HomeMy WebLinkAboutIR 7262 INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 7262 P.I
To the Mayor and Members of the City Council February 23, 1988
it �raxt�z Z5
Subject: FIRE AND POLICE TRAINING ACADEMY
IS 7 1 RENOVATIONS
RECOMMENDATION:
Bids were received on December 30, 1987 on the project with nine contractors
submitting proposals. The apparent low bidder, Inform Construction did not
submit the required MBE forms or the proposed list of sub-contractors and was
thus disqualified as being non-responsive to City bidding requirements .
Inform Construction was apprised of the disqualification and did not object.
The bids were tabulated by Transportation and Pubic Works staff and evaluated
against the estimated budget as of September 15, 1987 which showed $1 ,405 ,000
estimate for the total construction costs including all alternates and
$85,000 established as a contingency. Under normal circumstances , when
working on existing buildings, the conditions anticipated and the actual
findings result in minor change orders. This contingency was placed in the
budget estimate to cover such findings . Suggestions were made by
Transportation and Public Works to the Fire and Police Departments based on
the evaluations made.
A recommendation was received from the Fire and Police Departments which was
based on their needs and budget. This recommendation was within the
established budget and an M&C was prepared based on the recommendation of the
Fire and Police Departments.
For the Council ' s information, regardless of the options selected, only two
firms are in contention for the contract: Witcher Construction, Inc. , and
Ed A. Wilson , Inc . , whose bids are reflected below and in the summary
attached.
BASE BID
Included:
A. Alterations to approximately 11,777 square feet of the existing
building affecting offices, toilets, lockers and kitchen.
B. Remodeling the existing pistol range to house four large classrooms
and conference room.
C. A new addition of approximately 8,329 square feet on the ground
floor and 2,558 square feet on the second floor of an audio/visual
complex including an auditorium, studio library, lobby, public
safety room, toilets and ancillary spaces.
D. Alterations and addition of approximately 1,377 square feet of
OP611 podium and toilet areas to the existing activity room.
ISSUED BY THE CITY MANAGER FORT WORTH, TEXAR
INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 7262 p.2
Alk M4, February 23, 1988
A.-
0i 10 R? To the Mayor and Members of the City Council
V
Subject: FIRE AND POLICE TRAINING ACADEMY
RENOVATIONS
E. Addition of a shelled-in space of approximately 6,969 square feet
above the existing pistol range and corridor. This space was
designed for future classrooms and would be deleted from the base
bid if Alternate #4 is selected.
F. Addition of a 1 ,440 square foot classroom pavilion at the fire
simulation lab site.
G. Addition of a concrete burn pad and fuel storage tank.
H. Additional paving and parking for approximately 106 automobiles.
I. Site work including grading, fencing, and a concrete flume to carry
water from the site to the river.
Witcher Construction, Inc. 's base bid is $1,354.000.
Ed A. Wilson, Inc. 's base bid is $1,398,000.
ALTERNATE NO. 1:
OW Included addition of a ceiling and new light fixtures with accompanying HVAC
duct work in the existing activity room so that it could be used by the
public as a suitable meeting space. This usage was requested by citizens
before the bond issue was voted.
Witcher Construction, Inc. bid $16,500 on this Alternate.
Ed A. Wilson, Inc. bid $11,000 on this Alternate.
ALTERNATE NO. 2:
Included adding a skylighted canopy to the entrance of the audi-o/visual
complex with the intention of making this a major entrance into the building.
It also included adding four skylights over the corridor between the
audio/visual complex and the new classrooms.
Witcher Construction, Inc. did not bid this Alternate.
Ed A. Wilson, Inc. bid $12,000 on this Alternate.
ALTERNATE NO. 3:
Included adding approximately 2 ,704 square feet of shelled-in space on the
ground floor next to the exercise room. This space was originally scheduled
to become the Police Records Room and offices for the Chaplain with an in-
terim use for physical testing of Police rookies. This space was requested
ISSUED BY THE CITY MANAGER FORT WORTH, TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS No. - 7262 p.3
f 0 P,- To the Mayor and Members of the City Council February 23, 1988
ti
FIRE AND POLICE TRAINING ACADEMY
Subject:
10711 RENOVATIONS
to be located as near the lockers.- showers, gym and exercise room as possible
for the best utilization.
Witcher Construction, Inc. bid $65,000 on this Alternate.
Ed A. Wilson, Inc. bid $60,000 on this Alternate.
ALTERNATE NO. 4:
Included a deduction for omitting the shelled-in classroom space on the
second floor indicated in the base bid Item No. E above, and providing for
structure that would carry a roof load only. The deduction would not preclude
the addition of a second floor on this same space at a later date, but at a
greater cost than was bid.
It must be pointed out that some discrepancies in the plans have been
discovered since the bids were opened concerning this space. If the second
floor is built under this contract, the six air-conditioning units shown on
the plans on the first floor roof would need to be relocated up to the second
floor roof, resulting in extending the duct work through the space to the
ceiling of the first floor at an added cost estimated at $3,000. The roof
ladder would also have to be extended to the higher roof at an added cost
estimated at $800. A second stair would have to be designed and included to
meet the building codes at an added cost estimated at $8,000. Total estimate
for this work which was not in the plans is $11,800.
Witcher Construction, Inc. did not bid this Alternate.
Ed A. Wilson, Inc. bid a deduct of $80,000 on this Alternate.
ALTERNATE NO. 5:
Included adding a thermal ice storage system that would provide
air-conditioning for the entire building in lieu of the chillers now being
used. This system would reduce the electrical demand load during the day and
the City would receive a cash rebate from the electrical company . Only
Steele/Freeman submitted a bid on this alternate which was above the amount
budgeted for a reasonable pay-back period.
ALTERNATE NO. 6:
Incl6ded another deduction for using a slab on grade in lieu of the
structural slab as scheduled in the base bid. Because of the expansive soil
conditions in the area, it was determined that this alternate would not be a
[ISSUED BY THE CITY MANAGER FORT WORTH, TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 7262 p.4
,0,9 T I qf" February 23, 1988
to P,- To the Mayor and Members of the City Council
Subject: FIRE AND POLICE TRAINING ACADEMY
RENOVATIONS
Attached is a bidding matrix that shows all possible bid combinations .
Considering value received for the cost involved , the following
recommendation is submitted:
Award the contract to Ed A. Wilson, Inc. , for $1,389,000, to include the Base
Bid of $1 ,398,000; Alternate No. I of $11 ,000 to provide meeting space;
Alternate No. 3 of $60,000 to provide additional shelled-in space on the
,ground floor; and Alternate No. 4 for a deduction of $80,000 to eliminate
second floor shelled-in space for classrooms.
a.,;/— J'_
1 uglas Harman
City Manager
DH:d
Attachment
ISSUED BY THE CITY MANAGER FORT WORTH, TEXAS
FIRE AND POLICE TRAINING ACADEMY RENOVATIONS
BIDDING SUMMARY FEBRUARY 18, 1988
OPTIONS WITCHER CONST. INC. ED A. WILSON,
1. Base Bid Only $1,354,000 $1,398,000
2. Base Bid & Alt. No. 1 $1,370,500 $1,409,000
3. Base Bid & Alts. No. 1 and 2 NA $1,421,000
4. Base Bid & Alts. No. 1 - 2 and 3 NA $1,481,000
5. Base Bid & Alts. No. 1 - 2 - 3 and 4 NA $1,401,000
6. Base Bid & Alts. No. I - 2 and 4 NA $1,341,000
7. Base Bid & Alts. No. 1 and 3 $1,435,000 $1,469,000
8. Base Bid & Alts. No. 1 - 3 and 4 NA $1,389,000
9. Base Bid & Alts. No. 1 and 4 NA $1,329,000
10. Base Bid & Alt. No. 2 NA $1,410,000
11. Base Bid & Alts. No. 2 and 3 NA $1,470,000
opoll 12. Base Bid & Alts. No. 2 - 3 and 4 NA $1,390,000
13. Base Bid & Alts. No. 2 and 4 NA $1,330,000
14. Base Bid & Alt. No. 3 $1,419,000 $1,458,000
15. Base Bid & Alt. No. 3 and 4 NA $1,378,000
16. Base Bid & Alt. No. 4 NA $1,318,000
Low bidder in each case is underlined.
Witcher Construction, Inc. did not bid Alternates No. 2 or No. 4.
Only Alternates considered by staff are included.
If Witcher Construction , Inc. is selected, base bid + Alt. No. 1 would be
the preferrable combination of options.
If Ed A. Wilson, Inc. is selected, base bid + Alt. No. 1, 3, and 4 would be
the preferrable combination of options.
NA: Not applicable bid because Witcher did not bid at least one of the
Alternatives.
00b,