HomeMy WebLinkAboutContract 61786-PM1CSC No. 61786-PMI
PROJECT MANUAL
FOR
THE CONSTRUCTION OF
WATER, SEWER, PAVING AND DRAINAGE IMPROVEMENTS
TO SERVE
ACN Fossil Creek
IPRC Record No. 22-0140
City Project No. 104255
FID No. 30114-0200431-104255-EO7685
File No. W-2848
X File No. 27433
Mattie Parker David Cooke
Mayor City Manager
Christopher P. Harder, P.E.
Director, Water Department
Lauren Prieur, P.E.
Director, Transportation and Public Works Department
3AF...
.T.......S-
Prepared for
The City of Fort Worth
August 2024
Westwood
500 W. 7tn Street, Suite 1300
Fort Worth, TX 76102
817-953-2777
TBPE: 12207
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
8/15/2024
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 1 of 5
SECTION 00 00 10
TABLE OF CONTENTS
DEVELOPER AWARDED PROJECTS
Division 00 - General Conditions
Last Revised
1001113
inyiia4ion ,,, Bidders
03/20/2020
nno�3
lastF,,etiors t Bidde :s
03/20/2020
00 41 00
Bid Fefm
04/02/2014
00 42 43
Proposal Form Unit Price
05/22/2019
0043 13
Bid Bond
04/02/2014
nno n�=
Bidde :s Pf:eq, alifiecaiea's
04/02/2014
0045 12
Prequalification Statement
09/01/2015
0045 13
Bidde . Pfegtta1 f;,,a4ien kWiaz.,ian
03/09/2020
00 45 26
Contractor Compliance with Workers' Compensation Law
04/02/2014
0045 40
r finer- ty Business Enterprise Goa
08/21/2018
00 52 43
Agreement
06/16/2016
00 61 25
Certificate of Insurance
07/01/2011
00 62 13
Performance Bond
01/31/2012
00 62 14
Payment Bond
01/31/2012
00 62 19
Maintenance Bond
01/31/2012
00 7200
Geneful Conditions
11/15/2017
007300
c,,,.,.io,,.,enta y C rdifi np
07/01/2011
0073 10
Standard City Conditions of the Construction Contract for Developer
01/10/2013
Awarded Projects
Division 01- General Requirements
Last Revised
01 1100
Summary of Work
12/20/2012
012500
Substitution Procedures
08/30/2013
01 31 19
Preconstruction Meeting
08/30/2013
013120
Pr-egeet Meet* -
07/01/2011
01 3233
Preconstruction Video
08/30/2013
01 33 00
Submittals
08/30/2013
01 35 13
Special Project Procedures
08/30/2013
01 45 23
Testing and Inspection Services
03/20/2020
01 5000
Temporary Facilities and Controls
07/01/2011
01 5526
Street Use Permit and Modifications to Traffic Control
07/01/2011
0157 13
Storm Water Pollution Prevention Plan
07/01/2011
01 60 00
Product Requirements
03/20/2020
01 66 00
Product Storage and Handling Requirements
04/07/2014
01 70 00
Mobilization and Remobilization
04/07/2014
01 71 23
Construction Staking
04/07/2014
01 74 23
Cleaning
04/07/2014
01 77 19
Closeout Requirements
04/07/2014
01 78 23
Operation and Maintenance Data
04/07/2014
01 78 39
Project Record Documents
04/07/2014
CITY OF FORT WORTH ACNFossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised March 20, 2020
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 2 of 5
Technical Specifications listed below are included for this Project by reference and can be
viewed/downloaded from the City's website at:
httD:Hfortworthtexas.aov/tvw/contractors/
or
httvs:HaviDs.fortworthtexas.Lyov/Proi ectResources/
Division 02 - Existing Conditions
Last Revised
0241 13
Selective Site Demolition
12/20/2012
02 4414
r 44it- , n ^,.,ey l i n >,an r,,.,e
12/20/2012
0241 15
Paving Removal
02/02/2016
Division 03
- Concrete
03 30 00
Cast -In -Place Concrete
12/20/2012
03 34 13
Controlled Low Strength Material (CLSM)
12/20/2012
0334 16
Concrete Base Material for Trench Repair
12/20/2012
03 80 00
Modifications to Existing Concrete Structures
12/20/2012
Division 26 - Electrical
26 05 00 C e we v Results f ,.1~'1eetf eal 11/22/2013
q6 05 10 Demolition f Qeetfieal Systems 12/20/2012
q6 05 33 Raee. ays and Boxes f Qeetfieal Systems 12/20/2012
'tip Uncle .^ .^„r,a Duets a -a Raee ays f L 1 ^jt Taal figs 07/01/2011
q6 05 50 E31A1Aurizati ns Multi Duet Gen „ t. 02/26/2016
Division 31- Earthwork
31 1000
Site Clearing
12/20/2012
3123 16
Unclassified Excavation
01/28/2013
31�3
BE)FFE)
01/28/2013
3'� �4 00
Em. i-ad1ma-PAs
01/28/2013
31 25 00
Erosion and Sediment Control
12/20/2012
12/20/2012
12/20/2012
Division 32 - Exterior Improvements
27�
D^...,.,, n^rt Asphalt Pa-y ng n^.. a
12/20/2012
3201 18
Tempef ary Aooralt f\-4-irk
12/20/2012
320129
Concrete Paving Repair
12/20/2012
'27�3
Flexible Base C,,ufses
12/20/2012
'27�9
Lime e Tr-epAed Base C,,,,fs
12/20/2012
32 1133
Gamoxt Traa4ed Base C
12/20/2012
32 1137
Liquid „a T-r-ea ^'rail E'kA li er
08/21/2015
'27�o
n s. hah n,,N4*9
12/20/2012
Z7�3
n s..ha ft Paving Gr-aev Seal ffts
12/20/2012
32 13 13
Concrete Paving
12/20/2012
32 1320
Concrete Sidewalks, Driveways and Barrier Free Ramps
06/05/2018
32 1373
Concrete Paving Joint Sealants
12/20/2012
3'��4 16
Bfial un,t -%: Mg
12/20/2012
32 16 13
Concrete Curb and Gutters and Valley Gutters
10/05/2016
CITY OF FORT WORTH ACNFossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised March 20, 2020
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 3 of 5
Z7�3
Payefnet41, af-kifigs
11/22/2013
27�5
!-'',, �)oz Pai.:�,:rg
11/04/2013
3231 3
Cinr. Fcriies and Gates
12/20/2012
3'�6
W -e Fenees and Gates
12/20/2012
37�9
Woo 1 ^f^^s .,r,l Gates
12/20/2012
17�3
Cast i Dlaee C f^.^te n:rn,.-�ing Wails
06/05/2018
3291 19
Topsoil Placement and Finishing of Parkways
12/20/2012
32 92 13
Hydro -Mulching, Seeding, and Sodding
12/20/2012
3293 43
Trees 3 f1.-.trubz
12/20/2012
Division 33 - Utilities
33 01 30
Sewer and Manhole Testing
12/20/2012
33 01 31
Closed Circuit Television (CCTV) Inspection
03/03/2016
33 03 10
%—pao3 DuW' /`g 9FExisting Sewer- Systems
12/20/2012
33 04 100
T ipA >?,,fidi .,..,...,a Qeetfieal is la4ie
12/20/2012
ZZ�i
CeFFesio C ffel Test Sta4ief s
12/20/2012
33 04 12
raagnesitff node Gathedie Pfete tie Systeffl
12/20/2012
33�
T^,,.,refar , Water- Sef-, ^
07/01/2011
33 04 40
Cleaning and Acceptance Testing of Water Mains
02/06/2013
33 04 50
Cleaning of Sewer Mains
12/20/2012
3305 10
Utility Trench Excavation, Embedment, and Backfill
12/12/2016
33 05 42
Wa4ef Line Lower -in
12/20/2012
3305 13
Frame, Cover and Grade Rings — Cast Iron
01/22/2016
33 n�0
L'.-.,me, C,yef:. *,l r a o Ringz Composite
01/22/2016
33 05 14
Adjusting Manholes, Inlets, Valve Boxes, and Other Structures to
12/20/2012
Grade
3305 16
Concrete Water Vaults
12/20/2012
33 05 17
C fef:ete C llafs
12/20/2012
33 05 20
12/20/2012
330521
TuNrewl l.inar- Pla4e
12/20/2012
330522
Steel Casing -Pipe
12/20/2012
330523
Pkand Turewling
12/20/2012
33 05 24
Installation of Carrier Pipe in Casing or Tunnel Liner Plate
06/19/2013
330526 26
U44 t., MadEef:s/T e tees
12/20/2012
33 05 30
Location of Existing Utilities
12/20/2012
33 1105
Bolts, Nuts, and Gaskets
12/20/2012
33 11 10
Ductile Iron Pipe
12/20/2012
33 11 11
Ductile Iron Fittings
12/20/2012
33 11 12
Polyvinyl Chloride (PVC) Pressure Pipe
11/16/2018
?i3 11 13
Eexefet3 Proocuro Dino, liar AALFapped, Steel Cylinder- Type
12/20/2012
?i3 11 11
Died &ool Pir,"z d Fittings
12/20/2012
Z'2�o
Wa4ef: Sefviees 1 ineh to 2 ifie
02/14/2017
33 1211
Large Water Meters
12/20/2012
33 1220
Resilient Seated Gate Valve
12/20/2012
33 1221
AWWk P_ubsbor. Feated n„tto.fl., Valves
12/20/2012
33 1225
Connection to Existing Water Mains
02/06/2013
3� 1230
Co i.-md f Air- Valve Assemblies for- Potable Tx7.,t^. System
12/20/2012
33 1240
Fire Hydrants
01/03/2014
33 1250
Water gamj1� f'teatiafis
12/20/2012
CITY OF FORT WORTH
ACNFossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS
CPN 104255
Revised March 20, 2020
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 4 of 5
44-v 06/ 19/2013
1-1
Cur-ed i f Place Pipe (CIPP)
12/20/2012
33 3113
RrbeFg1wo P_orf ,-ee Piro for- Gr-a ,;t., I;G.I1tar s
12/20/2012
33 31 15
High Deal k, Polyethylene (14DPE) Piro f r Sanitary Sewef
12/20/2012
33 31 20
Polyvinyl Chloride (PVC) Gravity Sanitary Sewer Pipe
06/19/2013
Polyvinyl C1 lef:ide ClosedPr !` file -a-y ty C`an t.
Sewer-
12/20/2012
(PVC) y
Pipe
34 _;I 2
Sa-aitafy SePar F)i* L;&,i&g
12/20/2012
33 3123
S a;tafy Sewef Pipe L'alar-..e e
12/20/2012
33 31 50
Sanitary Sewer Service Connections and Service Line
04/26/2013
33 31 70
Combi.-Waa Air- Valve f3F f'wn-t&113" Sewef: Fef:ee Mains
12/20/2012
33 39 10
Cast -in -Place Concrete Manholes
12/20/2012
33 39 20
Precast Concrete Manholes
12/20/2012
333930
FibcrglxF lees
12/20/2012
33 3940
Waste. awe . n eeess C1..,mbef: (W n C)
12/20/2012
33 39 60
Epoxy Liners for Sanitary Sewer Structures
12/20/2012
3341 10
Reinforced Concrete Storm Sewer Pipe/Culverts
07/01/2011
✓3 11 11
High Deal k, Polyethylene (14DP r) Pipe f r Stzww. D�6i
12/20/2012
11 12
Reinfer-eed P lyetl.le o (E RPE) Pira
11/13/2015
33 4600
Subdr-ainage
12/20/2012
33-46 01
warm Diuirr
07/01/2011
33-46 02
Tr-arzoh Dimionj
07/01/2011
33 49 10
Cast -in -Place Manholes and Junction Boxes
12/20/2012
33 49 20
Curb and Drop Inlets
12/20/2012
33 49 40
St0r:� Drd-usage uo.,,l.:,.,lls and Wing.:,.,lls
07/01/2011
Division 34
- Transportation
34 41 10
T,.affi . Sign lss
10/12/2015
34 ^�nv11
At4aehme11A C—entrellerC—abinet
12/18/2015
34 ^�02
Att-aehmeat B C—'entfallz- ffoz
02/2012
34� n-i 0.03
Attaehmeat G Seft'V afe Speeiea4ien
01/2012
?/I 11 11
Tempefary "r"^ffi^ Signals
11/22/2013
3n�3
Removing T-r-af eS;..nals
12/20/2012
3 ^�15
Reetangulx Ram d L`laJ�,g Beaeon
11/22/2013
34 4 16
gedoot6aA I-I;bfid-Sigx-al
11/22/2013
34 4120
Read-w n1urAryatia Assemblies Mies
12/20/2012
34 ^� �; SOT
Afta6al L T\D naadw
06/15/2015
3n n�o2
>~ -eeway LED P.,.,dw ., Dwn�&ail9s
06/15/2015
3n n�03
Resider i l LED Roadway Dan. irswi--s
06/15/2015
34 0
Alum iMum fi gns
11 / 12/2013
Z n�
Single e r iede Fiber- Optie Cable
02/26/2016
3471 13
Traffic Control
11/22/2013
CITY OF FORT WORTH ACNFossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS CPN 104255
Revised March 20, 2020
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Appendix
Page 5 of 5
FG4,91
Availulity ,.P
GG 4.02
Fi.-./arr e . a a Physie i r n a; iefi
Fib-406
Ihmrl etis Envifefffaen4al Condition , 4 Site
GG 6.07
W
GG-6-M
f\ar iitvam- r T
1
1`T�ac�atian
TPW Standard Product List 2024-05-16
Water Standard Product List 2023-12-29
END OF SECTION
CITY OF FORT WORTH ACNFossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised March 20, 2020
DocuSign Envelope ID: 24D98E4F-344E-4674-9CAC-8AFD25C096EF
00 42 43
DAP - BID PROPOSAL
Page 1 of 5
SECTION 00 42 43
Developer Awarded Projects - PROPOSAL FORM
UNIT PRICE BID Bidder's Application
Project Item Information Bidder's Proposal
Bidlist Item
Description
Specification
Unit of
Bid
Unit Price
Bid Value
No.
Section No.
Measure
Quantity
UNIT I: WATER)MPROVEMENTS
1
3311.0141 6" Water Pipe
33 11 12
LF
31
$135.00
$4,185.00
2
3311.0441 12" Water Pipe
33 11 12
LF
416
$250.00
$104,000.00
3
3311.0451 12" DIP Water w/ CLSM
330510
LF
52
$300.00
$15,600.00
4
3305.1004 24" Steel Casing by Open Cut
33 05 22
LF
31
$350.00
$10,850.00
5
3311.0001 Dictile Iron Water Fittings w/ Restraint
33 11 11
TON
1
$6,250.00
$6,250.00
6
3305.0109 Trench Safety
3305 10
LF
515
$1.00
$515.00
7
3312.2802 4" Water Meter and Vault
3305 16
EA
1
$35,000.00
$35,000.00
8
3312.0001 Fire Hydrant
33 1240
EA
1
$5,000.00
$5,000.00
9
3312.2203 2" Water Service
33 12 10
EA
1
$3,500.00
$3,500.00
10
3312.3002 6" Gate Valve
33 1220
EA
2
$2,000.00
$4,000.00
11
3312.3005 12" Gate Valve
33 1220
EA
1
$4,000.00
$4,000.00
12
3312.0117 Connect to Existing 4"-12" Water Main
33 1225
EA
1
$5,000.00
$5,000.00
13
9999.0001 Automatic Flushing System
EA
1
$10,000.00
$10,000.00
14
0241.1118 12" Pressure Plug
0241 14
EA
1
$1,000.00
$1,000.00
15
3305.0202 Imported Embedment/Backfill, CSS
3305 10
CY
5.5
$215.00
$1,182.50
16
3291.0100 Topsoil
3291 19
CY
19
$100.00
$1,900.00
17
3292.0400 Hydromulch Seeding
32 92 14
SY
111
$5.00
$555.00
TOTA _ UNIT I: WATER IMPROVEMENTS $212,537.50
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS
Tom Version May 22, 2019 00 42 43_Bid Proposal_DAP
DocuSign Envelope ID: 24D98E4F-344E-4674-9CAC-8AFD25C096EF
00 42 43
DAP - BID PROPOSAL
Page 2 of 5
SECTION 00 42 43
Developer Awarded Projects - PROPOSAL FORM
UNIT PRICE BID
Bidder's Application
Project Item Information
Bidder's Proposal
Bidlist Item
Description
Specification
Unit of
Bid
Unit Price
Bid Value
No.
Section No.
Measure
Quantity
UNIT II: SANITARY
SEWER IMPROV
,MENTS
1
3301.0002 Post -CCTV Inspection
3301 31
LF
458
$2.00
$916.00
2
3305.0109 Trench Safety
3305 10
LF
458
$1.00
$458.00
3
3331.4108 6" Sewer Pipe
3331 20
LF
18
$125.00
$2,250.00
4
3331.4115 8" Sewer Pipe (SDR-26)
3331 20
LF
8
$108.00
$864.00
5
3305.3002 8" Sewer Pipe (DR14 C900 Green Pipe)
3331 20
LF
388
$150.00
$58,200.00
6
3331.4119 8" DIP Sewer Pipe
33 11 10
LF
44
$505.00
$22,220.00
7
3305.1004 20" Casing by Open Cut
33 05 22
LF
44
$325.00
$14,300.00
8
3331.4116 8" Sewer Pipe, CSS Backfill
3305 10
LF
18
$215.00
$3,870.00
9
3301.0101 Manhole Vacuum Testing
3301 30
EA
4
$200.00
$800.00
10
3339.0001 Epoxy Manhole Liner
33 39 60
VF
24
$500.00
$12,000.00
11
3339.1001 4' Manhole
33 39 20
EA
4
$6,500.00
$26,000.00
12
3339.1003 4' Extra Depth Manhole
33 39 20
VF
6
$500.00
$3,000.00
13
3291.0100 Topsoil
3291 19
CY
20
$100.00
$2,000.00
14
3292.0400 Hydromulch Seeding
3292 14
SY
119
$5.00
$595.00
15
3305.0113 Trench Water Stops
EA
2
$1,000.00
$2,000.00
16
Tree Protection
LS
1
$5,000.00
$5,000.00
TOTAL UNIT II: SANITARY SEWER IMPROVEMENTS $154,473.00
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS
Tom Version May 22, 2019 00 42 43_Bid Proposal_DAP
DocuSign Envelope ID: 24D98E4F-344E-4674-9CAC-8AFD25C096EF
00 42 43
DAP - BID PROPOSAL
Page 3 of 5
SECTION 00 42 43
Developer Awarded Projects - PROPOSAL FORM
UNIT PRICE BID
Bidder's Application
Project Item Information
Bidder's Proposal
Bidlist Item
Description
Specification
Unit of
Bid
Unit Price
Bid Value
No.
Section No.
I Measure
Quantity
UNIT III: DRAINAGE IMPROVEMENTS
1
0241.3018 Remove 33" Storm Line
0241 14
LF
15
$20.00
$300.00
2
0241.4101 Remove 20' recessed Inlet
0241 14
EA
1
$1,500.00
$1,500.00
3
3201.0616 Conc. Pvmt Repair Arterial
3201 29
SY
212
$225.00
$47,700.00
4
3305.0109 Trench Safety
3305 10
LF
109
$1.00
$109.00
5
3341.0205 24" RCP, Class III
3341 10
LF
93
$145.00
$13,485.00
6
3349.6003 20' Recessed Curb Inlet
33 49 20
EA
1
$15,000.00
$15,000.00
7
3349.0003 6' Storm Junction Box
3349 10
EA
1
$10,000.00
$10,000.00
8
9999.0001 Connect 18" SD to Back of Existing Inlet
LS
1
$1,600.00
$1,600.00
TOTAL UN T III: DRAINAGE IMPROVEMENTS $89,694.00
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS
Tom Version May 22, 2019 00 42 43_Bid Proposal_DAP
DocuSign Envelope ID: 24D98E4F-344E-4674-9CAC-8AFD25C096EF
00 42 43
DAP - BID PROPOSAL
Page 4 of 5
SECTION 00 42 43
Developer Awarded Projects - PROPOSAL FORM
UNIT PRICE BID
Bidder's Application
Project Item Information
Bidder's Proposal
Bidlist Item
Description
Specification
Unit of
Bid
Unit Price
Bid Value
No.
Section No.
I Measure
Quantity
UNIT IV: PAVING IMPROVEMENTS
1 0241.0100 Remove Sidewalk
0241 15
SF
427
$6.00 $2,562.00
2 0241.1300 Remove Conc Curb & Gutter
0241 15
LF
127
$10.00 $1,270.00
3 3213.0402 7" Concrete Driveway
32 1320
SF
817
$5.76 $4,705.92
4 3471.0001 Traffic Control
3471 13
MO
2
$5,000.00 $10,000.00
TOTAL JNIT IV: PAVING IMPROVEMENTS
$18,537.92
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS
Tom Version May 22, 2019
00 42 43_Bid Proposal_DAP
DocuSign Envelope ID: 24D98E4F-344E-4674-9CAC-8AFD25C096EF
UNIT PRICE BID
SECTION 00 42 43
Developer Awarded Projects - PROPOSAL FORM
Project Item Information
00 42 43
DAP - BID PROPOSAL
Page 5 of 5
Bidder's Application
Bidder's Proposal
Bidlist Item Specification Unit of Bid
Description Unit Price
No. Section No. Measure Quantity
Bid Summary
UNIT I: WATER IMPROVEMENTS
UNIT II: SANITARY SEWER IMPROVEMENTS
UNIT III: DRAINAGE IMPROVEMENTS
UNIT IV: PAVING IMPROVEMENTS
Total Construction Bid
This Bid is submitted by the entity named below:
BIDDER:
Bob Moore Construction
3611 William D. Tate Ave.
Grapevine, TX 76051
Contractor agrees to complete WORK for FINAL ACCEPTANCE within
CONTRACT commences to run as provided in the General Conditions.
BY: Mark Duvall
V1
TITLE: Executive V ice"CO3ident
DATE:6/2/2024 1 16:03:57 CDT
END OF SECTION
Bid Value
$212,537.50
$154,473.00
$89,694.00
$18,537.92
$475,242.42
60 working days after the date when the
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS
Form Version May 22, 2019 00 42 43_Bid Proposal DAP
0045 11 -1
BIDDERS PREQUALIFICATIONS
Page 1 of 3
SECTION 00 45 11
BIDDERS PREQUALIFICATIONS
1. Summary. All contractors are required to be prequalified by the City prior to submitting
bids. To be eligible to bid the contractor must submit Section 00 45 12, Prequalification
Statement for the work type(s) listed with their Bid. Any contractor or subcontractor who is
not prequalified for the work type(s) listed must submit Section 00 45 13, Bidder
Prequalification Application in accordance with the requirements below.
The prequalification process will establish a bid limit based on a technical evaluation and
financial analysis of the contractor. The information must be submitted seven (7) days prior
to the date of the opening of bids. For example, a contractor wishing to submit bids on
projects to be opened on the 7th of April must file the information by the 31 st day of March
in order to bid on these projects. In order to expedite and facilitate the approval of a Bidder's
Prequalification Application, the following must accompany the submission.
a. A complete set of audited or reviewed financial statements.
(1) Classified Balance Sheet
(2) Income Statement
(3) Statement of Cash Flows
(4) Statement of Retained Earnings
(5) Notes to the Financial Statements, if any
b. A certified copy of the firm's organizational documents (Corporate Charter, Articles
of Incorporation, Articles of Organization, Certificate of Formation, LLC
Regulations, Certificate of Limited Partnership Agreement).
c. A completed Bidder Prequalification Application.
(1) The firm's Texas Taxpayer Identification Number as issued by the Texas
Comptroller of Public Accounts. To obtain a Texas Taxpayer Identification
number visit the Texas Comptroller of Public Accounts online at the
following web address www.window.state.tx.us/taxDermit/ and fill out the
application to apply for your Texas tax ID.
(2) The firm's e-mail address and fax number.
(3) The firm's DUNS number as issued by Dun & Bradstreet. This number
is used by the City for required reporting on Federal Aid projects. The DUNS
number may be obtained at www.dnb.com.
d. Resumes reflecting the construction experience of the principles of the firm for firms
submitting their initial prequalification. These resumes should include the size and
scope of the work performed.
c. Other information as requested by the City.
2. Prequalification Requirements
a. Financial Statements. Financial statement submission must be provided in
accordance with the following:
(1) The City requires that the original Financial Statement or a certified copy
be submitted for consideration.
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS CPN 104255
Revised April 2, 2014
0045 11 -2
BIDDERS PREQUALIFICATIONS
Page 2 of 3
(2)
To be satisfactory, the financial statements must be audited or reviewed
by an independent, certified public accounting firm registered and in
good standing in any state. Current Texas statues also require that
accounting firms performing audits or reviews on business entities within
the State of Texas be properly licensed or registered with the Texas State
Board of Public Accountancy.
(3)
The accounting firm should state in the audit report or review whether
the contractor is an individual, corporation, or limited liability company.
(4)
Financial Statements must be presented in U.S. dollars at the current rate
of exchange of the Balance Sheet date.
(5)
The City will not recognize any certified public accountant as
independent who is not, in fact, independent.
(6)
The accountant's opinion on the financial statements of the contracting
company should state that the audit or review has been conducted in
accordance with auditing standards generally accepted in the United
States of America. This must be stated in the accounting firm's opinion.
It should: (1) express an unqualified opinion, or (2) express a qualified
opinion on the statements taken as a whole.
(7)
The City reserves the right to require a new statement at any time.
(8)
The financial statement must be prepared as of the last day of any month,
not more than one year old and must be on file with the City 16 months
thereafter, in accordance with Paragraph 1.
(9)
The City will determine a contractor's bidding capacity for the purposes
of awarding contracts. Bidding capacity is determined by multiplying the
positive net working capital (working capital = current assets — current
liabilities) by a factor of 10. Only those statements reflecting a positive
net working capital position will be considered satisfactory for
prequalification purposes.
(10)
In the case that a bidding date falls within the time a new financial
statement is being prepared, the previous statement shall be updated with
proper verification.
b. Bidder Prequalification Application. A Bidder Prequalifcation Application must be
submitted along with audited or reviewed financial statements by firms wishing to be
eligible to bid on all classes of construction and maintenance projects. Incomplete
Applications will be rejected.
(1)
In those schedules where there is nothing to report, the notation of
"None" or "N/A" should be inserted.
(2) A minimum of five (5) references of related work must be provided.
(3) Submission of an equipment schedule which indicates equipment under
the control of the Contractor and which is related to the type of work for
which the Contactor is seeking prequalification. The schedule must
include the manufacturer, model and general common description of
each piece of equipment. Abbreviations or means of describing
equipment other than provided above will not be accepted.
3. Eligibility to Bid
a. The City shall be the sole judge as to a contractor's prequalification.
b. The City may reject, suspend, or modify any prequalification for failure by the
contractor to demonstrate acceptable financial ability or performance.
c. The City will issue a letter as to the status of the prequalification approval.
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS CPN 104255
Revised April 2, 2014
0045 11 -3
BIDDERS PREQUALIFICATIONS
Page 3 of 3
d. If a contractor has a valid prequalification letter, the contractor will be eligible to bid
the prequalified work types until the expiration date stated in the letter.
END OF SECTION
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS CPN 104255
Revised April 2, 2014
DocuSign Envelope ID: A70D2EC5-6AD3-4C99-BBA4-B4BA68D2BC40
0045 12
DAP PREQUALIFICATION STATEMENT
Page 1 of 1
SECTION 00 45 12
DAP — PREQUALIFICATION STATEMENT
Each Bidder is required to complete the information below by identifying the prequalified contractors
and/or subcontractors whom they intend to utilize for the major work type(s) listed. In the "Major Work
Tvpe" box provide the complete major work tvpe and actual description as provided by the Water
Department for water and sewer and TPW for paving.
Major Work Type
Water Distribution,
Development, 12-inch diameter
And smaller
CCTV, 8-inch and smaller
Sewer Collection System,
Development, 8-inch and smaller
Contractor/Subcontractor Company Name Prequalification
Expiration Date
Wild Stone Construction 4/30/2025
Wild Stone Construction 4/30/2025
Wild Stone Construction 4/30/2025
The undersigned hereby certifies that the contractors and/or subcontractors described in the table above
are currently prequalified for the work types listed.
BIDDER:
Bob Moore Construction
3611 William D. Tate Ave.
Grapevine, TX 76051
BY: Mark Duvall
FAtfhl iC VWIAW
SNUJ'Uc 0" ""'
(Signature
TITLE: Executive Vice President
DATE:5/21/2024 1 16:06:08 CDT
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION PREQUALIFICATION STATEMENT— DEVELOPER AWARDED PROJECTS$204be268f5e7$F674742D49F24A02BC174C12C72B10AF.docx
Form Version September 1, 2015
004526-1
CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSATION LAW
Page i of 1
1 SECTION 00 45 26
2 CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSATION
3 LAW
4 Pursuant to Texas Labor Code Section 406.096(a), as amended, Contractor certifies
5 that it provides worker's compensation insurance coverage for all of its employees
6 employed on City Project No. 104255. Contractor further certifies that, pursuant to
7 Texas Labor Code, Section 406.096(b), as amended, it will provide to City its
8 subcontractor's certificates of compliance with worker's compensation coverage.
9
10 CONTRACTOR:
11
12
13 By: Mark Duvall
14 Title: Executive Vice President
15 Bob Moore Construction
16 3611 William D. Tate Ave.
17 Grapevine, TX 76051
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
THE STATE OF TEXAS
COUNTY OF TARRANT
V
2
BEFORE ME, the undersigned authority, on this day personally appeared
V w V,�X` known to me to be the person whose
name is subscribed to the foregoing instrument, and acknowledged to me that he/she
executed the same as the act and deed of
5. cs t^, 0,-aw C oN s , w CTT — d 14 N c-. for the purposes and consideration
therein expressed and in the capacity therein stated.
GT ` ! � �L UNDER MY HAND AND SEAL py OFFICE this % day of
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised April 2, 2014
4K-
Notary Public in an f r the State of Texas
! 01�YpuBGC DEBRAKAY MOORE
�Notary Public, State of Texas
h My Comm. Exp.11108/2025
q�oF��P Notary ID 574100-3
ACNFossil CS-eek
CPN 104255
DocuSign Envelope ID: 3EllCC57-lC29-45C6-8A5F-ABOE429B3EF1
005243-1
Developer Awarded Project Agreement
Page 1 of 6
1 SECTION oo 52 43
2 AGREEMENT
3 This agreement, AUTHORIZED ON 5/17/2024 14: 3IS4MOE BY AND
4 BETWEEN THE DEVELOPER, STAR DRAGON PROPERTIES,
LLC TO DO
5 BUSINESS IN TEXAS ("DEVELOPER") , AND BOB MOORE CONSTRUCTION.
6 AUTHORIZED TO DO BUSINESS IN TEXAS, ACTING BY AND THROUGH ITS
7 DULY AUTHORIZED REPRESENTATIVE, ("CONTRACTOR").DEVELOPER
8 AND CONTRACTOR, IN CONSIDERATION OF THE MUTUAL COVENANTS
9 HEREINAFTER SET FORTH, AGREE AS FOLLOWS:
10 Article 1. WORK
11 Contractor shall complete all Work as specified or indicated in the Contract
12 Documents for the Project identified herein.
13 Article 2. PROJECT
14 The project for which the Work under the Contract Documents may be the whole
15 or only a part is generally described as follows:
16 ACNFossil Creek
17 CPN1o,525S
18 Article 3. CONTRACT TIME
19 3.1 TIME IS OF THE ESSENCE.
20 All time limits for Milestones, if any, and Final Acceptance as stated in the
21 Contract Documents are of the essence to this Contract.
22 3.2 FINAL ACCEPTANCE.
CITY OF FORT WORTH ACNFossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPNio4255
Revised June 16, 2o16
DocuSign Envelope ID: 3EllCC57-lC29-45C6-8A5F-ABOE429B3EF1
005243-2
Developer Awarded Project Agreement
Page 2 of 6
23 The Work will be complete for Final Acceptance within 60 working days after the
24 date when the Contract Time commences to run as provided in Paragraph 12.04 of the
25 Standard City Conditions of the Construction Contract for Developer Awarded
26 Projects.
27 3.3 LIQUIDATED DAMAGES
28 Contractor recognizes that time is of the essence of this Agreement and that
29 Developer will suffer financial loss if the Work is not completed within the times
30 specified in Paragraph 3.2 above, plus any extension thereof allowed in accordance
31 with Article 10 of the Standard City Conditions of the Construction Contract for
32 Developer Awarded Projects. The Contractor also recognizes the delays, expense and
33 difficulties involved in proving in a legal proceeding the actual loss suffered by the
34 Developer if the Work is not completed on time. Accordingly, instead of requiring any
35 such proof , Contractor agrees that as liquidated damages for delay (but not as a
36 penalty), Contractor shall pay Developer One Hundred Dollars ($100.00) for each day
37 that expires after the time specified in Paragraph 3.2 for Final Acceptance until the
38 City issues the Final Letter of Acceptance.
39 ARTICLE 4. Contract Price
40 DEVELOPER AGREES TO PAY CONTRACTOR FOR PERFORMANCE OF THE WORK IN
41 ACCORDANCE WITH THE CONTRACT DOCUMENTS AN AMOUNT IN CURRENT FUNDS OF
42 Four hundred twenty-eight thousand, three hundred eighty-three DOLLARS ($ 475,242.42
43 ARTICLE 5. Contract documents
44 5.1 Contents:
45 A. The Contract Documents which comprise the entire agreement between
46 Developer and Contractor concerning the Work consist of the following:
47 1. This Agreement.
48 2. Attachments to this Agreement:
49 A. BID FORM (AS PROVIDED BY DEVELOPER)
50 1) PROPOSAL FORM (DAP VERSION)
51 2) PREQUALIFICATION STATEMENT
52 3) STATE AND FEDERAL DOCUMENTS (PROJECT SPECIFIC)
53 B. INSURANCE ACORD FORM(S)
54 C. PAYMENT BOND (DAP VERSION)
55 D. PERFORMANCE BOND (DAP VERSION)
56 E. MAINTENANCE BOND (DAP VERSION)
57 F. POWER OF ATTORNEY FOR THE BONDS
58 G. WORKER'S COMPENSATION AFFIDAVIT
59 H. MBE AND/OR SBE COMMITMENT FORM (IF REQUIRED)
CITY OF FORT WORTH ACNFossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN104255
Revised June 16, 2o16
DocuSign Envelope ID: 3EllCC57-lC29-45C6-8A5F-ABOE429B3EF1
005243-3
6o
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
Developer Awarded Project Agreement
Page 3 of 6
3. Standard City General Conditions of the Construction Contract for
Developer Awarded Projects.
4. Supplementary Conditions.
5. Specifications specifically made a part of the Contract Documents by
attachment or, if not attached, as incorporated by reference and
described in the Table of Contents of the Project's Contract
Documents.
6. Drawings.
7. Addenda.
8. Documentation submitted by Contractor prior to Notice of Award.
9. The following which may be delivered or issued after the Effective
Date of the Agreement and, if issued, become an incorporated part of
the Contract Documents:
A. NOTICE TO PROCEED.
B. FIELD ORDERS.
C. CHANGE ORDERS.
D. LETTER OF FINAL ACCEPTANCE.
CITY OF FORT WORTH ACNFossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPNio4255
Revised June 16, 2o16
DocuSign Envelope ID: 3EllCC57-lC29-45C6-8A5F-ABOE429B3EF1
005243-4
Developer Awarded Project Agreement
Page 4 of 6
ARTICLE 6. INDEMNIFICATION
CONTRACTOR COVENANTS AND AGREES TO INDEMNIFY, HOLD HARMLESS AND
DEFEND, AT ITS OWN EXPENSE, THE CITY, ITS OFFICERS, SERVANTS AND EMPLOYEES,
FROM AND AGAINST ANY AND ALL CLAIMS ARISING OUT OF, OR ALLEGED TO ARISE OUT
OF, THE WORK AND SERVICES TO BE PERFORMED BY THE CONTRACTOR, ITS OFFICERS,
AGENTS, EMPLOYEES, SUBCONTRACTORS, LICENSES OR INVITEES UNDER THIS
CONTRACT. THIS INDEMNIFICATION PROVISION IS SPECIFICALLY INTENDED TO OPERATE
AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR PROVEN THAT ALL OR SOME OF THE
DAMAGES BEING SOUGHT WERE CAUSED, IN WHOLE OR IN PART, BY ANY ACT,
OMISSION OR NEGLIGENCE OF THE CITY. THIS INDEMNITY PROVISION IS INTENDED TO
INCLUDE, WITHOUT LIMITATION, INDEMNITY FOR COSTS, EXPENSES AND LEGAL FEES
INCURRED BY THE CITY IN DEFENDING AGAINST SUCH CLAIMS AND CAUSES OF
ACTIONS.
CITY OF FORT WORTH ACNFossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN104255
Revised June 16, 2o16
DocuSign Envelope ID: 3EllCC57-lC29-45C6-8A5F-ABOE429B3EF1
005243-5
Developer Awarded Project Agreement
Page 5 of 6
93 6.2 CONTRACTOR COVENANTS AND AGREES TO INDEMNIFY AND HOLD HARMLESS, AT
94 ITS OWN EXPENSE, THE CITY, ITS OFFICERS, SERVANTS AND EMPLOYEES, FROM
95 AND AGAINST ANY AND ALL LOSS, DAMAGE OR DESTRUCTION OF PROPERTY OF
96 THE CITY, ARISING OUT OF, OR ALLEGED TO ARISE OUT OF, THE WORK AND
97 SERVICES TO BE PERFORMED BY THE CONTRACTOR, ITS OFFICERS, AGENTS,
98 EMPLOYEES, SUBCONTRACTORS, LICENSEES OR INVITEES UNDER THIS CONTRACT.
99 THIS INDEMNIFICATION PROVISION IS SPECIFICALLY INTENDED TO OPERATE AND
100 BE EFFECTIVE EVEN IF IT IS ALLEGED OR PROVEN THAT ALL OR SOME OF THE
101 DAMAGES BEING SOUGHT WERE CAUSED, IN WHOLE OR IN PART, BY ANY ACT,
102 OMISSION OR NEGLIGENCE OF THE CITY.
103
104 ARTICLE 7. MISCELLANEOUS
105 7.1 TERMS.
1o6 Terms used in this Agreement are defined in Article 1 of the Standard City Conditions
107 of the Construction Contract for Developer Awarded Projects.
1o8 7.2 ASSIGNMENT OF CONTRACT.
log This Agreement, including all of the Contract Documents may not be assigned by the
110 Contractor without the advanced express written consent of the Developer.
lit 7.3 SUCCESSORS AND ASSIGNS.
112 Developer and Contractor each binds itself, its partners, successors, assigns and legal
113 representatives to the other party hereto, in respect to all covenants, agreements and
114 obligations contained in the Contract Documents.
115 7.4 SEVERABILITY.
116 Any provision or part of the Contract Documents held to be unconstitutional, void or
117 unenforceable by a court of competent jurisdiction shall be deemed stricken, and all
118 remaining provisions shall continue to be valid and binding upon DEVELOPER and
1i9 CONTRACTOR.
120 7.5 GOVERNING LAW AND VENUE.
121 This Agreement, including all of the Contract Documents is performable in the State of
122 Texas. Venue shall be Tarrant County, Texas, or the United States District Court for the
123 Northern District of Texas, Fort Worth Division.
124
125 7.6 AUTHORITY TO SIGN.
126 Contractor shall attach evidence of authority to sign Agreement, if other than duly
127 authorized signatory of the Contractor.
128
129 IN WITNESS WHEREOF, Developer and Contractor have executed this
13o Agreement in multiple counterparts.
131
CITY OF FORT WORTH ACNFossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN104255
Revised June 16, 2o16
DocuSign Envelope ID: 3EllCC57-lC29-45C6-8A5F-ABOE429B3EF1
132
133
134
135
005243-6
Developer Awarded Project Agreement
Page 6 of 6
This Agreement is effective as of the last date signed by the Parties ("Effective
Date").
Contractor:
Bob Moore Construction
DocuSigned by:
By:AkA VmxA
ll ✓✓✓✓n��rc-i✓...
(Signature)
Mark Duvall
(Printed Name)
Title: Executive Vice President
Company Name: Bob Moore
Construction
Address:
3611 William D. Tate Ave.
City/State/Zip:
Grapevine, Tx 76051
Date 5/15/2024 1 14:38:49 CDT
Developer:
Star Dragon Properties, LLC
�DocuSigned by:
By..
(9Ignature)
He Reg Zhou
(Printed Name)
Title: Partner
Company name: Star Dragon
Properties, LLC
Address:
1163 Fairway Dr.
City/State/Zip:
Industry, CA 91789
Date 5/15/2024 1 11:45:54 CDT
CITY OF FORT WORTH ACNFossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPNio4255
Revised June 16, 2o16
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
SECTION 00 62 13
PERFORMANCE BOND
THE STATE OF TEXAS 9
COUNTY OFTARRANT 5
006213-1
PERFORMANCE BOND
Page 1 of 4
Bond No.107603699
KNOW ALL BY THESE PRESENTS:
That we, Bob Moore Construction. Inc., known as "Principal" herein and
Travelers Casualty and Surety Company of America a corporate surety(sureties, if more than
one) duly authorized to do business in the State of Texas, known as "Surety" herein (whether
one or more), are held and firmly bound unto the Developer, Land Dragon Properties
Holding, Inc., authorized to do business in Texas ("Developer") and the City of Fort Worth, a
Texas municipal corporation ("City"), in the penal sum of, four hundred seventv five
thousand two hundred forty two dollars and forty two cents ($475,242.42), lawful money of
the United States, to be paid in Fort Worth, Tarrant County, Texas for the payment of which
sum well and truly to be made jointly unto the Developer and the City as dual obligees, we
bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and
severally, firmly by these presents.
19 WHEREAS, Developer and City have entered into an Agreement for the construction
20 of community facilities in the City of Fort Worth by and through a Community Facilities
21 Agreement, CFA Number 23-0032; and
22 WHEREAS, the Principal has entered into a certain written contract with the Developer
23 awarded the 17th day of May, 2024, which Contract is hereby referred to and made a part
24 hereof for all purposes as if fully set forth herein, to furnish all materials, equipment labor
25 and other accessories defined by law, in the prosecution of the Work, including any Change
26 Orders, as provided for in said Contract designated as ACN Fossil Creek CPN 104255.
27 NOW, THEREFORE, the condition of this obligation is such that if the said Principal
28 shall faithfully perform it obligations under the Contract and shall in all respects duly and
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CITY CONDITIONS— DEVELOPER AWARDED PROJECTS CPN 104255
Revised January 31, 2012
006213-2
PERFORMANCE BOND
Page 2 of 4
1 faithfully perform the Work, including Change Orders, under the Contract, according to the
2 plans, specifications, and contract documents therein referred to, and as well during any
3 period of extension of the Contract that may be granted on the part of the Developer and/or
4 City, then this obligation shall be and become null and void, otherwise to remain in full force
5 and effect.
6 PROVIDED FURTHER, that if any legal action be filed on this Bond, venue shall lie in
7 Tarrant County, Texas or the United States District Court for the Northern District of Texas,
8 Fort Worth Division.
9 This bond is made and executed in compliance with the provisions of Chapter 2253
10 of the Texas Government Code, as amended, and all liabilities on this bond shall be
11 determined in accordance with the provisions of said statue.
12 IN WITNESS WHEREOF, the Principal and the Surety have SIGNED and SEALED this
13 instrument by duly authorized agents and officers on this the 15th day of May
14 2024 .
15 PRINCIPAL:
16 Bob Moore Construction, Inc.
17
18
19 BY:
Mark Duvall, Executive Vice President
20 Signature
21 ATI-ST:
22
23 Debra Moore
M]
25
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CITY CONDITIONS— DEVELOPER AWARDED PROJECTS CPN 104255
Revised January 31, 2012
1 (Principal) Secretary
2 Name and Title
3
4 Address: 3611 William D. Tate Avenue
5 Grapevine, TX 76051
6
7
8 Witness as to Principal
9 SURETY:
10 Travelers Casualty and Surety Company of America
11
12,,
13 BY:
14 - Signature
16 Jessica Turner, Attorney -in -Fact
17 Name and Title
18
19 Address: One Tower Square
20 Hartford, CT 06183
21
22
23 Witness as to Surety
24 11TA/Vl7W rl Mn'Y
Caitlin Kelley(/
CITY OF FORT WORTH
STANDARD CITY CONDITIONS— DEVELOPER AWARDED PROJECTS
Revised January 31, 2012
006213-3
PERFORMANCE BOND
Page 3 of 4
Telephone Number: (860) 277-0111
ACN Fossil Creek
CPN 104255
006213-4
PERFORMANCE BOND
Page 4 of 4
1
K
3
4 *Note: If signed by an officer of the Surety Company, there must be on file a certified
5 extract from the by-laws showing that this person has authority to sign such
6 obligation. If Surety's physical address is different from its mailing address, both
7 must be provided.
0
9 The date of the bond shall not be prior to the date the Contract is awarded.
10
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CITY CONDITIONS— DEVELOPER AWARDED PROJECTS CPN 104255
Revised January 31, 2012
Travelers Casualty and Surety Company of America
AA► Travelers Casualty and Surety Company
TRAVELERS J St. Paul Fire and Marine Insurance Company
POWER OF ATTORNEY
KNOW ALL MEN BY THESE PRESENTS: That Travelers Casualty and Surety Company of America, Travelers Casualty and Surety Company, and St.
Paul Fire and Marine Insurance Company are corporations duly organized under the laws of the State of Connecticut (herein collectively called the
"Companies"), and that the Companies do hereby make, constitute and appoint Jessica Turner of FORT WORTH
Texas , their true and lawful Attorney -in -Fact to sign, execute, seal and acknowledge any and all bonds, recognizances,
conditional undertakings and other writings obligatory in the nature thereof on behalf of the Companies in their business of guaranteeing the
fidelity of persons, guaranteeing the performance of contracts and executing or guaranteeing bonds and undertakings required or permitted in any
actions or proceedings allowed by law.
IN WITNESS WHEREOF, the Companies have caused this instrument to be signed, and their corporate seals to be hereto affixed, this 17th day of January,
2019.
010"7;,)
YAA
cow OWWR
o
. %jW eR,
ar
State of Connecticut
City of Hartford ss.
i
By:
Robert L. Rane enior Vice President
On this the 17th day of January, 2019, before me personally appeared Robert L. Raney, who acknowledged himself to be the Senior Vice President
of Travelers Casualty and Surety Company of America, Travelers Casualty and Surety Company, and St. Paul Fire and Marine Insurance Company, and
that he, as such, being authorized so to do, executed the foregoing instrument for the purposes therein contained by signing on behalf of said
Companies by himself as a duly authorized officer.
IN WITNESS WHEREOF, I hereunto set my hand and official seal.
My Commission expires the 30th day of June, 2021
✓'AP Np^�4� AAn
NOTARY
MWO a P. Nowik, Notary Public
This Power of Attorney is granted under and by the authority of the following resolutions adopted by the Boards of Directors of Travelers Casualty and
Surety Company of America, Travelers Casualty and Surety Company, and St. Paul Fire and Marine Insurance Company, which resolutions are now in full
force and effect, reading as follows:
RESOLVED, that the Chairman, the President, any Vice Chairman, any Executive Vice President, any Senior Vice President, any Vice President, any
Second Vice President, the Treasurer, any Assistant Treasurer, the Corporate Secretary or any Assistant Secretary may appoint Attorneys -in -Fact and
Agents to act for and on behalf of the Company and may give such appointee such authority as his or her certificate of authority may prescribe to sign
with the Company's name and seal with the Company's seal bonds, recognizances, contracts of indemnity, and other writings obligatory in the nature of a
bond, recognizance, or conditional undertaking, and any of said officers or the Board of Directors at any time may remove any such appointee and revoke
the power given him or her; and it is
FURTHER RESOLVED, that the Chairman, the President, any Vice Chairman, any Executive Vice President, any Senior Vice President or any Vice
President may delegate all or any part of the foregoing authority to one or more officers or employees of this Company, provided that each such
delegation is in writing and a copy thereof is filed in the office of the Secretary; and it is
FURTHER RESOLVED, that any bond, recognizance, contract of indemnity, or writing obligatory in the nature of a bond, recognizance, or conditional
undertaking shall be valid and binding upon the Company when (a) signed by the President, any Vice Chairman, any Executive Vice President, any
Senior Vice President or any Vice President, any Second Vice President, the Treasurer, any Assistant Treasurer, the Corporate Secretary or any
Assistant Secretary and duly attested and sealed with the Company's seal by a Secretary or Assistant Secretary; or (b) duly executed (under seal, if
required) by one or more Attorneys -in -Fact and Agents pursuant to the power prescribed in his or her certificate or their certificates of authority or by one
or more Company officers pursuant to a written delegation of authority; and it is
FURTHER RESOLVED, that the signature of each of the following officers: President, any Executive Vice President, any Senior Vice President, any Vice
President, any Assistant Vice President, any Secretary, any Assistant Secretary, and the seal of the Company may be affixed by facsimile to any Power of
Attorney or to any certificate relating thereto appointing Resident Vice Presidents, Resident Assistant Secretaries or Attomeys-in-Fact for purposes only of
executing and attesting bonds and undertakings and other writings obligatory in the nature thereof, and any such Power of Attorney or certificate bearing
such facsimile signature or facsimile seal shall be valid and binding upon the Company and any such power so executed and certified by such facsimile
signature and facsimile seal shall be valid and binding on the Company in the future with respect to any bond or understanding to which it is attached.
I, Kevin E. Hughes, the undersigned, Assistant Secretary of Travelers Casualty and Surety Company of America, Travelers Casualty and Surety
Company, and St. Paul Fire and Marine Insurance Company, do hereby certify that the above and foregoing is a true and correct copy of the Power of
Attorney executed by said Companies, which remains in full force and effect.
Dated'this 15th day of May , 2024
�f
Kevin E. Hughes, Ass�cretary
To verify the authenticity of this Power of Attorney, please calf us at 1-800-411-3880.
X?a.se refer to the above -named Attorney-fn-Fact and the details of the bond to which this Power of Attorney is attached.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
SECTION 00 6214
PAYMENT BOND
THE STATE OF TEXAS §
§
COUNTY OF TARRANT §
006214-1
PAYMENT BOND
Page 1 of 3
Bond No.107603699
KNOW ALL BY THESE PRESENTS:
That we, Bob Moore Construction. Inc., known as "Principal" herein, and
Travelers Casualty and Surety Company of America . a corporate surety ( Or
sureties if more than one), duly authorized to do business in the State of Texas, known as
"Surety" herein (whether one or more), are held and firmly bound unto the Developer, Land
Dragon Properties Holding, Inc., authorized to do business in Texas "(Developer"), and the
City of Fort Worth, a Texas municipal corporation ("City"), in the penal sum of four hundred
seventv five thousand two hundred fortv two dollars and forty two cents ($475,242.42),
Lawful money of the United States, to be paid in Fort Worth, Tarrant County, Texas, for the
payment of which sum well and truly be made jointly unto the Developer and the City as
dual obligees, we bind ourselves, our heirs, executors, administrators, successors and
assigns, jointly and severally, firmly by these presents:
19 WHEREAS, Developer and City have entered into an Agreement for the construction
20 of community facilities in the City of Fort Worth, by and through a Community Facilities
21 Agreement, CFA Number 23-0032; and
22 WHEREAS, Principal has entered into a certain written Contract with Developer,
23 awarded the 17th day of May, 2024, which Contract is hereby referred to and made a part
24 hereof for all purposes as if fully set forth herein, to furnish all materials, equipment, labor
25 and other accessories as defined by law, in the prosecution of the Work as provided for in
26 said Contract and designated as ACN Fossil Creek CPN 104255.
27 NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that if Principal
28 shall pay all monies owing to any (and all) payment bond beneficiary (as defined in Chapter
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CITY CONDITIONS— DEVELOPER AWARDED PROJECTS CPN 104255
Revised January31, 2012
006214-2
PAYMENTBOND
Page 2 of 3
1 2253 of the Texas Government Code, as amended) in the prosecution of the Work under the
2 Contract, then this obligation shall be and become null and void; otherwise to remain in full
3 force and effect.
4 This bond is made and executed in compliance with the provisions of Chapter 2253
5 of the Texas Government Code, as amended, and all liabilities on this bond shall be
6 determined in accordance with the provisions of said statute.
7 IN WITNESS WHEREOF, the Principal and Surety have each SIGNED and SEALED
8 this instrument by duly authorized agents and officers on this the 15th day of
g May 20 24
10
PRINCIPAL:
Bob Moore Construction, Inc.
ATTEST: BY.
17�v
Signature
A&A- 1-1k onw-�
Debra Moore
(Principal) Secretary
Stephanie Chambers
Witness as to Principal
Mark Duvall, Executive Vice President
Name and Title
Address: 3611 William D. Tate Avenue
Grapevine, TX 76051
SURETY:
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CITY CONDITIONS - DEVELOPER AWARDED PROJECTS CPN 104255
Revised January 31, 2012
ATTEST:
Lindsay Senior
(Surety) Secretary
Caitlin Kelley
Witness as to Surety
1
006214-3
PAYMENT BOND
Page 3 of 3
Travelers Casualty and Surety Company of America
BY:
Signature
Jessica Turner, Attorney -in -Fact
Name and Title
Address: One Tower Square
Hartford, CT 06183
Telephone Number: (860) 277-0111
2 Note: If signed by an officer of the Surety, there must be on file a certified extract from the
3 bylaws showing that this person has authority to sign such obligation. If Surety's physical
4 address is different from its mailing address, both must be provided.
5
6 The date of the bond shall not be prior to the date the Contract is awarded.
7 END OF SECTION
LV
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CITY CONDITIONS— DEVELOPER AWARDED PROJECTS CPN 104255
Revised January 31, 2012
Travelers Casualty and Surety Company of America
A4W Travelers Casualty and Surety Company
TRAVELERS J St. Paul Fire and Marine Insurance Company
POWER OF ATTORNEY
KNOW ALL MEN BY THESE PRESENTS: That Travelers Casualty and Surety Company of America, Travelers Casualty and Surety Company, and St.
Paul Fire and Marine Insurance Company are corporations duly organized under the laws of the State of Connecticut (herein collectively called the
"Companies"), and that the Companies do hereby make, constitute and appoint Jessica Turner of FORT WORTH
Texas , their true and lawful Attorney -in -Fact to sign, execute, seal and acknowledge any and all bonds, recognizances,
conditional undertakings and other writings obligatory in the nature thereof on behalf of the Companies in their business of guaranteeing the
fidelity of persons, guaranteeing the performance of contracts and executing or guaranteeing bonds and undertakings required or permitted in any
actions or proceedings allowed by law.
IN WITNESS WHEREOF, the Companies have caused this instrument to be signed, and their corporate seals to be hereto affixed, this 17th day of January,
2019.
10 S-4 ; eJ•�tr ANp@
or 49a
S Cow P mCONKq
AX • W C KK '
State of Connecticut
City of Hartford ss.
By: ,
Robert L. Rane , enior Vice President
On this the 17th day of January, 2019, before me personally appeared Robert L. Raney, who acknowledged himself to be the Senior Vice President
of Travelers Casualty and Surety Company of America, Travelers Casualty and Surety Company, and St. Paul Fire and Marine Insurance Company, and
that he, as such, being authorized so to do, executed the foregoing instrument for the purposes therein contained by signing on behalf of said
Companies by himself as a duly authorized officer.
IN WITNESS WHEREOF, I hereunto set my hand and official seal.
My Commission expires the 30th day of June, 2021
t � P Now,w,,
NOTARY
// ��
PUBLIC
Anna P. Nowik, Notary Public
This Power of Attorney is granted under and by the authority of the following resolutions adopted by the Boards of Directors of Travelers Casualty and
Surety Company of America, Travelers Casualty and Surety Company, and St. Paul Fire and Marine Insurance Company, which resolutions are now in full
force and effect, reading as follows:
RESOLVED, that the Chairman, the President, any Vice Chairman, any Executive Vice President, any Senior Vice President, any Vice President, any
Second Vice President, the Treasurer, any Assistant Treasurer, the Corporate Secretary or any Assistant Secretary may appoint Attorneys -in -Fact and
Agents to act for and on behalf of the Company and may give such appointee such authority as his or her certificate of authority may prescribe to sign
with the Company's name and seal with the Company's seal bonds, recognizances, contracts of indemnity, and other writings obligatory in the nature of a
bond, recognizance, or conditional undertaking, and any of said officers or the Board of Directors at any time may remove any such appointee and revoke
the power given him or her; and it is
FURTHER RESOLVED, that the Chairman, the President, any Vice Chairman, any Executive Vice President, any Senior Vice President or any Vice
President may delegate all or any part of the foregoing authority to one or more officers or employees of this Company, provided that each such
delegation is in writing and a copy thereof is filed in the office of the Secretary; and it is
FURTHER RESOLVED, that any bond, recognizance, contract of indemnity, or writing obligatory in the nature of a bond, recognizance, or conditional
undertaking shall be valid and binding upon the Company when (a) signed by the President, any Vice Chairman, any Executive Vice President, any
Senior Vice President or any Vice President, any Second Vice President, the Treasurer, any Assistant Treasurer, the Corporate Secretary or any
Assistant Secretary and duly attested and sealed with the Company's seal by a Secretary or Assistant Secretary; or (b) duly executed (under seal, if
required) by one or more Attorneys -in -Fact and Agents pursuant to the power prescribed in his or her certificate or their certificates of authority or by one
or more Company officers pursuant to a written delegation of authority; and it is
FURTHER RESOLVED, that the signature of each of the following officers: President, any Executive Vice President, any Senior Vice President, any Vice
President, any Assistant Vice President, any Secretary, any Assistant Secretary, and the seal of the Company may be affixed by facsimile to any Power of
Attorney or to any certificate relating thereto appointing Resident Vice Presidents, Resident Assistant Secretaries or Attorneys -in -Fact for purposes only of
executing and attesting bonds and undertakings and other writings obligatory in the nature thereof, and any such Power of Attorney or certificate bearing
such facsimile signature or facsimile seal shall be valid and binding upon the Company and any such power so executed and certified by such facsimile
signature and facsimile seal shall be valid and binding on the Company in the future with respect to any bond or understanding to which it is attached.
I, Kevin E. Hughes, the undersigned, Assistant Secretary of Travelers Casualty and Surety Company of America, Travelers Casualty and Surety
Company, and St. Paul Fire and Marine Insurance Company, do hereby certify that the above and foregoing is a true and correct copy of the Power of
Attorney executed by said Companies, which remains in full force and effect.
Dated this 15th day of May , 2024
y ��y-'yGyJp�SY ANp � -x
ft
.•ll,�% 4 4P S4 y
3f'9 C O < rae�aa�t VA
• s1 �+ IF
Kevin E. Hughes, Assi tant Secretary
To verify the authenticity of this Power of Attorney, please call us at 1-800-421-3880.
Please refer to the above -named Attorney -in -Fact and the details of the bond to which this Power of Attorney is attached.
006219-1
MAINTENANCE BOND
Page 1 of 5
Bond No.107603699
1
SECTION 00 62 19
2
MAINTENANCE BOND
3
4 THE STATE OF TEXAS
§
5
§ KNOW ALL BY THESE PRESENTS:
6 COUNTY OF TARRANT
§
7
8 That we Bob Moore Construction. Inc., known as "Principal" herein and
9 Travelers Casualty and Surety Company of America , a corporate surety (sureties, if more than
10 one) duly authorized to do business in the State of Texas, known as "Surety" herein (whether
11 one or more), are held and firmly bound unto the Developer, Land Dragon Properties
12 Holding, Inc., authorized to do business in Texas ("Developer") and the City of Fort Worth, a
13 Texas municipal corporation ("City"), in the sum of four hundred seventy five thousand two
14 hundred fortv two dollars and fortv two cents ($475,242.42), lawful money of the United
15 States, to be paid in Fort Worth, Tarrant County, Texas, for payment of which sum well and
16 truly be made jointly unto the Developer and the City as dual obligees and their successors,
17 we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and
18 severally, firmly by these presents.
19 WHEREAS, Developer and City have entered into an Agreement for the construction of
20 community facilities in the City of Fort Worth by and through a Community Facilities
21 Agreement, CFA Number 23-0032; and
22 WHEREAS, the Principal has entered into a certain written contract with the
23 Developer awarded the17th day of May, 2024, which Contract is hereby referred to and a
24 made part hereof for all purposes as if fully set forth herein, to furnish all materials,
25 equipment labor and other accessories as defined by law, in the prosecution of the Work,
26 including any Work resulting from a duly authorized Change Order (collectively herein, the
27 "Work") as provided for in said Contract and designated as ACN Fossil Creek CPN 104255;
28 and
29
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CITY CONDITIONS —DEVELOPER AWARDED PROJECTS CPN 104255
Revised January 31, 2012
006219-2
MAINTENANCE BOND
Page 2 of 5
1 WHEREAS, Principal binds itself to use such materials and to so construct the Work
2 in accordance with the plans, specifications and Contract Documents that the Work is and
3 will remain free from defects in materials or workmanship for and during the period of two
4 (2) years after the date of Final Acceptance of the Work by the City ("Maintenance Period");
5 and
A
7 WHEREAS, Principal binds itself to repair or reconstruct the Work in whole or in part
8 upon receiving notice from the Developer and/or City of the need thereof at any time within
9 the Maintenance Period.
10
11 NOW THEREFORE, the condition of this obligation is such that if Principal shall
12 remedy any defective Work, for which timely notice was provided by Developer or City, to a
13 completion satisfactory to the City, then this obligation shall become null and void;
14 otherwise to remain in full force and effect.
15
16 PROVIDED, HOWEVER, if Principal shall fail so to repair or reconstruct any timely
17 noticed defective Work, it is agreed that the Developer or City may cause any and all such
18 defective Work to be repaired and/or reconstructed with all associated costs thereof being
19 borne by the Principal and the Surety under this Maintenance Bond; and
20
21 PROVIDED FURTHER, that if any legal action be filed on this Bond, venue shall lie in
22 Tarrant County, Texas or the United States District Court for the Northern District of Texas,
23 Fort Worth Division; and
24
25 PROVIDED FURTHER, that this obligation shall be continuous in nature and
26 successive recoveries may be had hereon for successive breaches.
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised January 31, 2012
006219-3
MAINTENANCE BOND
Page 3 of 5
1 IN WITNESS WHEREOF, the Principal and the Surety have each SIGNED and SEALED this
2 instrument by duly authorized agents and officers on this the 15th day of May
3 2024,
4
5
6
7
8
9
10
11
12
13
14
15
16 ATTEST:
17
18
19 Debra Moore
20
21 (Principal) Secretary
22
23 1
24
Stephanie Chambers
25
26
27
28
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised January 31, 2012
PRINCIPAL:
Bob Moore Construction, Inc.
BY: )v L%-*
Signature
Mark Duvall, Executive Vice President
Name and Title
Address:
3611 William D. Tate Avenue
Grapevine, TX 76051
ACN Fossil Creek
CPN 104255
1
2 Witness as to Principal
3
n
5
6
7
8
9
10
11
12
13 -
14
15
16
17
18 ATTEST:
19
20 a. `
21 Lindsay Senior
22 (Surety) Secretary
23
24
25
26 �AA/VMAA
27 Witness as to Surety
28 Caitlin Kelley
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised January 31, 2012
006219-4
MAINTENANCE BOND
Page 4 of 5
SURETY:
Travelers Casualty and Surety Company of America
L:"
Signature
Jessica Turner, Attorney -in -Fact
Name and Title
Address:
One Tower Square
Hartford, CT 06183
Telephone
Number: (860) 277-0111
ACN Fossil Creek
CPN 104255
006219-5
MAINTENANCE BOND
Page 5 of 5
1
2 *Note: If signed by an officer of the Surety Company, there must be on file a certified
3 extract from the by-laws showing that this person has authority to sign such
4 obligation. If Surety's physical address is different from its mailing address, both
5 must be provided.
0
7 The date of the bond shall not be prior to the date the Contract is awarded.
0
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CITY CONDITIONS— DEVELOPER AWARDED PROJECTS CPN 104255
Revised January 31, 2012
Travelers Casualty and Surety Company of America
AA. Travelers Casualty and Surety Company
TRAVELERS J St. Paul Fire and Marine Insurance Company
POWER OF ATTORNEY
KNOW ALL MEN BY THESE PRESENTS: That Travelers Casualty and Surety Company of America, Travelers Casualty and Surety Company, and St.
Paul Fire and Marine Insurance Company are corporations duly organized under the laws of the State of Connecticut (herein collectively called the
"Companies"), and that the Companies do hereby make, constitute and appoint Jessica Turner of FORT WORTH
Texas , their true and lawful Attorney -in -Fact to sign, execute, seal and acknowledge any and all bonds, recognizances,
conditional undertakings and other writings obligatory in the nature thereof on behalf of the Companies in their business of guaranteeing the
fidelity of persons, guaranteeing the performance of contracts and executing or guaranteeing bonds and undertakings required or permitted in any
actions or proceedings allowed by law.
IN WITNESS WHEREOF, the Companies have caused this instrument to be signed, and their corporate seals to be hereto affixed, this 17th day of January,
2019.
w
�1YAE7p \Y ANpm
COtkf. 8 `m L O 'l
@ CONK
o VA
t • �,t �aa 13'
State of Connecticut
City of Hartford ss.
By:
Robert L. Rane enior Vice President
On this the 17th day of January, 2019, before me personally appeared Robert L. Raney, who acknowledged himself to be the Senior Vice President
of Travelers Casualty and Surety Company of America, Travelers Casualty and Surety Company, and St. Paul Fire and Marine Insurance Company, and
that he, as such, being authorized so to do, executed the foregoing instrument for the purposes therein contained by signing on behalf of said
Companies by himself as a duly authorized officer.
IN WITNESS WHEREOF, I hereunto set my hand and official seal.
My Commission expires the 30th day of June, 2021
= NOTARY *�
°UE`10
NwF0
Anna P. Nowik, Notary Public
This Power of Attorney is granted under and by the authority of the following resolutions adopted by the Boards of Directors of Travelers Casualty and
Surety Company of America, Travelers Casualty and Surety Company, and St. Paul Fire and Marine Insurance Company, which resolutions are now in full
force and effect, reading as follows:
RESOLVED, that the Chairman, the President, any Vice Chairman, any Executive Vice President, any Senior Vice President, any Vice President, any
Second Vice President, the Treasurer, any Assistant Treasurer, the Corporate Secretary or any Assistant Secretary may appoint Attorneys -in -Fact and
Agents to act for and on behalf of the Company and may give such appointee such authority as his or her certificate of authority may prescribe to sign
with the Company's name and seal with the Company's seal bonds, recognizances, contracts of indemnity, and other writings obligatory in the nature of a
bond, recognizance, or conditional undertaking, and any of said officers or the Board of Directors at any time may remove any such appointee and revoke
the power given him or her; and it is
FURTHER RESOLVED, that the Chairman, the President, any Vice Chairman, any Executive Vice President, any Senior Vice President or any Vice
President may delegate all or any part of the foregoing authority to one or more officers or employees of this Company, provided that each such
delegation is in writing and a copy thereof is filed in the office of the Secretary; and it is
FURTHER RESOLVED, that any bond, recognizance, contract of indemnity, or writing obligatory in the nature of a bond, recognizance, or conditional
undertaking shall be valid and binding upon the Company when (a) signed by the President, any Vice Chairman, any Executive Vice President, any
Senior Vice President or any Vice President, any Second Vice President, the Treasurer, any Assistant Treasurer, the Corporate Secretary or any
Assistant Secretary and duly attested and sealed with the Company's seal by a Secretary or Assistant Secretary; or (b) duly executed (under seal, if
required) by one or more Attorneys -in -Fact and Agents pursuant to the power prescribed in his or her certificate or their certificates of authority or by one
or more Company officers pursuant to a written delegation of authority; and it is
FURTHER RESOLVED, that the signature of each of the following officers: President, any Executive Vice President, any Senior Vice President, any Vice
President, any Assistant Vice President, any Secretary, any Assistant Secretary, and the seal of the Company may be affixed by facsimile to any Power of
Attorney or to any certificate relating thereto appointing Resident Vice Presidents, Resident Assistant Secretaries or Attorneys -in -Fact for purposes only of
executing and attesting bonds and undertakings and other writings obligatory in the nature thereof, and any such Power of Attorney or certificate bearing
such facsimile signature or facsimile seal shall be valid and binding upon the Company and any such power so executed and certified by such facsimile
signature and facsimile seal shall be valid and binding on the Company in the future with respect to any bond or understanding to which it is attached.
I, Kevin E. Hughes, the undersigned, Assistant Secretary of Travelers Casualty and Surety Company of America, Travelers Casualty and Surety
Company, and St. Paul Fire and Marine Insurance Company, do hereby certify that the above and foregoing is a true and correct copy of the Power of
Attorney executed by said Companies, which remains in full force and effect.
Dated this 15th day of May 2024
06 bJP�TY AryO
JL W
pp T1
RGU
� HMTFORD. t C40C�3K! JCL
A?W CONN. a #�L
FFF Kevin in EE. Hughes�As,,st�atSe retary
To verify the authenticity of this Power of Attorney, please call us at 1-800-421-3880.
Please refer to the above -named Attorney -in -Pact and the details of the bond to which this Power of Attorney is attached.
IMPORTANT NOTICE
To obtain information or make a complaint:
You may call Travelers Casualty and Surety Company of America and its affiliates'
toll -free telephone number for information or to make a complaint at:
1-800-328-2189
You may contact the Texas Department of Insurance to obtain information on
companies, coverages, rights or complaints at:
1-800-252-3439
You may write the Texas Department of Insurance:
P. O. Box 149104
Austin, TX 78714-9104
Fax: (512) 475-1771
Web: hfti)://www.tdi.state.tx.us
E-mail: ConsumerProtection(a)tdi.state.tx.us
PREMIUM OR CLAIM DISPUTES:
Should you have a dispute concerning your premium or about a claim you should
contact your Agent or Travelers first. If the dispute is not resolved, you may contact the
Texas Department of Insurance.
ATTACH THIS NOTICE TO YOUR BOND:
This notice is for information only and does not become a part or condition of the
attached document and is given to comply with Texas legal and regulatory requirements.
(PN-042-B) Ed.10.18.07
STANDARD CITY CONDITIONS
OF THE CONSTRUCTION CONTRACT
FOR DEVELOPER AWARDED PROJECTS
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
STANDARD CITY CONDITIONS OF THE
CONSTRUCTION CONTRACT
FOR DEVELOPER AWARDED PROJECTS
TABLE OF CONTENTS
Article 1 — Definitions and Terminology..........
1.01 Defined Terms ...............................
1.02 Terminology ..................................
Article 2 —
Preliminary Matters .......................
2.01
Before Starting Construction......
2.02
Preconstruction Conference........
2.03
Public Meeting ............................
Page
.............................................1
.............................................1
............................................. 5
....................................................... 6
....................................................... 6
....................................................... 6
....................................................... 6
Article 3 — Contract Documents and Amending............................................................................................... 6
3.01 Reference Standards..................................................................................................................... 6
3.02 Amending and Supplementing Contract Documents.................................................................. 6
Article 4 — Bonds and Insurance....................................................................................................................... 7
4.01 Licensed Sureties and Insurers..................................................................................................... 7
4.02 Performance, Payment, and Maintenance Bonds........................................................................ 7
4.03 Certificates of Insurance............................................................................................................... 7
4.04 Contractor's Insurance.................................................................................................................. 9
4.05 Acceptance of Bonds and Insurance; Option to Replace...........................................................12
Article 5 —
Contractor's Responsibilities........................................................................................................12
5.01
Supervision and Superintendent.................................................................................................12
5.02
Labor; Working Hours................................................................................................................13
5.03
Services, Materials, and Equipment...........................................................................................13
5.04
Project Schedule..........................................................................................................................14
5.05
Substitutes and "Or-Equals".......................................................................................................14
5.06
Pre -Qualification of Bidders (Prime Contractors and Subcontractors).....................................16
5.07
Concerning Subcontractors, Suppliers, and Others...................................................................16
5.08
Wage Rates..................................................................................................................................18
5.09
Patent Fees and Royalties...........................................................................................................19
5.10
Laws and Regulations.................................................................................................................19
5.11
Use of Site and Other Areas.......................................................................................................19
5.12
Record Documents......................................................................................................................20
5.13
Safety and Protection..................................................................................................................
21
5.14
Safety Representative.................................................................................................................21
5.15
Hazard Communication Programs.............................................................................................22
5.16
Submittals....................................................................................................................................22
5.17
Contractor's General Warranty and Guarantee..........................................................................23
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
5.18 Indemnification ............................................
5.19 Delegation of Professional Design Services
5.20 Right to Audit: .............................................
5.21 Nondiscrimination ........................................
Article 6 - Other Work at the Site.......
6.01 Related Work at Site .......
Article 7 - City's Responsibilities ............................................
7.01 Inspections, Tests, and Approvals .......................
7.02 Limitations on City's Responsibilities ................
7.03 Compliance with Safety Program ........................
Article 8 - City's Observation Status During Construction.......
8.01 City's Project Representative .................................
8.02 Authorized Variations in Work ..............................
8.03 Rejecting Defective Work ......................................
8.04 Determinations for Work Performed ......................
Article 9 - Changes in the Work ......................
9.01 Authorized Changes in the Work
9.02 Notification to Surety ...................
Article 10 - Change of Contract Price; Change of Contract Time
10.01 Change of Contract Price ...........................................
10.02 Change of Contract Time ...........................................
10.03 Delays.........................................................................
Article 11 - Tests and Inspections; Correction, Removal or Acceptance of Defective Work ............
11.01 Notice of Defects..............................................................................................................
11.02 Access to Work.................................................................................................................
11.03 Tests and Inspections........................................................................................................
11.04 Uncovering Work.............................................................................................................
11.05 City May Stop the Work...................................................................................................
11.06 Correction or Removal of Defective Work......................................................................
11.07 Correction Period..............................................................................................................
11.08 City May Correct Defective Work...................................................................................
Article 12 - Completion ...........................................
12.01 Contractor's Warranty of Title ............
12.02 Partial Utilization .................................
12.03 Final Inspection ....................................
12.04 Final Acceptance ..................................
Article 13 - Suspension of Work .....................................
13.01 City May Suspend Work .............................
Article 14 - Miscellaneous .........................................
14.01 Giving Notice .........................................
CITY OF FORT WORTH
STANDARD CITY CONDITIONS - DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
24
24
25
25
26
26
26
26
26
27
a
a
... 29
... 29
... 29
... 29
... 30
... 30
... 30
... 30
... 31
................................. 32
................................. 32
................................. 32
................................. 32
................................. 33
............................................................. 33
............................................................. 33
34
34
14.02 Computation of Times................................................................................................................ 34
14.03 Cumulative Remedies................................................................................................................. 34
14.04 Survival of Obligations...............................................................................................................35
14.05 Headings......................................................................................................................................35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10- 1
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 1 of 35
ARTICLE 1— DEFINITIONS AND TERMINOLOGY
1.01 Defined Terms
A. Wherever used in these General Conditions or in other Contract Documents, the terms listed
below have the meanings indicated which are applicable to both the singular and plural thereof,
and words denoting gender shall include the masculine, feminine and neuter. Said terms are
generally capitalized or written in italics, but not always. When used in a context consistent with
the definition of a listed -defined term, the term shall have a meaning as defined below whether
capitalized or italicized or otherwise. In addition to terms specifically defined, terms with initial
capital letters in the Contract Documents include references to identified articles and paragraphs,
and the titles of other documents or forms.
1. Agreement - The written instrument which is evidence of the agreement between Developer
and Contractor covering the Work
2. Asbestos —Any material that contains more than one percent asbestos and is friable or is
releasing asbestos fibers into the air above current action levels established by the United
States Occupational Safety and Health Administration.
3. Business Day — A business day is defined as a day that the City conducts normal business,
generally Monday through Friday, except for federal or state holidays observed by the City.
4. Buzzsaw — City's on-line, electronic document management and collaboration system.
5. Calendar Day — A day consisting of 24 hours measured from midnight to the next midnight.
6. City— The City of Fort Worth, Texas, a Texas home -rule municipal corporation, acting by,
its governing body through its City Manager, his designee, or agents authorized pursuant to
its duly authorized charter on his behalf.
7. Community Facilities Agreement (CFA) A Contract between the Developer and the City
for the Construction of one or more following public facilities within the City public right-of-
way or easement: Water, Sanitary Sewer, Street, Storm Drain, Street Light, and Street Signs.
A CFA may include private facilities within the right-of-way dedicated as private right-of-
way or easement on a recorded plat.
8. Contract —The entire and integrated written document incorporating the Contract
Documents between the Developer, Contractor, and/or City concerning the Work. The
Contract supersedes prior negotiations, representations, or agreements, whether written or
oral.
9. Contract Documents —Those items that make up the contract and which must include the
Agreement, and it's attachments such as standard construction specifications, standard City
Conditions, other general conditions of the Developer, including:
a. An Agreement
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10-2
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 2 of 35
b. Attachments to the Agreement
i. Bid Form
ii. Vendor Compliance with State Law Non -Resident Bidder
iii. Prequalification Statement
C. Current Prevailing Wage Rates Table (if required by City)
d. Insurance Accord Form
e. Payment Bond
f. Performance Bond
g. Maintenance Bond
h. Power of Attorney for Bonds
i. Workers Compensation Affidavit
j. MWBE Commitment Form( If required by City)
k. General Conditions
1. Supplementary Conditions
in. The Standard City Conditions
n. Specifications specifically made part of the Contract Documents by attachment, if
not attached, as incorporated by reference and described in the Table of Contents of
the Project's Contract Documents
o. Drawings
P. Documentation submitted by contractor prior to Notice of Award.
q. The following which may be delivered or issued after the effective date if the
Agreement and, if issued become an incorporated part of the Contract Documents
i. Notice to Proceed
ii. Field Orders
iii. Change Orders
iv. Letters of Final Acceptance
r. Approved Submittals, other Contractor submittals, and the reports and drawings of
subsurface and physical conditions are not Contract Documents.
10. Contractor —The individual or entity with whom Developer has entered into the Agreement.
11. Day or day —A day, unless otherwise defined, shall mean a Calendar Day.
12. Developer — An individual or entity that desires to make certain improvements within the
City of Fort Worth
13. Drawings —That part of the Contract Documents prepared or approved by Engineer which
graphically shows the scope, extent, and character of the Work to be performed by
Contractor. Submittals are not Drawings as so defined.
14. Engineer —The licensed professional engineer or engineering firm registered in the State of
Texas performing professional services for the Developer.
15. Final Acceptance — The written notice given by the City to the Developer and/or Contractor
that the Work specified in the Contract Documents has been completed to the satisfaction of
the City.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10- 3
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 3 of 35
16. Final Inspection — Inspection carried out by the City to verify that the Contractor has
completed the Work, and each and every part or appurtenance thereof, fully, entirely, and in
conformance with the Contract Documents.
17. General Requirements —A part of the Contract Documents between the Developer and a
Contractor.
18. Laws and Regulations Any and all applicable laws, rules, regulations, ordinances, codes,
and orders of any and all governmental bodies, agencies, authorities, and courts having
jurisdiction.
19. Liens —Charges, security interests, or encumbrances upon Project funds, real property, or
personal property.
20. Milestone —A principal event specified in the Contract Documents relating to an
intermediate Contract Time prior to Final Acceptance of the Work.
21. Non -Participating Change Order —A document, which is prepared for and reviewed by the
City, which is signed by Contractor, and Developer, and authorizes an addition, deletion, or
revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on
or after the Effective Date of the Agreement.
22. Participating Change Order —A document, which is prepared for and approved by the City,
which is signed by Contractor, Developer, and City and authorizes an addition, deletion, or
revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on
or after the Effective Date of the Agreement.
23. Plans — See definition of Drawings.
24. Project Schedule —A schedule, prepared and maintained by Contractor, in accordance with
the General Requirements, describing the sequence and duration of the activities comprising
the Contractor's plan to accomplish the Work within the Contract Time.
25. Project —The Work to be performed under the Contract Documents.
26. Project Representative —The authorized representative of the City who will be assigned to
the Site.
27. Public Meeting — An announced meeting conducted by the Developer to facilitate public
participation and to assist the public in gaining an informed view of the Project.
28. Regular Working Hours — Hours beginning at 7: 00 a.m. and ending at 6:00 p.m., Monday
thru Friday (excluding legal holidays).
29. Samples Physical examples of materials, equipment, or workmanship that are
representative of some portion of the Work and which establish the standards by which such
portion of the Work will be judged.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10- 4
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 4 of 35
30. Schedule of Submittals —A schedule, prepared and maintained by Contractor, of required
submittals and the time requirements to support scheduled performance of related
construction activities.
31. Site —Lands or areas indicated in the Contract Documents as being furnished by City or
Developer upon which the Work is to be performed, including rights -of -way, permits, and
easements for access thereto, and such other lands furnished by City or Developer which are
designated for the use of Contractor.
32. Specifications —That part of the Contract Documents consisting of written requirements for
materials, equipment, systems, standards and workmanship as applied to the Work, and
certain administrative requirements and procedural matters applicable thereto.
Specifications may be specifically made a part of the Contract Documents by attachment or,
if not attached, may be incorporated by reference as indicated in the Table of Contents
(Division 00 00 00) of each Project.
33. Standard City Conditions — That part of the Contract Documents setting forth requirements
of the City.
34. Subcontractor —An individual or entity having a direct contract with Contractor or with any
other Subcontractor for the performance of apart of the Work at the Site.
35. Submittals All drawings, diagrams, illustrations, schedules, and other data or information
which are specifically prepared or assembled by or for Contractor and submitted by
Contractor to illustrate some portion of the Work.
36. Superintendent — The representative of the Contractor who is available at all times and able
to receive instructions from the City and/or Developer and to act for the Contractor.
37. Supplementary Conditions —That part of the Contract Documents which amends or
supplements the General Conditions.
38. Supplier —A manufacturer, fabricator, supplier, distributor, materialman, or vendor having
a direct contract with Contractor or with any Subcontractor to furnish materials or
equipment to be incorporated in the Work by Contractor or Subcontractor.
39. Underground Facilities All underground pipelines, conduits, ducts, cables, wires,
manholes, vaults, tanks, tunnels, or other such facilities or attachments, and any
encasements containing such facilities, including but not limited to, those that convey
electricity, gases, steam, liquid petroleum products, telephone or other communications,
cable television, water, wastewater, storm water, other liquids or chemicals, or traffic or
other control systems.
40. Weekend Working Hours — Hours beginning at 9: 00 a. in. and ending at 5: 00 p.m., Saturday,
Sunday or legal holiday, as approved in advance by the City.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10- 5
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 5 of 35
41. Work —The entire construction or the various separately identifiable parts thereof required
to be provided under the Contract Documents. Work includes and is the result of performing
or providing all labor, services, and documentation necessary to produce such construction
including any Participating Change Order, Non -Participating Change Order, or Field
Order, and furnishing, installing, and incorporating all materials and equipment into such
construction, all as required by the Contract Documents.
42. Working Day — A working day is defined as a day, not including Saturdays, Sundays, or
legal holidays authorized by the City for contract purposes, in which weather or other
conditions not under the control of the Contractor will permit the performance of the
principal unit of work underway for a continuous period of not less than 7 hours between 7
a.m. and 6 p. m.
1.02 Terminology
A. The words and terms discussed in Paragraph 1.02.13 through D are not defined but, when used in
the Bidding Requirements or Contract Documents, have the indicated meaning.
B. Defective:
1. The word "defective," when modifying the word "Work," refers to Work that is
unsatisfactory, faulty, or deficient in that it:
a. does not conform to the Contract Documents; or
b. does not meet the requirements of any applicable inspection, reference standard, test, or
approval referred to in the Contract Documents; or
c. has been damaged prior to City's written acceptance.
C. Furnish, Install, Perform, Provide:
1. The word "Furnish" or the word "Install" or the word "Perform" or the word "Provide" or
the word "Supply," or any combination or similar directive or usage thereof, shall mean
furnishing and incorporating in the Work including all necessary labor, materials, equipment,
and everything necessary to perform the Work indicated, unless specifically limited in the
context used.
D. Unless stated otherwise in the Contract Documents, words or phrases that have a well-known
technical or construction industry or trade meaning are used in the Contract Documents in
accordance with such recognized meaning.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10- 6
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 6 of 35
ARTICLE 2 — PRELIMINARY MATTERS
2.01 Before Starting Construction
Baseline Schedules: Submit to City in accordance with the Contract Documents, and prior to starting
the Work. New schedules will be submitted to City when Participating Change Orders or Non -
Participating Change Orders occur.
2.02 Preconstruction Conference
Before any Work at the Site is started, the Contractor shall attend a Preconstruction Conference as
specified in the Contract Documents.
2.03 Public Meeting
Contractor may not mobilize any equipment, materials or resources to the Site prior to Contractor
attending the Public Meeting as scheduled by the City.
ARTICLE 3 — CONTRACT DOCUMENTS AND AMENDING
3.01 Reference Standards
A. Standards, Specifications, Codes, Laws, and Regulations
1. Reference to standards, specifications, manuals, or codes of any technical society,
organization, or association, or to Laws or Regulations, whether such reference be specific or
by implication, shall mean the standard, specification, manual, code, or Laws or Regulations
in effect at the time of opening of Bids (or on the Effective Date of the Agreement if there
were no Bids), except as may be otherwise specifically stated in the Contract Documents.
2. No provision or instruction shall be effective to assign to City, or any of its officers,
directors, members, partners, employees, agents, consultants, or subcontractors, any duty or
authority to supervise or direct the performance of the Work or any duty or authority to
undertake responsibility inconsistent with the provisions of the Contract Documents.
3.02 Amending and Supplementing Contract Documents
A. The Contract Documents may be amended to provide for additions, deletions, and revisions in
the Work or to modify the terms and conditions thereof by a Participating Change Order or a
Non -Participating Change Order.
B. The requirements of the Contract Documents may be supplemented, and minor variations and
deviations in the Work not involving a change in Contract Price or Contract Time, may be
authorized, by one or more of the following ways:
1. A Field Order;
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10- 7
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 7 of 35
1. City's or Engineer's review of a Submittal (subject to the provisions of Paragraph 5.16.C); or
2. City's written interpretation or clarification.
ARTICLE 4 — BONDS AND INSURANCE
4.01 Licensed Sureties and Insurers
All bonds and insurance required by the Contract Documents to be purchased and maintained by
Contractor shall be obtained from surety or insurance companies that are duly licensed or authorized
in the State of Texas to issue bonds or insurance policies for the limits and coverage so required.
Such surety and insurance companies shall also meet such additional requirements and qualifications
as may be provided Section 4.04.
4.02 Performance, Payment, and Maintenance Bonds
A. Contractor shall furnish performance and payment bonds in the name of Developer and City, in
accordance with Texas Government Code Chapter 2253 or successor statute, each in an amount
equal to the Contract Price as security for the faithful performance and payment of all of
Contractor's obligations under the Contract Documents.
B. Contractor shall furnish maintenance bonds in the name of Developer and City in an amount
equal to the Contract Price as security to protect the City against any defects in any portion of the
Work described in the Contract Documents. Maintenance bonds shall remain in effect for two
(2) years after the date of Final Acceptance by the City.
C. All bonds shall be in the form prescribed by the Contract Documents except as provided
otherwise by Laws or Regulations, and shall be executed by such sureties as are named in the list
of "Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and
as Acceptable Reinsuring Companies" as published in Circular 570 (amended) by the Financial
Management Service, Surety Bond Branch, U.S. Department of the Treasury. All bonds signed
by an agent or attorney -in -fact must be accompanied by a sealed and dated power of attorney
which shall show that it is effective on the date the agent or attorney -in -fact signed each bond.
D. If the surety on any bond furnished by Contractor is declared bankrupt or becomes insolvent or
its right to do business is terminated in the State of Texas or it ceases to meet the requirements of
Paragraph 4.02.C, Contractor shall promptly notify City and shall, within 30 days after the event
giving rise to such notification, provide another bond and surety, both of which shall comply
with the requirements of Paragraphs 4.01 and 4.02.C.
4.03 Certificates of Insurance
Contractor shall deliver to Developer and City, with copies to each additional insured and loss payee
identified in these Standard City Conditions certificates of insurance (and other evidence of
insurance requested by City or any other additional insured) which Contractor is required to
purchase and maintain.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10- 8
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 8 of 35
1. The certificate of insurance shall document the City, an as "Additional Insured" on all
liability policies.
2. The Contractor's general liability insurance shall include a, "per project" or "per location",
endorsement, which shall be identified in the certificate of insurance provided to the City.
3. The certificate shall be signed by an agent authorized to bind coverage on behalf of the
insured, be complete in its entirety, and show complete insurance carrier names as listed in
the current A.M. Best Property & Casualty Guide
4. The insurers for all policies must be licensed and/or approved to do business in the State of
Texas. Except for workers' compensation, all insurers must have a minimum rating of A-:
VII in the current A. M. Best Key Rating Guide or have reasonably equivalent financial
strength and solvency to the satisfaction of Risk Management. If the rating is below that
required, written approval of City is required.
5. All applicable policies shall include a Waiver of Subrogation (Rights of Recovery) in favor
of the City. In addition, the Contractor agrees to waive all rights of subrogation against the
Engineer (if applicable), and each additional insured identified in these Standard City
Conditions. Failure of the City to demand such certificates or other evidence of full
compliance with the insurance requirements or failure of the City to identify a deficiency
from evidence that is provided shall not be construed as a waiver of Contractor's obligation
to maintain such lines of insurance coverage.
6. If insurance policies are not written for specified coverage limits, an Umbrella or Excess
Liability insurance for any differences is required. Excess Liability shall follow form of the
primary coverage.
7. Unless otherwise stated, all required insurance shall be written on the "occurrence basis". If
coverage is underwritten on a claims -made basis, the retroactive date shall be coincident with
or prior to the date of the effective date of the agreement and the certificate of insurance shall
state that the coverage is claims -made and the retroactive date. The insurance coverage shall
be maintained for the duration of the Contract and for three (3) years following Final
Acceptance provided under the Contract Documents or for the warranty period, whichever is
longer. An annual certificate of insurance submitted to the City shall evidence such
insurance coverage.
8. Policies shall have no exclusions by endorsements, which, neither nullify or amend, the
required lines of coverage, nor decrease the limits of said coverage unless such endorsements
are approved in writing by the City. In the event a Contract has been bid or executed and the
exclusions are determined to be unacceptable or the City desires additional insurance
coverage, and the City desires the contractor/engineer to obtain such coverage, the contract
price shall be adjusted by the cost of the premium for such additional coverage plus 10%.
9. Any self -insured retention (SIR), in excess of $25,000.00, affecting required insurance
coverage shall be approved by the City in regards to asset value and stockholders' equity. In
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10-9
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 9 of 35
lieu of traditional insurance, alternative coverage maintained through insurance pools or risk
retention groups, must also be approved by City.
10. Any deductible in excess of $5,000.00, for any policy that does not provide coverage on a
first -dollar basis, must be acceptable to and approved by the City.
11. City, at its sole discretion, reserves the right to review the insurance requirements and to
make reasonable adjustments to insurance coverage's and their limits when deemed
necessary and prudent by the City based upon changes in statutory law, court decision or the
claims history of the industry as well as of the contracting party to the City. The City shall
be required to provide prior notice of 90 days, and the insurance adjustments shall be
incorporated into the Work by Change Order.
12. City shall be entitled, upon written request and without expense, to receive copies of policies
and endorsements thereto and may make any reasonable requests for deletion or revision or
modifications of particular policy terms, conditions, limitations, or exclusions necessary to
conform the policy and endorsements to the requirements of the Contract. Deletions,
revisions, or modifications shall not be required where policy provisions are established by
law or regulations binding upon either parry or the underwriter on any such policies.
13. City shall not be responsible for the direct payment of insurance premium costs for
Contractor's insurance.
4.04 Contractor's Insurance
A. Workers Compensation and Employers' Liability. Contractor shall purchase and maintain such
insurance coverage with limits consistent with statutory benefits outlined in the Texas Workers'
Compensation Act (Texas Labor Code, Ch. 406, as amended), and minimum limits for
Employers' Liability as is appropriate for the Work being performed and as will provide
protection from claims set forth below which may arise out of or result from Contractor's
performance of the Work and Contractor's other obligations under the Contract Documents,
whether it is to be performed by Contractor, any Subcontractor or Supplier, or by anyone directly
or indirectly employed by any of them to perform any of the Work, or by anyone for whose acts
any of them may be liable:
1. claims under workers' compensation, disability benefits, and other similar employee benefit
acts;
2. claims for damages because of bodily injury, occupational sickness or disease, or death of
Contractor's employees.
3. The limits of liability for the insurance shall provide the following coverages for not less
than the following amounts or greater where required by Laws and Regulations
a. Statutory limits
b. Employer's liability
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 10
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 10 of 35
1) $100,000 each accident/occurrence
2) $100,000 Disease - each employee
3) $500,000 Disease - policy limit
B. Commercial General Liability. Coverage shall include but not be limited to covering liability
(bodily injury or property damage) arising from: premises/operations, independent contractors,
products/completed operations, personal injury, and liability under an insured contract. Insurance
shall be provided on an occurrence basis, and as comprehensive as the current Insurance
Services Office (ISO) policy. This insurance shall apply as primary insurance with respect to
any other insurance or self-insurance programs afforded to the City. The Commercial General
Liability policy, shall have no exclusions by endorsements that would alter of nullify
premises/operations, products/completed operations, contractual, personal injury, or advertising
injury, which are normally contained with the policy, unless the City approves such exclusions
in writing.
1. For construction projects that present a substantial completed operation exposure, the City
may require the contractor to maintain completed operations coverage for a minimum of no
less than three (3) years following the completion of the project
2. Contractor's Liability Insurance under this Section which shall be on a per project basis
covering the Contractor with minimum limits of:
a. $1,000,000 each occurrence
b. $2,000,000 aggregate limit
3. The policy must have an endorsement (Amendment — Aggregate Limits of Insurance)
making the General Aggregate Limits apply separately to each job site.
4. The Commercial General Liability Insurance policies shall provide "X", "C", and "U"
coverage's. Verification of such coverage must be shown in the Remarks Article of the
Certificate of Insurance.
C. Automobile Liability. A commercial business auto policy shall provide coverage on "any auto",
defined as autos owned, hired and non -owned and provide indemnity for claims for damages
because bodily injury or death of any person and or property damage arising out of the work,
maintenance or use of any motor vehicle by the Contractor, any Subcontractor or Supplier, or by
anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone
for whose acts any of them may be liable.
1. Automobile Liability, Contractor's Liability Insurance under this Section, which shall be in
an amount not less than the following amounts:
a. Automobile Liability - a commercial business policy shall provide coverage on "Any
Auto", defined as autos owned, hired and non -owned.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 11
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 11 of 35
1) $1, 000, 000 each accident on a combined single limit basis. Split limits are
acceptable if limits are at least:
2) $250,000 Bodily Injury per person
3) $500,000 Bodily Injury per accident /
4) $100,000 Property Damage
D. Railroad Protective Liability. If any of the work or any warranty work is within the limits of
railroad right-of-way, the Contractor shall comply with the following requirements:
1. The Contractor's construction activities will require its employees, agents, subcontractors,
equipment, and material deliveries to cross railroad properties and tracks owned and
operated by: NONE
Write the name of the railroad company. (If none, then write none)
2. The Contractor shall conduct its operations on railroad properties in such a manner as not to
interfere with, hinder, or obstruct the railroad company in any manner whatsoever in the use
or operation of its/their trains or other property. Such operations on railroad properties may
require that Contractor to execute a "Right of Entry Agreement" with the particular railroad
company or companies involved, and to this end the Contractor should satisfy itself as to the
requirements of each railroad company and be prepared to execute the right -of -entry (if any)
required by a railroad company. The requirements specified herein likewise relate to the
Contractor's use of private and/or construction access roads crossing said railroad company's
properties.
3. The Contractual Liability coverage required by Paragraph 5.04D of the General Conditions
shall provide coverage for not less than the following amounts, issued by companies
satisfactory to the City and to the Railroad Company for a term that continues for so long as
the Contractor's operations and work cross, occupy, or touch railroad property:
a. General Aggregate: NONE
Enter limits provided by Railroad Company (If none, write none)
b. Each Occurrence:: NONE
Enter limits provided by Railroad Company (If none, write none)
4. With respect to the above outlined insurance requirements, the following shall govern:
a. Where a single railroad company is involved, the Contractor shall provide one insurance
policy in the name of the railroad company. However, if more than one grade separation
or at -grade crossing is affected by the Project at entirely separate locations on the line or
lines of the same railroad company, separate coverage may be required, each in the
amount stated above.
b. Where more than one railroad company is operating on the same right-of-way or where
several railroad companies are involved and operated on their own separate rights -of -
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 12
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 12 of 35
way, the Contractor may be required to provide separate insurance policies in the name
of each railroad company.
c. If, in addition to a grade separation or an at -grade crossing, other work or activity is
proposed on a railroad company's right-of-way at a location entirely separate from the
grade separation or at -grade crossing, insurance coverage for this work must be included
in the policy covering the grade separation.
d. If no grade separation is involved but other work is proposed on a railroad company's
right-of-way, all such other work may be covered in a single policy for that railroad, even
though the work may be at two or more separate locations.
5. No work or activities on a railroad company's property to be performed by the Contractor
shall be commenced until the Contractor has furnished the City with an original policy or
policies of the insurance for each railroad company named, as required above. All such
insurance must be approved by the City and each affected Railroad Company prior to the
Contractor's beginning work.
6. The insurance specified above must be carried until all Work to be performed on the railroad
right-of-way has been completed and the grade crossing, if any, is no longer used by the
Contractor. In addition, insurance must be carried during all maintenance and/or repair work
performed in the railroad right-of-way. Such insurance must name the railroad company as
the insured, together with any tenant or lessee of the railroad company operating over tracks
involved in the Project.
E. Notification of Policy Cancellation: Contractor shall immediately notify City upon cancellation
or other loss of insurance coverage. Contractor shall stop work until replacement insurance has
been procured. There shall be no time credit for days not worked pursuant to this section.
4.05 Acceptance of Bonds and Insurance; Option to Replace
If City has any objection to the coverage afforded by or other provisions of the bonds or insurance
required to be purchased and maintained by the Contractor in accordance with Article 5 on the basis
of non-conformance with the Contract Documents, the Developer and City shall so notify the
Contractor in writing within 10 Business Days after receipt of the certificates (or other evidence
requested). Contractor shall provide to the City such additional information in respect of insurance
provided as the Developer or City may reasonably request. If Contractor does not purchase or
maintain all of the bonds and insurance required by the Contract Documents, the Developer or City
shall notify the Contractor in writing of such failure prior to the start of the Work, or of such failure
to maintain prior to any change in the required coverage.
ARTICLE 5 — CONTRACTOR'S RESPONSIBILITIES
5.01 Supervision and Superintendent
A. Contractor shall supervise, inspect, and direct the Work competently and efficiently, devoting
such attention thereto and applying such skills and expertise as may be necessary to perform the
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 13
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 13 of 35
Work in accordance with the Contract Documents. Contractor shall be solely responsible for the
means, methods, techniques, sequences, and procedures of construction.
B. At all times during the progress of the Work, Contractor shall assign a competent, English-
speaking, Superintendent who shall not be replaced without written notice to City. The
Superintendent will be Contractor's representative at the Site and shall have authority to act on
behalf of Contractor. All communication given to or received from the Superintendent shall be
binding on Contractor.
C. Contractor shall notify the City 24 hours prior to moving areas during the sequence of
construction.
5.02 Labor; Working Hours
A. Contractor shall provide competent, suitably qualified personnel to perform construction as
required by the Contract Documents. Contractor shall at all times maintain good discipline and
order at the Site.
B. Except as otherwise required for the safety or protection of persons or the Work or property at
the Site or adjacent thereto, and except as otherwise stated in the Contract Documents, all Work
at the Site shall be performed during Regular Working Hours. Contractor will not permit the
performance of Work beyond Regular Working Hours or for Weekend Working Hours without
City's written consent (which will not be unreasonably withheld). Written request (by letter or
electronic communication) to perform Work:
1. for beyond Regular Working Hours request must be made by noon at least two (2) Business
Days prior
2. for Weekend Working Hours request must be made by noon of the preceding Thursday
3. for legal holidays request must be made by noon two Business Days prior to the legal
holiday.
5.03 Services, Materials, and Equipment
A. Unless otherwise specified in the Contract Documents, Contractor shall provide and assume full
responsibility for all services, materials, equipment, labor, transportation, construction
equipment and machinery, tools, appliances, fuel, power, light, heat, telephone, water, sanitary
facilities, temporary facilities, and all other facilities and incidentals necessary for the
performance, Contractor required testing, start-up, and completion of the Work.
B. All materials and equipment incorporated into the Work shall be as specified or, if not specified,
shall be of good quality and new, except as otherwise provided in the Contract Documents. All
special warranties and guarantees required by the Specifications shall expressly run to the benefit
of City. If required by City, Contractor shall furnish satisfactory evidence (including reports of
required tests) as to the source, kind, and quality of materials and equipment.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 14
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 14 of 35
C. All materials and equipment to be incorporated into the Work shall be stored, applied, installed,
connected, erected, protected, used, cleaned, and conditioned in accordance with instructions of
the applicable Supplier, except as otherwise may be provided in the Contract Documents.
5.04 Project Schedule
A. Contractor shall adhere to the Project Schedule established in accordance with Paragraph 2.01
and the General Requirements as it may be adjusted from time to time as provided below.
1. Contractor shall submit to City for acceptance (to the extent indicated in Paragraph 2.01 and
the General Requirements) proposed adjustments in the Project Schedule.
2. Proposed adjustments in the Project Schedule that will change the Contract Time shall be
submitted in accordance with the requirements of Article 9. Adjustments in Contract Time
for projects with City participation shall be made by participating change orders.
5.05 Substitutes and "Or -Equals "
A. Whenever an item of material or equipment is specified or described in the Contract Documents
by using the name of a proprietary item or the name of a particular Supplier, the specification or
description is intended to establish the type, function, appearance, and quality required. Unless
the specification or description contains or is followed by words reading that no like, equivalent,
or "or -equal" item or no substitution is permitted, other items of material or equipment of other
Suppliers may be submitted to City for review under the circumstances described below.
1. "Or -Equal" Items: If in City's sole discretion an item of material or equipment proposed by
Contractor is functionally equal to that named and sufficiently similar so that no change in
related Work will be required, it may be considered by City as an "or -equal" item, in which
case review and approval of the proposed item may, in City's sole discretion, be
accomplished without compliance with some or all of the requirements for approval of
proposed substitute items. For the purposes of this Paragraph 5.05.A.1, a proposed item of
material or equipment will be considered functionally equal to an item so named if:
a. City determines that:
1) it is at least equal in materials of construction, quality, durability, appearance,
strength, and design characteristics;
2) it will reliably perform at least equally well the function and achieve the results
imposed by the design concept of the completed Project as a functioning whole; and
3) it has a proven record of performance and availability of responsive service; and
b. Contractor certifies that, if approved and incorporated into the Work:
1) there will be no increase in cost to the City or increase in Contract Time; and
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 15
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 15 of 35
2) it will conform substantially to the detailed requirements of the item named in the
Contract Documents.
2. Substitute Items:
a. If in City's sole discretion an item of material or equipment proposed by Contractor does
not qualify as an "or -equal" item under Paragraph 5.05.A.1, it may be submitted as a
proposed substitute item.
b. Contractor shall submit sufficient information as provided below to allow City to
determine if the item of material or equipment proposed is essentially equivalent to that
named and an acceptable substitute therefor. Requests for review of proposed substitute
items of material or equipment will not be accepted by City from anyone other than
Contractor.
c. Contractor shall make written application to City for review of a proposed substitute item
of material or equipment that Contractor seeks to furnish or use. The application shall
comply with Section 0125 00 and:
1) shall certify that the proposed substitute item will:
i. perform adequately the functions and achieve the results called for by the general
design;
ii. be similar in substance to that specified;
iii. be suited to the same use as that specified; and
2) will state:
i. the extent, if any, to which the use of the proposed substitute item will prejudice
Contractor's achievement of final completion on time;
ii. whether use of the proposed substitute item in the Work will require a change in
any of the Contract Documents (or in the provisions of any other direct contract
with City for other work on the Project) to adapt the design to the proposed
substitute item;
iii. whether incorporation or use of the proposed substitute item in connection with
the Work is subject to payment of any license fee or royalty; and
3) will identify:
i. all variations of the proposed substitute item from that specified;
ii. available engineering, sales, maintenance, repair, and replacement services; and
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 16
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 16 of 35
4) shall contain an itemized estimate of all costs or credits that will result directly or
indirectly from use of such substitute item, including costs of redesign and Damage
Claims of other contractors affected by any resulting change.
B. Substitute Construction Methods or Procedures: If a specific means, method, technique,
sequence, or procedure of construction is expressly required by the Contract Documents,
Contractor may furnish or utilize a substitute means, method, technique, sequence, or procedure
of construction approved by City. Contractor shall submit sufficient information to allow City, in
City's sole discretion, to determine that the substitute proposed is equivalent to that expressly
called for by the Contract Documents. Contractor shall make written application to City for
review in the same manner as those provided in Paragraph 5.05.A.2.
C. City's Evaluation: City will be allowed a reasonable time within which to evaluate each
proposal or submittal made pursuant to Paragraphs 5.05.A and 5.05.13. City may require
Contractor to furnish additional data about the proposed substitute. City will be the sole judge of
acceptability. No "or -equal" or substitute will be ordered, installed or utilized until City's review
is complete, which will be evidenced by a Change Order in the case of a substitute and an
accepted Submittal for an "or -equal." City will advise Contractor in writing of its determination.
D. Special Guarantee: City may require Contractor to furnish at Contractor's expense a special
performance guarantee, warranty, or other surety with respect to any substitute. Contractor shall
indemnify and hold harmless City and anyone directly or indirectly employed by them from and
against any and all claims, damages, losses and expenses (including attorneys fees) arising out
of the use of substituted materials or equipment.
E. City's Cost Reimbursement: City will record City's costs in evaluating a substitute proposed or
submitted by Contractor pursuant to Paragraphs 5.05.A.2 and 5.05.B. Whether or not City
approves a substitute so proposed or submitted by Contractor, Contractor may be required to
reimburse City for evaluating each such proposed substitute. Contractor may also be required to
reimburse City for the charges for making changes in the Contract Documents.
F. Contractor's Expense: Contractor shall provide all data in support of any proposed substitute or
"or -equal" at Contractor's expense.
G. Substitute Reimbursement: Costs (savings or charges) attributable to acceptance of a substitute
shall be incorporated to the Contract by Participating Change Order.
5.06 Pre -Qualification of Bidders (Prime Contractors and Subcontractors)
A. The Contractor and any subcontractors are required to be prequalified for the work types
requiring pre -qualification
5.07 Concerning Subcontractors, Suppliers, and Others
A. Minority and Women Owned Business Enterprise Compliance:
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 17
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 17 of 35
❑ Required for this Contract.
(Check this box if there is any City Participation)
® Not Required for this Contract.
It is City policy to ensure the full and equitable participation by Minority and Women Business
Enterprises (MWBE) in the procurement of goods and services on a contractual basis. If the
Contract Documents provide for a MWBE goal, Contractor is required to comply with the intent
of the City's MWBE Ordinance (as amended) by the following:
1. Contractor shall, upon request by City, provide complete and accurate information regarding
actual work performed by a MWBE on the Contract and payment therefor.
2. Contractor will not make additions, deletions, or substitutions of accepted MWBE without
written consent of the City. Any unjustified change or deletion shall be a material breach of
Contract and may result in debarment in accordance with the procedures outlined in the
Ordinance.
3. Contractor shall, upon request by City, allow an audit and/or examination of any books,
records, or files in the possession of the Contractor that will substantiate the actual work
performed by an MWBE. Material misrepresentation of any nature will be grounds for
termination of the Contract. Any such misrepresentation may be grounds for disqualification
of Contractor to bid on future contracts with the City for a period of not less than three years.
B. Contractor shall be fully responsible to City for all acts and omissions of the Subcontractors,
Suppliers, and other individuals or entities performing or furnishing any of the Work just as
Contractor is responsible for Contractor's own acts and omissions. Nothing in the Contract
Documents:
1. shall create for the benefit of any such Subcontractor, Supplier, or other individual or entity
any contractual relationship between City and any such Subcontractor, Supplier or other
individual or entity; nor
2. shall create any obligation on the part of City to pay or to see to the payment of any moneys
due any such Subcontractor, Supplier, or other individual or entity except as may otherwise
be required by Laws and Regulations.
C. Contractor shall be solely responsible for scheduling and coordinating the Work of
Subcontractors, Suppliers, and other individuals or entities performing or furnishing any of the
Work under a direct or indirect contract with Contractor.
D. All Subcontractors, Suppliers, and such other individuals or entities performing or furnishing
any of the Work shall communicate with City through Contractor.
E. All Work performed for Contractor by a Subcontractor or Supplier will be pursuant to an
appropriate agreement between Contractor and the Subcontractor or Supplier which specifically
binds the Subcontractor or Supplier to the applicable terms and conditions of these Contract
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 18
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 18 of 35
Documents, Contractor shall provide City contract numbers and reference numbers to the
Subcontractors and/or Suppliers.
5.08 Wage Rates
❑ Required for this Contract.
® Not Required for this Contract.
A. Duty to pay Prevailing Wage Rates. The Contractor shall comply with all requirements of
Chapter 2258, Texas Government Code (as amended), including the payment of not less than the
rates determined by the City Council of the City of Fort Worth to be the prevailing wage rates in
accordance with Chapter 2258. Such prevailing wage rates are included in these Contract
Documents.
B. Penalty for Violation. A Contractor or any Subcontractor who does not pay the prevailing wage
shall, upon demand made by the City, pay to the City $60 for each worker employed for each
calendar day or part of the day that the worker is paid less than the prevailing wage rates
stipulated in these contract documents. This penalty shall be retained by the City to offset its
administrative costs, pursuant to Texas Government Code 2258.023.
C. Complaints of Violations and City Determination of Good Cause. On receipt of information,
including a complaint by a worker, concerning an alleged violation of 2258.023, Texas
Government Code, by a Contractor or Subcontractor, the City shall make an initial
determination, before the 31 st day after the date the City receives the information, as to whether
good cause exists to believe that the violation occurred. The City shall notify in writing the
Contractor or Subcontractor and any affected worker of its initial determination. Upon the
City's determination that there is good cause to believe the Contractor or Subcontractor has
violated Chapter 2258, the City shall retain the full amounts claimed by the claimant or
claimants as the difference between wages paid and wages due under the prevailing wage rates,
such amounts being subtracted from successive progress payments pending a final determination
of the violation.
D. Arbitration Required if Violation Not Resolved. An issue relating to an alleged violation of
Section 2258.023, Texas Government Code, including a penalty owed to the City or an affected
worker, shall be submitted to binding arbitration in accordance with the Texas General
Arbitration Act (Article 224 et seq., Revised Statutes) if the Contractor or Subcontractor and any
affected worker does not resolve the issue by agreement before the 15th day after the date the
City makes its initial determination pursuant to Paragraph C above. If the persons required to
arbitrate under this section do not agree on an arbitrator before the 1 Ith day after the date that
arbitration is required, a district court shall appoint an arbitrator on the petition of any of the
persons. The City is not a party in the arbitration. The decision and award of the arbitrator is
final and binding on all parties and may be enforced in any court of competent jurisdiction.
E. Records to be Maintained. The Contractor and each Subcontractor shall, for a period of three (3)
years following the date of acceptance of the work, maintain records that show (i) the name and
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 19
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 19 of 35
occupation of each worker employed by the Contractor in the construction of the Work provided
for in this Contract; and (ii) the actual per diem wages paid to each worker. The records shall be
open at all reasonable hours for inspection by the City. The provisions of Paragraph 6.23, Right
to Audit, shall pertain to this inspection.
F. Progress Payments. With each progress payment or payroll period, whichever is less, the
Contractor shall submit an affidavit stating that the Contractor has complied with the
requirements of Chapter 2258, Texas Government Code.
G. Posting of Wage Rates. The Contractor shall post prevailing wage rates in a conspicuous place at
all times.
H. Subcontractor Compliance. The Contractor shall include in its subcontracts and/or shall
otherwise require all of its Subcontractors to comply with Paragraphs A through G above.
5.09 Patent Fees and Royalties
A. To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and hold
harmless City, from and against all claims, costs, losses, and damages (including but not limited
to all fees and charges of engineers, architects, attorneys, and other professionals and all court
or arbitration or other dispute resolution costs) arising out of or relating to any infringement of
patent rights or copyrights incident to the use in the performance of the Work or resulting from
the incorporation in the Work of any invention, design, process, product, or device not specified
in the Contract Documents.
5.10 Laws and Regulations
A. Contractor shall give all notices required by and shall comply with all Laws and Regulations
applicable to the performance of the Work. Except where otherwise expressly required by
applicable Laws and Regulations, the City shall not be responsible for monitoring Contractor's
compliance with any Laws or Regulations.
B. If Contractor performs any Work knowing or having reason to know that it is contrary to Laws
or Regulations, Contractor shall bear all claims, costs, losses, and damages (including but not
limited to all fees and charges of engineers, architects, attorneys, and other professionals and all
court or arbitration or other dispute resolution costs) arising out of or relating to such Work.
However, it shall not be Contractor's responsibility to make certain that the Specifications and
Drawings are in accordance with Laws and Regulations, but this shall not relieve Contractor of
Contractor's obligations under Paragraph 3.01.
5.11 Use of Site and Other Areas
A. Limitation on Use of Site and Other Areas:
1. Contractor shall confine construction equipment, the storage of materials and equipment, and
the operations of workers to the Site and other areas permitted by Laws and Regulations, and
shall not unreasonably encumber the Site and other areas with construction equipment or
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 20
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 20 of 35
other materials or equipment. Contractor shall assume full responsibility for any damage to
any such land or area, or to the owner or occupant thereof, or of any adjacent land or areas
resulting from the performance of the Work.
2. At any time when, in the judgment of the City, the Contractor has obstructed or closed or is
carrying on operations in a portion of a street, right-of-way, or easement greater than is
necessary for proper execution of the Work, the City may require the Contractor to finish the
section on which operations are in progress before work is commenced on any additional
area of the Site.
3. Should any Damage Claim be made by any such owner or occupant because of the
performance of the Work, Contractor shall promptly attempt to resolve the Damage Claim.
4. Pursuant to Paragraph 5.18, Contractor shall indemnify and hold harmless City, from and
against all claims, costs, losses, and damages arising out of or relating to any claim or
action, legal or equitable, brought by any such owner or occupant against City.
B. Removal of Debris During Performance of the Work: During the progress of the Work
Contractor shall keep the Site and other areas free from accumulations of waste materials,
rubbish, and other debris. Removal and disposal of such waste materials, rubbish, and other
debris shall conform to applicable Laws and Regulations.
C. Site Maintenance Cleaning: 24 hours after written notice is given to the Contractor that the
clean-up on the job site is proceeding in a manner unsatisfactory to the City or Developer, if the
Contractor fails to correct the unsatisfactory procedure, the City may take such direct action as
the City deems appropriate to correct the clean-up deficiencies cited to the Contractor in the
written notice (by letter or electronic communication), and shall be entitled to recover its cost in
doing so. The City may withhold Final Acceptance until clean-up is complete and cost are
recovered.
D. Final Site Cleaning: Prior to Final Acceptance of the Work Contractor shall clean the Site and
the Work and make it ready for utilization by City or adjacent property owner. At the completion
of the Work Contractor shall remove from the Site all tools, appliances, construction equipment
and machinery, and surplus materials and shall restore to original condition or better all property
disturbed by the Work.
E. Loading Structures: Contractor shall not load nor permit any part of any structure to be loaded
in any manner that will endanger the structure, nor shall Contractor subject any part of the Work
or adjacent property to stresses or pressures that will endanger it.
5.12 Record Documents
A. Contractor shall maintain in a safe place at the Site or in a place designated by the Contractor
and approved by the City, one (1) record copy of all Drawings, Specifications, Addenda, Change
Orders, Field Orders, and written interpretations and clarifications in good order and annotated
to show changes made during construction. These record documents together with all approved
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 21
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 21 of 35
Samples and a counterpart of all accepted Submittals will be available to City for reference.
Upon completion of the Work, these record documents, any operation and maintenance manuals,
and Submittals will be delivered to City prior to Final Inspection. Contractor shall include
accurate locations for buried and imbedded items.
5.13 Safety and Protection
A. Contractor shall be solely responsible for initiating, maintaining and supervising all safety
precautions and programs in connection with the Work. Such responsibility does not relieve
Subcontractors of their responsibility for the safety of persons or property in the performance of
their work, nor for compliance with applicable safety Laws and Regulations. Contractor shall
take all necessary precautions for the safety of, and shall provide the necessary protection to
prevent damage, injury or loss to:
1. all persons on the Site or who may be affected by the Work;
2. all the Work and materials and equipment to be incorporated therein, whether in storage on
or off the Site; and
3. other property at the Site or adjacent thereto, including trees, shrubs, lawns, walks,
pavements, roadways, structures, utilities, and Underground Facilities not designated for
removal, relocation, or replacement in the course of construction.
B. Contractor shall comply with all applicable Laws and Regulations relating to the safety of
persons or property, or to the protection of persons or property from damage, injury, or loss; and
shall erect and maintain all necessary safeguards for such safety and protection. Contractor shall
notify owners of adjacent property and of Underground Facilities and other utility owners when
prosecution of the Work may affect them, and shall cooperate with them in the protection,
removal, relocation, and replacement of their property.
C. Contractor shall comply with the applicable requirements of City's safety programs, if any.
D. Contractor shall inform City of the specific requirements of Contractor's safety program, if any,
with which City's employees and representatives must comply while at the Site.
E. All damage, injury, or loss to any property referred to in Paragraph 5.13.A.2 or 5.13.A.3 caused,
directly or indirectly, in whole or in part, by Contractor, any Subcontractor, Supplier, or any
other individual or entity directly or indirectly employed by any of them to perform any of the
Work, or anyone for whose acts any of them may be liable, shall be remedied by Contractor.
F. Contractor's duties and responsibilities for safety and for protection of the Work shall continue
until such time as all the Work is completed and City has accepted the Work.
5.14 Safety Representative
Contractor shall inform City in writing of Contractor's designated safety representative at the Site.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 22
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 22 of 35
5.15 Hazard Communication Programs
Contractor shall be responsible for coordinating any exchange of material safety data sheets or other
hazard communication information required to be made available to or exchanged between or
among employers in accordance with Laws or Regulations.
5.16 Submittals
A. Contractor shall submit required Submittals to City for review and acceptance. Each submittal
will be identified as required by City.
1. Submit number of copies specified in the General Requirements.
2. Data shown on the Submittals will be complete with respect to quantities, dimensions,
specified performance and design criteria, materials, and similar data to show City the
services, materials, and equipment Contractor proposes to provide and to enable City to
review the information for the limited purposes required by Paragraph 5.16.C.
3. Submittals submitted as herein provided by Contractor and reviewed by City for
conformance with the design concept shall be executed in conformity with the Contract
Documents unless otherwise required by City.
4. When Submittals are submitted for the purpose of showing the installation in greater detail,
their review shall not excuse Contractor from requirements shown on the Drawings and
Specifications.
5. For -Information -Only submittals upon which the City is not expected to conduct review or
take responsive action may be so identified in the Contract Documents.
6. Submit required number of Samples specified in the Specifications.
7. Clearly identify each Sample as to material, Supplier, pertinent data such as catalog numbers,
the use for which intended and other data as City may require to enable City to review the
submittal for the limited purposes required by Paragraph 5.16.C.
B. Where a Submittal is required by the Contract Documents or the Schedule of Submittals, any
related Work performed prior to City's review and acceptance of the pertinent submittal will be
at the sole expense and responsibility of Contractor.
C. City's Review:
1. City will provide timely review of required Submittals in accordance with the Schedule of
Submittals acceptable to City. City's review and acceptance will be only to determine if the
items covered by the submittals will, after installation or incorporation in the Work, conform
to the information given in the Contract Documents and be compatible with the design
concept of the completed Project as a functioning whole as indicated by the Contract
Documents.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 23
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 23 of 35
2. City's review and acceptance will not extend to means, methods, techniques, sequences, or
procedures of construction (except where a particular means, method, technique, sequence,
or procedure of construction is specifically and expressly called for by the Contract
Documents) or to safety precautions or programs incident thereto. The review and
acceptance of a separate item as such will not indicate approval of the assembly in which the
item functions.
3. City's review and acceptance shall not relieve Contractor from responsibility for any
variation from the requirements of the Contract Documents unless Contractor has complied
with the requirements of Section 01 33 00 and City has given written acceptance of each
such variation by specific written notation thereof incorporated in or accompanying the
Submittal. City's review and acceptance shall not relieve Contractor from responsibility for
complying with the requirements of the Contract Documents.
5.17 Contractor's General Warranty and Guarantee
A. Contractor warrants and guarantees to City that all Work will be in accordance with the Contract
Documents and will not be defective. City and its officers, directors, members, partners,
employees, agents, consultants, and subcontractors shall be entitled to rely on representation of
Contractor's warranty and guarantee.
B. Contractor's warranty and guarantee hereunder excludes defects or damage caused by:
1. abuse, modification, or improper maintenance or operation by persons other than Contractor,
Subcontractors, Suppliers, or any other individual or entity for whom Contractor is
responsible; or
2. normal wear and tear under normal usage.
C. Contractor's obligation to perform and complete the Work in accordance with the Contract
Documents shall be absolute. None of the following will constitute an acceptance of Work that is
not in accordance with the Contract Documents or a release of Contractor's obligation to
perform the Work in accordance with the Contract Documents:
1. observations by City;
2. recommendation or payment by City or Developer of any progress or final payment;
3. the issuance of a certificate of Final Acceptance by City or any payment related thereto by
City;
4. use or occupancy of the Work or any part thereof by City;
5. any review and acceptance of a Submittal by City;
6. any inspection, test, or approval by others; or
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 24
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 24 of 35
7. any correction of defective Work by City.
D. The Contractor shall remedy any defects or damages in the Work and pay for any damage to
other work or property resulting therefrom which shall appear within a period of two (2) years
from the date of Final Acceptance of the Work unless a longer period is specified and shall
furnish a good and sufficient maintenance bond, complying with the requirements of Article
4.02.13. The City will give notice of observed defects with reasonable promptness.
5.18 Indemnification
A. Contractor covenants and agrees to indemnify, hold harmless and defend, at its own expense, the
City, its officers, servants and employees, from and against any and all claims arising out of, or
alleged to arise out of, the work and services to be performed by the Contractor, its officers,
agents, employees, subcontractors, licenses or invitees under this Contract. THIS
INDEMNIFICATION PROVISION IS SPECIFICALLY INTENDED TO OPERATE
AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR PROVEN THAT ALL OR SOME
OF THE DAMAGES BEING SOUGHT WERE CAUSED, IN WHOLE OR IN PART, BY
ANY ACT, OMISSION OR NEGLIGENCE OF THE CITY. This indemnity provision is
intended to include, without limitation, indemnity for costs, expenses and legal fees incurred by
the City in defending against such claims and causes of actions.
B. Contractor covenants and agrees to indemnify and hold harmless, at its own expense, the City, its
officers, servants and employees, from and against any and all loss, damage or destruction of
property of the City, arising out of, or alleged to arise out of, the work and services to be
performed by the Contractor, its officers, agents, employees, subcontractors, licensees or invitees
under this Contract. THIS INDEMNIFICATION PROVISION IS SPECIFICALLY
INTENDED TO OPERATE AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR
PROVEN THAT ALL OR SOME OF THE DAMAGES BEING SOUGHT WERE
CAUSED, IN WHOLE OR IN PART, BY ANY ACT, OMISSION OR NEGLIGENCE OF
THE CITY.
5.19 Delegation of Professional Design Services
A. Contractor will not be required to provide professional design services unless such services are
specifically required by the Contract Documents for a portion of the Work or unless such
services are required to carry out Contractor's responsibilities for construction means, methods,
techniques, sequences and procedures.
B. If professional design services or certifications by a design professional related to systems,
materials or equipment are specifically required of Contractor by the Contract Documents, City
will specify all performance and design criteria that such services must satisfy. Contractor shall
cause such services or certifications to be provided by a properly licensed professional, whose
signature and seal shall appear on all drawings, calculations, specifications, certifications, and
Submittals prepared by such professional. Submittals related to the Work designed or certified
by such professional, if prepared by others, shall bear such professional's written approval when
submitted to City.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 25
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 25 of 35
C. City shall be entitled to rely upon the adequacy, accuracy and completeness of the services,
certifications or approvals performed by such design professionals, provided City has specified
to Contractor performance and design criteria that such services must satisfy.
D. Pursuant to this Paragraph 5.19, City's review and acceptance of design calculations and design
drawings will be only for the limited purpose of checking for conformance with performance
and design criteria given and the design concept expressed in the Contract Documents. City's
review and acceptance of Submittals (except design calculations and design drawings) will be
only for the purpose stated in Paragraph 5.16.C.
5.20 Right to Audit:
A. The City reserves the right to audit all projects utilizing City funds
B. The Contractor agrees that the City shall, until the expiration of three (3) years after final
payment under this Contract, have access to and the right to examine and photocopy any directly
pertinent books, documents, papers, and records of the Contractor involving transactions relating
to this Contract. Contractor agrees that the City shall have access during Regular Working Hours
to all necessary Contractor facilities and shall be provided adequate and appropriate work space
in order to conduct audits in compliance with the provisions of this Paragraph. The City shall
give Contractor reasonable advance notice of intended audits.
C. Contractor further agrees to include in all its subcontracts hereunder a provision to the effect that
the subcontractor agrees that the City shall, until the expiration of three (3) years after final
payment under this Contract, have access to and the right to examine and photocopy any directly
pertinent books, documents, papers, and records of such Subcontractor, involving transactions to
the subcontract, and further, that City shall have access during Regular Working Hours to all
Subcontractor facilities, and shall be provided adequate and appropriate work space in order to
conduct audits in compliance with the provisions of this Paragraph. The City shall give
Subcontractor reasonable advance notice of intended audits.
D. Contractor and Subcontractor agree to photocopy such documents as may be requested by the
City. The City agrees to reimburse Contractor for the cost of the copies as follows at the rate
published in the Texas Administrative Code in effect as of the time copying is performed.
5.21 Nondiscrimination
A. The City is responsible for operating Public Transportation Programs and implementing transit -
related projects, which are funded in part with Federal financial assistance awarded by the U.S.
Department of Transportation and the Federal Transit Administration (FTA), without
discriminating against any person in the United States on the basis of race, color, or national
origin.
B. Title VI, Civil Rights Act of 1964 as amended: Contractor shall comply with the requirements of
the Act and the Regulations as further defined in the Supplementary Conditions for any project
receiving Federal assistance.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 26
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 26 of 35
ARTICLE 6 — OTHER WORK AT THE SITE
6.01 Related Work at Site
A. City may perform other work related to the Project at the Site with City's employees, or other
City contractors, or through other direct contracts therefor, or have other work performed by
utility owners. If such other work is not noted in the Contract Documents, then written notice
thereof will be given to Contractor prior to starting any such other work; and
B. Contractor shall afford each other contractor who is a party to such a direct contract, each utility
owner, and City, if City is performing other work with City's employees or other City
contractors, proper and safe access to the Site, provide a reasonable opportunity for the
introduction and storage of materials and equipment and the execution of such other work, and
properly coordinate the Work with theirs. Contractor shall do all cutting, fitting, and patching of
the Work that may be required to properly connect or otherwise make its several parts come
together and properly integrate with such other work. Contractor shall not endanger any work of
others by cutting, excavating, or otherwise altering such work; provided, however, that
Contractor may cut or alter others' work with the written consent of City and the others whose
work will be affected.
C. If the proper execution or results of any part of Contractor's Work depends upon work
performed by others under this Article 7, Contractor shall inspect such other work and promptly
report to City in writing any delays, defects, or deficiencies in such other work that render it
unavailable or unsuitable for the proper execution and results of Contractor's Work. Contractor's
failure to so report will constitute an acceptance of such other work as fit and proper for
integration with Contractor's Work except for latent defects in the work provided by others.
ARTICLE 7 — CITY'S RESPONSIBILITIES
7.01 Inspections, Tests, and Approvals
City's responsibility with respect to certain inspections, tests, and approvals is set forth in Paragraph
11.03.
7.02 Limitations on City's Responsibilities
A. The City shall not supervise, direct, or have control or authority over, nor be responsible for,
Contractor's means, methods, techniques, sequences, or procedures of construction, or the safety
precautions and programs incident thereto, or for any failure of Contractor to comply with Laws
and Regulations applicable to the performance of the Work. City will not be responsible for
Contractor's failure to perform the Work in accordance with the Contract Documents.
B. City will notify the Contractor of applicable safety plans pursuant to Paragraph 5.13.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 27
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 27 of 35
7.03 Compliance with Safety Program
While at the Site, City's employees and representatives shall comply with the specific applicable
requirements of Contractor's safety programs of which City has been informed pursuant to
Paragraph 5.13.
ARTICLE 8 — CITY'S OBSERVATION STATUS DURING CONSTRUCTION
8.01 City's Project Representative
City will provide one or more Project Representative(s) during the construction period. The duties
and responsibilities and the limitations of authority of City's representative during construction are
set forth in the Contract Documents.
A. City's Project Representative will make visits to the Site at intervals appropriate to the various
stages of construction as City deems necessary in order to observe the progress that has been
made and the quality of the various aspects of Contractor's executed Work. Based on
information obtained during such visits and observations, City's Project Representative will
determine, in general, if the Work is proceeding in accordance with the Contract Documents.
City's Project Representative will not be required to make exhaustive or continuous inspections
on the Site to check the quality or quantity of the Work. City's Project Representative's efforts
will be directed toward providing City a greater degree of confidence that the completed Work
will conform generally to the Contract Documents.
B. City's Project Representative's visits and observations are subject to all the limitations on
authority and responsibility in the Contract Documents.
8.02 Authorized Variations in Work
City's Project Representative may authorize minor variations in the Work from the requirements of
the Contract Documents which do not involve an adjustment in the Contract Price or the Contract
Time and are compatible with the design concept of the completed Project as a functioning whole as
indicated by the Contract Documents. These may be accomplished by a Field Order and will be
binding on City Developer, and also on Contractor, who shall perform the Work involved promptly.
8.03 Rejecting Defective Work
City will have authority to reject Work which City's Project Representative believes to be defective,
or will not produce a completed Project that conforms to the Contract Documents or that will
prejudice the integrity of the design concept of the completed Project as a functioning whole as
indicated by the Contract Documents. City will have authority to conduct special inspection or
testing of the Work as provided in Article 11, whether or not the Work is fabricated, installed, or
completed.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 28
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 28 of 35
8.04 Determinations for Work Performed
Contractor will determine the actual quantities and classifications of Work performed. City's Project
Representative will review with Contractor the preliminary determinations on such matters before
rendering a written recommendation. City's written decision will be final (except as modified to
reflect changed factual conditions or more accurate data).
ARTICLE 9 — CHANGES IN THE WORK
9.01 Authorized Changes in the Work
A. Without invalidating the Contract and without notice to any surety, City may, at any time or
from time to time, order Extra Work. Upon notice of such Extra Work, Contractor shall
promptly proceed with the Work involved which will be performed under the applicable
conditions of the Contract Documents (except as otherwise specifically provided). Extra Work
shall be memorialized by a Participating Change Order which may or may not precede an order
of Extra work.
B. For minor changes of Work not requiring changes to Contract Time or Contract Price on a
project with City participation, a Field Order may be issued by the City.
9.02 Notification to Surety
If the provisions of any bond require notice to be given to a surety of any change affecting the
general scope of the Work or the provisions of the Contract Documents (including, but not limited
to, Contract Price or Contract Time), the giving of any such notice will be Contractor's
responsibility. The amount of each applicable bond will be adjusted by the Contractor to reflect the
effect of any such change.
ARTICLE 10 — CHANGE OF CONTRACT PRICE; CHANGE OF CONTRACT TIME
10.01 Change of Contract Price
A. The Contract Price may only be changed by a Participating Change Order for projects with City
participation.
10.02 Change of Contract Time
A. The Contract Time may only be changed by a Participating Change Order for projects with City
participation.
10.03 Delays
A. If Contractor is delayed, City shall not be liable to Contractor for any claims, costs, losses, or
damages (including but not limited to all fees and charges of engineers, architects, attorneys, and
other professionals and all court or arbitration or other dispute resolution costs) sustained by
Contractor on or in connection with any other project or anticipated project.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 29
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 29 of 35
ARTICLE 11— TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF
DEFECTIVE WORK
11.01 Notice of Defects
Notice of all defective Work of which City has actual knowledge will be given to Contractor.
Defective Work may be rejected, corrected, or accepted as provided in this Article 13.
11.02 Access to Work
City, independent testing laboratories, and governmental agencies with jurisdictional interests will
have access to the Site and the Work at reasonable times for their observation, inspection, and
testing. Contractor shall provide them proper and safe conditions for such access and advise them of
Contractor's safety procedures and programs so that they may comply therewith as applicable.
11.03 Tests and Inspections
A. Contractor shall give City timely notice of readiness of the Work for all required inspections,
tests, or approvals and shall cooperate with inspection and testing personnel to facilitate required
inspections or tests.
B. If Contract Documents, Laws or Regulations of any public body having jurisdiction require any
of the Work (or part thereof) to be inspected, tested, or approved, Contractor shall assume full
responsibility for arranging and obtaining such independent inspections, tests, retests or
approvals, pay all costs in connection therewith, and furnish City the required certificates of
inspection or approval; excepting, however, those fees specifically identified in the
Supplementary Conditions or any Texas Department of Licensure and Regulation (TDLR)
inspections, which shall be paid as described in the Supplementary Conditions.
C. Contractor shall be responsible for arranging and obtaining and shall pay all costs in connection
with any inspections, tests, re -tests, or approvals required for City's acceptance of materials or
equipment to be incorporated in the Work; or acceptance of materials, mix designs, or equipment
submitted for approval prior to Contractor's purchase thereof for incorporation in the Work.
Such inspections, tests, re -tests, or approvals shall be performed by organizations approved by
City.
D. City may arrange for the services of an independent testing laboratory ("Testing Lab") to
perform any inspections or tests ("Testing") for any part of the Work, as determined solely by
City.
1. City will coordinate such Testing to the extent possible, with Contractor;
2. Should any Testing under this Section 11.03 D result in a "fail", "did not pass" or other
similar negative result, the Contractor shall be responsible for paying for any and all retests.
Contractor's cancellation without cause of City initiated Testing shall be deemed a negative
result and require a retest.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 30
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 30 of 35
3. Any amounts owed for any retest under this Section 11.03 D shall be paid directly to the
Testing Lab by Contractor.
Developer/Contractor.
City will forward all invoices for retests to
4. If Contractor fails to pay the Testing Lab, City will not issue a letter of Final Acceptance
until the Testing Lab is Paid
E. If any Work (or the work of others) that is to be inspected, tested, or approved is covered by
Contractor without written concurrence of City, Contractor shall, if requested by City, uncover
such Work for observation.
11.04 Uncovering Work
A. If any Work is covered contrary to the Contract Documents or specific instructions by the City, it
must, if requested by City, be uncovered for City's observation and replaced at Contractor's
expense.
11.05 City May Stop the Work
If the Work is defective, or Contractor fails to supply sufficient skilled workers or suitable materials
or equipment, or fails to perform the Work in such a way that the completed Work will conform to
the Contract Documents, City may order Contractor to stop the Work, or any portion thereof, until
the cause for such order has been eliminated; however, this right of City to stop the Work shall not
give rise to any duty on the part of City to exercise this right for the benefit of Contractor, any
Subcontractor, any Supplier, any other individual or entity, or any surety for, or employee or agent
of any of them.
11.06 Correction or Removal of Defective Work
A. Promptly after receipt of written notice, Contractor shall correct all defective Work pursuant to
an acceptable schedule, whether or not fabricated, installed, or completed, or, if the Work has
been rejected by City, remove it from the Project and replace it with Work that is not defective.
Contractor shall pay all claims, costs, additional testing, losses, and damages (including but not
limited to all fees and charges of engineers, architects, attorneys, and other professionals and all
court or arbitration or other dispute resolution costs) arising out of or relating to such correction
or removal (including but not limited to all costs of repair or replacement of work of others).
Failure to require the removal of any defective Work shall not constitute acceptance of such
Work.
B. When correcting defective Work under the terms of this Paragraph 11.06 or Paragraph 11.07,
Contractor shall take no action that would void or otherwise impair City's special warranty and
guarantee, if any, on said Work.
11.07 Correction Period
A. If within two (2) years after the date of Final Acceptance (or such longer period of time as may
be prescribed by the terms of any applicable special guarantee required by the Contract
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 31
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 31 of 35
Documents), any Work is found to be defective, or if the repair of any damages to the land or
areas made available for Contractor's use by City or permitted by Laws and Regulations as
contemplated in Paragraph 5.10.A is found to be defective, Contractor shall promptly, without
cost to City and in accordance with City's written instructions:
1. repair such defective land or areas; or
2. correct such defective Work; or
3. if the defective Work has been rejected by City, remove it from the Project and replace it
with Work that is not defective, and
4. satisfactorily correct or repair or remove and replace any damage to other Work, to the work
of others or other land or areas resulting therefrom.
B. If Contractor does not promptly comply with the terms of City's written instructions, or in an
emergency where delay would cause serious risk of loss or damage, City may have the defective
Work corrected or repaired or may have the rejected Work removed and replaced. All claims,
costs, losses, and damages (including but not limited to all fees and charges of engineers,
architects, attorneys, and other professionals and all court or other dispute resolution costs)
arising out of or relating to such correction or repair or such removal and replacement (including
but not limited to all costs of repair or replacement of work of others) will be paid by Contractor.
C. Where defective Work (and damage to other Work resulting therefrom) has been corrected or
removed and replaced under this Paragraph 11.07, the correction period hereunder with respect
to such Work may be required to be extended for an additional period of one year after the end
of the initial correction period. City shall provide 30 days written notice to Contractor and
Developer should such additional warranty coverage be required. Contractor's obligations under
this Paragraph 11.07 are in addition to any other obligation or warranty. The provisions of this
Paragraph 11.07 shall not be construed as a substitute for, or a waiver of, the provisions of any
applicable statute of limitation or repose.
11.08 City May Correct Defective Work
A. If Contractor fails within a reasonable time after written notice from City to correct defective
Work, or to remove and replace rejected Work as required by City in accordance with Paragraph
11.06.A, or if Contractor fails to perform the Work in accordance with the Contract Documents,
or if Contractor fails to comply with any other provision of the Contract Documents, City may,
after seven (7) days written notice to Contractor and the Developer, correct, or remedy any such
deficiency.
B. In exercising the rights and remedies under this Paragraph 11.09, City shall proceed
expeditiously. In connection with such corrective or remedial action, City may exclude
Contractor from all or part of the Site, take possession of all or part of the Work and suspend
Contractor's services related thereto, and incorporate in the Work all materials and equipment
incorporated in the Work, stored at the Site or for which City has paid Contractor but which are
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 32
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 32 of 35
stored elsewhere. Contractor shall allow City, City's representatives, agents, consultants,
employees, and City's other contractors, access to the Site to enable City to exercise the rights
and remedies under this Paragraph.
C. All claims, costs, losses, and damages (including but not limited to all fees and charges of
engineers, architects, attorneys, and other professionals and all court or other dispute resolution
costs) incurred or sustained by City in exercising the rights and remedies under this Paragraph
13.09 will be charged against Contractor, and a Change Order will be issued incorporating the
necessary revisions in the Contract Documents with respect to the Work; and City shall be
entitled to an appropriate decrease in the Contract Price.
D. Contractor shall not be allowed an extension of the Contract Time because of any delay in the
performance of the Work attributable to the exercise of City's rights and remedies under this
Paragraph 11.09.
ARTICLE 12 — COMPLETION
12.01 Contractor's Warranty of Title
Contractor warrants and guarantees that title to all Work, materials, and equipment covered by any
Application for Payment will pass to City no later than the time of Final Acceptance and shall be
free and clear of all Liens.
12.02 Partial Utilization
A. Prior to Final Acceptance of all the Work, City may use or occupy any substantially completed
part of the Work which has specifically been identified in the Contract Documents, or which
City, determines constitutes a separately functioning and usable part of the Work that can be
used by City for its intended purpose without significant interference with Contractor's
performance of the remainder of the Work. City at any time may notify Contractor in writing to
permit City to use or occupy any such part of the Work which City determines to be ready for its
intended use, subject to the following conditions:
1. Contractor at any time may notify City in writing that Contractor considers any such part of
the Work ready for its intended use.
2. Within a reasonable time after notification as enumerated in Paragraph 14.05.A.1, City and
Contractor shall make an inspection of that part of the Work to determine its status of
completion. If City does not consider that part of the Work to be substantially complete, City
will notify Contractor in writing giving the reasons therefor.
3. Partial Utilization will not constitute Final Acceptance by City.
12.03 Final Inspection
A. Upon written notice from Contractor that the entire Work is complete in accordance with the
Contract Documents:
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 33
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 33 of 35
1. within 10 days, City will schedule a Final Inspection with Contractor.
2. City will notify Contractor in writing of all particulars in which this inspection reveals that
the Work is incomplete or defective. Contractor shall immediately take such measures as are
necessary to complete such Work or remedy such deficiencies.
12.04 Final Acceptance
A. Upon completion by Contractor to City's satisfaction, of any additional Work identified in the
Final Inspection, City will issue to Contractor a letter of Final Acceptance upon the satisfaction
of the following:
1. All documentation called for in the Contract Documents, including but not limited to the
evidence of insurance required by Paragraph 5.03;
2. consent of the surety, if any, to Final Acceptance;
3. a list of all pending or released Damage Claims against City that Contractor believes are
unsettled; and
4. affidavits of payments and complete and legally effective releases or waivers (satisfactory to
City) of all Lien rights arising out of or Liens filed in connection with the Work.
5. after all Damage Claims have been resolved:
a. directly by the Contractor or;
b. Contractor provides evidence that the Damage Claim has been reported to Contractor's
insurance provider for resolution.
6. Issuing Final Acceptance by the City shall not relieve the Contractor of any guarantees or
other requirements of the Contract Documents which specifically continue thereafter.
ARTICLE 13 — SUSPENSION OF WORK
13.01 City May Suspend Work
A. At any time and without cause, City may suspend the Work or any portion thereof by written
notice to Contractor and which may fix the date on which Work will be resumed. Contractor
shall resume the Work on the date so fixed. During temporary suspension of the Work covered
by these Contract Documents, for any reason, the City will stop contract time on City
participation projects.
B. Should the Contractor not be able to complete a portion of the Project due to causes beyond the
control of and without the fault or negligence of the Contractor, and should it be determined by
mutual consent of the Contractor and City that a solution to allow construction to proceed is not
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 34
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 34 of 35
available within a reasonable period of time, Contractor may request an extension in Contract
Time, directly attributable to any such suspension.
C. If it should become necessary to suspend the Work for an indefinite period, the Contractor shall
store all materials in such a manner that they will not obstruct or impede the public unnecessarily
nor become damaged in any way, and he shall take every precaution to prevent damage or
deterioration of the work performed; he shall provide suitable drainage about the work, and erect
temporary structures where necessary.
ARTICLE 14 — MISCELLANEOUS
14.01 Giving Notice
A. Whenever any provision of the Contract Documents requires the giving of written notice, it will
be deemed to have been validly given i£
1. delivered in person to the individual or to a member of the firm or to an officer of the
corporation for whom it is intended; or
2. delivered at or sent by registered or certified mail, postage prepaid, to the last business
address known to the giver of the notice.
B. Business address changes must be promptly made in writing to the other party.
C. Whenever the Contract Documents specifies giving notice by electronic means such electronic
notice shall be deemed sufficient upon confirmation of receipt by the receiving party.
14.02 Computation of Times
When any period of time is referred to in the Contract Documents by days, it will be computed to
exclude the first and include the last day of such period. If the last day of any such period falls on a
Saturday or Sunday or on a day made a legal holiday the next Working Day shall become the last
day of the period.
14.03 Cumulative Remedies
The duties and obligations imposed by these General Conditions and the rights and remedies
available hereunder to the parties hereto are in addition to, and are not to be construed in any way as
a limitation of, any rights and remedies available to any or all of them which are otherwise imposed
or available by Laws or Regulations, by special warranty or guarantee, or by other provisions of the
Contract Documents. The provisions of this Paragraph will be as effective as if repeated specifically
in the Contract Documents in connection with each particular duty, obligation, right, and remedy to
which they apply.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 35
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 35 of 35
14.04 Survival of Obligations
All representations, indemnifications, warranties, and guarantees made in, required by, or given in
accordance with the Contract Documents, as well as all continuing obligations indicated in the
Contract Documents, will survive final payment, completion, and acceptance of the Work or
termination or completion of the Contract or termination of the services of Contractor.
14.05 Headings
Article and paragraph headings are inserted for convenience only and do not constitute parts of these
General Conditions.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
011100-1
DAP SUMMARY OF WORK
SECTION 01 11 00
SUMMARY OF WORK
PART1- GENERAL
1.1 SUMMARY
A. Section Includes:
Page 1 of 3
1. Summary of Work to be performed in accordance with the Contract Documents
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the Contract
2. Division 1 - General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
Work associated with this Item is considered subsidiary to the various items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Work Covered by Contract Documents
1. Work is to include furnishing all labor, materials, and equipment, and performing
all Work necessary for this construction project as detailed in the Drawings and
Specifications.
B. Subsidiary Work
Any and all Work specifically governed by documentary requirements for the
project, such as conditions imposed by the Drawings or Contract Documents in
which no specific item for bid has been provided for in the Proposal and the item is
not a typical unit bid item included on the standard bid item list, then the item shall
be considered as a subsidiary item of Work, the cost of which shall be included in
the price bid in the Proposal for various bid items.
C. Use of Premises
1. Coordinate uses of premises under direction of the City.
2. Assume full responsibility for protection and safekeeping of materials and
equipment stored on the Site.
Use and occupy only portions of the public streets and alleys, or other public places
or other rights -of -way as provided for in the ordinances of the City, as shown in the
Contract Documents, or as may be specifically authorized in writing by the City.
a. A reasonable amount of tools, materials, and equipment for construction
purposes may be stored in such space, but no more than is necessary to avoid
delay in the construction operations.
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects CPN 104255
Revised December 20, 2012
01 11 00 - 2
DAP SUMMARY OF WORK
Page 2 of 3
b. Excavated and waste materials shall be stored in such a way as not to interfere
with the use of spaces that may be designated to be left free and unobstructed
and so as not to inconvenience occupants of adjacent property.
c. If the street is occupied by railroad tracks, the Work shall be carried on in such
manner as not to interfere with the operation of the railroad.
1) All Work shall be in accordance with railroad requirements set forth in
Division 0 as well as the railroad permit.
D. Work within Easements
1. Do not enter upon private property for any purpose without having previously
obtained permission from the owner of such property.
2. Do not store equipment or material on private property unless and until the
specified approval of the property owner has been secured in writing by the
Contractor and a copy furnished to the City.
3. Unless specifically provided otherwise, clear all rights -of -way or easements of
obstructions which must be removed to make possible proper prosecution of the
Work as a part of the project construction operations.
4. Preserve and use every precaution to prevent damage to, all trees, shrubbery, plants,
lawns, fences, culverts, curbing, and all other types of structures or improvements,
to all water, sewer, and gas lines, to all conduits, overhead pole lines, or
appurtenances thereof, including the construction of temporary fences and to all
other public or private property adjacent to the Work.
5. Notify the proper representatives of the owners or occupants of the public or private
lands of interest in lands which might be affected by the Work.
a. Such notice shall be made at least 48 hours in advance of the beginning of the
Work.
b. Notices shall be applicable to both public and private utility companies and any
corporation, company, individual, or other, either as owners or occupants,
whose land or interest in land might be affected by the Work.
c. Be responsible for all damage or injury to property of any character resulting
from any act, omission, neglect, or misconduct in the manner or method or
execution of the Work, or at any time due to defective work, material, or
equipment.
6. Fence
a. Restore all fences encountered and removed during construction of the Project
to the original or a better than original condition.
b. Erect temporary fencing in place of the fencing removed whenever the Work is
not in progress and when the site is vacated overnight, and/or at all times to
provide site security.
c. The cost for all fence work within easements, including removal, temporary
closures and replacement, shall be subsidiary to the various items bid in the
project proposal, unless a bid item is specifically provided in the proposal.
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects CPN 104255
Revised December 20, 2012
011100-3
DAP SUMMARY OF WORK
Page 3 of 3
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
I DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects CPN 104255
Revised December 20, 2012
012500-1
DAP SUBSTITUTION PROCEDURES
SECTION 0125 00
SUBSTITUTION PROCEDURES
PART1- GENERAL
1.1 SUMMARY
A. Section Includes:
Page 1 of 4
The procedure for requesting the approval of substitution of a product that is not
equivalent to a product which is specified by descriptive or performance criteria or
defined by reference to 1 or more of the following:
a. Name of manufacturer
b. Name of vendor
c. Trade name
d. Catalog number
2. Substitutions are not "or -equals".
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 — General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various items bid. No
separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Request for Substitution - General
1. Within 30 days after award of Contract (unless noted otherwise), the City will
consider formal requests from Contractor for substitution of products in place of
those specified.
2. Certain types of equipment and kinds of material are described in Specifications by
means of references to names of manufacturers and vendors, trade names, or catalog
numbers.
a. When this method of specifying is used, it is not intended to exclude from
consideration other products bearing other manufacturer's or vendor's names,
trade names, or catalog numbers, provided said products are "or -equals," as
determined by City.
3. Other types of equipment and kinds of material may be acceptable substitutions
under the following conditions:
a. Or -equals are unavailable due to strike, discontinued production of products
meeting specified requirements, or other factors beyond control of Contractor;
or,
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised August 30, 2013
01 25 00 - 2
DAP SUBSTITUTION PROCEDURES
Page 2 of 4
b. Contractor proposes a cost and/or time reduction incentive to the City.
1.5 SUBMITTALS
A. See Request for Substitution Form (attached)
B. Procedure for Requesting Substitution
1. Substitution shall be considered only:
a. After award of Contract
b. Under the conditions stated herein
2. Submit 3 copies of each written request for substitution, including:
a. Documentation
1) Complete data substantiating compliance of proposed substitution with
Contract Documents
2) Data relating to changes in construction schedule, when a reduction is
proposed
3) Data relating to changes in cost
b. For products
1) Product identification
a) Manufacturer's name
b) Telephone number and representative contact name
c) Specification Section or Drawing reference of originally specified
product, including discrete name or tag number assigned to original
product in the Contract Documents
2) Manufacturer's literature clearly marked to show compliance of proposed
product with Contract Documents
3) Itemized comparison of original and proposed product addressing product
characteristics including, but not necessarily limited to:
a) Size
b) Composition or materials of construction
c) Weight
d) Electrical or mechanical requirements
4) Product experience
a) Location of past projects utilizing product
b) Name and telephone number of persons associated with referenced
projects knowledgeable concerning proposed product
c) Available field data and reports associated with proposed product
5) Samples
a) Provide at request of City.
b) Samples become the property of the City.
c. For construction methods:
1) Detailed description of proposed method
2) Illustration drawings
C. Approval or Rejection
1. Written approval or rejection of substitution given by the City
2. City reserves the right to require proposed product to comply with color and pattern
of specified product if necessary to secure design intent.
3. In the event the substitution is approved, if a reduction in cost or time results, it will
be documented by Change Order.
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised August 30, 2013
012500-3
DAP SUBSTITUTION PROCEDURES
Page 3 of 4
4. Substitution will be rejected if:
a. Submittal is not through the Contractor with his stamp of approval
b. Request is not made in accordance with this Specification Section
c. In the Developer's opinion, acceptance will require substantial revision of the
original design
d. In the City's or Developer's opinion, substitution will not perform adequately
the function consistent with the design intent
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE
A. In making request for substitution or in using an approved product, the Contractor
represents that the Contractor:
1. Has investigated proposed product, and has determined that it is adequate or
superior in all respects to that specified, and that it will perform function for which it
is intended
2. Will provide same guarantee for substitute item as for product specified
3. Will coordinate installation of accepted substitution into Work, to include building
modifications if necessary, making such changes as may be required for Work to be
complete in all respects
4. Waives all claims for additional costs related to substitution which subsequently
arise
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised August 30, 2013
01 25 00 - 4
DAP SUBSTITUTION PROCEDURES
Page 4 of 4
EXHIBIT A
REQUEST FOR SUBSTITUTION FORM:
PROJECT: DATE:
We hereby submit for your consideration the following product instead of the specified item for
the above project:
SECTION PARAGRAPH SPECIFIED ITEM
Proposed Substitution:
Reason for Substitution:
Include complete information on changes to Drawings and/or Specifications which proposed
substitution will require for its proper installation.
Fill in Blanks Below:
A. Will the undersigned contractor pay for changes to the building design, including engineering
and detailing costs caused by the requested substitution?
B. What effect does substitution have on other trades?
C. Differences between proposed substitution and specified item?
D. Differences in product cost or product delivery time?
E. Manufacturer's guarantees of the proposed and specified items are:
Equal Better (explain on attachment)
The undersigned states that the function, appearance and quality are equivalent or superior to the
specified item.
Submitted By: For Use by City
Signature
as noted
Firm
Address
Date
Telephone
For Use by City:
Approved
City
Recommended _ Recommended
Not recommended
By
Date
Remarks
Date
Rejected
Received late
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised August 30, 2013
013119-1
DAP PRECONSTRUCTION MEETING
SECTION 013119
PRECONSTRUCTION MEETING
PART1- GENERAL
1.1 SUMMARY
A. Section Includes:
Page 1 of 3
1. Provisions for the preconstruction meeting to be held prior to the start of Work to
clarify construction contract administration procedures
B. Deviations from this City of Fort Worth Standard Specification
1. No construction schedule required unless requested by the City.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division I — General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Coordination
1. Attend preconstruction meeting.
2. Representatives of Contractor, subcontractors and suppliers attending meetings
shall be qualified and authorized to act on behalf of the entity each represents.
3. Meeting administered by City may be tape recorded.
a. If recorded, tapes will be used to prepare minutes and retained by City for
future reference.
B. Preconstruction Meeting
1. A preconstruction meeting will be held within 14 days after the delivery of the
distribution package to the City.
a. The meeting will be scheduled and administered by the City.
2. The Project Representative will preside at the meeting, prepare the notes of the
meeting and distribute copies of same to all participants who so request by fully
completing the attendance form to be circulated at the beginning of the meeting.
3. Attendance shall include:
a. Developer and Consultant
b. Contractor's project manager
c. Contractor's superintendent
d. Any subcontractor or supplier representatives whom the Contractor may desire
to invite or the City may request
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised August 30, 2013
01 31 19 - 2
DAP PRECONSTRUCTION MEETING
Page 2 of 3
e. Other City representatives
f. Others as appropriate
4. Preliminary Agenda may include:
a. Introduction of Project Personnel
b. General Description of Project
c. Status of right-of-way, utility clearances, easements or other pertinent permits
d. Contractor's work plan and schedule
e. Contract Time
f. Notice to Proceed
g. Construction Staking
h. Progress Payments
i. Extra Work and Change Order Procedures
j. Field Orders
k. Disposal Site Letter for Waste Material
1. Insurance Renewals
in. Payroll Certification
n. Material Certifications and Quality Control Testing
o. Public Safety and Convenience
p. Documentation of Pre -Construction Conditions
q. Weekend Work Notification
r. Legal Holidays
s. Trench Safety Plans
t. Confined Space Entry Standards
u. Coordination with the City's representative for operations of existing water
systems
v. Storm Water Pollution Prevention Plan
w. Coordination with other Contractors
x. Early Warning System
y. Contractor Evaluation
z. Special Conditions applicable to the project
aa. Damages Claims
bb. Submittal Procedures
cc. Substitution Procedures
dd. Correspondence Routing
ee. Record Drawings
ff. Temporary construction facilities
gg. MBE/SBE procedures
hh. Final Acceptance
ii. Final Payment
J. Questions or Comments
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised August 30, 2013
013119-3
DAP PRECONSTRUCTION MEETING
Page 3 of 3
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
I DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised August 30, 2013
013233-1
DAP PRECONSTRUCTION VIDEO
Page 1 of 2
SECTION 0132 33
PRECONSTRUCTION VIDEO
PART1- GENERAL
1.1 SUMMARY
A. Section Includes:
1. Administrative and procedural requirements for:
a. Preconstruction Videos
B. Deviations from this City of Fort Worth Standard Specification
1. Though not mandatory, it is highly recommended on infill developer projects.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 — General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Preconstruction Video
1. Produce a preconstruction video of the site/alignment, including all areas in the
vicinity of and to be affected by construction.
a. Provide digital copy of video upon request by the City.
2. Retain a copy of the preconstruction video until the end of the maintenance surety
period.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised August 30, 2013
01 32 33 - 2
DAP PRECONSTRUCTION VIDEO
Page 2 of 2
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised August 30, 2013
SECTION 0133 00
DAP SUBMITTALS
PART1- GENERAL
1.1 SUMMARY
A. Section Includes:
013300-1
DAP SUBMITTALS
Page 1 of 8
General methods and requirements of submissions applicable to the following
Work -related submittals:
a. Shop Drawings
b. Product Data (including Standard Product List submittals)
c. Samples
d. Mock Ups
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 — General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Coordination
1. Notify the City in writing, at the time of submittal, of any deviations in the
submittals from the requirements of the Contract Documents.
2. Coordination of Submittal Times
a. Prepare, prioritize and transmit each submittal sufficiently in advance of
performing the related Work or other applicable activities, or within the time
specified in the individual Work Sections, of the Specifications.
b. Contractor is responsible such that the installation will not be delayed by
processing times including, but not limited to:
a) Disapproval and resubmittal (if required)
b) Coordination with other submittals
c) Testing
d) Purchasing
e) Fabrication
f) Delivery
g) Similar sequenced activities
c. No extension of time will be authorized because of the Contractor's failure to
transmit submittals sufficiently in advance of the Work.
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised August 30, 2013
013300-2
DAP SUBMITTALS
Page 2 of 8
d. Make submittals promptly in accordance with approved schedule, and in such
sequence as to cause no delay in the Work or in the work of any other
contractor.
B. Submittal Numbering
When submitting shop drawings or samples, utilize a 9-character submittal cross-
reference identification numbering system in the following manner:
a. Use the first 6 digits of the applicable Specification Section Number.
b. For the next 2 digits number use numbers 01-99 to sequentially number each
initial separate item or drawing submitted under each specific Section number.
c. Last use a letter, A-Z, indicating the resubmission of the same drawing (i.e.
A=2nd submission, B=3rd submission, C=4th submission, etc.). A typical
submittal number would be as follows:
03 30 00-08-B
1) 03 30 00 is the Specification Section for Concrete
2) 08 is the eighth initial submittal under this Specification Section
3) B is the third submission (second resubmission) of that particular shop
drawing
C. Contractor Certification
Review shop drawings, product data and samples, including those by
subcontractors, prior to submission to determine and verify the following:
a. Field measurements
b. Field construction criteria
c. Catalog numbers and similar data
d. Conformance with the Contract Documents
2. Provide each shop drawing, sample and product data submitted by the Contractor
with a Certification Statement affixed including:
a. The Contractor's Company name
b. Signature of submittal reviewer
c. Certification Statement
1) `By this submittal, I hereby represent that I have determined and verified
field measurements, field construction criteria, materials, dimensions,
catalog numbers and similar data and I have checked and coordinated each
item with other applicable approved shop drawings."
D. Submittal Format
1. Fold shop drawings larger than 8 '/2 inches x 11 inches to 8 '/2 inches x 11 inches.
2. Bind shop drawings and product data sheets together.
3. Order
a. Cover Sheet
1) Description of Packet
2) Contractor Certification
b. List of items / Table of Contents
c. Product Data /Shop Drawings/Samples /Calculations
E. Submittal Content
1. The date of submission and the dates of any previous submissions
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised August 30, 2013
013300-3
DAP SUBMITTALS
Page 3 of 8
2. The Project title and number
3. Contractor identification
4. The names of
a. Contractor
b. Supplier
c. Manufacturer
5. Identification of the product, with the Specification Section number, page and
paragraph(s)
6. Field dimensions, clearly identified as such
7. Relation to adjacent or critical features of the Work or materials
8. Applicable standards, such as ASTM or Federal Specification numbers
9. Identification by highlighting of deviations from Contract Documents
10. Identification by highlighting of revisions on resubmittals
11. An 8-inch x 3-inch blank space for Contractor and City stamps
F. Shop Drawings
1. As specified in individual Work Sections includes, but is not necessarily limited to:
a. Custom -prepared data such as fabrication and erection/installation (working)
drawings
b. Scheduled information
c. Setting diagrams
d. Actual shopwork manufacturing instructions
e. Custom templates
f. Special wiring diagrams
g. Coordination drawings
h. Individual system or equipment inspection and test reports including:
1) Performance curves and certifications
i. As applicable to the Work
2. Details
a. Relation of the various parts to the main members and lines of the structure
b. Where correct fabrication of the Work depends upon field measurements
1) Provide such measurements and note on the drawings prior to submitting
for approval.
G. Product Data
1. For submittals of product data for products included on the City's Standard Product
List, clearly identify each item selected for use on the Project.
2. For submittals of product data for products not included on the City's Standard
Product List, submittal data may include, but is not necessarily limited to:
a. Standard prepared data for manufactured products (sometimes referred to as
catalog data)
1) Such as the manufacturer's product specification and installation
instructions
2) Availability of colors and patterns
3) Manufacturer's printed statements of compliances and applicability
4) Roughing -in diagrams and templates
5) Catalog cuts
6) Product photographs
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised August 30, 2013
013300-4
DAP SUBMITTALS
Page 4 of 8
7) Standard wiring diagrams
8) Printed performance curves and operational -range diagrams
9) Production or quality control inspection and test reports and certifications
10) Mill reports
11) Product operating and maintenance instructions and recommended
spare -parts listing and printed product warranties
12) As applicable to the Work
H. Samples
As specified in individual Sections, include, but are not necessarily limited to:
a. Physical examples of the Work such as:
1) Sections of manufactured or fabricated Work
2) Small cuts or containers of materials
3) Complete units of repetitively used products color/texture/pattern swatches
and range sets
4) Specimens for coordination of visual effect
5) Graphic symbols and units of Work to be used by the City for independent
inspection and testing, as applicable to the Work
I. Do not start Work requiring a shop drawing, sample or product data nor any material to
be fabricated or installed prior to the approval or qualified approval of such item.
1. Fabrication performed, materials purchased or on -site construction accomplished
which does not conform to approved shop drawings and data is at the Contractor's
risk.
2. The City will not be liable for any expense or delay due to corrections or remedies
required to accomplish conformity.
3. Complete project Work, materials, fabrication, and installations in conformance
with approved shop drawings, applicable samples, and product data.
J. Submittal Distribution
Electronic Distribution
a. Confirm development of Project directory for electronic submittals to be
uploaded to City's Buzzsaw site, or another external FTP site approved by the
City.
b. Shop Drawings
1) Upload submittal to designated project directory and notify appropriate
City representatives via email of submittal posting.
2) Hard Copies
a) 3 copies for all submittals
b) If Contractor requires more than 1 hard copy of Shop Drawings
returned, Contractor shall submit more than the number of copies listed
above.
c. Product Data
1) Upload submittal to designated project directory and notify appropriate
City representatives via email of submittal posting.
2) Hard Copies
a) 3 copies for all submittals
d. Samples
1) Distributed to the Project Representative
2. Hard Copy Distribution (if required in lieu of electronic distribution)
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised August 30, 2013
013300-5
DAP SUBMITTALS
Page 5 of 8
a. Shop Drawings
1) Distributed to the City
2) Copies
a) 8 copies for mechanical submittals
b) 7 copies for all other submittals
c) If Contractor requires more than 3 copies of Shop Drawings returned,
Contractor shall submit more than the number of copies listed above.
b. Product Data
1) Distributed to the City
2) Copies
a) 4 copies
c. Samples
1) Distributed to the Project Representative
2) Copies
a) Submit the number stated in the respective Specification Sections.
Distribute reproductions of approved shop drawings and copies of approved
product data and samples, where required, to the job site file and elsewhere as
directed by the City.
a. Provide number of copies as directed by the City but not exceeding the number
previously specified.
K. Submittal Review
1. The review of shop drawings, data and samples will be for general conformance
with the design concept and Contract Documents. This is not to be construed as:
a. Permitting any departure from the Contract requirements
b. Relieving the Contractor of responsibility for any errors, including details,
dimensions, and materials
c. Approving departures from details furnished by the City, except as otherwise
provided herein
2. The review and approval of shop drawings, samples or product data by the City
does not relieve the Contractor from his/her responsibility with regard to the
fulfillment of the terms of the Contract.
a. All risks of error and omission are assumed by the Contractor, and the City will
have no responsibility therefore.
3. The Contractor remains responsible for details and accuracy, for coordinating the
Work with all other associated work and trades, for selecting fabrication processes,
for techniques of assembly and for performing Work in a safe manner.
4. If the shop drawings, data or samples as submitted describe variations and show a
departure from the Contract requirements which City finds to be in the interest of
the City and to be so minor as not to involve a change in Contract Price or time for
performance, the City may return the reviewed drawings without noting an
exception.
5. Submittals will be returned to the Contractor under 1 of the following codes:
a. Code 1
1) "NO EXCEPTIONS TAKEN" is assigned when there are no notations or
comments on the submittal.
a) When returned under this code the Contractor may release the
equipment and/or material for manufacture.
b. Code 2
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised August 30, 2013
013300-6
DAP SUBMITTALS
Page 6 of 8
1) "EXCEPTIONS NOTED". This code is assigned when a confirmation of
the notations and comments IS NOT required by the Contractor.
a) The Contractor may release the equipment or material for manufacture;
however, all notations and comments must be incorporated into the
final product.
c. Code 3
1) "EXCEPTIONS NOTED/RESUBMIT". This combination of codes is
assigned when notations and comments are extensive enough to require a
resubmittal of the package.
a) The Contractor may release the equipment or material for manufacture;
however, all notations and comments must be incorporated into the
final product.
b) This resubmittal is to address all comments, omissions and
non -conforming items that were noted.
c) Resubmittal is to be received by the City within 15 Calendar Days of
the date of the City's transmittal requiring the resubmittal.
d. Code 4
1) "NOT APPROVED" is assigned when the submittal does not meet the
intent of the Contract Documents.
a) The Contractor must resubmit the entire package revised to bring the
submittal into conformance.
b) It may be necessary to resubmit using a different manufacturer/vendor
to meet the Contract Documents.
6. Resubmittals
a. Handled in the same manner as first submittals
1) Corrections other than requested by the City
2) Marked with revision triangle or other similar method
a) At Contractor's risk if not marked
b. Submittals for each item will be reviewed no more than twice at the City's
expense.
1) All subsequent reviews will be performed at times convenient to the City
and at the Contractor's expense, based on the City's or City
Representative's then prevailing rates.
2) Provide Contractor reimbursement to the City within 30 Calendar Days for
all such fees invoiced by the City.
c. The need for more than 1 resubmission or any other delay in obtaining City's
review of submittals, will not entitle the Contractor to an extension of Contract
Time.
7. Partial Submittals
a. City reserves the right to not review submittals deemed partial, at the City's
discretion.
b. Submittals deemed by the City to be not complete will be returned to the
Contractor, and will be considered "Not Approved" until resubmitted.
c. The City may at its option provide a list or mark the submittal directing the
Contractor to the areas that are incomplete.
8. If the Contractor considers any correction indicated on the shop drawings to
constitute a change to the Contract Documents, then written notice must be
provided thereof to the Developer at least 7 Calendar Days prior to release for
manufacture.
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised August 30, 2013
013300-7
DAP SUBMITTALS
Page 7 of 8
9. When the shop drawings have been completed to the satisfaction of the City, the
Contractor may carry out the construction in accordance therewith and no further
changes therein except upon written instructions from the City.
10. Each submittal, appropriately coded, will be returned within 30 Calendar Days
following receipt of submittal by the City.
L. Mock ups
1. Mock Up units as specified in individual Sections, include, but are not necessarily
limited to, complete units of the standard of acceptance for that type of Work to be
used on the Project. Remove at the completion of the Work or when directed.
M. Qualifications
1. If specifically required in other Sections of these Specifications, submit a P.E.
Certification for each item required.
N. Request for Information (RFI)
1. Contractor Request for additional information
a. Clarification or interpretation of the contract documents
b. When the Contractor believes there is a conflict between Contract Documents
c. When the Contractor believes there is a conflict between the Drawings and
Specifications
1) Identify the conflict and request clarification
2. Sufficient information shall be attached to permit a written response without further
information.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised August 30, 2013
013300-8
DAP SUBMITTALS
Page 8 of 8
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
12/20/2012 D. Johnson 1.4.K.8. Working Days modified to Calendar Days
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised August 30, 2013
0135 13- 1
DAP SPECIAL PROJECT PROCEDURES
Page 1 of 7
1 SECTION 0135 13
2 SPECIAL PROJECT PROCEDURES
3 PART1- GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. The procedures for special project circumstances that includes, but is not limited to:
7 a. Coordination with the Texas Department of Transportation
8 b. Work near High Voltage Lines
9 c. Confined Space Entry Program
10 d. Air Pollution Watch Days
11 e. Use of Explosives, Drop Weight, Etc.
12 £ Water Department Notification
13 g. Public Notification Prior to Beginning Construction
14 h. Coordination with United States Army Corps of Engineers
15 i. Coordination within Railroad permits areas
16 j. Dust Control
17 k. Employee Parking
18 B. Deviations from this City of Fort Worth Standard Specification
19 1. None.
20 C. Related Specification Sections include, but are not necessarily limited to:
21 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
22 2. Division 1— General Requirements
23 3. Section 33 12 25 — Connection to Existing Water Mains
24
25 1.2 REFERENCES
26 A. Reference Standards
27 1. Reference standards cited in this Specification refer to the current reference
28 standard published at the time of the latest revision date logged at the end of this
29 Specification, unless a date is specifically cited.
30 2. Health and Safety Code, Title 9. Safety, Subtitle A. Public Safety, Chapter 752.
31 High Voltage Overhead Lines.
32 1.3 ADMINISTRATIVE REQUIREMENTS
33 A. Coordination with the Texas Department of Transportation
34 1. When work in the right-of-way which is under the jurisdiction of the Texas
35 Department of Transportation (TxDOT):
36 a. Notify the Texas Department of Transportation prior to commencing any work
37 therein in accordance with the provisions of the permit
38 b. All work performed in the TxDOT right-of-way shall be performed in
39 compliance with and subject to approval from the Texas Department of
40 Transportation
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised August, 30, 2013
013513-2
DAP SPECIAL PROJECT PROCEDURES
Page 2 of 7
I B. Work near High Voltage Lines
2 1. Regulatory Requirements
3 a. All Work near High Voltage Lines (more than 600 volts measured between
4 conductors or between a conductor and the ground) shall be in accordance with
5 Health and Safety Code, Title 9, Subtitle A, Chapter 752.
6 2. Warning sign
7 a. Provide sign of sufficient size meeting all OSHA requirements.
8 3. Equipment operating within 10 feet of high voltage lines will require the following
9 safety features
10 a. Insulating cage -type of guard about the boom or arm
11 b. Insulator links on the lift hook connections for back hoes or dippers
12 c. Equipment must meet the safety requirements as set forth by OSHA and the
13 safety requirements of the owner of the high voltage lines
14 4. Work within 6 feet of high voltage electric lines
15 a. Notification shall be given to:
16 1) The power company (example: ONCOR)
17 a) Maintain an accurate log of all such calls to power company and record
18 action taken in each case.
19 b. Coordination with power company
20 1) After notification coordinate with the power company to:
21 a) Erect temporary mechanical barriers, de -energize the lines, or raise or
22 lower the lines
23 c. No personnel may work within 6 feet of a high voltage line before the above
24 requirements have been met.
25 C. Confined Space Entry Program
26 1. Provide and follow approved Confined Space Entry Program in accordance with
27 OSHA requirements.
28 2. Confined Spaces include:
29 a. Manholes
30 b. All other confined spaces in accordance with OSHA's Permit Required for
31 Confined Spaces
32 D. Use of Explosives, Drop Weight, Etc.
33 1. When Contract Documents permit on the project the following will apply:
34 a. Public Notification
35 1) Submit notice to City and proof of adequate insurance coverage, 24 hours
36 prior to commencing.
37 2) Minimum 24 hour public notification in accordance with Section 0131 13
38 E. Water Department Coordination
39 1. During the construction of this project, it will be necessary to deactivate, for a
40 period of time, existing lines. The Contractor shall be required to coordinate with
41 the Water Department to determine the best times for deactivating and activating
42 those lines.
43 2. Coordinate any event that will require connecting to or the operation of an existing
44 City water line system with the City's representative.
45 a. Coordination shall be in accordance with Section 33 12 25.
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised August, 30, 2013
013513-3
DAP SPECIAL PROJECT PROCEDURES
Page 3 of 7
1 b. If needed, obtain a hydrant water meter from the Water Department for use
2 during the life of named project.
3 c. In the event that a water valve on an existing live system be turned off and on
4 to accommodate the construction of the project is required, coordinate this
5 activity through the appropriate City representative.
6 1) Do not operate water line valves of existing water system.
7 a) Failure to comply will render the Contractor in violation of Texas Penal
8 Code Title 7, Chapter 28.03 (Criminal Mischief) and the Contractor
9 will be prosecuted to the full extent of the law.
10 b) In addition, the Contractor will assume all liabilities and
11 responsibilities as a result of these actions.
12 F. Public Notification Prior to Beginning Construction
13 1. Prior to beginning construction on any block in the project, on a block by block
14 basis, prepare and deliver a notice or flyer of the pending construction to the front
15 door of each residence or business that will be impacted by construction. The notice
16 shall be prepared as follows:
17 a. Post notice or flyer 7 days prior to beginning any construction activity on each
18 block in the project area.
19 1) Prepare flyer on the Contractor's letterhead and include the following
20 information:
21 a) Name of Project
22 b) City Project No (CPN)
23 c) Scope of Project (i.e. type of construction activity)
24 d) Actual construction duration within the block
25 e) Name of the contractor's foreman and phone number
26 f) Name of the City's inspector and phone number
27 g) City's after-hours phone number
28 2) A sample of the `pre -construction notification' flyer is attached as Exhibit
29 A.
30 3) Submit schedule showing the construction start and finish time for each
31 block of the project to the inspector.
32 4) Deliver flyer to the City Inspector for review prior to distribution.
33 b. No construction will be allowed to begin on any block until the flyer is
34 delivered to all residents of the block.
35 G. Public Notification of Temporary Water Service Interruption during Construction
36 1. In the event it becomes necessary to temporarily shut down water service to
37 residents or businesses during construction, prepare and deliver a notice or flyer of
38 the pending interruption to the front door of each affected resident.
39 2. Prepared notice as follows:
40 a. The notification or flyer shall be posted 24 hours prior to the temporary
41 interruption.
42 b. Prepare flyer on the contractor's letterhead and include the following
43 information:
44 1) Name of the project
45 2) City Project Number
46 3) Date of the interruption of service
47 4) Period the interruption will take place
48 5) Name of the contractor's foreman and phone number
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised August, 30, 2013
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
01 35 13 - 4
DAP SPECIAL PROJECT PROCEDURES
Page 4 of 7
6) Name of the City's inspector and phone number
c. A sample of the temporary water service interruption notification is attached as
Exhibit B.
d. Deliver a copy of the temporary interruption notification to the City inspector
for review prior to being distributed.
e. No interruption of water service can occur until the flyer has been delivered to
all affected residents and businesses.
f. Electronic versions of the sample flyers can be obtained from the Project
Construction Inspector.
H. Coordination with United States Army Corps of Engineers (USACE)
1. At locations in the Project where construction activities occur in areas where
USACE permits are required, meet all requirements set forth in each designated
permit.
I. Coordination within Railroad Permit Areas
1. At locations in the project where construction activities occur in areas where
railroad permits are required, meet all requirements set forth in each designated
railroad permit. This includes, but is not limited to, provisions for:
a. Flagmen
b. Inspectors
c. Safety training
d. Additional insurance
e. Insurance certificates
f. Other employees required to protect the right-of-way and property of the
Railroad Company from damage arising out of and/or from the construction of
the project. Proper utility clearance procedures shall be used in accordance
with the permit guidelines.
2. Obtain any supplemental information needed to comply with the railroad's
requirements.
J. Dust Control
1. Use acceptable measures to control dust at the Site.
a. If water is used to control dust, capture and properly dispose of waste water.
b. If wet saw cutting is performed, capture and properly dispose of slurry.
K. Employee Parking
1. Provide parking for employees at locations approved by the City.
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised August, 30, 2013
013513-5
DAP SPECIAL PROJECT PROCEDURES
Page 5 of 7
1 1.4
SUBMITTALS [NOT USED]
2 1.5
ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
3 1.6
CLOSEOUT SUBMITTALS [NOT USED]
4 1.7
MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
5 1.8
QUALITY ASSURANCE [NOT USED]
6 1.9
DELIVERY, STORAGE, AND HANDLING [NOT USED]
7 1.10
FIELD [SITE] CONDITIONS [NOT USED]
8 1.11
WARRANTY [NOT USED]
9 PART 2 - PRODUCTS [NOT USED]
10 PART 3 - EXECUTION [NOT USED]
11
12
13
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
1.33 — Added requirement of compliance with Health and Safety Code, Title 9.
8/31/2012 D. Johnson Safety, Subtitle A. Public Safety, Chapter 752. High Voltage Overhead Lines.
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised August, 30, 2013
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
01 35 13 -6
DAP SPECIAL PROJECT PROCEDURES
Page 6 of 7
EXHIBIT A
(To be printed on Contractor's Letterhead)
Date:
CPN No.: 104255
Project Name: ACN Fossil Creek
Mapsco Location:
Limits of Construction:
THIS IS TO INFORM YOU THAT UNDER A CONTRACT WITH THE CITY OF FORT
WORTH, OUR COMPANY WILL WORK ON UTILITY LINES ON OR AROUND YOUR
PROPERTY.
CONSTRUCTION WILL BEGIN APPROXIMATELY SEVEN DAYS FROM THE DATE
OF THIS NOTICE.
IF YOU HAVE QUESTIONS ABOUT ACCESS, SECURITY, SAFETY OR ANY OTHER
ISSUE, PLEASE CALL:
Mr.
OR
AT
Mr. <CITY INSPECTOR> AT < TELEPHONE NO.>
AFTER 4:30 PM OR ON WEEKENDS, PLEASE CALL (817) 392 8306
PLEASE KEEP THIS FLYER HANDY WHEN YOU CALL
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised August, 30, 2013
2
Date:
EXHIBIT B
FORT WORTH
DOE NO. xxxx
Project Name:
013513-7
DAP SPECIAL PROJECT PROCEDURES
Page 7 of 7
NOTICE OF TEMPORARY WATER SERVICE
INTERRUPTION
DUE TO UTILITY IMPROVEMENTS IN YOUR NEIGHBORHOOD, YOUR
WATER SERVICE WILL BE INTERRUPTED ON
BETWEEN THE HOURS OF AND
IF YOU HAVE QUESTIONS ABOUT THIS SHUT -OUT, PLEASE CALL:
MR. AT
(CONTRACTORS SUPERINTENDENT) (TELEPHONE NUMBER)
OR
MR. AT
(CITY INSPECTOR) (TELEPHONE NUMBER)
THIS INCONVENIENCE WILL BE AS SHORT AS POSSIBLE.
THANK YOU,
3 --
4
,CONTRACTOR
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised August, 30, 2013
01 45 23
DAP TESTING AND INSPECTION SERVICES
Page 1 of 2
SECTION 0145 23
TESTING AND INSPECTION SERVICES
PART1- GENERAL
1.1 SUMMARY
A. Section Includes:
1. Testing and inspection services procedures and coordination
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 — General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
a. Contractor is responsible for performing, coordinating, and payment of all
Quality Control testing.
b. City is responsible for performing and payment for first set of Quality
Assurance testing.
1) If the first Quality Assurance test performed by the City fails, the
Contractor is responsible for payment of subsequent Quality Assurance
testing until a passing test occurs.
a) Final acceptance will not be issued by City until all required payments
for testing by Contractor have been paid in full.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Testing
1. Complete testing in accordance with the Contract Documents.
2. Coordination
a. When testing is required to be performed by the City, notify City, sufficiently
in advance, when testing is needed.
b. When testing is required to be completed by the Contractor, notify City,
sufficiently in advance, that testing will be performed.
3. Distribution of Testing Reports
a. Electronic Distribution
1) Confirm development of Project directory for electronic submittals to be
uploaded to the City's document management system, or another form of
distribution approved by the City.
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised March 20, 2020
01 45 23
DAP TESTING AND INSPECTION SERVICES
Page 2 of 2
2) Upload test reports to designated project directory and notify appropriate
City representatives via email of submittal posting.
3) Hard Copies
a) 1 copy for all submittals submitted to the Project Representative
b. Hard Copy Distribution (if required in lieu of electronic distribution)
1) Tests performed by City
a) Distribute 1 hard copy to the Contractor
2) Tests performed by the Contractor
a) Distribute 3 hard copies to City's Project Representative
4. Provide City's Project Representative with trip tickets for each delivered load of
Concrete or Lime material including the following information:
a. Name of pit
b. Date of delivery
c. Material delivered
B. Inspection
1. Inspection or lack of inspection does not relieve the Contractor from obligation to
perform work in accordance with the Contract Documents.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
03/20/2020 D.V. Magaiia Removed reference to Buzzsaw and noted that electronic submittals be uploaded
through the City's document management system.
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised March 20, 2020
015000-1
DAP TEMPORARY FACILITIES AND CONTROLS
Page 1 of 4
SECTION 0150 00
TEMPORARY FACILITIES AND CONTROLS
PART1- GENERAL
1.1 SUMMARY
A. Section Includes:
Provide temporary facilities and controls needed for the Work including, but not
necessarily limited to:
a. Temporary utilities
b. Sanitary facilities
c. Storage Sheds and Buildings
d. Dust control
e. Temporary fencing of the construction site
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 — General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Temporary Utilities
1. Obtaining Temporary Service
a. Make arrangements with utility service companies for temporary services.
b. Abide by rules and regulations of utility service companies or authorities
having jurisdiction.
c. Be responsible for utility service costs until Work is approved for Final
Acceptance.
1) Included are fuel, power, light, heat and other utility services necessary for
execution, completion, testing and initial operation of Work.
2. Water
a. Contractor to provide water required for and in connection with Work to be
performed and for specified tests of piping, equipment, devices or other use as
required for the completion of the Work.
b. Provide and maintain adequate supply of potable water for domestic
consumption by Contractor personnel and City's Project Representatives.
c. Coordination
1) Contact City 1 week before water for construction is desired
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised JULY 1, 2011
015000-2
DAP TEMPORARY FACILITIES AND CONTROLS
Page 2 of 4
d. Contractor Payment for Construction Water
1) Obtain construction water meter from City for payment as billed by City's
established rates.
3. Electricity and Lighting
a. Provide and pay for electric powered service as required for Work, including
testing of Work.
1) Provide power for lighting, operation of equipment, or other use.
b. Electric power service includes temporary power service or generator to
maintain operations during scheduled shutdown.
4. Telephone
a. Provide emergency telephone service at Site for use by Contractor personnel
and others performing work or furnishing services at Site.
5. Temporary Heat and Ventilation
a. Provide temporary heat as necessary for protection or completion of Work.
b. Provide temporary heat and ventilation to assure safe working conditions.
B. Sanitary Facilities
1. Provide and maintain sanitary facilities for persons on Site.
a. Comply with regulations of State and local departments of health.
2. Enforce use of sanitary facilities by construction personnel at job site.
a. Enclose and anchor sanitary facilities.
b. No discharge will be allowed from these facilities.
c. Collect and store sewage and waste so as not to cause nuisance or health
problem.
d. Haul sewage and waste off -site at no less than weekly intervals and properly
dispose in accordance with applicable regulation.
3. Locate facilities near Work Site and keep clean and maintained throughout Project.
4. Remove facilities at completion of Project
C. Storage Sheds and Buildings
1. Provide adequately ventilated, watertight, weatherproof storage facilities with floor
above ground level for materials and equipment susceptible to weather damage.
2. Storage of materials not susceptible to weather damage may be on blocks off
ground.
3. Store materials in a neat and orderly manner.
a. Place materials and equipment to permit easy access for identification,
inspection and inventory.
4. Equip building with lockable doors and lighting, and provide electrical service for
equipment space heaters and heating or ventilation as necessary to provide storage
environments acceptable to specified manufacturers.
5. Fill and grade site for temporary structures to provide drainage away from
temporary and existing buildings.
6. Remove building from site prior to Final Acceptance.
D. Temporary Fencing
Provide and maintain for the duration or construction when required in contract
documents
E. Dust Control
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised JULY 1, 2011
015000-3
DAP TEMPORARY FACILITIES AND CONTROLS
Page 3 of 4
1. Contractor is responsible for maintaining dust control through the duration of the
project.
a. Contractor remains on -call at all times
b. Must respond in a timely manner
F. Temporary Protection of Construction
1. Contractor or subcontractors are responsible for protecting Work from damage due
to weather.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
3.1 INSTALLERS [NOT USED]
3.2 EXAMINATION [NOT USED]
3.3 PREPARATION [NOT USED]
3.4 INSTALLATION
A. Temporary Facilities
1. Maintain all temporary facilities for duration of construction activities as needed.
3.5 [REPAIR] / [RESTORATION]
3.6 RE -INSTALLATION
3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED]
3.8 SYSTEM STARTUP [NOT USED]
3.9 ADJUSTING [NOT USED]
3.10 CLEANING [NOT USED]
3.11 CLOSEOUT ACTIVITIES
A. Temporary Facilities
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised JULY 1, 2011
015000-4
DAP TEMPORARY FACILITIES AND CONTROLS
Page 4 of 4
1. Remove all temporary facilities and restore area after completion of the Work, to a
condition equal to or better than prior to start of Work.
3.12 PROTECTION [NOT USED]
3.13 MAINTENANCE [NOT USED]
3.14 ATTACHMENTS [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised JULY 1, 2011
015526-1
DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
Page 1 of 3
SECTION 0155 26
STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
PART1- GENERAL
1.1 SUMMARY
A. Section Includes:
1. Administrative procedures for:
a. Street Use Permit
b. Modification of approved traffic control
c. Removal of Street Signs
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 — General Requirements
3. Section 34 71 13 — Traffic Control
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES
A. Reference Standards
1. Reference standards cited in this specification refer to the current reference standard
published at the time of the latest revision date logged at the end of this
specification, unless a date is specifically cited.
2. Texas Manual on Uniform Traffic Control Devices (TMUTCD).
1.4 ADMINISTRATIVE REQUIREMENTS
A. Traffic Control
1. General
a. When traffic control plans are included in the Drawings, provide Traffic
Control in accordance with Drawings and Section 34 71 13.
b. When traffic control plans are not included in the Drawings, prepare traffic
control plans in accordance with Section 34 71 13 and submit to City for
review.
1) Allow minimum 10 working days for review of proposed Traffic Control.
B. Street Use Permit
1. Prior to installation of Traffic Control, a City Street Use Permit is required.
a. To obtain Street Use Permit, submit Traffic Control Plans to City
Transportation and Public Works Department.
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised July 1, 2011
015526-2
DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
Page 2 of 3
1) Allow a minimum of 5 working days for permit review.
2) Contractor's responsibility to coordinate review of Traffic Control plans for
Street Use Permit, such that construction is not delayed.
C. Modification to Approved Traffic Control
Prior to installation traffic control:
a. Submit revised traffic control plans to City Department Transportation and
Public Works Department.
1) Revise Traffic Control plans in accordance with Section 34 71 13.
2) Allow minimum 5 working days for review of revised Traffic Control.
3) It is the Contractor's responsibility to coordinate review of Traffic Control
plans for Street Use Permit, such that construction is not delayed.
D. Removal of Street Sign
1. If it is determined that a street sign must be removed for construction, then contact
City Transportation and Public Works Department, Signs and Markings Division to
remove the sign.
E. Temporary Signage
1. In the case of regulatory signs, replace permanent sign with temporary sign meeting
requirements of the latest edition of the Texas Manual on Uniform Traffic Control
Devices (MUTCD).
2. Install temporary sign before the removal of permanent sign.
3. When construction is complete, to the extent that the permanent sign can be
reinstalled, contact the City Transportation and Public Works Department, Signs
and Markings Division, to reinstall the permanent sign.
F. Traffic Control Standards
1. Traffic Control Standards can be found on the City's Buzzsaw website.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised July 1, 2011
015526-3
DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
Page 3 of 3
Revision Log
DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised July 1, 2011
015713-1
DAP STORM WATER POLLUTION PREVENTION
Page 1 of 3
SECTION 01 5713
STORM WATER POLLUTION PREVENTION
PART1- GENERAL
1.1 SUMMARY
A. Section Includes:
1. Procedures for Storm Water Pollution Prevention Plans
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the
Contract
2. Division 1 — General Requirements
3. Section 3125 00 — Erosion and Sediment Control
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Construction Activities resulting in less than 1 acre of disturbance
a. Work associated with this Item is considered subsidiary to the various Items
bid. No separate payment will be allowed for this Item.
2. Construction Activities resulting in greater than 1 acre of disturbance
a. Measurement and Payment shall be in accordance with Section 3125 00.
1.3 REFERENCES
A. Abbreviations and Acronyms
1. Notice of Intent: NOI
2. Notice of Termination: NOT
3. Storm Water Pollution Prevention Plan: SWPPP
4. Texas Commission on Environmental Quality: TCEQ
5. Notice of Change: NOC
A. Reference Standards
1. Reference standards cited in this Specification refer to the current reference
standard published at the time of the latest revision date logged at the end of this
Specification, unless a date is specifically cited.
2. Integrated Storm Management (iSWM) Technical Manual for Construction
Controls
1.4 ADMINISTRATIVE REQUIREMENTS
A. General
1. Contractor is responsible for resolution and payment of any fines issued associated
with compliance to Stormwater Pollution Prevention Plan.
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised July 1, 2011
01 57 13 - 2
DAP STORM WATER POLLUTION PREVENTION
Page 2 of 3
B. Construction Activities resulting in:
1. Less than 1 acre of disturbance
a. Provide erosion and sediment control in accordance with Section 3125 00 and
Drawings.
2. 1 to less than 5 acres of disturbance
a. Texas Pollutant Discharge Elimination System (TPDES) General Construction
Permit is required
b. Complete SWPPP in accordance with TCEQ requirements
1) TCEQ Small Construction Site Notice Required under general permit
TXR150000
a) Sign and post at job site
b) Prior to Preconstruction Meeting, send 1 copy to City Department of
Transportation and Public Works, Environmental Division, (817) 392-
6088.
2) Provide erosion and sediment control in accordance with:
a) Section 3125 00
b) The Drawings
c) TXR150000 General Permit
d) SWPPP
e) TCEQ requirements
5 acres or more of Disturbance
a. Texas Pollutant Discharge Elimination System (TPDES) General Construction
Permit is required
b. Complete SWPPP in accordance with TCEQ requirements
1) Prepare a TCEQ NOI form and submit to TCEQ along with required fee
a) Sign and post at job site
b) Send copy to City Department of Transportation and Public Works,
Environmental Division, (817) 392-6088.
2) TCEQ Notice of Change required if making changes or updates to NOI
3) Provide erosion and sediment control in accordance with:
a) Section 3125 00
b) The Drawings
c) TXR150000 General Permit
d) SWPPP
e) TCEQ requirements
4) Once the project has been completed and all the closeout requirements of
TCEQ have been met a TCEQ Notice of Termination can be submitted.
a) Send copy to City Department of Transportation and Public Works,
Environmental Division, (817) 392-6088.
1.5 SUBMITTALS
A. SWPPP
Submit in accordance with Section 0133 00, except as stated herein.
a. Prior to the Preconstruction Meeting, submit a draft copy of SWPPP to the City
as follows:
1) 1 copy to the City Project Manager
a) City Project Manager will forward to the City Department of
Transportation and Public Works, Environmental Division for review
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised July 1, 2011
0157 13 -3
DAP STORM WATER POLLUTION PREVENTION
Page 3 of 3
B. Modified SWPPP
1. If the SWPPP is revised during construction, resubmit modified SWPPP to the City
in accordance with Section 0133 00.
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised July 1, 2011
SECTION 0160 00
PRODUCT REQUIREMENTS
PART1- GENERAL
1.1 SUMMARY
A. Section Includes:
01 60 00
DAP PRODUCT REQUIREMENTS
Page 1 of 2
1. References for Product Requirements and City Standard Products List
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 — General Requirements
1.2 PRICE AND PAYMENT PROCEDURES [NOT USED]
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A list of City approved products for use is available through the City's website at:
httiDs:Hapes.fortworthtexas.2ov/ProiectResources/ and following the directory
path: 02 - Construction Documents\Standard Products List
A. Only products specifically included on City's Standard Product List in these Contract
Documents shall be allowed for use on the Project.
1. Any subsequently approved products will only be allowed for use upon specific
approval by the City.
B. Any specific product requirements in the Contract Documents supersede similar
products included on the City's Standard Product List.
1. The City reserves the right to not allow products to be used for certain projects even
though the product is listed on the City's Standard Product List.
C. Although a specific product is included on City's Standard Product List, not all
products from that manufacturer are approved for use, including but not limited to, that
manufacturer's standard product.
D. See Section 0133 00 for submittal requirements of Product Data included on City's
Standard Product List.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised March 20, 2020
01 60 00
DAP PRODUCT REQUIREMENTS
Page 2 of 2
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
10/12/12 D. Johnson Modified Location of City's Standard Product List
4/7/2014 M.Domenech Revised for DAP application
03/20/2020 D.V. Magaiia Removed reference to Buzzsaw and noted that the City approved products list is
accessible through the City's website.
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised March 20, 2020
016600-1
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 1 of 4
SECTION 0166 00
PRODUCT STORAGE AND HANDLING REQUIREMENTS
PART1- GENERAL
1.1 SUMMARY
A. Section Includes:
1. Scheduling of product delivery
2. Packaging of products for delivery
3. Protection of products against damage from:
a. Handling
b. Exposure to elements or harsh environments
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 — General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY AND HANDLING
A. Delivery Requirements
1. Schedule delivery of products or equipment as required to allow timely installation
and to avoid prolonged storage.
2. Provide appropriate personnel and equipment to receive deliveries.
3. Delivery trucks will not be permitted to wait extended periods of time on the Site
for personnel or equipment to receive the delivery.
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised April 7, 2014
016600-2
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 2 of 4
4. Deliver products or equipment in manufacturer's original unbroken cartons or other
containers designed and constructed to protect the contents from physical or
environmental damage.
5. Clearly and fully mark and identify as to manufacturer, item and installation
location.
6. Provide manufacturer's instructions for storage and handling.
B. Handling Requirements
1. Handle products or equipment in accordance with these Contract Documents and
manufacturer's recommendations and instructions.
C. Storage Requirements
1. Store materials in accordance with manufacturer's recommendations and
requirements of these Specifications.
2. Make necessary provisions for safe storage of materials and equipment.
a. Place loose soil materials and materials to be incorporated into Work to prevent
damage to any part of Work or existing facilities and to maintain free access at
all times to all parts of Work and to utility service company installations in
vicinity of Work.
3. Keep materials and equipment neatly and compactly stored in locations that will
cause minimum inconvenience to other contractors, public travel, adjoining owners,
tenants and occupants.
a. Arrange storage to provide easy access for inspection.
4. Restrict storage to areas available on construction site for storage of material and
equipment as shown on Drawings, or approved by City's Project Representative.
5. Provide off -site storage and protection when on -site storage is not adequate.
a. Provide addresses of and access to off -site storage locations for inspection by
City's Project Representative.
6. Do not use lawns, grass plots or other private property for storage purposes without
written permission of owner or other person in possession or control of premises.
7. Store in manufacturers' unopened containers.
8. Neatly, safely and compactly stack materials delivered and stored along line of
Work to avoid inconvenience and damage to property owners and general public
and maintain at least 3 feet from fire hydrant.
9. Keep public and private driveways and street crossings open.
10. Repair or replace damaged lawns, sidewalks, streets or other improvements to
satisfaction of City's Project Representative.
a. Total length which materials may be distributed along route of construction at
one time is 1,000 linear feet, unless otherwise approved in writing by City's
Project Representative.
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised April 7, 2014
016600-3
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 3 of 4
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION
3.1 INSTALLERS [NOT USED]
3.2 EXAMINATION [NOT USED]
3.3 PREPARATION [NOT USED]
3.4 ERECTION [NOT USED]
3.5 REPAIR / RESTORATION [NOT USED]
3.6 RE -INSTALLATION [NOT USED]
3.7 FIELD [OR] SITE QUALITY CONTROL
A. Tests and Inspections
1. Inspect all products or equipment delivered to the site prior to unloading.
B. Non -Conforming Work
1. Reject all products or equipment that are damaged, used or in any other way
unsatisfactory for use on the project.
3.8 SYSTEM STARTUP [NOT USED]
3.9 ADJUSTING [NOT USED]
3.10 CLEANING [NOT USED]
3.11 CLOSEOUT ACTIVITIES [NOT USED]
3.12 PROTECTION
A. Protect all products or equipment in accordance with manufacturer's written directions.
B. Store products or equipment in location to avoid physical damage to items while in
storage.
C. Protect equipment from exposure to elements and keep thoroughly dry if required by
the manufacturer.
3.13 MAINTENANCE [NOT USED]
3.14 ATTACHMENTS [NOT USED]
END OF SECTION
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised April 7, 2014
016600-4
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 4 of 4
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP application
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised April 7, 2014
017000-1
DAP MOBILIZATION AND REMOBILIZATION
Page 1 of 4
SECTION 0170 00
MOBILIZATION AND REMOBILIZATION
PART1- GENERAL
1.1 SUMMARY
A. Section Includes:
1. Mobilization and Demobilization
a. Mobilization
1) Transportation of Contractor's personnel, equipment, and operating supplies
to the Site
2) Establishment of necessary general facilities for the Contractor's operation
at the Site
3) Premiums paid for performance and payment bonds
4) Transportation of Contractor's personnel, equipment, and operating supplies
to another location within the designated Site
5) Relocation of necessary general facilities for the Contractor's operation
from 1 location to another location on the Site.
b. Demobilization
1) Transportation of Contractor's personnel, equipment, and operating supplies
away from the Site including disassembly
2) Site Clean-up
3) Removal of all buildings and/or other facilities assembled at the Site for this
Contract
c. Mobilization and Demobilization do not include activities for specific items of
work that are for which payment is provided elsewhere in the contract.
2. Remobilization
a. Remobilization for Suspension of Work specifically required in the Contract
Documents or as required by City includes:
1) Demobilization
a) Transportation of Contractor's personnel, equipment, and operating
supplies from the Site including disassembly or temporarily securing
equipment, supplies, and other facilities as designated by the Contract
Documents necessary to suspend the Work.
b) Site Clean-up as designated in the Contract Documents
2) Remobilization
a) Transportation of Contractor's personnel, equipment, and operating
supplies to the Site necessary to resume the Work.
b) Establishment of necessary general facilities for the Contractor's
operation at the Site necessary to resume the Work.
3) No Payments will be made for:
a) Mobilization and Demobilization from one location to another on the
Site in the normal progress of performing the Work.
b) Stand-by or idle time
c) Lost profits
3. Mobilizations and Demobilization for Miscellaneous Projects
a. Mobilization and Demobilization
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised April 7, 2014
017000-2
DAP MOBILIZATION AND REMOBILIZATION
Page 2 of 4
1) Mobilization shall consist of the activities and cost on a Work Order basis
necessary for:
a) Transportation of Contractor's personnel, equipment, and operating
supplies to the Site for the issued Work Order.
b) Establishment of necessary general facilities for the Contractor's
operation at the Site for the issued Work Order
2) Demobilization shall consist of the activities and cost necessary for:
a) Transportation of Contractor's personnel, equipment, and operating
supplies from the Site including disassembly for each issued Work
Order
b) Site Clean-up for each issued Work Order
c) Removal of all buildings or other facilities assembled at the Site for
each Work Oder
b. Mobilization and Demobilization do not include activities for specific items of
work for which payment is provided elsewhere in the contract.
4. Emergency Mobilizations and Demobilization for Miscellaneous Projects
a. A Mobilization for Miscellaneous Projects when directed by the City and the
mobilization occurs within 24 hours of the issuance of the Work Order.
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 — General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Mobilization and Demobilization
a. Measure
1) This Item is considered subsidiary to the various Items bid.
b. Payment
1) The work performed and materials furnished in accordance with this Item
are subsidiary to the various Items bid and no other compensation will be
allowed.
2. Remobilization for suspension of Work as specifically required in the Contract
Documents
a. Measurement
1) Measurement for this Item shall be per each remobilization performed.
b. Payment
1) The work performed and materials furnished in accordance with this Item
and measured as provided under "Measurement" will be paid for at the unit
price per each "Specified Remobilization" in accordance with Contract
Documents.
c. The price shall include:
1) Demobilization as described in Section 1.1.A.2.a.1)
2) Remobilization as described in Section 1.1.A.2.a.2)
d. No payments will be made for standby, idle time, or lost profits associated this
Item.
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised April 7, 2014
017000-3
DAP MOBILIZATION AND REMOBILIZATION
Page 3 of 4
Remobilization for suspension of Work as required by City
a. Measurement and Payment
1) This shall be submitted as a Contract Claim in accordance with Article 10
of Section 00 72 00.
2) No payments will be made for standby, idle time, or lost profits associated
with this Item.
4. Mobilizations and Demobilizations for Miscellaneous Projects
a. Measurement
1) Measurement for this Item shall be for each Mobilization and
Demobilization required by the Contract Documents
b. Payment
1) The Work performed and materials furnished in accordance with this Item
and measured as provided under "Measurement" will be paid for at the unit
price per each "Work Order Mobilization" in accordance with Contract
Documents. Demobilization shall be considered subsidiary to mobilization
and shall not be paid for separately.
c. The price shall include:
1) Mobilization as described in Section 1.1.A.3.a.1)
2) Demobilization as described in Section 1.1.A.3.a.2)
d. No payments will be made for standby, idle time, or lost profits associated this
Item.
Emergency Mobilizations and Demobilizations for Miscellaneous Projects
a. Measurement
1) Measurement for this Item shall be for each Mobilization and
Demobilization required by the Contract Documents
b. Payment
1) The Work performed and materials furnished in accordance with this Item
and measured as provided under "Measurement" will be paid for at the unit
price per each "Work Order Emergency Mobilization" in accordance with
Contract Documents. Demobilization shall be considered subsidiary to
mobilization and shall not be paid for separately.
c. The price shall include
1) Mobilization as described in Section 1.1.A.4.a)
2) Demobilization as described in Section 1.1.A.3.a.2)
d. No payments will be made for standby, idle time, or lost profits associated this
Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]
1.5 SUBMITTALS [NOT USED]
1.6 INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised April 7, 2014
017000-4
DAP MOBILIZATION AND REMOBILIZATION
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
U7V110
4/7/2014
I►/\►yjI�l
M.Domenech
END OF SECTION
Revision Log
SUMMARY OF CHANGE
Revised for DAP application
Page 4 of 4
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised April 7, 2014
017123-1
CONSTRUCTION STAKING AND SURVEY
Page 1 of 7
1 SECTION 01 71 23
2 CONSTRUCTION STAKING AND SURVEY
3 PART1- GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Requirements for construction staking and construction survey
7 B. Deviations from this City of Fort Worth Standard Specification
8 1. See Changes (Highlighted in Yellow).
9 C. Related Specification Sections include, but are not necessarily limited to:
10 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
11 2. Division 1 — General Requirements
12 1.2 PRICE AND PAYMENT PROCEDURES
13 A. Measurement and Payment
14 1. Construction Staking
15 a. Measurement
16 1) This Item is considered subsidiary to the various Items bid.
17 b. Payment
18 1) The work performed and the materials furnished in accordance with this
19 Item are subsidiary to the various Items bid and no other compensation will
20 be allowed.
21 2. Construction Survey
22 a. Measurement
23 1) This Item is considered subsidiary to the various Items bid.
24 b. Payment
25 1) The work performed and the materials furnished in accordance with this
26 Item are subsidiary to the various Items bid and no other compensation will be
27 allowed.
28 3. As -Built Survey
29 a. Measurement
30 1) This Item is considered subsidiary to the various Items bid.
31 b. Payment
32 1) The work performed and the materials furnished in accordance with this
33 Item are subsidiary to the various Items bid and no other compensation will be
34 allowed.
35 1.3 REFERENCES
36 A. Definitions
37 1. Construction Survev - The survey measurements made prior to or while
38 construction is in progress to control elevation, horizontal position, dimensions and
39 configuration of structures/improvements included in the Project Drawings.
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised February 14, 2018
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
017123-2
CONSTRUCTION STAKING AND SURVEY
Page 2 of 7
2. As -built Survev —The measurements made after the construction of the
improvement features are complete to provide position coordinates for the features
of a project.
3. Construction Staking — The placement of stakes and markings to provide offsets
and elevations to cut and fill in order to locate on the ground the designed
structures/improvements included in the Project Drawings. Construction staking
shall include staking easements and/or right of way if indicated on the plans.
4. Survev "Field Checks" — Measurements made after construction staking is
completed and before construction work begins to ensure that structures marked on
the ground are accurately located per Project Drawings.
B. Technical References
1. City of Fort Worth — Construction Staking Standards (available on City's Buzzsaw
website) — 01 71 23.16.01— Attachment A Survey Staking Standards
2. City of Fort Worth - Standard Survey Data Collector Library (fxl) files (available
on City's Buzzsaw website).
3. Texas Department of Transportation (TxDOT) Survey Manual, latest revision
4. Texas Society of Professional Land Surveyors (TSPS), Manual of Practice for Land
Surveying in the State of Texas, Category 5
20 1.4 ADMINISTRATIVE REQUIREMENTS
21 A. The Contractor's selection of a surveyor must comply with Texas Government
22 Code 2254 (qualifications based selection) for this project.
23 1.5 SUBMITTALS
24 A. Submittals, if required, shall be in accordance with Section 0133 00.
25 B. All submittals shall be received and reviewed by the City prior to delivery of work.
26 1.6 ACTION SUBMITTALSANFORMATIONAL SUBMITTALS
27 A. Field Quality Control Submittals
28 1. Documentation verifying accuracy of field engineering work, including coordinate
29 conversions if plans do not indicate grid or ground coordinates.
30 2. Submit "Cut -Sheets" conforming to the standard template provided by the City
31 (refer to 01 71 23.16.01 — Attachment A — Survey Staking Standards).
32 1.7 CLOSEOUT SUBMITTALS
33 B. As -built Redline Drawing Submittal
34 1. Submit As -Built Survey Redline Drawings documenting the locations/elevations of
35 constructed improvements signed and sealed by Registered Professional Land
36 Surveyor (RPLS) responsible for the work (refer to 01 71 23.16.01 — Attachment A
37 — Survey Staking Standards) .
38 2. Contractor shall submit the proposed as -built and completed redline drawing
39 submittal one (1) week prior to scheduling the project final inspection for City
40 review and comment. Revisions, if necessary, shall be made to the as -built redline
41 drawings and resubmitted to the City prior to scheduling the construction final
42 inspection.
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised February 14, 2018
017123-3
CONSTRUCTION STAKING AND SURVEY
Page 3 of 7
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
2 1.9 QUALITY ASSURANCE
3 A. Construction Staking
4 1. Construction staking will be performed by the Contractor.
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
2. Coordination
a. Contact City and Developer's Project Representative at least one week in
advance notifying the City of when Construction Staking is scheduled.
b. It is the Contractor's responsibility to coordinate staking such that
construction activities are not delayed or negatively impacted.
3. General
a. Contractor is responsible for preserving and maintaining stakes. If
Developer's Project Representative is required to re -stake for any reason, the
Contractor will be responsible for costs to perform staking. If in the opinion of
the City, a sufficient number of stakes or markings have been lost, destroyed
disturbed or omitted that the contracted Work cannot take place then the
Contractor will be required to stake or re -stake the deficient areas.
B. Construction Survey
1. Construction Survey will be performed by the Contractor.
2. Coordination
a. Contractor to verify that horizontal and vertical control data established in the
design survey and required for construction survey is available and in place.
3. General
a. Construction survey will be performed in order to construct the work shown
on the Construction Drawings and specified in the Contract Documents.
b. For construction methods other than open cut, the Contractor shall perform
construction survey and verify control data including, but not limited to, the
following:
1) Verification that established benchmarks and control are accurate.
2) Use of Benchmarks to furnish and maintain all reference lines and grades
for tunneling.
3) Use of line and grades to establish the location of the pipe.
4) Submit to the City copies of field notes used to establish all lines and
grades, if requested, and allow the City to check guidance system setup prior
to beginning each tunneling drive.
5) Provide access for the City, if requested, to verify the guidance system and
the line and grade of the carrier pipe.
6) The Contractor remains fully responsible for the accuracy of the work and
correction of it, as required.
7) Monitor line and grade continuously during construction.
8) Record deviation with respect to design line and grade once at each pipe
joint and submit daily records to the City.
9) If the installation does not meet the specified tolerances (as outlined in
Sections 33 05 23 and/or 33 05 24), immediately notify the City and correct
the installation in accordance with the Contract Documents.
C. As -Built Survey
1. Required As -Built Survey will be performed by the Contractor.
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised February 14, 2018
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
01 71 23 - 4
CONSTRUCTION STAKING AND SURVEY
Page 4 of 7
2. Coordination
a. Contractor is to coordinate with City to confirm which features require as -
built surveying.
b. It is the Contractor's responsibility to coordinate the as -built survey and
required measurements for items that are to be buried such that construction
activities are not delayed or negatively impacted.
c. For sewer mains and water mains 12" and under in diameter, it is acceptable
to physically measure depth and mark the location during the progress of
construction and take as -built survey after the facility has been buried. The
Contractor is responsible for the quality control needed to ensure accuracy.
3. General
a. The Contractor shall provide as -built survey including the elevation and
location (and provide written documentation to the City) of construction
features during the progress of the construction including the following:
1) Water Lines
a) Top of pipe elevations and coordinates for waterlines at the following
locations:
(1) Minimum every 25O linear feet, including
(2) Horizontal and vertical points of inflection, curvature,
etc.
(3) Fire line tee
(4) Plugs, stub -outs, dead-end lines
(5) Casing pipe (each end) and all buried fittings
2) Sanitary Sewer
a) Top of pipe elevations and coordinates for force mains and siphon
sanitary sewer lines (non -gravity facilities) at the following locations:
(1) Minimum every 25O linear feet and any buried fittings
(2) Horizontal and vertical points of inflection, curvature,
etc.
3) Stormwater — Not Applicable
b. The Contractor shall provide as -built survey including the elevation and
location (and provide written documentation to the City) of construction
features after the construction is completed including the following:
1) Manholes
a) Rim and flowline elevations and coordinates for each manhole
2) Water Lines
a) Cathodic protection test stations
b) Sampling stations
c) Meter boxes/vaults (All sizes)
d) Fire hydrants
e) Valves (gate, butterfly, etc.)
f) Air Release valves (Manhole rim and vent pipe)
g) Blow off valves (Manhole rim and valve lid)
h) Pressure plane valves
i) Underground Vaults
(1) Rim and flowline elevations and coordinates for each
Underground Vault.
3) Sanitary Sewer
a) Cleanouts
(1) Rim and flowline elevations and coordinates for each
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised February 14, 2018
017123-5
CONSTRUCTION STAKING AND SURVEY
Page 5 of 7
1 b) Manholes and Junction Structures
2 (1) Rim and flowline elevations and coordinates for each
3 manhole and junction structure.
4 4) Stormwater — Not Applicable
5 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
6 1.11 FIELD [SITE] CONDITIONS [NOT USED]
7 1.12 WARRANTY
8 PART2- PRODUCTS
9
A. A construction survey will produce, but will not be limited to:
10
1.
Recovery of relevant control points, points of curvature and points of intersection.
11
2.
Establish temporary horizontal and vertical control elevations (benchmarks)
12
sufficiently permanent and located in a manner to be used throughout construction.
13
3.
The location of planned facilities, easements and improvements.
14
a. Establishing final line and grade stakes for piers, floors, grade beams, parking
15
areas, utilities, streets, highways, tunnels, and other construction.
16
b. A record of revisions or corrections noted in an orderly manner for reference.
17
c. A drawing, when required by the client, indicating the horizontal and vertical
18
location of facilities, easements and improvements, as built.
19
4.
Cut sheets shall be provided to the City inspector and Survey Superintendent for all
20
construction staking projects. These cut sheets shall be on the standard city template
21
which can be obtained from the Survey Superintendent (817-392-7925).
22
5.
Digital survey files in the following formats shall be acceptable:
23
a. AutoCAD (.dwg)
24
b. ESRI Shapefile (.shp)
25
c. CSV file (.csv), formatted with X and Y coordinates in separate columns (use
26
standard templates, if available)
27
6.
Survey files shall include vertical and horizontal data tied to original project
28
control and benchmarks, and shall include feature descriptions
29 PART 3 - EXECUTION
30 3.1 INSTALLERS
31 A. Tolerances:
32 1. The staked location of any improvement or facility should be as accurate as
33 practical and necessary. The degree of precision required is dependent on many
34 factors all of which must remain judgmental. The tolerances listed hereafter are
35 based on generalities and, under certain circumstances, shall yield to specific
36 requirements. The surveyor shall assess any situation by review of the overall plans
37 and through consultation with responsible parties as to the need for specific
38 tolerances.
39 a. Earthwork: Grades for earthwork or rough cut should not exceed 0.1 ft. vertical
40 tolerance. Horizontal alignment for earthwork and rough cut should not exceed
41 1.0 ft. tolerance.
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised February 14, 2018
017123-6
CONSTRUCTION STAKING AND SURVEY
Page 6 of 7
1
b. Horizontal alignment on a structure shall be within .0.1 ft tolerance.
2
c. Paving or concrete for streets, curbs, gutters, parking areas, drives, alleys and
3
walkways shall be located within the confines of the site boundaries and,
4
occasionally, along a boundary or any other restrictive line. Away from any
5
restrictive line, these facilities should be staked with an accuracy producing no
6
more than 0.05ft. tolerance from their specified locations.
7
d. Underground and overhead utilities, such as sewers, gas, water, telephone and
8
electric lines, shall be located horizontally within their prescribed areas or
9
easements. Within assigned areas, these utilities should be staked with an
10
accuracy producing no more than 0.1 ft tolerance from a specified location.
11
e. The accuracy required for the vertical location of utilities varies widely. Many
12
underground utilities require only a minimum cover and a tolerance of 0.1 ft.
13
should be maintained. Underground and overhead utilities on planned profile,
14
but not depending on gravity flow for performance, should not exceed 0.1 ft.
15
tolerance.
16 B. Surveying instruments shall be kept in close adjustment according to manufacturer's
17 specifications or in compliance to standards. The City reserves the right to request a
18 calibration report at any time and recommends regular maintenance schedule be
19 performed by a certified technician every 6 months.
20 1. Field measurements of angles and distances shall be done in such fashion as to
21 satisfy the closures and tolerances expressed in Part 3.1.A.
22 2. Vertical locations shall be established from a pre -established benchmark and
23 checked by closing to a different bench mark on the same datum.
24 3. Construction survey field work shall correspond to the client's plans. Irregularities
25 or conflicts found shall be reported promptly to the City.
26 4. Revisions, corrections and other pertinent data shall be logged for future reference.
27
28 3.2 EXAMINATION [NOT USED]
29 3.3 PREPARATION [NOT USED]
30 3.4 APPLICATION
31 3.5 REPAIR / RESTORATION
32 A. If the Contractor's work damages or destroys one or more of the control
33 monuments/points set by the Developer's Project Representative, the monuments shall be
34 adequately referenced for expedient restoration.
35 1. Notify City or Developer's Project Representative if any control data needs to be
36 restored or replaced due to damage caused during construction operations.
37 a. Contractor shall perform replacements and/or restorations.
38 b. The City or Developer's Project Representative may require at anytime a
39 survey "Field Check" of any monument or benchmarks that are set be verified
40 by the Developer's Project Representative before further associated work can
41 move forward.
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised February 14, 2018
017123-7
CONSTRUCTION STAKING AND SURVEY
Page 7 of 7
1 3.6 RE -INSTALLATION [NOT USED]
2 3.7 FIELD [OR] SITE QUALITY CONTROL
3 A. It is the Contractor's responsibility to maintain all stakes and control data placed by the
4 Developer's Project Representative in accordance with this Specification. This includes
5 easements and right of way, if noted on the plans.
6 B. Do not change or relocate stakes or control data without approval from the City.
7 3.8 SYSTEM STARTUP
8
9
10
11
12
13
14
15
16
17
18
19
20
21
ON
A. Survey Checks
1. The City reserves the right to perform a Survey Check at any time deemed
necessary.
2. Checks by City personnel or 3' party contracted surveyor are not intended to
relieve the contractor of his/her responsibility for accuracy.
3.9 ADJUSTING [NOT USED]
3.10 CLEANING [NOT USED]
3.11 CLOSEOUT ACTIVITIES [NOT USED]
3.12 PROTECTION [NOT USED]
3.13 MAINTENANCE [NOT USED]
3.14 ATTACHMENTS [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
8/31/2012 D. Johnson
Added instruction and modified measurement & payment under 1.2; added
8/31/2017 M. Owen definitions and references under 1.3; modified 1.6; added 1.7 closeout submittal
requirements; modified 1.9 Quality Assurance; added PART 2 — PRODUCTS;
Added 3.1 Installers; added 3.5 Repair/Restoration; and added 3.8 System Startup.
Removed "blue text"; revised measurement and payment sections for Construction
Staking and As -Built Survey; added reference to selection compliance with TGC
2/14/2018 M Owen 2254; revised action and Closeout submittal requirements; added acceptable depth
measurement criteria; revised list of items requiring as -built survey "during" and
"after" construction; and revised acceptable digital survey file format
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised February 14, 2018
SECTION 0174 23
CLEANING
PART1- GENERAL
1.1 SUMMARY
017423-1
DAP CLEANING
Page 1 of 4
A. Section Includes:
1. Intermediate and final cleaning for Work not including special cleaning of closed
systems specified elsewhere
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division I — General Requirements
3. Section 32 92 13 — Hydro -Mulching, Seeding and Sodding
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Scheduling
1. Schedule cleaning operations so that dust and other contaminants disturbed by
cleaning process will not fall on newly painted surfaces.
2. Schedule final cleaning upon completion of Work and immediately prior to final
inspection.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 STORAGE, AND HANDLING
A. Storage and Handling Requirements
1. Store cleaning products and cleaning wastes in containers specifically designed for
those materials.
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised April 7, 2014
01 74 23 - 2
DAP CLEANING
Page 2 of 4
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART2- PRODUCTS
2.1 OWNER -FURNISHED [OR] OWNER-SUPPLIEDPRODUCTS [NOT USED]
2.2 MATERIALS
A. Cleaning Agents
1. Compatible with surface being cleaned
2. New and uncontaminated
3. For manufactured surfaces
a. Material recommended by manufacturer
2.3 ACCESSORIES [NOT USED]
2.4 SOURCE QUALITY CONTROL [NOT USED]
PART 3 - EXECUTION
3.1 INSTALLERS [NOT USED]
3.2 EXAMINATION [NOT USED]
3.3 PREPARATION [NOT USED]
3.4 APPLICATION [NOT USED]
3.5 REPAIR / RESTORATION [NOT USED]
3.6 RE -INSTALLATION [NOT USED]
3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED]
3.8 SYSTEM STARTUP [NOT USED]
3.9 ADJUSTING [NOT USED]
3.10 CLEANING
A. General
1. Prevent accumulation of wastes that create hazardous conditions.
2. Conduct cleaning and disposal operations to comply with laws and safety orders of
governing authorities.
3. Do not dispose of volatile wastes such as mineral spirits, oil or paint thinner in
storm or sanitary drains or sewers.
4. Dispose of degradable debris at an approved solid waste disposal site.
5. Dispose of nondegradable debris at an approved solid waste disposal site or in an
alternate manner approved by City and regulatory agencies.
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised April 7, 2014
01 74 23 - 3
DAP CLEANING
Page 3 of 4
6. Handle materials in a controlled manner with as few handlings as possible.
7. Thoroughly clean, sweep, wash and polish all Work and equipment associated with
this project.
8. Remove all signs of temporary construction and activities incidental to construction
of required permanent Work.
9. If project is not cleaned to the satisfaction of the City, the City reserves the right to
have the cleaning completed at the expense of the Contractor.
10. Do not burn on -site.
B. Intermediate Cleaning during Construction
1. Keep Work areas clean so as not to hinder health, safety or convenience of
personnel in existing facility operations.
2. At maximum weekly intervals, dispose of waste materials, debris and rubbish.
3. Confine construction debris daily in strategically located container(s):
a. Cover to prevent blowing by wind
b. Store debris away from construction or operational activities
c. Haul from site at a minimum of once per week
4. Vacuum clean interior areas when ready to receive finish painting.
a. Continue vacuum cleaning on an as -needed basis, until Final Acceptance.
5. Prior to storm events, thoroughly clean site of all loose or unsecured items, which
may become airborne or transported by flowing water during the storm.
C. Exterior (Site or Right of Way) Final Cleaning
1. Remove trash and debris containers from site.
a. Re -seed areas disturbed by location of trash and debris containers in accordance
with Section 32 92 13.
2. Sweep roadway to remove all rocks, pieces of asphalt, concrete or any other object
that may hinder or disrupt the flow of traffic along the roadway.
3. Clean any interior areas including, but not limited to, vaults, manholes, structures,
junction boxes and inlets.
4. If no longer required for maintenance of erosion facilities, and upon approval by
City, remove erosion control from site.
5. Clean signs, lights, signals, etc.
3.11 CLOSEOUT ACTIVITIES [NOT USED]
3.12 PROTECTION [NOT USED]
3.13 MAINTENANCE [NOT USED]
3.14 ATTACHMENTS [NOT USED]
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised April 7, 2014
DATE
4nl2014
END OF SECTION
Revision Log
NAME SUMMARY OF CHANGE
M.Domenech Revised for DAP application
01 74 23 - 4
DAP CLEANING
Page 4 of 4
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised April 7, 2014
SECTION 01 7719
CLOSEOUT REQUIREMENTS
PART1- GENERAL
1.1 SUMMARY
017719-1
DAP CLOSEOUT REQUIREMENTS
Page 1 of 3
A. Section Includes:
1. The procedure for closing out a contract
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 — General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Guarantees, Bonds and Affidavits
1. No application for final payment will be accepted until all guarantees, bonds,
certificates, licenses and affidavits required for Work or equipment as specified are
satisfactorily filed with the City.
B. Release of Liens or Claims
1. No application for final payment will be accepted until satisfactory evidence of
release of liens has been submitted to the City.
1.5 SUBMITTALS
A. Submit all required documentation to City's Project Representative.
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised April 7, 2014
017719-2
DAP CLOSEOUT REQUIREMENTS
Page 2 of 3
1.6 INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION
3.1 INSTALLERS [NOT USED]
3.2 EXAMINATION [NOT USED]
3.3 PREPARATION [NOT USED]
3.4 CLOSEOUT PROCEDURE
A. Prior to requesting Final Inspection, submit:
1. Project Record Documents in accordance with Section 0178 39
2. Operation and Maintenance Data, if required, in accordance with Section 0178 23
B. Prior to requesting Final Inspection, perform final cleaning in accordance with Section
01 74 23.
C. Final Inspection
1. After final cleaning, provide notice to the City Project Representative that the Work
is completed.
a. The City will make an initial Final Inspection with the Contractor present.
b. Upon completion of this inspection, the City will notify the Contractor, in
writing within 10 business days, of any particulars in which this inspection
reveals that the Work is defective or incomplete.
2. Upon receiving written notice from the City, immediately undertake the Work
required to remedy deficiencies and complete the Work to the satisfaction of the
City.
3. Upon completion of Work associated with the items listed in the City's written
notice, inform the City, that the required Work has been completed. Upon receipt
of this notice, the City, in the presence of the Contractor, will make a subsequent
Final Inspection of the project.
4. Provide all special accessories required to place each item of equipment in full
operation. These special accessory items include, but are not limited to:
a. Specified spare parts
b. Adequate oil and grease as required for the first lubrication of the equipment
c. Initial fill up of all chemical tanks and fuel tanks
d. Light bulbs
e. Fuses
f. Vault keys
g. Handwheels
h. Other expendable items as required for initial start-up and operation of all
equipment
D. Notice of Project Completion
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised April 7, 2014
017719-3
DAP CLOSEOUT REQUIREMENTS
Page 3 of 3
1. Once the City Project Representative finds the Work subsequent to Final Inspection
to be satisfactory, the City will issue a Notice of Project Completion (Green Sheet).
E. Supporting Documentation
1. Coordinate with the City Project Representative to complete the following
additional forms:
a. Final Payment Request
b. Statement of Contract Time
c. Affidavit of Payment and Release of Liens
d. Consent of Surety to Final Payment
e. Pipe Report (if required)
f. Contractor's Evaluation of City
g. Performance Evaluation of Contractor
F. Letter of Final Acceptance
1. Upon review and acceptance of Notice of Project Completion and Supporting
Documentation, in accordance with General Conditions, City will issue Letter of
Final Acceptance and release the Final Payment Request for payment.
3.5 REPAIR / RESTORATION [NOT USED]
3.6 RE -INSTALLATION [NOT USED]
3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED]
3.8 SYSTEM STARTUP [NOT USED]
3.9 ADJUSTING [NOT USED]
3.10 CLEANING [NOT USED]
3.11 CLOSEOUT ACTIVITIES [NOT USED]
3.12 PROTECTION [NOT USED]
3.13 MAINTENANCE [NOT USED]
3.14 ATTACHMENTS [NOT USED]
DATE NAME
4/7/2014 M.Domenech
END OF SECTION
Revision Log
SUMMARY OF CHANGE
Revised for DAP application
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised April 7, 2014
017823-1
DAP OPERATION AND MAINTENANCE DATA
Page 1 of 5
SECTION 0178 23
OPERATION AND MAINTENANCE DATA
PART1- GENERAL
1.1 SUMMARY
A. Section Includes:
1. Product data and related information appropriate for City's maintenance and
operation of products furnished under Contract
2. Such products may include, but are not limited to:
a. Traffic Controllers
b. Irrigation Controllers (to be operated by the City)
c. Butterfly Valves
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 — General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Schedule
1. Submit manuals in final form to the City within 30 calendar days of product
shipment to the project site.
1.5 SUBMITTALS
A. Submittals shall be in accordance with Section 0133 00. All submittals shall be
approved by the City prior to delivery.
1.6 INFORMATIONAL SUBMITTALS
A. Submittal Form
1. Prepare data in form of an instructional manual for use by City personnel.
2. Format
a. Size: 8 '/2 inches x 11 inches
b. Paper
1) 40 pound minimum, white, for typed pages
2) Holes reinforced with plastic, cloth or metal
c. Text: Manufacturer's printed data, or neatly typewritten
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised April 7, 2014
01 78 23 - 2
DAP OPERATION AND MAINTENANCE DATA
Page 2 of 5
d. Drawings
1) Provide reinforced punched binder tab, bind in with text
2) Reduce larger drawings and fold to size of text pages.
e. Provide fly -leaf for each separate product, or each piece of operating
equipment.
1) Provide typed description of product, and major component parts of
equipment.
2) Provide indexed tabs.
f. Cover
1) Identify each volume with typed or printed title "OPERATING AND
MAINTENANCE INSTRUCTIONS".
2) List:
a) Title of Project
b) Identity of separate structure as applicable
c) Identity of general subject matter covered in the manual
3. Binders
a. Commercial quality 3-ring binders with durable and cleanable plastic covers
b. When multiple binders are used, correlate the data into related consistent
groupings.
4. If available, provide an electronic form of the O&M Manual.
B. Manual Content
Neatly typewritten table of contents for each volume, arranged in systematic order
a. Contractor, name of responsible principal, address and telephone number
b. A list of each product required to be included, indexed to content of the volume
c. List, with each product:
1) The name, address and telephone number of the subcontractor or installer
2) A list of each product required to be included, indexed to content of the
volume
3) Identify area of responsibility of each
4) Local source of supply for parts and replacement
d. Identify each product by product name and other identifying symbols as set
forth in Contract Documents.
2. Product Data
a. Include only those sheets which are pertinent to the specific product.
b. Annotate each sheet to:
1) Clearly identify specific product or part installed
2) Clearly identify data applicable to installation
3) Delete references to inapplicable information
3. Drawings
a. Supplement product data with drawings as necessary to clearly illustrate:
1) Relations of component parts of equipment and systems
2) Control and flow diagrams
b. Coordinate drawings with information in Project Record Documents to assure
correct illustration of completed installation.
c. Do not use Project Record Drawings as maintenance drawings.
4. Written text, as required to supplement product data for the particular installation:
a. Organize in consistent format under separate headings for different procedures.
b. Provide logical sequence of instructions of each procedure.
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised April 7, 2014
01 78 23 - 3
DAP OPERATION AND MAINTENANCE DATA
Page 3 of 5
5. Copy of each warranty, bond and service contract issued
a. Provide information sheet for City personnel giving:
1) Proper procedures in event of failure
2) Instances which might affect validity of warranties or bonds
C. Manual for Materials and Finishes
1. Submit 5 copies of complete manual in final form.
2. Content, for architectural products, applied materials and finishes:
a. Manufacturer's data, giving full information on products
1) Catalog number, size, composition
2) Color and texture designations
3) Information required for reordering special manufactured products
b. Instructions for care and maintenance
1) Manufacturer's recommendation for types of cleaning agents and methods
2) Cautions against cleaning agents and methods which are detrimental to
product
3) Recommended schedule for cleaning and maintenance
3. Content, for moisture protection and weather exposure products:
a. Manufacturer's data, giving full information on products
1) Applicable standards
2) Chemical composition
3) Details of installation
b. Instructions for inspection, maintenance and repair
D. Manual for Equipment and Systems
1. Submit 5 copies of complete manual in final form.
2. Content, for each unit of equipment and system, as appropriate:
a. Description of unit and component parts
1) Function, normal operating characteristics and limiting conditions
2) Performance curves, engineering data and tests
3) Complete nomenclature and commercial number of replaceable parts
b. Operating procedures
1) Start-up, break-in, routine and normal operating instructions
2) Regulation, control, stopping, shut -down and emergency instructions
3) Summer and winter operating instructions
4) Special operating instructions
c. Maintenance procedures
1) Routine operations
2) Guide to "trouble shooting"
3) Disassembly, repair and reassembly
4) Alignment, adjusting and checking
d. Servicing and lubrication schedule
1) List of lubricants required
e. Manufacturer's printed operating and maintenance instructions
f. Description of sequence of operation by control manufacturer
1) Predicted life of parts subject to wear
2) Items recommended to be stocked as spare parts
g. As installed control diagrams by controls manufacturer
h. Each contractor's coordination drawings
1) As installed color coded piping diagrams
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised April 7, 2014
01 78 23 - 4
DAP OPERATION AND MAINTENANCE DATA
Page 4 of 5
i. Charts of valve tag numbers, with location and function of each valve
j. List of original manufacturer's spare parts, manufacturer's current prices, and
recommended quantities to be maintained in storage
k. Other data as required under pertinent Sections of Specifications
3. Content, for each electric and electronic system, as appropriate:
a. Description of system and component parts
1) Function, normal operating characteristics, and limiting conditions
2) Performance curves, engineering data and tests
3) Complete nomenclature and commercial number of replaceable parts
b. Circuit directories of panelboards
1) Electrical service
2) Controls
3) Communications
c. As installed color coded wiring diagrams
d. Operating procedures
1) Routine and normal operating instructions
2) Sequences required
3) Special operating instructions
e. Maintenance procedures
1) Routine operations
2) Guide to "trouble shooting"
3) Disassembly, repair and reassembly
4) Adjustment and checking
£ Manufacturer's printed operating and maintenance instructions
g. List of original manufacturer's spare parts, manufacturer's current prices, and
recommended quantities to be maintained in storage
h. Other data as required under pertinent Sections of Specifications
4. Prepare and include additional data when the need for such data becomes apparent
during instruction of City's personnel.
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE
A. Provide operation and maintenance data by personnel with the following criteria:
1. Trained and experienced in maintenance and operation of described products
2. Skilled as technical writer to the extent required to communicate essential data
3. Skilled as draftsman competent to prepare required drawings
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised April 7, 2014
01 78 23 - 5
DAP OPERATION AND MAINTENANCE DATA
Page 5 of 5
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
DATE NAME
8/31/2012 D. Johnson
4/7/2014 M.Domenech
END OF SECTION
Revision Log
SUMMARY OF CHANGE
1.5.A.1 — title of section removed
Revised for DAP Application
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised April 7, 2014
017839-1
DAP PROJECT RECORD DOCUMENTS
Page 1 of 4
SECTION 0178 39
PROJECT RECORD DOCUMENTS
PART1- GENERAL
1.1 SUMMARY
A. Section Includes:
1. Work associated with the documenting the project and recording changes to project
documents, including:
a. Record Drawings
b. Water Meter Service Reports
c. Sanitary Sewer Service Reports
d. Large Water Meter Reports
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 — General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]
1.5 SUBMITTALS
A. Prior to submitting a request for Final Inspection, deliver Project Record Documents to
City's Project Representative.
1.6 ACTION SUBMITTALSANFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE
A. Accuracy of Records
1. Thoroughly coordinate changes within the Record Documents, making adequate
and proper entries on each page of Specifications and each sheet of Drawings and
other Documents where such entry is required to show the change properly.
2. Accuracy of records shall be such that future search for items shown in the Contract
Documents may rely reasonably on information obtained from the approved Project
Record Documents.
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised April 7, 2014
017839-2
DAP PROJECT RECORD DOCUMENTS
Page 2 of 4
3. To facilitate accuracy of records, make entries within 24 hours after receipt of
information that the change has occurred.
4. Provide factual information regarding all aspects of the Work, both concealed and
visible, to enable future modification of the Work to proceed without lengthy and
expensive site measurement, investigation and examination.
1.10 STORAGE AND HANDLING
A. Storage and Handling Requirements
1. Maintain the job set of Record Documents completely protected from deterioration
and from loss and damage until completion of the Work and transfer of all recorded
data to the final Project Record Documents.
2. In the event of loss of recorded data, use means necessary to again secure the data
to the City's approval.
a. In such case, provide replacements to the standards originally required by the
Contract Documents.
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART2- PRODUCTS
2.1 OWNER -FURNISHED [OR] OWNER -SUPPLIED PRODUCTS [NOT USED]
2.2 RECORD DOCUMENTS
A. Job set
1. Promptly following receipt of the Notice to Proceed, secure from the City, at no
charge to the Contractor, 1 complete set of all Documents comprising the Contract.
B. Final Record Documents
1. At a time nearing the completion of the Work and prior to Final Inspection, provide
the City 1 complete set of all Final Record Drawings in the Contract.
2.3 ACCESSORIES [NOT USED]
2.4 SOURCE QUALITY CONTROL [NOT USED]
PART 3 - EXECUTION
3.1 INSTALLERS [NOT USED]
3.2 EXAMINATION [NOT USED]
3.3 PREPARATION [NOT USED]
3.4 MAINTENANCE DOCUMENTS
A. Maintenance of Job Set
1. Immediately upon receipt of the job set, identify each of the Documents with the
title, "RECORD DOCUMENTS - JOB SET".
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised April 7, 2014
017839-3
DAP PROJECT RECORD DOCUMENTS
Page 3 of 4
2. Preservation
a. Considering the Contract completion time, the probable number of occasions
upon which the job set must be taken out for new entries and for examination,
and the conditions under which these activities will be performed, devise a
suitable method for protecting the job set.
b. Do not use the job set for any purpose except entry of new data and for review
by the City, until start of transfer of data to final Project Record Documents.
c. Maintain the job set at the site of work.
3. Coordination with Construction Survey
a. At a minimum clearly mark any deviations from Contract Documents
associated with installation of the infrastructure.
4. Making entries on Drawings
a. Record any deviations from Contract Documents.
b. Use an erasable colored pencil (not ink or indelible pencil), clearly describe the
change by graphic line and note as required.
c. Date all entries.
d. Call attention to the entry by a "cloud" drawn around the area or areas affected.
e. In the event of overlapping changes, use different colors for the overlapping
changes.
Conversion of schematic layouts
a. In some cases on the Drawings, arrangements of conduits, circuits, piping,
ducts, and similar items, are shown schematically and are not intended to
portray precise physical layout.
1) Final physical arrangement is determined by the Contractor, subject to the
City's approval.
2) However, design of future modifications of the facility may require
accurate information as to the final physical layout of items which are
shown only schematically on the Drawings.
b. Show on the job set of Record Drawings, by dimension accurate to within 1
inch, the centerline of each run of items.
1) Final physical arrangement is determined by the Contractor, subject to the
City's approval.
2) Show, by symbol or note, the vertical location of the Item ("under slab", "in
ceiling plenum", "exposed", and the like).
3) Make all identification sufficiently descriptive that it may be related
reliably to the Specifications.
c. The City may waive the requirements for conversion of schematic layouts
where, in the City's judgment, conversion serves no useful purpose. However,
do not rely upon waivers being issued except as specifically issued in writing
by the City.
B. Final Project Record Documents
Transfer of data to Drawings
a. Carefully transfer change data shown on the job set of Record Drawings to the
corresponding final documents, coordinating the changes as required.
b. Clearly indicate at each affected detail and other Drawing a full description of
changes made during construction, and the actual location of items.
c. Call attention to each entry by drawing a "cloud" around the area or areas
affected.
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised April 7, 2014
017839-4
DAP PROJECT RECORD DOCUMENTS
Page 4 of 4
d. Make changes neatly, consistently and with the proper media to assure
longevity and clear reproduction.
2. Transfer of data to other Documents
a. If the Documents, other than Drawings, have been kept clean during progress of
the Work, and if entries thereon have been orderly to the approval of the City,
the job set of those Documents, other than Drawings, will be accepted as final
Record Documents.
b. If any such Document is not so approved by the City, secure a new copy of that
Document from the City at the City's usual charge for reproduction and
handling, and carefully transfer the change data to the new copy to the approval
of the City.
3.5 REPAIR / RESTORATION [NOT USED]
3.6 RE -INSTALLATION [NOT USED]
3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED]
3.8 SYSTEM STARTUP [NOT USED]
3.9 ADJUSTING [NOT USED]
3.10 CLEANING [NOT USED]
3.11 CLOSEOUT ACTIVITIES [NOT USED]
3.12 PROTECTION [NOT USED]
3.13 MAINTENANCE [NOT USED]
3.14 ATTACHMENTS [NOT USED]
DATE NAME
4/7/2014 M.Domenech
END OF SECTION
Revision Log
SUMMARY OF CHANGE
Revised for DAP Application
CITY OF FORT WORTH ACN Fossil Creek
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104255
Revised April 7, 2014
F'oH r WORT
CITY OF FORT WORTH TRANSPORTATION/PUBLIC WORKS DEPARTMENT
.
STANDARD PRODUCTS LIST AS OF 05/ 16/2024
t.'uuc.a r.
9P64d73
13u nl
dlix rkwR
/rnrerraae l'9o-w C'wmavr
LZF0:91900mL'one.evr1.5rdmAL.dADAR.-
�I3Ai3Y3
9/0/2022
133000
mglb "
Americm Concrcec Com0uny
ipp0 p.i L.wmw na.¢ Mw-w [1x Trcneh 1k•[wrr
19N+7ALin
33n 00
11Six F3celrn
Amerreari'wKeaec(.)xor
40CXF0654ppp 1a+['anncic Wr Hndwin L'lJltlrslruc[uru
1k) 9,2022
OJ 3000
M,x Dc 11n
American Concrcec Coumam-
45C'AP076+SW Lb4uuk fof Itmd Plaud P+.hJ�p
19/92022
03 30 0a
.IRrhta
Argos
p �%j 7 i+ [ CORerclr 6r liu.d Pfxv4 Pa inr
19r9l=
030a
�1: ReH�g
Atwh
hludWRld* S ml Ca�rrre fox lWd ptactdP wY
19/9/2022
03 J0 00
Mix Dclr
Argos
h1000000 P793 4500 wCow" fw It" Plaed P-m
19/9/2022
033000
Mix Dcs�en
Argos
nlOOWM[[034500 Crnnex rorlland Pfxad P-MR
19/9/2022
0330.0
Mix Design
Argo.
n10W0002[074500 Cbsxrp4:fp limd
19+w=
033W 00
rhea llni�pn
Ar
n[ 0600o0i273a100 a C'_mW r. lJ-d YEaed pnm/[
19/9/2022
033000
Mix Design
Argos
I3lOWWOIh177800 LV.K.Ac rw Mechn.I Aland Pa%mm
19/9/2022
033000
"e +IiJn
Atlpu.
I, u000u083Y[JS00 CmKk fer l lf& P..Y
j
I9/9/2022
03 30 00
Mix Dcsicn
Argos
I[
pl 0Wg009df750 fpi v'-4W Fd]•LISM
19.99022
b3 3d 00
AlrI f].ylen
Aeg"
n1000W01055 ] Conpcic rot hdd; losdw Rutca R{m1W}p Chmnel Lmerr. SAe jll , Ihrx'.n cwl) Bona
19/9/2022
03 30 00
Mix Design
Argos
01 WMI0435 )0W Canfnac §sr a'd:++ILx, Curh.
19/9/2022
03 30 00
Mix Dcsiem
Argos
DI O00001 $65S ]000 q}1 Ne f Curt" Cl.h &Uw SWc.at4w Dli.[x'aH, AIM R4ngr.
I9H1i022
03 I000
Mix Ddjfj.
-UNA
nIA0W01hl33600 meAw Arkix f[u4et r-nca¢uKnr. Redd'
19/9/2022
03 30 00
M,x Des,//tn
Argos
D[0v0000196! SL00�" Cmerwe LY klga, Ruxn, Euuxv4 '.
19/9/3022
03 30 00
Mix f3CrIYA
Areus
rtip� pipp{qf{q�p�qp�p�pQP�+.r..� Ca.sp.7C Be Yal.r Padti Alter. 5nvarura l 'all.. in-. mo i u
19/9/2022
03 30 00
M.. i3glrgr
Ar!us
i3I G�NfAd�611 d90Gprl i'wrroe Rrr Va1x•Pada. lnleu, slnwwn.liradwdlh Thrna 13tead=aY
Ig10rim
p3300o
Rlr. r._.m
Ar
D100M](45 M17u0ddJJ���Caiefo[r Wr Valtr Pau
19/9/2022
03 30 00
3fix T"m
Argos
n10d0000575] 759 Pskioe.e.Yk ANC to Trmsh XpNq
19/92022
031000
Mee fk•,uFe
Ms
n100o0W14%I 4010 I.. C—de for fkudw411r. RcWa Wn9 Wa114. Box CO •tlt• VAIN Gullnl
19I92022
033000
Mrx f3rurW
Ai`l'uncrdc
75kGA7)CWyu Crwrcrcscf G.wWrrq
I A9i'_02±
15r±.20]]
W 30 W
)21113
Hrx flc.0n
Mn17al�.n
Ris1� L'aarts¢
A�73Cunarecu
Ii50dAf i70d f�lyI L'onauec f Rr fylY Yitp, N.�nnk
C�111+i:WAt:aipp Cp.uPrfor dllYuocdPanne
19i9/2022
Mix=n
A, Tuwn C'unerde
=nY
JS20e1Y14590 kund30
�f033'3000
OU
h+nd n
;s00Ilu
19 730±=
1f] 39 W
Mix 13-m
R _ _mutupe
eee
i sy0 Hond Plpwd Pawnr_Srumr3NLLporn
199.2032
3000
Mo ijNjv
Bumw T¢
4"531104Wd du C...dc Mi, A. Maddh¢ PLxxd DAVi-4
j9;92022
1J3000
ffla I)c
Aumco Texas
1b Aan9!9/2022
030Mix
D2
Rumca Tc. a
WokG Wo01'n4 kw—ALx fp CWarw In IL5&w,,,9/9.^022
1SWnG
033000
hit. heir
$t. c T¢
IdtAG 3WO mr A•—m. M[+fo LI9/9/2022
luo T•u CPnw' ilex fee hp 0e 11,1--1, C'mbl ku JWt411un Fjox Fu¢ fl2*.un Ppl� EM—Ap, C.-I, Yc Cyrr¢ew
03 3000
Mix Design
Aumco Texas
�Wewflit AF1A Rai
1FR"�I2
O736W
31p 13Mdn
Bomw T¢.N
JO[:jO0M:400v 7Mr. fa SadtlniLa:n 5lrrrswa. perkq' &4Ras Wdl4 ['opsa
OR.207±
05000 00
Mn
LpurR¢o TqN
DSOORD 3o00 C'pR'.Kif Mm (w I iphi ir�pn4 Truffle Siod Fpurdv loot
4.9, 2022
R4Z0==
033000
033000
Nix ik4
��111�
Flum.n TnaaY+SOBA
urneu 7eYu
N00 FConerCr931ix ip Rasr leuirrnch Rgmr
I Ce,mde Mn fm xW=.V41¢fdl
�
r.Y 3034
033000
F.Sea�
Wrorn Texa.
3AU0 Ctnerrec Mea WrliprlinvB Traf6e uYwl Fonnd,glaa.
9/1/2024
033000
iN DIx[�
Aumco Tcxax
;SUWRG Imemi C91k1=►Sl. Rr C'N.—IL
4/1/2024
033000
Mix Des`cj�
Rw9ea T_
30U500R1370001ui Concrce Mi. Gx Sid 4Bx
41i1301"
033000
Mlx Rgs0ee
BRm.e Tex.>•
99W"ISAC yu1
4r172024
033000
m,x Dwiun
Aumco icxu
0[Yfy011F ]00 Cararcle hhx for FwwatAc rip
.W rNN
0] 30 00
Mrx Dni
Bumeo Z.
SSU13aAGa l'WrKen Mix fecal3"� F g,-,'�,yrr]'r 30lIlAeJ'l3 dan
1/1/2023
OJ 34 I6
Mrx Dp1Pe
Aumco Tcxm
IdYHSORF I ppqq cane=ric Ra.e b14Y.+W f0e pxb R(Nil
9/9/2022
03 30 00
I9 offl'
Carder L'uncrcec
FwCi760J025 JSI(0 auoc[ge f FT.nd Plaoul Pa.mR
9NRd22
03 30 00
jdn np.ryn
Carder Cuncrcrc
PlAt"SI09i 36W�r 6f MYdrir�e Pluead Aninp
9.NADJ3
03 ]Od0
idW[ bh7
Lbrdee.LboCrek
FWCL00205[ 3KV pp�� 6 Mxhuic P1xad I-wm
9NR022
033000
Mix D-m
Carder Concrcec
PWCCi59 EDE Fto..vhk SU. CISM
9/9/2022
03
Mix ncsian
Carder Concrcec
FIMTF23MI IR9ecaV. Pd1 CLAM
9/9/2022
07 70 00
Mix Dcsikn
Carder Concrcec
FWCC60MW1 4000 p�1+ICpKrpe $Sru , M.I. Snuemrea, M4uF91e. Pkxl a4lw RY4lrft'Wa1L, V-4ky C.Mv DrlU AmP lln
WW=
0] 10 00
Mi. r"jp
Carder Cnxfe:x
PWI.Y'S02071 3300 Ncans oa fsv Sid -AL'. Mixcw4v�Rm Cur" ak Ooa
9192022
03 30 00
Mix Design
Cwdcr Concrm
FWCC500v01 30M Pa for Srdewal" D.is axx�a RwvlN.loth& eia.", FLewa1.
9,9/2022
1D 30 00
Mix r3¢41YP
Ch,,Mc( Concrcec
41423600 Psi Curve r rCurb lnkm. JoNti n A.a.p
9/9/2022
033000
Mix Dei�2
Charlc\-Concrcec
4SER i000/w C'wwd¢Iir fiadwalla. Wy]� R.
9/9/2022
033000
Mix Design
Charle Concrcec
55h73nm71.c. Caeere/e She Oat Mmin0ePa.+
41 122
033000
V. .��
Ch.lcv Cwicmw
46044SOO Pa. CWKta¢4n Tat flaad.Plaird PaMe2lianhuln
9/9/2022
033000
Mix Design
e'hwic Cpiercee
4107 a5001Cpwere]in Wr Raad Placed lRrnrib R4anoolrs
9/9/2022
033000
Vexnaim+
Chwlcs Concrcec
45023000JJ�9ser
9/9/2022
03 30 00
Me. Ddla
Chwlc s Cuncrcrc
, 37"300 mi Ceoerge M foe S30esxr1la
9/912022
ID 30 00
Mrx flpiYu
Chwlc - Concrcec
ISO] ISo Co.crarC Wr Pk=a4sl¢ Fdlil.Sa1
9f92�22
03 39 00
Rry T>., "
LiwIL3y Cmclne
1516 150 F., Cmc k 0r Flowak RO•CI SM
9,92022
9,9,2022
03 30 00
033000
Mix Design
51ix Z-V
Char c`s Conercrc
Ch.ulc\)3s Cancrcic
7i000 pr�yjj Pf nraen SleueWr¢4
5000p.e Por.cr r. e�fer f 1yy Sbcnyh Parnrg
9,9/2022
03 300
Ali. tjd"
Charle s Concrcec
6SyP 4300 C'anrrpe Mee 1G f fj'51w.e�h Paxanf
I49/2022
037000
Mix Dcsi¢n
Chuhlm "frail Rcdl ti,x
�CI]02oAR3000 p.I Lbn[rexr Tw n¢wsSw L'u�!]&4uua
IW9/2022
03 30 00
Mix Dceiun
Ciev Concrcec Coi, n v
11 330•FF 50-I �G w. Co em for Flowahk rocLUS 1
CITY OF FORT WORTH TRANSPORTATION/PUBLIC WORKS DEPARTMENT
STANDARD PRODUCTS LIST AS OF 05/16/2024
Za.ueJeer�'-nredl
19.91_02Z
0} 3i100
31ix Desio
Ci,y Cawe,e Lwquny
3WIA21a 3WO Mi Cwcwv fw Rplia/
9,v 2023
03 3000
'1n D.w
Cny Connor Curl r
�WIA2W1 ]9dh�i C¢acrne lL, r F�xYa��,. SidewalLr. 1Uwwt, Pad.
99':o22
0330 oil
Nn Deswn
Cnf' Cexxewv4lr!�syrY
a5AG25Al6011)wcanrlr 3fi, fa FT,IIniSM,,R.l.f.h,m¢unJ T,uiDv S+¢n.J FawxLllm.
99,2022
033000
Mix nrs'n
Ci1x UmiclC Cwvi.-y
ITI7600,Ai 51.0,' r)"Ccd hrwcd Shop
�A20RlSo01rsl
91 Zo--
13000
�)
Mlx Dcs�!n
L'nY CM kC'wwwnr
Lb�c+es Aln 1. R.W Pt—,d Par'
9+9.7Y72
300a
Mix Dcs�!n
CiL L• cw Cwryun+•
'161 A2011 3500 mi C' me M,4 Fw N�9i'rne Mum IF.n,np
33
III
II .Tlwx.wn
L•in•Cmem¢ L'9ngxurx'
IWAOOi3 Sup I'wren+e Mli, 1w hlaeMine Plaerd Pa,iax
9f4r11Fx:
u320W
Lrt!'Cdo00. L'UnWn,�
J01A30113�I9�x rGa+do M!. f¢r almnfhaln5nYpu.[
P1144,1
�[[[m[[�^^��,1knotic.
y
I's,m]3:
033000
�1,n n4:ip
L'rn'Ca6crtic 4mr4—
CL�AzsoA(.i3EOO n.1 L•JM.nc rI1M 11cS 8M1x iL.l ne`a T.11lc 49nd i�¢Imduiuna
V,W,323
03 3000
Ix 1lpixn
L'n, Cennald [' ,
C 2WAFi s, ['wncraa fa slur rninaxdn�S7u0., tinJc,xwv 9.0,
9ivi2022
03 30 u`u
Idr, I3cuxn
Corr Tp„n R� Irlr,
7W ]000 pN C:oucrdC ti fp aalcwdk.,i .�rv,. AhA Rirb.
9/9/2022
03 30 00
�1n npg0,
Cux Tuxnitadl Mix
3S9 ]000j C¢nerLLe iLa f y}Jew •aR�y, DrHxtlan. AnA Km,
9,91202!
03341)
r. D-iin
Cs.r Tv Stag Mn
�7V -Jhic PIU-CE,$MS
9JW2023
03 ]1 13
Dcov
Ca6•Toxn Rah m x
9-5-2 '+O wr Fkw'A c Fill
WW2021
03 H 13
�1.
U Dewxn
Vw Tpa Rcbl Ma.
3763 30 ¢a C¢ncrpoc Mi. far Flim.- is fill -cLsat
9 9na92
0l34 IS
l x Dcsiwn
L'ew'T ¢ Rsm mi.
3M•N j9ppNn L'anereu M1ix IW 'a6fe FdI.LT 5Mi
wwU23
03]009
'ix Dcsinn
CuW Torh RWi Mrs
33a•li 73d i Cawiw,c Ra.¢ Ma,rriJl Wr TrcacY r
1*3032
111 ]000
ix Dcsi�sn
Co+Tana N[+F M1,
330.5E 7S0 ra: C'wKl, IWe Mu 16R Yx�¢L
9"22
03 30 00
Mix Dcacn
Cow Torn RaRMA
353 ]WO L',nnac Mi, fw $,draa1Ln AIV, It 1 C•Yrh ttkW. S.fpYl=nd Yrramu,x.. Yun•Ta1WT Rcunnnp WJ11.
<Il�rir�t'sphrc- �v Fnd 7!u4¢mb, WrYTafM]T R�dnWp 51',J1r
fa
W O21
O] 0 00
SIM [4 0
Car Twn Redl Mix
30a a004u Lmarek Nii Ihy�u 514w. Ron Culma.l Wdw+11,0h$
pry!]022
03!0 00
11in f1p,0
L•oW Town Rcd, MIX
3W}•I S61f0 p¢ L•unanc Ura W 1�
979W2
3a3N}
-1 tw,,
V"Tm,,Rafi It
3W0 .34,zq C9ruxnv Mln I. RR—C'oE.O,, Ic4dwalle
%W2023
Si000
3li, Dea,'P
Cow T~RW,34K
)W ADm O+1 Cwwnc Hn faL.11o, B1l cotiw,tWaKxd4
91913p3:
300a
L1,r i3"10
L'aw Yuwa Rdi.lSn
]6R1 J� Corlcm9Ml,s CW
9r4?022
3000
Mlx ndim!
Cw Tma, RWE M.,
3M•K d50Q Ltli Crxoat,e 3Iw fn HodPly4cd Na.n,w
t
4i9/]o32
30 Oa
hln ik¢Cn
Cow iwpn Rd, #n
3AA451 iN Ili%fw Wad PL.W Paving
093023
3490
M!u 3MW0
C'ew Town Rd, M,.c
]054500 eri Cvc Nlin fo IW,J Placwl Pavinit
g 9 W311
30 Oa
311x
Cow Twn RW, 5A,
366AS110 L'¢nnA. Mlin 5w FLmd PW Pane.
9 9 +
130 00
hl,s
Cear i'ewm Rd, 74a
�701.0 f500 p+i Cwnne 1pr Iila Psrinp
{9913023
370o
Mix Dcsiun
CO. Tuwn Roth Mix
]7tl-3 NC5 ¢,1 Luonwlr! HFSPa>•i*,r
�99'7Q37
330 a0
Mmoo llx Dcsiun
Ca,.T¢,mR J Mi.
InNC7000`pp/1 C--fw HFS
ManMrJc. lnd c
W
EI++. iN11�
Cwaw I.— k4d, Mit
5a0a l,d ['a,unc ?f44 yr ,.,uamn
�9:v+2073
WWAO23
3 3000
M1x hnfim
1•w' Tpw. It d1 Mi,
TO 50p0 Cw OC MSia Ipl LS,1•in �It lloa cwl.
9NfJ023
03 30 Do
ht. Ik.7w
ow Town RW, Mn
55.2 StlfIC CwusnG MLr fv inlua. Thma ali:6, • Cimi" Enea,urmg
l9N.'AA22
m4,'3022
Ol ]o W
32 l3 ll
Mi. D-V
M,a Dcs�!n
�nr 7ora Rtd,:tix
Cow' 7pwn ricdi Mn
25Y ]600y+�cu nds lh YallpyGwm
3 ta, Corm 1. hhc hw ,� 19pcuJ PsmR
I
19ro/3a23
33I]i1
M4. DalEn
Cau To—Rcd, M:,
�37-M1I
23P•M 36o0 p, co—m,.. Mlx rd.. Mxo—Nww Pnm¢
197W2025
34 l3 I3
MI. DeaiM
e;or Tam, Raj, -m
26PM 4000 aJ [:oN m MI, it LSW." PMJwea P--v
I%WIU23
35 1] i1
Mlx Dwm
Cow T n RW, AU=
3W-,A 1Ud¢pr, C.mene Mi. fae MOCHM Maud P4dn¢
1ww=
033000
�4ia nsbkw
i•ow Tw MRodi Ali,
AWLP3 Pk C-oau9Ea Mix fpr Cob 4 CNJlp
17Mf3023
0)]000
nikwxo
L•ox Turn Rpl, MI,
335•LP l00p{`. vwlvor Mlis i¢, CuO,&L:Wen
IWf!a22
0330 QO
ix 17csien
L'ax Tae Steal M,s
2553500P,1[ ele Mlia f¢rRA—I. Wwe. 31a0a R1ueUn¢ Cmpcic Fleno,wwe
19+Wi022
03 toW
ix DCSI m
Cola Tuxn RC4 Alva
353 2000��.1 Cusick M.la Wm T!"a IaOc . ['wrrne Frasm,nn
191ORa03
O] ]o Otl
M„ hey ,
1:a T.. RMI M4.
365•ST%,iGffl pi C'm m Fr Rr JahA. lug. ofdinc wflk Ll ,Jw,—h Ad-T)i{V" Cb- 3•V,, Fly Art,
19,V13o32
13411102i
03.7000
p3lQ OO
Mfiv ]3c„ri,
M„llculm,
L'uw Town Beth M+x
Cw Tum R,Yk hlu
303600 ICa9w4a411i. go, VdTGyih m.
3Gp2n�1'unfnle Hre Toc TXF1CrT L7c+r C'f71111ed %AJA.
I W2I n¢A,
3]000
Mnflnir0
CWr Town Rq: Mi.
360•hS Concr 11.lkJleJ 9uMJma,n9and TfulGe5rpnd FwuWy,ua
11116202Y
0330"
Sl,n fkw9n
CwT Ball Yn
31MC'45 L'oncrer4 fw ItFSP
I IR91S024
]a 13 IS
Mn i3,rlw,
AanW4 Brad%' Mn
a57SAlS['17 517 5a 7, Ii300�u I1.0001,a 0,' Sao ICw1uA: Iw flFs P4wlf,
I IlUP03i
03 LN W
M,xrn10
Fmed4 R �5}n
R3p5aAF.WR 1 5.00 S:lA+l3 f10 pJ Cnnarle fA ,uYlu. R��V °a. LJan Mldwlo
11P_9I30la
W 3400
M,x DunW
Ed-L R¢uiy Mh,
R3655ARWR15:1{, 5aeAx11.60a1,w Co„c914 Rr}Ic«[waai. {(Sn¢w.11x 4n0Cal,�et,
I I(3920R4
63 30 M
11.1 1'/au.n
F,duJa RryJy }11a
R40NAt.WR • 6Aa Sac6. 11.00D//N Coocrn4 far Ar,dl�f Si4 L T�RSlahs, and Ae9 ,I,5lnMi
12 h'aM
331313
IS f
m,x fxa.p,
M11r j7.tilp,
Iyradl/1e7Jj Mln
E.1raL, Nmd\MSix
ThSb55AP-WA 'SSa S.a�s 3NR1 C- d-fN 3la-I1nc h�l,xcd N..vma
K4-%"F.WR 5.00 SacA+: LS00� R,r HJxd Plxcd Pml
11 39703J
I::_I 2tl31
3
�3a 00
9
Mi. ij,e ,m
Il,vadn Rr rpyllfie
{I]d575M1R1VR 15,705aeL.'S. pJ ['arespe ldr AlAcd 56,J1.4 �ep,aW Tr41;;e 5lVA Fouudtlu+n,
19/92021
111111
hl1* DvJEn
C.L•N Cq,cn le S4rriccK
C,CIYI0004a00 qH I.anerte fo, fw a, Iludwvlh. In a,. anJ Slow Dram Swcmu
Igflr3p_=
30 0t1
11011
Mix ne,i¢n
GCFI C'ur,crne 5enea
5w,ica
1.0c
[:L1iV54goon,I�wy ne Fn Mrd,hre P1axJ P�
�iLRti5h0i Concra0 H,Vnl P11Md Pa,inR
19AIy13I
14,oma
{wwMm
!0 00
]000
3000
Mix Dcsi9n
Mu D.)
Ml la g¢
CSL•}I Cmcwpw
Inpm,L•mcrec &. (Rtl¢r�.,rY
InN�aro l'o lxYpoh mp
iC47fNSf•33000M Cp,crtle frx5ukwdkr ADA RAq�
H'7i-70123504 iIp0 L'oacrele la S,dex 414f,AhA Ra,J�
03Mo0
a0
M{,x1k,l�p
Mix Dcs�f
iw[r.4n L'merpe� rs
In¢INn Cweoanede A�prie+,P
�Mlgi[•1. A'S1 53oa0 C— ht,. lur Slder'aMr. ADAR�
71,1{f1t{SpP55h5 4UW� pauw.,dc AS.+eF+nt Md-d P.,"
9+V=2
%VZ(122
03 30
013000
Mix F�X-�3'�i,
In9rxn Cwi—i. & AAWW*r
WwFt-I AI[ry5Da145d1 iConnciwLv ltimli!IuWI'a,.x¢
19�Aaai2
9rv12032
03 ]000
la,a -'Ir'
iu.ram Comm&A.4¢x.un
7MWR•Ia1.'f0Vd500 u.r C-1-4r UmW PL—d 8z,m.
WW202
OS 311 U0
'M,x 11c 1,,
1. crrn Cm uc & App'c "
161PSSGM a01bi Cuntmc for }IxiJ Placed A4,rr¢
ww2=
033000
Mix Dcsi¢n
1nr;rmn Cuaune$R .mr.nrr,
e'J9P51iF53aM p,{F'wp.Xnr-Mnfrn 6,des, A6. AM. R..L
CITY OF FORT WORTH TRANSPORTATION/PUBLIC WORKS DEPARTMENT
STANDARD PRODUCTS LIST AS OF 05116/2024
I
C-te(C- Inucd)
1.117/2023
03 30 00
Dux Bailin
J wana cuinic un; A ewlu
919 1U22
03 30 00
]Tri TFnlna
ledranv Conc+cic & r(wPMNw
9 i.70..-
0))Crw
Mix Bc:�:n
Holcim-SOR. Inc.
9.9:022
03 coo
Ali. flpnin
1lekun.YOR. k.r
992022
43000
Mrc Deaim
Holcim -SOR. Inc.
R�Ro22
0131200
M Dauw
Holcim-SOR.Inc-
%VPQ22
033000
Mix Dcsicn
Holcim-SOR. Inc.
ga21M
ingull
�lix lk+p
H01c1m -So R. Ine.
1211512du
330Wi
M. Oeuua
Hulrim-SOR. Inc
%VI"22
043000
A4ix Dcsicn
H01cim-SOR. Inc.
9t9/2N2
Il37tl1"
Ix, 114xu1»
Ifuk7-!K*.l t,
WW2022
0311.
Aln D'vien
Hole anInc.
I2r5r2aI2
430W
Mix 17 v0
Hdpm.SOR, kt.
42ROIa
33tim
Mix Dcsirn
Holcun -SOR, Inc.
91gR1120
d3 3d 04
Mi: 17a.y/n
Fldcinr • SDR, J1.
VW023
0]]V 00
Mi a Dort
Holcim -SOR. Inc
9f312022
M11109
'Mt:l
HOlciin -SUR. Inc
4f1R023
W 30 Od
Mix Desi-
Li9wd Swne
4f2N2021
033900
MI. T"Cri
IJWldilPllt
427 M3
OS 10 00
Mrx Dnien
Liumd stone
lr;?440;3
D3 ]0 00
Mix Desimr
L IS",
9N.20)3
0] lw 00
Mtn Delves
rim Siula3
li,W )2
033000
M.Dh10
blulin Main,
91950u f) 30 00 AFrxNAM Mo w Ai-0i
ilAr. 2_ 0)5000 Mr. Ikallm Muu.M""
III"= 075000 Mi. 11tupn 1IwIft llarn-raa
jUl712023 035000 Mix Du n Mpnm Mantua
`"r,0',2 b)3000 Mix Dear Marun M1101.
97 W22 W "I"o 51 ra DDc0,xqjy,f�, "I'Al. Mantic,
4N:U20 0)3000 MI. '• ?IMiP3 Mariana
SU 00 if .x D- Martin Marrow
99f2021
0) 30 VO
Mix Dcsien
-
Martin Marieua
4.4f)05!
W 3000
Mix Dcsien
Marcha
tin Man
4P3R02-2
033000
kA. rie k"
}`�,rlama Alulcaa
9/MQ23
033w00
11 Meta-
Maninhwkna
9R.4d33
033000
Mlx I)N.
1ytm Afy.erlu
siffll ii
0336d0
Ali. rk%W
'dlanmAluwlu
I Ff2R012
]I 13 i1
%Sr;
hlsttn ALrurta
110/2032
32 13 {3
11. L.
.- Mantua
]2 I] !3
�L;11 0
klxhn M.uutta
:III=
I IA310622
]3.1313
rk Peuun
Martin Morita,
tic
11TSIM
341313
ix Dcsien
Min
ary
I I1y12022
]2 i3 I]
Mar1111 Kamm
11/2/2022
721313
la Flm]n
hfsrOr.3rlarie114
I l?ZaM
17 13 13
ix Dfxi�
Martin Morita,
IRnnr1
32 y113
�4,flx 1), i-
Marvin Marietta
I IRlSw73
I1313
AM!=Dt>aFp
VI;Mkl MAiw4
30 W
Mn i]ealpt
M-im Kledolu
91Vf2Q2:
>D Ib
Win r]ct�
Mmm Mor4 rk
9i4-'21122
�73wW
Nlnllpren
Mmrrn]larinw
9"ReNn
p] W 00
Wa rkuml
1101 Muneiu
9rw=1
'i0] goo
�fr. Vera,.
Mu1m 31ehm.a
9.Nn=
03 51100
3Tlx D.
Manta M.vu
yNfIC22
33
0o 00
s1n Fli gen
,}atria Alrfplu
4t1/30)3
2112w
tin 71"Am
1Wnn Murlellu
31i 2d73
3000
Sir. fkvpn
}farm xlaiWa
4 1•'b13
'''���''�j�ppppp] 3011111
Aln �pn
Matra "lariat,
47.1W
}213=11
116a 0-11.
Mama Alorltw
14?)rZM
p 13 13
Mi. F)-m
Mama Mrina
14111203
3edw
Mlx II
Marlin MaricOa
J5-22=
3J 13 1]
Mit Dr..��
Martin Mancha
1411R023
3 3000
Mix Design
Martin Mantua
]0[(�ISON ]A0U PPqq// L'9nuele Fa Drdkd jhJI1LI IJ�Ono and HdBe Srenul Fwntlprtp.
yN r,5i M4So P.{Calorn=Ilia r Hand P4c'd ,a no
5177 30001ui Conant Mix for Sidewalks
yUl 6- 30W CWKf9IC Mia for Sid-1,4
2125 450Concrctc for HES Pat-,
1701 4000 nst Concrctc Mix for Stonn Drain Structure, Sonilan• Scwcr Manholes, lunuim Box
5409 4000 psi Loncielc Mix for Sidewalks. Inlets _
5507 4500 nsi Concrctc Mix for Hand Placed Patin,
374I 100 nsi concrete for 0awablc fill/CSLM
150172 001f}}si Concrctc for Base Material for Trench Repair
Jdwd]ode pal [--trek Re Drii151xaM9,ly�ttirx*and TraOk 5i411.ai F0una+amn.
I+e513SOwTWCpepctefnScumFkun uelwra.!landPlaacceedd yj
I4R12 ]6W °�L'arpdc f Ikrllal S1uRVLFklipne ary1714Uk Stated FuueSuruba
I5940 3600JJ/si Concrctc far Machine Placcinc 1
a594pY0 Cunene MOWS7urlyhry61in6 and Traffic Sretul Fucndan-.
5940-1 40 0nst Concrctc for Hand Pluccri-
115513000�+ i Concrete Mix for Bluckine
C301 D 3 000 L'oncretc for sdew40.A .1ppra4cher. and Dltaxx.•4+�
C]nilk�113 ,\d''CawPtis fp litl.+fnv^�, 411,dnWn41'[�Pncextniwa aKh
L'361 DHR 3.(, ppsl Concrete for Drilled 51iaA/Linhun¢and Tragic Sicnal I'.andai an.,
C451 DHR-A 4506s, Concrete for HES Pavia1,
R21122141.000 Pei C-c Fer Stdc-lk. &. P-IFA
D94ML' 5.W0 Pr Conn for Sidernika& IIIM 4
R21]I'!P43,d00 Ma Cwade faY WI,-dk.,4. �anprt
R213131A J00d pti Ccncret fro SkL-JM 4F etmr
)I, I wi14 3.000 oat CmCde f0151derdka dr R41r
R2136214 3.000 ns� Concrctc for Sidewalks & Rwnns
R21412244,000I Concrctc for Sidewalks &Rmnns
rp-p 141034 4.WO jbi Cwrcrpt far SWc-Ik. &. Rung.
R:1342243 AW Ma Ceinmi f C.15 T.Iela
R2141233 3.600 Concrete for Sloan Strucwr,,. Inlets. Block- & Encasement
FLOW21A 50�I ii'.rC1cicfor Flowablc Ftll/CLSM
R2142233 3,69,,i Concrctc for M-1.1cs, Inles & Headwalls
it314U3713.6d0�.I C4ncrtle Yx AlnrlwFet. Nkln& IkaJ.vB. Cenerelti ppieni
R3141P]W.000 p� L1prltec Jnr Fr .hL*x, hdn. & )1ca1-4 Val. Padx
%21400334A00 drl Cana xIcs M4nhY1p. lab. 4 Itesd.nll. Val- Fad,
31214h,054-im Concrde for Band Pkotd Pa." . Tnlca. Skym Dram Stly -
'yy'yy..��''141N174.01Q pot L�sre itu Gr M.M1me Pl- (�u0r
4z3A i R!0 4jM r Yon.acw !a M.,i P -- Pl4cod Pds+ne
J I46N394,500 CiamicKt for R.J PLien1 PxmC
R2I46K36 4.500 psi Concrctc for Hand Placed Puxi.rz
R214 P36 4.500 psi Concrctc for Hand Plxvd Pavin
R] 1414X364.500 Vat Cvne-00 f., lend Plaecd Pa ''+V
,BSI49V33 I I'll Midi 14.S90 50 eaatme foe HaindP+ur Panrrx. Inlnw.MmWra tkai.1-1,
R2146K34 4.000pi Concrctc lbr Has, MJnhubm Hudw411%
R2141 N24 4,000 usi Concrctc for Sidewalks and Rumr�rs
R2 k41 R244A00 Cwc4eu la laawlat BOagsxlerdAs -d ii
1460"+sow P+i L-anonc fa Inks . Sti-rk is srractlrr
R214MM ,SIR 09 Cut. ox il.nd Plated N-IL lodr6
R 21460424300�IeiCiil fet lWtd Pl-d Penn%
112146242 450G Cu pe fw+Fund PLxcd PaxinR
RI I46236 4S00pr Ctrkrne for l6nd Woe d P.tsinl
rMgI5C 4 W pal L'--Ic I.IL d Plaecd Pannp
0214r&14.500 (' wrap Gr 1Wnd 3.. .Pa>nr1R
RII)BXI4 5A0 oath; 3,000pl cvn.Tneftlr Stdcmaila
"_186d334n000JM��uoc�rr-q 1 MON Do&
%:13EF:1+].U0{1JJff earerrrR a11a.wJ Caryl{{2�
1001AIK7w g11W 0d I L= MI 44. 26 Wn. ro 111;5 Pannp
3101.BP 3.600 Rsi Concrctc for Rmm�in^ halls
R2146K37/6.22 sack / 4500 B� i Con crctc for Hand Placed Patina
R2141030 4,000 psi Lunatic fur Rmrap
CITY OF FORT WORTH TRANSPORTATION/PUBLIC WORKS DEPARTMENT
STANDARD PRODUCTS LIST AS OF 05/16/2024
Coo I win
L7J202]
0
!In Clot a
A1,rtit, Sinerna
H7C427J4 4,0001.1 Conirese Ier R'"- IX-6
$01=3
321in
IMnD�Cn
hf+nm �lxnpu
R_I76R]D S.WO i.0 C-m. for Sekxll,,ad RaiF'•
M1 i 21173
�32 7120
�1h np,:su
Marne Marictia
R1 1 20 3.000//,s Connac far Sidewalks and Rmn
�,
03 3090
Mix Damn
Marlin Maricua
11 14fiN41 GA4sacks / 3.600 nsi Concrete for Dnllcd��ians 1 l' unu and Traffic Signal Foundauons
D 27 2023
bl'dd DO
Ahs t}u�pn
Al+nm Mmnfo
U:Ii61LiS ld��C »ck+- ].SpIPP�lCarcrcte for fhdGa156efk I.I�nnY.nl7raDcsiluai Fwnu,uuw
16'4r2031
3p 99
�Ila ne>'en
Marnn M_11.
U2146R4116.44 sacks 14.500 psi Concrac for Dnllcd Pwn•I iR 111 � ba cs
w4/2023
0}3p W
Mix
Mann Manila
R2136R14 / 5-00 sacks / 3.500 psi Concrcle for Sidewalks and y/�,'�' `
NAcr033
3213 ]0
ID3e�sdig�n
M.s' "
M"'n, It'
R214lR14 -' S"5314,000 nf: CIf�S.elc RR leea:at Flo'Bo. l'�.'l7 y�.1. FkR J A.R.
ZL 411023
�739 Otl
lr'
Mix Devlin
Marlin Marieua
R2146R35/611/4.500"�..,`I1CConcrete for Inlets,Manholes- rd Headwalls
fV]sl=3tlw
Ai .lkaffpppp
15.5+•un Aluvu.l
Alxiill+
r+1�11erdw'+an�D..
yyRx''3a1Sd11 SAY+1d.r4.09DIH LwiwuKHcf AFaek eVWed
A3uolu]IG915xWr{,OpO CaKtcic Al is f4w VIP$ a114adsule.
1129+3tl13
wmil3
11330W
43 30 0
■tn fk.frfn
Ml. l)wpn
AS4r11e
iSa ne Ala nv
mi
iLPIJpKl}7hpI tltltl R�1 L'mcrcic Ail. k PP Sc w M nNvlp
4FII1
l2R2R073
32 I3 1]
Mix Design
Marvin MarIeUa
=14
R214GR44 / G-GU Sacks / J,500JJ,si Concrete Mix for Hand Placed Pasinv
471]2aW3
32 1113
MtaDci0n
2-t4rpp M+rt
R21401C441 fiW S.'Lf l4_:5 pi C-ar Ma for Hmd n.;d Pn p
WRIM
3213 20
Mrr 13[aim
-ai[Y Rn711.ita
401113000 PM Cwrcrne P1. f cwt. A bluer" rh.ww'a "Sidmil,a
YAVd012
07 )Iidp
Mie nwjz
NIIR H-1, M,
C•-YY 3000 C'e. i Mia its CSKhlnkf.
4,W7022
93 30 W
'1fA Daam
NRR It Mix
TX C'-NY 3000 nsi Cuncrctc Mix fur Curb Inles
9172r2D73
bl J0 UU
Mix Dwig
NRR R�cud/`y�Q,M�ix
CLS P -YY / G.00 Sacks / 4.000'Vi Cuncrctc fur Cellars, MadlrMak Am' C•9i.atx
JOW2033
033000
Alta l.Or}�1
\TIR RpidYelI
CI.SA-YYlS.00 Sae1:i13,90U 7v�. L'wrcCelvf Y70CNa8ad 8.+ng4+aC ['ut6@C.unee
for & RainlV Curb & Gutter
IW4l3V33
03 30 00
' Ira D. ,,
VAR R,2y Mix
CLS A -NY/ 5-00 Sacks / 3.000p� CmlcrctC Sidewalks and
I4114RU33
32 13 13
hln Dp
KRR Retrfy ll x
t7Ii. SF.YY 1 S.595aekar].G00 L'pnanr Sor M4eitpr Plurd Tavn0.
19W3022
]2 I3 I
ylu FI.-.
NIT Rc+dy TRx
17(C5PdiY f.S05+rksl3hOV au�nnune fw M Tune P4cc+f P+xnr
SF'N
IN4rW3
32 i3 13
'Al. Design
NBR Reu v Miz
CLS / 6 50 Sucks / 4,500 psi f wo' fur !land Pr4a Petty{
1aVntll]
P- 13 17
\lie D.en
NAR Ready Mix
CLS P2-NY / 6-50 Sucks / 4,500 wi Cunene fur Hand Plared Pavane
1 Wif3037
D3 34 13
11i. f?ar;n
KBR 11.9d'�Ila
FTW FT OW F8].1 {jp Wnune fx Flw4Hc
4113/2024
13 30 00
,Ili. l7pgpt
KIIR llcadr lln
TX $A'Y 15.34SoC1u ['oPcrne Mot fa Caw. S Slih PRvnp- N. Fly Mir
4'IS met
b33000
!tx Deatvn
A7BCRaM Nn
Tit5Y3'1+,505aek.14 CuneMe Mrx fa (T Skeh P.7
10 4 2073
32 11 ]0
3Mx ilptdp
KBR Rp1d. ilia
TX r_-NT 470 S, 9u 3 i 'ranee forSWcwal4. T['udx. C�
I.
4'1S:U34
033090
Mix Dc
NAR Rcodv Mix
F0020022 / 2.5 Sacks: I I�si Concrac fur Flow Fill
2i1AR92]
M0U
Mix^Ta
O.,birn
30A50MR/5 SK/3.000p Concrac for Sidcw,"
7rlw2023
11 13 13
Ills. ik ire
Oda,m
dSA60111168K 14,500]}j��l L'taan•K foe Ii+nd PL.,d Pa a yt
3090
M1x Denen
Na�l1j R..ri Mix
RRM631'. a50001 i r" IneU Fete f Ilend Plxal Pa.mqq,
:12"201J
IgfRa21
W 110
hla >'leyan
Ramd R.41 Ali,
3tRM5525A 3ft00 l;ro�tcse 6w Vallh•[iv0a."$seen Jl. Alaruuehea ADA 1t-.
13-i
111$ua27
r11M110ii
39m
3000
Alex Dni,T
Mfr Deu4n
Rapp d Red i Mix
R+Md Npli Afla
RRMG020ASS 40r1D `rsi Concrcic for Drain Suoctures
RR:f337PA3pWJJ''pp calcr:sc fur Rleri,/nJY
OG
Mix Desk
Rapid Rcdi Mix
RRMSU2OA 3U06 i C.Ul- a Qot CnA LMlep, 17113pY+5� $klea'+IL, R+rip.
111S4p23
W01702}
J M
li's'l X00
Mix Des".
Rcdi-Mix
',
DCA2r.554 3000 nsi Concrete Mix fur Ril1,, R,
9RIHI22
OS 30 tltl
Mt4Dm8n
RrdeMt.
V071131+3000['retcene Rlu. Fur LLrL di.uutt
IY.Nf4932
O3 ]J ll
►tka Dc"'t
Rede•Mis
F0Cip02l 213 Ax' LWwiblc Fill • C115M
IWW]922
3000
Mi.D-W
t:.Vts
IOB SSli }000 pa C'prlpLeF MI. far Ikrx�xy $Fkxuik4 ADA Rvtr44
IYN73032
�}
] 30 00
Mla Dn*
t Mix
10111504 30w [wleree W, fat Sdne
1ww2WIt
]a 00
Mt Dma
Ikd. Mrr
I0LH5041C $4yL414im imxre9r M A w NI.L Nx,L"uY R tlffw. si u mahotL Nifvu, S 3ur tka Dww
•+V#[81
O3 ]A 00
Mix Dcsixn
Rtdl-M
IOLI 1524 / 6-00 Sacks / 4.00 W Cuncrctc Mix Mznhulcs, Inlets. Junction Ruxcs, Headwalls
9i2L22
933U 00
Mla Tkytl
Ytedu5la.
'AJ115143500,gu Lbtrn wWit ro, Tt". Ill YaIKPads
W391i022
033000
h3ia Deuots
�lydn Mi.
1OL215YA d00Gp.i Cpterrex Mi. R. miinhdl.
19,Yr2032
03 3tl 09
Mia ruiti1[II
Rudt Mir
IShI lS:i i00p�p Ceeirtic Sin for C+v m. P144CIiiwtr 17ra SerYawsy
I' W3032
Oil
ran D.v.gt
Art4 �Str
JOLSiliia 3COQ��•.f1 Camas My for Andtsc risauclur.•a
19iY12D22
07 ]000
xlt. rk9yyt
RaN!\la
1561156140pf M�Rnd1l�shM.l
19.W_07]
0)N 13
\tn De o:
pyMra
F]523F4Ri IDD prs#Iw'+Idr full-LT3H
IVrv,7b32
Q3 74 13
3!n rl.•a.p,t
edi'xtn
POD118Y51 100 FIow+IMe Pdl • CL.Slf
IOm2032
1O'N30L''
033. 13
013900
Hn lA iqn
%4t. I",u
�!.dl•31n
�ed.•Hn
Ip311553]� •naaelCHnf R'yHm
lim".151UW 1�Cneesne Nnfw 7rsneh Aelurr lWw Sl.Wrral
IWY13022
U3 30 00
Mtc Desu;n
Reds -\lax
10KI 1524 3600 w� Copccni Min for Fneucmeni
19 9 002
D3 30 00
.1 D--
Rcdi-\bx
ION] 1507 4500 wi (2600 wi (' 24 It.-7 Concrac Mix ror HISS Pavane
1v.9 30z`
03 30 p0
Mix D.a
Rcdi-Mix
ION 1 1504 5000 nsi f3600 psi r.2 da y Concrcic \lax fa HF•SPp>.pK
Iv92o".
0330M
m„r1n.r:n
Redi•Mla
50KIISM SOOtl,p+i C.]nCrge l.In Wr��LMr PI.�pyPw�
Iv.9C0]S
b1 3000
Mt. Deden
Rrdl Sln
IDMI IS'4 4 pxl C'oncrle Mix fw ]Lind Plaool Parw. hrainsenulutp
17.Vl2932
b1.30w
Ali. Ilnrce
ROdr•Mi1
I4AII1$344590" C'nneneae hhn Sa Ifand P14oa1 PA, ine
j9:VR012
1000
- Alix Dwicn
Rcdi-Mix
IOM 115044500 s Concrete Mix fw Kod Plaoei5 F6im
{YPi13023
30 00
Mii mmori
Radoriia
14507514 450dm, L'tsrw Ali, far ILad Pixel Pain[-Slamn A. Strmiwae
EI1112]I�
OO
RlixDe
R.µAlia
a
IiP25P4d1W Cmetr ffuor S�nvSiatlehahma�oincDuYi+SThuNr.aa
7JRN22
3000
koStvm
KIIHF5rCpnaelNrr
I120022
33000
Mi
Rcdi-Mix
uadrp..
nP
CTlalPs
115C44000psi Cunrctc
523
10W
1x
Ro•Ax
IOLI I iC{ ]A00 pN f.:onnda fv AlaMwlp into. I'm B . fu+.lfe.xlwdR
PS SP2023
p330r10
Mix Dusgn
Rcdi-Mix
80LI 15D5 3600 psi Concrcic fur Dn11cd Sba1ls/Li r``L npp and Tranic Si :m+l fuunilb s
S11 I77423
033000
7Mia D*
bRcdi-Mix
I ON 115D6 SlunDisplaccurent ShaRs. Undcrwalcrnnllcd sIians
tom Ratl�['wh&. Guucr
7777]!32
0334 !]
lax flops
�ix
P faraau
IONI"900 pCi Piper SrdewvRra+pd
40050 4.000p Cuncrctc fur Headwalls, ]LnYnuln WAl, Cu"'.
9RR022
03 3J i]
Dwian
SRM Concrete
P 33
03 30 00
�Isa rlv4lpn
OM L'0nw
35Od3 I,A0[I ryr cu oLi, for M.,hrnc PbmJ P+tinR
J%V2D32
03 10 00
Mix Deiii,p
SRM Can-,
40068 3,600 psi Concrcic for Maehire Placed Pavane
CITY OF FORT WORTH TRANSPORTATION/PUBLIC WORKS DEPARTMENT
STANDARD PRODUCTS LIST AS OF 05116/2024
w9ilp]2
03 30 J
$1. Dwga
Sk?I L'w+ncic
153W 43901¢¢l Cuwew Wr Unk Vtuol P rink
%V? 022
03 30 00
_
�111 ne. n
SRM Concrete
45000 4.500 ���i Concrete fo Hund Placed Paving
99707:
033000
Ih1a.[See
RSl cmrnte
4031n 4,5W I3.0003 1 Cvavnc 6r 141j pariq
9 Y.20s-3
33000
131110
hha Dwl
it C'tlnemS
SS0I7 3.600�sI Can[me Wr Swmoim 13w. Ruynm4y Wale
1' _ _ Tlurul BNda.l'urla Garter. Drsacr4%F user Rnnp
9 930_3
VIWt033
n3 30 00
033000
F ax Fmrkn
%1r. r1pr,;n
Rhl Ceram
Sol co-ew
Sao503.Q01fm4 C'9aeeele fa SdcwalkF R.-ipc Inld..JwleOm vmd
mII III S.WO pJ C-t Cie fur SfF.9 Parin
10134202/
33 1313
Mir ne,im.
SRM C... reic
45023 4.500 n,i Conerdc for Hand Placed Paving
'I11I301[
031000
hlt. Tlu.a<a
sIIht lYlncerr
9p6+ C9+MGr f9r Fl-;"k fdl
111eN/bl
]090
Mlx rx-00
SRM C'onen'Ie
PPS VConaGt TrK h! 7 ar:h R.Prir
•I71�W2a
13000
hliefk44JJ/I
SRM C'mcnre
vlpl cancrne la [7.5s1
a71RUIa
3O aD
hlix f]e.(a9
BRAS C9ncrle
�s00 C-,.-
s7+b373
130 WS
hhx ikran
SRM C'wwr+:
TM S 1I.1Am V.V' ooe rn IkL+ aadr Stair.1)wk S14
l9Pwm.
�l },l pp
Mn Da.lyn
7 J ['unerne
f'N'm%4P 4500 - r-m htn et lW plpurrnk
19NR013
Ila
Mi. lky
T am Cnrexne
G•A'm1v.3}IPJ CurnNe Mn Fv<Ilu+.1 PI4M1 P+Idlk
OS]0 Op
Ml.l1
Tara¢ C ele
T(7Fw60I0,%UP iSGI�1 Cawda Mir fpe Ef�M P1acW Pn;ny
1979#a12
03 30 00
hCe 31wA
Yanm1 Cwwgx
PN7320.111R 459tl 13p0pyti y, 3da>�t pkl mcrecs III'S Pa..�rR
:%w2nI
19ffiFM23
01 a0a0
mna13p m
T-- Cmade
W6S20AMR 4MO U nri 6ir Yd}yr}gp IIFS Mink
IWWWZt
'm 3000
Atha prrlapV
Taaranl C'9Paere
W3520AMP )M*ryi Ccoome fur �{ach- Fla..$ P-g
1.%W3023
9S 300a
Mia 13pem
Tamnr Cunerc}e
FZ0ATjWLCiewb R0-Ln$35
19720Z
034 I3
Sa }yr5Wd
FILSO•I h[
I9.W26'»
0] 34 3
MMikikAo
n [kaibr
Taaarx!'omfrcu�
FWu'at>Ic }-ill -i'LRM
IaVf_`�3
03 30 uu
tdtr I7ulkn
ianaM cumda.
Cutmne Mn for$n>rm 3luar 5+nwNne
IIWEfVdV32
033000
hfl. TS:aika
Tur"O.,pcic
A_ L'munrS,r Manhralea
1H V/-'U!3 033000
hhr Tkalpa
Trlanl C.nunr
TCFWj020A 3U00 qq�� [lxrnrlle fYrSidc+wJlr
1979R0.2
03 30 00
hllr ti.
T m Camp,
Imsms,%1000 pd C9M+ese Nn f Croht [id1¢r, fhrvvavy, jrJiWalk., ADA itrrSrs
191tlA3,:
0330 00
hlax I)ryrkp
Tway Ill S11n
3oull Sppp�1 Cmaeie C SIMaa16
191WIM
03 30 00
hIV. Dnlpn
T art Car me
L7SO:OA 3000jr Cw ,w Mn for Club aed iayrcer
1VM311 1
N 3000
�L. D-o
Tarrant Cemrrne
F'{VSLs5A1 ]¢�I Crncrrle Mn fw 5r ;Aka TNLW AOPNd- ADA Roar+
19 9 30.'-3
h3 30 00
Sl+. Dcsilm
711aM1 RcriJJ MI,
IRC4320 45W P•I S mercitf H.J P", 1, aid/
19 V'30:2
30 [ia
M. I]eukn
TrycGm Reds Mlx
'. 'p-SOSHI7000 rry Cmneve Afi.f wI CWSA[krtP•I7rrrerray Sir. nllA gmp
19 9 fiuu
HI.
Mix Z-.
Troe ehn Roll 'An
rr70.23a Sa00 +tapprlc In IWd PWced P.W.9
9 9r2021
613ow
stir Ik.1ym
TI Gm Ill 111n
OIS0.1301 pV C= Ain fur Curhh cmi-- Dllxaa'ay. ]id[AaRt AM Rapp.
919P_0x3
0430 as
Mir
T."(- Ill
b26013P140DO p.r CWdle Mit fm himbine,Iurd Paunal
9+9n022
03 3000
hAr ik..pi
T.-Gera PAJI Mt>,
3600 p.r C9nuuC Tlla fp hlacMne PIocW Parrnp
9.nX2Q13
03 3a00
,Mir ngym
_ Ti C' R0r S1n
�b355]3F11
IVtek1.i301 4W N Cu.vmc.Al;a fa IWied PluCu1 Pa..nk
9Pl/3011
OS.00
Mix Iheian
Truc Gnt Rcdi M1fix
0205.2301 4500 C'ancrete Mix for Valle+ Guucn }0mJ P1,ypl Pawnk
a
,)on
Yi IS 13
M.p
NOdutler?aU•Nh
j6ipAllh[10 11A00 C9 M H lc Wr SIMI&;ne PL-11J1Ptn�ln[
PMyi
E I71LL'1013
as 30110
n Fkq w
Wlldouc Redr•Mn
3d30A115.02 Sack. 73.WY PV t'a w M i fn i aRw and L+¢d.
4,tn 4
Q137 all
Dwm
�3-aldc.aOp RednMli
1sl 7 Sack. l 3fVi to dd hlia Qw Foundmwf1SWWWh
Mo.
t W0r10x3 0311,
L F)mm
W 0dw0re Roll Mn
40HIA110.0a S.I. 7 4 CwKraIe U.. leg %4caalkxa W
iu F--dadan.
VM022
03311 p1
xT3ai yr
Wiue Beth Mr.
3bu 3600 Pd l-usaGe Alra IJphd.1 mJ7ranlc SLymal
ti PayIK
Agt102i
32 l0
Mia A9deu
T.r+c l]I.mc S,
4NP.tlI1
32 12 16
%lA Mm"
Arsiin all
DAS[31'r+0+ ' Tyr4 DR-fi-rLa u
9,V'lOQ3
32 I3 I[.
3lI. Dplm
Aua11n ia1+
FTSR 11 T%5 PG64I' Y1oe R Fwd ltdc
9 13._0:3
311216
h1A Deno
A.M. aN
IT-111 P9011'GW$ SiFnnR-
99:022
13 IS i6
hha T7aiva
Amr14 all
Fi' LB117,3 ppjn4.22 T1W� Fin¢nue
5IM24
131110
3112 id
Alit lrkyre
Mix Dnasn
Bernd . call
Rem=A Ir
34o-T3Gfi pLi6•I•l2T pp��i111a1c CwnC
390fD K4Gd•31 T3t�]1F
9l9/M22
9Annsy
32 1! sn
Mq Tap r+
d. I
111R P[i61.21 nTr�AA pane
9R71032
32 12 16
u 13asan
Ii o-1
1lCrnyld.n 7111
f6128 P[ioF32'hPcA Flnc Boa
IN3114G33 321116
lsik .pr
Rnswlar au
xIOiD P(Na.kSnn nfltx su I-
97R4033
321115
lia l3cWm
Ip-prnwnl wink
341DVA422 PG0i•2 IS Frnt slur
1111wo21 32111M1
1rx lSuwpr
5omwwml Pp.ilrk
A0nW nP11W.2 34c F.na5wixc
1715'342i
�3 It Ih
in flwian
Sunr+awm ParanR
3070RV6417 PGp2.1Y Tmj4� Fu+c Rae
BTSne
4+'P.7023
13 11 16
�Irx [1 rn
Smmuwru pnma
Sal-RRAP61111:R[1 WTo- R Fie IL.e
ImIu22
32 i116
A1ra [`k.:an
T%B37
37.111705.xA IYibl.2;To-
T1oe D i 4c Fuw
VnAo 1
33 I2 Ilk
Mi. floien
-r-AnIT
al•21 IW47 PGW-12 Tyne RFnrc Slat
WV&WIl
3112 In
Mil tk-w
T5;nrr
111HAS I I n71 1`604-72 TypeB Zhu Hkae
9Nfi0ri
31316
Rita ileusT
TXBIT
231471(10 KiMs1 DFa+c S.Q.
9191J007in
Mta D+. p
TxRD'
19.11347s.T PG61-2x I us Surf Cc
9P1R122
32171n
Mia f3rsaAn
Txn1T
i•232a7y10 PG64 •i2T F-�nt $urfaae
A4R02i
12Ix16
h[ia lltwlp+
i%1S{7
n4.114i]5•III PGTOv'3 RFrnc yWfxc
11k9RE}23
131216
Ml. Phim,
T%nif
1A:22S75• I9 PGna•== DFare Suefxc
ilit:02i
1i2331f,
�1ia 11hikn
JXAFf
�44 MA^SP-D T022,.�.,..�..-1: TrpeD Glr Sw$u
I
Deleclable
Ward�nly9 Surf-
_
19+V12022
13DWs.
Prat.
Pr+x}1a11 Daek f9AnNm Salem, NCI
TarLIel4rNa19a4
on
321320
pws-N-
WnlunilrwkC•x7flwrWan. 7x1
TSelmlalleglom3na1%9210
321750
1,3,
T+q+rwg4 Pheyrk*(WdllumsHl(e Annor T&
1A
yr)ws-L'aiymle
�. °'�eAOA
PaKr147101]
?mr
7w!)Z1331]20F•
'1]10
r1W ,1y'Pa
Solw.rm. EWilriknd o ,'% A�
I7ciceldAu WarMI
Pa+ma
FORT WORTH. CITY OF FORT WORTH TRANSPORTATION/PUBLIC WORKS DEPARTMENT
'tar STANDARD PRODUCTS LIST AS OF 05/16/2024
91�2Q_'2
SOkan9 Sr4vr
121173
6nnr0c
11im Se.lmtr
Dow
nl,n Sm'S9+9
22
13T3
TlmKY
• �1[dSa�tl: wnpnen4 SiGC.nr lgnl Sidanl
15-E
A5T]i F157{93
I32
32 13 73
IIdn15uJ4nr
loon Suf4ni
PCrnra
- L'dd�� k+1. Sig131r Cogreenl, 5dunrx 1uIM Sca}Mu
RST6I 173%9399=
321373
l Sw4n1
Crx&n
ater Sd.em-CulffdAlKdied$wFk['arewnenl: S.Iu1wYc 7ulm ScVlml
•SSZM D3641
'
IiWk3-.Tract
Em6.dmw 5md
9.92D21
�J3 0 10
I ��i6nt�ucer sued
lklw�LT&LAM
V3G
11313
IF'-rmbi
�Yxp?furl
17.
9
O5
n
M� 3
'
IO
f 5a•M
]Imm.
171 .I .96K,kNIrnI N,m
L
Slpswsm--mm.6. a n1gAdlFrap14Y6 Cn'var6rntdwdllleund133-MI3
9rYYM]a 371151]
M+Nwk
'Kq-I.Tl
R►:pn05 LW- -•Si3ALI
ASTM A40 AASNO MIM
nl 33 O1
9 c9
ti-`r
Fcml
�F27Tr a
TA
jTfl3 aD069,
13
i3 p3 ]
99M.J31i:2'00131Y
1aWb
4nhWnxFFwramn sad Cwv.
t 1 --ld:,
N1: 7431 m 4]1'".r
ASTN$ MY AAgri9 a306I4
3013
ma"CFiA
Nnah1-1
93N301�l
ASTOA41AA%rj;m3m
93h:0111 3]OSit
h4phlc Fru
l-uh Fzdn
X•1741.IlV i5we • 31•F111.1
AM AJS AA591Tp u3%
7 20l9 3] L13 1]
Alaehuk FranA�and C:0-
SR Indwlrk.-•
':79ST Man - 24-T)L l
07M A48 AASNIV A1306
4P320i9 I193 !]
Nnnhclr n} _and Cntrn
51Pl9duw.cr ••
1]10511iirc-l3-Tba1
AM A41' AAS3RA M706
]OMn0.W S30S I]
1l onhde Fmrc. xd C-wr+.
FJ r 3°mutilt I" lades 1r W.14
FJ1017 �yA (7�4C• 3173' D41
ASTM AS76 AAS3R41 M306
Aiw.'.WrvlrrrkpwmlW.m i.lwWNn+..MrLal.'AL-' aM -h--.i Jl -A Wwtrs rryrYr>yrer.. yyegir+i[SpJj.ryl�lw#Y373.Aq rx4.,yr.:ura+a.9r.M 4r M4mm4 pr n.rnn4
�m�ir. rra.rxwra�rnr.rh+.r. Ws..rri
$Igrp li9.ner-!dN &Str9dWn 3]•OS-1}
iprr,+,yljp07I7 4910
Curb 44p.
Fwumr
FRT.I0r AO5.PRFCAST•' 420.. IO'X 33
ASTM C913
1 n'W=0 314930
Cwh wc.
Fwn '
FRT.I 00406 PREGte-1CAST•• fS0'7f 31
A5TM C'9r3
i101 T030 33 49 20
Cmb lnlcl.
?raxcpra
FRT-1Ot{.S�403•PRFCAST••(Sia-10wx4-n
AIMI L913
1101 I= M4920
kurb loWt
Fdlr.rr+
FRi•SOYA3.430•IgCP.CAS7•• ISirc.IV %4$T
ASTM C913
I M 1; NZO '13910
Futcnu
FRT-4%•Id09 ImWA5T-TOP [Sm 4'X 4'1
ASTAI C913
I r9 R;12p 3339 TO
�Urdevk
lw.4ok
Fmk
FIrr 4X4d99-IRF.CASF-HAYF.lSix -w y 41
Ml'F IN I
11013.3010 33 39 20
hl.v.hZ
fntmn
FRT-IXSd101'RFCAST•TEW iS3tc • S X 37
ASTM C913
ll0!4Fi0:0 3339_n
A1a9491r
F.r
FRT-SXS+r167'RrA!iSr4tASF. 16--S'%51
MSIM L'9Il
110RUON 3]3970
1m4nk
t•'dnClua
rR76X6a 11.74lFCAST-TOP ISirc•WXM
ASTht CN13
11p01^pip 3339 d0
A9k
Fonu.r4
FRT14X4.41 t.MYVAST-11AST, 45uK- X14
ASTM CID
13019OQIP 3149w
Mku
Thrgp.un P,pr Firw.p
7PU•I0X3w4o •-mECAS.T INI-17••rSim. IIP7[-I)
ASYM 615
11'!9l3p11 ]3493.0
-orb inKs.
Thurior.rm PJj�Cinw$O
±N).1.3xT-WS-PRI?L'AY7 RiLl7•'rSlrc-}6X3'I
'AST7d N13
IrmIN]9!0!I
t
T Fr)'seG-j
7PC�4X•T{W PREC 5T TOP 151r � %41
AS'FhI q1S
133920
13FIV2011 333Yirt
hlmlwk
AIMIlAc
.un
nwwrw. Pw:[iwP
TP&4X4409"rCAS7HASflSrn •J'XJ7
;ASTM'6t1
13Y191i07.1 33 39 20
ManhWr
Tid,Krwn Pier Ek-p
TPG-AX4.413. PRFC..,.T 4iT R 1SPR rl n 6 f %41
.L4T.h4 615
13/1912031 3339m
jjpmar,un Pp
TOP W.-TX31
'A-A1S
65
13/49=1 33190
P E-
PCI-SXS410-PkFCAST9ASIiISLc-5'%S
TW-5X5alY%tASTSFTRIFRf4u-%F
S61S
7AI1319g031
33920
11100233392
TFMmP
n�o"
Tf%44 I.PRPCAST TOP J&t-0X id
ASYMLIS
90
1]]2
Mt6du
4n
TC-1
n,4,Xa1
61f13494w
AM a
13019ROti 333971$
nawFr,C1
. 6•FT RW-Ft!Stet•6'X 0
4%6d2PRFCAST
AaALYS7�TT1Aaff46
13rI9lA21 313020
T4orwl PwU-tr
TPCr7XF4l-ARCCrSTToPlS.n•T%r
45
1115
'9 I7
I111Y191.Wl3
r[[H,xuiih4alrc
Thrnryrwn P�!hop
TNJ,7XT411PRTAIST HAST.!Se-7'%TT
I
S5S
66
92A392u
3I91 929
1, hd
I.Gr.r.
r
TPG7C+?Z..CASTIFTRISRIS:e-T. X71
I .3Y
TPc4x91111.PRFCASTTvFlt6L-%5T
ASiH t,
3I23339 m
lI
13[9.203133920
11
M-1.09
wO
T]o
TS-p-P Or tirw
i%j4X14141jCASTIIASxiS4re-8' X1l
TPC-8X6.411-PRECAST 5-FTREWRf3i.-0'X RT
Asml AIS
13.14p=t. 13 A910
Iiv. -1a
Tharm.ue nrnc rdwi
by, tRF.L'AST IN[ f:T f33rt-�4'X47
ASTIrf•615
13'19+AN j3 A9IO
I7r9p nk5
Tlmrpn¢ %{�Ciwgl
YPG=j]i5.x0FFPRECAST Rll3Y [S+re • 5'%
ASTAt QIS
AS'Mt El5
F7r1omr I34910
R/rp hkl
'+un
Tromgm l9pr G-V
TPG41i6.40A PRF-CAST IR:][T lSree-p'X8j
Rceat'Cx 4'SA.c alo.hok(Sin 4' X4
ASTM 04Td
S]W2p23 S1 A410
S ]114033 33 i410
9k
Manhuk
lNdcaNa
U1d[ Ic
cl •
iArctal Fh O'Ywru lunnim Rw ltirre • S iFi
'MM C47A
312aQp3f 33 49 lu
af:orhule
Wd-ale
lhruat A'x 4'si9rn. lunniur Iwt 45vc •4'X 4T
AM C471
1P38d3123 13 49 10
,'4" Ole
Old".1c
P._g 5'x S'S1._ l.nui9n Rv. IIS_ S'% S7
AM C471
1(r3ya3a"] 3149(0
M,wkc
01W.le
R6'Sw.m lunp.9n Ru.IS..C•N%6k
ASTAT C47N
fG23
iwc FR 17
ATM C-476
ATM f47%
I 4Y t0
JI1=2021 1149 10
Al nl9k
�rlmlwlr
Uldrlalc
krnka Mk-k
'f'.Tq.QCP9reti'..p
Ss rS um luHnw r[S Ad-S'X
Rnnfoud 4r Di,,wr - Sound puu4nF M4nh9k(PA 4'X47
`AST-aI Q433
8/28/2023 333920
Curl Coln l OIL3'Riaa
IoW Rile i9ur-3F-Fi
.75fM C413•IL
lZYI0 )5 39715
6'b L1ks !S S 3'kan
nk.� P� /fX Gruun
rnkt Rlar ISut • ] FT4
.55'iM In92
1<RA3023 31 s9 20
Curb T.I. 10'u 3'Rif.
I'- 1yyx0'iruu�
lnkt Rise lSlrc • 1 FT)
re.
AM co I-FI.
1r"CO4 3$491'p
hmn Wcl
M.w*rn pt&Pro ucia
Ilrwlells l4'X 4T
ASTh1 C917
1142QQ24 33492p
�Fkwr l'c
A -Tr. Njr&Pruducu
Fkrelrllk lVxn
AM V9
I11W]rCA 334E 20
r
•%,-Tc. PJgC@Pruducu
Pl u4W Sr JWMiM fw4
AST.N LV13
AM LYr3
11191?034 33A921
111wom 334970
3MduAt
Slmdi k
AnKn7r. ((II�� BP+udum
Alk"Tn Fi(e hlhuduet.
PrC�rS�r'Slpm Jwwu -Fiw
5PawlTasrcws ll ll l4'hl ll un Fhr lip uFS1H!
MTM L9il
i 19'7A2A 13 A9"
":",A
AnarrTcn Aglc BP.dwN
Pm4J 6S6'31p 0Kn91ipn Das
ASTM LY13
1394024 ]34929
11-14,
Amu T-Plpc&37'docic
SPrrC.H TWrtirKn 111E;4'Nll on nc� loP udA'1R3
jkm C-911
I.H'21W p 49 30
hlamrvl.
A-T-P4r kPwdikk
P'."X' w S9mr SrmrlNn Fier
ASntt C'9t3
119r30I4 334930
hlmsuk
AvrrrM-Pr Wl'w '
ry'Yra'Cu4 Tonutmn MIS;4'4U3mrthrl 9fR'1H]
ASIAI C%3
j lry9r2034 3149 30
A1�,r4
.u4rrTc.l•y'�%11,Auru
Free [' lu.rm 97- 3Le6ule rm Flua l4'. f un (hewn djlk7ll
'-A7At•µrvnr13a6n a.gp.adJw nlr.rutr IHr.W!nj/v+A..rrr Il�ry.vr¢•33ra4a J1 MGw NlFrfmrrwr
rv"ko fw Ames( inplure X.�.Md,n rrynrtfrnl ubd 7r.04+.N
CITY OF FORT WORTH TRANSPORTATIOWPUHLIC WORKS DEPARTMENT
STANDARD PRODUCTS LIST AS OF 05/1612024
1[ >ZIImNBeRR!'-1'tcudfkvu ii-0&13
[�N/!0al 1141 n
'shin, fn:+�P��
�Ir1w�.J 11t ��ip+ L� IAf1S1
RII�y I1I'`tii.:�tri l'.•Istyl "t14'n: IPPI f�,� IS-1:'-Z
Prpe inuufx P.p[IIy.e-il'p3pellwl
•%7Tm Fwl &AAA j�l mJ39
A`N7]5 C76-Lx7S
F:/=><7tl'-3 SSa910
�p7'S N23 31491tl
Slonn iA'aln PnaWwAIJlwu1•
Cejm R-
n3p V1y.rwl.
licmiercal L'omaee T��gggg�Ieuld kW
Ronfs "CtMcrne Ilox Cviws[Srt • V,nw.1
,
ASTS1 C71[d. C8j0 .
[]p I.1 =3 3341 ktl
S1mn Drwn I%m
%.-.T- PJJJJ''�� &N du
Agin( 7 Cwurno PiK Tpcaur and Q me Jon' Pipe- I&m- IPm tww)
A..' nI 01L C304
1 0 I2- On Hal l0
Cullen ima
�1 txr7 r rr .k i4ajuCv
j{pn[preeJ L-enerne Hex Culwll.ve • Vwiou.31
Ami CWi3.C1577
110 18202i 35" IV
Strom Orin Plan
`[dc 7ui>tn C-a.
�femfoneu Cox 1 pi. I --and Glw.e lwm A-W tsw- 15'ee 7.r�ea1
aml C7n. Oft
I001v2023 A41 10
[alms H.
The Turnn ['a.
Hne[Peeod 1•a — ILn ['ul.uxll.k - Vwtt l
AETM [7alS.CIs77
CITY OF FORT WORTH
FORT WORTH. WATER DEPARTMENT
STANDARD PRODUCT LIST
Updated: 12/29/2023
IApprovall
Spec No.
IClasssification
Manufacturer
Model No.
National Spec
Size
Water & Sewer - Manholes & Bases/Components 33-39-10 (Rev 2/3/16)
I 07/23/97
33 05 13
Urethane Hydrophilic Waterstop
Asahi Kogyo K.K.
Adeka Ultra -Seal P-201
ASTM 132240/13412/13792
I 04/26/00
33 05 13
Offset Joint for 4' Diam. MH
Hanson Concrete Products
Drawing No. 35-0048-001
I 04/26/00
33 05 13
Profile Gasket for 4' Diam. MH.
Press -Seal Gasket Corp.
250-4G Gasket
ASTM C-443/C-361
SS MH
I 1126199
33 05 13
HOPE Manhole Adjustment Rings
Ladtech, Inc
HDPE Adjustment Ring
Traffic and Non -traffic area
I 5/13105
33 05 13
Manhole External Wrap
Canusa - CPS WrapidSeal
Manhole Encapsulation System
I
Water & Sewer - Manholes & Bases/Fiberglass 33-39-13 (1/8/13)
I
I 1/26/99
33 39 13
Fiberglass Manhole
Fluid Containment, Inc.
Flowthe
ASTM 3753
Non -traffic area
I 08/30/06
I
33 39 13
Fiberglass Manhole
L.F. Manufacturing
Non -traffic area
I
Water & Sewer - Manholes & Bases/Frames & Covers/Rectangular 33-05-13 (Rev 2/3/16)
I33
05 13
IManhole Frames and Covers
I Westem Iron Works, Bass & Hays Foundry
1001
24"x40" WD
Water & Sewer - Manholes & Bases/Frames & Covers/Standard (Round) 33-05-13 (Rev 2/3/16)
"
3305 13
Manhole Frames and Covers
Westem Iron Works, Bass & Hays Foundry
30024
24" Dia.
*
3305 13
Manhole Frames and Covers
McKinley It. Works Inc.
A 24 AM
24" Dia.
I 08/24/18
33 05 13
Manhole Frames and Covers
Neenah Foundry
R-1272
ASTM A48 & AASHTO M306
24" Dia.
I 08/24/18
33 05 13
Manhole Frames and Covers
Neenah Foundry
NF 1274
ASTM A48 & AASHTO M306
30" Dia.
I33
05 13
Manhole Frames and Covers
Sigma Corporation
MH-144N
I33
05 13
Manhole Frames and Covers
Sigma Corporation
MH-143N
I33
05 13
Manhole Frames and Covers
Pont-A-Moreson
GTS-STD
24" the.
I33
05 13
Manhole Frames and Covers
Neenah Casting
24" the.
I 10/31/06
33 05 13
Manhole Frames and Covers (Hinged)
Powerseal
Hinged Ductile Iron Manhole
ASTM A536
24" Dia.
I 7/25/03
3305 13
Manhole Frames and Covers
Saint-Gobain Pipelines (Pamrex/rexus)
RE32-R8FS
30" Dia.
I 01/31/06
3305 13
30" Dia. MH Ring and Cover
East Jordan Iron Works
V1432-2 and V1483 Designs
AASFITO M306-04
30" Dia.
I 11/02/10
3305 13
30" Dia. MH Ring and Cover
Sigma Corporation
MH165IFWN & MH16502
30" Dia
I 07/19/1 t
3305 13
30" Dia. MH Ring and Cover
Star Pipe Products
NIH32FTWSS-DC
30" Dia
I 08/10/11
3305 13
30" Dia. MH Ring and Cover
Accucast
220700 Heavy Duty with Gasket Ring
30" Dia
30" ERGO XL Assembly
10/14/13
3305 13
30" Dia. MH Ring and Cover (Hinged & Lockable)
East Jordan Iron Works
with Cam Lock/MPIC/T-Gasket
ASSFITO MI 05 & ASTM A536
30" Dia
I 06/01/17
3405 13
30" Dia. MH Rine and Cover (Lockable) CI
SIP Industries
2280 (32")
ASTM A 48
30" Dia.
CAP-ONE-30-FTW, Composite, w/ Lock
09/16/19
33 05 13
30" Dia. MH Ring and Cover
Composite Access Products, L.P.
w/o Hing
30" Dia.
10/07/21
34 O 13
30" Dia. MH Ring and Cover
Trumbull Manufacturing
32"(30") Frame and Cover
30" Dia.
Water & Sewer - Manholes & Bases/Frames &
Covers/Water Tight & Pressure Tight 33-05-13 (Rev 2/3/16)
*
33 05 13
Manhole Frames and Covers
Pont-A-Mousson
Pamtight
24" Dia.
*
33 05 13
Manhole Frames and Covers
Neenah Casting
24" Dia.
*
3305 13
Manhole Frames and Covers
Western Iron Works,Bass & Hays Foundry
300-24P
24" Dia.
*
3305 13
Manhole Frames and Covers
McKinley Iron Works Inc.
WPA24AM
24" Dia.
03/08/00
3305 13
Manhole Frames and Covers
Accucast
RC-2100
ASTM A 48
24" Dia.
04/20/01
3305 13
Manhole Frames and Covers
(SIP)Serampore Industries Private Ltd.
300-24-23.75 Ring and Cover
ASTM A 48
24" Dia.
Water & Sewer - Manholes & Bases/Precast Concrete Tev 1/8/13)
*
33 39 10
Manhole, Precast Concrete
Hydro Condurt Corp
SPL Item -1
ASTM C 478
48"
*
33 39 10
Manhole, Precast Concrete
Wall Concrete Pipe Co. Inc.
ASTM C-443
48"
12/0S/23
33 39 10
IManhole, Precast Concrete
The Tumer Company
72" I.D. Manhole w/ 32" Cone
ASTM C 478
72"
OS/08/18
33 39 10
Manhole, Precast Concrete
The Turner Company
48", 60" I.D. Manhole w/ 32" Cone
ASTM C 478
48", 60"
I 10/27/06
33 39 10
Manhole, Precast Concrete
Oldeastle Precast Inc.
48" I.D. Manhole w/ 24" Cone
ASTM C 478
48" Diam w 24" Ring I
I 06/09/10
33 39 10
Manhole, Precast (Reinforced Polymer)Concrete
US Composite Pipe
Reinforced Polymer Concrete
ASTM C-76
48" to 72" I
I 09/06/19
33 3920
Manhole, Precast Concrete
Forterra Pipe and Precast
60" & 72" I.D. Manhole w/32" Cone
ASTM C-76
60" & 72" I
I 10/07/21
32 39 20
Manhole, Precast Concrete
Forterra Pipe and Precast
48" I.D. Manhole w/32" Cone
ASTM C-77
48" I
I 10/07/21
33 3920
Manhole, Precast (Reinforced Polymer) Concrete
Armon-k
48" & 60" I.D. Manhole w/32" Cone
48" & 60" I
I 10/07/21
33 3920
Manhole, Precast (Hybrid) Polymer & PVC
Predl Systems
48" & 60" I.D. Manhole w/32" Cone
48" & 60" Non Traffic Areas I
ASTM C-478; ASTM C-923;
-1/07/23
33 3920
Manhole, Precast Concrete
AmeriTex Pipe and Products, LLC
48" & 60" I.D. Manhole w/32" Cone
ASTM C-443
I 03/07/23
33 3920
Manhole, Precast (Reinforced Polymer) Concrete
P3 Polymers, RockHardscp
48" & 60" I.D. Manhole w/32" Cone
I
I 04/28/07
Manhole, Precast (Reinforced Polymer) Concrete
Amiteeh USA
Meyer Polycrete Pipe
I
I
I
I Sewer -(WAC) Wastewater Access Chamber 33 39 40
I
I
Water & Sewer - Manholes & Bases/Rehab Svstems/Cementitious
IE1-14
Manhole Rehab Systems
Ouadex
I 04/23/01
E1-14
Manhole Rehab Systems
Standard Cement Materials, Inc.
Relmer MSP
E1-14
Manhole Rehab Systems
AP/M Permaform
I 4/20/01
E1-14
Manhole Rehab System
Strong Company
Strong Seal MS2A Rehab System
I 5/12/03
E1-14
Manhole Rehab System (Liner)
Triplex Lining System
MH repair product to stop infiltration ASTM D5813
I08/30/06
I
General Concrete Repair
FlexKrete Technologies
Vinyl Polyester Reparr Product Misc. Use
I
* From Original Standard Products List 1
FORT WORTH®
CITY OF FORT WORTH
WATER DEPARTMENT
STANDARD PRODUCT LIST
(Approval
Spec No.
IClasssification I
Manufacturer
Water & Sewer
- Manholes & Bases/Rehab Svstems/NonCementitious
05/20/96
E1-14
Manhole Rehab Systems
Spravrog,
12/14/01
Coating for Corrosion protection(Exterior)
ERTECH
01/31/06
Coatings for Corrosion Protection
Chesterton
8/28/2006
Coatings for Corrosion Protection
Warren Environmental
33 01 16, 33 39 10,
03/19/18
33 39 20
Coating for Corrosion protection(Exterior)
Sherwin Williams
Water & Sewer
- Manhole Inserts - Field Onerations Use Only (Rev 2/3/16)
*
33 05 13
Manhole Insert
Knutson Enterprises
*
3305 13
Manhole Insert
South Western Packaging
*
33 05 13
Manhole Insert
Nofiow-Inflow
09/23/96
3305 13
Manhole Insert
Southwestem Packing & Seals, Inc.
09/23/96
3305 13
Manhole Insert
Southwestern Packing & Seals, Inc.
Water & Sewer
- Pine Casine Spacers 33-05-24 (07/01/13)
11/04/02
Steel Band Casing Spacers
Advanced Products and Systems, Inc.
02/02/93
Stainless Steel Casing Spacer
Advanced Products and Systems, Inc.
04/22/87
Casing Spacers
Cascade Waterworks Manufacturing
09/14/10
Stainless Steel Casing Spacer
Pipeline Seal and Insulator
09/14/10
Coated Steel Casin Spacers
Pipeline Seal and Insulator
05/10/11
Stainless Steel Casing Spacer
Powerseal
03/19/18
Casing Spacers
BWM
03/19/18
Casing Spacers
BWM
03/29/22
3305 13
Casing Spacers
CCI Pipeline Systems
Water & Sewer - PiDes/Ductile Iron 33-11-10(1/8/13)
Model No. National Spec
Spray Wall Polyurethane Coating ASTM D639/D790
Series 20230 and 2100 (Asphatic Emulsion)
Arc 791, S1BB, Sl, S2 Acid Resistance Test
S-301 and M-301
RR&C Dampproofing Non-Fibered Spray
Grade (Asphatic Emulsion)
Made to Order -
Plastic ASTM D 1248
Made to Order -
Plastic ASTM D 1248
Made to Order -
Plastic ASTM D 1248
Lifesaver - Stainless Steel
TetherLok- Stainless
Steel
Carbon Steel Spacers, Model SI
Stainless Steel Spacer, Model SSI
Casing Spacers
Stainless Steel Casing Spacer
Coated Steel Casin Spacers
4810 Powerchock
SS-12 Casing Spacer(Stainless Steel)
FB-12 Casing Spacer (Coated Carbon Steel)
for Non_rressme Pipe and Grouted Casing
CSC12, CSS12
*
33 11 10 Ductile Iron Pipe
Griffin Pipe Products, Co.
Super Bell-Tite Ductile Iron Pressure Pipe,
AW WA C150, C151
08/24/18
33 11 10 Ductile It. Pipe
American Ductile Iron Pipe Co.
American Futile Pipe (Bell Spigot)
AW WA C150, C151
08/24/18
33 11 10 Ductile Iron Pipe
American Ductile Iron Pipe Co.
American Flex Ring (Restrained Joint)
AW WA C150, C151
*
33 11 10 Ductile Iron Pipe
U.S. Pipe and Foundry Co.
AW WA C150, C151
*
33 11 10 Ductile Iron Pipe
McWane Cast Iron Pipe Co.
AW WA C150, C151
Water & Sewer - Utility Line Marker (08/24/2018)
Sewer - Coatin¢s/Enoxv 33-39-60 (01/08/13)
02/25/02
Epoxy Lining System
Sauereisen, Inc
SewerGard 21ORS
LA County #210-1.33
12/14/01
Epoxy Lining System
Enech Technical Coatings
Ertech 2030 and 2100 Series
04/14/05
Interior Ductile Iron Pipe Coating
Induron
Protean 401
ASTM B-117
01/31/06
Coatings for Corrosion Protection
Chesterton
Arc 791, S1BB, Sl, S2
Acid Resistance Test
8/28/2006
Coatings for Corrosion Protection
Warren Environmental
S-301 and M-301
Sewer - Coatin¢s/Polvurethane
Updated:12/29/2023
Size
Structures Only
Sewer Applications
Sealer Applications
For Exterior Coating of Concrete
Structures Only
For 24" dia.
For 24" dia.
For 24" dia.
For 24" dia.
For 24" dia
Up to 48"
Up to 48"
Up to 48"
3" fl m 24"
4" thm 30"
4" thm 30"
Ductile Iron Pipe Only
Sewer Applications
Sealer Applications
Sewer - Combination Air Valves
05/25/18 33-31-70 Air Release Valve
A.R.I. USA, Inc.
D025LTP02(Composite Body)
2"
Sewer - Pines/Concrete
* E:- Conc. Pipe, Reinforced
Wall Concrete Pipe Co. Inc.
ASTM C 76
* E I-04 Conc. Pipe, Reinforced
Hydro Conduit Corporation
Class III T&G, SPL Item #77
ASTM C 76
* E I-04 Conc. Pipe, Reinforced
Hanson Concrete Products
- - - -, -
ASTM C 76
* E I-04 Conc. Pipe, Reinforced
Concrete Pipe & Products Co. Inc.
ASTM C 76
Sewer - Pine Enlarement Svstem (Method)33-31-23 (01/18/13)
PIM System
PIM Corporation
Polyethylene
PIM CorP.. Piscata WaY, N.J.
Approved Previously
McConnell Systems
McLat Construction
Polyethylene
Houston, Texas
Approved Previously
TRS Systems
Trenchless Replacement System
Polyethylene
Calgary, Canada
Approved Previously
* From Original Standard Products List 2
FORT WORTH®
CITY OF FORT WORTH
WATER DEPARTMENT
STANDARD PRODUCT LIST
Updated: 12/29/2023
(Approval
Spec No. )Classsification
Manufacturer
Model No.
National Spec
Size
Sewer- PiDe/Fiber0ass Reinforced/33-31-13(1/8/13)
7/21/97
33 31 13
Cent. Cast Fiberglass (FRP)
Hobas Pipe USA, Inc.
Helios Pipe (Non -Pressure)
ASTM D3262/D3754
03/22/10
33 31 13
Fiberglass Pipe (FRP)
Ameron
Bondstrand RPMP Pipe
ASTM D3262/D3754
04/09/21
3331 13
Glass -Fiber Reinforced Polymer Pipe (FRP)
Thompson Pipe Group
Thompson Pipe (Flowtite)
ASTM D3262/D3754
03/07/23
3331 13
Fiberglass Pipe (FRP)
Future Pipe Industries
Fiberstrong FRP
ASTM D3262, ASTM D3681, ASTM D4161, AW WA M45
Sewer - PiDe/Polvmer PIDe
4/14/05
Polymer Modified Concrete Pioe
Anech USA
MPolwrete Pipe
ASTM C33, A276, -17
8" to 102", Class V
06/09/10
EI-9
Reinforced Polvmer Concrete Pipe
UmS Composite Pipe
Reinforcedeyer Polymer Concrete Pioe
ASTM C-76
Sewer - PiDes/HDPE 33-31-23(1/8/13)
*
High -density polyethylene pipe
Phillips Driswpipe, Inc.
Ovticore Ductile Polyethylene Pipe
ASTM D 1248
8"
*
High -density polyethylene pipe
Plexco Inc.
ASTM D 1248
8"
*
High -density polyethylene pipe
Polly Pipe, Inc.
ASTMD 1248
8"
High -density Polyethylene pipe
CSR Hydro Conduit/Pioeline Systems
McConnell Pipe Enlargement
ASTM D 1248
Sewer - PiDes/PVC (Pressure Sewer) 33-11-12 (4/1/13)
12/02/11
33-11-13
DR -Id PVC Pressure Pipe
Pipelife Jetstream
PVC Pressure Pipe
AW WA C900
4" thru 12"
10/22/14
33-11-12
DR-14 PVC Pressure Pipe
Royal Building Products
Royal Seal PVC Pressure Pipe
AW WA C900
4" thru 12"
Sewer - PiDes/PVC* 33-31-20 (7/1/13),
*
33-31-20
PVC Sewer Pioe
1-M Manufacturing Co., Inc. (JM Eagle)
SDR-26 (PS115)
ASTM D 3034
4" - 15"
12/23/97*
33-31-20
PVC Sewer Pioe
Diamond Plastics Corporation
SDR-26 (PS115)
ASTM D 3034
4" thin 15"
*
33-31-20
PVC Sewer Pioe
Lamson Vylm Pipe
SDR-26 (PSI 15)
ASTM D 3034
4" thm 15"
12/05/23
33-31-20
PVC Sewer Pie
Vin (tech PVC Pie
SDR-26 PS115
ASTM D3034
4" thm 15"
12/05/23
33-31-20
PVC Sewer Pie
Vin ltech PVC Pie
Grovi Sewer PS 115
ASTM F 679
18"
*
33-31-20 PVC Sewer PiJje
J-M Manufacmrinv�Co, Inc (JM Eagle)
PS 115
ASTM F 679
18" - 28"
05/06/05
33-31-20 PVC Solid Wall Pipe
Diamond Plashes Corporation
PS 115
ASTM F-679
18" to 48"
04/27/06
33-31-20 PVC Sewer Fittings
Harco
SDR-26 (PS 115) Gasket Finings
ASTM D-3034, D-1784, etc
4" - 15"
*
33-31-20 PVC Sewer Fittings
Plastic Trends, Ine.(Westlak)
Gasketed PVC Sewer Main Fittings
ASTM D 3034
1 3/19/2018
33 3120 PVC Sewer Pipe
Pipelife Jet Stream
SDR 26 (PS 115)
ASTM F679
18"- 24"
1 3/19/2018
33 3120 PVC Sewer PTe
Pipelife Jet Stream
SDR 26
ASTM D3034
4"- 11"
1 3/29/2019
33 3120 Gasketed Fittings (PVC)
GPK Products, Inc.
SDR 26
ASTM D3034
4"- 15"
1 10/21/2020
33 3120 PVC Sewer Pipe
NAPCO(Westlake)
SDR 26
ASTM D3034
4" - 15"
1 10/22/2020
33 3120 PVC Sewer Pipe
Sanderson Pipe Corp.
SDR 26
ASTM D3034
4"- 15"
1 10/21/2020
333120 PVC Sewer Pipe
NAPCO(Westlake)
SDR 26 PS 115
ASTM F-679
18"-36"
Sewer - PiDes/Rehab/CIPP 33-31-12 (01/18/131
*
Cured in Place Pioe
In in— Texark, Inc
ASTM F 1216
05/03/99
Cured in Place Pioe
National Envirotech Group
National Liner, (SPL) Item #27
ASF-1216/D-5813
05/29/96
Cured in Place Pipe
Remolds Inc/Inliner Technol" (Inliner USA)
Inlmer Technology
ASTM F 1216
Sewer - Piues/Rehab/Fold & Form
*
Fold and Form Pipe
Cullum Pipe Systems, hic.
11/03/98
Fold and Form Pipe
Insimform Technologies, Inc.
Insituform "NuPine"
ASTM F-1504
Fold and Form Pipe
American Pipe & Plastics, Inc.
Demo. Purpose Only
12/04/00
Fold and Form Pipe
Ultralner
Ultraliner PVC Alloy Pipelmer
ASTM F-1504, 1871, 1867
06/09/03
Fold and Form Pipe
Miller Pipeline Com.
EX Method
ASTM F-1504, F-1947
UP to 18" diameter
Sewer - PiDeS/ODen PCoelle Laree Diameter
09/26/91
E100-2 PVC Sewer Pipe, Ribbed
Lamson Vylon Pipe
Carlon Vylon H.C. Closed Profile Pipe,
ASTM F 679
18" to 48"
09/26/91
E100-2 PVC Sewer Pipe, Ribbed
Extrusion Technologies, Inc.
Ultra -Rib Open Profile Sewer Pipe
ASTM F 679
18" to 48"
E100-2 PVC Sewer Pipe, Ribbed
Up -or ETI Company
11/10/10
(E100-2) Polypropylene (PP) Sewer Pipe, Double Wall
Advanced Drainage Systems (ADS)
SaniTite UP Double Wall (Corrugated)
ASTM F 2736
24"-30"
11/10/10
(E100-2) Polypropylene (PP) Sewer Pipe, Triple Wall
Advanced Drainage Systems (ADS)
SaniTite HP Triple Wall Pipe
ASTM F 2764
30" to 60"
* From Original Standard Products List 3
CITY OF FORT WORTH
FORT WORTH. WATER DEPARTMENT
STANDARD PRODUCT LIST
Updated: 12/29/2023
(Approval
Spec No.
IClasssification
Manufacturer
Model No.
National Spec
Size
Water - Aoour-enances
33-12-10 (07/01/13)
01/18/18
33-12-10
Double Strap Saddle
Romac
202NS Nylon Coated
AWWA C800
1"-2" SVC, up to 24" Pipe
08/28/02
Double Strap Saddle
Smith Blau
4317 Nylon Coated Double Strap Saddle
07/23/12
33-12-10
Double Strap Service Saddle
Mueller Company
DR2S Double (SS) Strap DI Saddle
AWWA C800
1"-2" SVC, up to 24" Pipe
03/07/23
33-12-10
Double Strap Service Saddle
Powerseal
3450AS, Incl. Corp. Stop, ON Strap, Stainless
NSF ANSI 372
1"-2" SVC, up to 24" Pipe
10/27/87
Curb Stops -Ball Meter Valves
McDonald
6100M,6100MT & 61 OMT
3/4" and 1"
10/27/87
Curb Stops -Ball Meter Valves
McDonald
4603B, 4604B, 6100M, 6100TM and 6101M
1'/:" and 2"
FB600-7NL, FB1600-7-NL, FV23-777-W-NL,
1/25/2018
33-12-10
Curb Stops -Ball Meter Valves
Ford Meter Box Co., Inc.
-2-7-L
AWWA C800
2"
FB600-6-NL, FB1600-6-NL, FV23-666-W-
1111018
33-12-10
Curb Stops -Ball Meter Valves
Ford Meter Box Co., Inc.
NL, L22-66NL
AWWA C800
- ^'
FB600-4-NL, FB1600-4-NL, B11-444-WR-
1111.1.
33-12-10
Curb Stops -Ball Meter Valves
Ford Meter Box Co., Inc.
NL, B22444-WR-NL, L28-44NL
AWWA C800
I "
13-25000N, B-24277N-3, B-20200N-3, H-
AWWA C800, ANSF 61,
1/25/2018
33-12-10
Curb Stops -Ball Meter Valves
Mueller Co., Ltd.
15000N, , H-1552N, H142276N
ANSI/NSF 372
_
B-25000N, B-20200N-3, B-24277N-3,H-
AWWA C800, ANSF 61,
1111.1.
33-12-10
Curb Stops -Ball Meter Valves
Mueller Co., Ltd.
15000N, H-14276N, H-15525N
ANSI/NSF 372
1-1/3"
B-25000N, B-20200N-3,H-15000N, H-
AWWA C800, ANSF 61,
1111.1.
33-12-10
Curb Stops -Ball Meter Valves
Mueller Co., Ltd.
15530N
ANSI/NSF 372
V
01/26/00
Coated Tapping Saddle with Double SS Straps
1CM Industries, Inc.
#406 Double Band SS Saddle
1"-2" Taps on up to 12"
0/5/21/12
33-12-25
Tapping Sleeve (Coated Steel)
1CM Industries, Inc.
412 Tapping Sleeve ESS
AWWA C-223
Up to 30" w/12" Out
03/29/22
33-12-25
Tapping Sleeve (Coated or Stainless Steel)
1CM Industries, Inc.
415 Tapping Sleeve
AWWA C-223
Concrete Pipe Only
05/10/11
Tapping Sleeve (Stainless Steel)
Powerseal
3490AS (Flange) & 3490MJ
4"-8" and 16"
02/29/12
33-12-25
Tapping Sleeve (Coated Steel)
Romac
FTS 420
AWWA C-223
up to 42" w/24" Out
02/29/12
33-12-25
Tapping Sleeve (Stainless Steel)
Romac
SST Stainless Steel
AWWA C-223
Up to 24" w/12" Out
02/29/12
33-12-25
Tapping Sleeve (Stainless Steel)
Romac
SST III Stainless Steel
AWWA C-223
Up to 30" w/12" Out
05/10/11
Joint Repair Clamp
Powerseal
3232 Bell Joint Repair Clamp
4" to 30"
Plastic Meter Box w/Composite Lid
DFW Plastics Inc.
DFW37C-12-1EPAF FTW
Plastic Meter Box w/Composite Lid
DFW Plastics Inc.
DFW39C-12-1EPAF FTW
08/30/06
Plastic Meter Box w/Composite Lid
DFW Plastics Inc.
DFW65C-14-1EPAF FTW
Class "A"
Concrete Meter Box
Bass & Hays
CMB37-B12 1118 LID-9
Concrete Meter Box
Bass & Hays
CMB-18-Dual 1416 LID-9
Concrete Meter Box
Bass & Hays
CMB65-B65 1527 LID-9
Water - Bolts.
Nuts. and Gaskets 33-11-05 (01/08/13).
Water - Combination Air Release 33-31-70 (01/08/13)
*
E1-11
Air Release Valve
GA Industries, Inc.
Empire Air and Vacuum Valve, Model 935
ASTM A 126 Class B, ASTM A
1" & 2"
*
E1-11
[rarbombination
inationAir Release Valve
Multiplex Manufacturing Co.
Crispin Air and Vacuum Valves, Model No.
11" 1" & 2"
E1-11
ombination Air Release Valve
Valve and Primer Corp.
APCO 4143C, #145C and #147C
1", 2" & 3"
Water - Dry Barrel Fire Hvdrants 33-1240 (01/15/14)
10/01/87
E-1-12
Dry Barrel Fire Hydrant
American -Darling Valve
Drawing Nos. 90-18608, 94-18560
AWWA C-502
03/31/88
E-1-12
Dry Barrel Fire Hydrant
American Darling Valve
Shop Drawing No. 94-18791
AWWA C-502
09/30/87
E-1-12
Dry Barrel Fire Hydrant
Clow Corporation
Shop Drawing No. D-19895
AWWA C-502
01/12/93
E-1-12
Dry Barrel Fire Hydrant
American AVK Company
Model 2700
AWWA C-502
08/24/88
E-1-12
Dry Barrel Fire Hydrant
Clow Corporation
Drawings D20435, D20436, B20506
AWWA C-502
E-1-12
Dry Barrel Fire Hydrant
ITT Kennedy Valve
Shop Drawing No. D-80783FW
AWWA C-502
0.1.7
E-1-12
Dry Barrel Fire Hydrant
M&H Valve Company
Shop Drawing No. 13476
AWWA C-502
Shop Drawings No. 6461
l0/14/87
E-1-12
Dry Barrel Fire Hydrant
Mueller Company
A-423 Centurion
AWWA C-502
Shop Drawing FH-12
01/15/88
E1-12
Dry Barrel Fire Hydrant
Mueller Company
A-423 Super Centurion 200
AWWA C-502
10/09/87
E-1-12
Dry Barrel Fire Hydrant
U.S. Pipe & Foundry
Shop Drawing No. 960250
AWWA C-502
09/16/87
E-1-12
Dry Barrel Fire Hydrant
American Flow Control (AFC)
Waterous Pacer WB67
AWWA C-502
08/12/16
33-12-40
Dry Barrel Fire Hydrant
EJ (East Jordan Iron Works)
WaterMaster 5CD250
Water - Meters
02/05/93
E101-5
Detector Check Meter
Ames Company
Model 1000 Detector Check Valve
AW WA C550
4" - 10"
08/05/04
Magnetic Drive Vertical Turbine
Hersey
Magnetic Drive Vertical
AWWA C701, Class 1
3/4" - 6"
* From Original Standard Products List 4
CITY OF FORT WORTH
FORT WORTH.
WATER DEPARTMENT
STANDARD PRODUCT LIST
Updated:
12/29/2023
IApprovall
Spec No.
IClasssification
Manufacturer
Model No.
National Spec
Size
Water - Pines/PVC (Pressure Water) 33-31-70 (01/08/13)
AWWA C900, AW WA C605,
12/05/23
33-I1-12
PVC Pressure Pie
Vin loch PVC Pipe
DR14
ASTM D1784
V-16"
AWWA C900, AWWA C605,
12/OS/23
33-11-12
PVC Pressure Pipe
Vinyltech PVC Pipe
DR18
ASTM D1784
16"-18"
3/19/2018
33 11 12
PVC Pressure Pipe
Pipelife Jet Stream
DR14
AWWA C900
4"-12"
1 3/19/2018
3311 12
PVC Pressure Pipe
Pipelife Jet Stream
DR18
AWWA C900
16"-24"
1 5/25/2018
33 11 12
PVC Pressure Pipe
Diamond Plastics Comoration
DR 14
AWWA C900
4"-12"
5/25/2018
33 11 12
PVC Pressure Pipe
Diamond Plastics Corporation
DR 18
AWWA C900
16"-24"
AWWA C900-16
UL 1285
12/6/2018
3311 12
PVC Pressure Pipe
J-M Manufacturing Co., Inc d/b/a JM Eagle
DR 14
ANSI/NSF 61
4"-28"
FM 1612
12/6/2018
33 11 12
PVC Pressure Pipe
J-M Manufacturing Co., Inc d/b/a JM Eagle
DR 18
" °
16"-24"
9/6/2019
33 11 12
PVC Pressure Pipe
Underground Solutions Inc.
DR14 Fusible PVC
AWWA C900
4" - 8"
9/6/2019
33 11 12
PVC Pressure Pipe
NAPCO(Westlake)
DR18
AWWA C900
16"-24"
9/6/2019
33 11 12
PVC Pressure Pipe
NAPCO(Westlake)
DR14
AWWA C900
4%12"
9/6/2019
33 11 12
PVC Pressure Pipe
Sanderson Pipe Corp.
DR14
AWWA C900
4%12"
Water - PlDes/Valves & Fittings/Ductile Iron Fittings 33-11-11 (01/08/13)
07/23/92
EI-07
Ductile Iron Fittings
Star Pipe Products, Inc.
Mechanical Joint Fittings
AW WA C153 & C110
*
E1-07
Ductile Iron Fittings
Griffin Pipe Products, Co.
Mechanical Joint Fittin, @
AWWA C 110
*
E1-07
Ductile Iron Fittings
McWane/Tyler Pipe/ Union Utilities Division
Mechanical Joint Finings, SSB lass 350
AWWA C 153, C 110, C III
08/11/98
E1-07
Ductile Iron Fittings
Sigma, Co.
Mechanical Joint Finings, SSB Class 351
AWWA C 153, C 110, C 112
02/26/14
E1-07
MJ Fittings
Accucast
Class 350 C-153 MJ Finings
AWWA C153
4"-12"
05/14/98
E1-07
Ductile Iron Joint Restraints
Ford Meter Box Co./Uni-Flange
Uni-Flange Series 1400
AW WA C111/C153
4" to 36"
05/14/98
E1-24
PVC Joint Restraints
Ford Meter Box Co./Um-Flange
Uni-Flange Series 1500 Circle -Lock
AW WA C111/C153
4" to 24"
11/09/04
E1-07
Ductile Iron Joint Restraints
One Bolt, Inc.
One Bolt Restrained Joint Fitting
AWWA C111/C116/C153
4" to 12"
02/29/12
33-11-11
Ductile Iron Pipe Mechanical Joint Restraint
EBAA Iron, Inc.
Megalug Series 1100 (for DI Pipe)
AWWA C111/C116/C153
4" to 42"
02/29/12
33-11-11
PVC Pipe Mechanical Joint Restraint
EBAA Iron, Inc.
Megalug Series 2000 (for PVC Pipe)
AWWA C111/C116/C153
4" to 24"
08/05/04
E1-07
Mechanical Joint Retainer Glands(PVC)
Sigma, Co.
Sigma One-Lok SLC4 - SLC10
AW WA C111/C153
4" to 10"
03/06/19
33-11-11
Mechanical Joint Retainer Glands(PVC)
Sigma, Co.
Sigma One-Lok SLCS4 - SLCS12
AW WA C111/C153
4" to 12"
08/05/04
E1-07
Mechanical Joint Retainer Glands(PVC)
Sigma, Co.
Sigma One-Lok SLCE
AW WA C111/C153
12" to 24"
08/10/98
E1-07
MJ Fittings(DIP)
Sigma, Co.
Sigma One-Lok SLDE
AWWA C153
4" - 24"
10/12/10
E1-24
Interim Restrained Joint Svstem
S & B Techncial Products
Bulldog System ( Diamond Lok 21 & JM
ASTM F-1624
4" to 12"
08/16/06
E1-07
Mechanical Joint Fittings
SIP Industries(Serampore)
Mechanical Joint Fittings
AWWA C153
4" to 24"
11/07/16
33-11-11
Mechanical Joint Retainer Glands
Star Pipe Products, Inc.
PVC Stargnp Series 4000
ASTM A536 AW WA CI I I
11/07/16
33-11-I1
Mechanical Joint Retainer Glands
Star Pipe Products, Inc.
DIP Stargrip Series 3000
ASTM A536 AW WA CI I I
EZ Grip Joint Restraint (EZD) Black For DIP
03/19/18
33-11-I1
Mechanical Joint Retaner Glands
SIP Industries(Serampore)
ASTM A536 AW WA CI I I
3"-48"
EZ Grip Joint Restraint (EZD) Red for C900
03/19/18
33-11-I1
Mechanical Joint Retainer Glands
SIP Industries(Serampore)
DR14 PVC Pipe
ASTM A536 AW WA CI I I
4"-12"
EZ Grip Joint Restraint (EZD) Red for C900
03/19/18
33-11-I1
Mechanical Joint Retainer Glands
SIP Industries(Serampore)
DR18 PVC Pipe
ASTM A536 AW WA CI I I
16"-24"
Water - Pines/Valves & Fittings/Resilient Seated Gate Valve* 33-12-20 (05/13/15)
Resilient Wedged Gate Valve w/no Gears
American Flow Control
Series 2500 Drawing # 94-20247
16"
12/13/02
Resilient Wedge Gate Valve
American Flow Control
Series 2530 and Series 2536
AWWA C515
30" and 36"
08/31/99
Resilient Wedge Gate Valve
American Flow Control
Series 2520 & 2524 (SD 94-20255)
AWWA C515
20" and 24"
05/18/99
Resilient Wedge Gate Valve
American Flow Control
Series 2516 (SD 94-20247)
AWWA C515
16"
10/24/00
E1-26
Resilient Wedge Gate Valve
American Plow Control
Series 2500 (Ductile Iron)
AWWA C515
4" to 12"
08/05/04
Resilient Wedge Gate Valve
American Flow Control
42" and 48" AFC 2500
AWWA C515
42" and 48"
05/23/91
E1-26
Resilient Wedge Gate Valve
American AVK Company
American AVK Resilient Seaded GV
AWWA C509
4" to 12"
01/24/02
E1-26
Resilient Wedge Gate Valve
American AVK Company
20" and smaller
*
E1-26
Resilient Seated Gate Valve
Kennedy
4" - 12"
*
E1-26
Resilient Seated Gate Valve
M&H
4" - 12"
*
E1-26
Resilient Seated Gate Valve
Mueller Co.
4" - 12"
11/08/99
Resilient Wedge Gate Valve
Mueller Co.
Series A2361 (SD 6647)
AWWA C515
16"
01/23/03
Resilient Wedge Gate Valve
Mueller Co.
Series A2360 for 18"-24" (SD 6709)
AWWA C515
24" and smaller
05/13/05
Resilient Wedge Gate Valve
Mueller Co.
Mueller 30" & 36", C-515
AWWA C515
30" and 36"
01/31/06
Resilient Wedge Gate Valve
Mueller Co.
Mueller 42" & 48", C-515
AWWA C515
42" and 48"
01/28/88
E1-26
Resilient Wedge Gate Valve
Clow Valve Co.
AWWA C509
4" - 12"
10/04/94
Resilient Wedge Gate Valve
Clow Valve Co.
16" RS GV (SD D-20995)
AWWA C515
16"
11/08/99
EI-26
Resilient Wedge Gate Valve
Clow Valve Co.
Clow RW Valve (SD D-21652)
AWWA C515
24" and smaller
11/29/04
Resilient Wedge Gate Valve
Clow Valve Co.
Clow 30" & 36" C-515
AWWA C515
30" and 36" (Note 3)
11/30/12
ReaihentW Gate Valve
eGate
Clow Valve Co.
Clow Valve Model 2638
AWWA C515
24" to 48" ote 3)
05/08/91
E1-26
Resilient Seat Valve
Stockham Valves & Finings
AWWA C 509, ANSI 420 - stem,
4" -
*
E1-26
Resilient Seated Gate Valve
U.S. Pipe and Foundry Co.
Met,,, a1250, requirements SPL #74
3" to 16"
10/26/16
33-12-20
Resilient Seated Gate Valve
EJ (East Jordan Iron Works)
IIIFlowMester Gate Valve & Boxes
08/24/18
Mateo Gate Valve
Matco-Norca
225 MR
AWWA/ANSI C115/An21.15
4" to 16"
* From Original Standard Products List 5
FORT WORTH®
CITY OF FORT WORTH
WATER DEPARTMENT
STANDARD PRODUCT LIST
Updated: 12/29/2023
(Approval
Spec No. [Classsification Manufacturer
Water - PiDes alves & Fittings/Rubber Seated Batter Valve 33-12-21 (07/10/14)
Model No.
National Spec
Size
*
y
E1-30 Rubber Seated Butterfly Valve Hei ry Pratt Co.
AW WA C-504
24"
*
E1-30 Rubber Seated Butterfly Valve Mueller Co.
AW WA C-504
24"and smaller
1/11/99
E1-30 Rubber Seated Butterfly Valve Dezurik Valves Co.
AW WA C-504
24" and larger
06/12/03
E1-30 Valmatic American Butterfly Valve Valmanc Valve and Manufacturing Com.
Valmatic American Butterfly Valve.
AW WA C-504
Up to 84" diameter
04/06/07
E1-30 Rubber Seated Butterfly Valve M&H Valve
M&H Style 4500 & 1450
AW WA C-504
24" to 48"
03/19/18
33 1221 Rubber Seated Butterfly Valve G. A. Industries (Golden Anderson)
AW WA C504 Butterfly Valve
AW WA C-504
30"-54"
Water - Polvethvlene Encasement 33-11-10 (01/08/13)
05/12/05
E1-13 Polyethylene Encasment Fl—ol Packaging
Fulton Entemrises
AW WA C105
8 mil LLD
05/12/05
E1-13 Polyethylene Encasment Mountain States Plastics (MSP) and AEP Ind.
Standard Hardware
AW WA C105
8 mil LLD
05/12/05
E1-13 Polyethylene Encasment AEP Industries
Bullstrong by Cowtown Bolt & Gasket
AW WA C105
8 mil LLD
09/06/19
33-11-11 Polyethylene Encasment Northtown Products Inc.
PE Encasement for DIP
AW WA C105
8 mil LLD
Water - SamDlinE Station
03/07/23
33 12 50 l Water Sampling Station Eclipse
Number 88 , 12-inch Depth of Bury
As shown in spec. 33 12 50
Water - Automatic Flusher
HG6-A-IN-2-BRN-LPRR(Portable)
1.110
Automated Flushing System Mueller Hydroguard
HG2-A-IN--2-PVC-018-LPLG(Perinanent)
04/09/21
Automated Flushing System Kupferle Foundry Company
Eclipse #9800we
04/09/21
Automated Flushing System Kupferle Foundry Company
Eclipse #9700 (Portable)
The Fort Worth Water Department's Standard Products List has been developed to minimize the submittal review of products which meet the Fort Worth Water Department's Standard Specifications during utility construction projects. When Technical
Specifications for specific products, are included as part of the Construction Contract Documents, the regmrements of the Technical Specification w 11 override the Fort Worth Water Department's Standard Specifications and the Fort Worth Water Department's
Standard Products List and approval of the specific products will be based on the requirements of the Technical Specification whether or not the specific product meets the Fort Worth Water Department's Standard Specifications or is on the Fort Worth Water
Yellow Highlight indicates recent changes
* From Original Standard Products List