HomeMy WebLinkAboutContract 57278-CO3CSC No. 57278-CO3
FOR'' WORTH City of Fort Worth
Change Order Request
Project Name:l Westside III/IVN (Markum lunch Pump Stalion-PS & Ground Storage Tank-GST)
City Sec No.: 1 57278
Project No.(s):l 56020 / 06004301001680 1 DOE No. I N/A I City Proj. No.: l 103010 1
Project Description:! PS Building; Three 4,750 gpm horizontal spilt case pumps v, 400 HP niotors;Three 7,000 gpm horizontal split case pumps w 300 HP motors; A 3 MG Concrete
I GST; Electrical & Controls,1,600 kVV generator, necessary piping, vaults and site work, etc,
Contractor.1 Crescent Constructors, Inc. Change Order # ( 3 Date: 8/2/2024
City Project Mgr. I Farida Goderya, PE
Phone Number] 817-392-8214
Dept.
Original Contract Amount
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date
!Amount of Proposed Change Order
Revised Contract Amount
Original Funds Available for Change Orders
Remaining Funds Available for this CO
Additional Funding (if necessary)
CHANGE ORDERS to DATE (l
MAX ALLOWABLE CON
City Inspector: I Ivan Rocha (KHA) I Ronnie Cardenas
Phone Number:j 682.234.2767 1
Water
120/993,000.00
$25,400.00
Sewer
I
I Totals
$20,993,000.00
Contract Time
(Calender days)
640
160
$25,400.00
$56,100.00
$56,100.00
$20,962,300.00
$20,962,300,00
800
$0.00
$20, 62,300.00
$0.00
110
910
$20,962,300.00
$419,860.00
$394,00.u0
$419,860.00
$394,460.00
NCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
TRACT AMOUNT (ORIGINAL CONTRACTCOST+ 25%)
.0.15%
$26,241,250.00
JUSTIFICATION (REASONS) FOR CHANGE ORDER
Change Order No. 3 provides for the addition of 110 calendar days to the contract for the delays associated with the
fabrication and delivery of WS5 pumps.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in
full (both time and money) for all costs arising out of, or incidental to, the above Change Order.
Contractor's Company Name Contractor Name joqtracto�Zignature 1 Date
Crescent Constructors, Inc. Ryan Glanz, PE -�� r 4,,,,. f-- VVIL
Inspector
Date
Project Mana a
Date
Iv "ilv
08/16/24
Fa+-Lo(.a� CroAe r a,
08/20/2024
Director (Water Dept)
Date
Construction Supervisor
Date
cCk sto�/zer��
Aug 26, 2024
N/A
Assistah C Aftome
Date
Assistant City Manager
Date
Aug 28, 2024
—,.c _ IAug
28, 2024
Council Action (If Required) OFFICIAL RECORD
M&C Number n/a I M&C Date Approved n/a CITY SECRETARY
FT. WORTH, TX
FORT WORTH City of Fort Worth
Change Order Additions
Project Name Westside IIIIIVN (Markum Ranch Pump Station -PS & Ground Storage Tank-GST) City Sec No.: 57278
Project No.(s): 56020 / 0600430 / 001680 1 DOE No. 1 N/A City Proj. No.: 103010
I V UUIIUII IJI I111G0 Y,1 JV IJplII IIVI ILVIIIQI 0F/II1 V000 [JUMV0 VY YVV 111 IIwlV10, I MCC 1,VVV 1J�./1l1 IIVI ILVl I1QI oplll VQOG
Project I pumps w 300 HP motors; A 3 MG Concrete GST; Electrical & Controls, 1,600 kW generator, necessary piping, vaults
Description . -A _4 '- A, -+-
Contractor Crescent Constructors, Inc. Change Order: 3 Date: 1 8/2/2024
City Project Mgr. Farida Goderya, PE City Inspector I Ivan Rocha (KHA) / Ronnie
ADDITIONS
I I tM DF-SCItIP I IUN DEPT Qty Unit Unit Cost I Total
Water
Sewer
Page 1 of 1 Additions Sub Total
FORT WORTH City of Fort Worth
Change Order Deletions
Project Name I Westside IIIIIVN (Markum Ranch Pump Station -PS & Ground Storage Tank-GST) City Sec No.: I 57278
Project No.(s): I 56020 / 0600430 / 001680 I DOE No. I N/A City Proj. No.: I 103010
Project Description PS Building; Three 4,750 gpm horizontal split case pumps w 400 HP motors;Three 7,000 gpm horizontal split case
pumps w 300 HP motors; A 3 MG Concrete GST; Electrical & Controls, 1,600 kW generator, necessary piping,
Contractor I Crescent Constructors, Inc. I Change Order: F3 ] Date I 8/2/2024
City Project Mgr. I Farida Goderya, PE I City Inspector: I Ivan Rocha (KHA) / Ronnie Cardenas
ITEM DESCRIPTION
DELETIONS
DEPT Oty Unit Unit Cost Total
Water
Sewer
Page 1 of 1 Deletions Sub Total
MMBE Breakdown for this Change Order
MWBE Sub I Type of Service
Same as original Contract Miscellaneous
Previous Change Orders
CO # DATE
1 1 /9/2023
2 12/5/2024
Total
Total
AMOUNT
Amount for this CO I
$25,400.00
-$56,100.00
-$30,700.00 1
$0.00
$0.00 1
Page 1 of 1
Crescent Constructors, Inc.
2560 Technology Dr. Suite 400
Plano, TX 75074
Office:972.422.0014 Cell:469.576.0612 Fax:972.422.0016
04.17.23
Farida Goderya
Senior Project Manager
City of Fort Worth
200 Texas Street
Fort Worth, TX 76102
Reference: Markum GST & Pump Station
CMR-06 Time Extension Request (Thru 04.19.24)
Here is a written request for a time extension of 110 days due to extended WS5 pump
fabrication time to take the project completion to 09.30.24 based on the 04.19.24 CPM
schedule update.
Time Extension Request (As of 04.19.24)
Days
Original SC =
11/5/2023
580
CO#1 (Added Scope) =
11/14/2023
9
CO#2 (Electrical Gear Delviery) =
4/13/2024
151
CMR 06 (Pumps Delivery) =
7/31/2024
110
Current SC (Thru CO#3) =
7/31/2024
270
Original FC =
1/4/2024
640
CO#1 (Added Scope) =
1/13/2024
9
CO#2 (Electrical Gear Delviery) =
6/12/2024
151
CMR 06 (Pumps Delivery) =
9/30/2024
110
Current FC (Thru CO#3) =
9/30/2024
270
Sincerely,
Ryan Glanz, PE
Project Manager
+ 110 Days
MARKUM PUMP STATION GST (04.19 Update)
UUKAIIUN(UAVS)
SUBIVIIIIEU(89)
Kh-SUBIVIIIIAL(89.1&89.1) KEVIEWLUIVIMENIS ANKUVAL
ACTUAL WSS PUMP SUBMITTAL PROCESS (89.2)
169
6/29/2022
11/10/22 & 12/14/22 07/18/22 & 11/16/22 12/14/2022
BASELINE WSS PUMP SUBMITTAL PROCESS (89.2)
117
4/4/2022
7/29/2022
ACTUAL VS. BASELINE PLANNED (SUBMITTAL) = +52 DAYS
RELEASED FOR FAB
ONSITE (PROJECTED)
ACTUAL WS5 PUMP FABRICATION PROCESS
504
12/14/2022
4/30/2024
BASELINE WS5 PUMP FABRICATION PROCESS
285
8/1/2022
5/12/2023
ACTUAL VS. BASELINE PLANNED FAB====
+219DAYS
Acfih*ID
Activity Name
Remaining To1a19-1 Earl,/Start EarlyRnish (4
May2024
June 2024
July2024 I August2024 September2024
Duration 21 28 OS
12 19 26 02
09 1 16 1 23 1 30
1 07 1 14 1 21 1 28 1 04 1 11 18 25 01 08 1 15 1 22 J`-
MARKUM PUMP • t•
' •®'
PROJECT SUMMARY($20,993,000)
62 -14 01Jul-24 30-Sept4
010-0530 STARTUP==INSTRUMENTIONSYSTEM(TARGET=07.0124)
01 -76 01Ju1-24
STARTUP=== INSTRLMENTION SYSTEM(TARGET=07.0124);01Ju1.24
010-0540 STARTUP==ENTIRE PLMPSTATIONSYSTEM(TARGET=0731:
30 -110 01.Iu1-24 31.1ul-24
STARTUP==ENTIREPLMPSTATIONSYSTEM(TARGET-07
010-0910 PROJEC7SUBSTANTIALCOMPLETION(COWRACT=04.1324=0
I 0 -110 31JW-24
4 PROJECTSU&STANf1AL COMPLETION (CONTRACT=04.132,
__-
010-0920 PUNCHLIST
1 60 -110 01-Aug-24 30Sep-24
---__.,.___.__.__.__..____........_
-------------------------
.----
_-___________._________.___-____._.______.__----- ----
010-0950 PROJECTFINALCOMPLETION(CONTRACT=06.1224=04.0422-
0 -110 30Sep-24
4
CHANGE ORDERS & RFFS
0 0
SUBMITTALS
0 0
MATERIAL FABRICATION 11
030-0270 HORIZONTALPl1MPS(SMrIHPUMP)(Taget=043024) 11
MOBILIZATION ($650,000) - 0
YARD PIPING ($5,000,000) 0
SITE IMPROVEMENTS ($1,500,000) 0
PUMP STATION BUILDING ($2,000,000) 0
GROUND STORAGE TANK ($3,000,000) 0
PUMP STATION MECHANICAL ($2,641,000) 33
S06-0110 H&R-IZW RCASEPUMPS DELNERY(WS5) 11
BO6-0140 SETPUMPS 9
B06-0142 PUMPS TO PIPE FINALOMPECTIONS 7
B06-0060 HORIZSPUTCASE PUMPS RELDSUPERVISON(WS4) 5
B06-0070 HORESPLTTCASE PUMPS STARTUP(WS4) 5
ELECTRICAL, INSTRUMENTATION & CONTROLS ($5,000,000) 16
PRIMECONTROLS I&C 16
B07-1040 �Complebonof0pemtonal Readiness Testng(ORT) 10,
B07-1050 Completion of Functional Demonstalion Test(FDT) 6
1,600 KW GEN SET ($1,000,000) 0
PUMP STATION PLUMBING & HVAC ($200,000) °
TRENCH SAFETY ($2,000) °
Actual Level of Effort 0 Remaining Work ♦ ♦Milestone
AclualWork Critical Remaining Work
-109 19-Apr24 30-Apr24
— ---
--109 19-Apr-24 30-Apr-24
_---- --- _ -
j FIOR¢ONTALPLMPS(SMITH PWP)(rag et-043024)
0
0
0
0
0
- ------- ------------------------'--------------------------1---------- - --- ---- - --- -- ---------- ----------------------------------------------
-76 19-Apr--24 05Jun24
-109 19-Apr-24 30,4pr-24 J
FIOR1ZSPUrCASEPLMPSDELIVERYMS5)
761 30-Apr24 104vtay24
SETPUMPS
76I13-May24 21-May24
-76122-May-24 29-May24
- _______.______.._.-_.._..__--__-._.._._._.-. -._....___...__._._._..-
FiOPoZSPLRCASEPLMPS FIELDSUPERVISON(WS4)--------------------- ---
-76 30-May-24 I, 05Jun-24
HORIZSPLRCASEPLfAPSSTARiUP(WS4)
-76 06Jun-24 28.1un24
-76 06Jun-24 28Jun-24
----------- ----- ---- ---! - - - - ------------------------------------- -----------------------------
-76!! 06,J n-24 20Jun-24
;_______.____._.__CompL-(onofOperalonal Readines Tes6ng(ORT)
:...._...._...___..____.___;_.___._.________
-76 21Jun-24 28Jun-24
_--------- ---_._______._-_____-_-_____-_--- ;_--__---___._-.__-.
ComplefonofFunctional Demonshafon Test(FDT)
0
0
0
MARKUM PUMP
STATION GST (04.19 Update) (CO2669) TASK filter. Longest Path.
Page 1
of 1 Date Date (19-Apr-24) 0 Oracle Corporation
8/2/2024
Westside III/IV/V (Markum Ranch Pump Station -PS & Ground Storage Tank-GST)
CSC: 57278-CO3
CPN 103010
Change Order 3 Notes
Staff has reviewed the requested days and considers them to be fair and reasonable.
.Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
Signature
Farida Goderya, PhD, PE
Name of Employee
Senior Project Manager
Title
ATTEST:
Jannette Goodall
City Secretary
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX