of the State of Iowa, dlbla Merchants National Indemnity Company (in California only) (herein collectively called the
"Companies") do hereby make, constitute and appoint, individually,
Clem F Lesch; Eric Lesch; Felix Navejar; Melissa Lesch
their true and lawful Attorneys) -in -Fact, to sign its name as surety(ies) and to execute, seal and acknowledge any and all bonds, undertakings,
contracts and other written instruments in the nature thereof, on behalf of the Companies in their business of guaranteeing the fidelity of
persons, guaranteeing the performance of contracts and executing or guaranteeing bonds and undertakings required or permitted in any actions
or proceedings allowed by law
This Power -of -Attorney is granted and is signed and sealed by facsimile under and by authority of the following By -Laws adopted by the Board
of Directors of Merchants Bonding Company (Mutual) on April 23, 2011 and amended August 14, 2015 and adopted by the Board of Directors of
Merchants National Bonding, Inc., on October 16, 2015.
"The President, Secretary, Treasurer, or any Assistant Treasurer or any Assistant Secretary or any Vice President shall have power and
authority to appoint Attorneys -in -Fact, and to authorize them to execute on behalf of the Company, and attach the seal of the Company thereto,
bonds and undertakings, recognizances, contracts of indemnity and other writings obligatory in the nature thereof."
"The signature of any authorized officer and the seal of the Company may be affixed by facsimile or electronic transmission to any Power of Attorney
or Certification thereof authorizing the execution and delivery of any bond, undertaking, recognizance, or other suretyship obligations of the
Company, and such signature and seal when so used shall have the same force and effect as though manually fixed."
In connection with obligations in favor of the Florida Department of Transportation only, it is agreed that the power and aut hority hereby given to the
Attorney -in -Fact includes any and all consents for the release of retained percentages andlor final estimates on engineering and construction
contracts required by the State of Florida Department of Transportation. It is fully understood that consenti ng to the State of Florida Department
of Transportation making payment of the final estimate to the Contractor and/or its assignee, shall not relieve this surety company of any of
its obligations under its bond.
In connection with obligations in favor of the Kentucky Department of Highways only, it is agreed that the power and authority hereby given
to the Attorney -in -Fact cannot be modified or revoked unless prior written personal notice of such intent has been given to the Commissioner -
Department of Highways of the Commonwealth of Kentucky at least thirty (30) days prior to the modification or revocation.
In Witness Whereof, the Companies have caused this instrument to be signed and sealed this 8th day of December 2022
+�;�'••, . • MERCHANTS BONDING COMPANY (MUTUAL)
+'+1P. (• • •Q�N�.CQ••. MERCHANTS NATIONAL BONDING, INC.
ep R 0 A9 •dlbla MERCHANTS NATIONAL INDEMNITY COMPANY
•
2003 ;1�>7 = : y' 1933 . y : By
J� ,
...... �•,•�1•.....• �1�•�� President
STATE OF IOWA ••'•,,,1!l11.++'• •• • • • `••
COUNTY OF DALLAS ss.
On this 8th day of December 2022 before me appeared Larry Taylor, to me personally known, who being by me duly sworn
did say that he is President of MERCHANTS BONDING COMPANY (MUTUAL) and MERCHANTS NATIONAL BONDING, INC.; and that the
seals affixed to the foregoing instrument are the Corporate Seals of the Companies; and that the said instrument was signed and sealed in behalf
of the Companies by authority of their respective Boards of Directors.
05�'lAt Kin Lee
z° 7 Commission Numbea 702737 l
i)ItY Corrrrtimn Expires
rP,iE April 14, 2024
Notary Public
(Expiration of notary's commission does not invalidate this instrument)
I, William Warner, Jr., Secretary of MERCHANTS BONDING COMPANY (MUTUAL) and MERCHANTS NATIONAL BONDING, INC., do hereby
certify that the above and foregoing is a true and correct copy of the POWER -OF -ATTORNEY executed by said Companies, which is still in full
force and effect and has not been amended or revoked.
In Witness Whereof, I have hereunto set my hand and affixed the seal of the Companies on this 14th day of November. 2023.
+++7I111,7
C•�O
, s [-�- • "
o
•
r
,.7'.AEtPO/� :
RPU9�'4y..
. J'�it,••
�
2003 ; ,;�
;1933
Secretary
+� �y •�
••'
AL
POA 0018 (10I22)
Bond(s) produced by:
PCL Contract Bonding Agency PO Box 1306, Colleyville, TX 76034 972-459-4749 www.Dclbords.com bondrequest@pclbonds.com
� TM
=: ® Document Glob -1994
Contractor's Affidavit of Payment of Debts and Claims
PROJECT: (Name and address)
Harmon Field & Rolling Hills
Roiling Hills Soccer Complex
TO OWNER: (Name and address)
City of Fort Worth
STATE OF: Texas
COUNTY OF: Dallas
ARCHITECT'S PROJECT NUMBER:
CONTRACT FOR. General Construction
CONTRACT DATED:
OWNER:
ARCHITECT: ❑
CONTRACTOR: ❑
SURETY: ❑
OTHER: ❑
The undersigned hereby certifies that, except as listed below, payment has been made in full and all obligations have
otherwise been satisfied for all materials and equipment furnished, for all work, labor, and services performed, and for
all known indebtedness and claims against the Contractor for damages arising in any manner in connection with the
performance of the Contract referenced above for which the Owner or Owner's property might in any way be held
responsible or encumbered.
EXCEPTIONS:
SUPPORTING DOCUMENTS ATTACKED HERETO:
1. Consent of Surety to Final Payment, Whenever
Surety is involved, Consent of Surety is
required. AIA Document G707, Consent of
Surety, may be used for this purpose
Indicate Attachment ❑ Yes ® No
The following supporting documents should be attached
hereto if required by the Owner:
1, Contractor's Release or Waiver of Liens,
conditional upon receipt of final payment.
2. Separate Releases or Waivers of Liens from
Subcontractors and material and equipment
suppliers, to the extent required by the Owner,
accompanied by a list thereof.
3. Contractor's Affidavit of Release of Liens (AIA
Document G706A).
CONTRACTOR: (Name and address)
Groves Electrical Service, Inc.
2410 Squire Place
Farmers Branch, Texas 75234
BY: A fL-J
(Sign lure of authorised representative)
Maria Groves
(Printed name and title)
Subscribed and sworn to before me on this date:
14th Day of November, 2023
��nn
Notary Public: l Alp —
My Commission Expires:
m
EgdW6A
CHRIST;AV COLLAZO
Notary ID 4132838303 3
My Com(nission Expires iIDecorhmf 12, 2024
AIA Document G708TM —1994. Copyright O 1970 and 1994 by The American institute of Architects. All rights reserved. WARNING: This AIA' Document le
protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this A10 Document, or any portion of it, may 1
result In severe civil and criminal penakles, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA
software at 12:57:48 on 0911512009 under Order No.7078152731 1 which e)ires on 0712912010, end is not for resale.
User Notes: (1095324980)