HomeMy WebLinkAboutContract 45482 (2)PROJECT NUAL
Fob TOY,OF
CONSTRUCTION
Sanitary Sewer
b Contract �'' Part t
R�ha aso
Cat DOE No 651s
gao91�o1asos3
a,
'WaterProject No. p2� 609110148083 o p258^7091'�0148083
Serer project N
-Betsy Price
Mayor
Tam Pliggtns
luteritn City Manager
S. 'Prank Crumb, P •E.
erit
Director, 'Water Deparml
iersig,,iorksDePa'ti�ent
Douglas organ and Public
Director, Transportation
Prepared for
'Worth
The City of Fort
'Water Department
2013
5-toclkwood, An
drevVs, & Newna h1,
OFFICIAL RECORD
rir grf PFT4RY
RECEIVED APR 3 201N
FORT WORTH
PROJECT MANUAL
FOR
THE CONSTRUCTION OF
Sanitary Sewer Rehab Contract 75, Part 1
City Project No. 1480
DOE No. 6578
SRF No. P254-709170148083
Water Project No. P253-609170148083
Sewer Project No. P258-709170148083
Betsy Price
Mayor
Tom Higgins
Interim City Manager
S. Frank Crumb, P.E.
Director, Water Department
Douglas W. Wiersig, P.E.
Director, Transportation and Public Works Department
Prepared for
The City of Fort Worth
Water Department
2013
Lockwood, Andrews, & Newnam, Inc.
-E .°� r
r f
WAITER P. NORWOOD ,
}....,. " 82049 • cr •
s ONAL��
�704 / 3
P '2- 0 4*
000000-I
TABLE OF CONTENTS
1 SECTION 00 00 00
2 TABLE OF CONTENTS
3
4 Division 00 - General Conditions
5 00 05 10 Mayor and Council Communication
6 00 05 15 Addenda
7 00 11 13 Invitation to Bidders
8 00 21 13 Instructions to Bidders
9 00 35 13 Conflict of Interest Affidavit
10 00 41 00 Bid Form
11 00 42 43 Proposal Form Unit Price
12 00 43 13 Bid Bond
13 00 43 37 Vendor Compliance to State Law Nonresident Bidder
14 00 45 11 Bidders Prequalifications
15 00 45 12 Prequalification Statement
16 00 45 13 Bidder Prequalification Application
17 00 52 43 Agreement
18 00 61 13 Performance Bond
19 00 61 14 Payment Bond
20 00 61 19 Maintenance Bond
21 00 61 25 Certificate of Insurance
22 00 72 00 General Conditions
23 00 73 00 Supplementary Conditions
24
25 Division 01 - General Requirements
26
27 01 11 00 Summary of Work
28 01 25 00 Substitution Procedures
29 01 31 19 Preconstruction Meeting
30 01 32 16 Construction Progress Schedule
31 01 33 00 Submittals
32 01 35 13 Special Project Procedures
33 01 45 23 Testing and Inspection Services
34 01 50 00 Temporary Facilities and Controls
35 01 55 26 Street Use Permit and Modifications to Traffic Control
36 01 57 13 Storm Water Pollution Prevention Plan
37 01 58 13 Temporary Project Signage
38 01 60 00 Product Requirements
39 01 66 00 Product Storage and Handling Requirements
40 01 71 23 Construction Staking
41 01 70 00 Mobilization and Remobilization
42 01 74 23 Cleaning
43 01 77 19 Closeout Requirements
44 01 78 23 Operation and Maintenance Data
45 01 78 39 Project Record Documents
46
47
48
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised August 20, 2012
Page 1 of4
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project 41480
000000-2
TABLE OF CONTENTS
Page 2 of 4
1 Technical Specifications listed below are included for this Project by reference and can be
2 viewed/downloaded from the City's Buzzsaw site at:
3
4 htus://uroiectuoint.buzzsaw.com/client/fortworthgov/Resources/02%20-
5 %20Construction%20Documents/Specifications
6
7 Division 02 - Existing Conditions
8 02 41 13 Selective Site Demolition
9 02 41 14 Utility Removal/Abandonment
10 02 41 15 Paving Removal
11 02 82 33 Asbestos Removal
12
13 Division 03 - Concrete
14 03 34 13 Controlled Low Strength Material (CLSM)
15 03 34 16 Concrete Base Material for Trench Repair
16 03 80 00 Modifications to Existing Concrete Structures
17
18 Division 31 - Earthwork
19 31 10 00 Site Clearing
20 31 23 16 Unclassified Excavation
21 31 25 00 Erosion and Sediment Control
22 31 37 00 Riprap
23
24 Division 32 - Exterior Improvements
25 32 01 17 Permanent Asphalt Paving Repair
26 32 01 18 Temporary Asphalt Paving Repair
27 32 01 29 Concrete Paving Repair
28 32 31 13 Chain Link Fences and Gates
29 32 31 29 Wood Fences and Gates
30 32 92 13 Hydro -Mulching, Seeding, and Sodding
31
32 Division 33 - Utilities
33 33 01 30 Sewer and Manhole Testing
34 33 01 31 Closed Circuit Television (CCTV) Inspection
35 33 03 10 Bypass Pumping of Existing Sewer Systems
36 33 04 30 Temporary Water Services
37 33 04 40 Cleaning and Acceptance Testing of Water Mains
38 33 05 10 Utility Trench Excavation, Embedment, and Backfill
39 33 05 12 Water Line Lowering
40 33 05 13 Frame, Cover and Grade Rings
41 33 05 20 Auger Boring
42 33 05 22 Steel Casing Pipe
43 33 05 26 Utility Markers/Locators
44 33 05 30 Location of Existing Utilities
45 33 11 10 Ductile Iron Pipe
46 33 11 11 Ductile Iron Fittings
47 33 11 12 Polyvinyl Chloride (PVC) Pressure Pipe
48 33 12 10 Water Services 1-inch to 2-inch
49 33 12 20 Resilient Seated Gate Valve
50 33 12 25 Connection to Existing Water Mains
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised August 20, 2012
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
000000-3
TABLE OF CONTENTS
Page 3 of4
1 33 12 40 Fire Hydrants
2 33 31 12 Cured in Place Pipe (CIPP)
3 33 31 15 HDPE Pipe For Sanitary Sewers (Gravity and Force Mains)
4 33 31 20 Polyvinyl Chloride (PVC) Gravity Sanitary Sewer Pipe
5 33 31 23 Sanitary Sewer Pipe Enlargement
6 33 31 50 Sanitary Sewer Service Connections and Service Line
7 33 39 10 Cast -in -Place Concrete Manholes
8 33 39 20 Precast Concrete Manholes
9 33 39 60 Epoxy Liners for Sanitary Sewer Structures
10 33 41 10 Reinforced Concrete Storm Sewer Pipe/Culverts
11
12 Division 34 - Transportation
13 34 41 10 Traffic Signals
14
15 Appendix
16 GC-4.01 Availability of Lands
17 GC-4.02 Subsurface and Physical Conditions
18 GC-6.07 Wage Rates
19 GC-6.09 Permits and Utilities
20 SRF-1 CWSRF Forms
21
22 Details
23 33 05 10 Acceptable Backfill
24 33 05 10 Controlled Low Strength Material (CLSM) Backfill
25 33 05 10 Deep Trench Backfill
26 33 05 10 Trench Water Stop
27 02 41 14 Pipe Abandonment Plug
28 33 05 13 Water -Tight Hinged Manhole Frame, Cover and Grade Rings
29 33 05 13 Manhole Frame, Cover and Grade Rings
30 33 05 13 Manhole Lid Assembly - Existing HMAC Pavement (Cone)
31 33 05 13 Manhole Lid Assembly - Existing Concrete Pavement (Cone)
32 33 05 13 Manhole Lid Assembly - Proposed Concrete Pavement (Cone)
33 33 05 13 Manhole Lid Assembly -Unimproved Surface (Flat Top)
34 33 05 10 Embedment for Water Lines 12-inch and Smaller
35 33 05 10 Embedment for Water Services
36 33 12 10 1-inch Water Service
37 33 12 10 1-1/2-inch & 2-inch Water Service
38 33 12 10 1-inch Standard Plastic Meter Box (3/4-inch & 1-inch Meters)
39 33 12 10 2-inch Standard Plastic Meter Box (1-1/2-inch & 2-inch Meters)
40 33 12 10 1-inch Standard Concrete Meter Box (3/4-inch & 1-inch Meters)
41 33 12 10 2-inch Standard Concrete Meter Box (1-1/2-inch & 2-inch Meters)
42 33 12 40 Standard Fire Hydrant (Straight)
43 33 12 40 Standard Fire Hydrant (Ell)
44 02 41 14 PVC, Ductile Iron, Concrete Pressure and Buried Steel Pipe Pressure Plugs
45 33 12 20 Water Distribution Gate Valve & Box (12-inch and Smaller)
46 33 12 25 Connection to Existing Water Mains
47 33 11 00 Horizontal Thrust Blocking
48 33 11 00 Concrete Cradle
49 33 11 00 Vertical Tie -Down Blocking
50 33 04 30 Temporary Service Connection
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised August 20, 2012
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project#1480
000000-4
TABLE OF CONTENTS
Page 4 of 4
1 33 04 30 Intersection & Driveway Approach Crossing for Temporary Water Service
2 33 05 10 Embedment for Sanitary Sewer All Sizes
3 33 05 10 Embedment for Sanitary Sewer Services
4 33 05 24 San. Sewer Carrier Pipe Installation in Steel Casing Pipe and Tunnel Liner Plate
5 33 05 24 Sanitary Sewer Pipe in Steel Casing & Tunnel Liner Plate Profile
6 03 80 00 Hydraulic Slide
7 33 39 10/20 Standard Manhole
8 33 39 10/20 Standard 4' Diameter Drop Manhole
9 33 39 30 Fiberglass Manhole
10 33 31 50 Sanitary Sewer Service
11 33 31 50 Deep Sanitary Sewer Service
12 33 31 23 Sanitary Sewer Point Repair (4" to 12")
13 32 01 17 Asphalt Pavement Trench Repair — Arterial & Industrial Streets
14 32 01 17 Asphalt Pavement Trench Repair — Residential Streets
15 32 01 29 Concrete Pavement Trench Repair — Arterial & Industrial Streets
16 32 01 29 Concrete Pavement Trench Repair — Residential Streets
17 32 13 13 Standard Monolithic Curb
18 32 16 13 Concrete Valley Gutter
19 32 16 13 Standard Curb and Gutter
20 END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised August 20, 2012
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project#1480
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
000510-1
MAYOR AND COUNCIL COMMUNICATION (M&C)
Page 1 of 1
SECTION 00 05 10
MAYOR AND COUNCIL COMMUNICATION (M&C)
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project # 1480
1 SECTION 00 05 15
2 ADDENDA
3
4
5
6 THIS PAGE INTENTIONALLY LEFT BLANK
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
000515-1
ADDENDA
Page 1 of 1
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project # 1480
00 11 13-1
INVITATION TO BIDDERS
Page 1 of 2
1 SECTION 00 11 13
2 INVITATION TO BIDDERS
3 RECEIPT OF BIDS
4 Sealed bids for the construction of the 2010 Sanitary Sewer Rehabilitation Contract 75, Part 1,
5 City of Fort Worth Project #1480, DOE #6578 will be received by the City of Fort Worth
6 Purchasing Office:
7
8 City of Fort Worth
9 Purchasing Division
10 1000 Throckmorton Street
11 Fort Worth, Texas 76102
12 until 1:30 P.M. CST, Thursday, October 31, 2013, and bids will be opened publicly and read
13 aloud at 2:00 PM CST in the Council Chambers.
14
15 GENERAL DESCRIPTION OF WORK
16 The major work will consist of the (approximate) following:
17
18 • 5500 LF 8" Sanitary Sewer Pipe By Open Cut
19 • 2600 LF 12" Sanitary Sewer Pipe By Open Cut
20 • 1400 LF 15" Sanitary Sewer Pipe By Open Cut
21 • 160 LF 8" Sanitary Sewer Pipe By Bursting
22 • 530 LF 8" Sanitary Sewer Pipe By CIPP
23 • 715 LF Sanitary Sewer Pipe By Other Than Open Cut
24 • 44 Manholes
25 • 1075 LF of 8" Water Pipe By Open Cut
26 • Pavement Repair
27
28 The Engineer's Opinion of Probably Construction cost is $2 million.
29
30 PREQUALIFICATION
31 The improvements included in this project must be performed by a contractor who is pre-
32 qualified by the City at the time of bid opening. The procedures for qualification and pre-
33 qualification are outlined in the Section 00 21 13 — INSTRUCTIONS TO BIDDERS.
34
35 DOCUMENT EXAMINATION AND PROCUREMENTS
36 The Bidding and Contract Documents may be examined or obtained on-line by visiting the City
37 of Fort Worth's Purchasing Division website at http://www.fortwortl-wov.orWnurchasin0 and
38 clicking on the Buzzsaw link to the advertised project folders on the City's Buzzsaw site. The
39 Contract Documents may be downloaded, viewed, and printed by interested contractors and/or
40 suppliers. This is a state funded project with TWDB.
41
42 Copies of the Bidding and Contract Documents may be purchased from Lockwood, Andrews, &
43 Newnarn, Inc. which is as follows: 1320 South University Dr., Suite 450. Fort Worth, TX 76107.
44
45 The cost of Bidding and Contract Documents is:
46 Set of Bidding and Contract Documents with full size drawings: $85
47 Set of Bidding and Contract Documents with half size (if available) drawings: $45
48
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
00 11 13 -2
INVITATION TO BIDDERS
Page 2 of 2
1 CITY'S RIGHT TO ACCEPT OR REJECT BIDS
2 City reserves the right to waive irregularities and to accept or reject bids.
3 FUNDING
4 Any contract awarded under this INVITATION TO BIDDERS is expected to be funded from
5 revenues generated from user fees, bonds, and grants and dedicated by resolution of the City of
6 Fort Worth City Council to the work under this INVITATION TO BIDDERS.
7
8 INQUIRIES
9 All inquiries relative to this procurement should be addressed to the following:
10 Attn: Robert Sauceda, City of Fort Worth
11 Email: robert.sauceda@FortWorthTexas.gov
12 Phone: 682-432-5478
13 AND/OR
14 Attn: Walter Norwood, Lockwood, Andrews, & Newnam, Inc.
15 Email: WPNorwood(lan-inc.com
16 Phone: 817-338-7509
17
18 ADVERTISEMENT DATES
19 October 10, 2013
20 October 17, 2013
21
22 END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project N 1480
002113-1
INSTRUCTIONS TO BIDDERS
Page 1 of 10
1 SECTION 00 21 13
2 INSTRUCTIONS TO BIDDERS
3 1. Defined Terms
4
5 1.1. Terms used in these INSTRUCTIONS TO BIDDERS, which are defined in Section 00 72
6 00 - GENERAL CONDITIONS.
7
8 1.2. Certain additional terms used in these INSTRUCTIONS TO BIDDERS have the
9 meanings indicated below which are applicable to both the singular and plural thereof.
10
11 1.2.1. Bidder: Any person, firm, partnership, company, association, or corporation acting
12 directly through a duly authorized representative, submitting a bid for performing
13 the work contemplated under the Contract Documents.
14
15 1.2.2. Nonresident Bidder: Any person, firm, partnership, company, association, or
16 corporation acting directly through a duly authorized representative, submitting a
17 bid for performing the work contemplated under the Contract Documents whose
18 principal place of business is not in the State of Texas.
19
20 1.2.3. Successful Bidder: The lowest responsible and responsive Bidder to whom City
21 (on the basis of City's evaluation as hereinafter provided) makes an award.
22
23 2. Copies of Bidding Documents
24
25 2.1. Neither City nor Engineer shall assume any responsibility for errors or misinterpretations
26 resulting from the Bidders use of incomplete sets of Bidding Documents.
27
28 2.2. City and Engineer in making copies of Bidding Documents available do so only for the
29 purpose of obtaining Bids for the Work and do not authorize or confer a license or grant
30 for any other use.
31
32 3. Prequalification of Bidders (Prime Contractors and Subcontractors)
33
34 3.1. All Bidders and their subcontractors are required to be prequalified for the work types
35 requiring prequalification at the time of bidding. Bids received from contractors who are
36 not prequalified (even if inadvertently opened) shall not be considered. Prequalification
37 requirement work types and documentation are as follows:
38
39 3.1.1. Paving — Requirements document located at;
40 https://projectpoint.buzzsaw.com/fortworthgov/Resources/02%20-
41 %20Construction%20Documents/Contractor%20Prequalification/TP W %20Paving
42%20Contractor%20Prequaliiication%20Program/PREQUALIFICATION%2OREQ
43 UI REMENTS%20FOR%20PAV ING%2000NTRACTORS.PDF?public
44
45 3.1.2. Roadway and Pedestrian Lighting — Requirements document located at;
46 httos://oroiectooint.buzzsaw.com/fortworthgov/Resources/02%20-
47 %20Construction%20Documents/Contractor%20Prequalification/TPW%20Pavina
48%20Contractor%20Prequalification%20Program/PREQUAL1FICATION%20REO
49 UIREMENTS%20FOR%20PAVING%2000NTRACTORS.PDF?public
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised November 27, 2012
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project # 1480
00 21 13 -2
INSTRUCTIONS TO BIDDERS
Page 2 of 10
2 3.1.3. Water and Sanitary Sewer — Requirements document located at;
3 https://projectpoint.buzzsaw.com/fortworthgov/Resources/02%20-
4 %20Construction%20Documents/Contractor%20Precivalification/Water%20and%2
5 OSanitarv%20Sewer%20Contractor%20Prequalification%20Pro2ram/WSS%20Dre
6 ival%20requirements.doc?public
7
8
9 3.2. Each Bidder unless currently prequalified, must be prepared to submit to City within
10 seven (7) calendar days prior to Bid opening, the documentation identified in Section 00
11 45 11, BIDDERS PREQUALIFICATIONS.
12
13 3.2.1. Submission of and/or questions related to prequalification should be addressed to
14 the City contact as provided in Paragraph 6.1.
15
16
17 3.3. The City reserves the right to require any pre -qualified contractor who is the apparent low
18 bidder(s) for a project to submit such additional information as the City, in its sole
19 discretion may require, including but not limited to manpower and equipment records,
20 information about key personnel to be assigned to the project, and construction schedule,
21 to assist the City in evaluating and assessing the ability of the apparent low bidder(s) to
22 deliver a quality product and successfully complete projects for the amount bid within
23 the stipulated time frame. Based upon the City's assessment of the submitted
24 information, a recommendation regarding the award of a contract will be made to the
25 City Council. Failure to submit the additional information, if requested, may be grounds
26 for rejecting the apparent low bidder as non -responsive. Affected contractors will be
27 notified in writing of a recommendation to the City Council.
28
29 3.4. In addition to prequalification, additional requirements for qualification may be required
30 within various sections of the Contract Documents.
31
32 4. Examination of Bidding and Contract Documents, Other Related Data, and Site
33
34 4.1. Before submitting a Bid, each Bidder shall:
35
36 4.1.1. Examine and carefully study the Contract Documents and other related data
37 identified in the Bidding Documents (including "technical data" referred to in
38 Paragraph 4.2. below). No information given by City or any representative of the
39 City other than that contained in the Contract Documents and officially
40 promulgated addenda thereto, shall be binding upon the City.
41
42 4.1.2. Visit the site to become familiar with and satisfy Bidder as to the general, local and
43 site conditions that may affect cost, progress, performance or furnishing of the
44 Work.
45
46 4.1.3. Consider federal, state and local Laws and Regulations that may affect cost,
47 progress, performance or furnishing of the Work.
48
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised November 27, 2012
Sanitary Sewer Rehab Contract 75, Part I
CFW Project#1480
00 21 13 -3
INSTRUCTIONS TO BIDDERS
Page 3 of 10
1 4.1.4. Be advised, City, in accordance with Title VI of the Civil Rights Act of 1964, 78
2 Stat. 252, 42 U.S.C. 2000d to 2000d-4 and Title 49, Code of Federal Regulations,
3 Department of Transportation, Subtitle A, Office of the Secretary, Part 21,
4 Nondiscrimination in Federally -assisted programs of the Department of
5 Transportation issued pursuant to such Act, hereby notifies all bidders that it will
6 affirmatively insure that in any contract entered into pursuant to this advertisement,
7 minority business enterprises will be afforded full opportunity to submit bids in
8 response to this invitation and will not be discriminated against on the grounds of
9 race, color, or national origin in consideration of award.
10
11 4.1.5. Study all: (i) reports of explorations and tests of subsurface conditions at or
12 contiguous to the Site and all drawings of physical conditions relating to existing
13 surface or subsurface structures at the Site (except Underground Facilities) that
14 have been identified in the Contract Documents as containing reliable "technical
15 data" and (ii) reports and drawings of Hazardous Environmental Conditions, if any,
16 at the Site that have been identified in the Contract Documents as containing
17 reliable "technical data."
18
19 4.1.6. Be advised that the Contract Documents on file with the City shall constitute all of
20 the information which the City will furnish. All additional information and data
21 which the City will supply after promulgation of the formal Contract Documents
22 shall be issued in the form of written addenda and shall become part of the Contract
23 Documents just as though such addenda were actually written into the original
24 Contract Documents. No information given by the City other than that contained in
25 the Contract Documents and officially promulgated addenda thereto, shall be
26 binding upon the City.
27
28 4.1.7. Perform independent research, investigations, tests, borings, and such other means
29 as may be necessary to gain a complete knowledge of the conditions which will be
30 encountered during the construction of the project. On request, City may provide
31 each Bidder access to the site to conduct such examinations, investigations,
32 explorations, tests and studies as each Bidder deems necessary for submission of a
33 Bid. Bidder must fill all holes and clean up and restore the site to its former
34 conditions upon completion of such explorations, investigations, tests and studies.
35
36 4.1.8. Determine the difficulties of the Work and all attending circumstances affecting the
37 cost of doing the Work, time required for its completion, and obtain all information
38 required to make a proposal. Bidders shall rely exclusively and solely upon their
39 own estimates, investigation, research, tests, explorations, and other data which are
40 necessary for full and complete information upon which the proposal is to be based.
41 It is understood that the submission of a proposal is prima -facie evidence that the
42 Bidder has made the investigation, examinations and tests herein required. Claims
43 for additional compensation due to variations between conditions actually
44 encountered in construction and as indicated in the Contract Documents will not be
45 allowed.
46
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised November 27, 2012
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project#1480
00 21 13 -4
INSTRUCTIONS TO BIDDERS
Page 4 of 10
1 4.1.9. Promptly notify City of all conflicts, errors, ambiguities or discrepancies in or
2 between the Contract Documents and such other related documents. The Contractor
3 shall not take advantage of any gross error or omission in the Contract Documents,
4 and the City shall be permitted to make such corrections or interpretations as may
5 be deemed necessary for fulfillment of the intent of the Contract Documents.
6
7 4.2. Reference is made to Section 00 73 00 — Supplementary Conditions for identification of:
8
9 4.2.1. those reports of explorations and tests of subsurface conditions at or contiguous to
10 the site which have been utilized by City in preparation of the Contract Documents.
11 The logs of Soil Borings, if any, on the plans are for general information only.
12 Neither the City nor the Engineer guarantee that the data shown is representative of
13 conditions which actually exist.
14
15 4.2.2. those drawings of physical conditions in or relating to existing surface and
16 subsurface structures (except Underground Facilities) which are at or contiguous to
17 the site that have been utilized by City in preparation of the Contract Documents.
18
19 4.2.3. copies of such reports and drawings will be made available by City to any Bidder
20 on request. Those reports and drawings may not be part of the Contract
21 Documents, but the "technical data" contained therein upon which Bidder is entitled
22 to rely as provided in Paragraph 4.02. of the General Conditions has been identified
23 and established in Paragraph SC 4.02 of the Supplementary Conditions. Bidder is
24 responsible for any interpretation or conclusion drawn from any "technical data" or
25 any other data, interpretations, opinions or information.
26
27 4.3. The submission of a Bid will constitute an incontrovertible representation by Bidder (i)
28 that Bidder has complied with every requirement of this Paragraph 4, (ii) that without
29 exception the Bid is premised upon performing and furnishing the Work required by the
30 Contract Documents and applying the specific means, methods, techniques, sequences or
31 procedures of construction (if any) that may be shown or indicated or expressly required
32 by the Contract Documents, (iii) that Bidder has given City written notice of all
33 conflicts, errors, ambiguities and discrepancies in the Contract Documents and the
34 written resolutions thereof by City are acceptable to Bidder, and when said conflicts,
35 etc., have not been resolved through the interpretations by City as described in
36 Paragraph 6., and (iv) that the Contract Documents are generally sufficient to indicate
37 and convey understanding of all terms and conditions for performing and furnishing the
38 Work.
39
40 4.4. The provisions of this Paragraph 4, inclusive, do not apply to Asbestos, Polychlorinated
41 biphenyls (PCBs), Petroleum, Hazardous Waste or Radioactive Material covered by
42 Paragraph 4.06. of the General Conditions, unless specifically identified in the Contract
43 Documents.
44
45 5. Availability of Lands for Work, Etc.
46
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised November 27, 2012
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project 41480
0021 13-5
INSTRUCTIONS TO BIDDERS
Page 5 of 10
1 5.1. The lands upon which the Work is to be performed, rights -of -way and easements for
2 access thereto and other lands designated for use by Contractor in performing the Work
3 are identified in the Contract Documents. All additional lands and access thereto
4 required for temporary construction facilities, construction equipment or storage of
5 materials and equipment to be incorporated in the Work are to be obtained and paid for
6 by Contractor. Easements for permanent structures or permanent changes in existing
7 facilities are to be obtained and paid for by City unless otherwise provided in the
8 Contract Documents.
9
10 5.2. Outstanding right-of-way, easements, and/or permits to be acquired by the City are listed
11 in Paragraph SC 4.01 of the Supplementary Conditions. In the event the necessary right-
12 of -way, easements, and/or permits are not obtained, the City reserves the right to cancel
13 the award of contract at any time before the Bidder begins any construction work on the
14 project.
15
16 5.3. The Bidder shall be prepared to eminence construction without all executed right-of-
17 way, easements, and/or permits, and shall submit a schedule to the City of how
18 construction will proceed in the other areas of the project that do not require permits
19 and/or easements.
20
21 6. Interpretations and Addenda
22
23 6.1. All questions about the meaning or intent of the Bidding Documents are to be directed to
24 City in writing on or before 2 p.m., the Monday prior to the Bid opening. Questions
25 received after this day may not be responded to. Interpretations or clarifications
26 considered necessary by City in response to such questions will be issued by Addenda
27 delivered to all parties recorded by City as having received the Bidding Documents.
28 Only questions answered by formal written Addenda will be binding. Oral and other
29 interpretations or clarifications will be without legal effect.
30
31 Address questions to:
32
33 City of Fort Worth
34 1000 Throckmorton Street
35 Fort Worth, TX 76102
36 Attn: Robert Sauceda, Fort Worth Water Department
37 Fax: 817-392-8195
38 Email: robert.sauceda@FortWorthTexas.ov
39 Phone: 682-432-5478
40
41 6.2. Addenda may also be issued to modify the Bidding Documents as deemed advisable by
42 City.
43
44 6.3. Addenda or clarifications may be posted via Buzzsaw at <Insert Link to Documents>.
45
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised November 27, 2012
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project # 1480
0021 13-6
INSTRUCTIONS TO BIDDERS
Page 6 of 10
1 6.4. A prebid conference may be held at the time and place indicated in the Advertisement or
2 INVITATION TO BIDDERS. Representatives of City will be present to discuss the
3 Project. Bidders are encouraged to attend and participate in the conference. City will
4 transmit to all prospective Bidders of record such Addenda as City considers necessary
5 in response to questions arising at the conference. Oral statements may not be relied
6 upon and will not be binding or legally effective.
7
8 7. Bid Security
9
10 7.1. Each Bid must be accompanied by Bid Bond made payable to City in an amount of five
11 (5) percent of Bidder's maximum Bid price on form attached, issued by a surety meeting
12 the requirements of Paragraphs 5.01 of the General Conditions.
13
14 7.2. The Bid Bond of all Bidders will be retained until the conditions of the Notice of Award
15 have been satisfied. If the Successful Bidder fails to execute and deliver the complete
16 Agreement within 10 days after the Notice of Award, City may consider Bidder to be in
17 default, rescind the Notice of Award, and the Bid Bond of that Bidder will be forfeited.
18 Such forfeiture shall be City's exclusive remedy if Bidder defaults. The Bid Bond of all
19 other Bidders whom City believes to have a reasonable chance of receiving the award
20 will be retained by City until final contract execution.
21
22 8. Contract Times
23 The number of days within which, or the dates by which, Milestones are to be achieved in
24 accordance with the General Requirements and the Work is to be completed and ready for
25 Final Acceptance is set forth in the Agreement or incorporated therein by reference to the
26 attached Bid Form.
27
28 9. Liquidated Damages
29 Provisions for liquidated damages are set forth in the Agreement.
30
31 10. Substitute and "Or -Equal" Items
32 The Contract, if awarded, will be on the basis of materials and equipment described in the
33 Bidding Documents without consideration of possible substitute or "or -equal" items.
34 Whenever it is indicated or specified in the Bidding Documents that a "substitute" or "or-
35 equal" item of material or equipment may be furnished or used by Contractor if acceptable to
36 City, application for such acceptance will not be considered by City until after the Effective
37 Date of the Agreement. The procedure for submission of any such application by Contractor
38 and consideration by City is set forth in Paragraphs 6.05A., 6.05B. and 6.05C. of the General
39 Conditions and is supplemented in Section 01 25 00 of the General Requirements.
40
41 11. Subcontractors, Suppliers and Others
42
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised November 27, 2012
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project # 1480
0021 13-7
INSTRUCTIONS TO BIDDERS
Page 7 of 10
1 11.1. In accordance with the City's Business Diversity Enterprise Ordinance No. 20020-
2 12-2011 (as amended), the City has goals for the participation of minority business
3 and/or small business enterprises in City contracts. A copy of the Ordinance can be
4 obtained from the Office of the City Secretary. The Bidder shall submit the MBE and
5 SBE Utilization Form, Subcontractor/Supplier Utilization Form, Prime Contractor
6 Waiver Form and/or Good Faith Effort Form with documentation and/or Joint
7 Venture Form as appropriate. The Forms including documentation must be received
8 by the City no later than 5:00 P.M. CST, five (5) City business days after the bid
9 opening date. The Bidder shall obtain a receipt from the City as evidence the
10 documentation was received. Failure to comply shall render the bid as non-
11 responsive.
12
13 11.2. No Contractor shall be required to employ any Subcontractor, Supplier, other person
14 or organization against whom Contractor has reasonable objection.
15
16 12. Bid Form
17
18 12.1. Bids by corporations shall be executed in the corporate name by the president or a
19 vice-president or other corporate officer accompanied by evidence of authority to
20 sign. The corporate seal shall be affixed. The corporate address and state of
21 incorporation shall be shown below the signature.
22
23 12.2. Bids by partnerships shall be executed in the partnership name and signed by a
24 partner, whose title must appear under the signature accompanied by evidence of
25 authority to sign. The official address of the partnership shall be shown below the
26 signature.
27
28 12.3. Bids by limited liability companies shall be executed in the name of the firm by a
29 member and accompanied by evidence of authority to sign. The state of formation of
30 the firm and the official address of the firm shall be shown.
31
32 12.4. Bids by individuals shall show the Bidder's name and official address.
33
34 12.5. Bids by joint ventures shall be executed by each joint venturer in the manner
35 indicated on the Bid Form. The official address of the joint venture shall be shown.
36
37 12.6. All names shall be typed or printed in ink below the signature.
38
39 12.7. The Bid shall contain an acknowledgement of receipt of all Addenda, the numbers of
40 which shall be filled in on the Bid Form.
41
42 12.8. Postal and e-mail addresses and telephone number for communications regarding the
43 Bid shall be shown.
44
45 12.9. Evidence of authority to conduct business as a Nonresident Bidder in the state of
46 Texas shall be provided in accordance with Section 00 43 37 — Vendor Compliance
47 to State Law Non Resident Bidder.
48
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised November 27, 2012
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project 41,180
0021 13-8
INSTRUCTIONS TO BIDDERS
Page 8 of 10
1 13. Submission of Bids
2 Bids shall be submitted on the prescribed Bid Form, provided with the Bidding Documents,
3 at the time and place indicated in the Advertisement or INVITATION TO BIDDERS,
4 addressed to City Manager of the City, and shall be enclosed in an opaque sealed envelope,
5 marked with the City Project Number, Project title, the name and address of Bidder, and
6 accompanied by the Bid security and other required documents. If the Bid is sent through the
7 mail or other delivery system, the sealed envelope shall be enclosed in a separate envelope
8 with the notation "BID ENCLOSED" on the face of it.
9
10 14. Modification and Withdrawal of Bids
11
12 14.1. Bids addressed to the City Manager and filed with the Purchasing Office cannot be
13 withdrawn prior to the time set for bid opening. A request for withdrawal must be
14 made in writing by an appropriate document duly executed in the manner that a Bid
15 must be executed and delivered to the place where Bids are to be submitted at any
16 time prior to the opening of Bids. After all Bids not requested for withdrawal are
17 opened and publicly read aloud, the Bids for which a withdrawal request has been
18 properly filed may, at the option of the City, be returned unopened.
19
20 14.2. Bidders may modify their Bid by electronic communication at any time prior to the
21 time set for the closing of Bid receipt.
22
23 15. Opening of Bids
24 Bids will be opened and read aloud publicly at the place where Bids are to be submitted. An
25 abstract of the amounts of the base Bids and major alternates (if any) will be made available
26 to Bidders after the opening of Bids.
27
28 16. Bids to Remain Subject to Acceptance
29 All Bids will remain subject to acceptance for the time period specified for Notice of Award
30 and execution and delivery of a complete Agreement by Successful Bidder. City may, at
31 City's sole discretion, release any Bid and nullify the Bid security prior to that date.
32
33 17. Evaluation of Bids and Award of Contract
34
35 17.1. City reserves the right to reject any or all Bids, including without limitation the rights
36 to reject any or all nonconforming, nonresponsive, unbalanced or conditional Bids
37 and to reject the Bid of any Bidder if City believes that it would not be in the best
38 interest of the Project to make an award to that Bidder, whether because the Bid is
39 not responsive or the Bidder is unqualified or of doubtful financial ability or fails to
40 meet any other pertinent standard or criteria established by City. City also reserves
41 the right to waive informalities not involving price, contract time or changes in the
42 Work with the Successful Bidder. Discrepancies between the multiplication of units
43 of Work and unit prices will be resolved in favor of the unit prices. Discrepancies
44 between the indicated sum of any column of figures and the correct sum thereof will
45 be resolved in favor of the correct sum. Discrepancies between words and figures
46 will be resolved in favor of the words.
47
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised November 27, 2012
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project#1480
002113-9
INSTRUCTIONS TO BIDDERS
Page 9 of 10
1 17.1.1. Any or all bids will be rejected if City has reason to believe that collusion exists
2 among the Bidders, Bidder is an interested party to any litigation against City,
3 City or Bidder may have a claim against the other or be engaged in litigation,
4 Bidder is in arrears on any existing contract or has defaulted on a previous
5 contract, Bidder has performed a prior contract in an unsatisfactory manner, or
6 Bidder has uncompleted work which in the judgment of the City will prevent or
7 hinder the prompt completion of additional work if awarded.
8
9 17.2. City may consider the qualifications and experience of Subcontractors, Suppliers, and
10 other persons and organizations proposed for those portions of the Work as to which
11 the identity of Subcontractors, Suppliers, and other persons and organizations must
12 be submitted as provided in the Contract Documents or upon the request of the City.
13 City also may consider the operating costs, maintenance requirements, performance
14 data and guarantees of major items of materials and equipment proposed for
15 incorporation in the Work when such data is required to be submitted prior to the
16 Notice of Award.
17
18 17.3. City may conduct such investigations as City deems necessary to assist in the
19 evaluation of any Bid and to establish the responsibility, qualifications, and financial
20 ability of Bidders, proposed Subcontractors, Suppliers and other persons and
21 organizations to perform and furnish the Work in accordance with the Contract
22 Documents to City's satisfaction within the prescribed time.
23
24 17.4. Contractor shall perform with his own organization, work of a value not less than
25 35% of the value embraced on the Contract, unless otherwise approved by the City.
26
27 17.5. If the Contract is to be awarded, it will be awarded to lowest responsible and
28 responsive Bidder whose evaluation by City indicates that the award will be in the
29 best interests of the City.
30
31 17.6. Pursuant to Texas Government Code Chapter 2252.001, the City will not award
32 contract to a Nonresident Bidder unless the Nonresident Bidder's bid is lower than
33 the lowest bid submitted by a responsible Texas Bidder by the same amount that a
34 Texas resident bidder would be required to underbid a Nonresident Bidder to obtain a
35 comparable contract in the state in which the nonresident's principal place of
36 business is located.
37
38 17.7. A contract is not awarded until formal City Council authorization. If the Contract is
39 to be awarded, City will award the Contract within 90 days after the day of the Bid
40 opening unless extended in writing. No other act of City or others will constitute
41 acceptance of a Bid. Upon the contractor award a Notice of Award will be issued by
42 the City.
43
44 17.8. Failure or refusal to comply with the requirements may result in rejection of Bid.
45
46 18. Signing of Agreement
47 When City issues a Notice of Award to the Successful Bidder, it will be accompanied by the
48 required number of unsigned counterparts of the Agreement. Within 14 days thereafter
49 Contractor shall sign and deliver the required number of counterparts of the Agreement to
50 City with the required Bonds, Certificates of Insurance, and all other required documentation.
51 City shall thereafter deliver one fully signed counterpart to Contractor.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised November 27, 2012
Sanitary Sever Rehab Contract 75, Part 1
CFW Project 41480
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised November 27, 2012
00 21 13 - 10
INSTRUCTIONS TO BIDDERS
Page 10 of 10
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
1 I 24
25
LI
1
11
1Y
003513-1
CONFLICT OF INTEREST AFFIDAVIT
Page 1 of 1
SECTION 00 35 13
CONFLICT OF INTEREST AFFIDAVIT
Each bidder, offeror, or respondent (hereinafter also referred to as "you") to a City of Fort Worth
(also referred to as "City") procurement are required to complete Conflict of Interest
Questionnaire (the attached CIQ Form) and Local Government Officer Conflicts Disclosure
Statement (the attached CIS Form) below pursuant to state law. This affidavit will certify that the
Bidder has on file with the City Secretary the required documentation and is eligible to bid on
City Work. The referenced forms may be downloaded from the website links provided below.
httb://www.ethics.state.tx.us/forms/CIQ.bdf
httb://www.ethics.state.tx.us/forms/CIS.pdf
CIQ Form is on file with City Secretary
CIQ Form is being provided to the City Secretary
CIS Form is on File with City Secretary
CIS Form is being provided to the City Secretary
BIDDER:
27 � 1k 1�n�(o►Ul `_ tS
28 Company
29
30 "f dV S • 1 I - is C
31 Addressdale 32
flL'DL,t011J
34 City/State/Zip
35
36
B
Signature:
ef?;1Aent
(Please Print)
37 END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised March 27, 2012
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
TO: The City Manager
c/o: The Purchasing Department
1000 Throckmorton Street
City of Fort Worth, Texas 76102
FOR:
City Project No.:
Units/Sections:
1. Enter Into Agreement
SECTION 00 41 00
BID FORM
Water & Sanitary Sewer Replacement Contract 75 - Part 1
1480
Unit I Water Improvements
Unit 11 Sanitary Sewer Improvements
00 41 00
BID FORM
Page 1 of 3
The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with City in the form included in the
Bidding Documents to perform and furnish all Work as specified or indicated in the Contract Documents for the Bid Price and within the
Contract Time indicated in this Bid and in accordance with the other terms and conditions of the Contract Documents.
2. BIDDER Acknowledgements and Certification
2.1. In submitting this Bid, Bidder accepts all of the terms and conditions of the INVITATION TO BIDDERS and
INSTRUCTIONS TO BIDDERS, including without limitation those dealing with the disposition of Bid Bond.
2.2. Bidder is aware of all costs to provide the required insurance, will do so pending contract award, and will provide a valid
insurance certificate meeting all requirements within 14 days of notification of award.
2.3. Bidder certifies that this Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity
and is not submitted in conformity with any collusive agreement or rules of any group, association, organization, or
corporation.
2.4. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid.
2.5. Bidder has not solicited or induced any individual or entity to refrain from bidding.
2.6. Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract. For the
purposes of this Paragraph:
a. "corrupt practice" means the offering, giving, receiving, or soliciting of any thing of value likely to influence
the action of a public official in the bidding process.
b. "fraudulent practice" means an intentional misrepresentation of facts made (a) to influence the bidding
process to the detriment of City (b) to establish Bid prices at artificial non-competitive levels, or (c) to
deprive City of the benefits of free and open competition.
c. 'collusive practice" means a scheme or arrangement between two or more Bidders, with or without the
knowledge of City, a purpose of which is to establish Bid prices at artificial, non-competitive levels.
d. "coercive practice" means harming or threatening to harm, directly or indirectly, persons or their property tc
influence their participation in the bidding process or affect the execution of the Contract.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Form Revised 20120327
00 41 00 Bid Proposal Workbook
3. Prequalification
The Bidder acknowledges that the following work types must be performed only by prequalified contractors and subcontractors:
a.
b.
c.
d.
4. Time of Completion
00 41 00
BID FORM
Page 2 of 3
4.1. The Work will be complete for Final Acceptance within 180 days after the date when the
the Contract Time commences to run as provided in Paragraph 2.03 of the General Conditions.
4.2. Bidder accepts the provisions of the Agreement as to liquidated damages in the event of failure to complete the Work
(and/or achievement of Milestones) within the times specified in the Agreement.
5. Attached to this Bid
The following documents are attached to and made a part of this Bid:
a. This Bid Form, Section 00 41 00
b. Required Bid Bond, Section 00 43 13 issued by a surety meeting the requirements of Paragraph 5.01 of
the General Conditions.
c. Proposal Form, Section 00 42 43
d. Vendor Compliance to State Law Non Resident Bidder, Section 00 43 37
e. MWBE Forms (optional at time of bid)
f. Prequalification Statement, Section 00 45 12
g. Conflict of Interest Affidavit, Section 00 35 13
*If necessary, CIQ or CIS forms are to be provided directly to City Secretary
h. Any additional documents that may be required by Section 12 of the Instructions to Bidders
6. Total Bid Amount
6.1. Bidder will complete the Work in accordance with the Contract Documents for the following bid amount. In the space
provided below, please enter the total bid amount for this project. Only this figure will be read publicly by the City at the
bid opening.
6.2. It is understood and agreed by the Bidder in signing this proposal that the total bid amount entered below is subject to
verification and/or modification by multiplying the unit bid prices for each pay item by the respective estimated quantities
shown in this proposal and then totaling all of the extended amounts.
Total Bid $
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Form Revised 20120327
00 41 00 Bid Proposal Workbook
7. Bid Submittal
This Bid is submitted on
Respectfully sub
By:
gnature)
G V i\ C. RD ,) MA9'f'1_
(Printed Name)
Tit le 1/44 Dad --
Company: L OX‘A"fc\ c 'Si
Address: i fw j� j�* ,r /7
Ke k7 e e , T 7lo�<aa�
State of Incorporation: ,—,�--
by the entity named below.
Email: J80/i11%91A ear%Cd iffrS> ,err/ j GY 5
Phone: g(-7 ,. tog 7
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Form Revised 20120327
Receipt is acknowledged of
the following Addenda:
Addendum No. 1: • 111
Addendum No. 2:
Addendum No. 3:
Addendum No. 4:
Corporate Seal:
00 41 00
BID FORM
Page 3 of 3
In al
00 41 00 Bid Proposal Workbook
o. 01480
Ci(yAYoject CPMS No. APPROX. UNIT
ITEM I QUANTITY
UNIT I • WATER IMPROVEMENTS
SECTION 00 42 43
PROPOSAL
DESCRIPTION OF ITEM
BID PRICES WRITTEN IN WORDS I UNIT PRICE
AMOUNT BID
5tkicr4• "TtryDollars &
1 3311.0241 1,010 LF 8" Water Pipe u0 Cents 72.00 72,720.00
Ohm /AiADag. D
frp*D 1k v Dollars &
2 3311.0251 60 LF 8" DIP Water MO Cents 110.00 6,600.00
AO 05/hd Dollars &
3 3311.0001 1 TN Ductile Iron Water Fittings o Cents 5,000.00 5,000.00
kVO Ahouta..,.,
t //L nI.%.rl Dollars &
4 3312.0001 1 EA Fire Hydrant /tt/) Cents 2,500.00 2,500.00
OAt rhoLSaonce
/N'o h(f6tdrCd Dollars &
5 3312.3003 4 EA 8" Gate Valve No Cents 1,200.00 4,800.00
/7{J0 I►.t tZ,.B ,� Dollars &
6 3312.2003 2 EA 1" Water Service MC Cents 1,200.00 2,400.00
7 3312.2001 2 EA 1" Water Service, Meter Relocation
air tir,izep Dollars &
0 Cents 100.00 200.00
'Y,r LI :t►Dollars&
8 3312.0102 2 EA Connection to Existing 6" Water Main . / Cents 800.00 1,600.00
►Vito% DDollars &
9 3312.0103 2 EA Connection to Existing 8" Water Main /10 112.CD Cents 1,500.00 3,000.00
°he TA 0oSakcr
7 JG *dtbR % Dollars &
10 3304.0101 2 LS Temporary Water Services A/O Cents 1,200.00 2,400.00
i ''1 Dollars &
11 3305.0204 10 CY Imported Embedment/Backfill, Crushed Rock NO Cents 30.00 300.00
12 3305.0109 1066 LF Trench Safety
0 isi" Dollars &
AID Cents 1.00 1,066.00
Ftehti
13 3201.0400 1055 LF Temporary Asphalt Paving Repair
Dollars &
Cents 18.00 18,990.00
Theirh i --SIX
14 3201.0111 350 LF 4' Wide Asphalt Pvmt Repair. Residential .�..
/ "'/
15 3201.0113 710 LF 6' Wide Asphalt Pvmt Weir, Residential Ail?
16 3213.0401 35 SF 6" Concrete Driveway IU OCents
Dollars &
Cents 26.00 9,100.00
Dollars &
Cents 30.00 21,300.00
Dollars &
10.00 350.00
Erhh _e,,'A Dollars &
17 3216.0302 15 SY 11" Conc Valley Gutter, Arterial/Industrial Cents 88.00 1,320.00
pair T,054 d
p' i/ pi/'I.1.teODollars &
18 3471.0001 3 Month Traffic Control A49 Cents 1,500.00 4,500.00
/G d Dollars &
19 3292.0100 10 SY Block Sod Placement A./O Cents 10.00 100.00
SUB -TOTAL UNIT I WATER IMPROVEMENTS : $ $158,246.00
CITY OF FORT WORTH Sanitary Sewer Rehabilitation Contract 75, Part 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project NO. 01480
City Project No. 01480
PAY
ITEM CPMS No. QUANTITY I UNIT
UNIT II - SANITARY SEWER IMPROVEMENTS
SECTION 00 42 43
PROPOSAL FORM
DESCRIPTION OF ITEMS
BID PRICES IN WORDS
UNIT PRICE AMOUNT BID
7 61 r'4- �! Dollars &
1 3331.4108 15 LF 6" Sewer Pipe '_A(O Cents 72.00 1,080.00
g/ 1e-0zf Dollars &
2 3331.4115 5,488 LF 8" Sewer Pipe /(/o Cents 80.00 439,040.00
- VA" Dollars &
3 3331.4208 2,463 LF 12" Sewer Pipe ' i1/o Cents 86.00 211,818.00
Olt t Am Mao rinr Dollars &
4 3331.4209 86 LF 12" Sewer Pipe, CSS Backfill /Y• Cents 110.00 9,460.00
71 /'t'+9 • Alle Dollars &
5 3331.4215 1,365 LF 15" Sewer Pipe WOCents 135.00 184,275.00
oneAvitit/`fF Ilars &
6 3331.1102 160 LF 8" Pipe Enlargement a Cents 150.00 24,000.00
7CvG '"F+Ve Dollars &
7 3331.2102 535 LF 8" CIPP 4i Cents 75.00 40,125.00
C. Akln 444tI/t'Dollars &
8 3471.0001 6 Month Traffic Control ' /{/G Cents 1,800.00 10,800.00
Z4Jl'S °Y "Dol'ars&
9 3125.0101 1 LS SWPPP >_ 1 acre I N° Cents 8,000.00 8,000.00
f%%b e Dollars &
10 3301.0002 10,790 LF Post -CCTV Inspection /\ltl9 Cents 1.00 10,790.00
%-ere Dollars &
11 3301.0001 9,565 LF Pre -CCTV Inspection ""/VO/ Cents 3.00 28,695.00
a'fk4i /{Dollars &
12 3305.0103 4 EA Exploratory Excavation of Existine Utilities A /D _Cents 1,500.00 6,000.00
•11511ALrd._1�ollars &
13 0241.2201 34 EA Remove 4' Sewer Manhole �1(o Cents 400.00 13,600.00
Dollars &
14 3339.0002 1,245 SF Epoxy Structure Liner A/0 Cents 14.00 17,430.00
raig-
/51,4e- Zlo�si.cc/
hl//1D/agbDollars &
15 3339.1002 7 EA 4' Drop Manhole %//O Cents 4,500.00 31,500.00
• 4 V/d&FDollars &
16 3339.1001 36 EA 4' Manhole ii/o Cents 3,800.00 136,800.00
• th/,Aal2ii Dollars &
17 3339.1003 142 VF 4' Extra Depth Manhole NO Cents 100.00 14,200.00
CITY OF FORT WORTH Sanitary Sewer Rehabilitation Contract 75, Part 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project NO. 01480
PAY
APPROX.
ITEM CPMS No. QUANTITY UNIT
UNIT II - SANITARY SEWER IMPROVEMENTS
DESCRIPTION OF ITEMS
BID PRICES IN WORDS
UNIT PRICE AMOUNT BID
fi k 71 14 Dollars &
18 3339.1102 1 EA 5' Drop Manhole O i //�� Cents 6,000.00 6,000.00
ay h ✓ d 444pllars &
19 3339.1103 10 VF 5' Extra Depth Manhole � A/ 0 Cents 150.00 1,500.00
,l tram; 14"Nlietxoliars &
20 3331.3101 231 EA 4" Sewer Service /ti• Cents 300.00 69,300.00
9N! w e 4 Dollars &
21 0241.2001 90 CY Sanitary Line Grouting Alt"Cents 110.00 9,900.00
f Gt)C ' 7 Dollars &
22 3305.0204 160 CY Imported Embedment/Backfill, Crushed Rock J/_9 Cents 25.00 4,000.00
1L✓9 Dollars &
23 3305.0109 9,140 LF Trench Safety 4.10 Cents 2.00 18,280.00
/Z-r/ Dollars &
24 3216.0101 60 LF 6" Cone Curb and Gutter C2 Cents 40.00 2,400.00
cT H Dollars &
25 3216.0301 115 SY 6" Cone Valley Gutter dIR% Cents 90.00 10,350.00
Dollars &
26 3341.0103 60 LF 18" RCP, Class III Ai U Cents 80.00 4,800.00
IfiAttli Dollars &
27 3341.0201 40 LF 21" RCP, Class III /1/0 Cents 90.00 3,600.00
OH�t' it/N Di/- D
lwzl '1>f Dollars &
28 3341.0205 20 LF 24" RCP, Class 111 Att, . Cents 120.00 2,400.00
S%C't Dollars &
29 3341.0309 10 LF 36" RCP, Class III Ali Cents 160.00 1,600.00
r 116 Dollars &
30 3441.1301 200 LF Loop Detector Cable Sawcut A/O Cents 5.00 1,000.00
!r id Dollars &
31 3441.1302 200 LF 14 AWG Loop Detect Cable ��/�/ O Cents 10.00 2,000.00
it /41/1.bIQ.Q-)Dollars &
32 0241.4001 1 EA Remove 10' Curb Inlet .A/ Cents 600.00 600.00
f
Y!*eee 7 JJJIII��� ' 23(I Dollars &
33 3349.5001 1 EA 10' Curb Inlet / 0 Cents 5,000.00 5,000.00
I-�%2'G.--t Dollars &
34 3201.0400 4330 LF Temporary Asphalt Paving Repair Ai Cents 18.00 77,940.00
TAT;oliars &
35 3201.0113 4000 LF 6' Wide Asphalt Pvm[ Repair, Residential �I ° Cents 28.00 112,000.00
"-ifL Dollars &
36 3213.0400 1060 SF 5" Cone Driveway �U Cents 8.00 8,480.00
ate +AI/Dollars
&
37 3201.0613 70 SY 8" Cone Pvmt Repair Cents 100.00 7,000.00
CITY OF FORT WORTH Sanitary Sewer Rehabilitation Contract 75, Part l
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project NO. 01480
PAY
ITEM
CPMS No. APPROX.
QUANTITY
UNIT
UNIT II - SANITARY SEWER IMPROVEMENTS
DESCRIPTION OF ITEMS
BID PRICES IN WORDS
0/lc 4fynppci
UNIT PRICE AMOUNT BID
— y I G "" Af/L Dollars &
38 3331.4212 465 LF 12" DIP Sewer . Cents 145.00 67,425.00
Ohe �//'na2ca
!%i`f sM4i Dollars &
39 3331.4222 145 LF 16" DIP Sewer /l//i Cents 180.00 26,100.00
7re"e A
lJi X Dollars &
40 3305.1104 465 LF 30" Casing By Other Than Open Cut 0�,/� ��Cents 360.00 167,400.00
�v rl /''" "' Dollars &
41 3305.1106 145 LF 36" Casing By Other Than Open Cut __4./0 Cents 400.00 58,000.00
i CI h'f )?►41dj' t'lars &
42 0135.0102 25 WD Railroad Flagmen AJ O Cents 800.00 20,000.00
.
i:^ Dollars &
43 3292.0100 100 SY Block Sod Placement /V _Cents 10.00 1,000.00
0 11/e-44:2,2 ar3 &
44 75 LF 12" DIP Sewer by Other than Open Cut �tf 0 _Cents 280.00 21,000.00
/ 6 1hiven Dollars &
45 3331.3105 95 LF 4" Sant. Sewer service -Private relocation ' WO Cents 18.00 1,710.00
',/X 7�7�/%t�Dollars &
46 241.2105 4 EA 12" sewer abandonment Plug !V Cents 600.00 2,400.00
1641 Dollars &
47 241.0500 400 EA Remove Fence /t/" Cents 10.00 4,000.00
t-71;°Dollars &
48 3231.0412 200 LF 6' Wood Fence / Cents 22.00 4,400.00
49 3231.0113 200 LF 6' Chain Link -steel
11---0411
Dollars &
Cents 30.00 6,000.00
SUB -TOTAL UNIT II SEWER IMPROVEMENTS: $ $1,915,198.00
TOTAL TO BE READ AT BID OPENING: $ $2,073,444.00
CITY OF FORT WORTH Sanitary Sewer Rehabilitation Contract 75, Part 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project NO. 01480
00 43 37
VENDOR COMPLIANCE TO STATE LAW
Page 1 of 1
SECTION 00 43 37
VENDOR COMPLIANCE TO STATE LAW NON RESIDENT BIDDER
Texas Government Code Chapter 2252 was adopted for the award of contracts to nonresident bidders. This law
provides that, in order to be awarded a contract as low bidder, nonresident bidders (out-of-state contractors whose
corporate offices or principal place of business are outside the State of Texas) bid projects for construction,
improvements, supplies or services in Texas at an amount lower than the lowest Texas resident bidder by the
same amount that a Texas resident bidder would be required to underbid a nonresident bidder in order to obtain a
comparable contract in the State which the nonresident's principal place of business is located.
A. Nonresident bidders in the State of , our principal place of business,
are required to be percent lower than resident bidders by State Law. A copy of the
statute is attached.
Nonresident bidders in the State of , our principal place of business,
are not required to underbid resident bidders.
B. The principal place of business o^f ocompany or our parent company or majority owner is
in the State of Texas. L�'
BIDDER:
By: ST v
(Signature)
Title: �ReS► oet\i—
Date: /D/ 3// 13
c• Bi)61m
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Form Revised 20110627
00 41 00 Bid Proposal Workbook
004511-1
BIDDERS PREQUALIFICATIONS
Page 1 of 3
1 SECTION 00 45 11
2 BIDDERS PREQUALIFICATIONS
3
4 1. Summary. All contractors are required to be prequalified by the City prior to submitting
5 bids. To be eligible to bid the contractor must submit Section 00 45 12, Prequalification
6 Statement for the work type(s) listed with their Bid. Any contractor or subcontractor who is
7 not prequalified for the work type(s) listed must submit Section 00 45 13, Bidder
8 Prequalification Application in accordance with the requirements below.
9
10 The prequalification process will establish a bid limit based on a technical evaluation and
11 financial analysis of the contractor. The information must be submitted seven (7) days prior
12 to the date of the opening of bids. For example, a contractor wishing to submit bids on
13 projects to be opened on the 7th of April must file the information by the 31st day of March
14 in order to bid on these projects. In order to expedite and facilitate the approval of a Bidder's
15 Prequalification Application, the following must accompany the submission.
16 a. A complete set of audited or reviewed financial statements.
17 (1) Classified Balance Sheet
18 (2) Income Statement
19 (3) Statement of Cash Flows
20 (4) Statement of Retained Earnings
21 (5) Notes to the Financial Statements, if any
22 b. A certified copy of the firm's organizational documents (Corporate Charter, Articles
23 of Incorporation, Articles of Organization, Certificate of Formation, LLC
24 Regulations, Certificate of Limited Partnership Agreement).
25 c. A completed Bidder Prequalification Application.
26 (1) The firm's Texas Taxpayer Identification Number as issued by the Texas
27 Comptroller of Public Accounts. To obtain a Texas Taxpayer Identification
28 number visit the Texas Comptroller of Public Accounts online at the
29 following web address www.window.state.tx.us/taxnermit/ and fill out the
30 application to apply for your Texas tax ID.
31 (2) The firm's e-mail address and fax number.
32 (3) The firm's DUNS number as issued by Dun & Bradstreet. This number
33 is used by the City for required reporting on Federal Aid projects. The DUNS
34 number may be obtained at www.dnb.com.
35 d. Resumes reflecting the construction experience of the principles of the firm for firms
36 submitting their initial prequalification. These resumes should include the size and
37 scope of the work performed.
38 e. Other information as requested by the City.
39
40 2. Prequalification Requirements
41 a. Financial Statements. Financial statement submission must be provided in
42 accordance with the following:
43 (1) The City requires that the original Financial Statement or a certified copy
44 be submitted for consideration.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project#1480
004511-2
BIDDERS PREQUALIFICATIONS
Page 2 of 3
1 (2) To be satisfactory, the financial statements must be audited or reviewed
2 by an independent, certified public accounting firm registered and in
3 good standing in any state. Current Texas statues also require that
4 accounting firms performing audits or reviews on business entities within
5 the State of Texas be properly licensed or registered with the Texas State
6 Board of Public Accountancy.
7 (3) The accounting firm should state in the audit report or review whether
8 the contractor is an individual, corporation, or limited liability company.
9 (4) Financial Statements must be presented in U.S. dollars at the current rate
10 of exchange of the Balance Sheet date.
11 (5) The City will not recognize any certified public accountant as
12 independent who is not, in fact, independent.
13 (6) The accountant's opinion on the financial statements of the contracting
14 company should state that the audit or review has been conducted in
15 accordance with auditing standards generally accepted in the United
16 States of America. This must be stated in the accounting firm's opinion.
17 It should: (1) express an unqualified opinion, or (2) express a qualified
18 opinion on the statements taken as a whole.
19 (7) The City reserves the right to require a new statement at any time.
20 (8) The financial statement must be prepared as of the last day of any month,
21 not more than one year old and must be on file with the City 16 months
22 thereafter, in accordance with Paragraph 1.
23 (9) The City will determine a contractor's bidding capacity for the purposes
24 of awarding contracts. Bidding capacity is determined by multiplying the
25 positive net working capital (working capital = current assets — current
26 liabilities) by a factor of 10. Only those statements reflecting a positive
27 net working capital position will be considered satisfactory for
28 prequalification purposes.
29 (10) In the case that a bidding date falls within the time a new financial
30 statement is being prepared, the previous statement shall be updated with
31 proper verification.
32 b. Bidder Prequalification Application. A Bidder Prequalification Application must be
33 submitted along with audited or reviewed financial statements by firms wishing to be
34 eligible to bid on all classes of construction and maintenance projects. Incomplete
35 Applications will be rejected.
36 (1) In those schedules where there is nothing to report, the notation of
37 "None" or "N/A" should be inserted.
38 (2) A minimum of five (5) references of related work must be provided.
39 (3) Submission of an equipment schedule which indicates equipment under
40 the control of the Contractor and which is related to the type of work for
41 which the Contactor is seeking prequalification. The schedule must
42 include the manufacturer, model and general common description of
43 each piece of equipment. Abbreviations or means of describing
44 equipment other than provided above will not be accepted.
45
46 3. Eligibility to Bid
47 a. The City shall be the sole judge as to a contractor's prequalification.
48 b. The City may reject, suspend, or modify any prequalification for failure by the
49 contractor to demonstrate acceptable financial ability or performance.
50 c. The City will issue a letter as to the status of the prequalification approval.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project#1480
1
2
3
4
5
6
7
8
9
00 45 11 - 3
BIDDERS PREQUALIFICATIONS
Page 3 of 3
d. If a contractor has a valid prequalification letter, the contractor will be eligible to bid
the prequalified work types until the expiration date stated in the letter.
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project # 1480
00 45 12 - 1
PREQUALIFICATION STATEMENT
Page 1 of 1
1 SECTION 00 45 12
2 PREQUALIFICATION STATEMENT
3 Each Bidder for a City procurement is required to complete the information below by
4 identifying the prequalified contractors and/or subcontractors whom they intend to utilize for the
5 major work type(s) listed.
6
Major Work Contractor/Subcontractor Company Name
Type
wniu56ic✓ F;(�
Prequalification
Expiration Date
‘/P1
8
9 The undersigned hereby certifies that the contractors and/or subcontractors described in
10 the table above are currently prequalified for the work types listed.
11
12 BIDDER:
13
14hki4c.(021 By: Sl A C
15 Company lea 6Pri
16 �/s�
17 T�i G�
'�� (it/ ' G� /�QC'C Signature:
18 A.dr-ss
20 0 � r4r n '� Title: �51�
21 Cit State/Zip (Please Print)
22
23
24
25
26
Date:
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1,2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project#1480
00 41 00
BID FORM
Page 1 of 3
TO: The City Manager
c/o: The Purchasing Department
1000 Throckmorton Street
City of Fort Worth, Texas 76102
FOR:
City Project No.:
Units/Sections:
1. Enter Into Agreement
SECTION 00 41 00
BID FORM
Water & Sanitary Sewer Replacement Contract 75 - Part 1
1480
Unit I Water Improvements
Unit II Sanitary Sewer Improvements
The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with City in the form included in the
Bidding Documents to perform and furnish all Work as specified or indicated in the Contract Documents for the Bid Price and within the
Contract Time indicated in this Bid and in accordance with the other terms and conditions of the Contract Documents.
2. BIDDER Acknowledgements and Certification
2.1. In submitting this Bid, Bidder accepts all of the terms and conditions of the INVITATION TO BIDDERS and
INSTRUCTIONS TO BIDDERS, including without limitation those dealing with the disposition of Bid Bond.
2.2. Bidder is aware of all costs to provide the required insurance, will do so pending contract award, and will provide a valid
insurance certificate meeting all requirements within 14 days of notification of award.
2.3. Bidder certifies that this Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity
and is not submitted in conformity with any collusive agreement or rules of any group, association, organization, or
corporation.
2.4. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid.
2.5. Bidder has not solicited or induced any individual or entity to refrain from bidding.
2.6. Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract. For the
purposes of this Paragraph:
a. "corrupt practice" means the offering, giving, receiving, or soliciting of any thing of value likely to influence
the action of a public official in the bidding process.
b. "fraudulent practice" means an intentional misrepresentation of facts made (a) to influence the bidding
process to the detriment of City (b) to establish Bid prices at artificial non-competitive levels, or (c) to
deprive City of the benefits of free and open competition.
c. "collusive practice" means a scheme or arrangement between two or more Bidders, with or without the
knowledge of City, a purpose of which is to establish Bid prices at artificial, non-competitive levels.
d. "coercive practice" means harming or threatening to harm, directly or indirectly, persons or their property tc
influence their participation in the bidding process or affect the execution of the Contract.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Form Revised 20120327
0041 00 Bid Proposal Workbook
3. Prequalification
The Bidder acknowledges that the following work types must be performed only by prequalified contractors and subcontractors:
a.
b.
c.
d.
4. Time of Completion
00 41 00
BID FORM
Page 2 of 3
4.1. The Work will be complete for Final Acceptance within 180 days after the date when the
the Contract Time commences to run as provided in Paragraph 2.03 of the General Conditions.
4.2. Bidder accepts the provisions of the Agreement as to liquidated damages in the event of failure to complete the Work
{and/or achievement of Milestones} within the times specified in the Agreement.
5. Attached to this Bid
The following documents are attached to and made a part of this Bid:
a. This Bid Form, Section 00 41 00
b. Required Bid Bond, Section 00 43 13 issued by a surety meeting the requirements of Paragraph 5.01 of
the General Conditions.
c. Proposal Form, Section 00 42 43
d. Vendor Compliance to State Law Non Resident Bidder, Section 00 43 37
e. MWBE Forms (optional at time of bid)
f. Prequalification Statement, Section 00 45 12
g. Conflict of Interest Affidavit, Section 00 35 13
'If necessary, CIQ or CIS forms are to be provided directly to City Secretary
h. Any additional documents that may be required by Section 12 of the Instructions to Bidders
6. Total Bid Amount
6.1. Bidder will complete the Work in accordance with the Contract Documents for the following bid amount. In the space
provided below, please enter the total bid amount for this project. Only this figure will be read publicly by the City at the
bid opening.
6.2. It is understood and agreed by the Bidder in signing this proposal that the total bid amount entered below is subject to
verification and/or modification by multiplying the unit bid prices for each pay item by the respective estimated quantities
shown in this proposal and then totaling all of the extended amounts.
Total Bid $
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Form Revised 20120327
00 41 00 Bid Proposal Workbook
00 41 00
BID FORM
Page 3 of 3
7. Bid Submittal
This Bid is submitted on by the entity named below.
Respectfully submitted,
By:
(Signature)
Title:
Company:
Address:
State of Incorporation:
Email:
Phone:
(Printed Name)
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Form Revised 20120327
Receipt is acknowledged of
the following Addenda:
'Addendum No. 1:
(Addendum No. 2:
(Addendum No. 3:
(Addendum No. 4:
Corporate Seal:
Initial
00 41 00 Bid Proposal Workbook
City Project No. 01480
ITEM I CPMS No. I APPROX. QUANTITY I UNIT
UNIT I- WATER IMPROVEMENTS
SECTION 00 42 43
PROPOSAL
DESCRIPTION OF ITEM
BID PRICES WRITTEN IN WORDS I UNIT PRICE I AMOUNT BID
Dollars &
1 3311.0241 1,010 LF 8" Water Pipe Cents $ $
Dollars &
2 3311.0251 60 LF 8" DIP Water Cents $ $
Dollars &
3 3311.0001 1 TN Ductile Iron Water Fittinfs Cents $ $
Dollars &
4 3312.0001 1 EA Fire Hydrant Cents $ $
Dollars &
5 3312.3003 4 EA 8" Gate Valve Cents $ $
Dollars &
6 3312.2003 2 EA 1" Water Service Cents $ $
Dollars &
7 3312.2001 2 EA 1" Water Service, Meter Relocation Cents $ $
Dollars &
8 3312.0102 2 EA Connection to Existing 6" Water Main Cents $ $
Dollars &
9 3312.0103 2 EA Connection to Existing 8" Water Main Cents $ $
Dollars &
10 3304.0101 2 LS Temporary Water Services Cents $ $
Dollars &
11 3305.0204 10 CY Imported Embedment/Backfill, Crushed Rock ,Cents $ $
Dollars &
12 3305.0109 1066 LF Trench Safety Cents $ $
Dollars &
13 3201.0400 1055 LF Temporary Asphalt Paving Repair Cents $ $
Dollars &
14 3201.0111 350 LF 4' Wide Asphalt Pvmt Repair, Residential Cents $ $
Dollars &
15 3201.0113 710 LF 6' Wide Asphalt Pvmt Repair, Residential Cents $ $
Dollars &
16 3213.0401 35 SF 6" Concrete Driveway Cents $ $
Dollars &
17 3216.0302 15 SY 11" Cone Valley Gutter, Arterial/Industrial Cents $ $
Dollars &
18 3471.0001 3 Month Traffic Control Cents $ $
Dollars &
19 3292.0100 10 SY Block Sod Placement Cents $ $
SUB -TOTAL UNIT I WATER IDIPROVERIENTS : S
CITY OF FORT WORTH Sanitary Sewer Rehabilitation Contract 75, Part 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project NO.01480
City Project No. 01480
ITEM I CPMS No. 1 QUAN APPRTTYX.
' UNIT
UNIT II SANITARY SEWER IMPROVEMENTS
SECTION 00 42 43
PROPOSAL FORM
DESCRIPTION OF ITEMS
BID PRICES IN WORDS
UNIT PRICE AMOUNT BID
Dollars &
1 3331.4108 15 LF 6" Sewer Pipe Cents $ $
Dollars &
2 3331.4115 5,488 LF 8" Sewer Pipe Cents $ $
Dollars &
3 3331.4208 2,463 LF 12" Sewer Pipe Cents $ $
Dollars &
4 3331.4209 86 LF 12" Sewer Pipe, CSS Backfill Cents $ $
Dollars &
5 3331.4215 1,365 LF 15" Sewer Pipe Cents $ $
Dollars &
6 3331.1102 160 LF 8" Pipe Enlargement Cents $ $
Dollars &
7 3331.2102 535 LF 8" CIPP Cents $ $
Dollars &
8 3471.0001 6 Month Traffic Control Cents $ $
Dollars &
9 3125.0101 1 LS SWPPP ? 1 acre Cents $
Dollars &
10 3301.0002 10,790 LF Post -CCTV Inspection Cents $
Dollars &
11 3301.0001 9,565 LF Pre -CCTV Inspection Cents $
Dollars &
12 3305.0103 4 EA Exploratory Excavation of Existing Utilities Cents $
Dollars &
13 0241.2201 34 EA Remove 4' Sewer Manhole Cents $
Dollars &
14 3339.0002 1,245 SF Epoxy Structure Liner Cents $
Dollars &
15 3339.1002 7 EA 4' Drop Manhole Cents $
Dollars &
16 3339.1001 36 EA 4' Manhole Cents $
Dollars &
17 3339.1003 142 VF 4' Extra Depth Manhole Cents $
CITY OF FORT WORTH Salutary Scecr Rehabilitation Contract 75, Part I
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project NO. 01480
PAY
APPROX.
ITEM I CPMS No. I QUANTITY I UNIT
UNIT 11 - SANITARY SEWER IMPROVEMENTS
DESCRIPTION OF ITEMS
BID PRICES IN WORDS
Dollars &
18 3339.1102 1 EA 5' Drop Manhole Cents $
Dollars &
19 3339.1103 10 VF 5' Extra Depth Manhole Cents $
Dollars &
20 3331.3101 231 EA 4" Sewer Service Cents $
Dollars &
21 02,11.2001 90 CY Sanitary Line Grouting _Cents $
Imported EmbedmenVBackfill, Crushed Dollars &
22 3305.0204 160 CY Rock Cents $
Dollars &
23 3305.0109 9,140 LF Trench Safety Cents $
Dollars &
24 3216.0101 60 LF 6" Conc Curb and Gutter Cents $
Dollars &
25 3216.0301 115 SY 6" Conc Valley Gutter _Cents $
Dollars &
26 3341.0103 60 LF 18" RCP, Class III Cents $
Dollars &
27 3341.0201 40 LF 21" RCP, Class III Cents $
Dollars &
28 3341.0205 20 LF 24" RCP, Class Ill _ Cents $
Dollars &
29 3341.0309 10 LF 36" RCP, Class Ill Cents $
Dollars &
30 3441.1301 200 LF Loop Detector Cable Sawcut Cents $
Dollars &
31 3441.1302 200 LE 14 AWG Loop Dclect Cable Cents $
Dollars &
32 0241.4001 1 EA Remove 10' Curb Inlet Cents $
Dollars &
33 3349.5001 1 EA 10' Curb Inlet _ Cents $
Dollars &
34 3201.0400 4330 LF Temporary Asphalt Paving Repair Cents $
Dollars &
35 3201.0113 4000 LF 6' Wide Asphalt Pvmt Repair, Residential Cents $
Dollars &
36 3213.0400 1060 SF 5" Conc Driveway Cents $
Dollars &
37 3201.0613 70 SY 8" Conc Pvnrt Repair _ _Cents $
UNIT PRICE AMOUNT BID
CITY OF FORT \NORTH Sanitary Sorer Rehabilitation Contract 75, Part I
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project NO. 01480
X.
ITEM CPD7S No. QUANTOITY I UNIT
UNIT 11 SANITARY SEWER IMPROVEMENTS
DESCRIPTION OF ITEMS
BID PRICES IN WORDS
UNIT PRICE AMOUNT BID
Dollars &
38 3331.42I2 540 LF 12" DIP Sewer Cents $ $
Dollars &
39 3331.4222 145 LF 16" DIP Sewer Cents $ $
Dollars &
40 3305.1104 465 LF 30" Casing By Other Than Open Cut Cents $ $
Dollars &
41 3305.1106 145 LF 36" Casing By Other Than Open Cut Cents $ $
Dollars &
42 0135.0102 25 WD Railroad Flagmen Cents $ $
Dollars &
43 3292.0100 100 SY Block Sod Placement Cents $ $
SUB -TOTAL UNIT II SEWER IMPROVEMENTS: $
TOTAL TO BE READ AT BID OPENING: $
CITY OF FORT NORTH Sanitary Serer Rehabilitation Contract 75. Part 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project NO. 01481)
SECTION 00 43 13
BID BOND
KNOW ALL BY THESE PRESENTS:
00 43 13
BID BOND
Page 1 of 1
That we, (Bidder Name)
hereinafter called the Principal, and (Surety Name)
a corporation or firm duly authorized to transact surety business in the State of Texas, hereinafter called the Surety, are held and
firmly bound unto the City, hereinafter called the Obligee, in the
sum of and No/100 Dollars
($ .00), the payment of which sum will be well and truly made and the
WHEREAS, the Principal has submitted a proposal to perform work for the following project of the Obligee,
identified as Water & Sanitary Sewer Replacement Contract 75 - Part 1
NOW, THEREFORE, if the Obligee shall award the Contract for the foregoing project to
the Principal, and the Principal shall satisfy all requirements and conditions required for the execution of the Contract and shall
enter into the Contract in writing with the Obligee in accordance with the terms of such proposal, then this bond shall be null and
void. If the Principal fails to execute such Contract in accordance with the terms of such proposal or fails to satisfy all requirements
and conditions required for the execution of the Contract in accordance with the proposal or fails to satisfy all requirements and
conditions required for the execution of the Contract in accordance with the proposal, this bond shall become the property of the
Obligee, without recourse of the Principal and/or Surety, not to exceed the penalty hereof, and shall be used to compensate Obligee for
the difference between Principal's Total Bid Amount and the next selected Bidder's Total Bid Amount.
SIGNED this
By:
*By:
*Attach Power of Attorney (Surety) for Attorney -in -Fact
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Form Revised 20110627
day of , 2013.
(Signature and Title of Principal)
(Signature of Attorney -of -Fact)
END OF SECTION
Impressed
Surety Seal
Only
00 41 00 Bid Proposal Workbook
00 43 37
VENDOR COMPLIANCE TO STATE LAW
Page 1 of 1
SECTION 00 43 37
VENDOR COMPLIANCE TO STATE LAW NON RESIDENT BIDDER
Texas Government Code Chapter 2252 was adopted for the award of contracts to nonresident bidders. This law
provides that, in order to be awarded a contract as low bidder, nonresident bidders (out-of-state contractors whose
corporate offices or principal place of business are outside the State of Texas) bid projects for construction,
improvements, supplies or services in Texas at an amount lower than the lowest Texas resident bidder by the
same amount that a Texas resident bidder would be required to underbid a nonresident bidder in order to obtain a
comparable contract in the State which the nonresident's principal place of business is located.
A. Nonresident bidders in the State of , our principal place of business,
are required to be percent lower than resident bidders by State Law. A copy of the
statute is attached.
Nonresident bidders in the State of , our principal place of business,
are not required to underbid resident bidders.
B. The principal place of business of our company or our parent company or majority owner is
in the State of Texas. ❑
BIDDER:
By:
Title:
Date:
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Form Revised 20110627
(Signature)
00 41 00 Bid Proposal Workbook
2
SECTION 00 45 11
BIDDERS PREQUALIFICATIONS
004511-1
BIDDERS PREQUALIFICATIONS
Page 1 of 3
3
4 1. Summary. All contractors are required to be prequalified by the City prior to submitting
5 bids. To be eligible to bid the contractor must submit Section 00 45 12, Prequalification
6 Statement for the work type(s) listed with their Bid. Any contractor or subcontractor who is
7 not prequalified for the work type(s) listed must submit Section 00 45 13, Bidder
8 Prequalification Application in accordance with the requirements below.
9
10 The prequalification process will establish a bid limit based on a technical evaluation and
11 financial analysis of the contractor. The information must be submitted seven (7) days prior
12 to the date of the opening of bids. For example, a contractor wishing to submit bids on
13 projects to be opened on the 7th of April must file the information by the 31 st day of March
14 in order to bid on these projects. In order to expedite and facilitate the approval of a Bidder's
15 Prequalification Application, the following must accompany the submission.
16 a. A complete set of audited or reviewed financial statements.
17 (1) Classified Balance Sheet
18 (2) Income Statement
19 (3) Statement of Cash Flows
20 (4) Statement of Retained Earnings
21 (5) Notes to the Financial Statements, if any
22 b. A certified copy of the firm's organizational documents (Corporate Charter, Articles
23 of Incorporation, Articles of Organization, Certificate of Formation, LLC
24 Regulations, Certificate of Limited Partnership Agreement).
25 c. A completed Bidder Prequalification Application.
26 (1) The firm's Texas Taxpayer Identification Number as issued by the Texas
27 Comptroller of Public Accounts. To obtain a Texas Taxpayer Identification
28 number visit the Texas Comptroller of Public Accounts online at the
29 following web address www.window.state.tx.us/taxpermit/ and fill out the
30 application to apply for your Texas tax ID.
31 (2) The firm's e-mail address and fax number.
32 (3) The firm's DUNS number as issued by Dun & Bradstreet. This number
33 is used by the City for required reporting on Federal Aid projects. The DUNS
34 number may be obtained at www.dnb.com.
35 d. Resumes reflecting the construction experience of the principles of the firm for firms
36 submitting their initial prequalification. These resumes should include the size and
37 scope of the work performed.
38 e. Other information as requested by the City.
39
40 2. Prequalification Requirements
41 a. Financial Statements. Financial statement submission must be provided in
42 accordance with the following:
43 (1) The City requires that the original Financial Statement or a certified copy
44 be submitted for consideration.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project # 1480
1
2
3
4
5
6
7
8
9
00 45 11-3
BIDDERS PREQUALIFICATIONS
Page 3 of 3
d. If a contractor has a valid prequalification letter, the contractor will be eligible to bid
the prequalified work types until the expiration date stated in the letter.
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project # 1480
004512-1
PREQUALIFICATION STATEMENT
Page 1 of 1
1 SECTION 00 45 12
2 PREQUALIFICATION STATEMENT
3 Each Bidder for a City procurement is required to complete the information below by
4 identifying the prequalified contractors and/or subcontractors whom they intend to utilize for the
5 major work type(s) listed.
6
Major Work
Type
Contractor/Subcontractor Company Name
Prequalification
Expiration Date
7
8
9 The undersigned hereby certifies that the contractors and/or subcontractors described in
10 the table above are currently prequalified for the work types listed.
11
12 BIDDER:
13
14 By:
15 Company (Please Print)
16
17 Signature:
18 Address
19
20 Title:
21 City/State/Zip (Please Print)
22
23
24
25
26
Date:
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
FORT WORTH
SECTION 00 45 13
BIDDER PREQUALIFICATION APPLICATION
Date of Balance Sheet
Mark only one:
Q Individual
QLimited Partnership
Name under which you wish to qualify p General Partnership
QCorporation
QLimited Liability Company
Post Office Box City State Zip Code
Street Address (required) City State Zip Code
Telephone
Fax E-mail Address
Area Code Number Area Code Number
Texas Taxpayer Identification No.
Federal Employers Identification No.
DUNS No. (if applicable)
MAIL THIS QUESTIONNAIRE ALONG WITH FINANCIAL STATEMENTS TO:
CITY OF FORT WORTH TEXAS
1000 THROCKMORTON STREET
FORT WORTH, TEXAS 76102-6311
00 45 40-1
MINORITY AND WOMEN BUSINESS ENTERPRISE GOAL
Page 1 of 1
1 SECTION 00 45 40
2 MINORITY BUSINESS ENTERPRISE GOAL
3 APPLICATION OF POLICY
4 If the total dollar value of the contract is greater than $50,000, then the MBE subcontracting goal
5 may be applicable. If the total dollar value of the contract is $50,000 or less, the MBE
6 subcontracting goal is not applicable.
7
8 POLICY STATEMENT
9 It is the policy of the City of Fort Worth to ensure the full and equitable participation by Minority
10 Business Enterprises (MBE) in the procurement of all goods and services. All requirements and
11 regulations stated in the City's current Business Diversity Enterprise Ordinance apply to this bid.
12
13 MBE PROJECT GOAL
14 The City's MBE goal on this project is 13% of the total bid (Base bid applies to Parks and
15 Community Services). Note: If both MBE and SBE subcontracting goals are established for this
16 project, then an Offeror must submit both a MBE Utilization Form and a SBE Utilization Form to be
17 deemed responsive.
18
19 COMPLIANCE TO BID SPECIFICATIONS
20 On City contracts greater than $50,000 where a MBE subcontracting goal is applied, bidders are
21 required to comply with the intent of the City's Business Diversity Ordinance by one of the
22 following:
23 1. Meet or exceed the above stated MBE goal through MBE subcontracting participation, or
24 2. Meet or exceed the above stated MBE goal through MBE Joint Venture participation, or
25 3. Good Faith Effort documentation, or;
26 4. Waiver documentation.
27 Failure to comply with the City's Business Diversity Ordinance shall result in the Bid being
28 considered non -responsive. Any questions, please contact the M/WBE Office at (817) 212-2674.
29
30 SUBMITTAL OF REQUIRED DOCUMENTATION
31 The applicable documents must be received by the Managing Department, within the following
32 times allocated, in order for the entire bid to be considered responsive to the specifications. The
33 Offeror shall deliver the MBE documentation in person to the appropriate employee of the Managing
34 Department and obtain a date/time receipt. Such receipt shall be evidence that the City received the
35 documentation in the timeallocated, A faxed copy will not be accepted.
1. Subcontractor Utilization Form, if goal is met received by 5:00 p.m., five (5) City business days after
or exceeded: the bid opening date, exclusive of the bid opening date.
2. Good Faith Effort and Subcontractor received by 5:00 p.m., five (5) City business days after
Utilization Form, if participation is less than the bid opening date, exclusive of the bid opening date.
stated goal:
3. Good Faith Effort and Subcontractor received by 5:00 p.m., five (5) City business days after
Utilization Form, if no MBE participation: the bid opening date, exclusive of the bid opening date.
4. Prime Contractor Waiver Form, if firm will received by 5:00 p.m., five (5) City business days after
perform all subcontracting/supplier work: the bid opening date, exclusive of the bid opening date.
5. Joint Venture Form, if utilizing a joint venture received by 5:00 p.m., five (5) City business days after
to meet or exceed goal. the bid opening date, exclusive of the bid opening date.
36 END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised September 29, 2012
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
FORT WORT H
PRIME COMPANY NAME:
PROJECT NAME:
City's MBE Project Goal:
%
City of Fort Worth
MBE Good Faith Effort Form
ATTACHMENT 1C
Page 1 of 3
Check applicable block to describe prime
M/W/DBE
NON-M//WDBE
BID DATE
Prime's MBE Project Commitment: PROJECT NUMBER
ova
IIf the Offeror did not meet or exceed the MBE subcontracting goal for this project, the Offeror must complete this
form.
If the Offeror's method of compliance with the MBE goal is based upon demonstration of a
"good faith effort", the Offeror will have the burden of correctly and accurately preparing and
submitting the documentation required by the City. Compliance with each item, 1 thru 11 below,
shall satisfy the Good Faith Effort requirement absent proof of fraud, intentional and/or knowing
misrepresentation of the facts or intentional discrimination by the Offeror.
Failure to complete this form, in its entirety with supporting documentation, and it being submitted to and
received by the Managing Department on or before 5:00 p.m. five (5) City business days after bid opening,
exclusive of bid opening date, will result in the bid being considered non -responsive to bid specifications.
1.) Please list each and every subcontracting and/or supplier opportunity for the completion of this
project, regardless of whether it is to be provided by a MBE or non -MBE. (DO NOT LIST NAMES OF
FIRMS) On all projects, the Offeror must list each subcontracting and or supplier opportunity
regardless of tier.
(Use additional sheets, if necessary)
List of Subcontracting Opportunities List of Supplier Opportunities
Rev. 5/30/12
ATTACHMENT 1C
Page 2 of 3
2.) Obtain a current (not more than two (2) months old from the bid open date) list of MBE subcontractors
and/or suppliers from the City's M/WBE Office or the City's website.
Yes Date of Listing / /
No
3.) Did you solicit bids from MBE firms, within the subcontracting and/or supplier areas previously listed,
at least ten calendar days prior to bid opening by mail, exclusive of the day the bids are opened?
Yes (If yes, attach MBE mail listing to include name of firm and address and a dated copy of letter mailed.)
No
4.) Did you solicit bids from MBE firms, within the subcontracting and/or supplier areas previously listed,
at least ten calendar days prior to bid opening by telephone, exclusive of the day the bids are
opened?
Yes (If yes, attach list to include name of MBE firm, person contacted, phone number and date and time of contact.)
No
5.) Did you solicit bids from MBE firms, within the subcontracting and/or supplier areas previously listed,
at least ten calendar days prior to bid opening by facsimile (fax), exclusive of the day the bids are
opened?
Yes (If yes, attach list to include name of MBE firm, fax number and date and time of contact. In addition, if the fax is
returned as undeliverable, then that "undeliverable confirmation" received must be printed directly from the
facsimile for proper documentation. Failure to submit confirmation and/or "undeliverable confirmation"
documentation may render the GFE non -responsive.)
No
6.) Did you solicit bids from MBE firms, within the subcontracting and/or supplier areas previously listed,
at least ten calendar days prior to bid opening by email, exclusive of the day the bids are opened?
Yes (If yes, attach email confirmation to include name of MBE firm, date and time. in addition, if an email is returned as
undeliverable, then that "undeliverable message" receipt must be printed directly from the email system for proper
documentation. Failure to submit confirmation and/or "undeliverable message" documentation may render the
GFE non- responsive.)
No
NOTE: The four methods identified above are acceptable for soliciting bids, and each selected method
must be applied to the applicable contract. The Offeror must document that either at least two attempts
were made using two of the four methods or that at least one successful contact was made using one of
the four methods in order to be deemed responsive to the Good Faith Effort requirement.
NOTE: The Offeror must contact the entire MBE list specific to each subcontracting and supplier
opportunity to be in compliance with questions 3 through 6.
7.) Did you provide plans and specifications to potential MBEs?
Yes
No
8.) Did you provide the information regarding the location of plans and specifications in order to assist
the MBEs?
Yes
No
Rev. 5/30/12
ATTACHMENT 1C
Page 3 of 3
9.) Did you prepare a quotation for the MBEs to bid on goods/services specific to their skill set?
Yes (If yes, attach all copies of quotations.)
No
10.) Was the contact information on any of the listings not valid?
Yes (If yes, attach the information that was not valid in order for the M/WBE Office to address the corrections
needed.)
No
11.)Submit documentation if MBE quotes were rejected. The documentation submitted should be in the
forms of an affidavit, include a detailed explanation of why the MBE was rejected and any supporting
documentation the Offeror wishes to be considered by the City. In the event of a bona fide dispute
concerning quotes, the Offeror will provide for confidential in -camera access to and inspection of any
relevant documentation by City personnel.
(Please use additional sheets, if necessary, and attach.)
Company Name Telephone Contact Person Scope of Work Reason for Rejection
ADDITIONAL INFORMATION:
Please provide additional information you feel will further explain your good and honest efforts to obtain
MBE participation on this project.
The Offeror further agrees to provide, directly to the City upon request, complete and
accurate information regarding actual work performed on this contract, the payment
thereof and any proposed changes to the original arrangements submitted with this bid.
The Offeror also agrees to allow an audit and/or examination of any books, records and
files held by their company that will substantiate the actual work performed on this
contract, by an authorized officer or employee of the City.
Any intentional and/or knowing misrepresentation of facts will be grounds for
terminating the contract or debarment from City work for a period of not Tess than three
(3) years and for initiating action under Federal, State or Local laws concerning false
statements. Any failure to comply with this ordinance shall create a material breach of
Rev. 5/30/12
ATTACHMENT 1C
Page 4 of 3
contract and may result in a determination of an irresponsible offeror and debarment
from participating in City work for a period of time not Tess than one (1) year.
The undersigned certifies that the information provided and the MBE(s) listed was/were
contacted in good faith. It is understood that any MBE(s) listed in Attachment 1C will be
contacted and the reasons for not using them will be verified by the City's M/WBE
Office.
Authorized Signature Printed Signature
Title Contact Name and Title (if different)
Company Name Phone Number Fax Number
Address Email Address
City/State/Zip Date
Rev. 5/30/12
FORT WORTH
CITY OF FORT WORTH
MBE Joint Venture Eligibility Form
All questions must be answered; use "N/A" if not applicable.
Name of City project:
A joint venture form must be completed on each project
RFP/Bid/Purchasing Number:
1. Joint venture information:
Joint Venture Name:
Joint Venture Address:
(If applicable)
Telephone: Facsimile:
Cellular:
E-mail address:
Joint Venture
Page 1 of 3
Identify the firms that comprise the joint venture:
Please attach extra sheets if additional space is required to provide detailed explanations of work to be performed by each firm comprising the
joint venture
MBE firm Non -MBE firm
name: name:
Business Address: Business Address:
City, State, Zip:
Telephone Facsimile E-mail
Cellular
Certification Status:
Name of Certifying Agency:
2. Scope of work performed by the Joint Venture:
I Describe the scope of work of the MBE:
City, State, Zip:
Telephone
Cellular
E-mail address
Facsimile
Describe the scope of work of the non -MBE:
Rev. 5/30/12
Joint Venture
Page 2 of 3
3. What is the percentage of MBE participation on this joint venture that you wish to be counted toward
meeting the project goal?
4. Attach a copy of the joint venture agreement.
5. List components of ownership of joint venture: (Do not complete if this information is described in joint venture agreement)
Profit and loss sharing:
Capital contributions, including
equipment:
Other applicable ownership interests:
6. Identify by name, race, sex and firm those individuals (with titles) who are responsible for the day-to-day
management and decision making of the joint venture:
Financial decisions
(to include Account Payable and Receivable):
Management decisions:
a. Estimating
b. Marketing and Sales
c. Hiring and Firing of management
personnel
d. Purchasing of major equipment
and/or supplies
Supervision of field operations
The City's Minority and Women Business Enterprise Office will review your joint venture submission and
will have final approval of the MBE percentage applied toward the goal for the project listed on this form.
NOTE:
From and after the date of project award, if any of the participants, the individually defined scopes of work or the dollar
amounts/percentages change from the originally approved information, then the participants must inform the City's
M/WBE Office immediately for approval. Any unjustified change or deletion shall be a material breach of contract and
may result in debarment in accord with the procedures outlined in the City's BDE Ordinance.
Rev. 5/30/12
Joint Venture
Page 3 of 3
AFFIDAVIT
The undersigned affirms that the foregoing statements are true and correct and include all material information
necessary to identify and explain the terms and operation of the joint venture. Furthermore, the undersigned shall
agree to provide to the joint venture the stated scope of work, decision -making responsibilities and payments
herein.
The City also reserves the right to request any additional information deemed necessary to determine if the joint
venture is eligible. Failure to cooperate and/or provide requested information within the time specified is grounds
for termination of the eligibility process.
The undersigned agree to permit audits, interviews with owners and examination of the books, records and files
of the joint venture by any authorized representatives of the City of Fort Worth. Failure to comply with this
provision shall result in the termination of any contract, which may be awarded under the provisions of this joint
venture's eligibility and may initiate action under Federal, State and/or Local laws/ordinances concerning false
statements or willful misrepresentation of facts.
Name of MBE firm Name of non -MBE firm
Printed Name of Owner Printed Name of Owner
Signature of Owner Signature of Owner
Printed Name of Owner Printed Name of Owner
Signature of Owner Signature of Owner
Title Title
Date Date
Notarization
State of County of
On this day of
and
, 20 , before me appeared
to me personally known and who, being duly sworn, did execute the foregoing affidavit and did state that they were
properly authorized to execute this affidavit and did so as their free act and deed.
Notary Public
Print Name
Notary Public
Signature
Commission Expires
(seal)
Rev. 5/30/12
FORT WORTH
PRIME COMPANY NAME:
PROJECT NAME:
City's MBE Project Goal:
%
City of Fort Worth
Prime Contractor Waiver Form
ATTACHMENT 1B
Page 1 of 1
Check applicable block to describe prime
M/W/DBE NON-M//WDBE
BID DATE
Prime's MBE Project Commitment: PROJECT NUMBER
If both answers to this form are YES, do not complete ATTACHMENT 1C (Good Faith Effort Form). All questions on
this form must be completed and a detailed explanation provided, if applicable. If the answer to either question is
NO, then you must complete ATTACHMENT 1 C. This form is only applicable if both answers are yes.
Failure to complete this form in its entirety and be received by the Managing Department on or before
5:00 p.m., five (5) Citv business days after bid opening, exclusive of the bid opening date, will result in the
bid being considered non -responsive to bid specifications.
Will you perform this entire contract without subcontractors?
If yes, please provide a detailed explanation that proves based on the size and scope of this
project, this is your normal business practice and provide an operational profile of your business.
Will you perform this entire contract without suppliers?
If yes, please provide a detailed explanation that proves based on the size and scope of this
project, this is your normal business practice and provide an inventory profile of your business.
YES
NO
YES
NO
The bidder further agrees to provide, directly to the City upon request, complete and accurate information
regarding actual work performed by all subcontractors, including MBE(s) on this contract, the payment therefore
and any proposed changes to the original MBE(s) arrangements submitted with this bid. The bidder also agrees
to allow an audit and/or examination of any books, records and files held by their company that will substantiate
the actual work performed by the MBEs on this contract, by an authorized officer or employee of the City. Any
intentional and/or knowing misrepresentation of facts will be grounds for terminating the contract or debarment
from City work for a period of not less than three (3) years and for initiating action under Federal, State or Local
laws concerning false statements. Any failure to comply with this ordinance creates a material breach of contract
may result in a determination of an irresponsible offeror and barred from participating in City work for a period of
time not less than one (1) year.
Authorized Signature Printed Signature
Title Contact Name (if different)
Company Name Phone Number
Address Email Address
City/State/Zip Date
Fax Number
Rev. 5/30/12
FORT WORTH
City of Fort Worth
Minority Business Enterprise Specifications
SPECIAL INSTRUCTIONS FOR BIDDERS
APPLICATION OF POLICY
If the total dollar value of the contract is greater than $50,000, then a MBE subcontracting goal may be
applicable. If the total dollar value of the contract is $50,000 or less, then an MBE subcontracting goal is not
applicable.
POLICY STATEMENT
It is the policy of the City of Fort Worth to ensure the full and equitable participation by Minority Business Enterprises
(MBE) in the procurement of all goods and services. All requirements and regulations stated in the City's current
Business Diversity Enterprise Ordinance applies to this bid.
The City's MBE goal on this project is
MBE PROJECT GOALS
of the total bid (Base bid applies to Parks and Community Services).
Note: If both MBE and SBE subcontracting goals are established for this project, then an Offeror must
submit both a MBE Utilization Form and a SBE Utilization Form to be deemed responsive.
COMPLIANCE TO BID SPECIFICATIONS
On City contracts greater than $50,000 where a MBE subcontracting goal is applied, bidders are required to comply
with the intent of the City's Business Diversity Enterprise Ordinance by one of the following:
1. Meet or exceed the above stated MBE goal through MBE subcontracting participation, or
2. Meet or exceed the above stated MBE goal through MBE Joint Venture participation, or;
3. Good Faith Effort documentation, or;
4. Waiver documentation.
SUBMITTAL OF REQUIRED DOCUMENTATION
The applicable documents must be received by the Managing Department, within the following times allocated, in order
for the entire bid to be considered responsive to the specifications. The Offeror shall deliver the MBE documentation in
person to the appropriate employee' of the managing department and obtain a date/time receipt. Such receipt shall be
evidence that the City received the documentation in the time allocated. A faxed copy will not be accepted.
1. Subcontractor Utilization Form, if goal is
met or exceeded:
2. Good Faith Effort and Subcontractor
Utilization Form, if participation is less than
stated goal:
3. Good Faith Effort and Subcontractor
Utilization Form, if no MBE participation:
4. Prime Contractor Waiver Form, if you will
perform all subcontracting/supplier work:
5. Joint Venture Form, if utilize a joint venture
to met or exceed goal.
received by 5:00 p.m., five (5) City business days after the bid
opening date, exclusive of the bid opening date.
received by 5:00 p.m., five (5) City business days after the bid
opening date, exclusive of the bid opening date.
received by 5:00 p.m., five (5) City business days after the bid
opening date, exclusive of the bid opening date.
received by 5:00 p.m., five (5) City business days after the bid
opening date, exclusive of the bid opening date.
received by 5:00 p.m., five (5) City business days after the bid
opening date, exclusive of the bid opening date.
I FAILURE TO COMPLY WITH THE CITY'S BUSINESS DIVERSITY ENTERPRISE ORDINANCE, WILL RESULT IN
THE BID BEING CONSIDERED NON -RESPONSIVE TO SPECIFICATIONS
Any questions, please contact the M/WBE Office at (817) 212-2674.
Rev. 5/30/12
ATTACHMENT 1A
Page 1 of 4
FORT WORTH
City of Fort Worth
MBE Subcontractors/Suppliers Utilization Form
PRIME COMPANY NAME: Check applicable block to describe prime
PROJECT NAME:
City's MBE Project Goal:
M/W/DBE
NON-M//WDBE
BID DATE
Prime's MBE Project Commitment: PROJECT NUMBER
OA
Identify all subcontractors/suppliers you will use on this project
Failure to complete this form, in its entirety with requested documentation, and received by the Managing
Department on or before 5:00 p.m. five (5) City business days after bid opening, exclusive of bid opening date,
will result in the bid being considered non -responsive to bid specifications.
The undersigned Offeror agrees to enter into a formal agreement with the MBE firm(s) listed in this utilization
schedule, conditioned upon execution of a contract with the City of Fort Worth. The intentional and/or knowing
misrepresentation of facts is grounds for consideration of disqualification and will result in the bid being
considered non -responsive to bid specifications
MBEs listed toward meeting the project goal must be located in the six (6) county marketplace at the time of
bid. Marketplace is the geographic area of Tarrant, Dallas. Denton. Johnson. Parker. and Wise counties.
Identify each Tier level. Tier is the level of subcontracting below the prime contractor, i.e., a direct
payment from the prime contractor to a subcontractor is considered 1st tier, a payment by a subcontractor to
its supplier is considered 2nd tier
ALL MBEs MUST BE CERTIFIED BEFORE CONTRACT AWARD.
Certification means those firms, located within the Marketplace, that have been determined to be a bondafide minority
business enterprise by the North Central Texas Regional Certification Agency (NCTRCA) or other certifying agencies
that the City may deem appropriate and accepted by the City of Fort Worth.
If hauling services are utilized, the prime will be given credit as long as the MBE listed owns and operates
at least one fully licensed and operational truck to be used on the contract. The MBE may lease trucks from
another MBE firm, including MBE owner -operators, and receive full MBE credit. The MBE may lease trucks
from non -MBEs, including owner -operators, but will only receive credit for the fees and commissions earned
by the MBE as outlined in the lease agreement.
Rev. 5/30/12
FORT WORTH
ATTACHMENT 1A
Page 2 of 4
Primes are required to identify ALL subcontractors/suppliers, regardless of status; i.e., Minority and non -MBEs.
MBE firms are to be listed first, use additional sheets if necessary. If a subcontractor/supplier is identified as an SBE, please attach a
copy of the firm's SBE certification if they have not previously registered with the City's M/WBE Office, which may be contacted for
verification. Please note that only certified MBEs will be counted to meet an MBE goal.
Attach
NCTRCA Certificate
SUBCONTRACTOR/SUPPLIER
Company Name
Address
Telephone/Fax
T
e
M
B
E
Detail Detail
Subcontracting Supplies
W S M Work Purchased
B B B
E E E
Dollar Amount
Rev. 5/30/12
FORT WORTH
ATTACHMENT 1A
Page 3 of 4
Primes are required to identify ALL subcontractors/suppliers, regardless of status; i.e., Minority and non -MBEs.
Please list MBE firm's first, use additional sheets if necessary. If a subcontractor/supplier is identified as an SBE, please attach a copy
of the firms SBE certification if they have not previously registered with the City's M/WBE Office which may be contacted for
verification. Please note that only certified MBEs will be counted to meet an MBE goal.
SUBCONTRACTOR/SUPPLIER
Company Name
Address
Telephone/Fax
NCTRCA
T,
e
r B
E
W
B
E
Attach N
Certificate °
Detail
Subcontracting
S M Work
B B
E E
Detail
Supplies
Purchased
Dollar Amount
Rev. 5/30/12
ATTACHMENT 1A
Page 4 of 4
FORT WORTH
Total Dollar Amount of MBE Subcontractors/Suppliers
Total Dollar Amount of Non -MBE Subcontractors/Suppliers
$
$
TOTAL DOLLAR AMOUNT OF ALL SUBCONTRACTORS/SUPPLIERS $
The Contractor will not make additions, deletions, or substitutions to this certified list without the prior approval
of the Minority and Women Business Enterprise Office through the submittal of a Request for Approval of
Change/Addition form. Any unjustified change or deletion shall be a material breach of contract and may
result in debarment in accord with the procedures outlined in the ordinance. The contractor shall submit a
detailed explanation of how the requested change/addition or deletion will affect the committed MBE goal. If the
detail explanation is not submitted, it will affect the final compliance determination.
By affixing a signature to this form, the Offeror further agrees to provide, directly to the City upon request,
complete and accurate information regarding actual work performed by all subcontractors, including MBE(s)
and any special arrangements with MBEs. The Offeror also agrees to allow an audit and/or examination of
any books, records and files held by their company. The bidder agrees to allow the transmission of interviews
with owners, principals, officers, employees and applicable subcontractors/suppliers participating on the
contract that will substantiate the actual work performed by the MBE(s) on this contract, by an authorized
officer or employee of the City. Any intentional and/or knowing misrepresentation of facts will be grounds for
terminating the contract or debarment from City work for a period of not less than three (3) years and for
initiating action under Federal, State or Local laws concerning false statements. Any failure to comply with this
ordinance creates a material breach of the contract and may result in a determination of an irresponsible
Offeror and debarment from participating in City work for a period of time not less than one (1) year.
Authorized Signature Printed Signature
Title Contact Name/Title (if different)
Company Name Telephone and/or Fax
Address E-mail Address
City/State/Zip Date
Rev. 5/30/12
005243-1
Agreement
Page 1 of 4
1 SECTION 00 52 43
2 AGREEMENT
3 THIS AGREEMENT, authorized on ��/vALf is made by and between the City of Forth
4 Worth, a Texas home rule municipality, acting by and through its duly authorized City Manager,
5 ("City"), and ✓K r4 CO Ic7i4s Se'' rs , G. L. C.
6 authorized to do business in Texas, acting by and through its duly authorized representative,
7 ("Contractor").
8 City and Contractor, in consideration of the mutual covenants hereinafter set forth, agree as
9 follows:
10 Article 1. WORK
11 Contractor shall complete all Work as specified or indicated in the Contract Documents for the
12 Project identified herein.
13 Article 2. PROJECT
14 The project for which the Work under the Contract Documents may be the whole or only a part is
15 generally described as follows:
16 Sanitary Sewer Rehab Contract 75, Part 1
17 CFW Project #1480. Water Project #P253-609170148083. Sewer Project #P258-709170148083
18 Article 3. CONTRACT TIME
19 3.1 Time is of the essence.
20 All time limits for Milestones, if any, and Final Acceptance as stated in the Contract
21 Documents are of the essence to this Contract.
22 3.2 Final Acceptance.
23 The Work will be complete for Final Acceptance within 180 days after the date when the
24 Contract Time commences to run as provided in Paragraph 2.03 of the General Conditions.
25 3.3 Liquidated damages
26 Contractor recognizes that time is of the essence of this Agreement and that City will
27 suffer financial loss if the Work is not completed within the times specified in Paragraph
28 3.2 above, plus any extension thereof allowed in accordance with Article 12 of the
29 General Conditions. The Contractor also recognizes the delays, expense and difficulties
30 involved in proving in a legal proceeding the actual loss suffered by the City if the Work
31 is not completed on time. Accordingly, instead of requiring any such proof , Contractor
32 agrees that as liquidated damages for delay (but not as a penalty), Contractor shall pay
33 City Five Hundred Dollars ($500.00) for each day that expires after the time specified in
34 Paragraph 3.2 for Final Acceptance until the City issues the Final Letter of Acceptance.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised August 17, 2012
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
00 52 43 - 2
Agreement
Page 2 of 4
35 Article 4. CONTRACT PRICE
36 City agrees to pay Contractor for performance of the Work in accordance with the Contract
37 Documents an amount in current funds of TU,o &;11 0,4 iev144) t 4194.41 Dollars
38 ($Z, a , 4/4/1/.). Vow It.chne i 4 P °ADo
39 Article 5. CONTRACT DOCUMENTS
40 5.1 CONTENTS:
41 A. The Contract Documents which comprise the entire agreement between City and
42 Contractor concerning the Work consist of the following:
43 1. This Agreement.
44 2. Attachments to this Agreement:
45 a. Bid Form
46 1) Proposal Form
47 2) Vendor Compliance to State Law Non -Resident Bidder
48 3) Prequalification Statement
49 4) State and Federal documents (project specific)
50 b. Current Prevailing Wage Rate Table
51 c. Insurance ACORD Form(s)
52 d. Payment Bond
53 e. Performance Bond
54 f. Maintenance Bond
55 g. Power of Attorney for the Bonds
56 h. Worker's Compensation Affidavit
57 i. MBE and/or SBE Commitment Form
58 3. General Conditions.
59 4. Supplementary Conditions.
60 5. Specifications specifically made a part of the Contract Documents by attachment
61 or, if not attached, as incorporated by reference and described in the Table of
62 Contents of the Project's Contract Documents.
63 6. Drawings.
64 7. Addenda.
65 8. Documentation submitted by Contractor prior to Notice of Award.
66 9. The following which may be delivered or issued after the Effective Date of the
67 Agreement and, if issued, become an incorporated part of the Contract Documents:
68 a. Notice to Proceed.
69 b. Field Orders.
70 c. Change Orders.
71 d. Letter of Final Acceptance.
72
73
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised August 17, 2012
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project # 1480
00 52 43 - 3
Agreement
Page 3 of 4
74 Article 6. INDEMNIFICATION
75 6.1 Contractor covenants and agrees to indemnify, hold harmless and defend, at its own
76 expense, the city, its officers, servants and employees, from and against any and all
77 claims arising out of, or alleged to arise out of, the work and services to be performed
78 by the contractor, its officers, agents, employees, subcontractors, licenses or invitees
79 under this contract. This indemnification provision is specifically intended to operate
80 and be effective even if it is alleged or proven that all or some of the damages being
81 sought were caused, in whole or in part, by any act, omission or negligence of the city.
82 This indemnity provision is intended to include, without limitation, indemnity for
83 costs, expenses and legal fees incurred by the city in defending against such claims and
84 causes of actions.
85
86 6.2 Contractor covenants and agrees to indemnify and hold harmless, at its own expense,
87 the city, its officers, servants and employees, from and against any and all loss, damage
88 or destruction of property of the city, arising out of, or alleged to arise out of, the work
89 and services to be performed by the contractor, its officers, agents, employees,
90 subcontractors, licensees or invitees under this contract. This indemnification
91 provision is +specifically intended to operate and be effective even if it is alleged or
92 proven that all or some of the damages being sought were caused. in whole or in part,
93 by anv act, omission or negligence of the city.
94
95 Article 7. MISCELLANEOUS
96 7.1 Terms.
97 Terms used in this Agreement which are defined in Article 1 of the General Conditions will
98 have the meanings indicated in the General Conditions.
99 7.2 Assignment of Contract.
100 This Agreement, including all of the Contract Documents may not be assigned by the
101 Contractor without the advanced express written consent of the City.
102 7.3 Successors and Assigns.
103 City and Contractor each binds itself, its partners, successors, assigns and legal
104 representatives to the other party hereto, in respect to all covenants, agreements and
105 obligations contained in the Contract Documents.
106 7.4 Severability.
107 Any provision or part of the Contract Documents held to be unconstitutional, void or
108 unenforceable by a court of competent jurisdiction shall be deemed stricken, and all
109 remaining provisions shall continue to be valid and binding upon CITY and
110 CONTRACTOR.
111 7.5 Governing Law and Venue.
112 This Agreement, including all of the Contract Documents is performable in the State of
113 Texas. Venue shall be Tarrant County, Texas, or the United States District Court for the
114 Northern District of Texas, Fort Worth Division.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised August 17, 2012
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project # 1480
005243-4
Agreement
Page 4 of4
115 7.6 Other Provisions.
116 The Contractor agrees to pay at least minimum wage per hour for all labor as the same is
117 classified, promulgated and set out by the City, a copy of which is attached hereto and
118 made a part hereof the same as if it were copied verbatim herein.
119 7.7 Authority to Sign.
Contractor shall attach evidence of authority to sign Agreement, if other than duly
authorized signatory of the Contractor.
120
121
122
123 IN WITNESS WHEREOF, City and Contractor have executed this Agreement in multiple
124 counterparts.
125
126 This Agreement is effective as of the last date signed by the Parties ("Effective Date").
127
128
129
130
131
132
133
134
135
136
137
Title:
Address:
City of Fort Worth
StliceSta)
By:
Fernando Costa
Assistant City Manager
Date /brit)
Attest: fr-vtA- I. `¢
(Printed Name) /0-City Sekretary
. (Seal)
LIM S .I)1(/Il� Priu�I c.
City/State/Zip: AP me,AO e , l X goo ppro -d as to Form and Lega
Dou! s W Black
Date
OFFICIAL RECORD
CITY SECRETARY
Ft WORTH, TX
Assistant City Attorney
APPROVAL RECOMMEND
Awirti
S. Frank Crumb
DIRECTOR,
Water Department
D:
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised August 17, 2012
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
Bond #PRF09147022
1
2
3
4 THE STATE OF TEXAS
5
6 COUNTY OF TARRANT
006113-1
PERFORMANCE BOND
Page 1 of2
SECTION 00 61 13
PERFORMANCE BOND
KNOW ALL BY THESE PRESENTS:
7 That we, Ark Contracting Services, L.L.C. , known as
colonial American casualty anti surety company and
8 "Principal" herein and Fidelity and Deposit Company of Maryland, a corporate
9 surety(sureties, if more than one) duly authorized to do business in the State of Texas, known as
10 "Surety" herein (whether one or more), are held and firmly bound unto the City of Fort Worth, a
11 municipal corporation created pursuant to the laws of Texas, known as "City" herein, in the penal
Two million Seventy Three Thousand
12 sum of, Four Hundred Forty Four and no/100 Dollars
13 ($. 2,073,444.00 ), lawful money of the United States, to be paid in Fort Worth,
14 Tarrant County, Texas for the payment of which sum well and truly to be made, we bind
15 ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally,
16 firmly by these presents.
17 WHEREAS, the Principal has entered into a certain written contract with the City
18 awarded the V f4 day of /?' r l ti . 20✓Y, which Contract is hereby referred to and
19 made a part hereof for all purposes as if fully set forth herein, to furnish all materials, equipment
20 labor and other accessories defined by law, in the prosecution of the Work, including any Change
21 Orders, as provided for in said Contract designated as 2010 Sanitary Sewer Rehab Contract 75,
22 Part 1, City Project #1480.
23 NOW, THEREFORE, the condition of this obligation is such that if the said Principal
24 shall faithfully perform it obligations under the Contract and shall in all respects duly and
25 faithfully perform the Work, including Change Orders, under the Contract, according to the plans,
26 specifications, and contract documents therein referred to, and as well during any period of
27 extension of the Contract that may be granted on the part of the City, then this obligation shall be
28 and become null and void, otherwise to remain in full force and effect.
29 PROVIDED FURTHER, that if any legal action be filed on this Bond, venue shall lie in
30 Tarrant County, Texas or the United States District Court for the Northern District of Texas, Fort
31 Worth Division.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project # 1480
00 61 13 - 2
PERFORMANCE BOND
Page 2 of 2
1 This bond is made and executed in compliance with the provisions of Chapter 2253 of the
2 Texas Government Code, as amended, and all liabilities on this bond shall be determined in
3 accordance with the provisions of said statue.
4 IN WITNESS WHEREOF, the Principal and the Surety haveSIGNEDand SEALED
/
5 this instrument by duly authorized agents and officers on this the i f 2 day of
6 iffy / (L, , 20 /V.
7
8
9
10
11
12
13
14
15
16 (Tine pal) 'L etary
17
18
19
20
21
22 Witness as to Principal
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37 Witness as to Su
38
39
40
41
42
43
44
45
PRINCIPAL:
Ark Contrapt%ing Se ices, L.L.C.
BY:
ature /
Vrn f,.T:o0fran��eS
Name and Title
Address: 420 S Dick Price Road
Kennedale. TX 76060
SURETY:
Colonial American Casualty and Surety Conlpan
and Fidelity and Depe,Rit Company of Maryland
Signatur
Tracy Tucker, Attorney —in —Fact
Name and Title
Address: 900 Summit Ave
Fort Worth, TX 76102
Telephone Number: 817 / 3 3 6-8 5 20
*Note: If signed by an officer of the Surety Company, there must be on file a certified extract
from the by-laws showing that this person has authority to sign such obligation. If
Surety's physical address is different from its mailing address, both must be provided.
The date of the bond shall not be prior to the date the Contract is awarded.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
e r
Bond #PRF09147022
2
3
4 THE STATE OF TEXAS
5
6 COUNTY OF TARRANT
7
8
9
10
11
12
13
14
15
16
That we,
Ark
"Principal" herein, and
00 61 14 - 1
PAYMENT BOND
Page 1 of 2
SECTION 00 61 14
PAYMENT BOND
KNOW ALL BY THESE PRESENTS:
Contracting Services, L.L.C. known
uoioniai American uasuaity anti surety company and
Fidelity and Deposit Company of Maryland
corporate surety (sureties), duly authorized to do business in the State of Texas, known
as
,a
as
"Surety" herein (whether one or more), are held and firmly bound unto the City of Fort Worth, a
municipal corporation created pursuant to the laws of the State of Texas, known as "City" herein,
Two Million Seventy Three Thousand
in the penal sum of Four Hundred Forty Four and no/100 Dollars
($ 2,073,444.00 ), lawful money of the United States, to be paid in Fort Worth,
Tarrant County, Texas, for the payment of which sum well and truly be made, we bind ourselves,
our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these
presents:
17 WHEREAS, Principal has entered into a certain written Contract with City, awarded the
18 day of /M (, 20 1/, which Contract is hereby referred to and
19 made a part hereof for all purposes as if fully set forth herein, to furnish all materials, equipment,
20 labor and other accessories as defined by law, in the prosecution of the Work as provided for in
21 said Contract and designated as 2010 Sanitary Sewer Rehab Contract 75, Part 1, City Project
22 #1480.
23 NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that if
24 Principal shall pay all monies owing to any (and all) payment bond beneficiary (as defined in
25 Chapter 2253 of the Texas Government Code, as amended) in the prosecution of the Work under
26 the Contract, then this obligation shall be and become null and void; otherwise to remain in full
27 force and effect.
28 This bond is made and executed in compliance with the provisions of Chapter 2253 of the
29 Texas Government Code, as amended, and all liabilities on this bond shall be determined in
30 accordance with the provisions of said statute.
31
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
00 61 14 - 2
PAYMENT BOND
Page 2 of 2
1 IN WITNESS WHEREOF, the Principal and Surety have each SIGNED and SEALED
2 this instrument by duly authorized agents and officers on this the «/4 day of
3 1/11 (r/ 0-1 .20 7 Y.
4
ATTEST:
(Principal) 'j cretary
/..
Witness as to Principal
ATTEST:
(Surety) Secretary
&‘k‘ G)-3-3L—
Witness as to Sty
PRINCIPAL:
Ark Contra ing Ser es, L.L.C.
BY:
12nagan7Ce5;a eaE
Name and Title
Address: 420 S Dick
Kennedale,
Price Road
TX 76060
SURETY:
Colonial American Casualty and Surety Company
Fidelity and Deposit Company of Maryland
Tracy Tucker, Attornev-in-Fact
Name and Title
Address: 900 Summit Ave
Fort Worth, TX 76102
Telephone Number: 817/336-8520
5
6 Note: If signed by an officer of the Surety, there must be on file a certified extract from the
7 bylaws showing that this person has authority to sign such obligation. If Surety's physical
8 address is different from its mailing address, both must be provided.
9
10 The date of the bond shall not be prior to the date the Contract is awarded.
11 END OF SECTION
12
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project 111480
PRF09147022
2
SECTION 00 61 19
MAINTENANCE BOND
00 61 19-)
MAINTENANCE BOND
Page 1 of3
4 THE STATE OF TEXAS §
5 § KNOW ALL BY THESE PRESENTS:
6 COUNTY OF TARRANT §
7
8 That we Ark Contracting Services, L.L.C. _, known as
Colonial American Casualty and Surety Company and
9 "Principal" herein and FiriP1 i ry and Dapndi t Company of Maryi anda corporate surety
10 (sureties, if more than one) duly authorized to do business in the State of Texas, known as
11 "Surety" herein (whether one or more), are held and firmly bound unto the City of Fort Worth, a
12 municipal corporation created pursuant to the laws of the State of Texas, known as "City" herein,
Two Million Seventy Three Thousand
13 in the sum of Four Hundred Forty Four and no/100 Dollars
14 ($. 2, 073, 444.00 , lawful money of the United States, to be paid in Fort Worth,
15 Tarrant County, Texas, for payment of which sum well and truly be made unto the City and its
16 successors, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly
17 and severally, firmly by these presents.
18
19 WHEREAS, the Principal has entered into a certain written contract with the City awarded
20 the 1' " day of kl4414 G-- , 20 (y , which Contract is hereby
21 referred to and a made part hereof for all purposes as if fully set forth herein, to furnish all
22 materials, equipment labor and other accessories as defined by law, in the prosecution of the
23 Work, including any Work resulting from a duly authorized Change Order (collectively herein,
24 the "Work") as provided for in said contract and designated as 2010 Sanitary Sewer Rehab
25 Contract 75, Part I, City Project # 1480; and
26
27 WHEREAS, Principal binds itself to use such materials and to so construct the Work in
28 accordance with the plans, specifications and Contract Documents that the Work is and will
29 remain free from defects in materials or workmanship for and during the period of two (2) years
30 after the date of Final Acceptance of the Work by the City ("Maintenance Period"); and
31
32 WHEREAS, Principal binds itself to repair or reconstruct the Work in whole or in part
33 upon receiving notice from the City of the need therefor at any time within the Maintenance
34 Period.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part I
CFW Project H 1480
1
1
PRF09147022
2
3
4 THE STA E OF TEXAS
5
6 COUNTY OF ' ARRANT
7
00 61 19 - 1
MAINTENANCE BOND
Page 1 of 3
SECTION 00 61 19
MAINTENANCE BOND
KNOW ALL BY THESE PRESENTS:
8 That we Ar Contracting Services, L.L.C. , known as
Colonial American Casualty and Surety Company an
9 "Principal" herein and F; P1 ; ty and Dppnsi t Company of Mavyi anda corpora , surety
10 (sureties, if more than on duly authorized to do business in the State of Texas, kno as
11 "Surety" herein (whether o - or more), are held and firmly bound unto the City o ort Worth, a
12 municipal corporation created eursuant to the laws of the State of Texas, kno as "City" herein,
Two Million eventy Three Thousand
13 in the sum of Four Hundred ortv Four and no / 100 Dollars
14 ($ 2, 073 , 400.00 , la ful money of the United States, to .e paid in Fort Worth,
15 Tarrant County, Texas, for payment o which sum well and truly be ade unto the City and its
16 successors, we bind ourselves, our heirs, xecutors, administrate s, successors and assigns, jointly
17 and severally, firmly by these presents.
18
19 WHEREAS, the Principal has entered int. a ce ain written contract with the City awarded
20 the 17111 day of 14'1 `1 / C h , 20 which Contract is hereby
21 referred to and a made part hereof for all purpe.es as 'f fully set forth herein, to furnish all
22 materials, equipment labor and other acces •ries as de ed by law, in the prosecution of the
23 Work, including any Work resulting fro • a duly authoriz- • Change Order (collectively herein,
24 the "Work") as provided for in said ntract and designated :s 2010 Sanitary Sewer Rehab
25 Contract 75, Part 1, City Project ; 480; and
26
27 WHEREAS, Pri ipal binds itself to use such materials anto so construct the Work in
28 accordance with the p : ns, specifications and Contract Documents tha the Work is and will
29 remain free from • fects in materials or workmanship for and during the period of two (2) years
30 after the date o inal Acceptance of the Work by the City ("Maintenance P iod"); and
31
32
33 upor receiving notice from the City of the need therefor at any time within the Maint-nance
34 Period.
W.' EREAS, Principal binds itself to repair or reconstruct the Work in who
or in part
CITY OF FORT WORTH Sanitary Sewer Rehab contract 75, Part 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS CF Project 111480
Revised July 1, 2011
0061 19-2
MAINTENANCE BOND
Page 2 of 3
1
2 NOW THEREFORE, the condition of this obligation is such that if Principal shall
3 remedy any defective Work, for which timely notice was provided by City, to a completion
4 satisfactory to the City, then this obligation shall become null and void; otherwise to remain in
5 full force and effect.
6
7 PROVIDED, HOWEVER, if Principal shall fail so to repair or reconstruct any timely
8 noticed defective Work, it is agreed that the City may cause any and all such defective Work to
9 be repaired and/or reconstructed with all associated costs thereof being borne by the Principal and
10 the Surety under this Maintenance bond; and
11
12 PROVIDED FURTHER, that if any legal action be filed on this Bond, venue shall lie in
13 Tarrant County, Texas or the United States District Court for the Northern District of Texas, Fort
14 Worth Division; and
15
16 PROVIDED FURTHER, that this obligation shall be continuous in nature and
17 successive recoveries may be had hereon for successive breaches.
18
19
20
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project 41480
Li
L�
0061 19-3
MAINTENANCE BOND
Page 3 of 3
1 IN WITNESS WHEREOF, the Principal and the Surety have each SIGNED and SEALED this
2 instrument by duly authorized agents and officers on this the Y i day of ill/ s C 6/
3 , 20 / y.
4
5
6
7
8
9
10
11
A r ST:
12 t ,
13
14 (Pr' • 'pal) C • cretary
15
16
17
18
19
20 Witness as to Principal
21
22
23
24
25
26
27
28
29 ATTEST:
30
31
32 (Surety) Secretary
33
34
35 Witness as to Sety
36
PRINCIPAL:
Ark Contrs tang ,,cervices.
BY:
Address:
griature
(A) mon Presiciert
Name and Title
420 S Dick Price Road
Kennedale, TX 76060
SURETY:
Colonial American Casualty and Surety Company
and Fidelity and Deposit Company of Maryland
Signs
Tracy Tucker, Attornev—in—Far_t_
Name and Title
Address:
900 Summit Avenue
Fort Worth, TX 76119
Telephone Number: 817 / 3 3 6-85 20
37 *Note: If signed by an officer of the Surety Company, there must be on file a certified extract
38 from the by-laws showing that this person has authority to sign such obligation. If
39 Surety's physical address is different from its mailing address, both must be provided.
40 The date of the bond shall not be prior to the date the Contract is awarded.
41
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
ZURICH AMERICAN INSURANCE COMPANY
COLONIAL AMERICAN CASUALTY AND SURETY COMPANY
FIDELITY AND DEPOSIT COMPANY OF MARYLAND
POWER OF ATTORNEY
KNOW ALL MEN BY THESE PRESENTS: That the ZURICH AMERICAN INSURANCE COMPANY, a corporation of the State of New
York, the COLONIAL AMERICAN CASUALTY AND SURETY COMPANY, a corporation of the State of Maryland, and the FIDELITY
AND DEPOSIT COMPANY OF MARYLAND a corporation of the State of Maryland (herein collectively called the "Companies"), by
GEOFFREY DELISIO, Vice President, in pursuance of authority granted by Article V, Section 8, of the By -Laws of said Companies,
which are set forth on the reverse side hereof and are hereby certified to be in full force and effect on the date hereof, do hereby nominate,
constitute, and appoint Tracy TUCKER, W. Lawrence BROWN, Kevin J. DUNN and Steven TUCKER, all of Ft. Worth, Texas,
EACH its true and lawful agent and Attorney -in -Fact, to make, execute, seal and deliver, for, and on its behalf as surety, and as its act and
deed: any and all bonds and undertakings, EXCEPT bonds on behalf of Independent Executors, Community Survivors and
Community Guardians. and the execution of such bonds or undertakings in pursuance of these presents, shall be as binding upon said
Companies, as fully and amply, to all intents and purposes, as if they had been duly executed and acknowledged by the regularly elected
officers of the ZURICH AMERICAN INSURANCE COMPANY at its office in New York, New York., the regularly elected officers of the
COLONIAL AMERICAN CASUALTY AND SURETY COMPANY at its office in Owings Mills, Maryland., and the regularly elected
officers of the FIDELITY AND DEPOSIT COMPANY OF MARYLAND at its office in Owings Mills, Maryland., in their own proper
persons.
The said Vice President does hereby certify that the extract set forth on the reverse side hereof is a true copy of Article V, Section 8, of
the By -Laws of said Companies, and is now in force.
IN WITNESS WHEREOF, the said Vice -President has hereunto subscribed his/her names and affixed the Corporate Seals of the said
ZURICH AMERICAN INSURANCE COMPANY, COLONIAL AMERICAN CASUALTY AND SURETY COMPANY, and
FIDELITY AND DEPOSIT COMPANY OF MARYLAND, this 6th day of December, A.D. 2012.
ATTEST:
BY
Assistant Secretary
Gerald F. Haley
ZURICH AMERICAN INSURANCE COMPANY
COLONIAL AMERICAN CASUALTY AND SURETY COMPANY
FIDELITY AND DEPOSIT COMPANY OF MARYLAND
Vice President
Geoffrey Delisio
State of Maryland
City of Baltimore
On this 6th day of December, A.D. 2012, before the subscriber, a Notary Public of the State of Maryland, duly commissioned and qualified,
GEOFFREY DELISIO, Vice President, and GERALD F. HALEY, Assistant Secretary, of the Companies, to me personally known to be the individuals
and officers described in and who executed the preceding instrument, and acknowledged the execution of same, and being by me duly sworn, deposeth and
saith, that he/she is the said officer of the Company aforesaid, and that the seals affixed to the preceding instrument are the Corporate Seals of said Companies,
and that the said Corporate Seals and the signature as such officer were duly affixed and subscribed to the said instrument by the authority and direction of the
said Corporations.
IN TESTIMONY WHEREOF, I have hereunto set my hand and affixed my Official Seal the day and year first above written.
Constance A. Dunn, Notary Public
My Commission Expires: July 14, 2015
POA-F 168-2829B
EXTRACT FROM BY-LAWS OF THE COMPANIES
"Article V, Section 8, Attornevs-in-Fact. The Chief Executive Officer, the President, or any Executive Vice President or Vice President
may, by written instrument under the attested corporate seal, appoint attorneys -in -fact with authority to execute bonds, policies,
recognizances, stipulations, undertakings, or other like instruments on behalf of the Company, and may authorize any officer or any such
attorney -in -fact to affix the corporate seal thereto; and may with or without cause modify of revoke any such appointment or authority at any
time."
CERTIFICATE
I, the undersigned, Vice President of the ZURICH AMERICAN INSURANCE COMPANY, the COLONIAL AMERICAN
CASUALTY AND SURETY COMPANY, and the FIDELITY AND DEPOSIT COMPANY OF MARYLAND, do hereby certify that the
foregoing Power of Attorney is still in full force and effect on the date of this certificate; and I do further certify that Article V, Section 8, of
the By -Laws of the Companies is still in force.
This Power of Attorney and Certificate may be signed by facsimile under and by authority of the following resolution of the Board of
Directors of the ZURICH AMERICAN INSURANCE COMPANY at a meeting duly called and held on the 15th day of December 1998.
RESOLVED: "That the signature of the President or a Vice President and the attesting signature of a Secretary or an Assistant Secretary
and the Seal of the Company may be affixed by facsimile on any Power of Attorney...Any such Power or any certificate thereof bearing such
facsimile signature and seal shall be valid and binding on the Company."
This Power of Attorney and Certificate may be signed by facsimile under and by authority of the following resolution of the Board of
Directors of the COLONIAL AMERICAN CASUALTY AND SURETY COMPANY at a meeting duly called and held on the 5th day of
May, 1994, and the following resolution of the Board of Directors of the FIDELITY AND DEPOSIT COMPANY OF MARYLAND at a
meeting duly called and held on the loth day of May, 1990.
RESOLVED: "That the facsimile or mechanically reproduced seal of the company and facsimile or mechanically reproduced signature
of any Vice -President, Secretary, or Assistant Secretary of the Company, whether made heretofore or hereafter, wherever appearing upon a
certified copy of any power of attorney issued by the Company, shall be valid and binding upon the Company with the same force and effect
as though manually affixed.
IN TESTIMONY WHEREOF, I have heFreunto subscribed my name and affixed the corporate seals of the said Companies,
this ((rit\ day of !VI ✓' i ,20/
James M. Carroll, Vice President
Fidelity and Deposit Companies
Home Office: 3910 Keswick Road Baltimore, MD 21211
IMPORTANT NOTICE
To obtain information or make a complaint:
You may call the Fidelity and Deposit Company of Maryland, Colonial American Casualty and
Surety Company, and/or Zurich American Insurance Company's toll -free telephone number for
information or to make a complaint at:
1-800-654-5155
You may contact the Texas Department of Insurance to obtain information on companies,
coverages, rights, or complaints at:
1-800-252-3439
You may write the Texas Department of Insurance:
P.O. Box 149104
Austin, TX 78714-9104
FAX # (512) 475-1771
PREMIUM OR CLAIM DISPUTES: Should you have a dispute concerning the premium or
about a claim, you should first contact Fidelity and Deposit Company of Maryland or Colonial
American Casualty and Surety Company. If the dispute is not resolved, you may contact the Texas
Department of Insurance.
ATTACH THIS NOTICE TO YOUR POLICY: This notice is for information only and does
not become a part or condition of the attached document.
S8543f(TX) (08/01)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
SECTION 00 61 25
CERTIFICATE OF INSURANCE
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
006125-1
CERTIFICATE OF INSURANCE
Page 1 of 1
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project 41480
STANDARD GENERAL CONDITIONS
OF THE CONSTRUCTION CONTRACT
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
STANDARD GENERAL CONDITIONS OF THE
CONSTRUCTION CONTRACT
TABLE OF CONTENTS
Page
Article 1 — Definitions and Terminology 1
1.01 Defined Terms 1
1.02 Terminology 6
Article 2 — Preliminary Matters 7
2.01 Copies of Documents 7
2.02 Commencement of Contract Time; Notice to Proceed 7
2.03 Starting the Work 8
2.04 Before Starting Construction 8
2.05 Preconstruction Conference 8
2.06 Public Meeting 8
2.07 Initial Acceptance of Schedules 8
Article 3 — Contract Documents: Intent, Amending, Reuse 8
3.01 Intent 8
3.02 Reference Standards 9
3.03 Reporting and Resolving Discrepancies 9
3.04 Amending and Supplementing Contract Documents 10
3.05 Reuse of Documents 10
3.06 Electronic Data 11
Article 4 — Availability of Lands; Subsurface and Physical Conditions; Hazardous Environmental
Conditions; Reference Points 11
4.01 Availability of Lands 11
4.02 Subsurface and Physical Conditions 12
4.03 Differing Subsurface or Physical Conditions 12
4.04 Underground Facilities 13
4.05 Reference Points 14
4.06 Hazardous Environmental Condition at Site 14
Article 5 — Bonds and Insurance 16
5.01 Licensed Sureties and Insurers 16
5.02 Performance, Payment, and Maintenance Bonds 16
5.03 Certificates of Insurance 16
5.04 Contractor's Insurance 18
5.05 Acceptance of Bonds and Insurance; Option to Replace 19
Article 6 — Contractor's Responsibilities 19
6.01 Supervision and Superintendence 19
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
6.02 Labor; Working Hours 20
6.03 Services, Materials, and Equipment 20
6.04 Project Schedule 21
6.05 Substitutes and "Or -Equals" 21
6.06 Concerning Subcontractors, Suppliers, and Others 24
6.07 Wage Rates 25
6.08 Patent Fees and Royalties 26
6.09 Permits and Utilities 27
6.10 Laws and Regulations 27
6.11 Taxes 28
6.12 Use of Site and Other Areas 28
6.13 Record Documents 29
6.14 Safety and Protection 29
6.15 Safety Representative 30
6.16 Hazard Communication Programs 30
6.17 Emergencies and/or Rectification 30
6.18 Submittals 31
6.19 Continuing the Work 32
6.20 Contractor's General Warranty and Guarantee 32
6.21 Indemnification 33
6.22 Delegation of Professional Design Services 34
6.23 Right to Audit 34
6.24 Nondiscrimination 35
Article 7 - Other Work at the Site 35
7.01 Related Work at Site 35
7.02 Coordination 36
Article 8 - City's Responsibilities 36
8.01 Communications to Contractor 36
8.02 Furnish Data 36
8.03 Pay When Due 36
8.04 Lands and Easements; Reports and Tests 36
8.05 Change Orders 36
8.06 Inspections, Tests, and Approvals 36
8.07 Limitations on City's Responsibilities 37
8.08 Undisclosed Hazardous Environmental Condition 37
8.09 Compliance with Safety Program 37
Article 9 - City's Observation Status During Construction 37
9.01 City's Project Representative 37
9.02 Visits to Site 37
9.03 Authorized Variations in Work 38
9.04 Rejecting Defective Work 38
9.05 Determinations for Work Performed 38
9.06 Decisions on Requirements of Contract Documents and Acceptability of Work 38
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
Article 10 - Changes in the Work; Claims; Extra Work 38
10.01 Authorized Changes in the Work 38
10.02 Unauthorized Changes in the Work 39
10.03 Execution of Change Orders 39
10.04 Extra Work 39
10.05 Notification to Surety 39
10.06 Contract Claims Process 40
Article 11 - Cost of the Work; Allowances; Unit Price Work; Plans Quantity Measurement 41
11.01 Cost of the Work 41
11.02 Allowances 43
11.03 Unit Price Work 44
11.04 Plans Quantity Measurement 45
Article 12 - Change of Contract Price; Change of Contract Time 46
12.01 Change of Contract Price 46
12.02 Change of Contract Time 47
12.03 Delays 47
Article 13 -
13.01
13.02
13.03
13.04
13.05
13.06
13.07
13.08
13.09
Article 14 -
14.01
14.02
14.03
14.04
14.05
14.06
14.07
14.08
14.09
Tests and Inspections; Correction, Removal or Acceptance of Defective Work 48
Notice of Defects 48
Access to Work 48
Tests and Inspections 48
Uncovering Work 49
City May Stop the Work 49
Correction or Removal of Defective Work 50
Correction Period 50
Acceptance of Defective Work 51
City May Correct Defective Work 51
Payments to Contractor and Completion 52
Schedule of Values 52
Progress Payments 52
Contractor's Warranty of Title 54
Partial Utilization 55
Final Inspection 55
Final Acceptance 55
Final Payment 56
Final Completion Delayed and Partial Retainage Release 56
Waiver of Claims 57
Article 15 - Suspension of Work and Termination 57
15.01 City May Suspend Work 57
15.02 City May Terminate for Cause 58
15.03 City May Terminate For Convenience 60
Article 16 - Dispute Resolution 61
16.01 Methods and Procedures 61
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
Article 17 — Miscellaneous 62
17.01 Giving Notice 62
17.02 Computation of Times 62
17.03 Cumulative Remedies 62
17.04 Survival of Obligations 63
17.05 Headings 63
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai t.,onmuons
Page 1 of 63
ARTICLE 1— DEFINITIONS AND TERMINOLOGY
1.01 Defined Terms
A. Wherever used in these General Conditions or in other Contract Documents, the terms listed
below have the meanings indicated which are applicable to both the singular and plural thereof,
and words denoting gender shall include the masculine, feminine and neuter. Said terms are
generally capitalized or written in italics, but not always. When used in a context consistent with
the definition of a listed -defined term, the term shall have a meaning as defined below whether
capitalized or italicized or otherwise. In addition to terms specifically defined, terms with initial
capital letters in the Contract Documents include references to identified articles and paragraphs,
and the titles of other documents or forms.
1. Addenda Written or graphic instruments issued prior to the opening of Bids which clarify,
correct, or change the Bidding Requirements or the proposed Contract Documents.
2. Agreement —The written instrument which is evidence of the agreement between City and
Contractor covering the Work.
3. Application for Payment —The form acceptable to City which is to be used by Contractor
during the course of the Work in requesting progress or final payments and which is to be
accompanied by such supporting documentation as is required by the Contract Documents.
4. Asbestos Any material that contains more than one percent asbestos and is friable or is
releasing asbestos fibers into the air above current action levels established by the United
States Occupational Safety and Health Administration.
5. Award — Authorization by the City Council for the City to enter into an Agreement.
6. Bid The offer or proposal of a Bidder submitted on the prescribed form setting forth the
prices for the Work to be performed.
7. Bidder —The individual or entity who submits a Bid directly to City.
8. Bidding Documents The Bidding Requirements and the proposed Contract Documents
(including all Addenda).
9. Bidding Requirements The advertisement or Invitation to Bid, Instructions to Bidders, Bid
security of acceptable form, if any, and the Bid Form with any supplements.
10. Business Day — A business day is defined as a day that the City conducts normal business,
generally Monday through Friday, except for federal or state holidays observed by the City.
11. Buzzsaw — City's on-line, electronic document management and collaboration system.
12. Calendar Day — A day consisting of 24 hours measured from midnight to the next midnight.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai k_.onamons
Page 2 of 63
13. Change Order A document, which is prepared and approved by the City, which is signed
by Contractor and City and authorizes an addition, deletion, or revision in the Work or an
adjustment in the Contract Price or the Contract Time, issued on or after the Effective Date
of the Agreement.
14. City The City of Fort Worth, Texas, a home -rule municipal corporation, authorized and
chartered under the Texas State Statutes, acting by its governing body through its City
Manager, his designee, or agents authorized under his behalf, each of which is required by
Charter to perform specific duties with responsibility for final enforcement of the contracts
involving the City of Fort Worth is by Charter vested in the City Manager and is the entity
with whom Contractor has entered into the Agreement and for whom the Work is to be
performed.
15. City Attorney — The officially appointed City Attorney of the City of Fort Worth, Texas, or
his duly authorized representative.
16. City Council - The duly elected and qualified governing body of the City of Fort Worth,
Texas.
17. City Manager — The officially appointed and authorized City Manager of the City of Fort
Worth, Texas, or his duly authorized representative.
18. Contract Claim A demand or assertion by City or Contractor seeking an adjustment of
Contract Price or Contract Time, or both, or other relief with respect to the terms of the
Contract. A demand for money or services by a third party is not a Contract Claim.
19. Contract The entire and integrated written document between the City and Contractor
concerning the Work. The Contract contains the Agreement and all Contract Documents and
supersedes prior negotiations, representations, or agreements, whether written or oral.
20. Contract Documents Those items so designated in the Agreement. All items listed in the
Agreement are Contract Documents. Approved Submittals, other Contractor submittals, and
the reports and drawings of subsurface and physical conditions are not Contract Documents.
21. Contract Price The moneys payable by City to Contractor for completion of the Work in
accordance with the Contract Documents as stated in the Agreement (subject to the
provisions of Paragraph 11.03 in the case of Unit Price Work).
22. Contract Time The number of days or the dates stated in the Agreement to: (i) achieve
Milestones, if any and (ii) complete the Work so that it is ready for Final Acceptance.
23. Contractor The individual or entity with whom City has entered into the Agreement.
24. Cost of the Work See Paragraph 11.01 of these General Conditions for definition.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai Lonomons
Page 3 of 63
25. Damage Claims — A demand for money or services arising from the Project or Site from a
third party, City or Contractor exclusive of a Contract Claim.
26. Day or day — A day, unless otherwise defined, shall mean a Calendar Day.
27. Director of Aviation — The officially appointed Director of the Aviation Department of the
City of Fort Worth, Texas, or his duly appointed representative, assistant, or agents.
28. Director of Parks and Community Services — The officially appointed Director of the Parks
and Community Services Department of the City of Fort Worth, Texas, or his duly appointed
representative, assistant, or agents.
29. Director of Planning and Development — The officially appointed Director of the Planning
and Development Department of the City of Fort Worth, Texas, or his duly appointed
representative, assistant, or agents.
30. Director of Transportation Public Works — The officially appointed Director of the
Transportation Public Works Department of the City of Fort Worth, Texas, or his duly
appointed representative, assistant, or agents.
31. Director of Water Department — The officially appointed Director of the Water Department
of the City of Fort Worth, Texas, or his duly appointed representative, assistant, or agents.
32. Drawings —That part of the Contract Documents prepared or approved by Engineer which
graphically shows the scope, extent, and character of the Work to be performed by
Contractor. Submittals are not Drawings as so defined.
33. Effective Date of the Agreement —The date indicated in the Agreement on which it becomes
effective, but if no such date is indicated, it means the date on which the Agreement is signed
and delivered by the last of the two parties to sign and deliver.
34. Engineer —The licensed professional engineer or engineering firm registered in the State of
Texas performing professional services for the City.
35. Extra Work — Additional work made necessary by changes or alterations of the Contract
Documents or of quantities or for other reasons for which no prices are provided in the
Contract Documents. Extra work shall be part of the Work.
36. Field Order A written order issued by City which requires changes in the Work but which
does not involve a change in the Contract Price, Contract Time, or the intent of the Engineer.
37. Final Acceptance — The written notice given by the City to the Contractor that the Work
specified in the Contract Documents has been completed to the satisfaction of the City.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai Commons
Page 4 of 63
38. Final Inspection — Inspection carried out by the City to verify that the Contractor has
completed the Work, and each and every part or appurtenance thereof, fully, entirely, and in
conformance with the Contract Documents.
39. General Requirements Sections of Division 1 of the Contract Documents.
40. Hazardous Environmental Condition The presence at the Site of Asbestos, PCBs,
Petroleum, Hazardous Waste, Radioactive Material, or other materials in such quantities or
circumstances that may present a substantial danger to persons or property exposed thereto.
41. Hazardous Waste —Hazardous waste is defined as any solid waste listed as hazardous or
possesses one or more hazardous characteristics as defined in the federal waste regulations,
as amended from time to time.
42. Laws and Regulations —Any and all applicable laws, rules, regulations, ordinances, codes,
and orders of any and all governmental bodies, agencies, authorities, and courts having
jurisdiction.
43. Liens Charges, security interests, or encumbrances upon Project funds, real property, or
personal property.
44. Major Item — An Item of work included in the Contract Documents that has a total cost equal
to or greater than 5% of the original Contract Price or $25,000 whichever is less.
45. Milestone A principal event specified in the Contract Documents relating to an intermediate
Contract Time prior to Final Acceptance of the Work.
46. Notice of Award The written notice by City to the Successful Bidder stating that upon
timely compliance by the Successful Bidder with the conditions precedent listed therein, City
will sign and deliver the Agreement.
47. Notice to Proceed A written notice given by City to Contractor fixing the date on which the
Contract Time will commence to run and on which Contractor shall start to perform the
Work specified in Contract Documents.
48. PCBs Polychlorinated biphenyls.
49. Petroleum Petroleum, including crude oil or any fraction thereof which is liquid at standard
conditions of temperature and pressure (60 degrees Fahrenheit and 14.7 pounds per square
inch absolute), such as oil, petroleum, fuel oil, oil sludge, oil refuse, gasoline, kerosene, and
oil mixed with other non -Hazardous Waste and crude oils.
50. Plans — See definition of Drawings.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai Lonomons
Page 5 of 63
51. Project Schedule A schedule, prepared and maintained by Contractor, in accordance with
the General Requirements, describing the sequence and duration of the activities comprising
the Contractor's plan to accomplish the Work within the Contract Time.
52. Project —The Work to be performed under the Contract Documents.
53. Project Representative —The authorized representative of the City who will be assigned to
the Site.
54. Public Meeting — An announced meeting conducted by the City to facilitate public
participation and to assist the public in gaining an informed view of the Project.
55. Radioactive Material Source, special nuclear, or byproduct material as defined by the
Atomic Energy Act of 1954 (42 USC Section 2011 et seq.) as amended from time to time.
56. Regular Working Hours — Hours beginning at 7:00 a.m. and ending at 6:00 p.m., Monday
thru Friday (excluding legal holidays).
57. Samples —Physical examples of materials, equipment, or workmanship that are
representative of some portion of the Work and which establish the standards by which such
portion of the Work will be judged.
58. Schedule of Submittals A schedule, prepared and maintained by Contractor, of required
submittals and the time requirements to support scheduled performance of related
construction activities.
59. Schedule of Values —A schedule, prepared and maintained by Contractor, allocating portions
of the Contract Price to various portions of the Work and used as the basis for reviewing
Contractor's Applications for Payment.
60. Site Lands or areas indicated in the Contract Documents as being furnished by City upon
which the Work is to be performed, including rights -of -way, permits, and easements for
access thereto, and such other lands furnished by City which are designated for the use of
Contractor.
61 Specifications That part of the Contract Documents consisting of written requirements for
materials, equipment, systems, standards and workmanship as applied to the Work, and
certain administrative requirements and procedural matters applicable thereto. Specifications
may be specifically made a part of the Contract Documents by attachment or, if not attached,
may be incorporated by reference as indicated in the Table of Contents (Division 00 00 00)
of each Project.
62. Subcontractor An individual or entity having a direct contract with Contractor or with any
other Subcontractor for the performance of a part of the Work at the Site.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai Lonamons
Page 6 of 63
63. Submittals All drawings, diagrams, illustrations, schedules, and other data or information
which are specifically prepared or assembled by or for Contractor and submitted by
Contractor to illustrate some portion of the Work.
64. Successful Bidder The Bidder submitting the lowest and most responsive Bid to whom City
makes an Award.
65. Superintendent — The representative of the Contractor who is available at all times and able
to receive instructions from the City and to act for the Contractor.
66. Supplementary Conditions —That part of the Contract Documents which amends or
supplements these General Conditions.
67. Supplier —A manufacturer, fabricator, supplier, distributor, materialman, or vendor having a
direct contract with Contractor or with any Subcontractor to furnish materials or equipment
to be incorporated in the Work by Contractor or Subcontractor.
68. Underground Facilities —All underground pipelines, conduits, ducts, cables, wires,
manholes, vaults, tanks, tunnels, or other such facilities or attachments, and any encasements
containing such facilities, including but not limited to, those that convey electricity, gases,
steam, liquid petroleum products, telephone or other communications, cable television,
water, wastewater, storm water, other liquids or chemicals, or traffic or other control systems.
69. Unit Price Work See Paragraph 11.03 of these General Conditions for definition.
70. Weekend Working Hours — Hours beginning at 9:00 a.m. and ending at 5:00 p.m., Saturday,
Sunday or legal holiday, as approved in advance by the City.
71. Work The entire construction or the various separately identifiable parts thereof required to
be provided under the Contract Documents. Work includes and is the result of performing or
providing all labor, services, and documentation necessary to produce such construction
including any Change Order or Field Order, and furnishing, installing, and incorporating all
materials and equipment into such construction, all as required by the Contract Documents.
72. Working Day — A working day is defined as a day, not including Saturdays, Sundays, or legal
holidays authorized by the City for contract purposes, in which weather or other conditions
not under the control of the Contractor will permit the performance of the principal unit of
work underway for a continuous period of not less than 7 hours between 7 a.m. and 6 p.m.
1.02 Terminology
A. The words and terms discussed in Paragraph 1.02.B through E are not defined but, when used in
the Bidding Requirements or Contract Documents, have the indicated meaning.
B. Intent of Certain Terms or Adjectives.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai Lonomons
Page 7 of 63
1. The Contract Documents include the terms "as allowed," "as approved," "as ordered," "as
directed" or terms of like effect or import to authorize an exercise of judgment by City. In
addition, the adjectives "reasonable," "suitable," "acceptable," "proper," "satisfactory," or
adjectives of like effect or import are used to describe an action or determination of City as to
the Work. It is intended that such exercise of professional judgment, action, or determination
will be solely to evaluate, in general, the Work for compliance with the information in the
Contract Documents and with the design concept of the Project as a functioning whole as
shown or indicated in the Contract Documents (unless there is a specific statement indicating
otherwise).
C. Defective:
1. The word "defective," when modifying the word "Work," refers to Work that is
unsatisfactory, faulty, or deficient in that it:
a. does not conform to the Contract Documents; or
b. does not meet the requirements of any applicable inspection, reference standard, test, or
approval referred to in the Contract Documents; or
c. has been damaged prior to City's written acceptance.
D. Furnish, Install, Perform, Provide:
1. The word "Furnish" or the word "Install" or the word "Perform" or the word "Provide" or
the word "Supply," or any combination or similar directive or usage thereof, shall mean
furnishing and incorporating in the Work including all necessary labor, materials, equipment,
and everything necessary to perform the Work indicated, unless specifically limited in the
context used.
E. Unless stated otherwise in the Contract Documents, words or phrases that have a well-known
technical or construction industry or trade meaning are used in the Contract Documents in
accordance with such recognized meaning.
ARTICLE 2 — PRELIMINARY MATTERS
2.01 Copies of Documents
City shall furnish to Contractor one (1) original executed copy and one (1) electronic copy of the
Contract Documents, and four (4) additional copies of the Drawings. Additional copies will be
furnished upon request at the cost of reproduction.
2.02 Commencement of Contract Time; Notice to Proceed
The Contract Time will commence to run on the day indicated in the Notice to Proceed. A Notice to
Proceed may be given at any time within 14 days after the Effective Date of the Agreement.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai Lononions
Page 8 of 63
2.03 Starting the Work
Contractor shall start to perform the Work on the date when the Contract Time commences to run.
No Work shall be done at the Site prior to the date on which the Contract Time commences to run.
2.04 Before Starting Construction
Baseline Schedules: Submit in accordance with the Contract Documents, and prior to starting the
Work.
2.05 Preconstruction Conference
Before any Work at the Site is started, the Contractor shall attend a Preconstruction Conference as
specified in the Contract Documents.
2.06 Public Meeting
Contractor may not mobilize any equipment, materials or resources to the Site prior to Contractor
attending the Public Meeting as scheduled by the City.
2.07 Initial Acceptance of Schedules
No progress payment shall be made to Contractor until acceptable schedules are submitted to City in
accordance with the Schedule Specification as provided in the Contract Documents.
ARTICLE 3 — CONTRACT DOCUMENTS: INTENT, AMENDING, REUSE
3.01 Intent
A. The Contract Documents are complementary; what is required by one is as binding as if required
by all.
B. It is the intent of the Contract Documents to describe a functionally complete project (or part
thereof) to be constructed in accordance with the Contract Documents. Any labor,
documentation, services, materials, or equipment that reasonably may be inferred from the
Contract Documents or from prevailing custom or trade usage as being required to produce the
indicated result will be provided whether or not specifically called for, at no additional cost to
City.
C. Clarifications and interpretations of the Contract Documents shall be issued by City.
D. The Specifications may vary in form, format and style. Some Specification sections may be
written in varying degrees of streamlined or declarative style and some sections may be
relatively narrative by comparison. Omission of such words and phrases as "the Contractor
shall," "in conformity with," "as shown," or "as specified" are intentional in streamlined
sections. Omitted words and phrases shall be supplied by inference. Similar types of provisions
may appear in various parts of a section or articles within a part depending on the format of the
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai commons
Page 9 of 63
section. The Contractor shall not take advantage of any variation of form, format or style in
making Contract Claims.
E. The cross referencing of specification sections under the subparagraph heading "Related
Sections include but are not necessarily limited to:" and elsewhere within each Specification
section is provided as an aid and convenience to the Contractor. The Contractor shall not rely on
the cross referencing provided and shall be responsible to coordinate the entire Work under the
Contract Documents and provide a complete Project whether or not the cross referencing is
provided in each section or whether or not the cross referencing is complete.
3.02 Reference Standards
A. Standards, Specifications, Codes, Laws, and Regulations
1. Reference to standards, specifications, manuals, or codes of any technical society,
organization, or association, or to Laws or Regulations, whether such reference be specific or
by implication, shall mean the standard, specification, manual, code, or Laws or Regulations
in effect at the time of opening of Bids (or on the Effective Date of the Agreement if there
were no Bids), except as may be otherwise specifically stated in the Contract Documents.
2. No provision of any such standard, specification, manual, or code, or any instruction of a
Supplier, shall be effective to change the duties or responsibilities of City, Contractor, or any
of their subcontractors, consultants, agents, or employees, from those set forth in the Contract
Documents. No such provision or instruction shall be effective to assign to City, or any of its
officers, directors, members, partners, employees, agents, consultants, or subcontractors, any
duty or authority to supervise or direct the performance of the Work or any duty or authority
to undertake responsibility inconsistent with the provisions of the Contract Documents.
3.03 Reporting and Resolving Discrepancies
A. Reporting Discrepancies:
1. Contractor's Review of Contract Documents Before Starting Work: Before undertaking each
part of the Work, Contractor shall carefully study and compare the Contract Documents and
check and verify pertinent figures therein against all applicable field measurements and
conditions. Contractor shall promptly report in writing to City any conflict, error, ambiguity,
or discrepancy which Contractor discovers, or has actual knowledge of, and shall obtain a
written interpretation or clarification from City before proceeding with any Work affected
thereby.
2. Contractor's Review of Contract Documents During Performance of Work: If, during the
performance of the Work, Contractor discovers any conflict, error, ambiguity, or discrepancy
within the Contract Documents, or between the Contract Documents and (a) any applicable
Law or Regulation , (b) any standard, specification, manual, or code, or (c) any instruction of
any Supplier, then Contractor shall promptly report it to City in writing. Contractor shall not
proceed with the Work affected thereby (except in an emergency as required by Paragraph
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai Lonamons
Page 10 of 63
6.17.A) until an amendment or supplement to the Contract Documents has been issued by
one of the methods indicated in Paragraph 3.04.
3. Contractor shall not be liable to City for failure to report any conflict, error, ambiguity, or
discrepancy in the Contract Documents unless Contractor had actual knowledge thereof.
B. Resolving Discrepancies:
1. Except as may be otherwise specifically stated in the Contract Documents, the provisions of
the Contract Documents shall take precedence in resolving any conflict, error, ambiguity, or
discrepancy between the provisions of the Contract Documents and the provisions of any
standard, specification, manual, or the instruction of any Supplier (whether or not specifically
incorporated by reference in the Contract Documents).
2. In case of discrepancies, figured dimensions shall govern over scaled dimensions, Plans shall
govern over Specifications, Supplementary Conditions shall govern over General Conditions
and Specifications, and quantities shown on the Plans shall govern over those shown in the
proposal.
3.04 Amending and Supplementing Contract Documents
A. The Contract Documents may be amended to provide for additions, deletions, and revisions in
the Work or to modify the terms and conditions thereof by a Change Order.
B. The requirements of the Contract Documents may be supplemented, and minor variations and
deviations in the Work not involving a change in Contract Price or Contract Time, may be
authorized, by one or more of the following ways:
1. A Field Order;
2. City's review of a Submittal (subject to the provisions of Paragraph 6.18.C); or
3. City's written interpretation or clarification.
3.05 Reuse of Documents
A. Contractor and any Subcontractor or Supplier shall not:
have or acquire any title to or ownership rights in any of the Drawings, Specifications, or
other documents (or copies of any thereof) prepared by or bearing the seal of Engineer,
including electronic media editions; or
2. reuse any such Drawings, Specifications, other documents, or copies thereof on extensions of
the Project or any other project without written consent of City and specific written
verification or adaptation by Engineer.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai Lommmons
Page 11 of 63
B. The prohibitions of this Paragraph 3.05 will survive final payment, or termination of the
Contract. Nothing herein shall preclude Contractor from retaining copies of the Contract
Documents for record purposes.
3.06 Electronic Data
A. Unless otherwise stated in the Supplementary Conditions, the data furnished by City or Engineer
to Contractor, or by Contractor to City or Engineer, that may be relied upon are limited to the
printed copies included in the Contract Documents (also known as hard copies) and other
Specifications referenced and located on the City's Buzzsaw site. Files in electronic media
format of text, data, graphics, or other types are furnished only for the convenience of the
receiving party. Any conclusion or information obtained or derived from such electronic files
will be at the user's sole risk. If there is a discrepancy between the electronic files and the hard
copies, the hard copies govern.
B. When transferring documents in electronic media format, the transferring party makes no
representations as to long term compatibility, usability, or readability of documents resulting
from the use of software application packages, operating systems, or computer hardware
differing from those used by the data's creator.
ARTICLE 4 — AVAILABILITY OF LANDS; SUBSURFACE AND PHYSICAL CONDITIONS;
HAZARDOUS ENVIRONMENTAL CONDITIONS; REFERENCE POINTS
4.01 Availability of Lands
A. City shall furnish the Site. City shall notify Contractor of any encumbrances or restrictions not of
general application but specifically related to use of the Site with which Contractor must comply
in performing the Work. City will obtain in a timely manner and pay for easements for
permanent structures or permanent changes in existing facilities.
1. The City has obtained or anticipates acquisition of and/or access to right-of-way, and/or
easements. Any outstanding right-of-way and/or easements are anticipated to be acquired in
accordance with the schedule set forth in the Supplementary Conditions. The Project
Schedule submitted by the Contractor in accordance with the Contract Documents must
consider any outstanding right-of-way, and/or easements.
2. The City has or anticipates removing and/or relocating utilities, and obstructions to the Site.
Any outstanding removal or relocation of utilities or obstructions is anticipated in accordance
with the schedule set forth in the Supplementary Conditions. The Project Schedule submitted
by the Contractor in accordance with the Contract Documents must consider any outstanding
utilities or obstructions to be removed, adjusted, and/or relocated by others.
B. Upon reasonable written request, City shall furnish Contractor with a current statement of record
legal title and legal description of the lands upon which the Work is to be performed.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai Lommnions
Page 12 of 63
C. Contractor shall provide for all additional lands and access thereto that may be required for
construction facilities or storage of materials and equipment.
4.02 Subsurface and Physical Conditions
A. Reports and Drawings: The Supplementary Conditions identify:
1. those reports known to City of explorations and tests of subsurface conditions at or
contiguous to the Site; and
2. those drawings known to City of physical conditions relating to existing surface or
subsurface structures at the Site (except Underground Facilities).
B. Limited Reliance by Contractor on Technical Data Authorized: Contractor may rely upon the
accuracy of the "technical data" contained in such reports and drawings, but such reports and
drawings are not Contract Documents. Such "technical data" is identified in the Supplementary
Conditions. Contractor may not make any Contract Claim against City, or any of their officers,
directors, members, partners, employees, agents, consultants, or subcontractors with respect to:
1. the completeness of such reports and drawings for Contractor's purposes, including, but not
limited to, any aspects of the means, methods, techniques, sequences, and procedures of
construction to be employed by Contractor, and safety precautions and programs incident
thereto; or
2. other data, interpretations, opinions, and information contained in such reports or shown or
indicated in such drawings; or
3. any Contractor interpretation of or conclusion drawn from any "technical data" or any such
other data, interpretations, opinions, or information.
4.03 Differing Subsurface or Physical Conditions
A. Notice: If Contractor believes that any subsurface or physical condition that is uncovered or
revealed either:
1. is of such a nature as to establish that any "technical data" on which Contractor is entitled to
rely as provided in Paragraph 4.02 is materially inaccurate; or
2. is of such a nature as to require a change in the Contract Documents; or
3. differs materially from that shown or indicated in the Contract Documents; or
4. is of an unusual nature, and differs materially from conditions ordinarily encountered and
generally recognized as inherent in work of the character provided for in the Contract
Documents;
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai commons
Page 13 of 63
then Contractor shall, promptly after becoming aware thereof and before further disturbing the
subsurface or physical conditions or performing any Work in connection therewith (except in an
emergency as required by Paragraph 6.17.A), notify City in writing about such condition.
B. Possible Price and Time Adjustments
Contractor shall not be entitled to any adjustment in the Contract Price or Contract Time if:
1. Contractor knew of the existence of such conditions at the time Contractor made a final
commitment to City with respect to Contract Price and Contract Time by the submission of a
Bid or becoming bound under a negotiated contract; or
2. the existence of such condition could reasonably have been discovered or revealed as a result
of the examination of the Contract Documents or the Site; or
3. Contractor failed to give the written notice as required by Paragraph 4.03.A.
4.04 Underground Facilities
A. Shown or Indicated: The information and data shown or indicated in the Contract Documents
with respect to existing Underground Facilities at or contiguous to the Site is based on
information and data furnished to City or Engineer by the owners of such Underground
Facilities, including City, or by others. Unless it is otherwise expressly provided in the
Supplementary Conditions:
1. City and Engineer shall not be responsible for the accuracy or completeness of any such
information or data provided by others; and
2. the cost of all of the following will be included in the Contract Price, and Contractor shall
have full responsibility for:
a. reviewing and checking all such information and data;
b. locating all Underground Facilities shown or indicated in the Contract Documents;
c. coordination and adjustment of the Work with the owners of such Underground
Facilities, including City, during construction; and
d. the safety and protection of all such Underground Facilities and repairing any damage
thereto resulting from the Work.
B. Not Shown or Indicated:
1. If an Underground Facility which conflicts with the Work is uncovered or revealed at or
contiguous to the Site which was not shown or indicated, or not shown or indicated with
reasonable accuracy in the Contract Documents, Contractor shall, promptly after becoming
aware thereof and before further disturbing conditions affected thereby or performing any
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai Lonaiuons
Page 14 of 63
Work in connection therewith (except in an emergency as required by Paragraph 6.17.A),
identify the owner of such Underground Facility and give notice to that owner and to City.
City will review the discovered Underground Facility and determine the extent, if any, to
which a change may be required in the Contract Documents to reflect and document the
consequences of the existence or location of the Underground Facility. Contractor shall be
responsible for the safety and protection of such discovered Underground Facility.
2. If City concludes that a change in the Contract Documents is required, a Change Order may
be issued to reflect and document such consequences.
3. Verification of existing utilities, structures, and service lines shall include notification of all
utility companies a minimum of 48 hours in advance of construction including exploratory
excavation if necessary.
4.05 Reference Points
A. City shall provide engineering surveys to establish reference points for construction, which in
City's judgment are necessary to enable Contractor to proceed with the Work. City will provide
construction stakes or other customary method of marking to establish line and grades for
roadway and utility construction, centerlines and benchmarks for bridgework. Contractor shall
protect and preserve the established reference points and property monuments, and shall make no
changes or relocations. Contractor shall report to City whenever any reference point or property
monument is lost or destroyed or requires relocation because of necessary changes in grades or
locations. The City shall be responsible for the replacement or relocation of reference points or
property monuments not carelessly or willfully destroyed by the Contractor. The Contractor shall
notify City in advance and with sufficient time to avoid delays.
B. Whenever, in the opinion of the City, any reference point or monument has been carelessly or
willfully destroyed, disturbed, or removed by the Contractor or any of his employees, the full
cost for replacing such points plus 25% will be charged against the Contractor, and the full
amount will be deducted from payment due the Contractor.
4.06 Hazardous Environmental Condition at Site
A. Reports and Drawings: The Supplementary Conditions identify those reports and drawings
known to City relating to Hazardous Environmental Conditions that have been identified at the
Site.
B. Limited Reliance by Contractor on Technical Data Authorized: Contractor may rely upon the
accuracy of the "technical data" contained in such reports and drawings, but such reports and
drawings are not Contract Documents. Such "technical data" is identified in the Supplementary
Conditions. Contractor may not make any Contract Claim against City, or any of their officers,
directors, members, partners, employees, agents, consultants, or subcontractors with respect to:
1. the completeness of such reports and drawings for Contractor's purposes, including, but not
limited to, any aspects of the means, methods, techniques, sequences and procedures of
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai Lonomons
Page 15 of 63
construction to be employed by Contractor and safety precautions and programs incident
thereto; or
2. other data, interpretations, opinions and information contained in such reports or shown or
indicated in such drawings; or
3. any Contractor interpretation of or conclusion drawn from any "technical data" or any such
other data, interpretations, opinions or information.
C. Contractor shall not be responsible for any Hazardous Environmental Condition uncovered or
revealed at the Site which was not shown or indicated in Drawings or Specifications or identified
in the Contract Documents to be within the scope of the Work. Contractor shall be responsible
for a Hazardous Environmental Condition created with any materials brought to the Site by
Contractor, Subcontractors, Suppliers, or anyone else for whom Contractor is responsible.
D. If Contractor encounters a Hazardous Environmental Condition or if Contractor or anyone for
whom Contractor is responsible creates a Hazardous Environmental Condition, Contractor shall
immediately: (i) secure or otherwise isolate such condition; (ii) stop all Work in connection with
such condition and in any area affected thereby (except in an emergency as required by
Paragraph 6.17.A); and (iii) notify City (and promptly thereafter confirm such notice in writing).
City may consider the necessity to retain a qualified expert to evaluate such condition or take
corrective action, if any.
E. Contractor shall not be required to resume Work in connection with such condition or in any
affected area until after City has obtained any required permits related thereto and delivered
written notice to Contractor: (i) specifying that such condition and any affected area is or has
been rendered suitable for the resumption of Work; or (ii) specifying any special conditions
under which such Work may be resumed.
F. If after receipt of such written notice Contractor does not agree to resume such Work based on a
reasonable belief it is unsafe, or does not agree to resume such Work under such special
conditions, then City may order the portion of the Work that is in the area affected by such
condition to be deleted from the Work. City may have such deleted portion of the Work
performed by City's own forces or others.
G. To the fullest extent permitted by Laws and Regulations, Contractor shall indemnibi and hold
harmless City, from and against all claims, costs, losses, and damages (including but not limited
to all fees and charges of engineers, architects, attorneys, and other professionals and all court
or arbitration or other dispute resolution costs) arising out of or relating to a Hazardous
Environmental Condition created by Contractor or by anyone for whom Contractor is
responsible. Nothing in this Paragraph 4.06. G shall obligate Contractor to indemnify any
individual or entity .from and against the consequences of that individual's or entity's own
negligence.
H. The provisions of Paragraphs 4.02, 4.03, and 4.04 do not apply to a Hazardous Environmental
Condition uncovered or revealed at the Site.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai Lonmuons
Page 16 of 63
ARTICLE 5 — BONDS AND INSURANCE
5.01 Licensed Sureties and Insurers
All bonds and insurance required by the Contract Documents to be purchased and maintained by
Contractor shall be obtained from surety or insurance companies that are duly licensed or authorized
in the State of Texas to issue bonds or insurance policies for the limits and coverages so required.
Such surety and insurance companies shall also meet such additional requirements and qualifications
as may be provided in the Supplementary Conditions.
5.02 Performance, Payment, and Maintenance Bonds
A. Contractor shall furnish performance and payment bonds, in accordance with Texas Government
Code Chapter 2253 or successor statute, each in an amount equal to the Contract Price as
security for the faithful performance and payment of all of Contractor's obligations under the
Contract Documents.
B. Contractor shall furnish maintenance bonds in an amount equal to the Contract Price as security
to protect the City against any defects in any portion of the Work described in the Contract
Documents. Maintenance bonds shall remain in effect for two (2) years after the date of Final
Acceptance by the City.
C. All bonds shall be in the form prescribed by the Contract Documents except as provided
otherwise by Laws or Regulations, and shall be executed by such sureties as are named in the list
of "Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and
as Acceptable Reinsuring Companies" as published in Circular 570 (amended) by the Financial
Management Service, Surety Bond Branch, U.S. Department of the Treasury. All bonds signed
by an agent or attorney -in -fact must be accompanied by a sealed and dated power of attorney
which shall show that it is effective on the date the agent or attorney -in -fact signed each bond.
D. If the surety on any bond furnished by Contractor is declared bankrupt or becomes insolvent or
its right to do business is terminated in the State of Texas or it ceases to meet the requirements of
Paragraph 5.02.C, Contractor shall promptly notify City and shall, within 30 days after the event
giving rise to such notification, provide another bond and surety, both of which shall comply
with the requirements of Paragraphs 5.01 and 5.02.C.
5.03 Certificates of Insurance
Contractor shall deliver to City, with copies to each additional insured and loss payee identified in
the Supplementary Conditions, certificates of insurance (and other evidence of insurance requested
by City or any other additional insured) which Contractor is required to purchase and maintain.
1. The certificate of insurance shall document the City, and all identified entities named in the
Supplementary Conditions as "Additional Insured" on all liability policies.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai Lonunions
Page 17 of 63
2. The Contractor's general liability insurance shall include a, "per project" or "per location",
endorsement, which shall be identified in the certificate of insurance provided to the City.
3. The certificate shall be signed by an agent authorized to bind coverage on behalf of the
insured, be complete in its entirety, and show complete insurance carrier names as listed in
the current A.M. Best Property & Casualty Guide
4. The insurers for all policies must be licensed and/or approved to do business in the State of
Texas. Except for workers' compensation, all insurers must have a minimum rating of A-:
VII in the current A. M. Best Key Rating Guide or have reasonably equivalent financial
strength and solvency to the satisfaction of Risk Management. If the rating is below that
required, written approval of City is required.
5. All applicable policies shall include a Waiver of Subrogation (Rights of Recovery) in favor
of the City. In addition, the Contractor agrees to waive all rights of subrogation against the
Engineer (if applicable), and each additional insured identified in the Supplementary
Conditions
6. Failure of the City to demand such certificates or other evidence of full compliance with the
insurance requirements or failure of the City to identify a deficiency from evidence that is
provided shall not be construed as a waiver of Contractor's obligation to maintain such lines
of insurance coverage.
7. If insurance policies are not written for specified coverage limits, an Umbrella or Excess
Liability insurance for any differences is required. Excess Liability shall follow form of the
primary coverage.
8. Unless otherwise stated, all required insurance shall be written on the "occurrence basis". If
coverage is underwritten on a claims -made basis, the retroactive date shall be coincident with
or prior to the date of the effective date of the agreement and the certificate of insurance shall
state that the coverage is claims -made and the retroactive date. The insurance coverage shall
be maintained for the duration of the Contract and for three (3) years following Final
Acceptance provided under the Contract Documents or for the warranty period, whichever is
longer. An annual certificate of insurance submitted to the City shall evidence such
insurance coverage.
9. Policies shall have no exclusions by endorsements, which, neither nullify or amend, the
required lines of coverage, nor decrease the limits of said coverage unless such endorsements
are approved in writing by the City. In the event a Contract has been bid or executed and the
exclusions are determined to be unacceptable or the City desires additional insurance
coverage, and the City desires the contractor/engineer to obtain such coverage, the contract
price shall be adjusted by the cost of the premium for such additional coverage plus 10%.
10. Any self -insured retention (SIR), in excess of $25,000.00, affecting required insurance
coverage shall be approved by the City in regards to asset value and stockholders' equity. In
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai Lonamons
Page 18 of 63
lieu of traditional insurance, alternative coverage maintained through insurance pools or risk
retention groups, must also be approved by City.
11. Any deductible in excess of $5,000.00, for any policy that does not provide coverage on a
first -dollar basis, must be acceptable to and approved by the City.
12. City, at its sole discretion, reserves the right to review the insurance requirements and to
make reasonable adjustments to insurance coverage's and their limits when deemed
necessary and prudent by the City based upon changes in statutory law, court decision or the
claims history of the industry as well as of the contracting party to the City. The City shall
be required to provide prior notice of 90 days, and the insurance adjustments shall be
incorporated into the Work by Change Order.
13. City shall be entitled, upon written request and without expense, to receive copies of policies
and endorsements thereto and may make any reasonable requests for deletion or revision or
modifications of particular policy terms, conditions, limitations, or exclusions necessary to
conform the policy and endorsements to the requirements of the Contract. Deletions,
revisions, or modifications shall not be required where policy provisions are established by
law or regulations binding upon either party or the underwriter on any such policies.
14. City shall not be responsible for the direct payment of insurance premium costs for
Contractor's insurance.
5.04 Contractor's Insurance
A. Workers Compensation and Employers' Liability. Contractor shall purchase and maintain such
insurance coverage with limits consistent with statutory benefits outlined in the Texas Workers'
Compensation Act (Texas Labor Code, Ch. 406, as amended), and minimum limits for
Employers' Liability as is appropriate for the Work being performed and as will provide
protection from claims set forth below which may arise out of or result from Contractor's
performance of the Work and Contractor's other obligations under the Contract Documents,
whether it is to be performed by Contractor, any Subcontractor or Supplier, or by anyone directly
or indirectly employed by any of them to perform any of the Work, or by anyone for whose acts
any of them may be liable:
1. claims under workers' compensation, disability benefits, and other similar employee benefit
acts;
2. claims for damages because of bodily injury, occupational sickness or disease, or death of
Contractor's employees.
B. Commercial General Liability. Coverage shall include but not be limited to covering liability
(bodily injury or property damage) arising from: premises/operations, independent contractors,
products/completed operations, personal injury, and liability under an insured contract. Insurance
shall be provided on an occurrence basis, and as comprehensive as the current Insurance Services
Office (ISO) policy. This insurance shall apply as primary insurance with respect to any other
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai cononions
Page 19 of 63
insurance or self-insurance programs afforded to the City. The Commercial General Liability
policy, shall have no exclusions by endorsements that would alter of nullify premises/operations,
products/completed operations, contractual, personal injury, or advertising injury, which are
normally contained with the policy, unless the City approves such exclusions in writing.
For construction projects that present a substantial completed operation exposure, the City may
require the contractor to maintain completed operations coverage for a minimum of no less than
three (3) years following the completion of the project (if identified in the Supplementary
Conditions).
C. Automobile Liability. A commercial business auto policy shall provide coverage on "any auto",
defined as autos owned, hired and non -owned and provide indemnity for claims for damages
because bodily injury or death of any person and or property damage arising out of the work,
maintenance or use of any motor vehicle by the Contractor, any Subcontractor or Supplier, or by
anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone
for whose acts any of them may be liable.
D. Railroad Protective Liability. If any of the work or any warranty work is within the limits of
railroad right-of-way, the Contractor shall comply with the requirements identified in the
Supplementary Conditions.
E. Notification of Policy Cancellation: Contractor shall immediately notify City upon cancellation
or other loss of insurance coverage. Contractor shall stop work until replacement insurance has
been procured. There shall be no time credit for days not worked pursuant to this section.
5.05 Acceptance of Bonds and Insurance; Option to Replace
If City has any objection to the coverage afforded by or other provisions of the bonds or insurance
required to be purchased and maintained by the Contractor in accordance with Article 5 on the basis
of non-conformance with the Contract Documents, the City shall so notify the Contractor in writing
within 10 Business Days after receipt of the certificates (or other evidence requested). Contractor
shall provide to the City such additional information in respect of insurance provided as the City may
reasonably request. If Contractor does not purchase or maintain all of the bonds and insurance
required by the Contract Documents, the City shall notify the Contractor in writing of such failure
prior to the start of the Work, or of such failure to maintain prior to any change in the required
coverage.
ARTICLE 6 — CONTRACTOR'S RESPONSIBILITIES
6.01 Supervision and Superintendence
A. Contractor shall supervise, inspect, and direct the Work competently and efficiently, devoting
such attention thereto and applying such skills and expertise as may be necessary to perform the
Work in accordance with the Contract Documents. Contractor shall be solely responsible for the
means, methods, techniques, sequences, and procedures of construction.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai Lonanions
Page 20 ot'63
B. At all times during the progress of the Work, Contractor shall assign a competent, English-
speaking, Superintendent who shall not be replaced without written notice to City. The
Superintendent will be Contractor's representative at the Site and shall have authority to act on
behalf of Contractor. All communication given to or received from the Superintendent shall be
binding on Contractor.
C. Contractor shall notify the City 24 hours prior to moving areas during the sequence of
construction.
6.02 Labor; Working Hours
A. Contractor shall provide competent, suitably qualified personnel to perform construction as
required by the Contract Documents. Contractor shall at all times maintain good discipline and
order at the Site.
B. Except as otherwise required for the safety or protection of persons or the Work or property at
the Site or adjacent thereto, and except as otherwise stated in the Contract Documents, all Work
at the Site shall be performed during Regular Working Hours. Contractor will not permit the
performance of Work beyond Regular Working Hours or for Weekend Working Hours without
City's written consent (which will not be unreasonably withheld). Written request (by letter or
electronic communication) to perform Work:
1. for beyond Regular Working Hours request must be made by noon at least two (2) Business
Days prior
2. for Weekend Working Hours request must be made by noon of the preceding Thursday
3. for legal holidays request must be made by noon two Business Days prior to the legal
holiday.
6.03 Services, Materials, and Equipment
A. Unless otherwise specified in the Contract Documents, Contractor shall provide and assume full
responsibility for all services, materials, equipment, labor, transportation, construction equipment
and machinery, tools, appliances, fuel, power, light, heat, telephone, water, sanitary facilities,
temporary facilities, and all other facilities and incidentals necessary for the performance,
Contractor required testing, start-up, and completion of the Work.
B. All materials and equipment incorporated into the Work shall be as specified or, if not specified,
shall be of good quality and new, except as otherwise provided in the Contract Documents. All
special warranties and guarantees required by the Specifications shall expressly run to the benefit
of City. If required by City, Contractor shall furnish satisfactory evidence (including reports of
required tests) as to the source, kind, and quality of materials and equipment.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
venerai Lonomons
Page 21 of 63
C. All materials and equipment to be incorporated into the Work shall be stored, applied, installed,
connected, erected, protected, used, cleaned, and conditioned in accordance with instructions of
the applicable Supplier, except as otherwise may be provided in the Contract Documents.
D. All items of standard equipment to be incorporated into the Work shall be the latest model at the
time of bid, unless otherwise specified.
6.04 Project Schedule
A. Contractor shall adhere to the Project Schedule established in accordance with Paragraph 2.07
and the General Requirements as it may be adjusted from time to time as provided below.
1. Contractor shall submit to City for acceptance (to the extent indicated in Paragraph 2.07 and
the General Requirements) proposed adjustments in the Project Schedule that will not result
in changing the Contract Time. Such adjustments will comply with any provisions of the
General Requirements applicable thereto.
2. Contractor shall submit to City a monthly Project Schedule with a monthly progress payment
for the duration of the Contract in accordance with the schedule specification 01 32 16.
3. Proposed adjustments in the Project Schedule that will change the Contract Time shall be
submitted in accordance with the requirements of Article 12. Adjustments in Contract Time
may only be made by a Change Order.
6.05 Substitutes and "Or -Equals"
A. Whenever an item of material or equipment is specified or described in the Contract Documents
by using the name of a proprietary item or the name of a particular Supplier, the specification or
description is intended to establish the type, function, appearance, and quality required. Unless
the specification or description contains or is followed by words reading that no like, equivalent,
or "or -equal" item or no substitution is permitted, other items of material or equipment of other
Suppliers may be submitted to City for review under the circumstances described below.
1. "Or -Equal" Items: If in City's sole discretion an item of material or equipment proposed by
Contractor is functionally equal to that named and sufficiently similar so that no change in
related Work will be required, it may be considered by City as an "or -equal" item, in which
case review and approval of the proposed item may, in City's sole discretion, be
accomplished without compliance with some or all of the requirements for approval of
proposed substitute items. For the purposes of this Paragraph 6.05.A.1, a proposed item of
material or equipment will be considered functionally equal to an item so named if:
a. the City determines that:
1) it is at least equal in materials of construction, quality, durability, appearance,
strength, and design characteristics;
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai Lonamons
Page 22 of 63
2) it will reliably perform at least equally well the function and achieve the results
imposed by the design concept of the completed Project as a functioning whole; and
3) it has a proven record of performance and availability of responsive service; and
b. Contractor certifies that, if approved and incorporated into the Work:
1) there will be no increase in cost to the City or increase in Contract Time; and
2) it will conform substantially to the detailed requirements of the item named in the
Contract Documents.
2. Substitute Items:
a. If in City's sole discretion an item of material or equipment proposed by Contractor does
not qualify as an "or -equal" item under Paragraph 6.O5.A.1, it may be submitted as a
proposed substitute item.
b. Contractor shall submit sufficient information as provided below to allow City to
determine if the item of material or equipment proposed is essentially equivalent to that
named and an acceptable substitute therefor. Requests for review of proposed substitute
items of material or equipment will not be accepted by City from anyone other than
Contractor.
c. Contractor shall make written application to City for review of a proposed substitute item
of material or equipment that Contractor seeks to furnish or use. The application shall
comply with Section 01 25 00 and:
1) shall certify that the proposed substitute item will:
a) perform adequately the functions and achieve the results called for by the general
design;
b) be similar in substance to that specified;
c) be suited to the same use as that specified; and
2) will state:
a) the extent, if any, to which the use of the proposed substitute item will prejudice
Contractor's achievement of final completion on time;
b) whether use of the proposed substitute item in the Work will require a change in
any of the Contract Documents (or in the provisions of any other direct contract
with City for other work on the Project) to adapt the design to the proposed
substitute item;
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
venerai Lonamons
Page 23 of 63
c) whether incorporation or use of the proposed substitute item in connection with
the Work is subject to payment of any license fee or royalty; and
3) will identify:
a) all variations of the proposed substitute item from that specified;
b) available engineering, sales, maintenance, repair, and replacement services; and
4) shall contain an itemized estimate of all costs or credits that will result directly or
indirectly from use of such substitute item, including costs of redesign and Damage
Claims of other contractors affected by any resulting change.
B. Substitute Construction Methods or Procedures: If a specific means, method, technique,
sequence, or procedure of construction is expressly required by the Contract Documents,
Contractor may furnish or utilize a substitute means, method, technique, sequence, or procedure
of construction approved by City. Contractor shall submit sufficient information to allow City, in
City's sole discretion, to determine that the substitute proposed is equivalent to that expressly
called for by the Contract Documents. Contractor shall make written application to City for
review in the same manner as those provided in Paragraph 6.05.A.2.
C. City's Evaluation: City will be allowed a reasonable time within which to evaluate each
proposal or submittal made pursuant to Paragraphs 6.05.A and 6.05.B. City may require
Contractor to furnish additional data about the proposed substitute. City will be the sole judge of
acceptability. No "or -equal" or substitute will be ordered, installed or utilized until City's review
is complete, which will be evidenced by a Change Order in the case of a substitute and an
accepted Submittal for an "or -equal." City will advise Contractor in writing of its determination.
D. Special Guarantee: City may require Contractor to furnish at Contractor's expense a special
performance guarantee, warranty, or other surety with respect to any substitute. Contractor shall
indemn and hold harmless City and anyone directly or indirectly employed by them from and
against any and all claims, damages, losses and expenses (including attorneys fees) arising out
of the use of substituted materials or equipment.
E. City's Cost Reimbursement: City will record City's costs in evaluating a substitute proposed or
submitted by Contractor pursuant to Paragraphs 6.05.A.2 and 6.05.B. Whether or not City
approves a substitute so proposed or submitted by Contractor, Contractor may be required to
reimburse City for evaluating each such proposed substitute. Contractor may also be required to
reimburse City for the charges for making changes in the Contract Documents (or in the
provisions of any other direct contract with City) resulting from the acceptance of each proposed
substitute.
F. Contractor's Expense: Contractor shall provide all data in support of any proposed substitute or
"or -equal" at Contractor's expense.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai Lonamons
Page 24 of 63
G. City Substitute Reimbursement: Costs (savings or charges) attributable to acceptance of a
substitute shall be incorporated to the Contract by Change Order.
H. Time Extensions: No additional time will be granted for substitutions.
6.06 Concerning Subcontractors, Suppliers, and Others
A. Contractor shall perform with his own organization, work of a value not less than 35% of the
value embraced on the Contract, unless otherwise approved by the City.
B. Contractor shall not employ any Subcontractor, Supplier, or other individual or entity, whether
initially or as a replacement, against whom City may have reasonable objection. Contractor shall
not be required to employ any Subcontractor, Supplier, or other individual or entity to furnish or
perform any of the Work against whom Contractor has reasonable objection (excluding those
acceptable to City as indicated in Paragraph 6.06.C).
C. The City may from time to time require the use of certain Subcontractors, Suppliers, or other
individuals or entities on the project, and will provide such requirements in the Supplementary
Conditions.
D. Business Diversity Enterprise Ordinance Compliance: It is City policy to ensure the full and
equitable participation by Minority and Small Business Enterprises (MBE)(SBE) in the
procurement of goods and services on a contractual basis. If the Contract Documents provide for
a MBE and/or SBE goal, Contractor is required to comply with the intent of the City's Business
Diversity Ordinance (as amended) by the following:
1. Contractor shall, upon request by the City, provide complete and accurate information
regarding actual work performed by a MBE and/or SBE on the Contract and payment
therefor.
2. Contractor will not make additions, deletions, or substitutions of accepted MBE without
written consent of the City. Any unjustified change or deletion shall be a material breach of
Contract and may result in debarment in accordance with the procedures outlined in the
Ordinance.
3. Contractor shall, upon request by City, allow an audit and/or examination of any books,
records, or files in the possession of the Contractor that will substantiate the actual work
performed by an MBE and/or SBE. Material misrepresentation of any nature may be grounds
for termination of the Contract in accordance with Paragraph 15.02.A. Any such
misrepresentation may be grounds for disqualification of Contractor to bid on future
contracts with the City for a period of not less than three years.
E. Contractor shall be fully responsible to City for all acts and omissions of the Subcontractors,
Suppliers, and other individuals or entities performing or furnishing any of the Work just as
Contractor is responsible for Contractor's own acts and omissions. Nothing in the Contract
Documents:
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai uonanions
Page 25 of 63
1. shall create for the benefit of any such Subcontractor, Supplier, or other individual or entity
any contractual relationship between City and any such Subcontractor, Supplier or other
individual or entity; nor
2. shall create any obligation on the part of City to pay or to see to the payment of any moneys
due any such Subcontractor, Supplier, or other individual or entity except as may otherwise
be required by Laws and Regulations.
F. Contractor shall be solely responsible for scheduling and coordinating the Work of
Subcontractors, Suppliers, and other individuals or entities performing or furnishing any of the
Work under a direct or indirect contract with Contractor.
G. All Subcontractors, Suppliers, and such other individuals or entities performing or furnishing any
of the Work shall communicate with City through Contractor.
H. All Work performed for Contractor by a Subcontractor or Supplier will be pursuant to an
appropriate agreement between Contractor and the Subcontractor or Supplier which specifically
binds the Subcontractor or Supplier to the applicable terms and conditions of the Contract
Documents for the benefit of City.
6.07 Wage Rates
A. Duty to pay Prevailing Wage Rates. The Contractor shall comply with all requirements of
Chapter 2258, Texas Government Code (as amended), including the payment of not less than the
rates determined by the City Council of the City of Fort Worth to be the prevailing wage rates in
accordance with Chapter 2258. Such prevailing wage rates are included in these Contract
Documents.
B. Penalty for Violation. A Contractor or any Subcontractor who does not pay the prevailing wage
shall, upon demand made by the City, pay to the City $60 for each worker employed for each
calendar day or part of the day that the worker is paid less than the prevailing wage rates
stipulated in these contract documents. This penalty shall be retained by the City to offset its
administrative costs, pursuant to Texas Government Code 2258.023.
C. Complaints of Violations and City Determination of Good Cause. On receipt of information,
including a complaint by a worker, concerning an alleged violation of 2258.023, Texas
Government Code, by a Contractor or Subcontractor, the City shall make an initial
determination, before the 31 st day after the date the City receives the information, as to whether
good cause exists to believe that the violation occurred. The City shall notify in writing the
Contractor or Subcontractor and any affected worker of its initial determination. Upon the City's
determination that there is good cause to believe the Contractor or Subcontractor has violated
Chapter 2258, the City shall retain the full amounts claimed by the claimant or claimants as the
difference between wages paid and wages due under the prevailing wage rates, such amounts
being subtracted from successive progress payments pending a final determination of the
violation.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai uonamons
Page 26 of 63
D. Arbitration Required if Violation Not Resolved. An issue relating to an alleged violation of
Section 2258.023, Texas Government Code, including a penalty owed to the City or an affected
worker, shall be submitted to binding arbitration in accordance with the Texas General
Arbitration Act (Article 224 et seq., Revised Statutes) if the Contractor or Subcontractor and any
affected worker does not resolve the issue by agreement before the 15th day after the date the
City makes its initial determination pursuant to Paragraph C above. If the persons required to
arbitrate under this section do not agree on an arbitrator before the 1 lth day after the date that
arbitration is required, a district court shall appoint an arbitrator on the petition of any of the
persons. The City is not a party in the arbitration. The decision and award of the arbitrator is
final and binding on all parties and may be enforced in any court of competent jurisdiction.
E. Records to be Maintained. The Contractor and each Subcontractor shall, for a period of three (3)
years following the date of acceptance of the work, maintain records that show (i) the name and
occupation of each worker employed by the Contractor in the construction of the Work provided
for in this Contract; and (ii) the actual per diem wages paid to each worker. The records shall be
open at all reasonable hours for inspection by the City. The provisions of Paragraph 6.23, Right
to Audit, shall pertain to this inspection.
F. Progress Payments. With each progress payment or payroll period, whichever is less, the
Contractor shall submit an affidavit stating that the Contractor has complied with the
requirements of Chapter 2258, Texas Government Code.
G. Posting of Wage Rates. The Contractor shall post prevailing wage rates in a conspicuous place at
all times.
H. Subcontractor Compliance. The Contractor shall include in its subcontracts and/or shall
otherwise require all of its Subcontractors to comply with Paragraphs A through G above.
6.08 Patent Fees and Royalties
A. Contractor shall pay all license fees and royalties and assume all costs incident to the use in the
performance of the Work or the incorporation in the Work of any invention, design, process,
product, or device which is the subject of patent rights or copyrights held by others. If a
particular invention, design, process, product, or device is specified in the Contract Documents
for use in the performance of the Work and if, to the actual knowledge of City, its use is subject
to patent rights or copyrights calling for the payment of any license fee or royalty to others, the
existence of such rights shall be disclosed by City in the Contract Documents. Failure of the City
to disclose such information does not relieve the Contractor from its obligations to pay for the
use of said fees or royalties to others.
B. To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and hold
harmless City, from and against all claims, costs, losses, and damages (including but not limited
to all fees and charges of engineers, architects, attorneys, and other professionals and all court
or arbitration or other dispute resolution costs) arising out of or relating to any infringement of
patent rights or copyrights incident to the use in the performance of the Work or resulting from
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai Lonunions
Page 27 of 63
the incorporation in the Work of any invention, design, process, product, or device not specified
in the Contract Documents.
6.09 Permits and Utilities
A. Contractor obtained permits and licenses. Contractor shall obtain and pay for all construction
permits and licenses except those provided for in the Supplementary Conditions or Contract
Documents. City shall assist Contractor, when necessary, in obtaining such permits and licenses.
Contractor shall pay all governmental charges and inspection fees necessary for the prosecution
of the Work which are applicable at the time of opening of Bids, or, if there are no Bids, on the
Effective Date of the Agreement, except for permits provided by the City as specified in 6.09.B.
City shall pay all charges of utility owners for connections for providing permanent service to the
Work.
B. City obtained permits and licenses. City will obtain and pay for all permits and licenses as
provided for in the Supplementary Conditions or Contract Documents. It will be the Contractor's
responsibility to carry out the provisions of the permit. If the Contractor initiates changes to the
Contract and the City approves the changes, the Contractor is responsible for obtaining
clearances and coordinating with the appropriate regulatory agency. The City will not reimburse
the Contractor for any cost associated with these requirements of any City acquired. permit. The
following are permits the City will obtain if required:
1. Texas Department of Transportation Permits
2. U.S. Army Corps of Engineers Permits
3. Texas Commission on Environmental Quality Permits
4. Railroad Company Permits
C. Outstanding permits and licenses. The City anticipates acquisition of and/or access to permits
and licenses. Any outstanding permits and licenses are anticipated to be acquired in accordance
with the schedule set forth in the Supplementary Conditions. The Project Schedule submitted by
the Contractor in accordance with the Contract Documents must consider any outstanding
permits and licenses.
6.10 Laws and Regulations
A. Contractor shall give all notices required by and shall comply with all Laws and Regulations
applicable to the performance of the Work. Except where otherwise expressly required by
applicable Laws and Regulations, the City shall not be responsible for monitoring Contractor's
compliance with any Laws or Regulations.
B. If Contractor performs any Work knowing or having reason to know that it is contrary to Laws or
Regulations, Contractor shall bear all claims, costs, losses, and damages (including but not
limited to all fees and charges of engineers, architects, attorneys, and other professionals and all
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai uonmuons
Page 28 of 63
court or arbitration or other dispute resolution costs) arising out of or relating to such Work.
However, it shall not be Contractor's responsibility to make certain that the Specifications and
Drawings are in accordance with Laws and Regulations, but this shall not relieve Contractor of
Contractor's obligations under Paragraph 3.02.
C. Changes in Laws or Regulations not known at the time of opening of Bids having an effect on
the cost or time of performance of the Work may be the subject of an adjustment in Contract
Price or Contract Time.
6.11 Taxes
A. On a contract awarded by the City, an organization which qualifies for exemption pursuant to
Texas Tax Code, Subchapter H, Sections 151.301-335 (as amended), the Contractor may
purchase, rent or lease all materials, supplies and equipment used or consumed in the
performance of this contract by issuing to his supplier an exemption certificate in lieu of the tax,
said exemption certificate to comply with State Comptroller's Ruling .007. Any such exemption
certificate issued to the Contractor in lieu of the tax shall be subject to and shall comply with the
provision of State Comptroller's Ruling .011, and any other applicable rulings pertaining to the
Texas Tax Code, Subchapter H.
B. Texas Tax permits and information may be obtained from:
Comptroller of Public Accounts
Sales Tax Division
Capitol Station
Austin, TX 78711; or
2. htto://www.window.state.tx.us/taxinfo/taxforms/93-forms.html
6.12 Use of Site and Other Areas
A. Limitation on Use of Site and Other Areas:
1. Contractor shall confine construction equipment, the storage of materials and equipment, and
the operations of workers to the Site and other areas permitted by Laws and Regulations, and
shall not unreasonably encumber the Site and other areas with construction equipment or
other materials or equipment. Contractor shall assume full responsibility for any damage to
any such land or area, or to the owner or occupant thereof, or of any adjacent land or areas
resulting from the performance of the Work.
2. At any time when, in the judgment of the City, the Contractor has obstructed or closed or is
carrying on operations in a portion of a street, right-of-way, or easement greater than is
necessary for proper execution of the Work, the City may require the Contractor to finish the
section on which operations are in progress before work is commenced on any additional
area of the Site.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai Lonamons
Page 29 of 63
3. Should any Damage Claim be made by any such owner or occupant because of the
performance of the Work, Contractor shall promptly attempt to resolve the Damage Claim.
4. Pursuant to Paragraph 6.21, Contractor shall indemn and hold harmless City, from and
against all claims, costs, losses, and damages arising out of or relating to any claim or
action, legal or equitable, brought by any such owner or occupant against City.
B. Removal of Debris During Performance of the Work: During the progress of the Work
Contractor shall keep the Site and other areas free from accumulations of waste materials,
rubbish, and other debris. Removal and disposal of such waste materials, rubbish, and other
debris shall conform to applicable Laws and Regulations.
C. Site Maintenance Cleaning: 24 hours after written notice is given to the Contractor that the
clean-up on the job site is proceeding in a manner unsatisfactory to the City, if the Contractor
fails to correct the unsatisfactory procedure, the City may take such direct action as the City
deems appropriate to correct the clean-up deficiencies cited to the Contractor in the written
notice (by letter or electronic communication), and the costs of such direct action, plus 25 % of
such costs, shall be deducted from the monies due or to become due to the Contractor.
D. Final Site Cleaning: Prior to Final Acceptance of the Work Contractor shall clean the Site and
the Work and make it ready for utilization by City or adjacent property owner. At the completion
of the Work Contractor shall remove from the Site all tools, appliances, construction equipment
and machinery, and surplus materials and shall restore to original condition or better all property
disturbed by the Work.
E. Loading Structures: Contractor shall not load nor permit any part of any structure to be loaded
in any manner that will endanger the structure, nor shall Contractor subject any part of the Work
or adjacent property to stresses or pressures that will endanger it.
6.13 Record Documents
A. Contractor shall maintain in a safe place at the Site or in a place designated by the Contractor and
approved by the City, one (1) record copy of all Drawings, Specifications, Addenda, Change
Orders, Field Orders, and written interpretations and clarifications in good order and annotated to
show changes made during construction. These record documents together with all approved
Samples and a counterpart of all accepted Submittals will be available to City for reference.
Upon completion of the Work, these record documents, any operation and maintenance manuals,
and Submittals will be delivered to City prior to Final Inspection. Contractor shall include
accurate locations for buried and imbedded items.
6.14 Safety and Protection
A. Contractor shall be solely responsible for initiating, maintaining and supervising all safety
precautions and programs in connection with the Work. Such responsibility does not relieve
Subcontractors of their responsibility for the safety of persons or property in the performance of
their work, nor for compliance with applicable safety Laws and Regulations. Contractor shall
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai uonawons
Page 30 of 63
take all necessary precautions for the safety of, and shall provide the necessary protection to
prevent damage, injury or loss to:
1. all persons on the Site or who may be affected by the Work;
2. all the Work and materials and equipment to be incorporated therein, whether in storage on
or off the Site; and
3. other property at the Site or adjacent thereto, including trees, shrubs, lawns, walks,
pavements, roadways, structures, utilities, and Underground Facilities not designated for
removal, relocation, or replacement in the course of construction.
B. Contractor shall comply with all applicable Laws and Regulations relating to the safety of
persons or property, or to the protection of persons or property from damage, injury, or loss; and
shall erect and maintain all necessary safeguards for such safety and protection. Contractor shall
notify owners of adjacent property and of Underground Facilities and other utility owners when
prosecution of the Work may affect them, and shall cooperate with them in the protection,
removal, relocation, and replacement of their property.
C. Contractor shall comply with the applicable requirements of City's safety programs, if any.
D. Contractor shall inform City of the specific requirements of Contractor's safety program, if any,
with which City's employees and representatives must comply while at the Site.
E. All damage, injury, or loss to any property referred to in Paragraph 6.14.A.2 or 6.14.A.3 caused,
directly or indirectly, in whole or in part, by Contractor, any Subcontractor, Supplier, or any
other individual or entity directly or indirectly employed by any of them to perform any of the
Work, or anyone for whose acts any of them may be liable, shall be remedied by Contractor.
F. Contractor's duties and responsibilities for safety and for protection of the Work shall continue
until such time as all the Work is completed and City has accepted the Work.
6.15 Safety Representative
Contractor shall inform City in writing of Contractor's designated safety representative at the Site.
6.16 Hazard Communication Programs
Contractor shall be responsible for coordinating any exchange of material safety data sheets or other
hazard communication information required to be made available to or exchanged between or among
employers in accordance with Laws or Regulations.
6.17 Emergencies and/or Rectification
A. In emergencies affecting the safety or protection of persons or the Work or property at the Site or
adjacent thereto, Contractor is obligated to act to prevent threatened damage, injury, or loss.
Contractor shall give City prompt written notice if Contractor believes that any significant
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai Lonamons
Page 31 of 63
changes in the Work or variations from the Contract Documents have been caused thereby or are
required as a result thereof. If City determines that a change in the Contract Documents is
required because of the action taken by Contractor in response to such an emergency, a Change
Order may be issued.
B. Should the Contractor fail to respond to a request from the City to rectify any discrepancies,
omissions, or correction necessary to conform with the requirements of the Contract Documents,
the City shall give the Contractor written notice that such work or changes are to be performed.
The written notice shall direct attention to the discrepant condition and request the Contractor to
take remedial action to correct the condition. In the event the Contractor does not take positive
steps to fulfill this written request, or does not show just cause for not taking the proper action,
within 24 hours, the City may take such remedial action with City forces or by contract. The City
shall deduct an amount equal to the entire costs for such remedial action, plus 25%, from any
funds due or become due the Contractor on the Project.
6.18 Submittals
A. Contractor shall submit required Submittals to City for review and acceptance in accordance
with the accepted Schedule of Submittals (as required by Paragraph 2.07). Each submittal will be
identified as City may require.
1. Submit number of copies specified in the General Requirements.
2. Data shown on the Submittals will be complete with respect to quantities, dimensions,
specified performance and design criteria, materials, and similar data to show City the
services, materials, and equipment Contractor proposes to provide and to enable City to
review the information for the limited purposes required by Paragraph 6.18.C.
3. Submittals submitted as herein provided by Contractor and reviewed by City for
conformance with the design concept shall be executed in conformity with the Contract
Documents unless otherwise required by City.
4. When Submittals are submitted for the purpose of showing the installation in greater detail,
their review shall not excuse Contractor from requirements shown on the Drawings and
Specifications.
5. For -Information -Only submittals upon which the City is not expected to conduct review or
take responsive action may be so identified in the Contract Documents.
6. Submit required number of Samples specified in the Specifications.
7. Clearly identify each Sample as to material, Supplier, pertinent data such as catalog numbers,
the use for which intended and other data as City may require to enable City to review the
submittal for the limited purposes required by Paragraph 6.18.C.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai Lonamons
Page 32 of 63
B. Where a Submittal is required by the Contract Documents or the Schedule of Submittals, any
related Work performed prior to City's review and acceptance of the pertinent submittal will be
at the sole expense and responsibility of Contractor.
C. City's Review:
1. City will provide timely review of required Submittals in accordance with the Schedule of
Submittals acceptable to City. City's review and acceptance will be only to determine if the
items covered by the submittals will, after installation or incorporation in the Work, conform
to the information given in the Contract Documents and be compatible with the design
concept of the completed Project as a functioning whole as indicated by the Contract
Documents.
2. City's review and acceptance will not extend to means, methods, techniques, sequences, or
procedures of construction (except where a particular means, method, technique, sequence,
or procedure of construction is specifically and expressly called for by the Contract
Documents) or to safety precautions or programs incident thereto. The review and acceptance
of a separate item as such will not indicate approval of the assembly in which the item
functions.
3. City's review and acceptance shall not relieve Contractor from responsibility for any
variation from the requirements of the Contract Documents unless Contractor has complied
with the requirements of Section 01 33 00 and City has given written acceptance of each
such variation by specific written notation thereof incorporated in or accompanying the
Submittal. City's review and acceptance shall not relieve Contractor from responsibility for
complying with the requirements of the Contract Documents.
6.19 Continuing the Work
Except as otherwise provided, Contractor shall carry on the Work and adhere to the Project Schedule
during all disputes or disagreements with City. No Work shall be delayed or postponed pending
resolution of any disputes or disagreements, except as City and Contractor may otherwise agree in
writing.
6.20 Contractor 's General Warranty and Guarantee
A. Contractor warrants and guarantees to City that all Work will be in accordance with the Contract
Documents and will not be defective. City and its officers, directors, members, partners,
employees, agents, consultants, and subcontractors shall be entitled to rely on representation of
Contractor's warranty and guarantee.
B. Contractor's warranty and guarantee hereunder excludes defects or damage caused by:
1. abuse, modification, or improper maintenance or operation by persons other than Contractor,
Subcontractors, Suppliers, or any other individual or entity for whom Contractor is
responsible; or
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai Lonaiuons
Page 33 of 63
2. normal wear and tear under normal usage.
C. Contractor's obligation to perform and complete the Work in accordance with the Contract
Documents shall be absolute. None of the following will constitute an acceptance of Work that is
not in accordance with the Contract Documents or a release of Contractor's obligation to perform
the Work in accordance with the Contract Documents:
1. observations by City;
2. recommendation or payment by City of any progress or final payment;
3. the issuance of a certificate of Final Acceptance by City or any payment related thereto by
City;
4. use or occupancy of the Work or any part thereof by City;
5. any review and acceptance of a Submittal by City;
6. any inspection, test, or approval by others; or
7. any correction of defective Work by City.
D. The Contractor shall remedy any defects or damages in the Work and pay for any damage to
other work or property resulting therefrom which shall appear within a period of two (2) years
from the date of Final Acceptance of the Work unless a longer period is specified and shall
furnish a good and sufficient maintenance bond, complying with the requirements of Article
5.02.B. The City will give notice of observed defects with reasonable promptness.
6.21 Indemnification
A. Contractor covenants and agrees to indemnify, hold harmless and defend, at its own
expense, the City, its officers, servants and employees, from and against any and all claims
arising out of, or alleged to arise out of, the work and services to be performed by the
Contractor, its officers, agents, employees, subcontractors, licenses or invitees under this
Contract. THIS INDEMNIFICATION PROVISION IS SPECIFICALLY INTENDED TO
OPERATE AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR PROVEN THAT ALL
OR SOME OF THE DAMAGES BEING SOUGHT WERE CAUSED. IN WHOLE OR IN
PART. BY ANY ACT. OMISSION OR NEGLIGENCE OF THE CITY. This indemnity
provision is intended to include, without limitation, indemnity for costs, expenses and legal
fees incurred by the City in defending against such claims and causes of actions.
B. Contractor covenants and agrees to indemnify and hold harmless, at its own expense, the
City, its officers, servants and employees, from and against any and all loss, damage or
destruction of property of the City, arising out of, or alleged to arise out of, the work and
services to be performed by the Contractor, its officers, agents, employees, subcontractors,
licensees or invitees under this Contract. THIS INDEMNIFICATION PROVISION IS
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai Lonamons
Page 34 of 63
SPECIFICALLY INTENDED TO OPERATE AND BE EFFECTIVE EVEN IF IT IS
ALLEGED OR PROVEN THAT ALL OR SOME OF THE DAMAGES BEING SOUGHT
WERE CAUSED. IN WHOLE OR IN PART. BY ANY ACT. OMISSION OR
NEGLIGENCE OF THE CITY.
6.22 Delegation of Professional Design Services
A. Contractor will not be required to provide professional design services unless such services are
specifically required by the Contract Documents for a portion of the Work or unless such
services are required to carry out Contractor's responsibilities for construction means, methods,
techniques, sequences and procedures.
B. If professional design services or certifications by a design professional related to systems,
materials or equipment are specifically required of Contractor by the Contract Documents, City
will specify all performance and design criteria that such services must satisfy. Contractor shall
cause such services or certifications to be provided by a properly licensed professional, whose
signature and seal shall appear on all drawings, calculations, specifications, certifications, and
Submittals prepared by such professional. Submittals related to the Work designed or certified by
such professional, if prepared by others, shall bear such professional's written approval when
submitted to City.
C. City shall be entitled to rely upon the adequacy, accuracy and completeness of the services,
certifications or approvals performed by such design professionals, provided City has specified
to Contractor performance and design criteria that such services must satisfy.
D. Pursuant to this Paragraph 6.22, City's review and acceptance of design calculations and design
drawings will be only for the limited purpose of checking for conformance with performance and
design criteria given and the design concept expressed in the Contract Documents. City's review
and acceptance of Submittals (except design calculations and design drawings) will be only for
the purpose stated in Paragraph 6.18.C.
6.23 Right to Audit
A. The Contractor agrees that the City shall, until the expiration of three (3) years after final
payment under this Contract, have access to and the right to examine and photocopy any directly
pertinent books, documents, papers, and records of the Contractor involving transactions relating
to this Contract. Contractor agrees that the City shall have access during Regular Working Hours
to all necessary Contractor facilities and shall be provided adequate and appropriate work space
in order to conduct audits in compliance with the provisions of this Paragraph. The City shall
give Contractor reasonable advance notice of intended audits.
B. Contractor further agrees to include in all its subcontracts hereunder a provision to the effect that
the subcontractor agrees that the City shall, until the expiration of three (3) years after final
payment under this Contract, have access to and the right to examine and photocopy any directly
pertinent books, documents, papers, and records of such Subcontractor, involving transactions to
the subcontract, and further, that City shall have access during Regular Working Hours to all
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai commons
Page 35 of 63
Subcontractor facilities, and shall be provided adequate and appropriate work space in order to
conduct audits in compliance with the provisions of this Paragraph. The City shall give
Subcontractor reasonable advance notice of intended audits.
C. Contractor and Subcontractor agree to photocopy such documents as may be requested by the
City. The City agrees to reimburse Contractor for the cost of the copies as follows at the rate
published in the Texas Administrative Code in effect as of the time copying is performed.
6.24 Nondiscrimination
A. The City is responsible for operating Public Transportation Programs and implementing transit -
related projects, which are funded in part with Federal financial assistance awarded by the U.S.
Department of Transportation and the Federal Transit Administration (FTA), without
discriminating against any person in the United States on the basis of race, color, or national
origin.
B. Title VI, Civil Rights Act of 1964 as amended.: Contractor shall comply with the requirements of
the Act and the Regulations as further defined in the Supplementary Conditions for any project
receiving Federal assistance.
ARTICLE 7 — OTHER WORK AT THE SITE
7.01 Related Work at Site
A. City may perform other work related to the Project at the Site with City's employees, or other
City contractors, or through other direct contracts therefor, or have other work perfouned by
utility owners. If such other work is not noted in the Contract Documents, then written notice
thereof will be given to Contractor prior to starting any such other work; and
B. Contractor shall afford each other contractor who is a party to such a direct contract, each utility
owner, and City, if City is performing other work with City's employees or other City
contractors, proper and safe access to the Site, provide a reasonable opportunity for the
introduction and storage of materials and equipment and the execution of such other work, and
properly coordinate the Work with theirs. Contractor shall do all cutting, fitting, and patching of
the Work that may be required to properly connect or otherwise make its several parts come
together and properly integrate with such other work. Contractor shall not endanger any work of
others by cutting, excavating, or otherwise altering such work; provided, however, that
Contractor may cut or alter others' work with the written consent of City and the others whose
work will be affected.
C. If the proper execution or results of any part of Contractor's Work depends upon work performed
by others under this Article 7, Contractor shall inspect such other work and promptly report to
City in writing any delays, defects, or deficiencies in such other work that render it unavailable
or unsuitable for the proper execution and results of Contractor's Work. Contractor's failure to so
report will constitute an acceptance of such other work as fit and proper for integration with
Contractor's Work except for latent defects in the work provided by others.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai Lonunions
Page 36 of 63
7.02 Coordination
A. If City intends to contract with others for the performance of other work on the Project at the
Site, the following will be set forth in Supplementary Conditions:
1. the individual or entity who will have authority and responsibility for coordination of the
activities among the various contractors will be identified;
2. the specific matters to be covered by such authority and responsibility will be itemized; and
3. the extent of such authority and responsibilities will be provided.
B. Unless otherwise provided in the Supplementary Conditions, City shall have authority for such
coordination.
ARTICLE 8 — CITY'S RESPONSIBILITIES
8.01 Communications to Contractor
Except as otherwise provided in the Supplementary Conditions, City shall issue all communications
to Contractor.
8.02 Furnish Data
City shall timely furnish the data required under the Contract Documents.
8.03 Pay When Due
City shall make payments to Contractor in accordance with Article 14.
8.04 Lands and Easements; Reports and Tests
City's duties with respect to providing lands and easements and providing engineering surveys to
establish reference points are set forth in Paragraphs 4.01 and 4.05. Paragraph 4.02 refers to City's
identifying and making available to Contractor copies of reports of explorations and tests of
subsurface conditions and drawings of physical conditions relating to existing surface or subsurface
structures at or contiguous to the Site that have been utilized by City in preparing the Contract
Documents.
8.05 Change Orders
City shall execute Change Orders in accordance with Paragraph 10.03.
8.06 Inspections, Tests, and Approvals
City's responsibility with respect to certain inspections, tests, and approvals is set forth in Paragraph
13.03.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai Lonmuons
Page 37 of 63
8.07 Limitations on City's Responsibilities
A. The City shall not supervise, direct, or have control or authority over, nor be responsible for,
Contractor's means, methods, techniques, sequences, or procedures of construction, or the safety
precautions and programs incident thereto, or for any failure of Contractor to comply with Laws
and Regulations applicable to the performance of the Work. City will not be responsible for
Contractor's failure to perform the Work in accordance with the Contract Documents.
B. City will notify the Contractor of applicable safety plans pursuant to Paragraph 6.14.
8.08 Undisclosed Hazardous Environmental Condition
City's responsibility with respect to an undisclosed Hazardous Environmental Condition is set forth
in Paragraph 4.06.
8.09 Compliance with Safety Program
While at the Site, City's employees and representatives shall comply with the specific applicable
requirements of Contractor's safety programs of which City has been informed pursuant to
Paragraph 6.14.
ARTICLE 9 — CITY'S OBSERVATION STATUS DURING CONSTRUCTION
9.01 City's Project Representative
City will provide one or more Project Representative(s) during the construction period. The duties
and responsibilities and the limitations of authority of City's representative during construction are
set forth in the Contract Documents. The Project Representative(s) will be as provided in the
Supplementary Conditions.
9.02 Visits to Site
A. City's Project Representative will make visits to the Site at intervals appropriate to the various
stages of construction as City deems necessary in order to observe the progress that has been
made and the quality of the various aspects of Contractor's executed Work. Based on
information obtained during such visits and observations, City's Project Representative will
determine, in general, if the Work is proceeding in accordance with the Contract Documents.
City's Project Representative will not be required to make exhaustive or continuous inspections
on the Site to check the quality or quantity of the Work. City's Project Representative's efforts
will be directed toward providing City a greater degree of confidence that the completed Work
will conform generally to the Contract Documents.
B. City's Project Representative's visits and observations are subject to all the limitations on
authority and responsibility in the Contract Documents including those set forth in Paragraph
8.07.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai Lommtiais
Page 38 of 63
9.03 Authorized Variations in Work
City's Project Representative may authorize minor variations in the Work from the requirements of
the Contract Documents which do not involve an adjustment in the Contract Price or the Contract
Time and are compatible with the design concept of the completed Project as a functioning whole as
indicated by the Contract Documents. These may be accomplished by a Field Order and will be
binding on City and also on Contractor, who shall perform the Work involved promptly.
9.04 Rejecting Defective Work
City will have authority to reject Work which City's Project Representative believes to be defective,
or will not produce a completed Project that conforms to the Contract Documents or that will
prejudice the integrity of the design concept of the completed Project as a functioning whole as
indicated by the Contract Documents. City will have authority to conduct special inspection or
testing of the Work as provided in Article 13, whether or not the Work is fabricated, installed, or
completed.
9.05 Determinations for Work Performed
Contractor will determine the actual quantities and classifications of Work performed. City's Project
Representative will review with Contractor the preliminary determinations on such matters before
rendering a written recommendation. City's written decision will be final (except as modified to
reflect changed factual conditions or more accurate data).
9.06 Decisions on Requirements of Contract Documents and Acceptability of Work
A. City will be the initial interpreter of the requirements of the Contract Documents and judge of the
acceptability of the Work thereunder.
B. City will render a written decision on any issue referred.
C. City's written decision on the issue referred will be final and binding on the Contractor, subject
to the provisions of Paragraph 10.06.
ARTICLE 10 — CHANGES IN THE WORK; CLAIMS; EXTRA WORK
10.01 Authorized Changes in the Work
A. Without invalidating the Contract and without notice to any surety, City may, at any time or from
time to time, order Extra Work. Upon notice of such Extra Work, Contractor shall promptly
proceed with the Work involved which will be performed under the applicable conditions of the
Contract Documents (except as otherwise specifically provided). Extra Work shall be
memorialized by a Change Order which may or may not precede an order of Extra work.
B. For minor changes of Work not requiring changes to Contract Time or Contract Price, a Field
Order may be issued by the City.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai uonanions
Page 39 of 63
10.02 Unauthorized Changes in the Work
Contractor shall not be entitled to an increase in the Contract Price or an extension of the Contract
Time with respect to any work performed that is not required by the Contract Documents as
amended, modified, or supplemented as provided in Paragraph 3.04, except in the case of an
emergency as provided in Paragraph 6.17.
10.03 Execution of Change Orders
A. City and Contractor shall execute appropriate Change Orders covering:
1. changes in the Work which are: (i) ordered by City pursuant to Paragraph 10.01.A, (ii)
required because of acceptance of defective Work under Paragraph 13.08 or City's correction
of defective Work under Paragraph 13.09, or (iii) agreed to by the parties;
2. changes in the Contract Price or Contract Time which are agreed to by the parties, including
any undisputed sum or amount of time for Work actually performed.
10.04 Extra Work
A. Should a difference arise as to what does or does not constitute Extra Work, or as to the payment
thereof, and the City insists upon its performance, the Contractor shall proceed with the work
after making written request for written orders and shall keep accurate account of the actual
reasonable cost thereof. Contract Claims regarding Extra Work shall be made pursuant to
Paragraph 10.06.
B. The Contractor shall furnish the City such installation records of all deviations from the original
Contract Documents as may be necessary to enable the City to prepare for permanent record a
corrected set of plans showing the actual installation.
C. The compensation agreed upon for Extra Work whether or not initiated by a Change Order shall
be a full, complete and final payment for all costs Contractor incurs as a result or relating to the
change or Extra Work, whether said costs are known, unknown, foreseen or unforeseen at that
time, including without limitation, any costs for delay, extended overhead, ripple or impact cost,
or any other effect on changed or unchanged work as a result of the change or Extra Work.
10.05 Notification to Surety
If the provisions of any bond require notice to be given to a surety of any change affecting the
general scope of the Work or the provisions of the Contract Documents (including, but not limited
to, Contract Price or Contract Time), the giving of any such notice will be Contractor's
responsibility. The amount of each applicable bond will be adjusted by the Contractor to reflect the
effect of any such change.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai Lonamons
Page 40 of 63
10.06 Contract Claims Process
A. City's Decision Required: All Contract Claims, except those waived pursuant to Paragraph
14.09, shall be referred to the City for decision. A decision by City shall be required as a
condition precedent to any exercise by Contractor of any rights or remedies he may otherwise
have under the Contract Documents or by Laws and Regulations in respect of such Contract
Claims.
B. Notice:
1. Written notice stating the general nature of each Contract Claim shall be delivered by the
Contractor to City no later than 15 days after the start of the event giving rise thereto. The
responsibility to substantiate a Contract Claim shall rest with the party making the Contract
Claim.
2. Notice of the amount or extent of the Contract Claim, with supporting data shall be delivered
to the City on or before 45 days from the start of the event giving rise thereto (unless the City
allows additional time for Contractor to submit additional or more accurate data in support of
such Contract Claim).
3. A Contract Claim for an adjustment in Contract Price shall be prepared in accordance with
the provisions of Paragraph 12.01.
4. A Contract Claim for an adjustment in Contract Time shall be prepared in accordance with
the provisions of Paragraph 12.02.
5. Each Contract Claim shall be accompanied by Contractor's written statement that the
adjustment claimed is the entire adjustment to which the Contractor believes it is entitled as a
result of said event.
6. The City shall submit any response to the Contractor within 30 days after receipt of the
claimant's last submittal (unless Contract allows additional time).
C. City's Action: City will review each Contract Claim and, within 30 days after receipt of the last
submittal of the Contractor, if any, take one of the following actions in writing:
1. deny the Contract Claim in whole or in part;
2. approve the Contract Claim; or
3. notify the Contractor that the City is unable to resolve the Contract Claim if in the City's
sole discretion, it would be inappropriate for the City to do so. For purposes of further
resolution of the Contract Claim, such notice shall be deemed a denial.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai Lonmuons
Page 41 of 63
D. City's written action under Paragraph 10.06.0 will be final and binding, unless City or
Contractor invoke the dispute resolution procedure set forth in Article 16 within 30 days of such
action or denial.
E. No Contract Claim for an adjustment in Contract Price or Contract Time will be valid if not
submitted in accordance with this Paragraph 10.06.
ARTICLE 11— COST OF THE WORK; ALLOWANCES; UNIT PRICE WORK; PLANS
QUANTITY MEASUREMENT
11.01 Cost of the Work
A. Costs Included: The term Cost of the Work means the sum of all costs, except those excluded in
Paragraph 11.01.B, necessarily incurred and paid by Contractor in the proper performance of the
Work. When the value of any Work covered by a Change Order, the costs to be reimbursed to
Contractor will be only those additional or incremental costs required because of the change in
the Work. Such costs shall not include any of the costs itemized in Paragraph 11.01.B, and shall
include but not be limited to the following items:
1. Payroll costs for employees in the direct employ of Contractor in the performance of the
Work under schedules of job classifications agreed upon by City and Contractor. Such
employees shall include, without limitation, superintendents, foremen, and other personnel
employed full time on the Work. Payroll costs for employees not employed full time on the
Work shall be apportioned on the basis of their time spent on the Work. Payroll costs shall
include;
a. salaries with a 55% markup, or
b. salaries and wages plus the cost of fringe benefits, which shall include social security
contributions, unemployment, excise, and payroll taxes, workers' compensation, health
and retirement benefits, bonuses, sick leave, vacation and holiday pay applicable thereto.
The expenses of performing Work outside of Regular Working Hours, Weekend
Working Hours, or legal holidays, shall be included in the above to the extent authorized
by City.
2. Cost of all materials and equipment furnished and incorporated in the Work, including costs
of transportation and storage thereof, and Suppliers' field services required in connection
therewith.
3. Rentals of all construction equipment and machinery, and the parts thereof whether rented
from Contractor or others in accordance with rental agreements approved by City, and the
costs of transportation, loading, unloading, assembly, dismantling, and removal thereof. All
such costs shall be in accordance with the terms of said rental agreements. The rental of any
such equipment, machinery, or parts shall cease when the use thereof is no longer necessary
for the Work.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai uonanions
Page 42 of 63
4. Payments made by Contractor to Subcontractors for Work performed by Subcontractors. If
required by City, Contractor shall obtain competitive bids from subcontractors acceptable to
City and Contractor and shall deliver such bids to City, who will then determine, which bids,
if any, will be acceptable. If any subcontract provides that the Subcontractor is to be paid on
the basis of Cost of the Work plus a fee, the Subcontractor's Cost of the Work and fee shall
be determined in the same manner as Contractor's Cost of the Work and fee as provided in
this Paragraph 11.01.
5. Costs of special consultants (including but not limited to engineers, architects, testing
laboratories, surveyors, attorneys, and accountants) employed for services specifically related
to the Work.
6. Supplemental costs including the following:
a. The proportion of necessary transportation, travel, and subsistence expenses of
Contractor's employees incurred in discharge of duties connected with the Work.
b. Cost, including transportation and maintenance, of all materials, supplies, equipment,
machinery, appliances, office, and temporary facilities at the Site, and hand tools not
owned by the workers, which are consumed in the performance of the Work, and cost,
less market value, of such items used but not consumed which remain the property of
Contractor.
c. Sales, consumer, use, and other similar taxes related to the Work, and for which
Contractor is liable not covered under Paragraph 6.11, as imposed by Laws and
Regulations.
d. Deposits lost for causes other than negligence of Contractor, any Subcontractor, or
anyone directly or indirectly employed by any of them or for whose acts any of them may
be liable, and royalty payments and fees for permits and licenses.
e. Losses and damages (and related expenses) caused by damage to the Work, not
compensated by insurance or otherwise, sustained by Contractor in connection with the
performance of the Work, provided such losses and damages have resulted from causes
other than the negligence of Contractor, any Subcontractor, or anyone directly or
indirectly employed by any of them or for whose acts any of them may be liable. Such
losses shall include settlements made with the written consent and approval of City. No
such losses, damages, and expenses shall be included in the Cost of the Work for the
purpose of determining Contractor's fee.
f. The cost of utilities, fuel, and sanitary facilities at the Site.
g.
Minor expenses such as telegrams, long distance telephone calls, telephone and
communication services at the Site, express and courier services, and similar petty cash
items in connection with the Work.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerat Lonantons
Page 43 of 63
h. The costs of premiums for all bonds and insurance Contractor is required by the Contract
Documents to purchase and maintain.
B. Costs Excluded: The term Cost of the Work shall not include any of the following items:
1. Payroll costs and other compensation of Contractor's officers, executives, principals (of
partnerships and sole proprietorships), general managers, safety managers, engineers,
architects, estimators, attorneys, auditors, accountants, purchasing and contracting agents,
expediters, timekeepers, clerks, and other personnel employed by Contractor, whether at the
Site or in Contractor's principal or branch office for general administration of the Work and
not specifically included in the agreed upon schedule of job classifications referred to in
Paragraph 11.01.A.1 or specifically covered by Paragraph 11.01.A.4, all of which are to be
considered administrative costs covered by the Contractor's fee.
2. Expenses of Contractor's principal and branch offices other than Contractor's office at the
Site.
3. Any part of Contractor's capital expenses, including interest on Contractor's capital
employed for the Work and charges against Contractor for delinquent payments.
4. Costs due to the negligence of Contractor, any Subcontractor, or anyone directly or indirectly
employed by any of them or for whose acts any of them may be liable, including but not
limited to, the correction of defective Work, disposal of materials or equipment wrongly
supplied, and making good any damage to property.
5. Other overhead or general expense costs of any kind.
C. Contractor's Fee: When all the Work is performed on the basis of cost-plus, Contractor's fee
shall be determined as set forth in the Agreement. When the value of any Work covered by a
Change Order for an adjustment in Contract Price is determined on the basis of Cost of the
Work, Contractor's fee shall be determined as set forth in Paragraph 12.01.C.
D. Documentation: Whenever the Cost of the Work for any purpose is to be determined pursuant to
Paragraphs 11.01.A and 11.01.B, Contractor will establish and maintain records thereof in
accordance with generally accepted accounting practices and submit in a form acceptable to City
an itemized cost breakdown together with supporting data.
11.02 Allowances
A. Specified Allowance: It is understood that Contractor has included in the Contract Price all
allowances so named in the Contract Documents and shall cause the Work so covered to be
performed for such sums and by such persons or entities as may be acceptable to City.
B. Pre -bid Allowances:
1. Contractor agrees that:
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
venerai Lonamons
Page 44 of 63
a. the pre -bid allowances include the cost to Contractor of materials and equipment required
by the allowances to be delivered at the Site, and all applicable taxes; and
b. Contractor's costs for unloading and handling on the Site, labor, installation, overhead,
profit, and other expenses contemplated for the pre -bid allowances have been included in
the allowances, and no demand for additional payment on account of any of the
foregoing will be valid.
C. Contingency Allowance: Contractor agrees that a contingency allowance, if any, is for the sole
use of City.
D. Prior to final payment, an appropriate Change Order will be issued to reflect actual amounts due
Contractor on account of Work covered by allowances, and the Contract Price shall be
correspondingly adjusted.
11.03 Unit Price Work
A. Where the Contract Documents provide that all or part of the Work is to be Unit Price Work,
initially the Contract Price will be deemed to include for all Unit Price Work an amount equal to
the sum of the unit price for each separately identified item of Unit Price Work times the
estimated quantity of each item as indicated in the Agreement.
B. The estimated quantities of items of Unit Price Work are not guaranteed and are solely for the
purpose of comparison of Bids and determining an initial Contract Price. Determinations of the
actual quantities and classifications of Unit Price Work performed by Contractor will be made by
City subject to the provisions of Paragraph 9.05.
C. Each unit price will be deemed to include an amount considered by Contractor to be adequate to
cover Contractor's overhead and profit for each separately identified item. Work described in the
Contract Documents, or reasonably inferred as required for a functionally complete installation,
but not identified in the listing of unit price items shall be considered incidental to unit price
work listed and the cost of incidental work included as part of the unit price.
D. City may make an adjustment in the Contract Price in accordance with Paragraph 12.01 if:
1. the quantity of any item of Unit Price Work performed by Contractor differs materially and
significantly from the estimated quantity of such item indicated in the Agreement; and
2. there is no corresponding adjustment with respect to any other item of Work.
E. Increased or Decreased Quantities: The City reserves the right to order Extra Work in
accordance with Paragraph 10.01.
. If the changes in quantities or the alterations do not significantly change the character of
work under the Contract Documents, the altered work will be paid for at the Contract unit
price.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
Jenerai Lonamons
Page 45 of 63
2. If the changes in quantities or alterations significantly change the character of work, the
Contract will be amended by a Change Order.
3. If no unit prices exist, this will be considered Extra Work and the Contract will be amended
by a Change Order in accordance with Article 12.
4. A significant change in the character of work occurs when:
a. the character of work for any Item as altered differs materially in kind or nature from that
in the Contract or
b. a Major Item of work varies by more than 25% from the original Contract quantity.
5. When the quantity of work to be done under any Major Item of the Contract is more than
125% of the original quantity stated in the Contract, then either party to the Contract may
request an adjustment to the unit price on the portion of the work that is above 125%.
6. When the quantity of work to be done under any Major Item of the Contract is less than 75%
of the original quantity stated in the Contract, then either party to the Contract may request
an adjustment to the unit price.
11.04 Plans Quantity Measurement
A. Plans quantities may or may not represent the exact quantity of work performed or material
moved, handled, or placed during the execution of the Contract. The estimated bid quantities are
designated as final payment quantities, unless revised by the governing Section or this Article.
B. If the quantity measured as outlined under "Price and Payment Procedures" varies by more than
25% (or as stipulated under "Price and Payment Procedures" for specific Items) from the total
estimated quantity for an individual Item originally shown in the Contract Documents, an
adjustment may be made to the quantity of authorized work done for payment purposes. The
party to the Contract requesting the adjustment will provide field measurements and calculations
showing the final quantity for which payment will be made. Payment for revised quantity will be
made at the unit price bid for that Item, except as provided for in Article 10.
C. When quantities are revised by a change in design approved by the City, by Change Order, or to
correct an error, or to correct an error on the plans, the plans quantity will be increased or
decreased by the amount involved in the change, and the 25% variance will apply to the new
plans quantity.
D. If the total Contract quantity multiplied by the unit price bid for an individual Item is less than
$250 and the Item is not originally a plans quantity Item, then the Item may be paid as a plans
quantity Item if the City and Contractor agree in writing to fix the final quantity as a plans
quantity.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai Lonaiuons
Page 46 of 63
E. For callout work or non -site specific Contracts, the plans quantity measurement requirements are
not applicable.
ARTICLE 12 — CHANGE OF CONTRACT PRICE; CHANGE OF CONTRACT TIME
12.01 Change of Contract Price
A. The Contract Price may only be changed by a Change Order.
B. The value of any Work covered by a Change Order will be determined as follows:
1. where the Work involved is covered by unit prices contained in the Contract Documents, by
application of such unit prices to the quantities of the items involved (subject to the
provisions of Paragraph 11.03); or
2. where the Work involved is not covered by unit prices contained in the Contract Documents,
by a mutually agreed lump sum or unit price (which may include an allowance for overhead
and profit not necessarily in accordance with Paragraph 12.01.C.2), and shall include the cost
of any secondary impacts that are foreseeable at the time of pricing the cost of Extra Work;
or
3. where the Work involved is not covered by unit prices contained in the Contract Documents
and agreement to a lump sum or unit price is not reached under Paragraph 12.01.B.2, on the
basis of the Cost of the Work (determined as provided in Paragraph 11.01) plus a
Contractor's fee for overhead and profit (determined as provided in Paragraph 12.01.C).
C. Contractor's Fee: The Contractor's additional fee for overhead and profit shall be determined as
follows:
1. a mutually acceptable fixed fee; or
2. if a fixed fee is not agreed upon, then a fee based on the following percentages of the various
portions of the Cost of the Work:
a. for costs incurred under Paragraphs 11.01.A.1, 11.01.A.2. and 11.01.A.3, the
Contractor's additional fee shall be 15 percent except for:
1) rental fees for Contractor's own equipment using standard rental rates;
2) bonds and insurance;
b. for costs incurred under Paragraph 11.01.A.4 and 11.01.A.5, the Contractor's fee shall be
five percent (5%);
1) where one or more tiers of subcontracts are on the basis of Cost of the Work plus a
fee and no fixed fee is agreed upon, the intent of Paragraphs 12.01.C.2.a and
12.01.C.2.b is that the Subcontractor who actually performs the Work, at whatever
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
venerai Lommnions
Page 47 of 63
tier, will be paid a fee of 15 percent of the costs incurred by such Subcontractor under
Paragraphs 11.01.A.1 and 11.01.A.2 and that any higher tier Subcontractor and
Contractor will each be paid a fee of five percent (5%) of the amount paid to the next
lower tier Subcontractor, however in no case shall the cumulative total of fees paid be
in excess of 25%;
c. no fee shall be payable on the basis of costs itemized under Paragraphs 11.01.A.6, and
11.01.B;
d. the amount of credit to be allowed by Contractor to City for any change which results in
a net decrease in cost will be the amount of the actual net decrease in cost plus a
deduction in Contractor's fee by an amount equal to five percent (5%) of such net
decrease.
12.02 Change of Contract Time
A. The Contract Time may only be changed by a Change Order.
B. No extension of the Contract Time will be allowed for Extra Work or for claimed delay unless
the Extra Work contemplated or claimed delay is shown to be on the critical path of the Project
Schedule or Contractor can show by Critical Path Method analysis how the Extra Work or
claimed delay adversely affects the critical path.
12.03 Delays
A. Where Contractor is reasonably delayed in the performance or completion of any part of the
Work within the Contract Time due to delay beyond the control of Contractor, the Contract Time
may be extended in an amount equal to the time lost due to such delay if a Contract Claim is
made therefor. Delays beyond the control of Contractor shall include, but not be limited to, acts
or neglect by City, acts or neglect of utility owners or other contractors performing other work as
contemplated by Article 7, fires, floods, epidemics, abnormal weather conditions, or acts of God.
Such an adjustment shall be Contractor's sole and exclusive remedy for the delays described in
this Paragraph.
B. If Contractor is delayed, City shall not be liable to Contractor for any claims, costs, losses, or
damages (including but not limited to all fees and charges of engineers, architects, attorneys, and
other professionals and all court or arbitration or other dispute resolution costs) sustained by
Contractor on or in connection with any other project or anticipated project.
C. Contractor shall not be entitled to an adjustment in Contract Price or Contract Time for delays
within the control of Contractor. Delays attributable to and within the control of a Subcontractor
or Supplier shall be deemed to be delays within the control of Contractor.
D. The Contractor shall receive no compensation for delays or hindrances to the Work, except when
direct and unavoidable extra cost to the Contractor is caused by the failure of the City to provide
information or material, if any, which is to be furnished by the City.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
venerai Lonanions
Page 48 of 63
ARTICLE 13 — TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF
DEFECTIVE WORK
13.01 Notice of Defects
Notice of all defective Work of which City has actual knowledge will be given to Contractor.
Defective Work may be rejected, corrected, or accepted as provided in this Article 13.
13.02 Access to Work
City, independent testing laboratories, and governmental agencies with jurisdictional interests will
have access to the Site and the Work at reasonable times for their observation, inspection, and
testing. Contractor shall provide them proper and safe conditions for such access and advise them of
Contractor's safety procedures and programs so that they may comply therewith as applicable.
13.03 Tests and Inspections
A. Contractor shall give City timely notice of readiness of the Work for all required inspections,
tests, or approvals and shall cooperate with inspection and testing personnel to facilitate required
inspections or tests.
B. If Contract Documents, Laws or Regulations of any public body having jurisdiction require any
of the Work (or part thereof) to be inspected, tested, or approved, Contractor shall assume full
responsibility for arranging and obtaining such independent inspections, tests, retests or
approvals, pay all costs in connection therewith, and furnish City the required certificates of
inspection or approval; excepting, however, those fees specifically identified in the
Supplementary Conditions or any Texas Department of Licensure and Regulation (TDLR)
inspections, which shall be paid as described in the Supplementary Conditions.
C. Contractor shall be responsible for arranging and obtaining and shall pay all costs in connection
with any inspections, tests, re -tests, or approvals required for City's acceptance of materials or
equipment to be incorporated in the Work; or acceptance of materials, mix designs, or equipment
submitted for approval prior to Contractor's purchase thereof for incorporation in the Work.
Such inspections, tests, re -tests, or approvals shall be performed by organizations acceptable to
City.
D. City may arrange for the services of an independent testing laboratory ("Testing Lab") to
perform any inspections or tests ("Testing") for any part of the Work, as determined solely by
City.
1. City will coordinate such Testing to the extent possible, with Contractor;
2. Should any Testing under this Section 13.03 D result in a "fail", "did not pass" or other
similar negative result, the Contractor shall be responsible for paying for any and all retests.
Contractor's cancellation without cause of City initiated Testing shall be deemed a negative
result and require a retest.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai Lonomons
Page 49 of 63
3. Any amounts owed for any retest under this Section 13.03 D shall be paid directly to the
Testing Lab by Contractor. City will forward all invoices for retests to Contractor.
4. If Contractor fails to pay the Testing Lab, City will not issue Final Payment until the Testing
Lab is paid.
E. If any Work (or the work of others) that is to be inspected, tested, or approved is covered by
Contractor without written concurrence of City, Contractor shall, if requested by City, uncover
such Work for observation.
F. Uncovering Work as provided in Paragraph 13.03.E shall be at Contractor's expense.
G. Contractor shall have the right to make a Contract Claim regarding any retest or invoice issued
under Section 13.03 D.
13.04 Uncovering Work
A. If any Work is covered contrary to the Contract Documents or specific instructions by the City, it
must, if requested by City, be uncovered for City's observation and replaced at Contractor's
expense.
B. If City considers it necessary or advisable that covered Work be observed by City or inspected or
tested by others, Contractor, at City's request, shall uncover, expose, or otherwise make available
for observation, inspection, or testing as City may require, that portion of the Work in question,
furnishing all necessary labor, material, and equipment.
1. If it is found that the uncovered Work is defective, Contractor shall pay all claims, costs,
losses, and damages (including but not limited to all fees and charges of engineers, architects,
attorneys, and other professionals and all court or other dispute resolution costs) arising out
of or relating to such uncovering, exposure, observation, inspection, and testing, and of
satisfactory replacement or reconstruction (including but not limited to all costs of repair or
replacement of work of others); or City shall be entitled to accept defective Work in
accordance with Paragraph 13.08 in which case Contractor shall still be responsible for all
costs associated with exposing, observing, and testing the defective Work.
2. If the uncovered Work is not found to be defective, Contractor shall be allowed an increase
in the Contract Price or an extension of the Contract Time, or both, directly attributable to
such uncovering, exposure, observation, inspection, testing, replacement, and reconstruction.
13.05 City May Stop the Work
If the Work is defective, or Contractor fails to supply sufficient skilled workers or suitable materials
or equipment, or fails to perform the Work in such a way that the completed Work will conform to
the Contract Documents, City may order Contractor to stop the Work, or any portion thereof, until
the cause for such order has been eliminated; however, this right of City to stop the Work shall not
give rise to any duty on the part of City to exercise this right for the benefit of Contractor, any
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai uonamons
Page 50 of 63
Subcontractor, any Supplier, any other individual or entity, or any surety for, or employee or agent of
any of them.
13.06 Correction or Removal of Defective Work
A. Promptly after receipt of written notice, Contractor shall correct all defective Work pursuant to
an acceptable schedule, whether or not fabricated, installed, or completed, or, if the Work has
been rejected by City, remove it from the Project and replace it with Work that is not defective.
Contractor shall pay all claims, costs, additional testing, losses, and damages (including but not
limited to all fees and charges of engineers, architects, attorneys, and other professionals and all
court or arbitration or other dispute resolution costs) arising out of or relating to such correction
or removal (including but not limited to all costs of repair or replacement of work of others).
Failure to require the removal of any defective Work shall not constitute acceptance of such
Work.
B. When correcting defective Work under the terms of this Paragraph 13.06 or Paragraph 13.07,
Contractor shall take no action that would void or otherwise impair City's special warranty and
guarantee, if any, on said Work.
13.07 Correction Period
A. If within two (2) years after the date of Final Acceptance (or such longer period of time as may
be prescribed by the terms of any applicable special guarantee required by the Contract
Documents), any Work is found to be defective, or if the repair of any damages to the land or
areas made available for Contractor's use by City or permitted by Laws and Regulations as
contemplated in Paragraph 6.10.A is found to be defective, Contractor shall promptly, without
cost to City and in accordance with City's written instructions:
1. repair such defective land or areas; or
2. correct such defective Work; or
3. if the defective Work has been rejected by City, remove it from the Project and replace it
with Work that is not defective, and
4. satisfactorily correct or repair or remove and replace any damage to other Work, to the work
of others or other land or areas resulting therefrom.
B. If Contractor does not promptly comply with the terms of City's written instructions, or in an
emergency where delay would cause serious risk of loss or damage, City may have the defective
Work corrected or repaired or may have the rejected Work removed and replaced. All claims,
costs, losses, and damages (including but not limited to all fees and charges of engineers,
architects, attorneys, and other professionals and all court or other dispute resolution costs)
arising out of or relating to such correction or repair or such removal and replacement (including
but not limited to all costs of repair or replacement of work of others) will be paid by Contractor.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai Lonauions
Page 51 of 63
C. In special circumstances where a particular item of equipment is placed in continuous service
before Final Acceptance of all the Work, the correction period for that item may start to run from
an earlier date if so provided in the Contract Documents.
D. Where defective Work (and damage to other Work resulting therefrom) has been corrected or
removed and replaced under this Paragraph 13.07, the correction period hereunder with respect
to such Work may be required to be extended for an additional period of one year after the end of
the initial correction period. City shall provide 30 days written notice to Contractor should such
additional warranty coverage be required. Contractor may dispute this requirement by filing a
Contract Claim, pursuant to Paragraph 10.06.
E. Contractor's obligations under this Paragraph 13.07 are in addition to any other obligation or
warranty. The provisions of this Paragraph 13.07 shall not be construed as a substitute for, or a
waiver of, the provisions of any applicable statute of limitation or repose.
13.08 Acceptance of Defective Work
If, instead of requiring correction or removal and replacement of defective Work, City prefers to
accept it, City may do so. Contractor shall pay all claims, costs, losses, and damages (including but
not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all
court or other dispute resolution costs) attributable to City's evaluation of and determination to
accept such defective Work and for the diminished value of the Work to the extent not otherwise
paid by Contractor. If any such acceptance occurs prior to Final Acceptance, a Change Order will be
issued incorporating the necessary revisions in the Contract Documents with respect to the Work,
and City shall be entitled to an appropriate decrease in the Contract Price, reflecting the diminished
value of Work so accepted.
13.09 City May Correct Defective Work
A. If Contractor fails within a reasonable time after written notice from City to correct defective
Work, or to remove and replace rejected Work as required by City in accordance with Paragraph
13.06.A, or if Contractor fails to perform the Work in accordance with the Contract Documents,
or if Contractor fails to comply with any other provision of the Contract Documents, City may,
after seven (7) days written notice to Contractor, correct, or remedy any such deficiency.
B. In exercising the rights and remedies under this Paragraph 13.09, City shall proceed
expeditiously. In connection with such corrective or remedial action, City may exclude
Contractor from all or part of the Site, take possession of all or part of the Work and suspend
Contractor's services related thereto, and incorporate in the Work all materials and equipment
incorporated in the Work, stored at the Site or for which City has paid Contractor but which are
stored elsewhere. Contractor shall allow City, City's representatives, agents, consultants,
employees, and City's other contractors, access to the Site to enable City to exercise the rights
and remedies under this Paragraph.
C. All claims, costs, losses, and damages (including but not limited to all fees and charges of
engineers, architects, attorneys, and other professionals and all court or other dispute resolution
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai uonanions
Page 52 of 63
costs) incurred or sustained by City in exercising the rights and remedies under this Paragraph
13.09 will be charged against Contractor, and a Change Order will be issued incorporating the
necessary revisions in the Contract Documents with respect to the Work; and City shall be
entitled to an appropriate decrease in the Contract Price.
D. Contractor shall not be allowed an extension of the Contract Time because of any delay in the
performance of the Work attributable to the exercise of City's rights and remedies under this
Paragraph 13.09.
ARTICLE 14 — PAYMENTS TO CONTRACTOR AND COMPLETION
14.01 Schedule of Values
The Schedule of Values for lump sum contracts established as provided in Paragraph 2.07 will serve
as the basis for progress payments and will be incorporated into a form of Application for Payment
acceptable to City. Progress payments on account of Unit Price Work will be based on the number of
units completed.
14.02 Progress Payments
A. Applications for Payments:
1. Contractor is responsible for providing all information as required to become a vendor of the
City.
2. At least 20 days before the date established in the General Requirements for each progress
payment, Contractor shall submit to City for review an Application for Payment filled out
and signed by Contractor covering the Work completed as of the date of the Application and
accompanied by such supporting documentation as is required by the Contract Documents.
3. If payment is requested on the basis of materials and equipment not incorporated in the Work
but delivered and suitably stored at the Site or at another location agreed to in writing, the
Application for Payment shall also be accompanied by a bill of sale, invoice, or other
documentation warranting that City has received the materials and equipment free and clear
of all Liens and evidence that the materials and equipment are covered by appropriate
insurance or other arrangements to protect City's interest therein, all of which must be
satisfactory to City.
4. Beginning with the second Application for Payment, each Application shall include an
affidavit of Contractor stating that previous progress payments received on account of the
Work have been applied on account to discharge Contractor's legitimate obligations
associated with prior Applications for Payment.
5. The amount of retainage with respect to progress payments will be as stipulated in the
Contract Documents.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai Lonanions
Page 53 of 63
B. Review ofApplications:
1. City will, after receipt of each Application for Payment, either indicate in writing a
recommendation of payment or return the Application to Contractor indicating reasons for
refusing payment. In the latter case, Contractor may make the necessary corrections and
resubmit the Application.
2. City's processing of any payment requested in an Application for Payment will be based on
City's observations of the executed Work, and on City's review of the Application for
Payment and the accompanying data and schedules, that to the best of City's knowledge:
a. the Work has progressed to the point indicated;
b. the quality of the Work is generally in accordance with the Contract Documents (subject
to an evaluation of the Work as a functioning whole prior to or upon Final Acceptance,
the results of any subsequent tests called for in the Contract Documents, a final
determination of quantities and classifications for Work performed under Paragraph 9.05,
and any other qualifications stated in the recommendation).
3. Processing any such payment will not thereby be deemed to have represented that:
a. inspections made to check the quality or the quantity of the Work as it has been
performed have been exhaustive, extended to every aspect of the Work in progress, or
involved detailed inspections of the Work beyond the responsibilities specifically
assigned to City in the Contract Documents; or
b. there may not be other matters or issues between the parties that might entitle Contractor
to be paid additionally by City or entitle City to withhold payment to Contractor, or
c. Contractor has complied with Laws and Regulations applicable to Contractor's
performance of the Work.
4. City may refuse to process the whole or any part of any payment because of subsequently
discovered evidence or the results of subsequent inspections or tests, and revise or revoke
any such payment previously made, to such extent as may be necessary to protect City from
loss because:
a. the Work is defective, or the completed Work has been damaged by the Contractor or his
subcontractors, requiring correction or replacement;
b. discrepancies in quantities contained in previous applications for payment;
c. the Contract Price has been reduced by Change Orders;
d. City has been required to correct defective Work or complete Work in accordance with
Paragraph 13.09; or
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
venerai _onamons
Page 54 of 63
e. City has actual knowledge of the occurrence of any of the events enumerated in
Paragraph 15.02.A.
C. Retainage:
1. For contracts less than $400,000 at the time of execution, retainage shall be ten percent
(10%).
2. For contracts greater than $400,000 at the time of execution, retainage shall be five percent
(5%).
D. Liquidated Damages. For each calendar day that any work shall remain uncompleted after the
time specified in the Contract Documents, the sum per day specified in the Agreement, will be
deducted from the monies due the Contractor, not as a penalty, but as liquidated damages
suffered by the City.
E. Payment: Contractor will be paid pursuant to the requirements of this Article 14 and payment
will become due in accordance with the Contract Documents.
F. Reduction in Payment:
1. City may refuse to make payment of the amount requested because:
a. Liens have been filed in connection with the Work, except where Contractor has
delivered a specific bond satisfactory to City to secure the satisfaction and discharge of
such Liens;
b. there are other items entitling City to a set-off against the amount recommended; or
c. City has actual knowledge of the occurrence of any of the events enumerated in
Paragraphs 14.02.B.4.a through 14.02.B.4.e or Paragraph 15.02.A.
2. If City refuses to make payment of the amount requested, City will give Contractor written
notice stating the reasons for such action and pay Contractor any amount remaining after
deduction of the amount so withheld. City shall pay Contractor the amount so withheld, or
any adjustment thereto agreed to by City and Contractor, when Contractor remedies the
reasons for such action.
14.03 Contractor's Warranty of Title
Contractor warrants and guarantees that title to all Work, materials, and equipment covered by any
Application for Payment, whether incorporated in the Project or not, will pass to City no later than
the time of payment free and clear of all Liens.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai commons
Page 55 of 63
14.04 Partial Utilization
A. Prior to Final Acceptance of all the Work, City may use or occupy any substantially completed
part of the Work which has specifically been identified in the Contract Documents, or which
City, determines constitutes a separately functioning and usable part of the Work that can be
used by City for its intended purpose without significant interference with Contractor's
performance of the remainder of the Work. City at any time may notify Contractor in writing to
permit City to use or occupy any such part of the Work which City determines to be ready for its
intended use, subject to the following conditions:
1. Contractor at any time may notify City in writing that Contractor considers any such part of
the Work ready for its intended use.
2. Within a reasonable time after notification as enumerated in Paragraph 14.05.A.1, City and
Contractor shall make an inspection of that part of the Work to determine its status of
completion. If City does not consider that part of the Work to be substantially complete, City
will notify Contractor in writing giving the reasons therefor.
3. Partial Utilization will not constitute Final Acceptance by City.
14.05 Final Inspection
A. Upon written notice from Contractor that the entire Work is complete in accordance with the
Contract Documents:
1. within 10 days, City will schedule a Final Inspection with Contractor.
2. City will notify Contractor in writing of all particulars in which this inspection reveals that
the Work is incomplete or defective. Contractor shall immediately take such measures as are
necessary to complete such Work or remedy such deficiencies.
B. No time charge will be made against the Contractor between said date of notification of the City
and the date of Final Inspection. Should the City determine that the Work is not ready for Final
Inspection, City will notify the Contractor in writing of the reasons and Contract Time will
resume.
14.06 Final Acceptance
Upon completion by Contractor to City's satisfaction, of any additional Work identified in the Final
Inspection, City will issue to Contractor a letter of Final Acceptance.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai uonomons
Page 56 of 63
14.07 Final Payment
A. Application for Payment:
1. Upon Final Acceptance, and in the opinion of City, Contractor may make an application for
final payment following the procedure for progress payments in accordance with the
Contract Documents.
2. The final Application for Payment shall be accompanied (except as previously delivered) by:
a. all documentation called for in the Contract Documents, including but not limited to the
evidence of insurance required by Paragraph 5.03;
b. consent of the surety, if any, to final payment;
c. a list of all pending or released Damage Claims against City that Contractor believes are
unsettled; and
d. affidavits of payments and complete and legally effective releases or waivers
(satisfactory to City) of all Lien rights arising out of or Liens filed in connection with the
Work.
B. Payment Becomes Due:
1. After City's acceptance of the Application for Payment and accompanying documentation,
requested by Contractor, less previous payments made and any sum City is entitled,
including but not limited to liquidated damages, will become due and payable.
2. After all Damage Claims have been resolved:
a. directly by the Contractor or;
b. Contractor provides evidence that the Damage Claim has been reported to Contractor's
insurance provider for resolution.
3. The making of the final payment by the City shall not relieve the Contractor of any
guarantees or other requirements of the Contract Documents which specifically continue
thereafter.
14.08 Final Completion Delayed and Partial Retainage Release
A. If final completion of the Work is significantly delayed, and if City so confirms, City may, upon
receipt of Contractor's final Application for Payment, and without terminating the Contract,
make payment of the balance due for that portion of the Work fully completed and accepted. If
the remaining balance to be held by City for Work not fully completed or corrected is less than
the retainage stipulated in Paragraph 14.02.C, and if bonds have been furnished as required in
Paragraph 5.02, the written consent of the surety to the payment of the balance due for that
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai Lonamons
Page 57 of 63
portion of the Work fully completed and accepted shall be submitted by Contractor to City with
the Application for such payment. Such payment shall be made under the terms and conditions
governing final payment, except that it shall not constitute a waiver of Contract Claims.
B. Partial Retainage Release. For a Contract that provides for a separate vegetative establishment
and maintenance, and test and performance periods following the completion of all other
construction in the Contract Documents for all Work locations, the City may release a portion of
the amount retained provided that all other work is completed as determined by the City. Before
the release, all submittals and final quantities must be completed and accepted for all other work.
An amount sufficient to ensure Contract compliance will be retained.
14.09 Waiver of Claims
The acceptance of final payment will constitute a release of the City from all claims or liabilities
under the Contract for anything done or furnished or relating to the work under the Contract
Documents or any act or neglect of City related to or connected with the Contract.
ARTICLE 15 — SUSPENSION OF WORK AND TERMINATION
15.01 City May Suspend Work
A. At any time and without cause, City may suspend the Work or any portion thereof by written
notice to Contractor and which may fix the date on which Work will be resumed. Contractor
shall resume the Work on the date so fixed. During temporary suspension of the Work covered
by these Contract Documents, for any reason, the City will make no extra payment for stand-by
time of construction equipment and/or construction crews.
B. Should the Contractor not be able to complete a portion of the Project due to causes beyond the
control of and without the fault or negligence of the Contractor, and should it be determined by
mutual consent of the Contractor and City that a solution to allow construction to proceed is not
available within a reasonable period of time, Contractor may request an extension in Contract
Time, directly attributable to any such suspension.
C. If it should become necessary to suspend the Work for an indefinite period, the Contractor shall
store all materials in such a manner that they will not obstruct or impede the public unnecessarily
nor become damaged in any way, and he shall take every precaution to prevent damage or
deterioration of the work performed; he shall provide suitable drainage about the work, and erect
temporary structures where necessary.
D. Contractor may be reimbursed for the cost of moving his equipment off the job and returning the
necessary equipment to the job when it is determined by the City that construction may be
resumed. Such reimbursement shall be based on actual cost to the Contractor of moving the
equipment and no profit will be allowed. Reimbursement may not be allowed if the equipment is
moved to another construction project for the City.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai Lonamons
Page 58 of 63
15.02 City May Terminate for Cause
A. The occurrence of any one or more of the following events by way of example, but not of
limitation, may justify termination for cause:
1. Contractor's persistent failure to perform the Work in accordance with the Contract
Documents (including, but not limited to, failure to supply sufficient skilled workers or
suitable materials or equipment, failure to adhere to the Project Schedule established under
Paragraph 2.07 as adjusted from time to time pursuant to Paragraph 6.04, or failure to adhere
to the City's Business Diversity Enterprise Ordinance #20020-12-2011established under
Paragraph 6.06.D);
2. Contractor's disregard of Laws or Regulations of any public body having jurisdiction;
3. Contractor's repeated disregard of the authority of City; or
4. Contractor's violation in any substantial way of any provisions of the Contract Documents;
or
5. Contractor's failure to promptly make good any defect in materials or workmanship, or
defects of any nature, the correction of which has been directed in writing by the City; or
6. Substantial indication that the Contractor has made an unauthorized assignment of the
Contract or any funds due therefrom for the benefit of any creditor or for any other purpose;
or
7. Substantial evidence that the Contractor has become insolvent or bankrupt, or otherwise
financially unable to carry on the Work satisfactorily; or
8. Contractor commences legal action in a court of competent jurisdiction against the City.
B. If one or more of the events identified in Paragraph 15.02A. occur, City will provide written
notice to Contractor and Surety to arrange a conference with Contractor and Surety to address
Contractor's failure to perform the Work. Conference shall be held not later than 15 days, after
receipt of notice.
1. If the City, the Contractor, and the Surety do not agree to allow the Contractor to proceed to
perform the construction Contract, the City may, to the extent permitted by Laws and
Regulations, declare a Contractor default and formally terminate the Contractor's right to
complete the Contract. Contractor default shall not be declared earlier than 20 days after the
Contractor and Surety have received notice of conference to address Contractor's failure to
perform the Work.
2. If Contractor's services are terminated, Surety shall be obligated to take over and perform the
Work. If Surety does not commence performance thereof within 15 consecutive calendar
days after date of an additional written notice demanding Surety's performance of its
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai Lonomons
Page 59 of 63
obligations, then City, without process or action at law, may take over any portion of the
Work and complete it as described below.
a. If City completes the Work, City may exclude Contractor and Surety from the site and
take possession of the Work, and all materials and equipment incorporated into the Work
stored at the Site or for which City has paid Contractor or Surety but which are stored
elsewhere, and finish the Work as City may deem expedient.
3. Whether City or Surety completes the Work, Contractor shall not be entitled to receive any
further payment until the Work is finished. If the unpaid balance of the Contract Price
exceeds all claims, costs, losses and damages sustained by City arising out of or resulting
from completing the Work, such excess will be paid to Contractor. If such claims, costs,
losses and damages exceed such unpaid balance, Contractor shall pay the difference to City.
Such claims, costs, losses and damages incurred by City will be incorporated in a Change
Order, provided that when exercising any rights or remedies under this Paragraph, City shall
not be required to obtain the lowest price for the Work performed.
4. Neither City, nor any of its respective consultants, agents, officers, directors or employees
shall be in any way liable or accountable to Contractor or Surety for the method by which the
completion of the said Work, or any portion thereof, may be accomplished or for the price
paid therefor.
5. City, notwithstanding the method used in completing the Contract, shall not forfeit the right
to recover damages from Contractor or Surety for Contractor's failure to timely complete the
entire Contract. Contractor shall not be entitled to any claim on account of the method used
by City in completing the Contract.
6. Maintenance of the Work shall continue to be Contractor's and Surety's responsibilities as
provided for in the bond requirements of the Contract Documents or any special guarantees
provided for under the Contract Documents or any other obligations otherwise prescribed by
law.
C. Notwithstanding Paragraphs 15.02.B, Contractor's services will not be terminated if Contractor
begins within seven days of receipt of notice of intent to terminate to correct its failure to
perform and proceeds diligently to cure such failure within no more than 30 days of receipt of
said notice.
D. Where Contractor's services have been so terminated by City, the termination will not affect any
rights or remedies of City against Contractor then existing or which may thereafter accrue. Any
retention or payment of moneys due Contractor by City will not release Contractor from liability.
E. If and to the extent that Contractor has provided a performance bond under the provisions of
Paragraph 5.02, the termination procedures of that bond shall not supersede the provisions of this
Article.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai Lonamons
Page 60 of 63
15.03 City May Terminate For Convenience
A. City may, without cause and without prejudice to any other right or remedy of City, terminate the
Contract. Any termination shall be effected by mailing a notice of the termination to the
Contractor specifying the extent to which performance of Work under the contract is terminated,
and the date upon which such termination becomes effective. Receipt of the notice shall be
deemed conclusively presumed and established when the letter is placed in the United States
Postal Service Mail by the City. Further, it shall be deemed conclusively presumed and
established that such termination is made with just cause as therein stated; and no proof in any
claim, demand or suit shall be required of the City regarding such discretionary action.
B. After receipt of a notice of termination, and except as otherwise directed by the City, the
Contractor shall:
1. Stop work under the Contract on the date and to the extent specified in the notice of
termination;
2. place no further orders or subcontracts for materials, services or facilities except as may be
necessary for completion of such portion of the Work under the Contract as is not terminated;
3. terminate all orders and subcontracts to the extent that they relate to the performance of the
Work terminated by notice of termination;
4. transfer title to the City and deliver in the manner, at the times, and to the extent, if any,
directed by the City:
a. the fabricated or unfabricated parts, Work in progress, completed Work, supplies and
other material produced as a part of, or acquired in connection with the performance of,
the Work terminated by the notice of the termination; and
b. the completed, or partially completed plans, drawings, information and other property
which, if the Contract had been completed, would have been required to be furnished to
the City.
5. complete performance of such Work as shall not have been terminated by the notice of
termination; and
6. take such action as may be necessary, or as the City may direct, for the protection and
preservation of the property related to its contract which is in the possession of the
Contractor and in which the owner has or may acquire the rest.
C. At a time not later than 30 days after the termination date specified in the notice of termination,
the Contractor may submit to the City a list, certified as to quantity and quality, of any or all
items of termination inventory not previously disposed of, exclusive of items the disposition of
which has been directed or authorized by City.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
venerai commons
Page 61 of 63
D. Not later than 15 days thereafter, the City shall accept title to such items provided, that the list
submitted shall be subject to verification by the City upon removal of the items or, if the items
are stored, within 45 days from the date of submission of the list, and any necessary adjustments
to correct the list as submitted, shall be made prior to final settlement.
E. Not later than 60 days after the notice of termination, the Contractor shall submit his termination
claim to the City in the form and with the certification prescribed by the City. Unless an
extension is made in writing within such 60 day period by the Contractor, and granted by the
City, any and all such claims shall be conclusively deemed waived.
F. In such case, Contractor shall be paid for (without duplication of any items):
1. completed and acceptable Work executed in accordance with the Contract Documents prior
to the effective date of termination, including fair and reasonable sums for overhead and profit on
such Work;
2. expenses sustained prior to the effective date of termination in performing services and
furnishing labor, materials, or equipment as required by the Contract Documents in connection
with uncompleted Work, plus fair and reasonable sums for overhead and profit on such expenses;
and
3. reasonable expenses directly attributable to termination.
G. In the event of the failure of the Contractor and City to agree upon the whole amount to be paid
to the Contractor by reason of the termination of the Work, the City shall determine, on the basis
of information available to it, the amount, if any, due to the Contractor by reason of the
termination and shall pay to the Contractor the amounts determined. Contractor shall not be paid
on account of loss of anticipated profits or revenue or other economic loss arising out of or
resulting from such termination.
ARTICLE 16 — DISPUTE RESOLUTION
16.01 Methods and Procedures
A. Either City or Contractor may request mediation of any Contract Claim submitted for a decision
under Paragraph 10.06 before such decision becomes final and binding. The request for
mediation shall be submitted to the other party to the Contract. Timely submission of the request
shall stay the effect of Paragraph 10.06.E.
B. City and Contractor shall participate in the mediation process in good faith. The process shall be
commenced within 60 days of filing of the request.
C. If the Contract Claim is not resolved by mediation, City's action under Paragraph 10.06.0 or a
denial pursuant to Paragraphs 10.06.C.3 or 10.06.D shall become final and binding 30 days after
termination of the mediation unless, within that time period, City or Contractor:
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai Commons
Page 62 of 63
1. elects in writing to invoke any other dispute resolution process provided for in the
Supplementary Conditions; or
2. agrees with the other party to submit the Contract Claim to another dispute resolution
process; or
3. gives written notice to the other party of the intent to submit the Contract Claim to a court of
competent jurisdiction.
ARTICLE 17 — MISCELLANEOUS
17.01 Giving Notice
A. Whenever any provision of the Contract Documents requires the giving of written notice, it will
be deemed to have been validly given if:
1. delivered in person to the individual or to a member of the firm or to an officer of the
corporation for whom it is intended; or
2. delivered at or sent by registered or certified mail, postage prepaid, to the last business
address known to the giver of the notice.
B. Business address changes must be promptly made in writing to the other party.
C. Whenever the Contract Documents specifies giving notice by electronic means such electronic
notice shall be deemed sufficient upon confirmation of receipt by the receiving party.
17.02 Computation of Times
When any period of time is referred to in the Contract Documents by days, it will be computed to
exclude the first and include the last day of such period. If the last day of any such period falls on a
Saturday or Sunday or on a day made a legal holiday the next Working Day shall become the last
day of the period.
17.03 Cumulative Remedies
The duties and obligations imposed by these General Conditions and the rights and remedies
available hereunder to the parties hereto are in addition to, and are not to be construed in any way as
a limitation of, any rights and remedies available to any or all of them which are otherwise imposed
or available by Laws or Regulations, by special warranty or guarantee, or by other provisions of the
Contract Documents. The provisions of this Paragraph will be as effective as if repeated specifically
in the Contract Documents in connection with each particular duty, obligation, right, and remedy to
which they apply.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
uenerai commons
Page 63 of 63
17.04 Survival of Obligations
All representations, indemnifications, warranties, and guarantees made in, required by, or given in
accordance with the Contract Documents, as well as all continuing obligations indicated in the
Contract Documents, will survive final payment, completion, and acceptance of the Work or
termination or completion of the Contract or termination of the services of Contractor.
17.05 Headings
Article and paragraph headings are inserted for convenience only and do not constitute parts of these
General Conditions.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS
Revision: August 17, 2012
007300-1
SUPPLEMENTARY CONDITIONS
1
2
SECTION 00 73 00
SUPPLEMENTARY CONDITIONS
Page 1 of 6
3 TO
4 GENERAL CONDITIONS
5
6 Supplementary Conditions
7
8 These Supplementary Conditions modify and supplement Section 00 72 00 - General Conditions, and other
9 provisions of the Contract Documents as indicated below. All provisions of the General Conditions that are
10 modified or supplemented remain in full force and effect as so modified or supplemented. All provisions
11 of the General Conditions which are not so modified or supplemented remain in full force and effect.
12
13 Defined Terms
14
15 The terns used in these Supplementary Conditions which are defined in the General Conditions have the
16 meaning assigned to them in the General Conditions, unless specifically noted herein.
17
18 56. Regular Working Hours — Hours beginning at 7:00 a.m. and ending at 6:00 p.m., Monday thru Friday
19 (excluding legal holidays) except on Cleburne Road and Benbrook Drive whose hours begin at 9:00 a.m.
20 and end at 4:00 p.m., Monday thru Friday (excluding legal holidays) or as noted in the plans.
21
22 Modifications and Supplements
23
24 The following are instructions that modify or supplement specific paragraphs in the General Conditions and
25 other Contract Documents.
26
27 SC-3.03B.2, "Resolving Discrepancies"
28
29 Plans govern over Specifications and Specifications shall govern over standard details.
30
31 SC-4.O1A
32
33 Easement limits shown on the Drawing are approximate and were provided to establish a basis for bidding.
34 Upon receiving the final easements descriptions, Contractor shall compare them to the lines shown on the
35 Contract Drawings.
36
37 SC-4.01A.1., "Availability of Lands"
38
39 The following is a list of known outstanding right-of-way, and/or easements to be acquired, if any as of
40 January 11, 2013:
41
42 Outstanding Right -Of -Way, and/or Easements to Be Acquired
PARCEL OWNER TARGET DATE
NUMBER OF POSSESSION
3205 Cleburne Road Pedro Alcantara
3233 Cleburne Road Cleburne Foods LLC
43 The Contractor understands and agrees that the dates listed above are estimates only, are not guaranteed,
44 and do not bind the City.
45
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised 12/12/12
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
00 73 00 - 2
SUPPLEMENTARY CONDITIONS
Page 2 of 6
1 If Contractor considers the final easements provided to differ materially from the representations on the
2 Contract Drawings, Contractor shall within five (5) Business Days and before proceeding with the Work,
3 notify City in writing associated with the differing easement line locations.
4
5 SC-4.01A.2, "Availability of Lands"
6
7 Utilities or obstructions to be removed, adjusted, and/or relocated
8
9 The following is List of utilities and/or obstructions that have not been removed, adjusted, and/or relocated
10 as of January 11, 2013:
11
EXPECTED UTILITY AND LOCATION TARGET DATE OF
OWNER ADJUSTMENT
None
12 The Contractor understands and agrees that the dates listed above are estimates only, are not guaranteed,
13 and do not bind the City.
14
15 SC-4.02A., "Subsurface and Physical Conditions"
16
17 The following are reports of explorations and tests of subsurface conditions at the site of the Work:
18
19 None
20
21 SC-4.06A., "Hazardous Environmental Conditions at Site"
22
23 The following are reports and drawings of existing hazardous environmental conditions known to the City:
24
25 None
26
27 SC-5.03A., "Certificates of Insurance"
28
29 The entities listed below are "additional insureds as their interest may appear" including their respective
30 officers, directors, agents and employees.
31
32 (1) City
33 (2) Consultant: Lockwood, Andrews, & Newnam, Inc.
34 (3) Other: None
35
36 SC-5.04A., "Contractor's Insurance"
37
38 The limits of liability for the insurance required by Paragraph GC-5.04 shall provide the following
39 coverages for not less than the following amounts or greater where required by laws and regulations:
40
41 5.04A. Workers' Compensation, under Paragraph GC-5.04A.
42
43 Statutory limits
44 Employer's liability
45 $100,000 each accident/occurrence
46 $100,000 Disease - each employee
47 $500,000 Disease - policy limit
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised 12/12/12
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project#1480
007300-3
SUPPLEMENTARY CONDITIONS
Page 3 of 6
1
2 SC-5.04B., "Contractor's Insurance"
3
4 5.04B. Commercial General Liability, under Paragraph GC-5.04B. Contractor's Liability Insurance
5 under Paragraph GC-5.04B., which shall be on a per project basis covering the Contractor with
6 minimum limits of:
7
8 $1,000,000 each occurrence
9 $2,000,000 aggregate limit
10
11 The policy must have an endorsement (Amendment — Aggregate Limits of Insurance) making the
12 General Aggregate Limits apply separately to each job site.
13
14 The Commercial General Liability Insurance policies shall provide "X", "C", and "U" coverage's.
15 Verification of such coverage must be shown in the Remarks Article of the Certificate of Insurance.
16
17 SC 5.04C., "Contractor's Insurance"
18 5.04C. Automobile Liability, under Paragraph GC-5.04C. Contractor's Liability Insurance under
19 Paragraph GC-5.04C., which shall be in an amount not less than the following amounts:
20
21 (1) Automobile Liability - a commercial business policy shall provide coverage on "Any Auto",
22 defined as autos owned, hired and non -owned.
23
24 $1,000,000 each accident on a combined single limit basis. Split limits are acceptable if limits are at
25 least:
26
27 $250,000 Bodily Injury per person /
28 $500,000 Bodily Injury per accident /
29 $100,000 Property Damage
30
31 SC-5.04D., "Contractor's Insurance"
32
33 The Contractor's construction activities will require its employees, agents, subcontractors, equipment, and
34 material deliveries to cross railroad properties and tracks owned and operated by Fort Worth and Western
35 Railroad (FWWR) and Burlington Northern Sante Fe (BNSF).
36
37 The Contractor shall conduct its operations on railroad properties in such a manner as not to interfere with,
38 hinder, or obstruct the railroad company in any manner whatsoever in the use or operation of its/their trains
39 or other property. Such operations on railroad properties may require that Contractor to execute a "Right of
40 Entry Agreement" with the particular railroad company or companies involved, and to this end the
41 Contractor should satisfy itself as to the requirements of each railroad company and be prepared to execute
42 the right -of -entry (if any) required by a railroad company. The requirements specified herein likewise relate
43 to the Contractor's use of private and/or construction access roads crossing said railroad company's
44 properties.
45
46 The Contractual Liability coverage required by Paragraph 5.04D of the General Conditions shall provide
47 coverage for not less than the following amounts, issued by companies satisfactory to the City and to the
48 Railroad Company for a term that continues for so long as the Contractor's operations and work cross,
49 occupy, or touch railroad property:
50
51 (1) General Aggregate: $Confirm Limits with Railroad
52
53 (2) Each Occurrence: $Confirm Limits with Railroad
54
55 X Required for this Contract Not required for this Contract
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised 12/12/12
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project # 1480
007300-4
SUPPLEMENTARY CONDITIONS
Page 4 of 6
1
2 With respect to the above outlined insurance requirements, the following shall govern:
3
4 1. Where a single railroad company is involved, the Contractor shall provide one insurance policy in
5 the name of the railroad company. However, if more than one grade separation or at -grade
6 crossing is affected by the Project at entirely separate locations on the line or lines of the same
7 railroad company, separate coverage may be required, each in the amount stated above.
8
9 2. Where more than one railroad company is operating on the same right-of-way or where several
10 railroad companies are involved and operated on their own separate rights -of -way, the Contractor
11 may be required to provide separate insurance policies in the name of each railroad company.
12
13 3. If, in addition to a grade separation or an at -grade crossing, other work or activity is proposed on a
14 railroad company's right-of-way at a location entirely separate from the grade separation or at-
15 grade crossing, insurance coverage for this work must be included in the policy covering the grade
16 separation.
17
18 4. If no grade separation is involved but other work is proposed on a railroad company's right-of-
19 way, all such other work may be covered in a single policy for that railroad, even though the work
20 may be at two or more separate locations.
21
22 No work or activities on a railroad company's property to be performed by the Contractor shall be
23 commenced until the Contractor has furnished the City with an original policy or policies of the insurance
24 for each railroad company named, as required above. All such insurance must be approved by the City and
25 each affected Railroad Company prior to the Contractor's beginning work.
26
27 The insurance specified above must be carried until all Work to be performed on the railroad right-of-way
28 has been completed and the grade crossing, if any, is no longer used by the Contractor. In addition,
29 insurance must be carried during all maintenance and/or repair work performed in the railroad right-of-way.
30 Such insurance must name the railroad company as the insured, together with any tenant or lessee of the
31 railroad company operating over tracks involved in the Project.
32
33 SC-6.07., "Wage Rates"
34
35 The following is the prevailing wage rate table(s) applicable to this project and is provided in the
36 Appendixes:
37
38 2008 Prevailing Wage Rates
39
40 SC-6.09., "Permits and Utilities"
41
42 SC-6.09A., "Contractor obtained permits and licenses"
43 The following are known permits and/or licenses required by the Contract to be acquired by the Contractor:
44
45 None.
46
47 SC-6.09B. "City obtained permits and licenses"
48 The following are known permits and/or licenses required by the Contract to be acquired by the City:
49
50 None.
51
52 SC-6.09C. "Outstanding permits and licenses"
53
54 The following is a list of known outstanding permits and/or licenses to be acquired, if any as of January 11,
55 2013:
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised 12/12/12
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project 41480
007300-5
SUPPLEMENTARY CONDITIONS
Page 5 of 6
1
2
3 Outstanding Permits and/or Licenses to Be Acquired
OWNER PERMIT OR LICENSE AND LOCATION TARGET DATE
OF POSSESSION
Fort Worth & Western R.R. Pipeline Crossing, Cleburne Rd & Forest Pk
Fort Worth & Western R.R. Pipeline Crossing, Cleburne Rd & Devitt St
BNSF R.R. Pipeline Crossing, Biddison St & James Ave
4
5 SC-6.24B., "Title VI, Civil Rights Act of 1964 as amended"
6
7 During the performance of this Contract, the Contractor, for itself, its assignees and successors in interest
8 (hereinafter referred to as the "Contractor") agrees as follows:
9
10 1. Compliance with Regulations: The Contractor shall comply with the Regulation relative to
11 nondiscrimination in Federally -assisted programs of the Department of Transportation (hereinafter,
12 "DOT") Title 49, Code of Federal Regulations, Part 21, as they may be amended from time to time,
13 (hereinafter referred to as the Regulations), which are herein incorporated by reference and made a part
14 of this contract.
15
16 2. Nondiscrimination: The Contractor, with regard to the work performed by it during the contract, shall
17 not discriminate on the grounds of race, color, or national origin, in the selection and retention of
18 subcontractors, including procurements of materials and leases of equipment. The Contractor shall not
19 participate either directly or indirectly in the discrimination prohibited by 49 CFR, section 21.5 of the
20 Regulations, including employment practices when the contract covers a program set forth in
21 Appendix B of the Regulations.
22
23 3. Solicitations for Subcontractors, Including Procurements of Materials and Equipment: In all
24 solicitations either by competitive bidding or negotiation made by the contractor for work to be
25 performed under a subcontract, including procurements of materials or leases of equipment, each
26 potential subcontactor or supplier shall be notified by the Contractor of the Contractor's obligations
27 under this contract and the Regulations relative to nondiscrimination on the grounds of race, color, or
28 national origin.
29
30 4. Information and Reports: The Contractor shall provide all information and reports required by the
31 Regulations or directives issued pursuant thereto, and shall permit access to its books, records,
32 accounts, other sources of information and its facilities as may be determined by City or the Texas
33 Department of Transportation to be pertinent to ascertain compliance with such Regulations, orders
34 and instructions. Where any information required of a contractor is in the exclusive possession of
35 another who fails or refuses to furnish this information the contractor shall so certify to the City, or the
36 Texas Department of Transportation, as appropriate, and shall set forth what efforts it has made to
37 obtain the information.
38
39 5. Sanctions for Noncompliance: In the event of the Contractor's noncompliance with the
40 nondiscrimination provisions of this Contract, City shall impose such contract sanctions as it or the
41 Texas Department of Transportation may determine to be appropriate, including, but not limited to:
42
43 a. withholding of payments to the Contractor under the Contract until the Contractor
44 complies, and/or
45 b. cancellation, termination or suspension of the Contract, in whole or in part.
46
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised 12/12/12
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project # 1480
01 11 00 -2
SUMMARY OF WORK
Page 2 of 3
1 b. Excavated and waste materials shall be stored in such a way as not to interfere
2 with the use of spaces that may be designated to be left free and unobstructed
3 and so as not to inconvenience occupants of adjacent property.
4 c. If the street is occupied by railroad tracks, the Work shall be carried on in such
5 manner as not to interfere with the operation of the railroad.
6 1) All Work shall be in accordance with railroad requirements set forth in
7 Division 0 as well as the railroad permit.
8 D. Work within Easements
9 1. Do not enter upon private property for any purpose without having previously
10 obtained permission from the owner of such property.
11 2. Do not store equipment or material on private property unless and until the
12 specified approval of the property owner has been secured in writing by the
13 Contractor and a copy furnished to the City.
14 3. Unless specifically provided otherwise, clear all rights -of -way or easements of
15 obstructions which must be removed to make possible proper prosecution of the
16 Work as a part of the project construction operations.
17 4. Preserve and use every precaution to prevent damage to, all trees, shrubbery, plants,
18 lawns, fences, culverts, curbing, and all other types of structures or improvements,
19 to all water, sewer, and gas lines, to all conduits, overhead pole lines, or
20 appurtenances thereof, including the construction of temporary fences and to all
21 other public or private property adjacent to the Work.
22 5. Notify the proper representatives of the owners or occupants of the public or private
23 lands of interest in lands which might be affected by the Work.
24 a. Such notice shall be made at least 48 hours in advance of the beginning of the
25 Work.
26 b. Notices shall be applicable to both public and private utility companies and any
27 corporation, company, individual, or other, either as owners or occupants,
28 whose land or interest in land might be affected by the Work.
29 c. Be responsible for all damage or injury to property of any character resulting
30 from any act, omission, neglect, or misconduct in the manner or method or
31 execution of the Work, or at any time due to defective work, material, or
32 equipment.
33 6. Fence
34 a. Restore all fences encountered and removed during construction of the Project
35 to the original or a better than original condition.
36 b. Erect temporary fencing in place of the fencing removed whenever the Work is
37 not in progress and when the site is vacated overnight, and/or at all times to
38 provide site security.
39 c. The cost for all fence work associated with easements, including removal,
40 temporary closures and replacement, shall be subsidiary to the various items bid
41 in the project proposal, unless a bid item is specifically provided in the
42 proposal.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project # 1480
01 I100-3
SUMMARY OF WORK
1 1.5 SUBMITTALS [NOT USED]
2 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
3 1.7 CLOSEOUT SUBMITTALS [NOT USED]
4 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
5 1.9 QUALITY ASSURANCE [NOT USED]
6 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
7 1.11 FIELD [SITE] CONDITIONS [NOT USED]
8 1.12 WARRANTY [NOT USED]
9 PART 2 - PRODUCTS [NOT USED]
10 PART 3 - EXECUTION [NOT USED]
11 END OF SECTION
12
13
Revision Log
DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Page 3 of 3
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
012500-1
SUBSTITUTION PROCEDURES
2
3 PART 1 - GENERAL
4 1.1 SUMMARY
SECTION 0125 00
SUBSTITUTION PROCEDURES
Page 1 of 4
5 A. Section Includes:
6 1. The procedure for requesting the approval of substitution of a product that is not
7 equivalent to a product which is specified by descriptive or performance criteria or
8 defined by reference to 1 or more of the following:
9 a. Name of manufacturer
10 b. Name of vendor
11 c. Trade name
12 d. Catalog number
13 2. Substitutions are not "or -equals".
14 B. Deviations from this City of Fort Worth Standard Specification
15 1. None.
16 C. Related Specification Sections include, but are not necessarily limited to:
17 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
18 2. Division 1 — General Requirements
19 1.2 PRICE AND PAYMENT PROCEDURES
20 A. Measurement and Payment
21 1. Work associated with this Item is considered subsidiary to the various items bid.
22 No separate payment will be allowed for this Item.
23 1.3 REFERENCES [NOT USED]
24 1.4 ADMINISTRATIVE REQUIREMENTS
25 A. Request for Substitution - General
26 1. Within 30 days after award of Contract (unless noted otherwise), the City will
27 consider formal requests from Contractor for substitution of products in place of
28 those specified.
29 2. Certain types of equipment and kinds of material are described in Specifications by
30 means of references to names of manufacturers and vendors, trade names, or
31 catalog numbers.
32 a. When this method of specifying is used, it is not intended to exclude from
33 consideration other products bearing other manufacturer's or vendor's names,
34 trade names, or catalog numbers, provided said products are "or -equals," as
35 determined by City.
36 3. Other types of equipment and kinds of material may be acceptable substitutions
37 under the following conditions:
38 a. Or -equals are unavailable due to strike, discontinued production of products
39 meeting specified requirements, or other factors beyond control of Contractor;
40 or,
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project11480
012500-2
SUBSTITUTION PROCEDURES
Page 2 of 4
1 b. Contractor proposes a cost and/or time reduction incentive to the City.
2 1.5 SUBMITTALS
3 A. See Request for Substitution Form (attached)
4 B. Procedure for Requesting Substitution
5 1. Substitution shall be considered only:
6 a. After award of Contract
7 b. Under the conditions stated herein
8 2. Submit 3 copies of each written request for substitution, including:
9 a. Documentation
10 1) Complete data substantiating compliance of proposed substitution with
11 Contract Documents
12 2) Data relating to changes in construction schedule, when a reduction is
13 proposed
14 3) Data relating to changes in cost
15 b. For products
16 1) Product identification
17 a) Manufacturer's name
18 b) Telephone number and representative contact name
19 c) Specification Section or Drawing reference of originally specified
20 product, including discrete name or tag number assigned to original
21 product in the Contract Documents
22 2) Manufacturer's literature clearly marked to show compliance of proposed
23 product with Contract Documents
24 3) Itemized comparison of original and proposed product addressing product
25 characteristics including, but not necessarily limited to:
26 a) Size
27 b) Composition or materials of construction
28 c) Weight
29 d) Electrical or mechanical requirements
30 4) Product experience
31 a) Location of past projects utilizing product
32 b) Name and telephone number of persons associated with referenced
33 projects knowledgeable concerning proposed product
34 c) Available field data and reports associated with proposed product
35 5) Samples
36 a) Provide at request of City.
37 b) Samples become the property of the City.
38 c. For construction methods:
39 1) Detailed description of proposed method
40 2) Illustration drawings
41 C. Approval or Rejection
42 1. Written approval or rejection of substitution given by the City
43 2. City reserves the right to require proposed product to comply with color and pattern
44 of specified product if necessary to secure design intent.
45 3. In the event the substitution is approved, the resulting cost and/or time reduction
46 will be documented by Change Order in accordance with the General Conditions.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
012500-3
SUBSTITUTION PROCEDURES
Page 3 of 4
1 4. No additional contract time will be given for substitution.
2 5. Substitution will be rejected if:
3 a. Submittal is not through the Contractor with his stamp of approval
4 b. Request is not made in accordance with this Specification Section
5 c. In the City's opinion, acceptance will require substantial revision of the original
6 design
7 d. In the City's opinion, substitution will not perform adequately the function
8 consistent with the design intent
9 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
10 1.7 CLOSEOUT SUBMITTALS [NOT USED]
11 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
12 1.9 QUALITY ASSURANCE
13 A. In making '•-'uest for substitution or in using an approved product, the Contractor
14 represents that the Contractor:
15 I. Has investigated proposed product, and has determined that it is adequate or
16 superior in all respects to that specified, and that it will perform function for which
17 it is intended
18 2. Will provide same guarantee for substitute item as for product specified
19 3. Will coordinate installation of accepted substitution into Work, to include building
20 modifications if necessary, making such changes as may be required for Work to be
21 complete in all respects
22 4. Waives all claims for additional costs related to substitution which subsequently
23 arise
24 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
25 1.11 FIELD [SITE] CONDITIONS [NOT USED]
26 1.12 WARRANTY [NOT USED]
27 PART 2 - PRODUCTS [NOT USED]
28 PART 3 - EXECUTION [NOT USED]
29
30
31
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project 41480
012500-4
SUBSTITUTION PROCEDURES
Page 4 of 4
1 EXHIBIT A
2 REQUEST FOR SUBSTITUTION FORM:
3
4 TO:
5 PROJECT: DATE:
6 We hereby submit for your consideration the following product instead of the specified item for
7 the above project:
8 SECTION PARAGRAPH SPECIFIED ITEM
9
10
11 Proposed Substitution:
12 Reason for Substitution:
13 Include complete information on changes to Drawings and/or Specifications which proposed
14 substitution will require for its proper installation.
15
16 Fill in Blanks Below:
17 A. Will the undersigned contractor pay for changes to the building design, including engineering
18 and detailing costs caused by the requested substitution?
19
20
21 B. What effect does substitution have on other trades?
22
23
24 C. Differences between proposed substitution and specified item?
25
26
27 D. Differences in product cost or product delivery time?
28
29
30 E. Manufacturer's guarantees of the proposed and specified items are:
31
32 Equal Better (explain on attachment)
33 The undersigned states that the function, appearance and quality are equivalent or superior to the
34 specified item.
35 Submitted By: For Use by City
36
37 Signature Recommended Recommended
38 as noted
39
40 Firm Not recommended Received late
41 Address By
42 Date
43 Date Remarks
44 Telephone
45
46 For Use by City:
47
48 Approved Rejected
49 City Date
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project 41480
013119-1
PRECONSTRUCTION MEETING
2
SECTION 01 31 19
PRECONSTRUCTION MEETING
Page 1 of 3
3 PART1- GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Provisions for the preconstruction meeting to be held prior to the start of Work to
7 clarify construction contract administration procedures
8 B. Deviations from this City of Fort Worth Standard Specification
9 1. None.
10 C. Related Specification Sections include, but are not necessarily limited to:
11 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
12 2. Division 1 — General Requirements
13 1.2 PRICE AND PAYMENT PROCEDURES
14 A. Measurement and Payment
15 1. Work associated with this Item is considered subsidiary to the various items bid.
16 No separate payment will be allowed for this Item.
17 1.3 REFERENCES [NOT USED]
18 1.4 ADMINISTRATIVE REQUIREMENTS
19 A. Coordination
20 1. Attend preconstruction meeting.
21 2. Representatives of Contractor, subcontractors and suppliers attending meetings
22 shall be qualified and authorized to act on behalf of the entity each represents.
23 3. Meeting administered by City may be tape recorded.
24 a. If recorded, tapes will be used to prepare minutes and retained by City for
25 future reference.
26 B. Preconstruction Meeting
27 1. A preconstruction meeting will be held within 14 days after the execution of the
28 Agreement and before Work is started.
29 a. The meeting will be scheduled and administered by the City.
30 2. The Project Representative will preside at the meeting, prepare the notes of the
31 meeting and distribute copies of same to all participants who so request by fully
32 completing the attendance form to be circulated at the beginning of the meeting.
33 3. Attendance shall include:
34 a. Project Representative
35 b. Contractor's project manager
36 c. Contractor's superintendent
37 d. Any subcontractor or supplier representatives whom the Contractor may desire
38 to invite or the City may request
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised August 17, 2012
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project # 1480
01 31 19 - 2
PRECONSTRUCTION MEETING
1
2
e. Other City representatives
f. Others as appropriate
Page 2 of 3
3 4. Construction Schedule
4 a. Prepare baseline construction schedule in accordance with Section 01 32 16 and
5 provide at Preconstruction Meeting.
6 b. City will notify Contractor of any schedule changes upon Notice of
7 Preconstruction Meeting.
8 5. Preliminary Agenda may include:
9 a. Introduction of Project Personnel
10 b. General Description of Project
11 c. Status of right-of-way, utility clearances, easements or other pertinent permits
12 d. Contractor's work plan and schedule
13 e. Contract Time
14 f Notice to Proceed
15 g. Construction Staking
16 h. Progress Payments
17 i. Extra Work and Change Order Procedures
18 j. Field Orders
19 k. Disposal Site Letter for Waste Material
20 1. Insurance Renewals
21 m. Payroll Certification
22 n. Material Certifications and Quality Control Testing
23 o. Public Safety and Convenience
24 p. Documentation of Pre -Construction Conditions
25 q. Weekend Work Notification
26 r. Legal Holidays
27 s. Trench Safety Plans
28 t. Confined Space Entry Standards
29 u. Coordination with the City's representative for operations of existing water
30 systems
31 v. Storm Water Pollution Prevention Plan
32 w. Coordination with other Contractors
33 x. Early Warning System
34 y. Contractor Evaluation
35 z. Special Conditions applicable to the project
36 aa. Damages Claims
37 bb. Submittal Procedures
38 cc. Substitution Procedures
39 dd. Correspondence Routing
40 ee. Record Drawings
41 ff. Temporary construction facilities
42 gg. M/WBE or MBE/SBE procedures
43 hh. Final Acceptance
44 ii. Final Payment
45 jj. Questions or Comments
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised August 17, 2012
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
01 31 19 - 3
PRECONSTRUCTION MEETING
1 1.5 SUBMITTALS [NOT USED]
2 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
3 1.7 CLOSEOUT SUBMITTALS [NOT USED]
4 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
5 1.9 QUALITY ASSURANCE [NOT USED]
6 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
7 1.11 FIELD [SITE] CONDITIONS [NOT USED]
8 1.12 WARRANTY [NOT USED]
9 PART 2 - PRODUCTS [NOT USED]
10 PART 3 - EXECUTION [NOT USED]
11 END OF SECTION
12
13
Revision Log
DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised August 17, 2012
Page 3 of 3
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
013216-1
CONSTRUCTION PROGRESS SCHEDULE
2
SECTION 01 32 16
CONSTRUCTION PROGRESS SCHEDULE
Page 1 of 5
3 PART 1 - GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. General requirements for the preparation, submittal, updating, status reporting and
7 management of the Construction Progress Schedule
8 2. Specific requirements are presented in the City of Fort Worth Schedule Guidance
9 Document
10 B. Deviations from this City of Fort Worth Standard Specification
11 1. None.
12 C. Related Specification Sections include, but are not necessarily limited to:
13 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
14 2. Division 1 — General Requirements
15 1.2 PRICE AND PAYMENT PROCEDURES
16 A. Measurement and Payment
17 1. Work associated with this Item is considered subsidiary to the various items bid.
18 No separate payment will be allowed for this Item.
19 1.3 REFERENCES
20 A. Definitions
21 1. Schedule Tiers
22 a. Tier 1 - No schedule submittal required by contract. Small, brief duration
23 projects
24 b. Tier 2 - No schedule submittal required by contract, but will require some
25 milestone dates. Small, brief duration projects
26 c. Tier 3 - Schedule submittal required by contract as described in the
27 Specification and herein. Majority of City projects, including all bond program
28 projects
29 d. Tier 4 - Schedule submittal required by contract as described in the
30 Specification and herein. Large and/or complex projects with long durations
31 1) Examples: large water pump station project and associated pipeline with
32 interconnection to another governmental entity
33 e. Tier 5 - Schedule submittal required by contract as described in the
34 Specification and herein. Large and/or very complex projects with long
35 durations, high public visibility
36 1) Examples might include a water or wastewater treatment plant
37 2. Baseline Schedule - Initial schedule submitted before work begins that will serve
38 as the baseline for measuring progress and departures from the schedule.
39 3. Progress Schedule - Monthly submittal of a progress schedule documenting
40 progress on the project and any changes anticipated.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project 41480
01 32 16 -2
CONSTRUCTION PROGRESS SCHEDULE
Page 2 of 5
1 4. Schedule Narrative - Concise narrative of the schedule including schedule
2 changes, expected delays, key schedule issues, critical path items, etc
3 B. Reference Standards
4 1. City of Fort Worth Schedule Guidance Document
5 1.4 ADMINISTRATIVE REQUIREMENTS
6 A. Baseline Schedule
7 1. General
8 a. Prepare a cost -loaded baseline Schedule using approved software and the
9 Critical Path Method (CPM) as required in the City of Fort Worth Schedule
10 Guidance Document.
11 b. Review the draft cost -loaded baseline Schedule with the City to demonstrate
12 understanding of the work to be performed and known issues and constraints
13 related to the schedule.
14 c. Designate an authorized representative (Project Scheduler) responsible for
15 developing and updating the schedule and preparing reports.
16 B. Progress Schedule
17 1. Update the progress Schedule monthly as required in the City of Fort Worth
18 Schedule Guidance Document.
19 2. Prepare the Schedule Narrative to accompany the monthly progress Schedule.
20 3. Change Orders
21 a. Incorporate approved change orders, resulting in a change of contract time, in
22 the baseline Schedule in accordance with City of Fort Worth Schedule
23 Guidance Document.
24 C. Responsibility for Schedule Compliance
25 1. Whenever it becomes apparent from the current progress Schedule and CPM Status
26 Report that delays to the critical path have resulted and the Contract completion
27 date will not be met, or when so directed by the City, make some or all of the
28 following actions at no additional cost to the City
29 a. Submit a Recovery Plan to the City for approval revised baseline Schedule
30 outlining:
31 1) A written statement of the steps intended to take to remove or arrest the
32 delay to the critical path in the approved schedule
33 2) Increase construction manpower in such quantities and crafts as will
34 substantially eliminate the backlog of work and return current Schedule to
35 meet projected baseline completion dates
36 3) Increase the number of working hours per shift, shifts per day, working
37 days per week, the amount of construction equipment, or any combination
38 of the foregoing, sufficiently to substantially eliminate the backlog of work
39 4) Reschedule activities to achieve maximum practical concurrency of
40 accomplishment of activities, and comply with the revised schedule
41 2. If no written statement of the steps intended to take is submitted when so requested
42 by the City, the City may direct the Contractor to increase the level of effort in
43 manpower (trades), equipment and work schedule (overtime, weekend and holiday
44 work, etc.) to be employed by the Contractor in order to remove or arrest the delay
45 to the critical path in the approved schedule.
46 a. No additional cost for such work will be considered.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project 111480
01 32 16 - 3
CONSTRUCTION PROGRESS SCHEDULE
Page 3 of 5
1 D. The Contract completion time will be adjusted only for causes specified in this
2 Contract.
3 a. Requests for an extension of any Contract completion date must be
4 supplemented with the following:
5 1) Furnish justification and supporting evidence as the City may deem
6 necessary to determine whether the requested extension of time is entitled
7 under the provisions of this Contract.
8 a) The City will, after receipt of such justification and supporting
9 evidence, make findings of fact and will advise the Contractor, in
10 writing thereof.
11 2) If the City finds that the requested extension of time is entitled, the City's
12 determination as to the total number of days allowed for the extensions
13 shall be based upon the approved total baseline schedule and on all data
14 relevant to the extension.
15 a) Such data shall be included in the next updating of the Progress
16 schedule.
17 b) Actual delays in activities which, according to the Baseline schedule,
18 do not affect any Contract completion date shown by the critical path in
19 the network will not be the basis for a change therein.
20 2. Submit each request for change in Contract completion date to the City within 30
21 days after the beginning of the delay for which a time extension is requested but
22 before the date of final payment under this Contract.
23 a. No time extension will be granted for requests which are not submitted within
24 the foregoing time limit.
25 b. From time to time, it may be necessary for the Contract schedule or completion
26 time to be adjusted by the City to reflect the effects of job conditions, weather,
27 technical difficulties, strikes, unavoidable delays on the part of the City or its
28 representatives, and other unforeseeable conditions which may indicate
29 schedule adjustments or completion time extensions.
30 1) Under such conditions, the City will direct the Contractor to reschedule the
31 work or Contract completion time to reflect the changed conditions and the
32 Contractor shall revise his schedule accordingly.
33 a) No additional compensation will be made to the Contractor for such
34 schedule changes except for unavoidable overall contract time
35 extensions beyond the actual completion of unaffected work, in which
36 case the Contractor shall take all possible action to minimize any time
37 extension and any additional cost to the City.
38 b) Available float time in the Baseline schedule may be used by the City
39 as well as by the Contractor.
40 3. Float or slack time is defined as the amount of time between the earliest start date
41 and the latest start date or between the earliest finish date and the latest finish date
42 of a chain of activities on the Baseline Schedule.
43 a. Float or slack time is not for the exclusive use or benefit of either the
44 Contractor or the City.
45 b. Proceed with work according to early start dates, and the City shall have the
46 right to reserve and apportion float time according to the needs of the project.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project # 1480
013216-4
CONSTRUCTION PROGRESS SCHEDULE
Page 4 of 5
1 c. Acknowledge and agree that actual delays, affecting paths of activities
2 containing float time, will not have any effect upon contract completion times,
3 providing that the actual delay does not exceed the float time associated with
4 those activities.
5 E. Coordinating Schedule with Other Contract Schedules
6 1. Where work is to be performed under this Contract concurrently with or contingent
7 upon work performed on the same facilities or area under other contracts, the
8 Baseline Schedule shall be coordinated with the schedules of the other contracts.
9 a. Obtain the schedules of the other appropriate contracts from the City for the
10 preparation and updating of Baseline schedule and make the required changes
11 in his schedule when indicated by changes in corresponding schedules.
12 2. In case of interference between the operations of different contractors, the City will
13 determine the work priority of each contractor and the sequence of work necessary
14 to expedite the completion of the entire Project.
15 a. In such cases, the decision of the City shall be accepted as final.
16 b. The temporary delay of any work due to such circumstances shall not be
17 considered as justification for claims for additional compensation.
18 1.5 SUBMITTALS
19 A. Baseline Schedule
20 1. Submit Schedule in native file format and pdf format as required in the City of Fort
21 Worth Schedule Guidance Document.
22 a. Native file format includes:
23 1) Primavera (P6 or Primavera Contractor)
24 2. Submit draft baseline Schedule to City prior to the pre -construction meeting and
25 bring in hard copy to the meeting for review and discussion.
26 B. Progress Schedule
27 1. Submit progress Schedule in native file format and pdf format as required in the
28 City of Fort Worth Schedule Guidance Document.
29 2. Submit progress Schedule monthly no later than the last day of the month.
30 C. Schedule Narrative
31 1. Submit the schedule narrative in pdf format as required in the City of Fort Worth
32 Schedule Guidance Document.
33 2. Submit schedule narrative monthly no later than the last day of the month.
34 D. Submittal Process
35 1. The City administers and manages schedules through Buzzsaw.
36 2. Contractor shall submit documents as required in the City of Fort Worth Schedule
37 Guidance Document.
38 3. Once the project has been completed and Final Acceptance has been issued by the
39 City, no further progress schedules are required.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project # 1480
013216-5
CONSTRUCTION PROGRESS SCHEDULE
Page 5 of 5
1 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
2 1.7 CLOSEOUT SUBMITTALS [NOT USED]
3 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
4 1.9 QUALITY ASSURANCE
5 A. The person preparing and revising the construction Progress Schedule shall be
6 experienced in the preparation of schedules of similar complexity.
7 B. Schedule and supporting documents addressed in this Specification shall be prepared,
8 updated and revised to accurately reflect the performance of the construction.
9 C. Contractor is responsible for the quality of all submittals in this section meeting the
10 standard of care for the construction industry for similar projects.
11 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
12 1.11 FIELD [SITE] CONDITIONS [NOT USED]
13 1.12 WARRANTY [NOT USED]
14 PART 2 - PRODUCTS [NOT USED]
15 PART 3 - EXECUTION [NOT USED]
16 END OF SECTION
17
18
Revision Log
DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project#1480
1
2
3 PART 1- GENERAL
4 1.1 SUMMARY
5
A. Section Includes:
SECTION 01 33 00
SUBMITTALS
01 33 00 - 1
SUBMITTALS
Page 1 of 8
6 1. General methods and requirements of submissions applicable to the following
7 Work -related submittals:
8 a. Shop Drawings
9 b. Product Data (including Standard Product List submittals)
10 c. Samples
11 d. Mock Ups
12 B. Deviations from this City of Fort Worth Standard Specification
13 1. None.
14 C. Related Specification Sections include, but are not necessarily limited to:
15 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
16 2. Division 1 — General Requirements
17 1.2 PRICE AND PAYMENT PROCEDURES
18 A. Measurement and Payment
19 1. Work associated with this Item is considered subsidiary to the various items bid.
20 No separate payment will be allowed for this Item.
21 1.3 REFERENCES [NOT USED]
22 1.4 ADMINISTRATIVE REQUIREMENTS
23
A.
Coordination
24 Notify the City in writing, at the time of submittal, of any deviations in the
25 submittals from the requirements of the Contract Documents.
2. Coordination of Submittal Times
a. Prepare, prioritize and transmit each submittal sufficiently
performing the related Work or other applicable activities,
specified in the individual Work Sections, of the Specifica
b. Contractor is responsible such that the installation will not
processing times including, but not limited to:
a) Disapproval and resubmittal (if required)
b) Coordination with other submittals
c) Testing
d) Purchasing
e) Fabrication
f) Delivery
Similar sequenced activities
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
1.
g)
in advance of
or within the time
tions.
be delayed by
c. No extension of time will be authorized because of the Contractor's failure to
transmit submittals sufficiently in advance of the Work.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project # 1480
013300-2
SUBMITTALS
Page 2 of 8
1 d. Make submittals promptly in accordance with approved schedule, and in such
2 sequence as to cause no delay in the Work or in the work of any other
3 contractor.
4 B. Submittal Numbering
5 1. When submitting shop drawings or samples, utilize a 9-character submittal cross-
6 reference identification numbering system in the following manner:
7 a. Use the first 6 digits of the applicable Specification Section Number.
8 b. For the next 2 digits number use numbers 01-99 to sequentially number each
9 initial separate item or drawing submitted under each specific Section number.
10 c. Last use a letter, A-Z, indicating the resubmission of the same drawing (i.e.
11 A=2nd submission, B=3rd submission, C=4th submission, etc.). A typical
12 submittal number would be as follows:
13
14 03 30 00-08-B
15
16 1) 03 30 00 is the Specification Section for Concrete
17 2) 08 is the eighth initial submittal under this Specification Section
18 3) B is the third submission (second resubmission) of that particular shop
19 drawing
20 C. Contractor Certification
21 1. Review shop drawings, product data and samples, including those by
22 subcontractors, prior to submission to determine and verify the following:
23 a. Field measurements
24 b. Field construction criteria
25 c. Catalog numbers and similar data
26 d. Conformance with the Contract Documents
27 2. Provide each shop drawing, sample and product data submitted by the Contractor
28 with a Certification Statement affixed including:
29 a. The Contractor's Company name
30 b. Signature of submittal reviewer
31 c. Certification Statement
32 1) "By this submittal, I hereby represent that I have determined and verified
33 field measurements, field construction criteria, materials, dimensions,
34 catalog numbers and similar data and I have checked and coordinated each
35 item with other applicable approved shop drawings."
36 D. Submittal Format
37 1. Fold shop drawings larger than 8 % inches x 11 inches to 8 % inches x 11 inches.
38 2. Bind shop drawings and product data sheets together.
39 3. Order
40 a. Cover Sheet
41 1) Description of Packet
42 2) Contractor Certification
43 b. List of items / Table of Contents
44 c. Product Data /Shop Drawings/Samples /Calculations
45 E. Submittal Content
46 1. The date of submission and the dates of any previous submissions
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project # 1480
01 33 00 - 3
SUBMITTALS
Page 3of8
1 2. The Project title and number
2 3. Contractor identification
3 4. The names of:
4 a. Contractor
5 b. Supplier
6 c. Manufacturer
7 5. Identification of the product, with the Specification Section number, page and
8 paragraph(s)
9 6. Field dimensions, clearly identified as such
10 7. Relation to adjacent or critical features of the Work or materials
11 8. Applicable standards, such as ASTM or Federal Specification numbers
12 9. Identification by highlighting of deviations from Contract Documents
13 10. Identification by highlighting of revisions on resubmittals
14 11. An 8-inch x 3-inch blank space for Contractor and City stamps
15 F. Shop Drawings
16 1. As specified in individual Work Sections includes, but is not necessarily limited to:
17 a. Custom -prepared data such as fabrication and erection/installation (working)
18 drawings
19 b. Scheduled information
20 c. Setting diagrams
21 d. Actual shopwork manufacturing instructions
22 e. Custom templates
23 f. Special wiring diagrams
24 g. Coordination drawings
25 h. Individual system or equipment inspection and test reports including:
26 1) Performance curves and certifications
27 i. As applicable to the Work
28 2. Details
29 a. Relation of the various parts to the main members and lines of the structure
30 b. Where correct fabrication of the Work depends upon field measurements
31 1) Provide such measurements and note on the drawings prior to submitting
32 for approval.
33 G. Product Data
34 1. For submittals of product data for products included on the City's Standard Product
35 List, clearly identify each item selected for use on the Project.
36 2. For submittals of product data for products not included on the City's Standard
37 Product List, submittal data may include, but is not necessarily limited to:
38 a. Standard prepared data for manufactured products (sometimes referred to as
39 catalog data)
40 1) Such as the ]manufacturer's product specification and installation
41 instructions
42 2) Availability of colors and patterns
43 3) Manufacturer's printed statements of compliances and applicability
44 4) Roughing -in diagrams and templates
45 5) Catalog cuts
46 6) Product photographs
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project 1/ 1480
01 33 00 - 4
SUBMITTALS
Page 4 of 8
1 7) Standard wiring diagrams
2 8) Printed performance curves and operational -range diagrams
3 9) Production or quality control inspection and test reports and certifications
4 10) Mill reports
5 11) Product operating and maintenance instructions and recommended
6 spare -parts listing and printed product warranties
7 12) As applicable to the Work
8 H. Samples
9 1. As specified in individual Sections, include, but are not necessarily limited to:
10 a. Physical examples of the Work such as:
11 1) Sections of manufactured or fabricated Work
12 2) Small cuts or containers of materials
13 3) Complete units of repetitively used products color/texture/pattern swatches
14 and range sets
15 4) Specimens for coordination of visual effect
16 5) Graphic symbols and units of Work to be used by the City for independent
17 inspection and testing, as applicable to the Work
18 I. Do not start Work requiring a shop drawing, sample or product data nor any material to
19 be fabricated or installed prior to the approval or qualified approval of such item.
20 1. Fabrication performed, materials purchased or on -site construction accomplished
21 which does not conform to approved shop drawings and data is at the Contractor's
22 risk.
23 2. The City will not be liable for any expense or delay due to corrections or remedies
24 required to accomplish conformity.
25 3. Complete project Work, materials, fabrication, and installations in conformance
26 with approved shop drawings, applicable samples, and product data.
27 J. Submittal Distribution
28 1. Electronic Distribution
29 a. Confirm development of Project directory for electronic submittals to be
30 uploaded to City's Buzzsaw site, or another external FTP site approved by the
31 City.
32 b. Shop Drawings
33 1) Upload submittal to designated project directory and notify appropriate
34 City representatives via email of submittal posting.
35 2) Hard Copies
36 a) 3 copies for all submittals
37 b) If Contractor requires more than 1 hard copy of Shop Drawings
38 returned, Contractor shall submit more than the number of copies listed
39 above.
40 c. Product Data
41 1) Upload submittal to designated project directory and notify appropriate
42 City representatives via email of submittal posting.
43 2) Hard Copies
44 a) 3 copies for all submittals
45 d. Samples
46 1) Distributed to the Project Representative
47 2. Hard Copy Distribution (if required in lieu of electronic distribution)
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project # 1480
013300-5
SUBMITTALS
Page 5 of 8
1 a. Shop Drawings
2 1) Distributed to the City
3 2) Copies
4 a) 8 copies for mechanical submittals
5 b) 7 copies for all other submittals
6 c) If Contractor requires more than 3 copies of Shop Drawings returned,
7 Contractor shall submit more than the number of copies listed above.
8 b. Product Data
9 1) Distributed to the City
10 2) Copies
11 a) 4 copies
12 c. Samples
13 1) Distributed to the Project Representative
14 2) Copies
15 a) Submit the number stated in the respective Specification Sections.
16 3. Distribute reproductions of approved shop drawings and copies of approved
17 product data and samples, where required, to the job site file and elsewhere as
18 directed by the City.
19 a. Provide number of copies as directed by the City but not exceeding the number
20 previously specified.
21 K. Submittal Review
22 1. The review of shop drawings, data and samples will be for general conformance
23 with the design concept and Contract Documents. This is not to be construed as:
24 a. Permitting any departure from the Contract requirements
25 b. Relieving the Contractor of responsibility for any errors, including details,
26 dimensions, and materials
27 c. Approving departures from details furnished by the City, except as otherwise
28 provided herein
29 2. The review and approval of shop drawings, samples or product data by the City
30 does not relieve the Contractor from his/her responsibility with regard to the
31 fulfillment of the terms of the Contract.
32 a. All risks of error and omission are assumed by the Contractor, and the City will
33 have no responsibility therefore.
34 3. The Contractor remains responsible for details and accuracy, for coordinating the
35 Work with all other associated work and trades, for selecting fabrication processes,
36 for techniques of assembly and for performing Work in a safe manner.
37 4. If the shop drawings, data or samples as submitted describe variations and show a
38 departure from the Contract requirements which City finds to be in the interest of
39 the City and to be so minor as not to involve a change in Contract Price or time for
40 performance, the City may return the reviewed drawings without noting an
41 exception.
42 5. Submittals will be returned to the Contractor under 1 of the following codes:
43 a. Code 1
44 1) "NO EXCEPTIONS TAKEN" is assigned when there are no notations or
45 comments on the submittal.
46 a) When returned under this code the Contractor may release the
47 equipment and/or material for manufacture.
48 b. Code 2
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project M 1480
013300-6
SUBMITTALS
Page 6 of 8
1 1) "EXCEPTIONS NOTED". This code is assigned when a confirmation of
2 the notations and comments IS NOT required by the Contractor.
3 a) The Contractor may release the equipment or material for manufacture;
4 however, all notations and comments must be incorporated into the
5 final product.
6 c. Code 3
7 1) "EXCEPTIONS NOTED/RESUBMIT". This combination of codes is
8 assigned when notations and comments are extensive enough to require a
9 resubmittal of the package.
10 a) The Contractor may release the equipment or material for manufacture;
11 however, all notations and comments must be incorporated into the
12 final product.
13 b) This resubmittal is to address all comments, omissions and
14 non -conforming items that were noted.
15 c) Resubmittal is to be received by the City within 15 calendar days of the
16 date of the City's transmittal requiring the resubmittal.
17 d. Code 4
18 1) "NOT APPROVED" is assigned when the submittal does not meet the
19 intent of the Contract Documents.
20 a) The Contractor must resubmit the entire package revised to bring the
21 submittal into conformance.
22 b) It may be necessary to resubmit using a different manufacturer/vendor
23 to meet the Contract Documents.
24 6. Resubmittals
25 a. Handled in the same manner as first submittals
26 1) Corrections other than requested by the City
27 2) Marked with revision triangle or other similar method
28 a) At Contractor's risk if not marked
29 b. Submittals for each item will be reviewed no more than twice at the City's
30 expense.
31 1) All subsequent reviews will be performed at times convenient to the City
32 and at the Contractor's expense, based on the City's or City
33 Representative's then prevailing rates.
34 2) Provide Contractor reimbursement to the City within 30 Calendar Days for
35 all such fees invoiced by the City.
36 c. The need for more than 1 resubmission or any other delay in obtaining City's
37 review of submittals, will not entitle the Contractor to an extension of Contract
38 Time.
39 7. Partial Submittals
40 a. City reserves the right to not review submittals deemed partial, at the City's
41 discretion.
42 b. Submittals deemed by the City to be not complete will be returned to the
43 Contractor, and will be considered "Not Approved" until resubmitted.
44 c. The City may at its option provide a list or mark the submittal directing the
45 Contractor to the areas that are incomplete.
46 8. If the Contractor considers any correction indicated on the shop drawings to
47 constitute a change to the Contract Documents, then written notice must be
48 provided thereof to the City at least 7 Working Days prior to release for
49 manufacture.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
013300-7
SUBMITTALS
Page 7 of 8
1 9. When the shop drawings have been completed to the satisfaction of the City, the
2 Contractor may carry out the construction in accordance therewith and no further
3 changes therein except upon written instructions from the City.
4 10. Each submittal, appropriately coded, will be returned within 30 calendar days
5 following receipt of submittal by the City.
6 L. Mock ups
7 1. Mock Up units as specified in individual Sections, include, but are not necessarily
8 limited to, complete units of the standard of acceptance for that type of Work to be
9 used on the Project. Remove at the completion of the Work or when directed.
10 M. Qualifications
11 1. If specifically required in other Sections of these Specifications, submit a P.E.
12 Certification for each item required.
13 N. Request for Information (RFI)
14 1. Contractor Request for additional information
15 a. Clarification or interpretation of the contract documents
16 b. When the Contractor believes there is a conflict between Contract Documents
17 c. When the Contractor believes there is a conflict between the Drawings and
18 Specifications
19 1) Identify the conflict and request clarification
20 2. Use the Request for Information (RFI) form provided by the City.
21 3. Numbering of RFI
22 a. Prefix with "RFI" followed by series number, "-xxx", beginning with "01" and
23 increasing sequentially with each additional transmittal.
24 4. Sufficient information shall be attached to permit a written response without further
25 information.
26 5. The City will log each request and will review the request.
27 a. If review of the project information request indicates that a change to the
28 Contract Documents is required, the City will issue a Field Order or Change
29 Order, as appropriate.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project # 1480
013300-8
SUBMITTALS
Page 8 of 8
1 1.5 SUBMITTALS [NOT USED]
2 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
3 1.7 CLOSEOUT SUBMITTALS [NOT USED]
4 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
5 1.9 QUALITY ASSURANCE [NOT USED]
6 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
7 1.11 FIELD [SITE] CONDITIONS [NOT USED]
8 1.12 WARRANTY [NOT USED]
9 PART 2 - PRODUCTS [NOT USED]
10 PART 3 - EXECUTION [NOT USED]
11 END OF SECTION
12
13
Revision Log
DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project # 1480
013513-1
SPECIAL PROJECT PROCEDURES
2
3 PART1- GENERAL
4 1.1 SUMMARY
SECTION 01 35 13
SPECIAL PROJECT PROCEDURES
Page 1 of 8
5 A. Section Includes:
6 1. The procedures for special project circumstances that includes, but is not limited to:
7 a. Coordination with the Texas Department of Transportation
8 b. Work near High Voltage Lines
9 c. Confined Space Entry Program
10 d. Air Pollution Watch Days
11 e. Use of Explosives, Drop Weight, Etc.
12 f. Water Department Notification
13 g. Public Notification Prior to Beginning Construction
14 h. Coordination with United States Army Corps of Engineers
15 i. Coordination within Railroad permits areas
16 j. Dust Control
17 k. Employee Parking
18 B. Deviations from this City of Fort Worth Standard Specification
19 1. None.
20 C. Related Specification Sections include, but are not necessarily limited to:
21 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
22 2. Division 1 — General Requirements
23 3. Section 33 12 25 — Connection to Existing Water Mains
24 1.2 PRICE AND PAYMENT PROCEDURES
25 A. Measurement and Payment
26 1. Coordination within Railroad permit areas
27 a. Measurement
28 1) Measurement for this Item will be by lump sum.
29 b. Payment
30 1) The work performed and materials furnished in accordance with this Item
31 will be paid for at the lump sum price bid for Railroad Coordination.
32 c. The price bid shall include:
33 1) Mobilization
34 2) Inspection
35 3) Safety training
36 4) Additional Insurance
37 5) Insurance Certificates
38 6) Other requirements associated with general coordination with Railroad,
39 including additional employees required to protect the right-of-way and
40 property of the Railroad from damage arising out of and/or from the
41 construction of the Project.
42 2. Railroad Flagmen
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised [Insert Revision Date]
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project#1480
01 35 13 - 2
SPECIAL PROJECT PROCEDURES
Page 2 of 8
1 a. Measurement
2 1) Measurement for this Item will be per working day.
3 b. Payment
4 1) The work performed and materials furnished in accordance with this Item
5 will be paid for each working day that Railroad Flagmen are present at the
6 Site .
7 c. The price bid shall include:
8 1) Coordination for scheduling flagmen
9 2) Flagmen
10 3) Other requirements associated with Railroad
11 3. All other items
12 a. Work associated with these Items is considered subsidiary to the various Items
13 bid. No separate payment will be allowed for this Item.
14 1.3 REFERENCES
15 A. Reference Standards
16 1. Reference standards cited in this Specification refer to the current reference
17 standard published at the time of the latest revision date logged at the end of this
18 Specification, unless a date is specifically cited.
19 2. North Central Texas Council of Governments (NCTCOG) — Clean Construction
20 Specification
21 1.4 ADMINISTRATIVE REQUIREMENTS
22 A. Coordination with the Texas Department of Transportation
23 1. When work in the right-of-way which is under the jurisdiction of the Texas
24 Department of Transportation (TxDOT):
25 a. Notify the Texas Department of Transportation prior to commencing any work
26 therein in accordance with the provisions of the permit
27 b. All work performed in the TxDOT right-of-way shall be performed in
28 compliance with and subject to approval from the Texas Department of
29 Transportation
30 B. Work near High Voltage Lines
31 1. Warning sign
32 a. Provide sign of sufficient size meeting all OSHA requirements.
33 2. Equipment operating within 10 feet of high voltage lines will require the following
34 safety features
35 a. Insulating cage -type of guard about the boom or arm
36 b. Insulator links on the lift hook connections for back hoes or dippers
37 c. Equipment must meet the safety requirements as set forth by OSHA and the
38 safety requirements of the owner of the high voltage lines
39 3. Work within 6 feet of high voltage electric lines
40 a. Notification shall be given to:
41 1) The power company (example: ONCOR)
42 a) Maintain an accurate log of all such calls to power company and record
43 action taken in each case.
44 b. Coordination with power company
45 1) After notification coordinate with the power company to:
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised [insert Revision Date]
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project#1480
013513-3
SPECIAL PROJECT PROCEDURES
Page 3 of 8
1 a) Erect temporary mechanical barriers, de -energize the lines, or raise or
2 lower the lines
3 c. No personnel may work within 6 feet of a high voltage line before the above
4 requirements have been met.
5 C. Confined Space Entry Program
6 1. Provide and follow approved Confined Space Entry Program in accordance with
7 OSHA requirements.
8 2. Confined Spaces include:
9 a. Manholes
10 b. All other confined spaces in accordance with OSHA's Permit Required for
11 Confined Spaces
12 D. Air Pollution Watch Days
13 1. General
14 a. Observe the following guidelines relating to working on City construction sites
15 on days designated as "AIR POLLUTION WATCH DAYS".
16 b. Typical Ozone Season
17 1) May 1 through October 31.
18 c. Critical Emission Time
19 1) 6:00 a.m. to 10:00 a.m.
20 2. Watch Days
21 a. The Texas Commission on Environmental Quality (TCEQ), in coordination
22 with the National Weather Service, will issue the Air Pollution Watch by 3:00
23 p.m. on the afternoon prior to the WATCH day.
24 b. Requirements
25 1) Begin work after 10:00 a.m. whenever construction phasing requires the
26 use of motorized equipment for periods in excess of 1 hour.
27 2) However, the Contractor may begin work prior to 10:00 a.m. if:
28 a) Use of motorized equipment is less than 1 hour, or
29 b) If equipment is new and certified by EPA as "Low Emitting", or
30 equipment burns Ultra Low Sulfur Diesel (ULSD), diesel emulsions, or
31 alternative fuels such as CNG.
32 E. Use of Explosives, Drop Weight, Etc.
33 1. When Contract Documents permit on the project the following will apply:
34 a. Public Notification
35 1) Submit notice to City and proof of adequate insurance coverage, 24 hours
36 prior to commencing.
37 2) Minimum 24 hour public notification in accordance with Section 01 31 13
38 F. Water Department Coordination
39 1. During the construction of this project, it will be necessary to deactivate, for a
40 period of time, existing lines. The Contractor shall be required to coordinate with
41 the Water Department to determine the best times for deactivating and activating
42 those lines.
43 2. Coordinate any event that will require connecting to or the operation of an existing
44 City water line system with the City's representative.
45 a. Coordination shall be in accordance with Section 33 12 25.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised [Insert Revision Date]
Sanitary Sewer Rehab Contract 75, Part I
CFW Project #1480
01 35 13 - 4
SPECIAL PROJECT PROCEDURES
Page 4 of 8
1 b. If needed, obtain a hydrant water meter from the Water Department for use
2 during the life of named project.
3 c. In the event that a water valve on an existing live system be turned off and on
4 to accommodate the construction of the project is required, coordinate this
5 activity through the appropriate City representative.
6 1) Do not operate water line valves of existing water system.
7 a) Failure to comply will render the Contractor in violation of Texas Penal
8 Code Title 7, Chapter 28.03 (Criminal Mischief) and the Contractor
9 will be prosecuted to the full extent of the law.
10 b) In addition, the Contractor will assume all liabilities and
11 responsibilities as a result of these actions.
12 G. Public Notification Prior to Beginning Construction
13 1. Prior to beginning construction on any block in the project, on a block by block
14 basis, prepare and deliver a notice or flyer of the pending construction to the front
15 door of each residence or business that will be impacted by construction. The notice
16 shall be prepared as follows:
17 a. Post notice or flyer 7 days prior to beginning any construction activity on each
18 block in the project area.
19 1) Prepare flyer on the Contractor's letterhead and include the following
20 information:
21 a) Name of Project
22 b) City Project No (CPN)
23 c) Scope of Project (i.e. type of construction activity)
24 d) Actual construction duration within the block
25 e) Name of the contractor's foreman and phone number
26 f) Name of the City's inspector and phone number
27 g) City's after-hours phone number
28 2) A sample of the `pre -construction notification' flyer is attached as Exhibit
29 A.
30 3) Submit schedule showing the construction start and finish time for each
31 block of the project to the inspector.
32 4) Deliver flyer to the City Inspector for review prior to distribution.
33 b. No construction will be allowed to begin on any block until the flyer is
34 delivered to all residents of the block.
35 H. Public Notification of Temporary Water Service Interruption during Construction
36 1. In the event it becomes necessary to temporarily shut down water service to
37 residents or businesses during construction, prepare and deliver a notice or flyer of
38 the pending interruption to the front door of each affected resident.
39 2. Prepared notice as follows:
40 a. The notification or flyer shall be posted 24 hours prior to the temporary
41 interruption.
42 b. Prepare flyer on the contractor's letterhead and include the following
43 information:
44 1) Name of the project
45 2) City Project Number
46 3) Date of the interruption of service
47 4) Period the interruption will take place
48 5) Name of the contractor's foreman and phone number
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised [Insert Revision Date]
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project # 1480
013513-5
SPECIAL PROJECT PROCEDURES
Page 5 of 8
1 6) Name of the City's inspector and phone number
2 c. A sample of the temporary water service interruption notification is attached as
3 Exhibit B.
4 d. Deliver a copy of the temporary interruption notification to the City inspector
5 for review prior to being distributed.
6 e. No interruption of water service can occur until the flyer has been delivered to
7 all affected residents and businesses.
8 f. Electronic versions of the sample flyers can be obtained from the Project
9 Construction Inspector.
10 I. Coordination with United States Army Corps of Engineers (USACE)
11 1. At locations in the Project where construction activities occur in areas where
12 USACE permits are required, meet all requirements set forth in each designated
13 permit.
14 J. Coordination within Railroad Permit Areas
15 1. At locations in the project where construction activities occur in areas where
16 railroad permits are required, meet all requirements set forth in each designated
17 railroad permit. This includes, but is not limited to, provisions for:
18 a. Flagmen
19 b. Inspectors
20 c. Safety training
21 d. Additional insurance
22 e. Insurance certificates
23 f. Other employees required to protect the right-of-way and property of the
24 Railroad Company from damage arising out of and/or from the construction of
25 the project. Proper utility clearance procedures shall be used in accordance
26 with the permit guidelines.
27 2. Obtain any supplemental information needed to comply with the railroad's
28 requirements.
29 3. Railroad Flagmen
30 a. Submit receipts to City for verification of working days that railroad flagmen
31 were personnel were present on Site.
32 K. Dust Control
33 1. Use acceptable measures to control dust at the Site.
34 a. If water is used to control dust, capture and properly dispose of waste water.
35 b. If wet saw cutting is performed, capture and properly dispose of slurry.
36 L. Employee Parking
37 1. Provide parking for employees at locations approved by the City.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised [Insert Revision Date]
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
01 35 13 - 6
SPECIAL PROJECT PROCEDURES
1 1.5 SUBMITTALS [NOT USED]
2 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
3 1.7 CLOSEOUT SUBMITTALS [NOT USED]
4 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
5 1.9 QUALITY ASSURANCE [NOT USED]
6 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
7 1.11 FIELD [SITE] CONDITIONS [NOT USED]
8 1.12 WARRANTY [NOT USED]
9 PART 2 - PRODUCTS [NOT USED]
10 PART 3 - EXECUTION [NOT USED]
11 END OF SECTION
12
13
Revision Log
DATE NAME SUMMARY OF CHANGE
July 2011
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised [Insert Revision Date]
Page 6 of 8
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project 41480
01 35 13 - 7
SPECIAL PROJECT PROCEDURES
Page 7 of 8
1 EXHIBIT A
2
3
4
5
6 Date:
7
8 CPN No.:
9 Project Name:
10 Mapsco Location:
11 Limits of Construction:
12
13
(To be printed on Contractor's Letterhead)
t jot t*%
15
16
17 THIS IS TO INFORM YOU THAT UNDER A CONTRACT WITH THE CITY OF FORT
18 WORTH, OUR COMPANY WILL WORK ON UTILITY LINES ON OR AROUND YOUR
19 PROPERTY.
20
21 CONSTRUCTION WILL BEGIN APPROXIMATELY SEVEN DAYS FROM THE DATE
22 OF THIS NOTICE.
23
24 IF YOU HAVE QUESTIONS ABOUT ACCESS, SECURITY, SAFETY OR ANY OTHER
25 ISSUE, PLEASE CALL:
26
27
28 Mr. <CONTRACTOR'S SUPERINTENDENT> AT <TELEPHONE NO.>
29
30 OR
31
32 Mr. <CITY INSPECTOR> AT < TELEPHONE NO.>
33
34 AFTER 4:30 PM OR ON WEEKENDS, PLEASE CALL (817) 392 8306
35
36
37
PLEASE KEEP THIS FLYER HANDY WHEN YOU CALL
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised [Insert Revision Date]
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
013513-8
SPECIAL PROJECT PROCEDURES
1
3
4
Data:
EXHIBIT B
FORT WORTH
DOE HO. XXXX
Project Name:
NOTICE OF TEMPORARY WATER SERVICE
INTERRUPTION
DUE TO UTILITY IMPROVEMENTS IN YOUR NEIGHBORHOOD, YOUR
WATER SERVICE WILL BE INTERRUPTED ON
BETWEEN THE HOURS OF AND
IF YOU HAVE QUESTIONS ABOUT THIS SHUT -OUT, PLEASE CALL:
MR. AT
(CONTRACTORS SUPERINTENDENT) (TELEPHONE NUMBER)
OR
MR. AT
(CITY INSPECTOR) (TELEPHONE NUMBER)
THIS INCONVENIENCE WILL BE AS SHORT AS POSSIBLE.
THANK YOU,
,CONTRACTOR
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised [Insert Revision Date]
Page 8 of 8
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project # 1480
014523-1
TESTING AND INSPECTION SERVICES
2
3 PART 1- GENERAL
SECTION 01 45 23
TESTING AND INSPECTION SERVICES
Page 1 of 2
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Testing and inspection services procedures and coordination
7 B. Deviations from this City of Fort Worth Standard Specification
8 1. None.
9 C. Related Specification Sections include, but are not necessarily limited to:
10 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
11 2. Division 1 — General Requirements
12 1.2 PRICE AND PAYMENT PROCEDURES
13 A. Measurement and Payment
14 1. Work associated with this Item is considered subsidiary to the various Items bid.
15 No separate payment will be allowed for this Item.
16 a. Contractor is responsible for performing, coordinating, and payment of all
17 Quality Control testing.
18 b. City is responsible for performing and payment for first set of Quality
19 Assurance testing.
20 1) If the first Quality Assurance test performed by the City fails, the
21 Contractor is responsible for payment of subsequent Quality Assurance
22 testing until a passing test occurs.
23 a) Final acceptance will not be issued by City until all required payments
24 for testing by Contractor have been paid in full.
25 1.3 REFERENCES [NOT USED]
26 1.4 ADMINISTRATIVE REQUIREMENTS
27 A. Testing
28 1. Complete testing in accordance with the Contract Documents.
29 2. Coordination
30 a. When testing is required to be performed by the City, notify City, sufficiently
31 in advance, when testing is needed.
32 b. When testing is required to be completed by the Contractor, notify City,
33 sufficiently in advance, that testing will be performed.
34 3. Distribution of Testing Reports
35 a. Electronic Distribution
36 1) Confirm development of Project directory for electronic submittals to be
37 uploaded to City's Buzzsaw site, or another external FTP site approved by
38 the City.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
014523-2
TESTING AND INSPECTION SERVICES
Page 2 of 2
1 2) Upload test reports to designated project directory and notify appropriate
2 City representatives via email of submittal posting.
3 3) Hard Copies
4 a) 1 copy for all submittals submitted to the Project Representative
5 b. Hard Copy Distribution (if required in lieu of electronic distribution)
6 1) Tests performed by City
7 a) Distribute 1 hard copy to the Contractor
8 2) Tests performed by the Contractor
9 a) Distribute 3 hard copies to City's Project Representative
10 4. Provide City's Project Representative with trip tickets for each delivered load of
11 Concrete or Lime material including the following information:
12 a. Name of pit
13 b. Date of delivery
14 c. Material delivered
15 B. Inspection
16 1. Inspection or lack of inspection does not relieve the Contractor from obligation to
17 perform work in accordance with the Contract Documents.
18 1.5 SUBMITTALS [NOT USED]
19 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
20 1.7 CLOSEOUT SUBMITTALS [NOT USED]
21 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
22 1.9 QUALITY ASSURANCE [NOT USED]
23 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
24 1.11 FIELD [SITE] CONDITIONS [NOT USED]
25 1.12 WARRANTY [NOT USED]
26 PART 2 - PRODUCTS [NOT USED]
27 PART 3 - EXECUTION [NOT USED]
28 END OF SECTION
29
30
Revision Log
DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Conlract 75, Part 1
CFW Project # 1480
01 50 00 - 1
TEMPORARY FACILITIES AND CONTROLS
Page 1 of4
2
SECTION 01 50 00
TEMPORARY FACILITIES AND CONTROLS
3 PART 1- GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Provide temporary facilities and controls needed for the Work including, but not
7 necessarily limited to:
8 a. Temporary utilities
9 b. Sanitary facilities
10 c. Storage Sheds and Buildings
11 d. Dust control
12 e. Temporary fencing of the construction site
13 B. Deviations from this City of Fort Worth Standard Specification
14 1. None.
15 C. Related Specification Sections include, but are not necessarily limited to:
16 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
17 2. Division 1 — General Requirements
18 1.2 PRICE AND PAYMENT PROCEDURES
19 A. Measurement and Payment
20 1. Work associated with this Item is considered subsidiary to the various Items bid.
21 No separate payment will be allowed for this Item.
22 1.3 REFERENCES [NOT USED]
23 1.4 ADMINISTRATIVE REQUIREMENTS
24 A. Temporary Utilities
25 1. Obtaining Temporary Service
26 a. Make arrangements with utility service companies for temporary services.
27 b. Abide by rules and regulations of utility service companies or authorities
28 having jurisdiction.
29 c. Be responsible for utility service costs until Work is approved for Final
30 Acceptance.
31 1) Included are fuel, power, light, heat and other utility services necessary for
32 execution, completion, testing and initial operation of Work.
33 2. Water
34 a. Contractor to provide water required for and in connection with Work to be
35 performed and for specified tests of piping, equipment, devices or other use as
36 required for the completion of the Work.
37 b. Provide and maintain adequate supply of potable water for domestic
38 consumption by Contractor personnel and City's Project Representatives.
39 c. Coordination
40 1) Contact City 1 week before water for construction is desired
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
01 5000-2
TEMPORARY FACILITIES AND CONTROLS
Page 2 of4
1 d. Contractor Payment for Construction Water
2 1) Obtain construction water meter from City for payment as billed by City's
3 established rates.
4 3. Electricity and Lighting
5 a. Provide and pay for electric powered service as required for Work, including
6 testing of Work.
7 1) Provide power for lighting, operation of equipment, or other use.
8 b. Electric power service includes temporary power service or generator to
9 maintain operations during scheduled shutdown.
10 4. Telephone
11 a. Provide emergency telephone service at Site for use by Contractor personnel
12 and others performing work or furnishing services at Site.
13 5. Temporary Heat and Ventilation
14 a. Provide temporary heat as necessary for protection or completion of Work.
15 b. Provide temporary heat and ventilation to assure safe working conditions.
16 B. Sanitary Facilities
17 1. Provide and maintain sanitary facilities for persons on Site.
18 a. Comply with regulations of State and local departments of health.
19 2. Enforce use of sanitary facilities by construction personnel at job site.
20 a. Enclose and anchor sanitary facilities.
21 b. No discharge will be allowed from these facilities.
22 c. Collect and store sewage and waste so as not to cause nuisance or health
23 problem.
24 d. Haul sewage and waste off -site at no less than weekly intervals and properly
25 dispose in accordance with applicable regulation.
26 3. Locate facilities near Work Site and keep clean and maintained throughout Project.
27 4. Remove facilities at completion of Project
28 C. Storage Sheds and Buildings
29 1. Provide adequately ventilated, watertight, weatherproof storage facilities with floor
30 above ground level for materials and equipment susceptible to weather damage.
31 2. Storage of materials not susceptible to weather damage may be on blocks off
32 ground.
33 3. Store materials in a neat and orderly manner.
34 a. Place materials and equipment to permit easy access for identification,
35 inspection and inventory.
36 4. Equip building with lockable doors and lighting, and provide electrical service for
37 equipment space heaters and heating or ventilation as necessary to provide storage
38 environments acceptable to specified manufacturers.
39 5. Fill and grade site for temporary structures to provide drainage away from
40 temporary and existing buildings.
41 6. Remove building from site prior to Final Acceptance.
42 D. Temporary Fencing
43 1. Provide and maintain for the duration or construction when required in contract
44 documents
45 E. Dust Control
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project # 1480
015000-3
TEMPORARY FACILITIES AND CONTROLS
Page 3 of 4
1 1. Contractor is responsible for maintaining dust control through the duration of the
2 project.
3 a. Contractor remains on -call at all times
4 b. Must respond in a timely manner
5 F. Temporary Protection of Construction
6 1. Contractor or subcontractors are responsible for protecting Work from damage due
7 to weather.
8 1.5 SUBMITTALS [NOT USED]
9 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
10 1.7 CLOSEOUT SUBMITTALS [NOT USED]
11 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
12 1.9 QUALITY ASSURANCE [NOT USED]
13 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
14 1.11 FIELD [SITE] CONDITIONS [NOT USED]
15 1.12 WARRANTY [NOT USED]
16 PART 2 - PRODUCTS [NOT USED]
17 PART 3 - EXECUTION [NOT USED]
18 3.1 INSTALLERS [NOT USED]
19 3.2 EXAMINATION [NOT USED]
20 3.3 PREPARATION [NOT USED]
21 3.4 INSTALLATION
22 A. Temporary Facilities
23 1. Maintain all temporary facilities for duration of construction activities as needed.
24 3.5 [REPAIR] / [RESTORATION]
25 3.6 RE -INSTALLATION
26 3.7 FIELD loR] SITE QUALITY CONTROL [NOT USED]
27 3.8 SYSTEM STARTUP [NOT USED]
28 3.9 ADJUSTING [NOT USED]
29 3.10 CLEANING [NOT USED]
30 3.11 CLOSEOUT ACTIVITIES
31 A. Temporary Facilities
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project 41480
015000-4
TEMPORARY FACILITIES AND CONTROLS
Page 4 of 4
1 1. Remove all temporary facilities and restore area after completion of the Work, to a
2 condition equal to or better than prior to start of Work.
3 3.12 PROTECTION [NOT USED]
4 3.13 MAINTENANCE [NOT USED]
5 3.14 ATTACHMENTS [NOT USED]
6 END OF SECTION
7
8
Revision Log
DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July I, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project # 1480
015526-1
STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
Page 1 of 3
2
SECTION 01 55 26
STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
3 PART 1 - GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Administrative procedures for:
7 a. Street Use Permit
8 b. Modification of approved traffic control
9 c. Removal of Street Signs
10 B. Deviations from this City of Fort Worth Standard Specification
11 1. None.
12 C. Related Specification Sections include, but are not necessarily limited to:
13 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
14 2. Division 1 — General Requirements
15 3. Section 34 71 13 — Traffic Control
16 1.2 PRICE AND PAYMENT PROCEDURES
17 A. Measurement and Payment
18 1. Work associated with this Item is considered subsidiary to the various Items bid.
19 No separate payment will be allowed for this Item.
20 1.3 REFERENCES
21 A. Reference Standards
22 1. Reference standards cited in this specification refer to the current reference standard
23 published at the time of the latest revision date logged at the end of this
24 specification, unless a date is specifically cited.
25 2. Texas Manual on Uniform Traffic Control Devices (TMUTCD).
26 1.4 ADMINISTRATIVE REQUIREMENTS
27 A. Traffic Control
28 1. General
29 a. When traffic control plans are included in the Drawings, provide Traffic
30 Control in accordance with Drawings and Section 34 71 13.
31 b. When traffic control plans are not included in the Drawings, prepare traffic
32 control plans in accordance with Section 34 71 13 and submit to City for
33 review.
34 1) Allow minimum 10 working days for review of proposed Traffic Control.
35 B. Street Use Permit
36 1. Prior to installation of Traffic Control, a City Street Use Permit is required.
37 a. To obtain Street Use Permit, submit Traffic Control Plans to City
38 Transportation and Public Works Department.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July I, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
01 55 26 - 2
STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
Page 2 of 3
1 1) Allow a minimum of 5 working days for permit review.
2 2) Contractor's responsibility to coordinate review of Traffic Control plans for
3 Street Use Permit, such that construction is not delayed.
4 C. Modification to Approved Traffic Control
5 1. Prior to installation traffic control:
6 a. Submit revised traffic control plans to City Department Transportation and
7 Public Works Department.
8 1) Revise Traffic Control plans in accordance with Section 34 71 13.
9 2) Allow minimum 5 working days for review of revised Traffic Control.
10 3) It is the Contractor's responsibility to coordinate review of Traffic Control
11 plans for Street Use Permit, such that construction is not delayed.
12 D. Removal of Street Sign
13 1. If it is determined that a street sign must be removed for construction, then contact
14 City Transportation and Public Works Department, Signs and Markings Division to
15 remove the sign.
16 E. Temporary Signage
17 1. In the case of regulatory signs, replace permanent sign with temporary sign meeting
18 requirements of the latest edition of the Texas Manual on Uniform Traffic Control
19 Devices (MUTCD).
20 2. Install temporary sign before the removal of permanent sign.
21 3. When construction is complete, to the extent that the permanent sign can be
22 reinstalled, contact the City Transportation and Public Works Department, Signs
23 and Markings Division, to reinstall the permanent sign.
24 F. Traffic Control Standards
25 1. Traffic Control Standards can be found on the City's Buzzsaw website.
26 1.5 SUBMITTALS [NOT USED]
27 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
28 1.7 CLOSEOUT SUBMITTALS [NOT USED]
29 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
30 1.9 QUALITY ASSURANCE [NOT USED]
31 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
32 1.11 FIELD [SITE] CONDITIONS [NOT USED]
33 1.12 WARRANTY [NOT USED]
34 PART 2 - PRODUCTS [NOT USED]
35 PART 3 - EXECUTION [NOT USED]
36 END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project # 1480
015526-3
STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
Revision Log
DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Page 3 of 3
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project 41480
015713-1
STORM WATER POLLUTION PREVENTION
1
2
3 PART 1- GENERAL
4 1.1 SUMMARY
SECTION 01 57 13
STORM WATER POLLUTION PREVENTION
Page 1 of 3
5 A. Section Includes:
6 1. Procedures for Storm Water Pollution Prevention Plans
7 B. Deviations from this City of Fort Worth Standard Specification
8 1. None.
9 C. Related Specification Sections include, but are not necessarily limited to:
10 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the
11 Contract
12 2. Division 1 — General Requirements
13 3. Section 31 25 00 — Erosion and Sediment Control
14 1.2 PRICE AND PAYMENT PROCEDURES
15 A. Measurement and Payment
16 1. Construction Activities resulting in less than 1 acre of disturbance
17 a. Work associated with this Item is considered subsidiary to the various Items
18 bid. No separate payment will be allowed for this Item.
19 2. Construction Activities resulting in greater than 1 acre of disturbance
20 a. Measurement and Payment shall be in accordance with Section 31 25 00.
21 1.3 REFERENCES
22 A. Abbreviations and Acronyms
23 1. Notice of Intent: NOI
24 2. Notice of Termination: NOT
25 3. Storm Water Pollution Prevention Plan: SWPPP
26 4. Texas Commission on Environmental Quality: TCEQ
27 5. Notice of Change: NOC
28 A. Reference Standards
29 1. Reference standards cited in this Specification refer to the current reference
30 standard published at the time of the latest revision date logged at the end of this
31 Specification, unless a date is specifically cited.
32 2. Integrated Storm Management (iSWM) Technical Manual for Construction
33 Controls
34 1.4 ADMINISTRATIVE REQUIREMENTS
35 A. General
36 1. Contractor is responsible for resolution and payment of any fines issued associated
37 with compliance to Stormwater Pollution Prevention Plan.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
015713-2
STORM WATER POLLUTION PREVENTION
Page 2 of 3
1 B. Construction Activities resulting in:
2 1. Less than 1 acre of disturbance
3 a. Provide erosion and sediment control in accordance with Section 31 25 00 and
4 Drawings.
5 2. 1 to less than 5 acres of disturbance
6 a. Texas Pollutant Discharge Elimination System (TPDES) General Construction
7 Permit is required
8 b. Complete SWPPP in accordance with TCEQ requirements
9 1) TCEQ Small Construction Site Notice Required under general permit
10 TXR150000
11 a) Sign and post at job site
12 b) Prior to Preconstruction Meeting, send 1 copy to City Department of
13 Transportation and Public Works, Environmental Division, (817) 392-
14 6088.
15 2) Provide erosion and sediment control in accordance with:
16 a) Section 31 25 00
17 b) The Drawings
18 c) TXR150000 General Permit
19 d) SWPPP
20 e) TCEQ requirements
21 3. 5 acres or more of Disturbance
22 a. Texas Pollutant Discharge Elimination System (TPDES) General Construction
23 Permit is required
24 b. Complete SWPPP in accordance with TCEQ requirements
25 1) Prepare a TCEQ NOI form and submit to TCEQ along with required fee
26 a) Sign and post at job site
27 b) Send copy to City Department of Transportation and Public Works,
28 Environmental Division, (817) 392-6088.
29 2) TCEQ Notice of Change required if making changes or updates to NOI
30 3) Provide erosion and sediment control in accordance with:
31 a) Section 31 25 00
32 b) The Drawings
33 c) TXR150000 General Permit
34 d) SWPPP
35 e) TCEQ requirements
36 4) Once the project has been completed and all the closeout requirements of
37 TCEQ have been met a TCEQ Notice of Termination can be submitted.
38 a) Send copy to City Department of Transportation and Public Works,
39 Environmental Division, (817) 392-6088.
40 1.5 SUBMITTALS
41 A. SWPPP
42 1. Submit in accordance with Section 01 33 00, except as stated herein.
43 a. Prior to the Preconstruction Meeting, submit a draft copy of SWPPP to the City
44 as follows:
45 1) 1 copy to the City Project Manager
46 a) City Project Manager will forward to the City Department of
47 Transportation and Public Works, Environmental Division for review
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project 41480
01 57 13 -3
STORM WATER POLLUTION PREVENTION
Page 3 of 3
1 B. Modified SWPPP
2 1. If the SWPPP is revised during construction, resubmit modified SWPPP to the City
3 in accordance with Section 01 33 00.
4 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
5 1.7 CLOSEOUT SUBMITTALS [NOT USED]
6 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
7 1.9 QUALITY ASSURANCE [NOT USED]
8 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
9 1.11 FIELD [SITE] CONDITIONS [NOT USED]
10 1.12 WARRANTY [NOT USED]
11 PART 2 - PRODUCTS [NOT USED]
12 PART 3 - EXECUTION [NOT USED]
13
14
15
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part I
CFW Project N1480
015813-1
TEMPORARY PROJECT SIGNAGE
2
3 PART 1- GENERAL
4 1.1 SUMMARY
SECTION 01 58 13
TEMPORARY PROJECT SIGNAGE
Page 1 of 3
5 A. Section Includes:
6 1. Temporary Project Signage Requirements
7 B. Deviations from this City of Fort Worth Standard Specification
8 1. None.
9 C. Related Specification Sections include, but are not necessarily limited to:
10 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
11 2. Division 1 — General Requirements
12 1.2 PRICE AND PAYMENT PROCEDURES
13 A. Measurement and Payment
14 1. Work associated with this Item is considered subsidiary to the various Items bid.
15 No separate payment will be allowed for this Item.
16 1.3 REFERENCES [NOT USED]
17 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]
18 1.5 SUBMITTALS [NOT USED]
19 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
20 1.7 CLOSEOUT SUBMITTALS [NOT USED]
21 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
22 1.9 QUALITY ASSURANCE [NOT USED]
23 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
24 1.11 FIELD [SITE] CONDITIONS [NOT USED]
25 1.12 WARRANTY [NOT USED]
26 PART 2 - PRODUCTS
27 2.1 OWNER -FURNISHED loR] OWNER-SUPPLIEDPRODUCTS [NOT USED]
28 2.2 EQUIPMENT, PRODUCT TYPES, AND MATERIALS
29 A. Design Criteria
30 1. Provide free standing Project Designation Sign in accordance with City's Standard
31 Details for project signs.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project#1480
015813-2
TEMPORARY PROJECT SIGNAGE
Page 2 of 3
1 B. Materials
2 1. Sign
3 a. Constructed of 3/4-inch fir plywood, grade A-C (exterior) or better
4 2.3 ACCESSORIES [NOT USED]
5 2.4 SOURCE QUALITY CONTROL [NOT USED]
6 PART 3 - EXECUTION
7 3.1 INSTALLERS [NOT USED]
8 3.2 EXAMINATION [NOT USED]
9 3.3 PREPARATION [NOT USED]
10 3.4 INSTALLATION
11 A. General
12 1. Provide vertical installation at extents of project.
13 2. Relocate sign as needed, upon request of the City.
14 B. Mounting options
15 a. Skids
16 b. Posts
17 c. Barricade
18 3.5 REPAIR / RESTORATION [NOT USED]
19 3.6 RE -INSTALLATION [NOT USED]
20 3.7 FIELD loR] SITE QUALITY CONTROL [NOT USED]
21 3.8 SYSTEM STARTUP [NOT USED]
22 3.9 ADJUSTING [NOT USED]
23 3.10 CLEANING [NOT USED]
24 3.11 CLOSEOUT ACTIVITIES [NOT USED]
25 3.12 PROTECTION [NOT USED]
26 3.13 MAINTENANCE
27 A. General
28 1. Maintenance will include painting and repairs as needed or directed by the City.
29 3.14 ATTACHMENTS [NOT USED]
30 END OF SECTION
31
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project 111480
01 58 13 -3
TEMPORARY PROJECT SIGNAGE
1
Revision Log
DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Page 3 of 3
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project # 1480
1
2
SECTION 01 60 00
PRODUCT REQUIREMENTS
01 60 00 - 1
PRODUCT REQUIREMENTS
Page 1 of 2
3 PART 1- GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. A listing of the approved products for use in the City
7 B. Deviations from this City of Fort Worth Standard Specification
8 I. None.
9 C. Related Specification Sections include, but are not necessarily limited to:
10 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
11 2. Division 1 — General Requirements
12 1.2 PRICE AND PAYMENT PROCEDURES [NOT USED]
13 1.3 REFERENCES [NOT USED]
14 1.4 ADMINISTRATIVE REQUIREMENTS
15 A. A list of City approved products for use is attached to this Section.
16 B. Only products specifically included on City's Standard Product List in these Contract
17 Documents shall be allowed for use on the Project.
18 1. Any subsequently approved products will only be allowed for use upon specific
19 approval by the City.
20 C. Any specific product requirements in the Contract Documents supersede similar
21 products included on the City's Standard Product List.
22 1. The City reserves the right to not allow products to be used for certain projects even
23 though the product is listed on the City's Standard Product List.
24 D. Although a specific product is included on City's Standard Product List, not all
25 products from that manufacturer are approved for use, including but not limited to, that
26 manufacturer's standard product.
27 E. See Section 01 33 00 for submittal requirements of Product Data included on City's
28 Standard Product List.
29 1.5 SUBMITTALS [NOT USED]
30 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
31 1.7 CLOSEOUT SUBMITTALS [NOT USED]
32 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
33 1.9 QUALITY ASSURANCE [NOT USED]
34 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project 41480
1 1.11 FIELD [SITE] CONDITIONS [NOT USED]
2 1.12 WARRANTY [NOT USED]
3 PART 2 - PRODUCTS [NOT USED]
4 PART 3 - EXECUTION [NOT USED]
5 END OF SECTION
6
7
01 60 00 - 2
PRODUCT REQUIREMENTS
Page 2 of 2
Revision Log
DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project # 1480
2
016600-1
PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 1 of4
SECTION 01 66 00
PRODUCT STORAGE AND HANDLING REQUIREMENTS
3 PART 1 - GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Scheduling of product delivery
7 2. Packaging of products for delivery
8 3. Protection of products against damage from:
9 a. Handling
10 b. Exposure to elements or harsh environments
11 B. Deviations from this City of Fort Worth Standard Specification
12 1. None.
13 C. Related Specification Sections include, but are not necessarily limited to:
14 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
15 2. Division 1 — General Requirements
16 1.2 PRICE AND PAYMENT PROCEDURES
17 A. Measurement and Payment
18 1. Work associated with this Item is considered subsidiary to the various Items bid.
19 No separate payment will be allowed for this Item.
20 1.3 REFERENCES [NOT USED]
21 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]
22 1.5 SUBMITTALS [NOT USED]
23 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
24 1.7 CLOSEOUT SUBMITTALS [NOT USED]
25 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
26 1.9 QUALITY ASSURANCE [NOT USED]
27 1.10 DELIVERY AND HANDLING
28 A. Delivery Requirements
29 1. Schedule delivery of products or equipment as required to allow timely installation
30 and to avoid prolonged storage.
31 2. Provide appropriate personnel and equipment to receive deliveries.
32 3. Delivery trucks will not be permitted to wait extended periods of time on the Site
33 for personnel or equipment to receive the delivery.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project # 1480
016600-2
PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 2 of 4
l 4. Deliver products or equipment in manufacturer's original unbroken cartons or other
2 containers designed and constructed to protect the contents from physical or
3 environmental damage.
4 5. Clearly and fully mark and identify as to manufacturer, item and installation
5 location.
6 6. Provide manufacturer's instructions for storage and handling.
7 B. Handling Requirements
8 1. Handle products or equipment in accordance with these Contract Documents and
9 manufacturer's recommendations and instructions.
10 C. Storage Requirements
11 1. Store materials in accordance with manufacturer's recommendations and
12 requirements of these Specifications.
13 2. Make necessary provisions for safe storage of materials and equipment.
14 a. Place loose soil materials and materials to be incorporated into Work to prevent
15 damage to any part of Work or existing facilities and to maintain free access at
16 all times to all parts of Work and to utility service company installations in
17 vicinity of Work.
18 3. Keep materials and equipment neatly and compactly stored in locations that will
19 cause minimum inconvenience to other contractors, public travel, adjoining owners,
20 tenants and occupants.
21 a. Arrange storage to provide easy access for inspection.
22 4. Restrict storage to areas available on construction site for storage of material and
23 equipment as shown on Drawings, or approved by City's Project Representative.
24 5. Provide off -site storage and protection when on -site storage is not adequate.
25 a. Provide addresses of and access to off -site storage locations for inspection by
26 City's Project Representative.
27 6. Do not use lawns, grass plots or other private property for storage purposes without
28 written permission of owner or other person in possession or control of premises.
29 7. Store in manufacturers' unopened containers.
30 8. Neatly, safely and compactly stack materials delivered and stored along line of
31 Work to avoid inconvenience and damage to property owners and general public
32 and maintain at least 3 feet from fire hydrant.
33 9. Keep public and private driveways and street crossings open.
34 10. Repair or replace damaged lawns, sidewalks, streets or other improvements to
35 satisfaction of City's Project Representative.
36 a. Total length which materials may be distributed along route of construction at
37 one time is 1,000 linear feet, unless otherwise approved in writing by City's
38 Project Representative.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project#1480
016600-3
PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 3 of 4
I 1.11 FIELD [SITE] CONDITIONS [NOT USED]
2 1.12 WARRANTY [NOT USED]
3 PART 2 - PRODUCTS [NOT USED]
4 PART 3 - EXECUTION
5 3.1 INSTALLERS [NOT USED]
6 3.2 EXAMINATION [NOT USED]
7 3.3 PREPARATION [NOT USED]
8 3.4 ERECTION [NOT USED]
9 3.5 REPAIR / RESTORATION [NOT USED]
10 3.6 RE -INSTALLATION [NOT USED]
11 3.7 FIELD [oR] SITE QUALITY CONTROL
12 A. Tests and Inspections
13 1. Inspect all products or equipment delivered to the site prior to unloading.
14 B. Non -Conforming Work
15 1. Reject all products or equipment that are damaged, used or in any other way
16 unsatisfactory for use on the project.
17 3.8 SYSTEM STARTUP [NOT USED]
18 3.9 ADJUSTING [NOT USED]
19 3.10 CLEANING [NOT USED]
20 3.11 CLOSEOUT ACTIVITIES [NOT USED]
21 3.12 PROTECTION
22 A. Protect all products or equipment in accordance with manufacturer's written directions.
23 B. Store products or equipment in location to avoid physical damage to items while in
24 storage.
25 C. Protect equipment from exposure to elements and keep thoroughly dry if required by
26 the manufacturer.
27 3.13 MAINTENANCE [NOT USED]
28 3.14 ATTACHMENTS [NOT USED]
29 END OF SECTION
30
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
016600-4
PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 4 of 4
Revision Log
DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project # 1480
01 70 00 - 1
MOBILIZATION AND REMOBILIZATION
2
3 PART 1- GENERAL
4 1.1 SUMMARY
SECTION 01 70 00
MOBILIZATION AND REMOBILIZATION
Page 1 of 3
5 A. Section Includes:
6 2. Mobilization and Demobilization
7 a. Mobilization:
8 1) Transportation of Contractor's personnel, equipment, and operating supplies
9 to the Site
10 2) Establishment of necessary general facilities for the Contractor's operation
11 at the Site
12 3) Premiums paid for performance and payment bonds
13 4) Transportation of Contractor's personnel, equipment, and operating supplies
14 to another location within the designated Site
15 5) Relocation of necessary general facilities for the Contractor's operation
16 from one location to another location on the Site.
17 b. Demobilization:
18 1) Transportation of Contractor's personnel, equipment, and operating supplies
19 away from the Site including disassembly
20 2) Site Clean-up
21 3) Removal of all buildings and/or other facilities assembled at the Site for this
22 Contract
23 c. Mobilization and Demobilization do not include activities for specific items of
24 work that are for which payment is provided elsewhere in the contract.
25 3. Remobilization
26 a. Remobilization for Suspension of Work specifically required in the Contract
27 Documents or as required by City includes:
28 1) Demobilization:
29 a) Transportation of Contractor's personnel, equipment, and operating
30 supplies from the Site including disassembly or temporarily securing
31 equipment, supplies, and other facilities as designated by the Contract
32 Documents necessary to suspend the Work.
33 b) Site Clean-up as designated in the Contract Documents
34 2) Remobilization:
35 a) Transportation of Contractor's personnel, equipment, and operating
36 supplies to the Site necessary to resume the Work.
37 b) Establishment of necessary general facilities for the Contractor's
38 operation at the Site necessary to resume the Work.
39 3) No Payments will be made for:
40 a) Mobilization and Demobilization from one location to another on the
41 Site in the normal progress of performing the Work.
42 b) Stand-by or idle time
43 c) Lost profits
44 3. Mobilizations and Demobilization for Miscellaneous Projects
45 a. Mobilization and Demobilization
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised June 7, 2012
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
01 70 00 - 2
MOBILIZATION AND REMOBILIZATION
Page 2 of 3
1 1) Mobilization shall consist of the activities and cost on a Work Order basis
2 necessary for:
3 a) Transportation of Contractor's personnel, equipment, and operating
4 supplies to the Site for the issued Work Order.
5 b) Establishment of necessary general facilities for the Contractor's
6 operation at the Site for the issued Work Order
7 2) Demobilization shall consist of the activities and cost necessary for:
8 a) Transportation of Contractor's personnel, equipment, and operating
9 supplies from the Site including disassembly for each issued Work
10 Order
11 b) Site Clean-up for each issued Work Order
12 c) Removal of all buildings or other facilities assembled at the Site for
13 each Work Oder
14 b. Mobilization and Demobilization do not include activities for specific items of
15 work for which payment is provided elsewhere in the contract.
16 4. Emergency Mobilizations and Demobilization for Miscellaneous Projects
17 a. A Mobilization for Miscellaneous Projects when directed by the City and the
18 mobilization occurs within 24 hours of the issuance of the Work Order.
19 B. Deviations from City of Fort Worth Standards
20 2. None
21 C. Related Specification Sections include but are not necessarily limited to
22 2. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the
23 Contract.
24 1.2 PRICE AND PAYMENT PROCEDURES
25 A. Measurement and Payment
26 2. Mobilization and Demobilization
27 a. Measurement and Payment
28 1) Work associated with this Item is considered subsidiary to the various items
29 bid. No separate payment will be allowed for this item.
30 3. Remobilization for suspension of Work as specifically required in the Contract
31 Documents
32 a. Measurement
33 1) Measurement for this Item shall be per each remobilization preformed.
34 b. Payment
35 1) The work performed in accordance with this Item will be paid for at the
36 unit price per each "Specified Remobilization" in accordance with Contract
37 Documents.
38 c. The price shall include:
39 1) Demobilization as described in Section 1.1.A.2.a.1)
40 2) Remobilization as described in Section 1.1.A.2.a.2)
41 d. No payments will be made for standby, idle time, or lost profits associated this
42 Item.
43 4. Remobilization for suspension of Work as required by City
44 a. Measurement and Payment
45 1) This shall be submitted as a Contract Claim in accordance with Article 10
46 of 00 72 00 General Conditions.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised June 7, 2012
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project # 1480
017000-3
MOBILIZATION AND REMOBILIZATION
Page 3 of 3
1 2) No payments will be made for standby, idle time, or lost profits associated
2 with this Item.
3 5. Mobilizations and Demobilizations for Miscellaneous Projects
4 a. Measurement
5 1) Measurement for this Item shall be for each Mobilization and
6 Demobilization required by the Contract Documents
7 b. Payment
8 1) The Work performed in accordance with this Item will be paid for at the
9 unit price per each "Work Order Mobilization" in accordance with
10 Contract Documents. Demobilization shall be considered subsidiary to
11 mobilization and shall not be paid for separately.
12 c. The price shall include
13 1) Mobilization as described in Section 1.1.A.3.a.1)
14 2) Demobilization as described in Section 1.1.A.3.a.2)
15 3) No payments will be made for standby, idle time, or lost profits associated
16 this Item.
17 6. Emergency Mobilizations and Demobilizations for Miscellaneous Projects
18 a. Measurement
19 1) Measurement for this Item shall be for each Mobilization and
20 Demobilization required by the Contract Documents
21 b. Payment
22 1) The Work performed in accordance with this Item will be paid for at the
23 unit price per each "Work Order Emergency Mobilization" in accordance
24 with Contract Documents. Demobilization shall be considered subsidiary
25 to mobilization and shall not be paid for separately.
26 c. The price shall include
27 1) Mobilization as described in Section 1.1.A.4.a)
28 2) Demobilization as described in Section 1.1.A.3.a.2)
29 3) No payments will be made for standby, idle time, or lost profits associated
30 this Item.
31 1.3 TO 1.12 [NOT USED]
32 PART 2 - PRODUCTS [NOT USED]
33 PART 3 - EXECUTION [NOT USED]
34
35
36
DATE
[2010 JAN 06]
END OF SECTION
Revision Log
NAME SUMMARY OF CHANGE
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised June 7, 2012
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
017123-1
CONSTRUCTION STAKING
2
3 PART 1- GENERAL
SECTION 01 71 23
CONSTRUCTION STAKING
Page 1 of 3
4 1.1 SUMMARY
5 A. Section includes:
6 1. Requirements for construction staking.
7 B. Deviations from this City of Fort Worth Standard Specification
8 1. None.
9 C. Related Specification Sections include, but are not necessarily limited to:
10 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
11 2. Division 1— General Requirements
12 1.2 PRICE AND PAYMENT PROCEDURES
13 A. Measurement and Payment
14 1. Work associated with this Item is considered subsidiary to the various Items bid.
15 No separate payment will be allowed for this Item.
16 1.3 REFERENCES [NOT USED]
17 1.4 ADMINISTRATIVE REQUIREMENTS
18 A. Construction Stakes
19 1. Construction staking will be performed by the City.
20 2. Coordination
21 a. Contact City's Project Representative at least 2 weeks in advance for
22 scheduling of Construction Staking.
23 3. General
24 a. It is the Contractor's responsibility to coordinate staking such that construction
25 activities are not delayed or negatively impacted.
26 b. Contractor is responsible for preserving and maintaining stakes furnished by
27 City.
28 c. If in the opinion of the City, a sufficient number of stakes or markings have
29 been lost, destroyed or disturbed, by Contractor's neglect such that the
30 contracted Work cannot take place, then the Contractor will be required to pay
31 the City for new staking with a 25 percent markup.
32 1) The cost for staking will be deducted from the payment due to the
33 Contractor for the Project.
34 1.5 SUBMITTALS
35 A. Submittals, if required, shall be in accordance with Section 01 33 00.
36 1. All submittals shall be approved by the Engineer or the City prior to delivery.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project#1480
01 71 23 -2
CONSTRUCTION STAKING
Page 2 of 3
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS
2 A. Certificates
3 1. Provide certificate certifying that elevations and locations of improvements are in
4 conformance or non-conformance with requirements of the Contract Documents.
5 a. Certificate must be sealed by a registered professional land surveyor in the
6 State of Texas.
7 B. Field Quality Control Submittals
8 1. Documentation verifying accuracy of field engineering work
9 1.7 CLOSEOUT SUBMITTALS [NOT USED]
10 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
11 1.9 QUALITY ASSURANCE
12 A. Use adequate numbers of skilled workmen who are thoroughly trained and experienced
13 in the necessary crafts and who are completely familiar with the specified requirements
14 and the methods needed for proper performance of the Work.
15 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
16 1.11 FIELD [SITE] CONDITIONS [NOT USED]
17 1.12 WARRANTY [NOT USED]
18 PART 2 - PRODUCTS [NOT USED]
19 PART 3 - EXECUTION
20 3.1 INSTALLERS [NOT USED]
21 3.2 EXAMINATION [NOT USED]
22 3.3 PREPARATION
23 A. Verify location and protect control points before commencing Work.
24 B. Notify City's Project Representative immediately of any discrepancies discovered.
25 3.4 APPLICATION [NOT USED]
26 3.5 REPAIR / RESTORATION [NOT USED]
27 3.6 RE -INSTALLATION [NOT USED]
28 3.7 FIELD 1oiz1 SITE QUALITY CONTROL
29 A. Preserve permanent reference points during progress of the Work.
30 B. Do not change or relocate reference points without approval from the City.
31 C. Utilize recognized engineering survey practices.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project#1480
017123-3
CONSTRUCTION STAKING
1 3.8 SYSTEM STARTUP [NOT USED]
2 3.9 ADJUSTING [NOT USED]
3 3.10 CLEANING [NOT USED]
4 3.11 CLOSEOUT ACTIVITIES [NOT USED]
5 3.12 PROTECTION [NOT USED]
6 3.13 MAINTENANCE [NOT USED]
7 3.14 ATTACHMENTS [NOT USED]
8 END OF SECTION
9
10
Revision Log
DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Page 3 of 3
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
017423-1
CLEANING
Page 1 of4
1 SECTION 0174 23
2 CLEANING
3 PART1- GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Intermediate and final cleaning for Work not including special cleaning of closed
7 systems specified elsewhere
8 B. Deviations from this City of Fort Worth Standard Specification
9 1. None.
10 C. Related Specification Sections include, but are not necessarily limited to:
11 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
12 2. Division 1 — General Requirements
13 3. Section 32 92 13 — Hydro -Mulching, Seeding and Sodding
14 1.2 PRICE AND PAYMENT PROCEDURES
15 A. Measurement and Payment
16 1. Work associated with this Item is considered subsidiary to the various Items bid.
17 No separate payment will be allowed for this Item.
18 1.3 REFERENCES [NOT USED]
19 1.4 ADMINISTRATIVE REQUIREMENTS
20 A. Scheduling
21 1. Schedule cleaning operations so that dust and other contaminants disturbed by
22 cleaning process will not fall on newly painted surfaces.
23 2. Schedule final cleaning upon completion of Work and immediately prior to final
24 inspection.
25 1.5 SUBMITTALS [NOT USED]
26 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
27 1.7 CLOSEOUT SUBMITTALS [NOT USED]
28 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
29 1.9 QUALITY ASSURANCE [NOT USED]
30 1.10 STORAGE, AND HANDLING
31 A. Storage and Handling Requirements
32 1. Store cleaning products and cleaning wastes in containers specifically designed for
33 those materials.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project # 1480
017423-4
CLEANING
Page 4 of 4
1 4. If no longer required for maintenance of erosion facilities, and upon approval by
2 City, remove erosion control from site.
3 5. Clean signs, lights, signals, etc.
4 3.11 CLOSEOUT ACTIVITIES [NOT USED]
5 3.12 PROTECTION [NOT USED]
6 3.13 MAINTENANCE [NOT USED]
7 3.14 ATTACHMENTS [NOT USED]
8 END OF SECTION
9
10
Revision Log
DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project#1480
2
3 PART1- GENERAL
SECTION 01 77 19
CLOSEOUT REQUIREMENTS
017719-1
CLOSEOUT REQUIREMENTS
Page 1 of 3
4 1.1 SUMMARY
5 A. Section Includes:
6 1. The procedure for closing out a contract
7 B. Deviations from this City of Fort Worth Standard Specification
8 1. None.
9 C. Related Specification Sections include, but are not necessarily limited to:
10 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
11 2. Division 1 — General Requirements
12 1.2 PRICE AND PAYMENT PROCEDURES
13 A. Measurement and Payment
14 1. Work associated with this Item is considered subsidiary to the various Items bid.
15 No separate payment will be allowed for this Item.
16 1.3 REFERENCES [NOT USED]
17 1.4 ADMINISTRATIVE REQUIREMENTS
18 A. Guarantees, Bonds and Affidavits
19 1. No application for final payment will be accepted until all guarantees, bonds,
20 certificates, licenses and affidavits required for Work or equipment as specified are
21 satisfactorily filed with the City.
22 B. Release of Liens or Claims
23 1. No application for final payment will be accepted until satisfactory evidence of
24 release of liens has been submitted to the City.
25 1.5 SUBMITTALS
26 A. Submit all required documentation to City's Project Representative.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project#1480
01 77 19 -2
CLOSEOUT REQUIREMENTS
Page 2 of 3
1 1.6 INFORMATIONAL SUBMITTALS [NOT USED]
2 1.7 CLOSEOUT SUBMITTALS [NOT USED]
3 PART 2 - PRODUCTS [NOT USED]
4 PART 3 - EXECUTION
5 3.1 INSTALLERS [NOT USED]
6 3.2 EXAMINATION [NOT USED]
7 3.3 PREPARATION [NOT USED]
8 3.4 CLOSEOUT PROCEDURE
9 A. Prior to requesting Final Inspection, submit:
10 1. Project Record Documents in accordance with Section 01 78 39
11 2. Operation and Maintenance Data, if required, in accordance with Section 01 78 23
12 B. Prior to requesting Final Inspection, perform final cleaning in accordance with Section
13 01 74 23.
14 C. Final Inspection
15 1. After final cleaning, provide notice to the City Project Representative that the Work
16 is completed.
17 a. The City will make an initial Final Inspection with the Contractor present.
18 b. Upon completion of this inspection, the City will notify the Contractor, in
19 writing within 10 business days, of any particulars in which this inspection
20 reveals that the Work is defective or incomplete.
21 2. Upon receiving written notice from the City, immediately undertake the Work
22 required to remedy deficiencies and complete the Work to the satisfaction of the
23 City.
24 3. Upon completion of Work associated with the items listed in the City's written
25 notice, inform the City, that the required Work has been completed. Upon receipt
26 of this notice, the City, in the presence of the Contractor, will make a subsequent
27 Final Inspection of the project.
28 4. Provide all special accessories required to place each item of equipment in full
29 operation. These special accessory items include, but are not limited to:
30 a. Specified spare parts
31 b. Adequate oil and grease as required for the first lubrication of the equipment
32 c. Initial fill up of all chemical tanks and fuel tanks
33 d. Light bulbs
34 e. Fuses
35 f. Vault keys
36 g. Handwheels
37 h. Other expendable items as required for initial start-up and operation of all
38 equipment
39 D. Notice of Project Completion
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
017719-3
CLOSEOUT REQUIREMENTS
Page 3 of 3
1 1. Once the City Project Representative finds the Work subsequent to Final Inspection
2 to be satisfactory, the City will issue a Notice of Project Completion (Green Sheet).
3 E. Supporting Documentation
4 1. Coordinate with the City Project Representative to complete the following
5 additional forms:
6 a. Final Payment Request
7 b. Statement of Contract Time
8 c. Affidavit of Payment and Release of Liens
9 d. Consent of Surety to Final Payment
10 e. Pipe Report (if required)
11 f. Contractor's Evaluation of City
12 g. Performance Evaluation of Contractor
13 F. Letter of Final Acceptance
14 1. Upon review and acceptance of Notice of Project Completion and Supporting
15 Documentation, in accordance with General Conditions, City will issue Letter of
16 Final Acceptance and release the Final Payment Request for payment.
17 3.5 REPAIR / RESTORATION [NOT USED]
18 3.6 RE -INSTALLATION [NOT USED]
19 3.7 FIELD loR] SITE QUALITY CONTROL [NOT USED]
20 3.8 SYSTEM STARTUP [NOT USED]
21 3.9 ADJUSTING [NOT USED]
22 3.10 CLEANING [NOT USED]
23 3.11 CLOSEOUT ACTIVITIES [NOT USED]
24 3.12 PROTECTION [NOT USED]
25 3.13 MAINTENANCE [NOT USED]
26 3.14 ATTACHMENTS [NOT USED]
27 END OF SECTION
28
29
Revision Log
DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
017823-3
OPERATION AND MAINTENANCE DATA
Page 3 of 5
1 5. Copy of each warranty, bond and service contract issued
2 a. Provide information sheet for City personnel giving:
3 1) Proper procedures in event of failure
4 2) Instances which might affect validity of warranties or bonds
5 C. Manual for Materials and Finishes
6 1. Submit 5 copies of complete manual in final form.
7 2. Content, for architectural products, applied materials and finishes:
8 a. Manufacturer's data, giving full information on products
9 1) Catalog number, size, composition
10 2) Color and texture designations
11 3) Information required for reordering special manufactured products
12 b. Instructions for care and maintenance
13 1) Manufacturer's recommendation for types of cleaning agents and methods
14 2) Cautions against cleaning agents and methods which are detrimental to
15 product
16 3) Recommended schedule for cleaning and maintenance
17 3. Content, for moisture protection and weather exposure products:
18 a. Manufacturer's data, giving full information on products
19 1) Applicable standards
20 2) Chemical composition
21 3) Details of installation
22 b. Instructions for inspection, maintenance and repair
23 D. Manual for Equipment and Systems
24 1. Submit 5 copies of complete manual in final form.
25 2. Content, for each unit of equipment and system, as appropriate:
26 a. Description of unit and component parts
27 1) Function, normal operating characteristics and limiting conditions
28 2) Performance curves, engineering data and tests
29 3) Complete nomenclature and commercial number of replaceable parts
30 b. Operating procedures
31 1) Start-up, break-in, routine and normal operating instructions
32 2) Regulation, control, stopping, shut -down and emergency instructions
33 3) Summer and winter operating instructions
34 4) Special operating instructions
35 c. Maintenance procedures
36 1) Routine operations
37 2) Guide to "trouble shooting"
38 3) Disassembly, repair and reassembly
39 4) Alignment, adjusting and checking
40 d. Servicing and lubrication schedule
41 1) List of lubricants required
42 e. Manufacturer's printed operating and maintenance instructions
43 f. Description of sequence of operation by control manufacturer
44 1) Predicted life of parts subject to wear
45 2) Items recommended to be stocked as spare parts
46 g. As installed control diagrams by controls manufacturer
47 h. Each contractor's coordination drawings
48 1) As installed color coded piping diagrams
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
01 78 23 - 4
OPERATION AND MAINTENANCE DATA
Page 4 of 5
1 i. Charts of valve tag numbers, with location and function of each valve
2 j. List of original manufacturer's spare parts, manufacturer's current prices, and
3 recommended quantities to be maintained in storage
4 k. Other data as required under pertinent Sections of Specifications
5 3. Content, for each electric and electronic system, as appropriate:
6 a. Description of system and component parts
7 1) Function, normal operating characteristics, and limiting conditions
8 2) Performance curves, engineering data and tests
9 3) Complete nomenclature and commercial number of replaceable parts
10 b. Circuit directories of panelboards
11 1) Electrical service
12 2) Controls
13 3) Communications
14 c. As installed color coded wiring diagrams
15 d. Operating procedures
16 1) Routine and normal operating instructions
17 2) Sequences required
18 3) Special operating instructions
19 e. Maintenance procedures
20 1) Routine operations
21 2) Guide to "trouble shooting"
22 3) Disassembly, repair and reassembly
23 4) Adjustment and checking
24 f. Manufacturer's printed operating and maintenance instructions
25 g. List of original manufacturer's spare parts, manufacturer's current prices, and
26 recommended quantities to be maintained in storage
27 h. Other data as required under pertinent Sections of Specifications
28 4. Prepare and include additional data when the need for such data becomes apparent
29 during instruction of City's personnel.
30 1.7 CLOSEOUT SUBMITTALS [NOT USED]
3 I 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
32 1.9 QUALITY ASSURANCE
33 A. Provide operation and maintenance data by personnel with the following criteria:
34 1. Trained and experienced in maintenance and operation of described products
35 2. Skilled as technical writer to the extent required to communicate essential data
36 3. Skilled as draftsman competent to prepare required drawings
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July I, 2011
Sanitary Sewer Rehab Contract 75, Part I
CFW Project #1480
017823-5
OPERATION AND MAINTENANCE DATA
1 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
2 1.11 FIELD [SITE] CONDITIONS [NOT USED]
3 1.12 WARRANTY [NOT USED]
4 PART 2 - PRODUCTS [NOT USED]
5 PART 3 - EXECUTION [NOT USED]
6 END OF SECTION
7
8
Revision Log
DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Page 5 of 5
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
017839-1
PROJECT RECORD DOCUMENTS
2
3 PART 1- GENERAL
4 1.1 SUMMARY
SECTION 01 78 39
PROJECT RECORD DOCUMENTS
Page 1 of4
5 A. Section Includes:
6 1. Work associated with the documenting the project and recording changes to project
7 documents, including:
8 a. Record Drawings
9 b. Water Meter Service Reports
10 c. Sanitary Sewer Service Reports
11 d. Large Water Meter Reports
12 B. Deviations from this City of Fort Worth Standard Specification
13 1. None.
14 C. Related Specification Sections include, but are not necessarily limited to:
15 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
16 2. Division 1 — General Requirements
17 1.2 PRICE AND PAYMENT PROCEDURES
18 A. Measurement and Payment
19 1. Work associated with this Item is considered subsidiary to the various Items bid.
20 No separate payment will be allowed for this Item.
21 1.3 REFERENCES [NOT USED]
22 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]
23 1.5 SUBMITTALS
24 A. Prior to submitting a request for Final Inspection, deliver Project Record Documents to
25 City's Project Representative.
26 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
27 1.7 CLOSEOUT SUBMITTALS [NOT USED]
28 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
29 1.9 QUALITY ASSURANCE
30 A. Accuracy of Records
31 1. Thoroughly coordinate changes within the Record Documents, making adequate
32 and proper entries on each page of Specifications and each sheet of Drawings and
33 other Documents where such entry is required to show the change properly.
34 2. Accuracy of records shall be such that future search for items shown in the Contract
35 Documents may rely reasonably on information obtained from the approved Project
36 Record Documents.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
017839-2
PROJECT RECORD DOCUMENTS
Page 2 of 4
1 3. To facilitate accuracy of records, make entries within 24 hours after receipt of
2 information that the change has occurred.
3 4. Provide factual information regarding all aspects of the Work, both concealed and
4 visible, to enable future modification of the Work to proceed without lengthy and
5 expensive site measurement, investigation and examination.
6 1.10 STORAGE AND HANDLING
7 A. Storage and Handling Requirements
8 1. Maintain the job set of Record Documents completely protected from deterioration
9 and from loss and damage until completion of the Work and transfer of all recorded
10 data to the final Project Record Documents.
11 2. In the event of loss of recorded data, use means necessary to again secure the data
12 to the City's approval.
13 a. In such case, provide replacements to the standards originally required by the
14 Contract Documents.
15 1.11 FIELD [SITE] CONDITIONS [NOT USED]
16 1.12 WARRANTY [NOT USED]
17 PART 2 - PRODUCTS
18 2.1 OWNER -FURNISHED loR] OWNER -SUPPLIED PRODUCTS [NOT USED]
19 2.2 RECORD DOCUMENTS
20 A. Job set
21 1. Promptly following receipt of the Notice to Proceed, secure from the City, at no
22 charge to the Contractor, 1 complete set of all Documents comprising the Contract.
23 B. Final Record Documents
24 1. At a time nearing the completion of the Work and prior to Final Inspection, provide
25 the City 1 complete set of all Final Record Drawings in the Contract.
26 2.3 ACCESSORIES [NOT USED]
27 2.4 SOURCE QUALITY CONTROL [NOT USED]
28 PART 3 - EXECUTION
29 3.1 INSTALLERS [NOT USED]
30 3.2 EXAMINATION [NOT USED]
31 3.3 PREPARATION [NOT USED]
32 3.4 MAINTENANCE DOCUMENTS
33 A. Maintenance of Job Set
34 1. Immediately upon receipt of the job set, identify each of the Documents with the
35 title, "RECORD DOCUMENTS - JOB SET".
CITY OF FORT WORTI-I
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project111480
01 78 39 - 3
PROJECT RECORD DOCUMENTS
Page 3 of 4
1 2. Preservation
2 a. Considering the Contract completion time, the probable number of occasions
3 upon which the job set must be taken out for new entries and for examination,
4 and the conditions under which these activities will be performed, devise a
5 suitable method for protecting the job set.
6 b. Do not use the job set for any purpose except entry of new data and for review
7 by the City, until start of transfer of data to final Project Record Documents.
8 c. Maintain the job set at the site of work.
9 3. Coordination with Construction Survey
10 a. At a minimum, in accordance with the intervals set forth in Section 01 71 23,
11 clearly mark any deviations from Contract Documents associated with
12 installation of the infrastructure.
13 4. Making entries on Drawings
14 a. Record any deviations from Contract Documents.
15 b. Use an erasable colored pencil (not ink or indelible pencil), clearly describe the
16 change by graphic line and note as required.
17 c. Date all entries.
18 d. Call attention to the entry by a "cloud" drawn around the area or areas affected.
19 e. In the event of overlapping changes, use different colors for the overlapping
20 changes.
21 5. Conversion of schematic layouts
22 a. In some cases on the Drawings, arrangements of conduits, circuits, piping,
23 ducts, and similar items, are shown schematically and are not intended to
24 portray precise physical layout.
25 1) Final physical arrangement is determined by the Contractor, subject to the
26 City's approval.
27 2) However, design of future modifications of the facility may require
28 accurate information as to the final physical layout of items which are
29 shown only schematically on the Drawings.
30 b. Show on the job set of Record Drawings, by dimension accurate to within 1
31 inch, the centerline of each run of items.
32 1) Final physical arrangement is determined by the Contractor, subject to the
33 City's approval.
34 2) Show, by symbol or note, the vertical location of the Item ("under slab", "in
35 ceiling plenum", "exposed", and the like).
36 3) Make all identification sufficiently descriptive that it may be related
37 reliably to the Specifications.
38 c. The City may waive the requirements for conversion of schematic layouts
39 where, in the City's judgment, conversion serves no useful purpose. However,
40 do not rely upon waivers being issued except as specifically issued in writing
41 by the City.
42 B. Final Project Record Documents
43 1. Transfer of data to Drawings
44 a. Carefully transfer change data shown on the job set of Record Drawings to the
45 corresponding final documents, coordinating the changes as required.
46 b. Clearly indicate at each affected detail and other Drawing a full description of
47 changes made during construction, and the actual location of items.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project # 1480
01 78 39 - 4
PROJECT RECORD DOCUMENTS
Page 4 of 4
1 c. Call attention to each entry by drawing a "cloud" around the area or areas
2 affected.
3 d. Make changes neatly, consistently and with the proper media to assure
4 longevity and clear reproduction.
5 2. Transfer of data to other Documents
6 a. If the Documents, other than Drawings, have been kept clean during progress of
7 the Work, and if entries thereon have been orderly to the approval of the City,
8 the job set of those Documents, other than Drawings, will be accepted as final
9 Record Documents.
10 b. If any such Document is not so approved by the City, secure a new copy of that
11 Document from the City at the City's usual charge for reproduction and
12 handling, and carefully transfer the change data to the new copy to the approval
13 of the City.
14 3.5 REPAIR / RESTORATION [NOT USED]
15 3.6 RE -INSTALLATION [NOT USED]
16 3.7 FIELD [oR] SITE QUALITY CONTROL [NOT USED]
17 3.8 SYSTEM STARTUP [NOT USED]
18 3.9 ADJUSTING [NOT USED]
19 3.10 CLEANING [NOT USED]
20 3.11 CLOSEOUT ACTIVITIES [NOT USED]
21 3.12 PROTECTION [NOT USED]
22 3.13 MAINTENANCE [NOT USED]
23 3.14 ATTACHMENTS [NOT USED]
24 END OF SECTION
25
26
Revision Log
DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1,2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
APPENDIX
GC-4.01 Availability of Lands
GC-4.02 Subsurface and Physical Conditions
GC-6.07 Wage Rates
GC-6.09 Permits and Utilities
GC-6.10 M&C
SRF-1 CWSRF Forms
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
017823-1
OPERATION AND MAINTENANCE DATA
2
3 PART 1- GENERAL
SECTION 01 78 23
OPERATION AND MAINTENANCE DATA
Page 1 of 5
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Product data and related information appropriate for City's maintenance and
7 operation of products furnished under Contract
8 2. Such products may include, but are not limited to:
9 a. Traffic Controllers
10 b. Irrigation Controllers (to be operated by the City)
11 c. Butterfly Valves
12 B. Deviations from this City of Fort Worth Standard Specification
13 1. None.
14 C. Related Specification Sections include, but are not necessarily limited to:
15 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
16 2. Division 1 — General Requirements
17 1.2 PRICE AND PAYMENT PROCEDURES
18 A. Measurement and Payment
19 1. Work associated with this Item is considered subsidiary to the various Items bid.
20 No separate payment will be allowed for this Item.
21 1.3 REFERENCES [NOT USED]
22 1.4 ADMINISTRATIVE REQUIREMENTS
23 A. Schedule
24 1. Submit manuals in final form to the City within 30 calendar days of product
25 shipment to the project site.
26 1.5 SUBMITTALS
27 A. Submittals shall be in accordance with Section 01 33 00 Submittal Procedures. All
28 submittals shall be approved by the City prior to delivery.
29 1.6 INFORMATIONAL SUBMITTALS
30 A. Submittal Form
31 1. Prepare data in form of an instructional manual for use by City personnel.
32 2. Format
33 a. Size: 8 %2 inches x 11 inches
34 b. Paper
35 1) 40 pound minimum, white, for typed pages
36 2) Holes reinforced with plastic, cloth or metal
37 c. Text: Manufacturer's printed data, or neatly typewritten
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July I, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project # 1480
017823-2
OPERATION AND MAINTENANCE DATA
Page 2 of 5
1 d. Drawings
2 1) Provide reinforced punched binder tab, bind in with text
3 2) Reduce larger drawings and fold to size of text pages.
4 e. Provide fly -leaf for each separate product, or each piece of operating
5 equipment.
6 1) Provide typed description of product, and major component parts of
7 equipment.
8 2) Provide indexed tabs.
9 f. Cover
10 1) Identify each volume with typed or printed title "OPERATING AND
11 MAINTENANCE INSTRUCTIONS".
12 2) List:
13 a) Title of Project
14 b) Identity of separate structure as applicable
15 c) Identity of general subject matter covered in the manual
16 3. Binders
17 a. Commercial quality 3-ring binders with durable and cleanable plastic covers
18 b. When multiple binders are used, correlate the data into related consistent
19 groupings.
20 4. If available, provide an electronic form of the O&M Manual.
21 B. Manual Content
22 1. Neatly typewritten table of contents for each volume, arranged in systematic order
23 a. Contractor, name of responsible principal, address and telephone number
24 b. A list of each product required to be included, indexed to content of the volume
25 c. List, with each product:
26 1) The name, address and telephone number of the subcontractor or installer
27 2) A list of each product required to be included, indexed to content of the
28 volume
29 3) Identify area of responsibility of each
30 4) Local source of supply for parts and replacement
31 d. Identify each product by product name and other identifying symbols as set
32 forth in Contract Documents.
33 2. Product Data
34 a. Include only those sheets which are pertinent to the specific product.
35 b. Annotate each sheet to:
36 1) Clearly identify specific product or part installed
37 2) Clearly identify data applicable to installation
38 3) Delete references to inapplicable information
39 3. Drawings
40 a. Supplement product data with drawings as necessary to clearly illustrate:
41 1) Relations of component parts of equipment and systems
42 2) Control and flow diagrams
43 b. Coordinate drawings with information in Project Record Documents to assure
44 correct illustration of completed installation.
45 c. Do not use Project Record Drawings as maintenance drawings.
46 4. Written text, as required to supplement product data for the particular installation:
47 a. Organize in consistent format under separate headings for different procedures.
48 b. Provide logical sequence of instructions of each procedure.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
GC-4.01 Availability of Lands
THIS PAGE LEFT INTENTIONALLY BLANK
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project It1480
Sanitary Sewer Replacement Contract 75 — Part 1
Parcel # _ / ROE
Doe # 6578 / WO# / P 258-709170148083; P 253-609170148083
Lots 1&2, Block 17, Byers & McCart Addition
3205 Cleburne Rd, Ft. Worth
CITY OF FORT WORTH
TEMPORARY RIGHT OF ENTRY
STATE OF TEXAS §
§
COUNTY OF TARRANT §
KNOW ALL BY THESE PRESENTS
That the undersigned, hereinafter referred to as "Grantor", does by these presents grant
and convey to the City of Fort Worth, TX, herein after referred to as "Grantee" a
temporary right of entry onto property described as Block 17, Lots 1 &2, Byers & McCart
Addition as shown on the deed recorded in Volume 0 Page 0 Tarrant County Deed
Records Fort Worth, Tarrant County, Texas, hereinafter referred to as the "Property", for
the purpose of disconnecting home/business from old water/sewer line, and
reconnecting to new water/sewer line. Upon execution of this agreement, Grantor will
grant Grantee and its contractor's access to the Property for the purpose stated herein,
until such time as the project is completed and approved by the Grantee, at which time
the above described temporary right of entry becomes void.
This Right of Entry shall include the right of Grantee and its employees, agents,
representatives, or contractors to access the aforementioned property.
TO HAVE AND TO HOLD the above described right of entry, together with all and
singular, the rights and appurtenances thereto, anywise belonging unto the said Grantee,
is successors and assigns, for the purposes set forth above.
Grantee shall restore the Property to the condition it was in immediately prior to
accessing the Property under this Right of Entry.
EXECUTED this the day of , 201
GRANTOR:
(Please Print) (Signature)
(Authorized Title) (Phone Number)
(Email Address)
TEMPORARY RIGHT OF ENTRY
Rev. 6/2007
Sanitary Sewer Replacement Contract 75 — Part 1
Parcel # _ / ROE
Doe # 6578 / WO# _ / P 258-709170148083; P 253-609170148083
Lots 6,7,8,9 Block 16, Byers & McCart Addition
3233 Cleburne Rd, Ft. Worth
CITY OF FORT WORTH
TEMPORARY RIGHT OF ENTRY
STATE OF TEXAS §
§
COUNTY OF TARRANT §
KNOW ALL BY THESE PRESENTS
That the undersigned, hereinafter referred to as "Grantor", does by these presents grant
and convey to the City of Fort Worth, TX, herein after referred to as "Grantee" a
temporary right of entry onto property described as Block 16, Lots 6,7,8,9, Byers &
McCart Addition as shown on the deed recorded in Volume 0 Page 0 Tarrant County
Deed Records Fort Worth, Tarrant County, Texas, hereinafter referred to as the
"Property", for the purpose of disconnectinE home/business from old water/sewer line,
and reconnecting to new water/sewer line. Upon execution of this agreement, Grantor
will grant Grantee and its contractor's access to the Property for the purpose stated
herein, until such time as the project is completed and approved by the Grantee, at which
time the above described temporary right of entry becomes void.
This Right of Entry shall include the right of Grantee and its employees, agents,
representatives, or contractors to access the aforementioned property.
TO HAVE AND TO HOLD the above described right of entry, together with all and
singular, the rights and appurtenances thereto, anywise belonging unto the said Grantee,
is successors and assigns, for the purposes set forth above.
Grantee shall restore the Property to the condition it was in immediately prior to
accessing the Property under this Right of Entry.
EXECUTED this the day of , 201_
GRANTOR:
(Please Print) (Signature)
(Authorized Title) (Phone Number)
(Email Address)
TEMPORARY RIGHT OF ENTRY
Rev. 6/2007
GC-4.02 Subsurface and Physical Conditions
The boring location diagram and the boring logs can be found attached. The complete Geotechnical
Report is available upon request.
Contact:
Paul Banschbach
Lockwood, Andrew, & Newnam, Inc.
1320 South University Dr., Suite 450
Fort Worth, TX 76107
817.820.0420
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project 1t1480
rraa110 Gorrondona & Associates
1 11710 North Freeway, Suite 700, Houston, TX 77060
7524 Jack Newell Blvd. So, Fort Worth, Texas 76118
Telephone: HOU: 281-469-3347; FW: 817-496-1424
Fax: HOU: 281-469.3594; FW: 817-496-1768
CLIENT Lockwood, Andrews & Newnam, Inc.
PROJECT NUMBER 12-0245
DATE STARTED 9/28/12
DRILLING CONTRACTOR StrataBore
DRILLING METHOD Auger
LOGGED BY DL
NOTES
COMPLETED 9/28/12
CHECKED BY VC
MATERIAL DESCRIPTION
CLAYEY SAND (SC) - Stiff, light brown and gray, with
calcareous nodules and gravel.
FAT CLAY (CH) - Stiff, brown, with calcareous nodules and
gravel.
a
LEAN CLAY (CL) TO SANDY LEAN CLAY (CL) - Stiff to very
CD 5 stiff, brown and light brown, with calcareous nodules.
With sand pockets at 4 feet.
Calcium deposits below 8 feet.
D
F-
z-
0
�-
0
10
U
z
0
0 _
0
W
0
n.
0
15 j
Bottom of hole at 15.0 feet.
m
w
0
U
V
N
4
N_
0
U
0
U
w
0
w
0
0
W
0)
W
N
BORING NUMBER B-01
PAGE 1 OF 1
PROJECT NAME City of Fort Worth Sewer Rehab, Contract 75
PROJECT LOCATION Fort Worth, Texas
GROUND ELEVATION HOLE SIZE
GROUND WATER LEVELS:
AT TIME OF DRILLING ---
AT END OF DRILLING ---
AFTER DRILLING ---
ATTERBERG i-
0 w z LIMITS w
_ o E-
�[0 W� �Z� �f Q� O
a2 O� m0> Yv �` a �~ 0 �~ OW OOa
z 0 oz 0 O >- OZ C7� Q rjo U)
W 0 F- �O _J JJ z
15-20-10
(30)
14-15-10
(25)
o 0 c) �' o_ g — z
a u
10
2.75 24 54 18 36 91
15
3.5 20
3.25 22 35 14 21 89
1.5 21
Gorrondona & Associates
111710 North Freeway, Suite 700, Houston, TX 77060
t 7524 Jack Newell Blvd. So, Fort Worth, Texas 76118
Telephone: HOU: 281-469-3347; FW: 817-496-1424
Fax: HOU: 281-469.3594; FW: 817-496-1768
CLIENT Lockwood, Andrews & Newnam, Inc.
PROJECT NUMBER 12-0245
DATE STARTED 9/28/12 COMPLETED 9/28/12
DRILLING CONTRACTOR StrataBore
DRILLING METHOD Auger 0 to 15 feet, Rock Coring from 15 to 20 feet
LOGGED BY DL CHECKED BY VC
NOTES
a a0
w q00
0
MATERIAL DESCRIPTION
FAT CLAY WITH SAND (CH) TO SANDY FAT CLAY (CH) -
Firm to hard, dark brown and brown, with gravel.
With calcareous nodules below 2 feet.
_ Sand pockets at 2 to 4 feet.
3
1-
5
rn
Z _
C7
0
O
O
15
_
ll1
-
c
cc
w- I- 1
r I
H
• 20
0
>>N
0
O
U
O
O
U
W
10
SANDY LEAN CLAY (CL) - Stiff, light brown and gray, with
limestone.
LIMESTONE - Hard, gray.
(Pawpaw Formation, Weno Limestone, and Denton Clay,
undivided and Fort Worth Limestone and Duck Creek
Formation, undivided)
Bottom of hole at 20.0 feet.
❑ RC
RC 88
(75)
BORING NUMBER B-02
PAGE 1 OF 1
PROJECT NAME City of Fort Worth Sewer Rehab, Contract 75
PROJECT LOCATION Fort Worth, Texas
GROUND ELEVATION HOLE SIZE
GROUND WATER LEVELS:
AT TIME OF DRILLING
AT END OF DRILLING
AFTER DRILLING ---
W
Z W o
F}- (0 LLI
W z
WCa WCI �Z-J I-C" Q. ~c�> F-Z p_
aDO� in0> ' �v a.�� �~ Sr?,�
Qz w Uz 0 O- o 5z0 �- ��
cn a. 0 0 n-
ST 4.5+ 11
ST 1.75 29
ST 1.25 34 57 22 35 86
ATTERBERG
LIMITS
UW
g
o_
ST 1.0 28 52 11 41 47
TCP 42
X SS
4-6-7
(13)
TCP; „ 100/1"
50/2" j
19
wt Gorrondona & Associates BORING NUMBER B-03
s 11710 North Freeway, Suite 700, Houston, TX 77060
! ! 7524 Jack Newell Blvd. So, Fort Worth, Texas 76118 PAGE 1 OF 1
r
Telephone: HOU: 281-469-3347; FW: 817-496-1424
MP/"`.��� Fax: HOU: 281-469.3594; FW: 817-496-1768
CLIENT Lockwood, Andrews & Newnam, Inc. PROJECT NAME City of Fort Worth Sewer Rehab, Contract 75
PROJECT NUMBER 12-0245 PROJECT LOCATION Fort Worth, Texas
DATE STARTED 9/28/12 COMPLETED 9/28/12 GROUND ELEVATION HOLE SIZE
DRILLING CONTRACTOR StrataBore GROUND WATER LEVELS:
DRILLING METHOD Auger 0 to 20 feet, Rock Coring from 20 to 25 feet AT TIME OF DRILLING ---
LOGGED BY DL CHECKED BY VC AT END OF DRILLING ---
NOTES AFTER DRILLING ---
U
o
uJ 0
0
N
a
sand pockets at 4 feet.
5
Light brown below 6 feet.
z_
1-
1-
0
Z
O
U _
1
U
O
o LEAN CLAY WITH SAND (CL) - Very stiff to hard, gray and
15 j light brown.
w
w_
CL
LIMESTONE - Very hard, gray.
20 I (Pawpaw Formation, Weno Limestone, and Denton Clay,
undivided and Fort Worth Limestone and Duck Creek
- - 1 Formation, undivided)
0
U
- - I
4_ I
0 25 I
0
U
U
w
MATERIAL DESCRIPTION
FAT CLAY (CH) TO SANDY FAT CLAY (CH) - Stiff to hard,
dark brown, with calcareous nodules.
10
Bottom of hole at 25.0 feet.
ATTERBERG F--
w o• iz W w a LIMITS w
wm WD >ZJ F-� Q� F� PZ U Z
o_= Oft ca-
m0> Y`-- o'er D sa.-- rn� �~ cn~ i=w Ovo
ow U
Qz 0 Uz O O- cL 5O �J gJ UZ W
cn r a o 0 o- .D v_
ST 4.5+ 21
ST 4.5+ 21
ST 4.5+ 13 57 20 37 75
SS 12-13-14
(27)
6-12-12
(24)
TCP 59
X SS
16-12-
50/5'
\TCP, 100/0" ,
RC 90
(78)
13
4.5+ 18
81
19 79
"d Gorrondona & Associates BORING NUMBER B-04
11710 North Freeway, Suite 700, Houston, TX 77060 PAGE 1 OF 1
7524 Jack Newell Blvd. So, Fort Worth, Texas 76118
Telephone: HOU: 281-469-3347; FW: 817-496-1424
Fax: HOU: 281-469.3594; FW: 817-496-1768
CLIENT Lockwood, Andrews & Newnam, Inc.
PROJECT NAME City of Fort Worth Sewer Rehab, Contract 75
PROJECT NUMBER 12-0245 PROJECT LOCATION Fort Worth, Texas
DATE STARTED 10/1/12 COMPLETED 10/1/12 GROUND ELEVATION HOLE SIZE
DRILLING CONTRACTOR StrataBore GROUND WATER LEVELS:
DRILLING METHOD Auger 0 to 20 feet, Rock Coring from 20 to 25 feet AT TIME OF DRILLING ---
LOGGED BY DL CHECKED BY VC AT END OF DRILLING ---
NOTES AFTER DRILLING ---
AT "ERBERG i—
U o I CO
w w wo IMITS w
CL Z CC
—
a a 0 MATERIAL DESCRIPTION �� > 0 9 D< w 0 > 0 z Q w w - r— j� (. 0��
o`_ CC Qz O mOZ o , o" > 0-o Ho Wv
0 co o a a U o — z
o
7-Inch ASPHALT at surface.
��// SANDY LEAN CLAY (CL) TO LEAN CLAY WITH SAND (CL)
Soft to very stiff, brown and reddish brown. ST 0.75 16
Sand pockets to 2 feet.
With calcareous nodules below 2 feet.
ST 0.5 17
1-_-
.
j
o
c? 5 ST 0.25 19
0
N SS 4-5 6 24 35 15 20 82
j (11)
3o
Brown and gray below 8 feet.
a - E. 4.25 24
0
j
10
z
z
o
U -
c Light brown and light gray below 13 feet.
15 / FS--; 4.25 20 47 20 27 81
z
0
c
cc
w j
w
LIMESTONE - Hard, gray. TCP, 100/3" ,
20 1 (Pawpaw Formation, Weno Limestone, and Denton Clay,
0 1 undivided and Fort Worth Limestone and Duck Creek
_ —. 1 Formation, undivided)
82
u I
o 1 RC (82)
N 1
0 25 1 1
Bottom of hole at 25.0 feet. \TCP1 , 100/1" ,
0
0
U
w
O
w
0
w
0
w
GC-6.07 Wage Rates
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
City of Fort Worth, Texas
Mayor and Council Communication
COUNCIL ACTION: Approved on 7/8/2008
DATE: Tuesday, July 08, 2008
LOG NAME: 30WAGE RATES
REFERENCE NO.: **G-16190
SUBJECT:
Adopt 2008 Prevailing Wage Rates for City -Awarded Public -Works Projects
RECOMMENDATION:
It is recommended that the City Council adopt the attached 2008 Prevailing Wage Rates for City -awarded
public works projects.
DISCUSSION:
Texas Government Code Chapter 2258 requires that a public body awarding a contract for public works
shall determine the general prevailing rate of per diem wages for each craft or type of worker needed to
execute the contract, and shall specify In the bid documents and in the contract the prevailing wage rates in
that locality.
Each year The Quoin Chapter of the Associated General Contractors, in conjunction with the Association of
Builders and Contractors (ABC) and the American Sub -Contractors Association (ASA), conducts a wage
rate survey for North Texas construction. The attached 2008 Prevailing Wage Rate data was compiled from
that survey.
FISCAL INFORMATION/CERTIFICATION:
The Finance Director certifies that this action will have no material effect on City funds.
TO Fund/Account/Centers FROM Fund/Account/Centers
Submitted for Citv Manaaer's Office bv: Fernando Costa (8476)
Oriainatina Department Head: . A. Douglas Rademaker (6157)
Additional Information Contact: Eric Bundy (7598)
HEAVY & HIGHWAY CONSTRUCTION
PREVAILING WAGE RATES 2008
Air Tool Operator $10.06
Asphalt Distributor Operator $13.99
Asphalt Paving Machine Operator $12,78
Asphalt Raker $11.01
Asphalt Shoveler $ 8.80
Batching Plant Weigher $14.15
Broom or Sweeper Operator $ 9,88
Bulldozer Operator $13.22 1
Carpenter $12.80
Concrete Finisher, Paving $12.85
Concrete Finisher, Structures $13.27
Concrete Paving Curbing Machine Operator $12.00
Concrete Paving Finishing Machine Operator $13.63
Concrete Paving Joint Sealer Operator $12,50
Concrete paving Saw Operator $13,56
Concrete Paving Spreader Operator $14,50
Concrete Rubber $10.61
Crane, Clamshell, Backhoe, Derrick, Dragline, Shovel Operator $14.12
Electrician $18.12
Flagger $ 8.43
Form Builder/Setter, Structures $11.63
Form Setter, Paving & Curb $11.83
Foundation Drill Operator, Crawler Mounted $13.67
Foundation Drill Operator, Truck Mounted $16.30 1
Front End Loader Operator $12.62
Laborer, Common $ 9.18
Laborer, Utility $10,65
Mechanic $16.97
Milling Machine Operator, Fine Grade $11,83
Mixer Operator $11,58
Motor Grader Operator, Fine Grade $15.20
Motor Grader Operator, Rough $14.50
Oiler $14,98
Painter, Structures $13.17
Pavement Marking Machine Operator $10.04 1
Pipelayer $11.04 1
Reinforcing Steel Setter, Paving $14.86
Reinforcing Steel Setter, Structure $16,29
Roller Operator, Pneumatic, Self -Propelled $11.07
Roller Operator, Steel Wheel, Flat Wheel/Tamping $10.92
Roller Operator, Steel Wheel, Plant Mix Pavement $11.28
Scraper Operator $11,42
Servicer $12.32
Slip Form Machine Operator $12.33 1
Spreader Box Operator $10.92 1
Tractor Operator, Crawler Type $12,60
Tractor Operator, Pneumatic $12,91
Traveling Mixer Operator $12.03
Truck Driver, Lowboy -Float $14.93
Truck Driver, Single Axle, Heavy $11.47
Truck Driver, Single Axle, Light $10,91
Truck Driver, Tandem Axle, Semi -Trailer $11.75
Truck Driver, Transit -Mix $12.08
Wagon Drill, Boring Machine, Post Hole Driller Operator $14.00
Welder $13.57
Work Zone Barricade Servicer $10.09
2008 PREVAILING WAGE RATES
CONSTRUCTION INDUSTRY
AC Mechanic $21.69 Plumber $20.43
AC Mechanic Helper $12.00 Plumber Helper 514.90 1
Acoustical Ceiling Mechanic $15.24 Reinforcing Steel Setter $10.00
Bricklayer/Stone Mason $19.12 Roofer $14.00
Bricklayer/Stone Mason Helper $10,10 Roofer Helper $10.00
Carpenter $16.23 Sheet Metal Worker $16.96
Carpenter Helper $11.91 Sheet Metal Worker Helper $12.31
Concrete Finisher $13.49 Sprinkler System Installer $18.00
Concrete Form Builder $13.12 Sprinkler System Installer Helper $9.00
Drywall Mechanic $14,62 Steel Worker Structural $17.43
Drywall Helper $10.91 Concrete Pump $20.50
Crane, Clamsheel, Backhoe, Derrick, nine
Drywall Taper $13.00 Shovel $17.76
Drywall Taper Helper $9.00 Forklift $12.63
Electrician (Journeyman) $20.20 Front End Loader $10.50
Electrician Helper $14.43 Truck Driver $14.91
Electronic Technician $19.86 Welder $16.06
Electronic Technician Helper $12.00 Welder Helper $9.75
Floor Layer (Resilient) $20.00
Floor Layer Helper $13.00
Glazier $18.00
Glazier Helper $13.00
Insulator $14.78
Insulator Helper $11.25
Laborer Common $10,27
Laborer Skilled $13.18
Lather $16.10
Painter $14.83
Painter Helper $8.00
Pipefitter $18.85
Pipefitter Helper $12.83
Plasterer $17.25
Plasterer Helper $12,25
GC-6.09 Permits and Utilities
THIS PAGE LEFT INTENTIONALLY BLANK
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project 111480
FORT WORTH & WESTERN RAILROAD COMPANY
Application for Temporary Right of Entry onto FWWR Property
Important: Attach a $500.00 application fee to this request and send with
engineering specifications, shoring plans and maps to:
Fort Worth & Western Railroad Company Tax ID: 75-2267711
Attention: Patsy Hayes
6300 Ridglea Place, Suite 1200
Fort Worth, TX 76116 Date of Application:
Applicant's Name: City of Fort Worth
Applicant's Address: 1000 Throckmorton St., Fort Worth, TX 76102
Applicant's Tax ID or SS No.:
Contact Person for Application: Robert Sauceda
Phone Number: (682) 432-5478
Email Address: Robert.Sauceda@FortWorthTexas.gov
Type of Crossing Requested:
0 Overhead (Aerial) Crossing
0 Grade Crossing
0 Private/Agricultural
0 Commercial
✓ Underground Crossing
0 Petroleum Pipeline (0 Oil 0 Gas 0 Other)
0 Water Line
✓ Sewage Line 4 Replace existing 10" san. sewer with proposed
12" ductile iron pipe sewer in steel casing
0 Electrical Line
0 Communications Line
0 Other (Explain below)
Size of Pipe
Applicant is a:
0 Public Utility
✓ Municipality
0 Water District
0 County of State
0 Common Carrier
0 Individual
0 Private (For Profit) Corporation
Line Voltage No. of Lines
Page 1
Temporary Right of Entry Application (Continues)
BRIEFLY DESCRIBE THE INTENDED USE OF THE CROSSING:
This crossing will be part of sanitary sewer rehabilitation project for the City of Fort Worth.
Contact information for individual signing Temporary Right of Entry Agreement
Name Address Phone Number
Project Location:
Fort Worth Tarrant TX
City County State
Railroad site location information:
0.1 Fort Worth Subdivision 60 ft. West of Centerline Benbrook Dr.
Mile Post Subdivision Other pertinent location details
Time period for beginning and ending of the project:
Start Date: March 2013 End Date: March 2014
Will you be working within 25-feet of the center of track?
(✓) No ( ) Yes (If yes, a flagman will be required. The cost is $100.00 an hour to you.)
Will there be any excavation involved? (✓) No ( ) Yes (Must comply with AREMA standards)
Note: Bore Pits off FWWR Right of Way
Application okayed by:
Date application okayed:
IMPORTANT: Application fee, engineer specification(s), shoring plans and maps
must be attached. Application without these items will be returned to you
and not considered by Fort Worth & Western Railroad Company until supplied.
Engineer specification and shoring plans will be sent to Chief Engineer for approval.
Allow 10 days for processing
FWWR 010 227 8/11
Page 2
FORT WORTH & WESTERN RAILROAD COMPANY
Application for Temporary Right of Entry onto FWWR Property
Important: Attach a $500.00 application fee to this request and send with
engineering specifications, shoring plans and maps to:
Fort Worth & Western Railroad Company Tax ID: 75-2267711
Attention: Patsy Hayes
6300 Ridglea Place, Suite 1200
Fort Worth, TX 76116 Date of Application:
Applicant's Name: City of Fort Worth
Applicant's Address: 1000 Throckmorton St., Fort Worth, TX 76102
Applicant's Tax ID or SS No.:
Contact Person for Application: Robert Sauceda
Phone Number: (682) 432-5478
Email Address: Robert.Sauceda@FortWorthTexas.eov
Type of Crossing Requested:
0 Overhead (Aerial) Crossing
0 Grade Crossing
0 Private/Agricultural
0 Commercial
✓ Underground Crossing
0 Petroleum Pipeline (0 Oil 0 Gas 0 Other)
0 Water Line
✓ Sewage Line --> Replace existing 12" san. sewer with proposed
12" ductile iron pipe sewer in steel casing
0 Electrical Line
0 Communications Line
0 Other (Explain below)
Size of Pipe
Applicant is a:
0 Public Utility
V Municipality
0 Water District
0 County of State
0 Common Carrier
0 Individual
0 Private (For Profit) Corporation
Line Voltage No. of Lines
Page 1
Temporary Right of Entry Application (Continues)
BRIEFLY DESCRIBE THE INTENDED USE OF THE CROSSING:
This crossing will be part of sanitary sewer rehabilitation project for the City of Fort Worth.
Contact information for individual signing Temporary Right of Entry Agreement
Name Address Phone Number
Project Location:
Fort Worth Tarrant TX
City County State
Railroad site location information:
0.3 Fort Worth Subdivision 12 ft. West of Centerline Devitt St.
Mile Post Subdivision Other pertinent location details
Time period for beginning and ending of the project:
Start Date: March 2013 End Date: March 2014
Will you be working within 25-feet of the center of track?
(✓) No ( ) Yes (If yes, a flagman will be required. The cost is $100.00 an hour to you.)
Will there be any excavation involved? (✓) No ( ) Yes (Must comply with AREMA standards)
Note: Bore Pits off FWWR Right of Way
Application okayed by:
Date application okayed:
IMPORTANT: Application fee, engineer specification(s), shoring plans and maps
must be attached. Application without these items will be returned to you
and not considered by Fort Worth & Western Railroad Company until supplied.
Engineer specification and shoring plans will be sent to Chief Engineer for approval.
Allow 10 days for processing
FWWR 010 227 8/11
Page 2
To be completed by FWWR
Job name
Sub/M.P.
TWC or Restricted?
FWWR Job Number
Brief Description
Est. calendar duration
Agreement name,
parties, effective date
CSJ if applicable
7r\cA?mArm
FORT WORTH & WESTERN
FLAGGING REQUEST FORM
For questions, scheduling, cancellation:
Cancellations must be made by phone (no
voicemail) 24-hours in advance.
Rich Marion
National Railway Safety Safety Services
(m) 513.266.2130, (o) 972.516.8608
Submit form by email: djg@fwwr.net
Current flagging information
• Flagger required when within 25' of center line of track with men, material or equipment
• Flagger may be required at any time work is performed by a third party in FWWR right-of-way
• $100.00/hour, eight -hour minimum per day = STANDARD RATE
• Flagging day (8-hour minimum) includes travel time, job briefing time, flag set up time
• Rates include all applicable taxes; flagging billable monthly, Net 30 basis, billed per project agreement
• $150.00/hour (1-'/2 time) from eight to twelve hours = OVERTIME RATE
• Projects with a flagging day up to 12 hours per 24-hour period require a single flagger*
• Projects with a flagging day from 13 to 16 hours per 24-hour period require two eight -hour flagger shifts
• Projects with a flagging day from 16 to 24 hours per 24-hour period require three eight -hour flaggers shifts
• Flagging should be scheduled no less than 48-hours in advance
• Cancellations must be made by phone (no voicemail) 24-hours in advance
To be completed by Requestor
Company Name
Contact Name/Title
Phone numbers
Email Address
Fax Number
Mailing Address
for Invoices and/or
correspondence
Brief Description of
Planned Work. Note
portions within 25' of
center line.
Recommend
attaching exhibit with
submittal of this form.
FWWR 010 238 10/26/11
FWWR TRACK DEPARTMENT MEMO
To: Contractors/Consultants working on FWWR property (or trackage rights property)
From: D. Guido, Chief Engineer
Date: May 5, 2011
Subject: Roadway Worker Protection/On-Track Safety Orientation for Contractors on FWWR
Fort Worth & Western Railroad requires all personnel who will be in the right-of-way to participate in the FWWR
Roadway Worker Protection/On-Track Safety (RWP/OTS) Contractor Orientation Program. The program is designed to
help personnel avoid putting themselves in a POSITION OF PERIL on our property. This is accomplished through basic
training on how to stay safe and aware around live railroad tracks.
FWWR's training contractor is National Railroad Safety Services (NRSS). Your contact for scheduling, cancellations or
questions is Rich Marion at: (513) 266-2130 or email: rmarion@nrssinc.net.
Locations:
1. FWWR Hodge Yard, 2495 E. Long Avenue, Fort Worth, TX 76106. Capacity 15.
2. NRSS Training Facility, 730 E. Park Boulevard, Suite 108, Plano, TX 75074. Capacity 20.
3. Your facility (or you rent facility) — additional charges include trainer's travel time/mileage.
MAP AND
DIRECTIONS
next page
The orientation session generally runs from 45 minutes to an hour in duration, including a 25-question multiple-choice
exam. Only participants passing the examination will be permitted on the property. A qualification card will be issued
to each participant after the exam, indicating training date; training is good for a period of twelve months.
Fee schedule (2011/2012 calendar vear):
• 1 to 4 individuals = $220.00.
• Each additional individual = $55.00.
• Maximum class size in FORT WORTH = 15; Maximum class size in PLANO = 20.
• Training hosted at your facility: $50/hour instructor travel time and $0.55/mile.
Scheduling:
• Classes will be scheduled between the hours of 8:OOAM-4:OOPM CST, Monday through Friday.
• NRSS requires three business days (72 hours) advanced notice for scheduling.
• Scheduling is first -come -first -serve basis.
• Your contact for scheduling is Rich Marion at: (513) 266-2130 or email: rmarion@nrssinc.net
• IF ANY PARTICIPANTS REQUIRE SPECIAL ACCOMODATIONS NOTIFY NRSS DURING SCHEDULING.
• If participants require training/materials in Spanish request bilingual training during scheduling.
Additional instructions:
• Cancellations must be made by 4:OOPM CST weekday prior to scheduled training.
• Payment must be made in full prior to or same day of training.
• NRSS reserves the right to cancel because of weather conditions with no charge to client. Class will be
rescheduled at the earliest opportunity.
• Travel time is portal to portal time from Plano, TX location.
• Returned/bounced check fee $35.00. Qualification badge replacement fee $10.00.
• Each participant must have a photo ID before taking training class.
TRAINING WILL BE IN THE ENGLISH LANGUAGE
If you require English/Spanish instruction and materials you must request this during scheduling.
TRACK DEPARTMENT DO IT RIGHT EVERY TIME and don't put yourself in a POSITION OF PERIL
FWWR Hodge Yard, 2495 E. Long Avenue, Fort Worth, TX 76106
From I-35E in Fort Worth heading south on 35:
• Exit # 54B, Papurt and take an immediate right on
Braswell Drive (near Conoco) at bottom of ramp
• Turn right on Long Avenue; cross railroad tracks
and turn left into FWWR driveway
• Cross railroad track and turn left — park in gravel
parking area; training room is across driveway,
door on left with yellow sticker
From I-35E in Fort Worth heading north on 35:
• Exit # 54C, 33rd/Long — continue through stop sign,
continue on access road
• At the "Y" in the access road at bottom of ramp
stay to the right but then turn under freeway
• Turn right on Long Avenue; cross railroad tracks
and turn left into FWWR driveway
• Cross railroad track and turn left — park in gravel
parking area; Training room is across driveway,
door on left with yellow sticker
T?4u16 Y,ugt"
Foil Worl1
Gi.1!A, AO. 4.4
`. ,.
A? :1101 7yvz Yrr;th
Kricit,tni, Sh.p n finninn op
E GoriO Ave
vog St
Reiable,
YeiL '
Erfitgm:..M •
r
CtaChre EI
halo Pi.nrg
HQ
�' Kentaatn ;limo Si
NE 380 SI _
r Sr ;yard:.
!Cr•nri',!h •
NE 36.0
NE 3501 SI NESth SI
NE 33rd St
hysseektupe
i pall Systems
NRSS Training Facility, 730 E. Park Boulevard, Suite 108, Plano, TX 75074
From Highway 75 in Plano heading north on 75:
• Exit # 29 for 15th Street and go about half a mile
on access road
• Turn right on E. Central Parkway (by Denny's
Restaurant) and go one-half mile
• Driveway entrance to complex is on the left side —
look for "RMB Realtor" sign.
• NRSS building is Building 730 — go to Suite 108
From Highway 75 in Plano heading south on 75:
• Exit # 29A on North Central Express Way
• Go about one mile and watch for Park Boulevard
sign (will be on the right-hand side)
• Turn right onto Chisholm Place; turn right onto W
Park Boulevard at traffic light
• Go over freeway
• Driveway entrance to complex is on the right-
hand side — look for "Brandywine Place" sign on
right
• NRSS building is Building 730 — go to Suite 108
cS'"ki"lnM1 TRACK DEPARTMENT
—LV'V V ISt'1.
lirer5+11; f t
.WIVN'FS
iudnSPm,
6 Toad
RgA"bLc4r
3
0
Irk B- lvd
• s
=bourn r't u•nr
Or
4
e`
ci
I anrotr Hn���r 11
Enlemase
7b
W Park Blvd E Park BO
DO IT RIGHT EVERY TIME and don't put yourself in a POSITION OF PERIL
Exult
JONES LANG
LASALLE.
July 29, 2013
Mr. Robert Sauceda
City of Fort Worth
1000 Throckmorton Street
Fort Worth, Texas 76102
Dear Mr. Sauceda:
Jones Lang LaSalle Americas, Inc.
4300 Amon Carter, Suite 100
Fort Worth, Texas 76155
tel +1 817-230-2600, fax +1 817 306-8265
Tracking no. 13-47134
Enclosed please find one (1) fully executed Pipeline Agreement between BNSF and the City
of Fort Worth. A copy of the executed Agreement(s) must be available upon request at
the job site allowing authorization to do the work. Please contact the Roadmaster at
telephone (817) 224-7009 or cell phone (817) 304-3549 as listed below, at least ten (10)
days in advance of any entry and BEFORE YOU DIG, CALL 1-800-533-2891.
If you have any questions or need additional information please contact me at (817) 230-
2627.
Sin
Annette Jeri ins
Sr. Contract Specialist
Enclosure
cc: Larry Wilson, BNSF; Iarrv.wilsonta'7.bnsf.com
Tracking No. 13-47134
PIPELINE LICENSE
THIS PIPELINE LICENSE ("License") is made to be effective July 30, 2013 (the "Effective Date")
by and between BNSF RAILWAY COMPANY, a Delaware corporation ("Licensor") and CITY OF FORT
WORTH, TEXAS, a Texas corporation ("Licensee").
NOW THEREFORE, in consideration of the mutual covenants contained herein, the parties agree
to the following:
GENERAL
1. Licensor hereby grants Licensee a non-exclusive license, subject to all rights, interests, and
estates of third parties, including, without limitation, any leases, use rights, easements, liens, or other
encumbrances, and upon the terms and conditions set forth below, to construct and maintain, in strict
accordance with the drawings and specifications approved by Licensor as part of Licensee's application
process (the "Drawings and Specifications"), one (1) existing pipeline, eight (8) inches in diameter (the
"PIPELINE), across or along Licensor's rail corridor at or near the station of Fort Worth, County of
Tarrant, State of Texas, Line Segment 7500, Opposite Mile Post 342.0 as shown on the attached Drawing
No. 1-57132, dated March 13, 2013, attached hereto as Exhibit "A" and incorporated herein by reference
(the "Premises").
2. Licensee shall not disturb any improvements of Licensor or Licensor's existing lessees, licensees,
easement beneficiaries or lien holders, if any, or interfere with the use, repair, maintenance or
replacement of such improvements.
3. Licensee shall use the Premises solely for construction, maintenance, and use of the PIPELINE in
accordance with the Drawings and Specifications. The PIPELINE shall carry sanitary sewage, and
Licensee shall not use the PIPELINE to carry any other material or use the Premises for any other
purpose.
4. In case of the eviction of Licensee by anyone owning or claiming title to or any interest in the
Premises, or by the abandonment by Licensor of the affected rail corridor, Licensor shall not be liable (i)
to refund Licensee any compensation paid hereunder, except for the pro-rata part of any recurring charge
paid in advance, or (ii) for any damage Licensee sustains in connection therewith.
5. Any contractors or subcontractors performing work on the PIPELINE or entering the Premises on
behalf of Licensee shall be deemed servants and agents of Licensee for purposes of this License.
TERM
6. This License shall commence on the Effective Date and shall continue for a period of Twenty-five
(25) years, subject to prior termination as hereinafter described, and shall continue thereafter on a month -
to -month basis unless terminated by either party giving thirty (30) days prior written notice.
COMPENSATION
7. (a) Licensee shall pay Licensor, prior to the Effective Date, the sum of Three Thousand and
No/100 Dollars ($3,000.00) as compensation for the use of the Premises.
(b) Licensee agrees to reimburse Licensor (pursuant to the terms of Section 7(c) below) for all
costs and expenses incurred by Licensor in connection with Licensee's use of the Premises or the
presence, construction and maintenance of the PIPELINE, including but not limited to the furnishing of
Licensor's flaggers and any vehicle rental costs incurred. Licensee shall bear the cost of flagger services
Form 424; Rev 2-9-12
-1-
Tracking No. 13-47134
and other safety measures provided by Licensor, when deemed necessary by Licensor's representative.
Flagging costs shall include, but not be limited to, the following: pay for at least an eight (8) hour basic
day with time and one-half or double time for overtime, rest days and holidays (as applicable); vacation
allowance; paid holidays (as applicable); Licensor and unemployment insurance; public liability and
property damage insurance; health and welfare benefits; transportation; meals; lodging and supervision.
Negotiations for Licensor labor or collective bargaining agreements and rate changes authorized by
appropriate Federal authorities may increase flagging rates. Flagging rates in effect at the time of
performance by the flaggers will be used to calculate the flagging costs pursuant to this Section 7(b).
Licensor shall give Licensee at least forty-eight (48) hours notice of its intent to provide flaggers to the
extent the same is reasonably practicable.
(c) All invoices are due thirty (30) days after the date of invoice. In the event that Licensee
shall fail to pay any monies due to Licensor within thirty (30) days after the invoice date, then Licensee
shall pay interest on such unpaid sum from the due date until paid at an annual rate equal to the lesser of
(i) the prime rate last published in The Wall Street Journal in the preceding December plus two and one-
half percent (2-1/2%), or (ii) the maximum rate permitted by law.
COMPLIANCE WITH LAWS
8. (a) Licensee shall observe and comply with any and all laws, statutes, regulations, ordinances,
orders, covenants, restrictions, or decisions of any court of competent jurisdiction ("Legal
Requirements") relating to the construction, maintenance, and use of the PIPELINE and the use of the
Premises.
(b) Prior to entering the Premises, Licensee shall and shall cause its contractor(s) to comply
with all of Licensor's applicable safety rules and regulations. Licensee must ensure that each of its
employees, contractors, agents or invitees entering upon the Premises completes the safety training
program at the Website "www.contractororientation.com" (the "Safety Orientation") within one year prior
to entering upon the Premises. Additionally, Licensee must ensure that each and every employee of
Licensee, its contractors, agents and invitees possess a card certifying completion of the Safety
Orientation prior to entering upon the Premises. Licensee must renew the Safety Orientation annually.
DEFINITION OF COST AND EXPENSE
9. For the purpose of this License, "cost" or "costs", "expense" or "expenses" includes, but is not
limited to, actual labor and material costs including all assignable additives, and material and supply costs
at current value where used.
RIGHT OF LICENSOR TO USE
10. Licensor excepts and reserves the right, to be exercised by Licensor and any other parties who
may obtain written permission or authority from Licensor:
(i)
to maintain, use, operate, repair, replace, modify and relocate any utility, power or
communication pipe/lines/cables and appurtenances (other than the PIPELINE) and other
facilities or structures of like character upon, over, under or across the Premises existing as
of the Effective Date;
(ii) to construct, maintain, renew, use, operate, change, modify and relocate any tracks or
additional facilities, structures and related appurtenances upon, over, under or across the
Premises; or
2-
Form 424; Rev 2-9-12
Tracking No. 13-47134
(iii) to use the Premises in any manner as Licensor in its sole discretion deems appropriate,
provided Licensor uses all commercially reasonable efforts to avoid material interference
with the use of the Premises by Licensee for the purpose specified in Section 3 above.
LICENSEE'S OPERATIONS
11. (a) Licensee shall notify Licensor's Roadmaster, Larry Wilson at Iarrv.wilsonccx7.bnsf.com or
telephone (817) 224-7009 or cell phone (817) 304-3549, at least ten (10) business days prior to
installation of the PIPELINE and prior to entering the Premises for any subsequent maintenance thereon.
In the event of emergency, Licensee shall notify Licensor of Licensee's entry onto the Premises at the
telephone number above as soon as practicable and shall promptly thereafter follow up with written notice
of such entry.
(b) While on the Premises, Licensee shall use only public roadways to cross from one side of
Licensor's tracks to the other.
12. (a) Under no conditions shall Licensee be permitted to conduct any tests, investigations or any
other activity using mechanized equipment and/or machinery, or place or store any mechanized
equipment, tools or other materials, within twenty-five (25) feet of the centerline of any railroad track on
the Premises unless Licensee has obtained prior written approval from Licensor. Licensee shall, at its
sole cost and expense, perform all activities on and about the Premises in such a manner as not at any
time to be a source of danger to or interference with (i) the existence or use of present or future tracks,
roadbeds or property of Licensor, (ii) the safe operation and activities of Licensor or existing third parties,
or (iii) the rights or interests of third parties. If ordered to cease using the Premises at any time by
Licensor's personnel due to any hazardous condition, Licensee shall immediately do so. Notwithstanding
the foregoing right of Licensor, the parties agree that Licensor has no duty or obligation to monitor
Licensee's use of the Premises to determine the safe nature thereof, it being solely Licensee's
responsibility to ensure that Licensee's use of the Premises is safe. Neither the exercise nor the failure by
Licensor to exercise any rights granted in this Section will alter the liability allocation provided by this
License.
(b) Licensee shall, at its sole cost and expense, construct and maintain the PIPELINE in such
a manner and of such material that it will not at any time be a source of danger to or interference with (i)
the existence or use of present or future tracks, roadbeds, or property of Licensor, (ii) the safe operation
and activities of Licensor or existing third parties, or (iii) the rights or interests of third parties. The
construction of the PIPELINE shall be completed within one (1) year of the Effective Date, and any
subsequent maintenance shall be completed within one (1) year of initiation, Upon completion of the
construction of the PIPELINE and after performing any subsequent maintenance thereon, Licensee shall,
at Licensee's own cost and expense, restore the Premises to substantially their state as of the Effective
Date, unless otherwise approved in advance by Licensor in writing. On or before expiration or termination
of this License for any reason, Licensee shall, at its sole cost and expense, surrender the Premises to
Licensor pursuant to the terms and conditions set forth in Section 26 hereof.
(c) Licensor may direct one or more of its field engineers to observe or inspect the
construction and/or maintenance of the PIPELINE at any time for compliance with the Drawings and
Specifications and Legal Requirements. If ordered at any time to halt construction or maintenance of the
PIPELINE by Licensor's personnel due to non-compliance with the same or any other hazardous
condition, Licensee shall immediately do so. Notwithstanding the foregoing right of Licensor, the parties
agree that Licensor has no duty or obligation to observe or inspect, or to halt work on, the PIPELINE, it
being solely Licensee's responsibility to ensure that the PIPELINE is constructed and maintained in strict
accordance with the Drawings and Specifications and in a safe and workmanlike manner in compliance
with all terms hereof. Neither the exercise nor the failure by Licensor to exercise any right granted by this
Section will alter in any way the liability allocation provided by this License. If at any time Licensee shall,
Form 424; Rev 2.9-12
-3-
Tracking No. 13-47134
in the sole judgment of Licensor, fail to properly perform its obligations under this Section 12, Licensor
may, at its option and at Licensee's sole expense, and after giving written notice to Licensee, arrange for
the performance of such work as it deems necessary for the safety of its operations and activities,
Licensee shall promptly reimburse Licensor for all costs and expenses of such work, pursuant to the
terms of Section 7(c). Licensor's failure to perform any obligations of Licensee shall not alter the liability
allocation hereunder.
13. If at any time during the term of this License, Licensor shall desire the use of its rail corridor in
such a manner as would, in Licensor's reasonable opinion, be interfered with by the PIPELINE, Licensee
shall, at its sole expense, within ninety (90) days after receiving written notice from Licensor to such
effect, make such changes in the PIPELINE as in the sole discretion of Licensor may be necessary to
avoid interference with the proposed use of Licensor's rail corridor, including, without limitation, the
relocation of the PIPELINE, or the construction of a new pipeline to replace the PIPELINE.
Notwithstanding the foregoing Licensee agrees to make all emergency changes and minor adjustments,
as determined by Licensor in its sole discretion to the PIPELINE promptly upon Licensor's request.
14. (a) Prior to Licensee conducting any boring, excavation, or similar work on or about any
portion of the Premises, Licensee shall explore the proposed location for such work with hand tools to a
depth of at least three (3) feet below the surface of the ground to determine whether pipelines or other
structures exist below the surface, provided, however, that in lieu of the foregoing, Licensee shall have the
right to use suitable detection equipment or other generally accepted industry practice (e.g., consulting
with the Underground Services Association) to determine the existence or location of pipelines and other
subsurface structures prior to drilling or excavating with mechanized equipment. Licensee may request
information from Licensor concerning the existence and approximate location of Licensor's underground
lines, utilities and pipelines at or near the vicinity of the proposed PIPELINE by notifying Licensor at
telephone number 1-800-362-9624 (option 1, option 2, and then option 4) at least thirty (30) business
days prior to installation of the PIPELINE. Upon receiving Licensee's timely notice, Licensor will provide
Licensee with the information Licensor has in its possession regarding any existing underground lines,
utilities and pipelines at or near the vicinity of the proposed PIPELINE and, if applicable, identify the
location of such lines on the Premises pursuant to Licensor's standard procedures. Licensor does not
warrant the accuracy or completeness of information relating to subsurface conditions of the Premises
and Licensee's operations will be subject at all times to the liability provisions herein.
(b) For all bores greater than 26-inch diameter and at a depth less than 10.0 feet below bottom
of rail, a soil investigation will need to be performed by Licensee and reviewed by Licensor prior to
construction. This study is to determine if granular material is present, and to prevent subsidence during
the installation process. If the investigation determines in Licensor's reasonable opinion that granular
material is present, Licensor may select a new location for Licensee's use, or may require Licensee to
furnish for Licensor's review and approval, in its sole discretion, a remedial plan to deal with the granular
material. Once Licensor has approved any such remedial plan in writing, Licensee shall, at its sole cost
and expense, carry out the approved plan in accordance with all terms thereof and hereof.
15. Any open hole, boring or well constructed on the Premises by Licensee shall be safely covered
and secured at all times when Licensee is not working in the actual vicinity thereof. Following completion
of that portion of the work, all holes or borings constructed on the Premises by Licensee shall be:
(i) filled in to surrounding ground level with compacted bentonite grout; or
(ii) otherwise secured or retired in accordance with any applicable Legal Requirement. No
excavated materials may remain on Licensor's property for more than ten (10) days, but
must be properly disposed of by Licensee in accordance with applicable Legal
Requirements.
Form 424; Rev 2-9-12
-4
Tracking No. 13-47134
16. Licensee's on -site supervisors shall retain/maintain a fully executed copy of this License at all
times while on the Premises.
LIABILITY
17. (a) TO THE FULLEST EXTENT PERMITTED BY LAW, LICENSEE SHALL AND SHALL
CAUSE ITS CONTRACTOR TO RELEASE, INDEMNIFY, DEFEND AND HOLD HARMLESS LICENSOR
AND LICENSOR'S AFFILIATED COMPANIES, PARTNERS, SUCCESSORS, ASSIGNS, LEGAL
REPRESENTATIVES, OFFICERS, DIRECTORS, SHAREHOLDERS, EMPLOYEES AND AGENTS
(COLLECTIVELY, "INDEMNITEES") FOR, FROM AND AGAINST ANY AND ALL CLAIMS,
LIABILITIES, FINES, PENALTIES, COSTS, DAMAGES, LOSSES, LIENS, CAUSES OF ACTION,
SUITS, DEMANDS, JUDGMENTS AND EXPENSES (INCLUDING, WITHOUT LIMITATION, COURT
COSTS, ATTORNEYS' FEES AND COSTS OF INVESTIGATION, REMOVAL AND REMEDIATION AND
GOVERNMENTAL OVERSIGHT COSTS) ENVIRONMENTAL OR OTHERWISE (COLLECTIVELY
"LIABILITIES") OF ANY NATURE, KIND OR DESCRIPTION OF ANY PERSON OR ENTITY DIRECTLY
OR INDIRECTLY ARISING OUT OF, RESULTING FROM OR RELATED TO (IN WHOLE OR IN PART):
(i)
THIS LICENSE, INCLUDING, WITHOUT LIMITATION, ITS ENVIRONMENTAL
PROVISIONS,
(ii) ANY RIGHTS OR INTERESTS GRANTED PURSUANT TO THIS LICENSE,
(iii) LICENSEE'S OCCUPATION AND USE OF THE PREMISES,
(iv) THE ENVIRONMENTAL CONDITION AND STATUS OF THE PREMISES CAUSED BY,
AGGRAVATED BY, OR CONTRIBUTED IN WHOLE OR IN PART BY LICENSEE, OR
(v) ANY ACT OR OMISSION OF LICENSEE OR LICENSEE'S OFFICERS, AGENTS,
INVITEES, EMPLOYEES, OR CONTRACTORS, OR ANYONE DIRECTLY OR
INDIRECTLY EMPLOYED BY ANY OF THEM, OR ANYONE THEY CONTROL OR
EXERCISE CONTROL OVER ("LICENSEE PARTIES"),
EVEN IF SUCH LIABILITIES ARISE FROM OR ARE ATTRIBUTED TO, IN WHOLE OR IN PART, ANY
NEGLIGENCE OF ANY INDEMNITEE. THE ONLY LIABILITIES WITH RESPECT TO WHICH
LICENSEE'S OBLIGATION TO INDEMNIFY THE INDEMNITEES DOES NOT APPLY ARE LIABILITIES
TO THE EXTENT PROXIMATELY CAUSED BY THE GROSS NEGLIGENCE OR WILLFUL
MISCONDUCT OF AN INDEMNITEE.
THE INDEMNIFICATION AND RELEASE REQUIRED ABOVE SHALL NOT APPLY IN THE EVENT THE
DISCHARGE, RELEASE OR ESCAPE OF HAZARDOUS SUBSTANCES OR CONTAMINANTS, OR
ASBESTOS IS PROXIMATELY AND WHOLLY CAUSED BY LICENSOR'S SOLE NEGLIGENCE.
(b) FURTHER, TO THE FULLEST EXTENT PERMITTED BY LAW, NOTWITHSTANDING
THE LIMITATION IN SECTION 17(a), LICENSEE SHALL AND SHALL CAUSE ITS CONTRACTOR TO
NOW AND FOREVER WAIVE ANY AND ALL CLAIMS, REGARDLESS WHETHER BASED ON STRICT
LIABILITY, NEGLIGENCE OR OTHERWISE, THAT LICENSOR IS AN "OWNER", "OPERATOR",
"ARRANGER", OR "TRANSPORTER" WITH RESPECT TO THE PIPELINE FOR THE PURPOSES OF
THE COMPREHENSIVE ENVIRONMENTAL RESPONSE, COMPENSATION, AND LIABILITY ACT, AS
AMENDED ("CERCLA") OR OTHER ENVIRONMENTAL LAWS. LICENSEE WILL INDEMNIFY,
DEFEND AND HOLD THE INDEMNITEES HARMLESS FROM ANY AND ALL SUCH CLAIMS
REGARDLESS OF THE NEGLIGENCE OF THE INDEMNITEES. TO THE FULLEST EXTENT
PERMITTED BY LAW, LICENSEE FURTHER AGREES THAT THE USE OF THE PREMISES AS
CONTEMPLATED BY THIS LICENSE SHALL NOT IN ANY WAY SUBJECT LICENSOR TO CLAIMS
Form 424; Rev 2-9-12
-5-
Tracking No, 13-47134
THAT LICENSOR IS OTHER THAN A COMMON CARRIER FOR PURPOSES OF ENVIRONMENTAL
LAWS AND EXPRESSLY AGREES TO INDEMNIFY, DEFEND, AND HOLD THE INDEMNITEES
HARMLESS FOR ANY AND ALL SUCH CLAIMS. IN NO EVENT SHALL LICENSOR BE
RESPONSIBLE FOR THE ENVIRONMENTAL CONDITION OF THE PREMISES.
(c) IF ANY EMPLOYEE OF ANY LICENSEE PARTY ASSERTS THAT HE OR SHE IS AN
EMPLOYEE OF ANY INDEMNITEE, TO THE FULLEST EXTENT PERMITTED BY LAW, LICENSEE
FURTHER AGREES, AND SHALL CAUSE ITS CONTRACTOR TO AGREE TO RELEASE, INDEMNIFY,
DEFEND, AND HOLD THE INDEMNITEES HARMLESS FROM AND AGAINST ANY LIABILITIES
ARISING OUT OF OR RELATED TO (IN WHOLE OR IN PART) ANY SUCH ASSERTION INCLUDING,
BUT NOT LIMITED TO, ASSERTIONS OF EMPLOYMENT BY AN INDEMNITEE RELATED TO THE
FOLLOWING OR ANY PROCEEDINGS THEREUNDER: THE FEDERAL EMPLOYERS' LIABILITY
ACT ("FELA") CLAIMS BASED ON ACTUAL OR ALLEGED VIOLATIONS OF ANY FEDERAL, STATE
OR LOCAL LEGAL REQUIREMENTS OR REGULATIONS; THE SAFETY APPLIANCE ACT; THE
LOCOMOTIVE INSPECTION ACT; THE OCCUPATIONAL SAFETY AND HEALTH ACT; THE
RESOURCE CONSERVATION AND RECOVERY ACT; AND ANY SIMILAR STATE OR FEDERAL
STATUTE. LICENSEE'S OBLIGATIONS UNDER THIS SECTION 17(c) ARE REGARDLESS OF ANY
NEGLIGENCE, INTENTIONAL ACTS, OR STRICT LIABILITY OF ANY INDEMNITEE RELATED TO
SUCH CAUSES OF ACTION.
(d) Upon written notice from Licensor, Licensee agrees to assume the defense of any lawsuit
or other proceeding brought against any Indemnitee by any entity, relating to any matter covered by this
License for which Licensee has an obligation to assume liability for and/or save and hold harmless any
indemnitee. Licensee shall pay all costs incident to such defense, including, but not limited to, attorneys'
fees, investigators' fees, litigation and appeal expenses, settlement payments, and amounts paid in
satisfaction of judgments.
PERSONAL PROPERTY WAIVER
18. ALL PERSONAL PROPERTY, INCLUDING, BUT NOT LIMITED TO, FIXTURES, EQUIPMENT,
OR RELATED MATERIALS UPON THE PREMISES WILL BE AT THE RISK OF LICENSEE ONLY, AND
NO INDEMNITEE WILL BE LIABLE FOR ANY DAMAGE THERETO OR THEFT THEREOF, WHETHER
OR NOT DUE IN WHOLE OR IN PART TO THE NEGLIGENCE OF ANY INDEMNITEE.
INSURANCE
19. Licensor acknowledges that the City of Fort Worth is basically a self -funded entity, with the
exception of Railroad Protective Liability Insurance. Damages for which the City of Fort Worth would
ultimately be found liable would be paid directly and primarily by the City of Fort Worth and not by a
commercial insurance company.
(a) Commercial General Liability Insurance. This insurance shall contain broad form
contractual liability with a combined single limit of a minimum of $5,000,000 each occurrence and an
aggregate limit of at least $10,000,000 but in no event less than the amount otherwise carried by
Licensee. Coverage must be purchased on a post 1998 ISO occurrence or equivalent and include
coverage for, but not limited to, the following:
• Bodily Injury and Property Damage
• Personal Injury and Advertising Injury
■ Fire legal liability
■ Products and completed operations
Form 424; Rev 2-9-12
-6
Tracking No. 13-47134
This policy shall also contain the following endorsements, which shall be indicated on the certificate of
insurance:
• The definition of insured contract shall be amended to remove any exclusion or other limitation for
any work being done within 50 feet of railroad property.
• Waiver of subrogation in favor of and acceptable to Licensor.
• Additional insured endorsement in favor of and acceptable to Licensor and Jones Lang LaSalle
Brokerage, Inc.
• Separation of insureds.
• The policy shall be primary and non-contributing with respect to any insurance carried by Licensor.
It is agreed that the workers' compensation and employers' liability related exclusions in the
Commercial General Liability Insurance policy(s) required herein are intended to apply to employees
of the policy holder and shall not apply to Licensor's employees.
No other endorsements limiting coverage may be included on the policy.
(b) Business Automobile Insurance. This insurance shall contain a combined single limit of at
least $1,000,000 per occurrence, and include coverage for, but not limited to the following:
• Bodily injury and property damage.
• Any and all vehicles owned, used or hired.
■ Waiver of subrogation in favor of and acceptable to Licensor.
• Additional insured endorsement in favor of and acceptable to Licensor.
• Separation of insureds.
• The policy shall be primary and non-contributing with respect to any insurance carried by Licensor.
(c) Workers' Compensation and Employers' Liability Insurance. This insurance shall include
coverage for, but not limited to:
■ Licensee's statutory liability under the workers' compensation Legal Requirements of the state(s)
in which the work is to be performed. If optional under state Legal Requirements, the insurance
must cover all employees anyway.
■ Employers' Liability (Part B) with limits of at least $500,000 each accident, $500,000 by disease
policy limit, $500,000 by disease each employee.
This policy shall also contain the following endorsements or language, which shall be indicated on the
certificate of insurance:
■ Waiver of subrogation in favor of and acceptable to Licensor.
(d) Railroad Protective Liability Insurance. This insurance shall name only Licensor as the
Insured with coverage of at least $5,000,000 per occurrence and $10,000,000 in the aggregate. The
coverage obtained under this policy shall only be effective during the initial installation and/or construction
of the PIPELINE. THE CONSTRUCTION OF THE PIPELINE SHALL BE COMPLETED WITHIN ONE (1)
YEAR OF THE EFFECTIVE DATE. If further maintenance of the PIPELINE is needed at a later date, an
additional Railroad Protective Liability Insurance Policy shall be required. The policy shall be issued on a
standard ISO form CG 00 35 10 93 and include the following:
• Endorsed to include the Pollution Exclusion Amendment (ISO form CG 28 31 10 93).
• Endorsed to include the Limited Seepage and Pollution Endorsement.
• Endorsed to include Evacuation Expense Coverage Endorsement.
• No other endorsements restricting coverage may be added.
• The original policy must be provided to Licensor prior to performing any work or services under
this License.
Form 424; Rev 2-9-12
7-
Tracking No, 13-47134
In lieu of providing a Railroad Protective Liability Policy, for a period of one (1) year from the Effective
Date, Licensee may participate in Licensor's Blanket Railroad Protective Liability Insurance Policy
available to Licensee or its contractor. The limits of coverage are the same as above. The cost is
$1150.00.
I elect to participate in Licensor's Blanket Policy;
o I elect not to participate in Licensor's Blanket Policy.
Other Requirements:
Where allowable by law, all policies (applying to coverage listed above) shall contain no exclusion
for punitive damages and certificates of insurance shall reflect that no exclusion exists.
Licensee agrees to waive its right of recovery against Licensor for all claims and suits against
Licensor. In addition, its insurers, through a policy endorsement, must waive their right of subrogation
against Licensor for all claims and suits, and the certificate of insurance must reflect the waiver of
subrogation endorsement. Licensee further waives its right of recovery, and its insurers must also waive
their right of subrogation against Licensor for loss of Licensee's owned or leased property, or property
under Licensee's care, custody, or control.
With the exception of Railroad Protective Liability insurance, Licensee is allowed to self insure.
Any deductible, self insured retention or other financial responsibility for claims shall be covered directly
by Licensee in lieu of insurance. Any and all Licensor liabilities that would otherwise, in accordance with
the provisions of this License, be covered by Licensee's insurance will be covered as if Licensee elected
not to include a deductible, self -insured retention, or other financial responsibility for claims.
Prior to entering the Premises, Licensee shall furnish to Licensor an acceptable certificate(s) of
insurance including an original signature of the authorized representative evidencing the required
coverage, endorsements, and amendments. The policy(ies) shall contain a provision that obligates the
insurance company(ies) issuing such policy(ies) to notify Licensor in writing at least 30 days prior to any
cancellation, non -renewal, substitution or material alteration. This cancellation provision shall be indicated
on the certificate of insurance. In the event of a claim or lawsuit involving Licensor arising out of this
License, Licensee will make available any required policy covering such claim or lawsuit.
Any insurance policy shall be written by a reputable insurance company acceptable to Licensor or
with a current Best's Guide Rating of A- and Class VII or better, and authorized to do business in the
state(s) in which the service is to be provided.
If coverage is purchased on a "claims made" basis, Licensee hereby agrees to maintain coverage
in force for a minimum of three years after expiration or termination of this License. Annually, Licensee
agrees to provide evidence of such coverage as required hereunder.
Licensee represents that this License has been thoroughly reviewed by Licensee's insurance
agent(s)/broker(s), who have been instructed by Licensee to procure the insurance coverage required by
this License. Allocated Loss Expense shall be in addition to all policy limits for coverages referenced
above.
Not more frequently than once every five years, Licensor may reasonably modify the required
insurance coverage to reflect then -current risk management practices in the railroad industry and
underwriting practices in the insurance industry.
Form 424; Rev 2-9-12
_8-
Tracking No. 13-47134
If any portion of the operation is to be subcontracted by Licensee, Licensee shall require that the
subcontractor shall provide and maintain insurance coverages as set forth herein, naming Licensor as an
additional insured, and shall require that the subcontractor shall release, defend and indemnify Licensor to
the same extent and under the same terms and conditions as Licensee is required to release, defend and
indemnify Licensor herein.
Failure to provide evidence as required by this Section 19 shall entitle, but not require, Licensor to
terminate this License immediately. Acceptance of a certificate that does not comply with this Section
shall not operate as a waiver of Licensee's obligations hereunder.
The fact that insurance (including, without limitation, self-insurance) is obtained by Licensee shall
not be deemed to release or diminish the liability of Licensee, including, without limitation, liability under
the indemnity provisions of this License. Damages recoverable by Licensor shall not be limited by the
amount of the required insurance coverage.
For purposes of this Section 19, Licensor shall mean "Burlington Northern Santa Fe LLC", "BNSF
Railway Company" and the subsidiaries, successors, assigns and affiliates of each.
ENVIRONMENTAL
20. (a) Licensee shall strictly comply with all federal, state and local environmental Legal
Requirements and regulations in its use of the Premises, including, but not limited to, the Resource
Conservation and Recovery Act, as amended (RCRA), the Clean Water Act, the Oil Pollution Act, the
Hazardous Materials Transportation Act, CERCLA (collectively referred to as the "Environmental Laws").
Licensee shall not maintain a treatment, storage, transfer or disposal facility, or underground storage
tank, as defined by Environmental Laws on the Premises. Licensee shall not release or suffer the release
of oil or hazardous substances, as defined by Environmental Laws on or about the Premises.
(b) Licensee covenants that it will not handle or transport "hazardous waste" or "hazardous
substances", as "hazardous waste" and "hazardous substances" may now or in the future be defined by
any federal, state, or local governmental agency or body through the PIPELINE on Licensor's property.
Licensee agrees periodically to furnish Licensor with proof, satisfactory to Licensor that Licensee is in
compliance with the provisions of this Section.
(c) Licensee shall give Licensor immediate notice to Licensor's Resource Operations Center at
(800) 832-5452 of any known (i) release of hazardous substances on, from, or affecting the Premises, (ii)
violation of Environmental Laws, or (iii) inspection or inquiry by governmental authorities charged with
enforcing Environmental Laws with respect to Licensee's use of the Premises. Licensee shall use the
best efforts to promptly respond to any release on, from, or affecting the Premises. Licensee also shall
give Licensor immediate notice of all measures undertaken on behalf of Licensee to investigate,
remediate, respond to or otherwise cure such release or violation.
(d) In the event that Licensor has notice from Licensee or otherwise of a release or violation of
Environmental Laws arising in any way with respect to the PIPELINE which occurred or may occur during
the term of this License, Licensor may require Licensee, at Licensee's sole risk and expense, to take
timely measures to investigate, remediate, respond to or otherwise cure such release or violation affecting
the Premises or Licensor's right-of-way.
(e) Licensee shall promptly report to Licensor in writing any conditions or activities upon the
Premises known to Licensee which create a risk of harm to persons, property or the environment and
shall take whatever action is necessary to prevent injury to persons, property, or the environment arising
out of such conditions or activities; provided, however, that Licensee's reporting to Licensor shall not
Form 424; Rev 2-9-12
9
Tracking No. 13-47134
relieve Licensee of any obligation whatsoever imposed on it by this License. Licensee shall promptly
respond to Licensor's request for information regarding said conditions or activities.
ALTERATIONS
21. Licensee may not make any alterations to the Premises or permanently affix anything to the
Premises or any buildings or other structures adjacent to the Premises without Licensor's prior written
consent.
NO WARRANTIES
22. LICENSOR'S DUTIES AND WARRANTIES ARE LIMITED TO THOSE EXPRESSLY STATED IN
THIS LICENSE AND SHALL NOT INCLUDE ANY IMPLIED DUTIES OR IMPLIED WARRANTIES, NOW
OR IN THE FUTURE. NO REPRESENTATIONS OR WARRANTIES HAVE BEEN MADE BY LICENSOR
OTHER THAN THOSE CONTAINED IN THIS LICENSE. LICENSEE HEREBY WAIVES ANY AND ALL
WARRANTIES, EXPRESS OR IMPLIED, WITH RESPECT TO THE PREMISES OR WHICH MAY EXIST
BY OPERATION OF LAW OR IN EQUITY, INCLUDING, WITHOUT LIMITATION, ANY WARRANTY OF
MERCHANTABILITY, HABITABILITY OR FITNESS FOR A PARTICULAR PURPOSE.
QUIET ENJOYMENT
23. LICENSOR DOES NOT WARRANT ITS TITLE TO THE PREMISES NOR UNDERTAKE TO
DEFEND LICENSEE IN THE PEACEABLE POSSESSION OR USE THEREOF. NO COVENANT OF
QUIET ENJOYMENT IS MADE.
LIENS AND CHARGES
24. Licensee shall promptly pay and discharge any and all liens arising out of any construction,
alterations or repairs done, suffered or permitted to be done by Licensee on Premises. Licensor is hereby
authorized to post any notices or take any other action upon or with respect to Premises that is or may be
permitted by law to prevent the attachment of any such liens to Premises; provided, however, that failure
of Licensor to take any such action shall not relieve Licensee of any obligation or liability under this
Section 24 or any other Section of this License. Licensee shall pay when due any taxes, assessments or
other charges (collectively, "Taxes") levied or assessed by any governmental or quasi -governmental body
upon the PIPELINE or any other improvements constructed or installed on the Premises by or for
Licensee (collectively, the "Improvements") or any Taxes levied or assessed against Licensor or the
Premises that are attributable to the Improvements.
DEFAULT AND REMEDIES; OTHER TERMINATION RIGHTS
25. In addition to and not in limitation of Licensor's right to terminate for failure to provide evidence of
insurance as required pursuant to the terms of Section 19, the following events are also deemed to be
events of default pursuant to which Licensor has the right to terminate as set forth below:
(a) If default shall be made in any of Licensee's covenants or agreements contained in this
License or in case of any assignment or transfer of this License in violation of Section 27 below, Licensor
shall give Licensee ten (10) days written notice of such default and shall give Licensee sixty (60) days to
cure or such additional period as agreed to by Licensor. If Licensee has commenced to cure such default
but is unable to complete such cure due to circumstances beyond the Licensee's reasonable control,
Licensor shall extend Licensee's time to cure an additional thirty (30) days or such additional time as
agreed to by Licensor, Licensor may, at its option, terminate this License by serving written notice upon
Licensee ten (10) days after the Licensee fails to cure such default during the specified cure period,
Form 424; Rov 2-9-12
- 10 -
Tracking No. 13-47134
Notwithstanding the foregoing, Licensor shall have the right to terminate this License immediately in the
event Licensee fails to provide evidence of insurance as required in Section 19.
(b) Should Licensee not comply fully with the obligations of Section 20(b) regarding the
handling or transporting of hazardous waste or hazardous material, notwithstanding anything contained in
any other provision of this License, Licensor may, at its option, terminate this License by serving five (5)
days' notice of termination upon Licensee.
(c) Any waiver by Licensor of any default or defaults shall not constitute a waiver of the right to
terminate this License for any subsequent default or defaults, nor shall any such waiver in any way affect
Licensor's ability to enforce any Section of this License. The remedy set forth in this Section 25 shall be
in addition to, and not in limitation of, any other remedies that Licensor may have at law or in equity.
(d) In addition to and not in limitation of Licensor's rights to terminate this License for failure to
provide evidence of insurance or occurrence of defaults as described above, this License may be
terminated by Licensor, at any time, by serving thirty (30) days' written notice of termination upon
Licensee.
(e) This License may be terminated by Licensee upon execution of Licensor's then -current
Mutual Termination Letter Agreement. Upon expiration of the time specified in such notice, this License
and all rights of Licensee shall absolutely cease.
SURRENDER
26. (a) On or before expiration or termination of this License for any reason, Licensee shall, at its
sole cost and expense:
(1)
if so directed by Licensor in writing, remove the Improvements, the PIPELINE and all
appurtenances thereto, or, at the sole discretion of Licensor, fill and cap or otherwise
appropriately decommission the PIPELINE with a method satisfactory to Licensor;
(ii) report and restore any damage to the Premises or Licensor's other property arising from,
growing out of, or connected with Licensee's use of the Premises;
(iii) remedy any unsafe conditions on the Premises created or aggravated by Licensee; and
(iv) leave the Premises in substantially the condition which existed as of the Effective Date of
this License, normal wear and tear excepted.
(b) Upon any expiration or termination of this License, if Licensee fails to surrender the
Premises to Licensor or if Licensee fails to complete its obligations under Section 26(a) above (the
"Restoration Obligations"), Licensee shall have a limited license to enter upon the Premises solely to
the extent necessary for Licensee to complete the Restoration Obligations, and all liabilities and
obligations of Licensee hereunder shall continue in effect until the Premises are surrendered and the
Restoration Obligations are completed. Neither termination nor expiration shall release Licensee from any
liability or obligation under this License, whether of indemnity or otherwise, resulting from any acts,
omissions or events happening prior to the date of termination, or, if later, the date when Licensee
surrenders the Premises and all of the Restoration Obligations are completed.
ASSIGNMENT
27. Licensee may not sell, assign, transfer, or hypothecate this License or any interest herein (either
voluntarily or by operation of law) without the prior written consent of Licensor, which consent may be
withheld by Licensor for any reason. Any attempted assignment by Licensee in violation of this
Form 424; Rev 2-9-12
- 11 -
Tracking No. 13-47134
Section 27 shall be absolutely void. For purposes of this Section 27, the word "assign" shall include
without limitation (a) any sale of the equity interests of Licensee following which the equity interest holders
of Licensee immediately prior to such sale own, directly or indirectly, less than 50% of the combined
voting power of the outstanding voting equity interests of Licensee, (b) any sale of all or substantially all of
the assets of (i) Licensee and (ii) to the extent such entities exist, Licensee's parent and subsidiaries,
taken as a whole, or (c) any reorganization, recapitalization, merger or consolidation involving Licensee,
except for a reorganization, recapitalization, merger or consolidation following which the equity interest
holders of Licensee immediately prior to such reorganization, recapitalization, merger or consolidation
own, directly or indirectly, at least 50% of the combined voting power of the outstanding voting equity
interests of Licensee or any successor thereto or the entity resulting from such reorganization,
recapitalization, merger or consolidation. THIS LICENSE SHALL NOT RUN WITH THE LAND WITHOUT
THE EXPRESS WRITTEN CONSENT OF LICENSOR, SUCH CONSENT TO BE IN LICENSOR'S SOLE
DISCRETION,
NOTICES
28. Any notice, invoice, or other writing required or permitted to be given hereunder by one party to the
other shall be in writing and the same shall be given and shall be deemed to have been served and given
if (i) placed in the United States mail, certified, return receipt requested, or (ii) deposited into the custody
of a nationally recognized overnight delivery service, addressed to the party to be notified at the address
for such party specified below, or to such other address as the party to be notified may designate by
giving the other party no less than thirty (30) days' advance written notice of such change in address.
If to Licensor: Jones Lang LaSalle Brokerage, Inc.
4300 Amon Carter Blvd., Suite 100
Fort Worth, Texas 76155
Attn: Licenses/Permits
with a copy to:
If to Licensee:
with a copy to:
RECORDATION
BNSF Railway Company
2500 Lou Menk Dr, —AOB3
Fort Worth, Texas 76131
Attn: Senior Manager Real Estate
City of Fort Worth
1000 Throckmorton
Fort Worth, Texas 76102
City Attorney
City of Fort Worth
1000 Throckmorton Street
Fort Worth, Texas 76102
29. It is understood and agreed that this License shall not be placed or allowed to be placed on public
record.
APPLICABLE LAW
30. All questions concerning the interpretation or application of provisions of this License shall be
decided according to the substantive laws of the State of Texas, without regard to conflicts of law
provisions, and venue for any lawsuit that may arise shall be in Tarrant County,
Form 424; Rev 2-9-12
- 12 -
Tracking No. 13-47134
S EVERABILITY
31. To the maximum extent possible, each provision of this License shall be interpreted in such
manner as to be effective and valid under applicable law, but if any provision of this License shall be
prohibited by, or held to be invalid under, applicable law, such provision shall be ineffective solely to the
extent of such prohibition or invalidity, and this shall not invalidate the remainder of such provision or any
other provision of this License.
INTEGRATION
32. This License is the full and complete agreement between Licensor and Licensee with respect to all
matters relating to Licensee's use of the Premises, and supersedes any and all other agreements
between the parties hereto relating to Licensee's use of the Premises as described herein. However,
nothing herein is intended to terminate any surviving obligation of Licensee or Licensee's obligation to
defend and hold Licensor harmless in any prior written agreement between the parties.
MISCELLANEOUS
33. In the event that Licensee consists of two or more parties, all the covenants and agreements of
Licensee herein contained shall be the joint and several covenants and agreements of such parties.
34. The waiver by Licensor of the breach of any provision herein by Licensee shall in no way impair
the right of Licensor to enforce that provision for any subsequent breach thereof.
35. No provision of this License shall be construed in favor of, or against, any particular party by
reason of any presumption with respect to the drafting of this License; both parties, being represented by
counsel and having fully participated in the negotiation of this instrument, hereby agree that this License
shall not be subject to the principle that a contract would be construed against the party which drafted the
same.
36. This License may be executed in multiple counterparts, each of which shall, for all purposes, be
deemed an original but which together shall constitute one and the same instrument, and the signature
pages from any counterpart may be appended to any other counterpart to assemble fully executed
documents, and counterparts of this License may also be exchanged via email or electronic facsimile
machines and any email or electronic facsimile of any party's signature shall be deemed to be an original
signature for all purposes.
37. All provisions contained in this License shall be binding upon, inure to the benefit of, and be
enforceable by the respective successors and assigns of Licensor and Licensee to the same extent as if
each such successor and assign was named a party to this License.
38. Jones Lang LaSalle Brokerage, Inc. is acting as representative for BNSF Railway Company.
[Signature Page Follows]
Form 424; Rev 2-9-12
- 13 -
Tracking No. 13-47134
IN WITNESS WHEREOF, this License has been duly executed by the parties hereto as of the
date below each party's signature; to be effective, however, as of the Effective Date.
LICENSOR:
BNSF Railway Company, a Delaware corporation
By: Jones Lang LaSalle Global Brokerage, Inc.
4300 Amon Carter Blvd., Suite 100
Fort Worth, Texas 76155
A
By:
Name:
Title:
Date:
LICENSEE:
City of Fort Worth, a Texas corporation
1000 Throckmorton
Fort Worth, Texas 76102
By:�,
Name: /'?. U & &
Title: / 1:rs/ v�ager
Date: 5/7/ 1
Form 424; Rev 2-9-12
-14-
TRACKING NO. 13-47134
EXHIBIT "A"
ATTACHED TO CONTRACT BETWEEN
BNSF RAILWAY COMPANY
AND
CITY OF FORT WORTH, TEXAS
SCALE: 1 IN.=_100 FT.
IEXAS DIV.
FORT WORTH SUBDIV. L.S.4,4
DATE 03/13/2013
y OPP. MF 342.0
ES ;.BB57+22 tzS
TO 'PT." 'UW((r,
t4
t6
Pci3 DEED -; +-+-
2Ol54
142'
0
SECTION:
TOWNSHIP:
RANGE:
MERIDIAN:
0
aiT
DESCRIPTION OF PIPELINE
PIPELINE SHOWN BOLD
CARRIER CASING
PIPE PIPE
SIZE: ,
CONTENTS: SAN I TA Y SEWER
PIPE MATERIAL: CURE IN PLACE
SPECIFICATION/GRADE:
WALL THICKNESS:
COATING:
Per F
_ TX-35
S-02A %
T; rROPER Y LINE
bt
TO ML LS 7500
-La CONTRACT ` 3iCo&%
41
LENGTH ON R/W:
WORKING PRESSURE:
BURY: BASE/RAIL TO TOP
BURY: NATURAL GROUND
BURY: ROADWAY DITCHES
CATHODIC PROTECTION
VENTS: NUMBER — SIZE — HEIGHT OF VENT ABOVE GROUND
NOTE: PIPE IS EXISTING IN PLACE
AT FORT WORTH
COUNTY OF TARRANT
STATE OF TX
135
Csz
k co
CARRIER CASING
PIPE PIPE
100
OF CASING
16'
4'
4'
J WD
DRAWING N0. 1-57132
•
w
CC
d
GC-6.10 M&C
THIS PAGE IS LEFT INTENTIONALLY BLANK
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
Official site of the City of Fort Worth, Texas
CITY COUNCIL AGENDA
FORT WORTI i
DATE: 4/12/2011 REFERENCE NO.: **C-24858 LOG NAME: 6060SS75-LAN
CODE: C TYPE: CONSENT PUBLIC HEARING: NO
SUBJECT: Authorize Execution of an Engineering Agreement in the Amount of $214,706.00 with
Lockwood, Andrews & Newman, Inc., for Sanitary Sewer Rehabilitation Contract 75 on
Devitt Street, Shaw Street, Cleburne Road and Six Alleyways and Adopt Appropriation
Ordinance (COUNCIL DISTRICT 9)
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize the transfer of $238,706.00 from the Water and Sewer Fund to the Sewer Capital
Projects Fund;
2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the
Sewer Capital Projects Fund in the amount of $238,706.00 from available funds; and
3. Authorize the City Manager to execute an engineering agreement in the amount of $214,706.00
with Lockwood, Andrews & Newman, Inc., for Sanitary Sewer Rehabilitation Contract 75.
DISCUSSION:
This project consists of the preparation of plans and specifications for the replacement of the
deteriorated sanitary sewer mains located on the following streets and alleyways:
Street From To
Devitt Street Forest Park Boulevard Gordon Avenue
Shaw Street Townsend Drive Stanley Avenue
Cleburne Road Devitt Street Wayside Avenue
Alleyway between Wayside Avenue Orange Street Biddison Street
and Frazier Avenue
Alleyway between Frazier Avenue Orange Street I Biddison Street
and Townsend Drive
Alleyway between Townsend Drive Cleburne Road I Biddison Street
and Gordon Avenue
Alleyway between Gordon Avenue Shaw Street I Biddison Street
and Livingston Avenue
Alleyway between Livingston Avenue Devitt Street I Shaw Street
and Stanley Avenue
Alleyway between Stanley Avenue Devitt Street I Biddison Street
and James Avenue
Lockwood, Andrews & Newman, Inc., proposes to perform the design work for a lump sum fee of
$214,706.00. City staff considers this fee to be fair and reasonable for the scope of services proposed.
Lockwood, Andrews & Newman, Inc., is in compliance with City's M/WBE ordinance by committing to
23 percent M/WBE participation. The City's goal on this project is 23 percent.
In addition to the contract amount, $24,000.00 is required for project management, real property
acquisition and utility coordination.
The project is located in COUNCIL DISTRICT 9.
FISCAL INFORMATION/CERTIFICATION:
The Financial Management Services Director certifies that funds are available in the current operating
budget of the Water and Sewer Fund and upon approval of the above recommendations, and
adoption of the attached appropriation ordinance, funds will be available in the current capital budget,
as appropriated of the Sewer Capital Projects Fund.
TO Fund/Account/Centers
1&2)
P258 476045 7091701480ZZ
2)
P258 511010 709170148030
P258 531200 709170148031
P258 531200 709170148032
2)
P258 531200 709170148033
2)
P258 531200 709170148051
2)
P258 531350 709170148051
2)
P258 531350 709170148073
$238 706_00
$20,000.00
$50, 000.00
$100,000.00
$17,280.00
$47,426.00
$2.000.00
$2.000.00
Submitted for City Manager's Office by:
Oriainatinp Department Head:
Additional Information Contact:
ATTACHMENTS
6060SS75-LAN AON.doc
60SS75-LAN MAP.pdf
FROM Fund/Account/Centers
P258 531200 709170148031
3)
P258 531200 709170148032
P258 531200 709170148051
P258 531200 709170148033
$50.000.00
$100.000.00
$47,426.00
$17,280.00
1) PE45 538040 0709020 $238.706.00
Fernando Costa (6122)
S. Frank Crumb (8207)
David L. Cooper (8252)
SRF-1
THIS PAGE INTENTIONALLY LEFT BLANK
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
Development Board
Texas Water Development Board
Instructions on Use of
Supplemental Contract Conditions
For Projects Funded through the
Clean Water Tier II State Revolving Fund
'Replaces ED-0044
TWDB-0551 Revised 6/19/2012 Page 1
Table of Contents
Applicability 3
Application of Conditions 3
Modifications to Provisions 3
Good Business Practices 3
Other Requirements 4
Advertisements for Bids 4
Bid Proposal 5
Bidding Process 5
Instructions to Bidders 6
1. CONTINGENT AWARD OF CONTRACT 6
2. EQUAL EMPLOYMENT OPPORTUNITY AND AFFIRMATIVE ACTION 6
3. BID GUARANTEE 6
4. AWARD OF CONTRACT TO NONRESIDENT BIDDER 6
Construction Contract — Supplemental Conditions 7
1. SUPERSESSION 7
2. PRIVITY OF CONTRACT 7
3. DEFINITIONS 7
4. LAWS TO BE OBSERVED 7
5. REVIEW BY OWNER and TWDB 7
6. PERFORMANCE AND PAYMENT BONDS 7
7. PROGRESS PAYMENTS AND PAYMENT SCHEDULE 8
8. WORKMAN'S COMPENSATION INSURANCE COVERAGE 10
9. CHANGES 10
10. PREVAILING WAGE RATES 11
11. Davis -Bacon Requirements 15
MONTHLY DAVIS BACON ACT CERTIFICATE of COMPLIANCE 26
Submittal by Recipient 26
STATEMENT OF COMPLIANCE CERTIFICATION BY CONTRACTOR FOR SRF 28
DOL Payroll form WH-347 30
12. EQUAL EMPLOYMENT OPPORTUNITY AND AFFIRMATIVE ACTION 34
12. DEBARMENT AND SUSPENSION 35
13. ARCHEOLOGICAL DISCOVERIES AND CULTURAL RESOURCES 36
14. ENDANGERED SPECIES 36
15. HAZARDOUS MATERIALS 36
16. PROJECT SIGN 36
17. OPERATION AND MAINTENANCE MANUALS AND TRAINING 37
18. AS -BUILT DIMENSIONS AND DRAWINGS 37
Forms to be submitted with executed contracts 38
BIDDER'S CERTIFICATIONS 39
VENDOR COMPLIANCE WITH RECIPROCITY ON NON- 40
RESIDENT BIDDERS 40
THIS FORM MUST BE RETURNED WITH THE BID 40
CONTRACTOR'S ACT OF ASSURANCE 41
CONTRACTOR'S RESOLUTION ON AUTHORIZED REPRESENTATIVE 42
TWDB-0551 Revised 6/19/2012 Page 2
Applicability
These Supplemental Conditions contain provisions that are worded to comply with certain
statutes and regulations which specifically relate to the Clean Water State Revolving Fund
(CWSRF) Tier II (projects receiving state funds only). Provisions that are applicable to the
project's funding source or dollar value of the contract are so noted within with the provision.
Construction projects that have Colonia Wastewater Treatment Assistance Program (CWTAP)
funding do not use these conditions but instead use the EPA Supplemental Conditions and
TWDB Special Conditions TWDB-0553 (formerly ED-004C). Construction projects which are
financed by CWSRF Tier III (projects receiving federal funds) and Drinking Water State
Revolving Fund do not use these conditions but instead use TWDB Supplemental Conditions
TWDB-0550 (formerly ED-004E). Projects with State Loan funding use Supplemental
Conditions TWDB-0552 (formerly ED-004G).
Application of Conditions
The conditions and forms listed under Instructions to Bidders are to be included in the
instructions to bidders for construction services. The provisions listed under Construction
Contract Supplemental Conditions should be included with the other general and special
conditions that are typically included in the construction contract documents by the design
engineer.
Modifications to Provisions
The Applicant may need to modify parts of these provisions to better fit the other provisions of
the construction contract_. The Applicant and the consulting engineer should carefully study
these provisions before incorporating them into the construction contract documents. In
particular, Water Districts and other types of districts should be aware of statutes relating to their
creation and operation that may affect the application of these conditions.
The Owner (Sub -Recipient) is to determine and incorporate the affirmative action goals for the
project into supplemental condition No. 11. Condition number No. 12 (Archeological
Discoveries and Cultural Resources) and No. 13 (Endangered Species) may be superseded or
modified by project specific conditions established during the application process.
These documents may confer certain duties and responsibilities on the consulting engineer that
are beyond, or short of, what the Applicant intends to delegate. The Applicant should ensure that
the contractual agreement with the engineer provides for the appropriate services. Otherwise the
Applicant should revise the wording in these special conditions to agree with actually delegated
functions.
Good Business Practices
There are other contract provisions that the Owner and Designer need to include as a matter of
good business practices. It is recommended that provisions addressing the following matters be
TWDB-0551 Revised 6/19/2012 Page 3
included in the construction contract. Contract Provisions that satisfy these are available from
TWDB upon request.
• Specifying the time frame for accomplishing the Construction of the project, and the
consequences of not completing on time, including liquidation damages.
• Specifying the type and dollar value of and documentation of insurance the contractor is to
carry. As a minimum the contractor should carry liability and builder's risk insurance
• Identifying the responsibility of the contractor - Responsibility and warranty of work.
• Price reduction for defective pricing of negotiated costs.
• Differing site conditions - notice and claims regarding site conditions differing from
indicated conditions.
• Covenants against contingent fees - Prohibit contingent fees for securing business.
• Gratuities - Prohibitions against offering and accepting gratuities
• Audit and access records
• Suspension of work - Conditions under which owner may suspend work.
• Termination - Conditions under which owner may terminate
• Remedies - How disputes will be remedied.
Other Requirements
There may be other local government requirements and applicable Federal and State statutes and
regulations that are not accommodated by these conditions. It is the Loan/Grant Recipient's
responsibility to ensure that the project and all contract provisions are consistent with the
relevant statutes and regulations.
Advertisements for Bids
The official advertisement for bids that is published in newspapers should include certain
information including:
• A clear description of what is being procured.
• How to obtain P&S, and necessary forms and information.
• The date and time by which bids are to be received. (deadline)
• The address where bids are to be provided.
• Acknowledgement of any special requirements such as mandatory pre -bid conference and
Affirmative Action requirements.
• Right to reject any and all bids.
• All laborers and mechanics employed by contractors and subcontractors on projects funded
directly by or assisted in whole or in part by and through the Clean Water State Revolving
Fund or Drinking Water State Revolving Fund shall by paid wages at rates not less than those
prevailing on projects of a character similar in the locality as determined by the Secretary of
Labor in accordance with subchapter IV of chapter 31 of title 40, United States Code. Wages
to be paid on this project will be governed by the Department of Labor Wage General
Decision or Decisions included in the bid documents for this project.
• Pursuant to Reorganization Plan No. 14 and the Copeland Act, 40 U.S.C. 3145, the
Department of Labor has issued regulations at 29 CFR parts 1, 3 and 5 to implement Davis-
TWDB-0551 Revised 6/19/2012 Page 4
Bacon and Related Acts. Regulations in 29 CFR 5.5 instruct agencies concerning application
of the standard Davis -Bacon contract clauses set forth in that section. All grants, cooperative
agreements and loans funded under the Clean Water State Revolving Fund and Drinking
Water State Revolving Fund programs shall include the standard Davis -Bacon contract
clauses found in 29 CFR 5.5(a), which shall also be incorporated in any resultant covered
contracts that are in excess of $2,000 for construction, alteration or repair (including painting
and decorating).
Bid Proposal
The Bid proposal form should account for the following:
• If lump sum bid, account for Property Consumed in Contracts to Improve Real Property; Tax
Code 151.056.
• Distinguish Eligible and Ineligible items.
• Accommodate Trench Safety requirements with separate per unit pay item for trench
excavation safety protection Health and Safety Code Chapter 756.
• Accommodate Non -Resident Bidder Reciprocity requirements in Government Code
2252.002, by utilizing WRD-259.
• Include space for Contractor to acknowledge receipt of each Addendum issued during the
bidding process.
Bidding Process
The Plans and Specifications should include an explanation of how the bids will be processed.
The explanation should include the following components:
• Whether a Pre -bid Conference, will be held, whether it is optional or mandatory, and where
and when it will be held.
• Specify the criteria and process for determining responsiveness and responsibleness of the
bidder.
• Specify the method of determining the successful bidder and award, and accounting for non-
resident bidder reciprocity requirements Gov. Code 2252.002 (IE. Award to the lowest
responsive responsible bidder, accounting for any multiple parts to bids.)
• Allow for withdrawal of a bid due to a material mistake.
• Identify the time frame that the bids may be held by the Owner before awarding a contract.
(IE. Typically for 60 or 90 days.)
• Acknowledge right of the Owner to reject any and all bids.
All proposed modifications to these conditions should be brought to the attention of and
discussed with the appropriate TWDB area engineer. The TWDB engineer can also answer any
questions regarding these conditions. The questions and proposed modifications can be sent to
the following address:
Texas Water Development Board
Construction Assistance
P. O. Box 13231
Austin, Texas 78711-3231
(512) 463-7853 FAX (512) 475-2086
TWDB-0551 Revised 6/19/2012 Page 5
Instructions to Bidders
1. CONTINGENT AWARD OF CONTRACT
This contract is contingent upon release of funds from the Water Development Board. Any
contract or contracts awarded under this Invitation for Bids are expected to be funded in part by a
loan or grant from the Texas Water Development Board, and a grant from the United States
Environmental Protection Agency (U.S. EPA.) Neither the State of Texas, or U.S. EPA nor any
of its departments, agencies, or employees are or will be a party to this Invitation for Bids or any
resulting contract.
2. EQUAL EMPLOYMENT OPPORTUNITY AND AFFIRMATIVE ACTION
All qualified applicants will receive consideration for employment without regard to race, color,
religion, sex (including pregnancy), national origin, age (40 or older), disability or genetic
information. Bidders on this work will be required to comply with the Department of Labor
regulations 41 CFR Part 60-2 Affirmative Action Programs which include the President's
Executive Order No. 11246 as amended by Executive Order 11375.
The Bidder's Certifications regarding Equal Employment Opportunity and Non -Segregated
Facilities (WRD-255) must be submitted with the bid.
3. BID GUARANTEE
Each bidder shall furnish a bid guarantee equivalent to five percent of the bid price. (Water Code
17.183) If a bid bond is provided; the contractor shall utilize a surety company which is
authorized to do business in Texas in accordance with Art. 7.19-1. Bond of Surety Company;
Chapter 7 of the Insurance Code.
4. AWARD OF CONTRACT TO NONRESIDENT BIDDER
A governmental entity may not award a governmental contract to a nonresident bidder unless the
nonresident underbids the lowest bid submitted by a responsible resident bidder by an amount
that is not less than the amount by which a resident bidder would be required to underbid the
nonresident bidder to obtain a comparable contract in the state in which the nonresident's
principal place of business is located. A non-resident bidder is a contractor whose corporate
offices or principal place of business is outside of the state of Texas. (Source: Texas
Government Code Chapter 2252 Subchapter A Nonresident Bidders, (§ 2252.002) The bidder
will complete form WRD-259 which must be submitted with the bid.
Forms to be submitted with Bid:
• Bidder's Certifications regarding Equal Employment Opportunity and Non -Segregated
Facilities (WRD-255)
• Vendor Compliance with Non -Resident Bidder Requirements (WRD-259)
TWDB-0551 Revised 6/19/2012 Page 6
Construction Contract — Supplemental Conditions
1. SUPERSESSION
The Owner and the contractor agree that the TWDB Supplemental Conditions apply to that work
eligible for Texas Water Development Board assistance to be performed under this contract and
these clauses supersede any conflicting provisions of this contract.
2. PRIVITY OF CONTRACT
Funding for this project is expected to be provided in part by the Texas Water Development
Board. Neither the State of Texas, nor any of its departments, agencies or employees is, or will
be, a party to this contract or any lower tier contract. This contract is subject to applicable
provisions 31 TAC Chapters 363 and 375 in effect on the date of the assistance award for this
proj ect.
3. DEFINITIONS
(a) The term Owner means the local entity contracting for the construction services.
(b) The term "TWDB" means the Executive Administrator of the Texas Water Development
Board, or other person who may be at the time acting in the capacity or authorized to perform
the functions of such Administrator, or the authorized representative thereof.
4. LAWS TO BE OBSERVED
In the execution of the Contract, the Contractor must comply with all applicable Local, State and
Federal laws, including but not limited to laws concerned with labor, safety, minimum wages,
and the environment. The Contractor shall make himself familiar with and at all times shall
observe and comply with all Federal, State, and Local laws, ordinances and regulations which in
any manner affect the conduct of the work, and shall indemnify and save harmless the Owner,
Texas Water Development Board, and their representatives against any claim arising from
violation of any such law, ordinance or regulation by himself or by his subcontractor or his
employees.
5. REVIEW BY OWNER and TWDB
(a) The Owner, authorized representatives and agents of the Owner, and TWDB shall, at all
times have access to and be permitted to observe and review all work, materials, equipment,
payrolls, personnel records, employment conditions, material invoices, and other relevant
data and records pertaining to this Contract, provided, however that all instructions and
approval with respect to the work will be given to the Contractor only by the Owner through
authorized representatives or agents.
(b) Any such inspection or review by the TWDB shall not subject the State of Texas to any
action for damages.
6. PERFORMANCE AND PAYMENT BONDS
Each contractor awarded a construction contract furnish performance and payment bonds:
TWDB-0551 Revised 6/19/2012 Page 7
(a) the performance bond shall include without limitation guarantees that work done under the
contract will be completed and performed according to approved plans and specifications and in
accordance with sound construction principles and practices; and
(b) the performance and payment bonds shall be in a penal sum of not less than 100 percent of
the contract price and remain in effect for one year beyond the date of approval by the engineer
of the political subdivision.
(c) The contractor shall utilize a surety company which is authorized to do business in Texas in
accordance with Art. 7.19-1. Bond of Surety Company; Chapter 7 of the Insurance Code
7. PROGRESS PAYMENTS AND PAYMENT SCHEDULE
(a) The Contractor shall submit for approval immediately after execution of the Agreement, a
carefully prepared Progress Schedule, showing the proposed dates of starting and completing
each of the various sections of the work, the anticipated monthly payments to become due the
Contractor, and the accumulated percent of progress each month.
(b) The following paragraph applies only to contracts awarded on a lump sum contract price:
COST BREAKDOWN - The Contractor shall submit to the Owner a detailed breakdown of his
estimated cost of all work to be accomplished under the contract, so arranged and itemized as to
meet the approval of the Owner or funding agencies. This breakdown shall be submitted
promptly after execution of the agreement and before any payment is made to the Contractor for
the work performed under the Contract. After approval by the Owner the unit prices established
in the breakdown shall be used in estimating the amount of partial payments to be made to the
Contractor.
(c) Progress Payments
(1) The Contractor shall prepare his requisition for progress payment as of the last day of the
payment month and submit it, with the required number of copies, to the Engineer for his
review. Except as provided in Paragraph (3) of this subsection, the amount of the
payment due the Contractor shall be determined by adding to the total value of work
completed to date, the value of materials properly stored on the site and deducting (1)
five percent (5%) minimum of the total amount, as a retainage and (2) the amount of all
previous payments. The total value of work completed to date shall be based on the
actual or estimated quantities of work completed and on the unit prices contained in the
agreement (or cost breakdown approved pursuant to section 6.b relating to lump sum
bids) and adjusted by approved change orders. The value of materials properly stored on
the site shall be based upon the estimated quantities of such materials and the invoice
prices. Copies of all invoices shall be available for inspection by the Engineer.
(2) The Contractor shall be responsible for the care and protection of all materials and work
upon which payments have been made until final acceptance of such work and materials
by the Owner. Such payments shall not constitute a waiver of the right of the Owner to
require the fulfillment of all terms of the Contract and the delivery of all improvements
embraced in this Contract complete and satisfactory to the Owner in all details.
TWDB-0551 Revised 6/19/2012 Page 8
(3) This clause applies to contracts when the Owner is a Municipal Utility District, or Water
Control and Improvement District. The retainage shall be ten percent minimum of the
amount otherwise due until at least fifty percent of the work has been completed. After
the project is fifty percent completed, the District may reduce the retainage from ten
percent to no less than five percent.
(4) The five percent (5%) minimum retainage of the progress payments due to the Contractor
may not be reduced until the building of the project is substantially complete and a
reduction in the retainage has been authorized by the TWDB.
(5) The following clause applies only to contracts where the total price at the time of
execution is $400,000 or greater and the retainage is greater than 5% and the Owner is
not legally exempted from the condition (i.e. certain types of water districts).
The Owner shall deposit the retainage in an interest -bearing account, and the interest earned on
such retainage funds shall be paid to the Contractor after completion of the contract and final
acceptance of the project by the Owner.
(d) Withholding Payments. The Owner may withhold from any payment otherwise due the
Contractor so much as may be necessary to protect the Owner and if so elects may also
withhold any amounts due from the Contractor to any subcontractors or material dealers, for
work performed or material furnished by them. The foregoing provisions shall be construed
solely for the benefit of the Owner and will not require the Owner to determine or adjust any
claims or disputes between the Contractor and his subcontractors or Material dealers, or to
withhold any moneys for their protection unless the Owner elects to do so. The failure or
refusal of the Owner to withhold any moneys from the Contractor shall in no way impair the
obligations of any surety or sureties under any bond or bonds furnished under this Contract.
(e) Payments Subject to Submission of Certificates. Each payment to the Contractor by the
Owner shall be made subject to submission by the Contractor of all written certifications
required of him and his subcontractors by Section 3 hereof (relating to labor standards) and
other general and special conditions elsewhere in this contract.
(f) Final Payment.
(1) Upon satisfactory completion of the work performed under this contract, as a condition
before final payment under this contract or as a termination settlement under this contract
the contractor shall execute and deliver to the Owner a release of all claims against the
Owner arising under, or by virtue of, this contract, except claims which are specifically
exempted by the contractor to be set forth therein. Unless otherwise provided in this
contract, by State law or otherwise expressly agreed to by the parties to this contract,
final payment under this contract or settlement upon termination of this contract shall not
constitute a waiver of the Owner's claims against the contractor or his sureties under this
contract or applicable performance and payment bonds.
TWDB-0551 Revised 6/19/2012 Page 9
(2) After final inspection and acceptance by the Owner of all work under the Contract, the
Contractor shall prepare his requisition for final payment which shall be based upon the
carefully measured or computed quantity of each item of work at the applicable unit
prices stipulated in the Agreement or cost breakdown (if lump sum), as adjusted by
approved change orders. The total amount of the final payment due the Contractor under
this contract shall be the amount computed as described above less all previous payments.
(3) The retainage and its interest earnings, if any, shall not be paid to the Contractor until the
TWDB has authorized a reduction in, or release of, retainage on the contract work.
(4) Withholding of any amount due the Owner, under general and/or special conditions
regarding "Liquidated Damages," shall be deducted from the final payment due the
Contractor.
8. WORKMAN'S COMPENSATION INSURANCE COVERAGE
(a) The contractor shall certify in writing that the contractor provides workers' compensation
insurance coverage for each employee of the contractor employed on the public project.
(b) Each subcontractor on the public project shall provide such a certificate relating to
coverage of the subcontractor's employees to the general contractor, who shall provide
the subcontractor's certificate to the governmental entity.
(c) A contractor who has a contract that requires workers' compensation insurance coverage
may provide the coverage through a group plan or other method satisfactory to the
governing body of the governmental entity.
(d) The employment of a maintenance employee by an employer who is not engaging in
building or construction as the employer's primary business does not constitute engaging
in building or construction.
(e) In this section:
(1) "Building or construction" includes:
(A) erecting or preparing to erect a structure, including a building, bridge, roadway,
public utility facility, or related appurtenance;
(B) remodeling, extending, repairing, or demolishing a structure; or
(C) otherwise improving real property or an appurtenance to real property through
similar activities.
(2) "Governmental entity" means this state or a political subdivision of this state. The
term includes a municipality.
9. CHANGES
(a) The Owner may at any time, without notice to any surety, by written order, make any change in
the work within the general scope of the contract, including but not limited to changes:
(1) In the specifications (including drawings and designs);
(2) In the time, method or manner of performance of the work;
(3) In the Owner -furnished facilities, equipment, materials, services or site, or
(4) Directing acceleration in the performance of the work.
(5) The original contract price may not be increased under this section by more than 25
percent. The original contract price may not be decreased under this section by more than
25 percent without the consent of the contractor. (Local Government Code 271.060)
TWDB-0551 Revised 6/19/2012 Page 10
(b) A change order shall also be any other written order (including direction, instruction,
interpretation or determination) from the Owner which causes any change, provided the
contractor gives the Owner written notice stating the date, circumstances and source of the order
and that the contractor regards the order as a change order.
(c) Except as provided in this clause, no order, statement or conduct of the Owner shall be treated as
a change under this clause or entitle the contractor to an equitable adjustment.
(d) If any change under this clause causes an increase or decrease in the contractor's cost or the time
required to perform any part of the work under this contract, whether or not changed by any
order, the Owner shall make an equitable adjustment and modify the contract in writing. Except
for claims based on defective specifications, no claim for any change under paragraph (a)(2)
above shall be allowed for any costs incurred more than 20 days before the contractor gives
written notice as required in paragraph (a)(2). In the case of defective specifications for which the
Owner is responsible, the equitable adjustment shall include any increased cost the contractor
reasonably incurred in attempting to comply with those defective specifications.
(e) If the contractor intends to assert a claim for an equitable adjustment under this clause, the
contractor must, within 30 days after receipt of a written change order under paragraph (a) (I) or
the furnishing of a written notice under paragraph (a) (2), submit a written statement to the Owner
setting forth the general nature and monetary extent of such claim The Owner may extend the 30-
day period. The contractor may include the statement of claim in the notice under paragraph (2)
of this changes clause.
(f) No claim by the contractor for an equitable adjustment shall be allowed if made after final
payment under this contract.
(g) Changes that involve an increase in price will be supported by documentation of the costs
components in a format acceptable to the Owner.
10. PREVAILING WAGE RATES
Insert Wage Rate Determination(s)
A "wage determination" is the listing of wage and fringe benefit for each classification of
laborers and mechanics which the Administrator of the Wage and Hour Division of the U.S.
DOL has determined to be prevailing in a given area for a particular type of construction. The
Davis Bacon Wage Determinations are classified by the nature of the construction projects
performed, specifically listed as "schedules": residential, building, highway, and heavy
construction. Insert Wage Rate Determinations indicating which construction type is being used.
(More than one may be checked).
(a) I I Construction Type: Heavy determination
Includes those projects that are not properly classified as either "building," "highway," or
"residential." Unlike these classifications, heavy construction is not a homogenous
classification. Because of this catch-all nature, projects within the heavy classification
may sometimes be distinguished on the basis of their particular project characteristics,
and separate schedules may be issued for dredging projects, water and sewer line
projects, dams, major bridges, and flood control projects.
(b) I I Construction Type: Highway determination
TWDB-0551 Revised 6/19/2012
Page 11
Includes construction, alteration or repair of roads, streets, highways, runways, taxiways,
alleys, trails, paths, parking areas, and other similar projects not incidental to building or
heavy construction.
(c) Construction Type: Building determination
Includes construction of sheltered enclosures with walk-in access for the purpose of
housing persons, machinery, equipment or supplies; all construction of such structures;
the installation of utilities and of equipment, both above and below grade levels; as well
as incidental grading, utilities and paving. Such structures need not be "habitable" to be
building construction. Also, the installation of heavy machinery and/or equipment does
not generally change the project's character as a building.
(d) Construction Type: Residential
Includes the construction, alteration or repair of single-family houses, apartment
buildings of no more than four stories in height. This includes all incidental items such as
site work, parking areas, utilities, streets, and sidewalks.
Entities should review their contractor's wage decisions and confirm they provide an adequate
classification of the labor required for the specific construction contract. Most CWSRF projects
will fall under the "Heavy" construction type, but entities should ask their consulting engineers if
unsure. Some contracts or projects may require more than one general schedule to be included
depending on the nature and extent of the work (i.e. a building is constructed in a water treatment
facility). This is described in more detail in DOL's All Agency Memo No. 131. See website
http://www.dol.2ov/whd/programs/dbra/memorand.htm. In such cases, the contracting agency
should designate the work to which each wage determination or part thereof applies per FAR
22.404-2 thru 404-3 (Federal Acquisition Regulations).
https://www.acquisition.aov/far/current/html/Subpart%2022 4.html#wp1102017.
Should overlaps occur in the wage classification schedules for the contract(s), the owner may
consider adopting the higher rate classification.
In all cases, the entity is responsible to insure an adequate classification is provided to insure
compliance with the law. Where contractors alert the owner that the classification is inadequate,
the owner should work with the contractor and the DOL to address any valid concerns. See the
Contact Information for additional resources.
Contact Information
All questions regarding the Davis -Bacon guidance can be directed to: U.S. Department of Labor
Wage and Hour Divisionl-866-4USWAGE (1-866-487-9243), TTY: 1-877-889-5627, Monday -
Friday 8 a.m. to 8 p.m. Eastern Time.
If you require further information about Davis -Bacon and how to apply it to your project, please
contact the Texas Water Development Board, Mark Hall, P.E., Director, at (512) 463-8489.
Additional Resources:
TWDB-055 1 Revised 6/19/2012 Page 12
1. For Wage Determinations applicable to construction projects in Texas:
httn://www.wdol.gov/dba.asnx#3
2. Source for determine the prevailing wage rate for each state and county is on the web
page, Selecting Davis -Bacon Wage Decisions, provides criteria for state and county:
httn://www.wdol . gov/archdba.asnx
3. For more information on prevailing wage and wage determinations visit the Prevailing
Wage Resource Book: http://www.dol.gov/whd/recoverv/pwrb/toc.htm
4. The United States Department of Labor website:
http://www.dol.Qov/compliance/laws/comp-dbra.htm
The webpage provides an overview, compliance assistance material, poster information,
recordkeeping, DOL contact information and more.
5. Davis -Bacon and Related Acts Frequently Asked questions
More in-depth information can be accessed at the Department of Labor (DOL) website:
httn://www.dol.gov/whd/nrograms/dbra/faq s.htm
TWDB-0551 Revised 6/19/2012 Page 13
Contact Information — DOL Texas Offices
Dallas District Office
US Dept. of Labor
Wage & Hour Division
The Offices @ Brookhollow
1701 E. Lamar Blvd., Suite 270, Box 22
Arlington, TX 76006-7303
Houston District Office
US Dept. of Labor
Wage & Hour Division
8701 S.Gessner Drive, Suite 1164
Houston, TX 77074-2944
McAllen District Office
US Dept. of Labor
Wage & Hour Division
320 N. Main Street, Room 238
McAllen, TX 78501
Corpus Christi Area Office
US Dept. of Labor
Wage & Hour Division
Wilson Plaza
606 W. Carancahua, Suite 705
Corpus Christi, Texas 78476
San Antonio District Office
US Dept. of Labor
Wage & Hour Division
Northchase 1 Office Building
10127 Morocco, Suite 140
San Antonio, TX 78216
West Texas Panhandle and Northwest
Albuquerque District Office
Mailing Address:
US Dept. of Labor
Wage and Hour Division
P.O. Box 907
Albuquerque, NM 87103-0907
Physical Address:
500 Gold, SW - Suite 12000
Albuquerque, NM 87102
Phone:
(817) 861-2150
1-866-4-USWAGE
(1-866-487-9243)
Phone:
(713) 339-5525
1-866-4-USWAGE
(1-866-487-9243)
Phone:
(956) 682-4631
1-866-4-USWAGE
(1-866-487-9243)
Phone:
(361) 888-3152
1-866-4-USWAGE
(1-866-487-9243)
Phone:
(210)308-4515
1-866-4-USWAGE
(1-866-487-9243)
Curtis L. Poer
District Director
Robin Mallet
District Director
Eden Ramirez
District Director
Vacant
Asst. District Director
Juan Coria
District Director
uadrant: See Albuquerque, NM
Phone:
(505) 248-6100
1-866-4-USWAGE
(1-866-487-9243)
Patricia Davidson
District Director
TWDB-0551 Revised 6/19/2012
Page 14
11. Davis -Bacon Requirements
A. The following terms and conditions specify how sub -recipients that are governmental entities
will assist the TWDB, as the State recipient, in meeting its Davis -Bacon responsibilities to EPA.
If a sub -recipient has questions regarding when Davis -Bacon applies, obtaining the correct
Davis -Bacon wager determinations, Davis -Bacon provisions, or compliance monitoring, it may
contact the TWDB. The sub -recipient may also obtain additional guidance from the Department
of Labor's website at http://www.dol.zov/esa/whd/recovery/.
1. Applicability of the Davis -Bacon prevailing wage requirements
Davis -Bacon prevailing wage requirements apply to the construction, alteration, and repair
activity of infrastructure, including all construction, alteration and repair activity involving
wastewater or drinking water treatment plants is subject to Davis -Bacon. If a sub -recipient
encounters a unique situation at a site that presents uncertainties regarding Davis -Bacon
applicability, the sub -recipient must discuss the situation with the recipient State before
authorizing work on that site.
2. Obtaining Wage Determinations
(a) Sub -recipients shall obtain the wage determination for the locality in which a covered
activity subject to Davis -Bacon will take place prior to issuing requests for bids,
proposals, quotes or other methods for soliciting contracts (solicitation) for activities
subject to Davis -Bacon. These wage determinations shall be incorporated into
solicitations and any subsequent contracts. Prime contracts must contain a provision
requiring that subcontractors follow the wage determination incorporated into the prime
contract.
(i) While the solicitation remains open, the sub -recipient shall monitor www.wdol.gov on
a on a weekly basis to ensure that the wage determination contained in the solicitation
remains current. The sub -recipients shall amend the solicitation if DOL issues a
modification more than 10 days prior to the closing date (i.e. bid opening) for the
solicitation. If DOL modifies or supersedes the applicable wage determination less than
10 days prior to the closing date, the sub -recipients may request a finding from the State
recipient that there is not a reasonable time to notify interested contractors of the
modification of the wage determination. The State recipient will provide a report of its
findings to the sub -recipient.
(ii) If the sub -recipient does not award the contract within 90 days of the closure of the
solicitation, any modifications or supersedes DOL makes to the wage determination
contained in the solicitation shall be effective unless the State recipient, at the request of
the sub -recipient, obtains an extension of the 90 day period from DOL pursuant to 29
CFR 1.6(c)(3)(iv). The sub -recipient shall monitor www.wdol.gov on a weekly basis if it
does not award the contract within 90 days of closure of the solicitation to ensure that
wage determinations contained in the solicitation remain current.
TWDB-0551 Revised 6/19/2012 Page 15
(b) If the sub -recipient carries out activity subject to Davis -Bacon by issuing a task order,
work assignment or similar instrument to an existing contractor (ordering instrument)
rather than by publishing a solicitation, the sub -recipient shall insert the appropriate DOL
wage determination from www.wdol.gov into the ordering instrument.
(c) Sub -recipients shall review all subcontracts subject to Davis -Bacon entered into by prime
contractors to verify that the prime contractor has required its subcontractors to include
the applicable wage determinations.
(d) As provided in 29 CFR 1.6(f), DOL may issue a revised wage determination applicable to
a sub -recipient's contract after the award of a contract or the issuance of an ordering
instrument if DOL determines that the sub -recipient has failed to incorporate a wage
determination or has used a wage determination that clearly does not apply to the contract
or ordering instrument. If this occurs, the sub -recipient shall either terminate the contract
or ordering instrument and issue a revised solicitation or ordering instrument or
incorporate DOL's wage determination retroactive to the beginning of the contract or
ordering instrument by change order. The sub -recipient's contractor must be
compensated for any increases in wages resulting from the use of DOL's revised wage
determination.
3. Contract and Subcontract provisions.
PLEASE NOTE: This language must be included in all Davis -Bacon covered construction
contracts and subcontracts. (29 CFR Part 5.5).
(a) The TWDB, as the State recipient, shall insure that the sub-recipient(s) shall insert in full
in any contract in excess of $2,000 which is entered into for the actual construction,
alteration and/or repair, including painting and decorating, of a public building or public
work, or building or work financed in whole or in part from Federal funds or in
accordance with guarantees of a Federal agency or financed from funds obtained by
pledge of any contract of a Federal agency to make a loan, grant or annual contribution
(except where a different meaning is expressly indicated), and which is subject to the
labor standards provisions of any of the acts listed in § 5.1, the following clauses:
(1) Minimum wages
(i) All laborers and mechanics employed or working upon the site of the work (or under
the United States Housing Act of 1937 or under the Housing Act of 1949 in the
construction or development of the project), will be paid unconditionally and not less
often than once a week, and without subsequent deduction or rebate on any account
(except such payroll deductions as are permitted by regulations issued by the Secretary
of Labor under the Copeland Act (29 CFR part 3)), the full amount of wages and bona
fide fringe benefits (or cash equivalents thereof) due at time of payment computed at
rates not less than those contained in the wage determination of the Secretary of Labor
which is attached hereto and made a part hereof, regardless of any contractual
relationship which may be alleged to exist between the contractor and such laborers
and mechanics.
TWDB-0551 Revised 6/19/2012 Page 16
Contributions made or costs reasonably anticipated for bona fide fringe benefits under
section 1(b)(2) of the Davis Bacon Act on behalf of laborers or mechanics are
considered wages paid to such laborers or mechanics, subject to the provisions of
paragraph (a)(1)(iv) of this section; also, regular contributions made or costs incurred
for more than a weekly period (but not less often than quarterly) under plans, funds, or
programs which cover the particular weekly period, are deemed to be constructively
made or incurred during such weekly period. Such laborers and mechanics shall be
paid the appropriate wage rate and fringe benefits on the wage determination for the
classification of work actually performed, without regard to skill, except as provided
in §5.5(a)(4). Laborers or mechanics performing work in more than one classification
may be compensated at the rate specified for each classification for the time actually
worked therein: Provided, That the employer's payroll records accurately set forth the
time spent in each classification in which work is performed. The wage determination
(including any additional classification and wage rates conformed under paragraph
(a)(1)(ii) of this section) and the Davis Bacon poster (WH1321) shall be posted at all
times by the contractor and its subcontractors at the site of the work in a prominent
and accessible place where it can be easily seen by the workers.
Sub -recipients may obtain wage determinations from the U.S. Department of Labor's
website, www.wdo1.2ov.
(ii)(A) The sub-recipient(s), on behalf of EPA, shall require that any class of laborers
or mechanics, including helpers, which is not listed in the wage determination and
which is to be employed under the contract shall be classified in conformance with
the wage determination. The EPA award official shall approve an additional
classification and wage rate and fringe benefits therefore only when the following
criteria have been met:
(1) The work to be performed by the classification requested is not performed by a
classification in the wage determination; and
(2) The classification is utilized in the area by the construction industry; and
(3) The proposed wage rate, including any bona fide fringe benefits, bears a
reasonable
relationship to the wage rates contained in the wage determination.
(B) If the contractor and the laborers and mechanics to be employed in the
classification (if known), or their representatives, and the sub-recipient(s) agree on
the classification and wage rate (including the amount designated for fringe benefits
where appropriate), a report of the action taken shall be sent by the sub -recipient
(s) to the State award official. The State award official will transmit the report, to
the Administrator of the Wage and Hour Division, Employment Standards
Administration, U.S. Department of Labor, Washington, DC 20210. The
Administrator, or an authorized representative, will approve, modify, or disapprove
every additional classification action within 30 days of receipt and so advise the
TWDB-0551 Revised 6/19/2012 Page 17
State award official or will notify the State award official within the 30day period
that additional time is necessary.
(C) In the event the contractor, the laborers or mechanics to be employed in the
classification or their representatives, and the and the sub-recipient(s) do not
agree on the proposed classification and wage rate (including the amount
designated for fringe benefits, where appropriate), the award official shall refer the
questions, including the views of all interested parties and the recommendation of
the State award official, to the Administrator for determination. The Administrator,
or an authorized representative, will issue a determination within 30 days of receipt
and so advise the contracting officer or will notify the contracting officer within
the 30day period that additional time is necessary.
(D) The wage rate (including fringe benefits where appropriate) determined pursuant
to paragraphs (a)(1)(ii)(B) or (C) of this section, shall be paid to all workers
performing work in the classification under this contract from the first day on
which work is performed in the classification.
(iii) Whenever the minimum wage rate prescribed in the contract for a class of laborers or
mechanics includes a fringe benefit which is not expressed as an hourly rate, the
contractor shall either pay the benefit as stated in the wage determination or shall pay
another bona fide fringe benefit or an hourly cash equivalent thereof.
(iv) If the contractor does not make payments to a trustee or other third person, the
contractor may consider as part of the wages of any laborer or mechanic the amount
of any costs reasonably anticipated in providing bona fide fringe benefits under a plan
or program, Provided, That the Secretary of Labor has found, upon the written request
of the contractor, that the applicable standards of the Davis -Bacon Act have been met.
The Secretary of Labor may require the contractor to set aside in a separate account
assets for the meeting of obligations under the plan or program.
(2) Withholding. The sub-recipient(s), shall upon written request of the EPA Award
Official or an authorized representative of the Department of Labor, withhold or
cause to be withheld from the contractor under this contract or any other Federal
contract with the same prime contractor, or any other federally assisted contract
subject to Davis Bacon prevailing wage requirements, which is held by the same
prime contractor, so much of the accrued payments or advances as may be considered
necessary to pay laborers and mechanics, including apprentices, trainees, and helpers,
employed by the contractor or any subcontractor the full amount of wages required by
the contract. In the event of failure to pay any laborer or mechanic, including any
apprentice, trainee, or helper, employed or working on the site of the work, all or part
of the wages required by the contract, the (Agency) may, after written notice to the
contractor, sponsor, applicant, or owner, take such action as may be necessary to
cause the suspension of any further payment, advance, or guarantee of funds until
such violations have ceased.
(3) Payrolls and basic records.
TWDB-0551 Revised 6/19/2012 Page 18
(i) Payrolls and basic records relating thereto shall be maintained by the contractor during
the course of the work and preserved for a period of three years thereafter for all laborers
and mechanics working at the site of the work. Such records shall contain the name,
address, and social security number of each such worker, his or her correct classification,
hourly rates of wages paid (including rates of contributions or costs anticipated for bona
fide fringe benefits or cash equivalents thereof of the types described in section
1(b)(2)(B) of the Davis Bacon Act),daily and weekly number of hours worked,
deductions made and actual wages paid. Whenever the Secretary of Labor has found
under 29 CFR 5.5(a)(1)(iv) that the wages of any laborer or mechanic include the amount
of any costs reasonably anticipated in providing benefits under a plan or program
described in section 1(b)(2)(B) of the Davis Bacon Act, the contractor shall maintain
records which show that the commitment to provide such benefits is enforceable, that the
plan or program is financially responsible, and that the plan or program has been
communicated in writing to the laborers or mechanics affected, and records which show
the costs anticipated or the actual cost incurred in providing such benefits. Contractors
employing apprentices or trainees under approved programs shall maintain written
evidence of the registration of apprenticeship programs and certification of trainee
programs, the registration of the apprentices and trainees, and the ratios and wage rates
prescribed in the applicable programs.
(ii)(A) The contractor shall submit weekly, for each week in which any contract work is
performed, a copy of all payrolls to the sub -recipient, that is, the entity that receives the
subgrant or loan from the State capitalization grant recipient. Such documentation shall
be available on request of the State recipient or EPA. As to each payroll copy received,
the sub -recipient shall provide written confirmation in a form satisfactory to the State
indicating whether or not the project is in compliance with the requirements of 29 CFR
5.5(a)(1) based on the most recent payroll copies for the specified week. The payrolls
shall set out accurately and completely all of the information required to be maintained
under 29 CFR 5.5(a)(3)(i), except that full social security numbers and home addresses
shall not be included on the weekly payrolls. Instead the payrolls shall only need to
include an individually identifying number for each employee (e.g., the last four digits of
the employee's social security number). The required weekly payroll information may be
submitted in any form desired. Optional Form WH347 is available for this purpose from
the Wage and Hour Division Web site at
http://www.do1.2,ov/esa/whd/forms/wh347instr.htm or its successor site. The prime
contractor is responsible for the submission of copies of payrolls by all subcontractors.
Contractors and subcontractors shall maintain the full social security number and current
address of each covered worker, and shall provide them upon request to the sub-
recipient(s) for transmission to the State or EPA if requested by EPA, the State, the
contractor, or the Wage and Hour Division of the Department of Labor for purposes of an
investigation or audit of compliance with prevailing wage requirements. It is not a
violation of this section for a prime contractor to require a subcontractor to provide
addresses and social security numbers to the prime contractor for its own records, without
weekly submission to the sub-recipient(s).
TWDB-0551 Revised 6/19/2012 Page 19
(B) Each payroll submitted shall be accompanied by a "Statement of Compliance,"
signed by the contractor or subcontractor or his or her agent who pays or
supervises the payment of the persons employed under the contract and shall
certify the following:
(1) That the payroll for the payroll period contains the information required to be
provided under Sec. 5.5 (a)(3)(ii) of Regulations, 29 CFR part 5, the
appropriate information is being maintained under Sec. 5.5 (a)(3)(i) of
Regulations, 29 CFR part 5, and that such information is correct and complete;
(2) That each laborer or mechanic (including each helper, apprentice, and trainee)
employed on the contract during the payroll period has been paid the full
weekly wages earned, without rebate, either directly or indirectly, and that no
deductions have been made either directly or indirectly from the full wages
earned, other than permissible deductions as set forth in Regulations, 29 CFR
part 3;
That each laborer or mechanic has been paid not less than the applicable wage
rates and fringe benefits or cash equivalents for the classification of work
performed, as specified in the applicable wage determination incorporated into
the contract.
(3)
(C) The weekly submission of a properly executed certification set forth on the reverse
side of Optional Form WH-347 shall satisfy the requirement for submission of the
"Statement of Compliance" required by paragraph (a)(3)(ii)(B) of this section.
(D) The falsification of any of the above certifications may subject the contractor or
subcontractor to civil or criminal prosecution under section 1001 of title 18 and
section 231 of title 31 of the United States Code.
(iii) The contractor or subcontractor shall make the records required under
paragraph(a)(3)(i) of this section available for inspection, copying, or transcription
by authorized representatives of the State, EPA or the Department of Labor, and
shall permit such representatives to interview employees during working hours on
the job. If the contractor or subcontractor fails to submit the required records or to
make them available, the Federal agency or State may, after written notice to the
contractor, sponsor, applicant, or owner, take such action as may be necessary to
cause the suspension of any further payment, advance, or guarantee of funds.
Furthermore, failure to submit the required records upon request or to make such
records available may be grounds for debarment action pursuant to 29 CFR 5.12.
(4) Apprentices and trainees.
(i) Apprentices. Apprentices will be permitted to work at less than the predetermined rate
for the work they performed when they are employed pursuant to and individually
registered in a bona fide apprenticeship program registered with the U.S. Department of
Labor, Employment and Training Administration, Office of Apprenticeship Training,
Employer and Labor Services, or with a State Apprenticeship Agency recognized by the
Office, or if a person is employed in his or her first 90 days of probationary employment
TWDB-0551 Revised 6/19/2012 Page 20
as an apprentice in such an apprenticeship program, who is not individually registered in
the program, but who has been certified by the Office of Apprenticeship Training,
Employer and Labor Services or a State Apprenticeship Agency (where appropriate) to
be eligible for probationary employment as an apprentice. The allowable ratio of
apprentices to journeymen on the job site in any craft classification shall not be greater
than the ratio permitted to the contractor as to the entire work force under the registered
program. Any worker listed on a payroll at an apprentice wage rate, who is not registered
or otherwise employed as stated above, shall be paid not less than the applicable wage
rate on the wage determination for the classification of work actually performed. In
addition, any apprentice performing work on the job site in excess of the ratio permitted
under the registered program shall be paid not less than the applicable wage rate on the
wage determination for the work actually performed. Where a contractor is performing
construction on a project in a locality other than that in which its program is registered,
the ratios and wage rates (expressed in percentages of the journeyman's hourly rate)
specified in the contractor's or subcontractor's registered program shall be observed.
Every apprentice must be paid at not less than the rate specified in the registered program
for the apprentice's level of progress, expressed as a percentage of the journeymen hourly
rate specified in the applicable wage determination. Apprentices shall be paid fringe
benefits in accordance with the provisions of the apprenticeship program. If the
apprenticeship program does not specify fringe benefits, apprentices must be paid the full
amount of fringe benefits listed on the wage determination for the applicable
classification. If the Administrator determines that a different practice prevails for the
applicable apprentice classification, fringes shall be paid in accordance with that
determination. In the event the Office of Apprenticeship Training, Employer and Labor
Services, or a State Apprenticeship Agency recognized by the Office, withdraws approval
of an apprenticeship program, the contractor will no longer be permitted to utilize
apprentices at less than the applicable predetermined rate for the
work performed until an acceptable program is approved.
(ii) Trainees. Except as provided in 29 CFR 5.16, trainees will not be permitted to work
at less than the predetermined rate for the work performed unless they are employed
pursuant to and individually registered in a program which has received prior approval,
evidenced by formal certification by the U.S. Department of Labor, Employment and
Training Administration. The ratio of trainees to journeymen on the job site shall not be
greater than permitted under the plan approved by the Employment and Training
Administration. Every trainee must be paid at not less than the rate specified in the
approved program for the trainee's level of progress, expressed as a percentage of the
journeyman hourly rate specified in the applicable wage determination. Trainees shall be
paid fringe benefits in accordance with the provisions of the trainee program. If the
trainee program does not mention fringe benefits, trainees shall be paid the full amount of
fringe benefits listed on the wage determination unless the Administrator of the Wage
and Hour Division determines that there is an apprenticeship program associated with the
corresponding journeyman wage rate on the wage determination which provides for less
than full fringe benefits for apprentices. Any employee listed on the payroll at a trainee
rate who is not registered and participating in a training plan approved by the
Employment and Training Administration shall be paid not less than the applicable wage
TWDB-0551 Revised 6/19/2012 Page 21
rate on the wage determination for the classification of work actually performed. In
addition, any trainee performing work on the job site in excess of the ratio permitted
under the registered program shall be paid not less than the applicable wage rate on the
wage determination for the work actually performed. In the event the Employment and
Training Administration withdraws approval of a training program, the contractor will no
longer be permitted to utilize trainees at less than the applicable predetermined rate for
the work performed until an acceptable program is approved.
(iii) Equal employment opportunity. The utilization of apprentices, trainees and
journeymen under this part shall be in conformity with the equal employment opportunity
requirements of Executive Order 11246, as amended and 29 CFR part 30.
(5) Compliance with Copeland Act requirements. The contractor shall comply with the
requirements of 29 CFR part 3, which are incorporated by reference in this contract.
(6) Subcontracts. The contractor or subcontractor shall insert in any subcontracts the
clauses contained in 29 CFR 5.5(a)(1) through (10) and such other clauses as the EPA
determines may by appropriate, and also a clause requiring the subcontractors to include
these clauses in any lower tier subcontracts. The prime contractor shall be responsible for
the compliance by any subcontractor or lower tier subcontractor with all the contract
clauses in 29 CFR 5.5.
(7) Contract termination: debarment. A breach of the contract clauses in 29 CFR 5.5 may
be grounds for termination of the contract, and for debarment as a contractor and a
subcontractor as provided in 29 CFR 5.12.
(8) Compliance with Davis -Bacon and Related Act requirements. All rulings and
interpretations of the Davis -Bacon and Related Acts contained in 29 CFR parts 1, 3, and
5 are herein incorporated by reference in this contract.
(9) Disputes concerning labor standards. Disputes arising out of the labor standards
provisions of this contract shall not be subject to the general disputes clause of this
contract. Such disputes shall be resolved in accordance with the procedures of the
Department of Labor set forth in 29 CFR parts 5, 6, and 7. Disputes within the meaning
of this clause include disputes between the contractor (or any of its subcontractors) and
Sub-recipient(s), State, EPA, the U.S. Department of Labor, or the employees or their
representatives.
(10) Certification of eligibility.
(i) By entering into this contract, the contractor certifies that neither it (nor he or she) nor
any person or firm who has an interest in the contractor's firm is a person or firm
ineligible to be awarded Government contracts by virtue of section 3(a) of the Davis -
Bacon Act or 29 CFR 5.12(a)(1).
(ii)No part of this contract shall be subcontracted to any person or firm ineligible for
award of a Government contract by virtue of section 3(a) of the Davis -Bacon Act or 29
TWDB-0551 Revised 6/19/2012 Page 22
CFR 5.12(a)(1)(iii). The penalty for making false statements is prescribed in the U.S.
Criminal Code, 18U.S.C. 1001.
4. Contract Provision for Contracts in Excess of $100,000
(a) Contract Work Hours and Safety Standards Act. The sub -recipient shall insert the
following clauses set forth in paragraphs (a)(1), (2), (3), and (4) of this section in full in
any contract in an amount in excess of $100,000 and subject to the overtime provisions of
the Contract Work Hours and Safety Standards Act. These clauses shall be inserted in
addition to the clauses required by Item 3, above or 29 CFR 4.6. As used in this
paragraph, the terms laborers and mechanics include watchmen and guards.
(1) Overtime requirements. No contractor or subcontractor contracting for any part of the
contract work which may require or involve the employment of laborers or mechanics
shall require or permit any such laborer or mechanic in any workweek in which he or she
is employed on such work to work in excess of forty hours in such workweek unless such
laborer or mechanic receives compensation at a rate not less than one and one-half times
the basic rate of pay for all hours worked in excess of forty hours in such workweek.
(2) Violation; liability for unpaid wages; liquidated damages. In the event of any
violation of the clause set forth in paragraph (b)(1) of this section the contractor and any
subcontractor responsible therefore shall be liable for the unpaid wages. In addition, such
contractor and subcontractor shall be liable to the United States (in the case of work done
under contract for the District of Columbia or a territory, to such District or to such
territory), for liquidated damages. Such liquidated damages shall be computed with
respect to each individual laborer or mechanic, including watchmen and guards,
employed in violation of the clause set forth in paragraph (b)(1) of this section, in the
sum of $10 for each calendar day on which such individual was required or permitted to
work in excess of the standard workweek of forty hours without payment of the overtime
wages required by the clause set forth in paragraph (b)(1) of this section.
(3) Withholding for unpaid wages and liquidated damages. The sub -recipient, upon
written request of the EPA Award Official or an authorized representative of the
Department of Labor, shall withhold or cause to be withheld, from any moneys payable
on account of work performed by the contractor or subcontractor under any such contract
or any other Federal contract with the same prime contractor, or any other federally
assisted contract subject to the Contract Work Hours and Safety Standards Act, which is
held by the same prime contractor, such sums as may be determined to be necessary to
satisfy any liabilities of such contractor or subcontractor for unpaid wages and liquidated
damages as provided in the clause set forth in paragraph (b)(2) of this section.
(4) Subcontracts. The contractor or subcontractor shall insert in any subcontracts the
clauses set forth in paragraph (b)(1) through (4) of this section and also a clause requiring
the subcontractors to include these clauses in any lower tier subcontracts. The prime
contractor shall be responsible for compliance by any subcontractor or lower tier
subcontractor with the clauses set forth in paragraphs (b)(1) through (4) of this section.
(b) In addition to the clauses contained in Item 3, above, in any contract subject only to
the Contract Work Hours and Safety Standards Act and not to any of the other statutes
TWDB-0551 Revised 6/19/2012 Page 23
cited in 29 CFR 5.1, the Sub -recipient shall insert a clause requiring that the contractor
or subcontractor shall maintain payrolls and basic payroll records during the course of the
work and shall preserve them for a period of three years from the completion of the
contract for all laborers and mechanics, including guards and watchmen, working on the
contract. Such records shall contain the name and address of each such employee, social
security number, correct classifications, hourly rates of wages paid, daily and weekly
number of hours worked, deductions made, and actual wages paid. Further, the Sub -
recipient shall insert in any such contract a clause providing hat the records to be
maintained under this paragraph shall be made available by the contractor or
subcontractor for inspection, copying, or transcription by authorized representatives of
the (write the name of agency) and the Department of Labor, and the contractor or
subcontractor will permit such representatives to interview employees during working
hours on the job.
5. Compliance Verification.
(a) The sub -recipient shall periodically interview a sufficient number of employees
entitled to Davis -Bacon prevailing wages (covered employees) to verify that contractors
or subcontractors are paying the appropriate wage rates. As provided in 29 CFR 5.6(a)(3),
all interviews must be conducted in confidence. The sub -recipient must use Standard
Form 1445 or equivalent documentation to memorialize the interviews. Copies of the SF
1445 are available from EPA on request.
(b) The sub -recipient shall establish and follow an interview schedule based on its
assessment of the risks of noncompliance with Davis -Bacon posed by contractors or
subcontractors and the duration of the contract or subcontract. At a minimum, the sub -
recipient must conduct interviews with a representative group of covered employees
within two weeks of each contractor or subcontractor's submission of its initial weekly
payroll data and two weeks prior to the estimated completion date for the contract or
subcontract. Sub -recipients must conduct more frequent interviews if the initial
interviews or other information indicates that there is a risk that the contractor or
subcontractor is not complying with Davis Bacon. Sub -recipients shall immediately
conduct necessary interviews in response to an alleged violation of the prevailing wage
requirements. All interviews shall be conducted in confidence.
(c) The sub -recipient shall periodically conduct spot checks of a representative sample
of weekly payroll data to verify that contractors or subcontractors are paying the
appropriate wage rates. The sub -recipient shall establish and follow a spot check
schedule based on its assessment of the risks of noncompliance with Davis -Bacon posed
by contractors or subcontractors and the duration of the contract or subcontract. At a
minimum, the sub -recipient must spot check payroll data within two weeks of each
contractor or subcontractor's submission of its initial payroll data and two weeks prior to
the completion date the contract or subcontract. Sub -recipients must conduct more
frequent spot checks if the initial spot check or other information indicates that there is a
risk that the contractor or subcontractor is not complying with Davis -Bacon . In addition,
during the examinations the sub -recipient shall verify evidence of fringe benefit plans
TWDB-0551 Revised 6/19/2012 Page 24
and payments thereunder by contractors and subcontractors who claim credit for fringe
benefit contributions.
(d) The sub -recipient shall periodically review contractors and sub -contractors use of
apprentices and trainees to verify registration and certification with respect to
apprenticeship and training programs approved by either the U.S Department of Labor or
a state, as appropriate, and that contractors and subcontractors are not using
disproportionate numbers of, laborers, trainees and apprentices. These reviews shall be
conducted in accordance with the schedules for spot checks and interviews described in
Item 5(b) and (c) above.
(e) Sub -recipients must immediately report potential violations of the Davis -Bacon
prevailing wage requirements to the EPA Davis -Bacon contact listed above and to the
appropriate DOL Wage and Hour District Office listed at
http://www.dol. I.o\i/esa/contacts/whd/america2.htm.
The following form, Monthly Davis Bacon Act Certificate of Compliance Submittal by
Owner (Sub -Recipient) (DB-0154), must be completed by the project owner/sub-recipient
and submitted with monthly with the outlay. Information on outlay reporting may be
accessed at: http://www.twdb.state.tx.us/assistance/financial/outlav/
TWDB-0551 Revised 6/19/2012 Page 25
DB-0154
Revised 5/24/2012
MONTHLY DAVIS BACON ACT CERTIFICATE of COMPLIANCE
Submittal by Recipient
TWDB Project No.
Loan/Grant No.
This executed certificate must be submitted with each Outlay report for labor included
within construction contracts. This Certificate applies only for LOANS CLOSED AFTER
10/30/2009.
I, , of
(Name) (Title)
hereby certify that interviews, periodic reviews of a
(Name of entity)
representative sample of the weekly payroll data, and contractor weekly payroll
certifications such as OMB No. 1215-0149, have been performed to verify that contractors
and subcontractors are paying the appropriate wage rate for compliance with the DAVIS
BACON ACT, 40 U.S.C. §§3141 et seq. as amended and in conformance with the U.S.
Department of Labor regulations at 29 CFR Part 5, (Labor Standards Provisions
Applicable to Contracts Covering Federally Financed and Assisted Construction) and 29
CFR Part 3 (Contractors and Subcontractors on Public Work Financed in Whole or in
Part by Loans or Grants from the United States).
I understand that a false statement herein may subject me to penalties under federal and
state laws relating to filing false statements and other relevant statutes.
Signature Date
TWDB-0551 Revised 6/19/2012 Page 26
Additional Forms for Davis -Bacon
The following forms are suggestions only and may be used as tools
which may aid in complying with the Davis Bacon requirements.
TWDB-0551 Revised 6/19/2012 Page 27
STATEMENT OF COMPLIANCE CERTIFICATION BY
CONTRACTOR FOR SRF
TWDB Davis -Bacon Requirements
In accordance with Title 29 CFR Part 5.5(a)(3)(ii), each weekly payroll must be accompanied by a Statement of
Compliance Certification executed by each contractor/subcontractor employing mechanics and laborers at the work
site in which the federal government is to participate. Contractors may choose to use the DOL Form WH-347
payroll with the accompanying statement of compliance located on the back of Form WH-347 OR provide
contractor's own payroll form using this TWDB Statement of Compliance Certification, DB-0155.
Date:
Estimate Number: for the payroll period to
Name of Project: Location:
Contract Number: TWDB SRF Project #:
Date Contract Awarded:
I (Name and Title of Signatory Party)
do hereby state:
(1) That I pay or supervise the payment, during the above payroll period, of the persons employed by
(Contractor or Subcontractor);
that all persons employed on said project have been paid the full weekly wages earned;
that no rebates have been or will be made either directly or indirectly to or on behalf of said
(Contractor or Subcontractor)
from the full weekly wages eamed by any person and that no deductions have been made either directly or indirectly
from the full wages earned by any person, other than permissible deductions as defined in Regulations Part 3 (29
C.F.R. Subtitle A), issued by the Secretary of Labor under the Copeland Act, as amended (48 Stat. 948, 63 Start.
108, 72 Stat. 967; 76 Stat. 357; 40 U.S.C. § 3145) as described below:
(2) That any payrolls otherwise under this contract required to be submitted for the above period are correct and
complete; that the wage rates for laborers or mechanics contained therein are not less than the applicable wage rates
contained in any wage determination incorporated into the contract; that the classifications set forth therein for each
laborer or mechanic conform with the work he performed.
(3) That any apprentices employed in the above period are duly registered in a bona fide apprenticeship program
registered with a State apprenticeship agency recognized by the Bureau of Apprenticeship and Training, United
States Department of Labor. or if no such recognized agency exists in a State, are registered with the Bureau of
Apprenticeship and Training, United States Department of Labor.
(4) That:
(a) WHERE FRINGE BENEFITS ARE PAID TO APPROVED PLANS, FUNDS, OR
PROGRAMS
TWDB-0551 Revised 6/19/2012
DB-0155
Revised 10/13/10
in addition to the basic hourly wage rates paid to each laborer or
mechanic listed in the above referenced payroll, payments of fringe
benefits as listed in the contract have been or will be made to appropriate
programs for the benefit of such employees, except as noted in section 4(c)
EXCEPTIONS below.
(b) WHERE FRINGE BENEFITS ARE PAID IN CASH
Each laborer or mechanic listed in the attached payroll has been paid, as
indicated on the payroll, an amount not less than the sum of the applicable
basic hourly wage rate plus the amount of the required fringe benefits as
listed in the contract, except as noted in section 4(c) below.
(c) EXCEPTIONS
EXCEPTION (CRAFT)
REMARKS
NAME AND TITLE SIGNATURE
EXPLANATION
THE WILLFUL FALSIFICATION OF ANY OF THE ABOVE STATEMENTS MAY SUBJECT THE CONTRACTOR
OR SUBCONTRACTOR TO CIVIL OR CRIMINAL PROSECUTION. SEE SECTION 1001 OF TITLE 18 AND
SECTION 231 OF TITLE 31 OF THE UNITED STATES CODE.
Page 28
DB-0155
Revised 10/13/10
TWDB-0551 Revised 6/19/2012 Page 29
TWDB-0551 Revised 6/19/2012
U.S. Department of Labor
Wags and Hour Divisl on
NAME OF CONTRACTOR ❑ OR SUBCONTRACTOR
PAYROLL NO.
(1) (2)
NAME AND INDIVIDUAL IDENTIFYING NUMBER
(e.g., (AST FOUR DIGITS OF SOCIAL SECURITY
NUMBER) OF WORKER
PAYROLL
(For Contractor's Optional Use; See Instructions at www.dot.govlwhdlformslwh347instr.htm)
Persons ere not required to respond to the collection of information unless A displays a currently valid OMS control number.
ADDRESS
FOR WEEKENDING
(3) (4) DAY AND DATE
PROJECT AND LOCATION
(5)
WORK o >> TOTAL
CLASSIFICATION 0 WJRKE EA(�iO4" HOURS
0
0
(6) (72
GROSS WITH -
RATE AMOUNT HOLDING
OF PAY EARNED FICA TAX
/
VHD
U.S. Wage and Hour Division
Rev Dec. 2008
OMB No.: 1215-0149
Expires. 12)3112011
PROJECT OR CONTRACT/NO
(6)
DEDUCTIONS
(9
NET
WAGES
TOTAL PAID
OTHER DEDUCTIONS FOR WEEK
While completion of Form W H-347 Is optional, It Is mandatory for covered contractors and subcontractors perorming work on Federall/ financed or assisted construction contracts to re pond to the Information co lest ion conta ned in 29 C F R. §§ 3 3, 5 5(a) The Copeland Act
(40US.C.§3145) contractors and subcontractors perforrnng work on Federally financed or assisted construction contracts to"furnish weekly a statement with respect to the wages paid each employee during the preceding week. U.S. Department of Labor (DO regulations at
29 C.F.R § 5.5(a)(3)(Ip require contractors to submitweekb a cop/ of all payrolls to the Federal agency contracting for or financing the construction project, accompanied by a signed"Statement o1 Compliance' ndl sating that the payrolls are correct and complete and that each laborer
or mechanic has been paid not less than the proper Davls-Eaton prevailing wage rate for the work performed DOL and federal contracting agencies reserving this Information review the lnformllon to determine hat employees have received legally required wages and fnnge benefits.
Public Burden Statement
We estimate that Is wgl take an average of 55 minutes to complete this collection, Including time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the c °Sechon of Information you have
am comments regarding these estimates or any other aspect °(inns collection, Including sugge stions for reducing this burden, send them to the Administrator, Wage and Hour Dlvlslon, U S. Department of Labor. Room53502, 200 ConslnW on Avenue, N.W.
Washington D C 20210
(over)
TWDB-0551 Revised 6/19/2012
Date
(Name of Signatory Party) (Title)
do hereby state:
(1) That I pay or supervise the payment of the persons employed by
m the
(Contractor or 9.Ibcontractor)
; that during the payroll period commencing on the
(Building or Work)
day of , and ending the day of
all persons employed on said project have been paid the full weekly wages earned, that no rebates have
been or will be made either directly or indirectly to or on behalf of said
from the full
(Contractor or Subcontractor)
weekly wages eamed by any person and that no deductions have been made either directly or indirectly
from the full wages eamed by any person, other than permissible deductions as defined in Regulations, Part
3 (29 C.F.R. Subtitle A). issued by the Secretary of Labor under the Copeland Act, as amended (48 Stat. 948,
63 Start. 108, 72 Stat. 967; 76 Stat. 357; 40 U.S.C. § 3145), and described below:
(2) That any payrolls otherwise under this contract required to be submitted for the above period are
correct and complete; that the wage rates for laborers or mechanics contained therein are not less than the
applicable wage rates contained in any wage determination incorporated into the contract; that the
classifications set forth therein for each laborer or mechanic conform with the work he performed.
(3) That any apprentices employed in the above period are duly registered in a bona fide
apprenticeship program registered with a State apprenticeship agency recognized by the Bureau of
Apprenticeship and Training, United States Department of Labor, or if no such recognized agency exists in a
State, are registered with the Bureau of Apprenticeship and Training, United States Department of Labor.
(4) That:
(a) WHERE FRINGE BENEFITS ARE PAID TO APPROVED PLANS, FUNDS, OR PROGRAMS
— in addition to the basic hourly wage rates paid to each laborer or mechanic listed in
the above referenced payroll, payments of fringe benefits as listed in the contract
have been or will be made to appropriate programs for the benefit of such
employees, except as noted in section 4(c) below.
(b) WHERE FRINGE BENEFITS ARE PAID IN CASH
❑ - Each laborer or mechanic listed in the above referenced payroll has been paid,
as indicated on the payroll, an amount not less than the sum of the applicable
basic hourly wage rate plus the amount of the required fringe benefits as listed
in the contract, except as noted in section 4(c) below.
(c) EXCEPTIONS
REMARKS -
NAME MOTE -LE
EXCEPTION (CRAFT) EXPLANATION
SIGNATURE
THE WILLFUL FALSIFICATION OF ANY OF THE ABOVE STATEMENTS MAY SUE..ECT THE CONTRACTOR OR
SUBCONTRACTOR TO CIVIL OR CRIMINAL PROSECUTION SEE SECTION 1001 OF TITLE 18 AND SECTION 231 OF TITLE
31 OF THE UNITED STATES CODE
DOL Labor Standards Interview SF-1445
LABOR STANDARDS INTERVIEW
CONTRACT NUMBER
NAME OF PRIME CONTRACTOR
NAM OF EMPLOYER
LAST NAMG
SUPERVISOR'S' 14AME
FIRST NAM
ACTION
LAST NAM
STREET ADDRESS
CITY
WORK CLASSIFICATION
EMPLOYEE INFORMATION
FIRST NAME MI
STATE
ZIP CODE
WAGE RATE
CHECK BELOW
YES NO
Do you work over 8 hour per day?
Do you work over 40 hours per week?
Are you paid at least time and a half for overtime hours?
Are you receiving any cash payments far fringe benefits required by the posted wage determination decision?
WHAT DEDUCTIONS OTHER THAN TLX AND SOCIAL SECURITY ARE MADE FROM YOUR PAY?
HOW MANY HOURS DID YOU WORK ON YOUR LAST WORK DAY GEFORE
THIS INTERVIEW?
OATS OF LAST WORK DAY BEFORE INTERVIEW Matti'D,D)
DATE YOU BEGAN 'A'ORK ON THIS PROJECT (ritiMDD)
THE ABOVE IS CORRECT TO THE ;EST OF MY KNOWLEDGE
EMPLOYEE'S SIGNATURE.
SIGNATURE
INTERVIEWER
'WORK EMPLOYEE WAS DOING WHEN INTERVIEWED
TOOLS YOU IJIG
DATE (YY.W.40D)
TYPED OR PRINTED NAME DATE (YMMOD)
INTERVIEWER'S COMMENTS
ACTION Of g.xFizratiun ncadad, use commcnrrtion) YES NO
IS EMPLOYEE. PROPERLY CLASSIFIED AND PAIO?
ARE WAGE RATES AND POSTERS DISPLAYED?
FOR USE BY PAYROLL CHECKER
C AGOVE INFORMATION IN AGREEMENT WITH PAYROLL OATA?
YES' L NO
C MMENTS
LAST NAMG
SIGNATURE
AUTHORIZED FOR LOCAL REPRODUCTION
Prrei,auition usabla
TWDB-0551 Revised 6/19/2012
CHECKER
FIRST NAME
MI
JOG TITLE
DATE reYW.,..!0D,I
STANDARD FORM 1445 (P.R.'. 12 96)
PrQszrihad bv GSA - FAR i4B CFRI 53 222.1;g;I
Page 32
Davis Bacon Poster, WH-1321 http://www.dol.gov/whd/reps/compliance/posters/davis.htm
FOR LABORERS AND MECHANICS
EMPLOYED ON FEDERAL OR FEDERALLY
ASSISTED CONSTRUCTION PROJECTS
THE UNITED STATES DEPARTMENT OF LABOR WAGE AND HOUR DIVISION
PREVAILING
WAGES
OVERTIME
You must be paid not less than the wage rate listed in the Davis -Bacon
Wage Decision posted with this Notice for the work you perform.
You must be paid not less than one and one-half times your basic
rate of pay for all hours worked over 40 in a work week. There are few
exceptions.
ENFORCEMENT Contract payments can be withheld to ensure workers receive wages
and overtime pay due, and liquidated damages may apply if overtime
pay requirements are not met. Davis -Bacon contract clauses allow
contract termination and debarment of contractors from future federal
contracts for up to three years. A contractor who falsifies certified
payroll records or induces wage kickbacks may be subject to civil or
criminal prosecution, fines and/or imprisonment.
APPRENTICES Apprentice rates apply only to apprentices properly registered under
approved Federal or State apprenticeship programs.
PROPER PAY If you do not receive proper pay, or require further information on the
applicable wages, contact the Contracting Officer listed below:
or contact the U.S. Department of Labor's Wage and Hour Division.
For additional information:
1-866-4-USWAGE
(1-866-487-9243) I I Y: 1-877-889-5627
1111WW.WAGEHOUR.DOL.GOV
U.S. Department of Labor I Employment Standards Administration I Wage and Hour Division
TWDB-0551 Revised 6/19/2012
rilji
Division
WH 1321 (Revised Apnl 2009)
Page 33
12. EQUAL EMPLOYMENT OPPORTUNITY AND AFFIRMATIVE ACTION
This provision only applies to Clean Water State Revolving Fund Program projects and Drinking
Water Financial Assistance Program projects which receive funds made directly available by
Federal funding and the contract agreement is for more than $10,000.
During the performance of this contract, the Contractor agrees as follows:
(a) The Contractor will not discriminate against any employee or applicant for employment
because of race, color, religion, sex, age, handicap, or national origin. The Contractor
will take affirmative action to ensure that applicants are employed, and that employees
are treated during employment without regard to their race, color, religion, sex, age,
handicap, or national origin. Such action shall include, but not be limited to the
following: Employment, upgrading, demotion, or transfer; recruitment or recruitment
advertising; layoff or termination; rates of pay or other forms of compensation; and
selection for training, including apprenticeship. The Contractor agrees to post in
conspicuous places, available to employees and applicants for employment, notices to
be provided setting forth the provisions of this nondiscrimination clause.
(b) The Contractor will, in all solicitations or advertisements for employees placed by or on
behalf of the Contractor, state that all qualified applicants will receive considerations for
employment without regard to race, color, religion, sex, age, handicap, or national
origin.
(c) The Contractor will send to each labor union or representative of workers with which he
has a collective bargaining agreement or other contract or understanding, a notice to be
provided advising the said labor union or workers' representatives of the Contractor's
commitments under this section, and shall post copies of the notice in conspicuous
places available to employees and applicants for employment.
(d) The Contractor will comply with all provisions of Executive Order 11246 of September
24, 1965, the Age Discrimination in Employment Act of 1967,29 U.S.C.A. 621 (1985),
Executive Order 12250 of November 2, 1980, the Rehabilitation Act of 1973, 29
U.S.C.A. 701 et seq. (1985), and of the rules, regulations, and relevant orders of the
Secretary of Labor.
(e) The Contractor will furnish all information and reports required by Executive Order
11246 of September 24, 1965, and by rules, regulations, and orders of the Secretary of
Labor, or pursuant thereto, and will permit access to his books, records, and accounts by
the administering agency and the Secretary of Labor for purposes of investigation to
ascertain compliance with such rules, regulations, and orders.
(f) In the event of the Contractor's noncompliance with the nondiscrimination clauses of
this contract or with any of the said rules, regulations, or orders, this contract may be
canceled, terminated, or suspended in whole or in part and the Contractor may be
declared ineligible for further Government contracts or federally assisted construction
contracts in accordance with procedures authorized in Executive Order 11246 of
September 24, 1965, and such other sanctions may be imposed and remedies invoked as
TWDB-0551 Revised 6/19/2012 Page 34
(g)
provided in Executive Order 11246 of September 24, 1965, or by rule, regulation, or
order of the Secretary of Labor, or as otherwise provided by law.
The Contractor will include the portion of the sentence immediately preceding
paragraph (a) and the provisions of paragraphs (a) through (g) in every subcontract or
purchase order unless exempted by rules, regulations, or orders of the Secretary of
Labor issued pursuant to section 204 of Executive Order 11246 of September 24, 1965,
so that such provisions will be binding upon each subcontractor or vendor. The
Contractor will take such action with respect to any subcontract or purchase order as the
administering agency may direct as a means of enforcing such provisions, including
sanctions for noncompliance: PROVIDED, HOWEVER, That in the event a Contractor
becomes involved in, or is threatened with, litigation with a subcontractor or vendor as a
result of such direction by the administering agency the Contractor may request the
United States to enter into such litigation to protect the interest of the United States.
(h) The Contractor will comply with Executive Order 11246 based on its implementation of
the Equal Opportunity Clause, specific affirmative action obligations required by the
Standard Federal Equal Employment Opportunity Construction Contract Specifications,
as set forth in 41 CFR Part 60-4 and its efforts to meet the goals established for the
geographical area where the Contract is to be performed. The hours of minority and
female employment and training must be substantially uniform throughout the length of
the Contract, and in each trade, and the Contractor shall make a good faith effort to
employ minorities and women evenly on each of its projects. The transfer of minority or
female employees or trainees from Contractor to Contractor or from project to project
for the sole purpose of meeting the Contractor's goals shall be a violation of the
Contract, the Executive Order, and the regulations in 41 CFR Part 60-4. The goals are
expressed as percentages of the total hours of employment and training of minority and
female utilization the Contractor should reasonably be able to achieve in each
construction trade in which it has employees in the covered area. Goals are published
periodically in the Federal Register in notice form, and such notices may be obtained
from any office of federal contract compliance programs office or from federal
procurement contracting officers (512) 229-5835. The Contractor is expected to make
substantially uniform progress toward its goal in each craft during the period specified.
Whenever the Contractor, or any subcontractor at any tier, subcontracts a portion of the work
involving any construction trade, it shall physically include in each subcontract in excess of
$10,000 the provisions of these specifications and the notice which contains the applicable goals set
for minority and female participation and which is set forth in the solicitations from which this
contract resulted.
12. DEBARMENT AND SUSPENSION
This provision applies only to Clean Water State Revolving Fund Program projects and Drinking
Water Financial Assistance Program projects which receive funds made directly available by
Federal funding. This contract is subject to the Title 40 Code of Federal Regulations Part 32
concerning Debarment and Suspension. The contractor will comply with the assurances provided
with the bid that led to this contract.
TWDB-0551 Revised 6/19/2012 Page 35
13. ARCHEOLOGICAL DISCOVERIES AND CULTURAL RESOURCES
No activity which may affect properties listed or properties eligible for listing in the National Register of
Historic Places, or eligible for designation as a State Archeological Landmark is authorized until the Owner
has complied with the provisions of the National Historic Preservation Act and the Antiquities Code of
Texas. The Owner has previously coordinated with the appropriate agencies and impacts to known cultural
or archeological deposits have been avoided or mitigated. However, the Contractor may encounter
unanticipated cultural or archeological deposits during construction.
If archeological sites or historic structures which may qualify for designation as a State Archeological
Landmark according to the criteria in 13 TAC 41.6 - 41.10, or that may be eligible for listing on the National
Register of Historic Places in accordance with 36 CFR Part 800, are discovered after construction operations
are begun, the Contractor shall immediately cease operations in that particular area and notify the Owner,
the TWDB, and the Texas Antiquities Committee, P.O. Box 12276, Capitol Station, Austin, Texas 78711-
2276. The Contractor shall take reasonable steps to protect and preserve the discoveries until they have been
inspected by the Owner's representative and the TWDB. The Owner will promptly coordinate with the State
Historic Preservation Officer and any other appropriate agencies to obtain any necessary approvals or
permits to enable the work to continue. The Contractor shall not resume work in the area of the discovery
until authorized to do so by the Owner.
14. ENDANGERED SPECIES
No activity is authorized that is likely to jeopardize the continued existence of a threatened or endangered
species as listed or proposed for listing under the Federal Endangered Species Act (ESA), and/or the State of
Texas Parks and Wildlife Code on Endangered Species, or to destroy or adversely modify the habitat of such
species.
If a threatened or endangered species is encountered during construction, the Contractor shall immediately
cease work in the area of the encounter and notify the Owner, who will immediately implement actions in
accordance with the ESA and applicable State statutes. These actions shall include reporting the encounter
to the TWDB, the U. S. Fish and Wildlife Service, and the Texas Parks and Wildlife Department, obtaining
any necessary approvals or permits to enable the work to continue, or implement other mitigation actions.
The Contractor shall not resume construction in the area of the encounter until authorized to do so by the
Owner.
15. HAZARDOUS MATERIALS
Materials utilized in the project shall be free of any hazardous materials, except as may be specifically
provided for in the specifications.
If the Contractor encounters existing material on sites owned or controlled by the Owner or in material
sources that are suspected by visual observation or smell to contain hazardous materials, the Contractor shall
immediately notify the Engineer and the Owner. The Owner will be responsible for the testing for and
removal or disposition of hazardous materials on sites owned or controlled by the Owner. The Owner may
suspend the work, wholly or in part during the testing, removal or disposition of hazardous materials on sites
owned or controlled by the Owner.
16. PROJECT SIGN
A project IDENTIFICATION SIGN will be provided to the contractor. The contractor shall erect the sign in
a prominent location at the construction project site or along a major thoroughfare within the community as
directed by the Owner.
TWDB-0551 Revised 6/19/2012 Page 36
17. OPERATION AND MAINTENANCE MANUALS AND TRAINING
(a) The Contractor shall obtain installation, operation, and maintenance manuals from manufacturers and
suppliers for equipment furnished under the contract. The Contractor shall submit three copies of
each complete manual to the Engineer within 90 days after approval of shop drawings, product data,
and samples, and not later than the date of shipment of each item of equipment to the project site or
storage location.
(b) The Owner shall require the Engineer to promptly review each manual submitted, noting necessary
corrections and revisions. If the Engineer rejects the manual, the Contractor shall correct and
resubmit the manual until it is acceptable to Engineer as being in conformance with design concept
of project and for compliance with information given in the Contract Documents. Owner may
assess Contractor a charge for reviews of same items in excess of three (3) times. Such procedure
shall not be considered cause for delay. Acceptance of manuals by Engineer does not relieve
Contractor of any requirements of terms of Contract.
(c) The Contractor shall provide the services of trained, qualified technicians to check final equipment
installation, to assist as required in placing same in operation, and to instruct operating personnel in
the proper manner of performing routine operation and maintenance of the equipment.
(d) Operations and maintenance manuals specified hereinafter are in addition to any operation,
maintenance, or installation instructions required by the Contractor to install, test, and start-up the
equipment.
(e) Each manual to be bound in a folder and labeled to identify the contents and project to which it
applies. The manual shall contain the following applicable items:
(1) A listing of the manufacturer's identification, including order number, model, serial number, and
location of parts and service centers.
(2) A list of recommended stock of parts, including part number and quantity.
(3) Complete replacement parts list.
(4) Performance data and rating tables.
(5) Specific instructions for installation, operation, adjustment, and maintenance.
(6) Exploded view drawings for major equipment items.
(7) Lubrication requirements.
(8) Complete equipment wiring diagrams and control schematics with terminal identification.
18. AS -BUILT DIMENSIONS AND DRAWINGS
(a) Contractor shall make appropriate daily measurements of facilities constructed and keep accurate
records of location (horizontal and vertical) of all facilities.
TWDB-0551 Revised 6/19/2012 Page 37
(b) Upon completion of each facility, the Contractor shall furnish Owner with one set of direct prints,
marked with red pencil, to show as -built dimensions and locations of all work constructed. As a
minimum, the final drawings shall include the following:
(1) Horizontal and vertical locations of work.
(2) Changes in equipment and dimensions due to substitutions.
(3) "Nameplate" data on all installed equipment.
(4) Deletions, additions, and changes to scope of work.
(5) Any other changes made.
Forms to be submitted with executed contracts
1. Contractor's act of Assurance (ED-103)
2. Contractor's Resolution on Authorized Representative (ED-104)
3. Bidder's Certification (WRD-255)
4. Vendor Compliance with Reciprocity on Non -Resident Bidders (TWDB-0459)
These forms are available on the TWDB website, httu://www.twdb.state.tx.us/financial/instructions/
TWDB-0551 Revised 6/19/2012 Page 38
WRD-255
01/2010
BIDDER'S CERTIFICATIONS
Project Name:
Project Number:
Contract For:
The following certifications must be completed by the bidder for each contract.
A. EQUAL EMPLOYMENT OPPORTUNITY:
( ) I have developed and have on file at my each establishment affirmative action programs
pursuant to 41 CFR Part 60-2.
( ) I have participated in previous contract(s) or subcontract(s) subject to the equal
opportunity clause under Executive Orders 11246 and 11375. I have filed all reports due
under the requirements contained in 41 CFR 60-1.7.
( ) I have not participated in previous contracts(s) subject to the equal opportunity clause
under Executive Orders 11246 and 11375.
( ) I will obtain a similar certification from any proposed subcontractor(s), when appropriate.
B. NONSEGREGATED FACILITIES
( ) I certify that I do not and will not maintain any facilities provided for my employees in a
segregated manner, or permit my employees to perform their services at any location under
my control where segregated facilities are maintained; and that I will obtain a similar
certification prior to the award of any federally assisted subcontract exceeding $10,000 which
is not exempt from the equal opportunity clause as required by 41 CFR 60-1.8.
I understand that a false statement on this certification may be grounds for rejection of this bid
proposal or termination of the contract award.
Typed Name & Title of Bidder's Authorized Representative
Signature of Bidder's Authorized Representative Date
Name & Address of Bidder
TWDB-0551 Revised 6/19/2012 Page 39
TWDB-0459
Reviewed 7/22/2010
VENDOR COMPLIANCE WITH RECIPROCITY ON NON-
RESIDENT BIDDERS
Government Code 2252.002 provides that, in order to be awarded a contract as low bidder, a non-
resident bidder must bid projects for construction, improvements, supplies or services in Texas at
an amount lower than the lowest Texas resident bidder by the same amount that a Texas resident
bidder would be required to underbid a non-resident bidder in order to obtain a comparable contract
in the state in which the non-resident's principal place of business is located. A non-resident bidder
is a contractor whose corporate offices or principal place of business is outside of the state of
Texas. This requirement does not apply to a contract involving Federal funds. The appropriate
blanks in Section A must be filled out by all out-of-state or non-resident bidders in order for your
bid to meet specifications. The failure of out-of-state or non-resident contractors to do so will
automatically disqualify that bidder. Resident bidders must check the blank in Section B.
A. Non-resident vendors in
business, are required to be
A copy of the statute is attached.
(give state), our principal place of
percent lower than resident bidders by state law.
Non-resident vendors in (give state), our principal place of
business, are not required to underbid resident bidders.
B. Our principal place of business or corporate offices are in the State of
Texas:
BIDDER:
Company
City State Zip
By: (please print)
Signature
Title: (please print)
THIS FORM MUST BE RETURNED WITH THE BID
TWDB-0551 Revised 6/19/2012 Page 40
ED-103
01/03/2010
CONTRACTOR'S ACT OF ASSURANCE
STATE OF TEXAS
COUNTY OF
BEFORE ME, , a Notary Public duly commissioned and qualified
in and for the County of in the State of Texas came and appeared
, as represented by , the
corporations , who declares he/she is authorized to
represent pursuant to provisions of a resolution
adopted by said corporation on the day of , 20
(a duly certified copy of such resolution is attached to and is hereby made a part of this
document).
, as the representative of
declares that assures the Texas Water Development
Board that it will construct
project at , Texas,
in accordance with sound construction practice, all laws of the State of Texas, and the rules
of the Texas Water Development Board.
GIVEN UNDER MY HAND and seal of office this day of
20 A.D.
My Commission expires
Signature
Printed Name
TWDB-0551 Revised 6/19/2012 Page 41
ED-I04
Revised 5/7/10
CONTRACTOR'S RESOLUTION ON AUTHORIZED
REPRESENTATIVE
Name or Names
I hereby certify that it was RESOLVED by a quorum of the directors of the
, meeting
Name of Corporation
on the day of , 20_, that ,
, and , be, and hereby is,
authorized to act on behalf of , as its
Name of Corporation
representative, in all business transactions conducted in the State of Texas, and;
That all above resolution was unanimously ratified by the Board of Directors at said
meeting and that the resolution has not been rescinded or amended and is now in full forces
and effect; and;
In authentication of the adoption of this resolution, I subscribe my name and
affix the seal of the corporation this
(seal)
day of , 20_.
Secretary
TWDB-0551 Revised 6/19/2012 Page 42
DETAILS
THIS PAGE INTENTIONALLY LEFT BLANK
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
Sanitary Sewer Rehab Contract 75, Part 1
CFW Project #1480
NOTE TO DESIGNER: IN
ACCORDANCE WITH SECTION
33 05 10, ACCEPTABLE
BACKFILL WALL BE
COMMONLY USED WHERE
SOIL CONDI11ONS ALLOW
ACCEPTABLE
BACKFILL MATERIAL
IN ACCORDANCE WITH
SECTION 33 05 10
FORT WORTH
SURFACE REPAIR
I� I
+ + + + + + + + + + + i
+ + + 4- + + + + + + + +
+ + + + + + + + + + + i -_
+ + + t + + + + + + + +
+ + + + + + + + + + + I-
++++fi+}+}++++++++++++t}i-I
+ t t + + + + + + + + +
+ + + + + + + + + + + i
+ + + + + + + + + + + +
+ + 95% COMPACTION + i-)
++++ -2% TO +5% OF OPTIMUM ++ I-
+/ + MOISTURE CONTENT }
i- + + + + + + + + + +
+ + + + + + + + + + + i -
+ + + + + + + + + + +
1- - ++
++ ++ ++ ++ ++ ++ ++ ++ ++ +++I+II-
_I
I I + + + + + + + + ++
- +++++++++++++
-1++++++++++++II
- + + + + + + + + + + + -
II- +++++++++++++++++++++++ �I
_ + + + + + + + + + + + +
- +++++++++++ill -
I_++++++++++++_
CITY OF FORT WORTH, TEXAS
FINAL BACKFILL
- < 15' UNDER PAVEMENT
- ALL DEPTHS FOR
NON -PAVED AREAS
REVISED: 10-08-2012
ACCEPTABLE BACKFILL
33 05 10-D001
NOTE TO DESIGNER: IN
ACCORDANCE WITH SECTION
33 05 10, CLSM WILL ONLY
BE USED WHEN AN
OBSTRUCTION CREATES THE
NEED FOR A FLOWING
BACKFILL, OR AS DIRECTED
BY CITY.
CLSM IN ACCORDANCE
WITH SECTION 03 34 13,
BACKFILL IN ACCORDANCE
WITH SECTION 33 05 10
F2ORTH
SURFACE REPAIR
'V VVVV7V'V V VV VV9`-
V V v V v V V V VV V V 9 V V V _
-1' V 9 V V V V V V V V 9 v V V V'1I
IITV V V V v V V v V V V V V V V V--1
=VV99VVV999V9 9 7II
II> 9 V V VVV V V V V V V V V V 5 =1
- 9 V 9 9 V V V V V V V V V V V V-
-1'vvvvvvv9 V V V vvvv'11-
11:V v v V V v V v 9 9 V V v V v V -'
j'' yVVVVVV999vV9v7vv'-�
= IF7 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 ((-
yjm,vvvvvvvvvvvVv V vvv-
I'9VVVVVV5VVV V9VV'11-
lT
v v 9 V 9 V V V V V V 9 v V V V-
Iry V 9 V V V v v V V 9V V V V V I I
di-11V V V V V V V V V V V V V V V
- V V V V 9 V V V 9 v V V V 9 v 9
—1 57VVVVVVVVVVVVVv'l1-
119 V 9 v V 9 V V V V V V 9 v V v-
- vvvvvvVv'v79v'v�1
-1vvvvvvvvvvvvvvvvRE
/ Iiii-------
EMBEDMENT
FINAL
BACKFILL
VARIES
CITY OF FORT WORTH, TEXAS
CONTROLLED LOW STRENGTH
MATERIAL (CLSM) BACKFILL
REVISED:10-08-2012
33 05 10-D004
NOTE TO DESIGNER: THE INTENT
IS THAT THE CONTRACTOR CAN
CHOOSE BETWEEN SELECT
BACKFILL AND CSS.
ACCEPTABLE BACKFILL
MATERIAL IN ACCORDANCE
WITH SECTION 33 05 10
BACKFILL WITH CSS OR
SELECT BACKFILL IN
ACCORDANCE WITH
SECTION 33 05 10
F24ORTH
SURFACE REPAIR
TTTTTTTY-TT.
+++++++++++
+ + + + + + + + + + i
+ + + + i• t + + + + + _
+ + + + + + + + + + 4
+ + + + + + + + + + I
+ + + + + + + + + + + 4 -
I-++++++++++++
- + + 95% COMPACTION F +
II:+ -2% TO +5% OF OPTIMUM + 1
++{' MOISTURE CONTENT F++i-I
--I++++++++++++11-
(I-++ ++ + + + +
+ + + + ++ + + + + + + +++t
Il
+ + + + + + + + + + + 1
+ + + + + + + + + t
+ +-++ 4- + + + + + +
, 0OOOO��_A� �N. l
O ° O ° O ° 98% COMPACTION -I
O O O -2% TO +5% OF
O°O°O°O OPTIMUM LIT
h0°O°O°O MOISTURE -_)
CONTENT II
►u
=�o°O°O°O
II O-O°°° \ `_
I I
EMBEDMENT
FINAL
BACKFILL
15'
FINAL
BACKFILL
VARIES
NOTE:
BACKFILL FOR TOTAL
FINAL BACKFILL DEPTH
GREATER THAN 15' DEEP
CITY OF FORT WORTH, TEXAS REVISED: 10-08-2012
DEEP TRENCH BACKFILL
33 05 10-D005
CLSM PER SECTION 33
04 13, BACIFLL PER
SECTION 33 05 10
2' MIN.
EXISTING GROUND
+ + + + + + + + + + + + + +
+ + + + + + + + + + + + + + + + + +
+ + + + + + + + + + +
+++++++++++++
a + + +
+ + + + + + + + + + + +
+ + + + + + + + + + + + +
++++++++++ V 4 17174 44174 4+
+++++' V V V V V V V V 4 V
+ ++++ V V V V V 4 a 4 44 \+
•+++++++++'vvvvvvvvvv +++
+ + v4444a4VVV04 +
+ + + +'vvvvvvvvvv + +
4.0417va44744+++
+
,i4A,V V VV V9 4 v44 V VV4+ + +`
V V 9 C + + +
+ + + + + '744v44vv44+ + +
'++++++++++v V V 4 v 4 4 4 V V 1%,++++++
+++++ +' V V V V V V V V V V + + + +
+ + + + + + 4aV4v4v444c+ + + + + + PIPE EMBEDMENT PER
r ++++++.vvvvvvvvvv ++++++
+++++ + +++ '9 V V 4 4 v V V 4 4 i� + + + + + SECTION 33 05 10
:•�:� 'vvvvvvvvvVI, •1
:•'49 a 4444444
"' 41744744449 .. .. ..
V V V 9 V 4 V 444
'4444v4v744
4 4 V v V 4 v 4 4 4'
VVVVVVVV9a
v V v V 4 v 4 a v v'
''a444 f44v7717 C{{I
.•• • ' v v v v 0 r1 n l :...
EXISTING GROUND
PIPE
TYPICAL PROFILE
SLOPED VERTICAL
TRENCH TRENCH
WALL WALL
PIPE BACKFILL PER
SECTION 33 05 10
/\//- /" /\//\\�/�*+Y+++=+r+-+T+*+*+*+*+*+*+*+.+~+/' /\''/\//\//\//\//' /�/\//•\// \//
\/\\ \\ \ +++++++++++++ + +/\j
is
vvvvvvvvvvvvvvvv
vvvvvv444vvavvvv'.
\ \ a a a a 4 a a a 9 a a a a 4 a\\ \//\\/\
vvvvvvvvvav4vvv'
//\ \ vvvvvvvvvvvvvvv\ \ \ \
VVVVVvVV4V49V',////
\\�\\\ vvavvvavvvavv\\\\/\\ \\ �UNDISTURBED SOIL
vvvvvvvvvvvv'
v 744444 vvvv ACCEPTABLE
Vv4Vv49 vvv' BACKFILL PER
vvvavvvv vv
vvv44vvvv SECTION 33 05 10
'9VVV7vvvv
a v v v 4 v 4 v
v 4vv 4v 4v CLSM PER SECTION 03
vvv vvvv'
'vv4444vv 3413, BACKFILL PER
vv v v ' SECTION 33 05 10
.vv7oioc�av
9
TRENCH WIDTH PER v v
SECTION 33 05 10 'vvvvvV
4 4 4 V 4 4 4 4'
v v n o v n n o
ORT WORTH
TRENCH
I WIDTH
TYPICAL SECTION
CITY OF FORT WORTH, TEXAS REVISED: 08-31-2012
TRENCH WATER STOP
33 05 10-D006
+
+ + + + 4- FILL. WITH CLSM UNTIL ENTIRE
+ + + + + +
DIAMETER OF PIPE IS FILLED
+ + + + + + + + +
+ + + + + + + + + + TO PREVENT INFILTRATION
+ + + + + +
BACKFILL ,
77.7 '7 '7 '7 7+ .7+`7 + + v r\\\ WITH
ACCEPTABLE ,„\--v, 7777777 -7 7 77777,777 7
BACKFILL PER //\,777777777 7777777 v 77,c
SECTION 33 05 10 /7777777777'77 77777777777
7\\:,777 V 7 '7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7
// '7777777' 7 7 7 V 7 7 7 7 777 7 7 44
EXISTING
PIPE TO BE
ABANDONED
'‘7 VVVVVV V 7 77,74777717477
/77777777777,7777777777
.,•:774777771 77977.77774747
"."777777'777 77777777777 /X--77777'777 7 7 V 7 777777777
V 7 7 7777777777777747-9
. . _
—12" TYR —
FORT WORTH
PLUG EXISTING PIPE BULKHEAD TO
WITH CLSM PER RETAIN CLSM
SECTION 03 34 13
NOTE:
1. ABANDONMENT SHALL BE PER SECTION 02 41 14
2. SURFACE REPAIR SHALL BE PER SECTIONS 32 01
17, 32 01 29 OR 32 14 16 DEPENDING ON
EXISTING SURFACE
3. A WATER PRESSURE PLUG PER 02 41 14—D123
SHALL BE AN ACCEPTABLE ALTERNATIVE WHERE
APPLICABLE.
CITY OF FORT WORTH, TEXAS REVISED: 08-31-2012
PIPE ABANDONMENT PLUG
02 41 14-D007
LIFTING BOX
HINGED COVER
PLAN VIEW - FRAME AND COVER
PROFILE VIEW - COVER
OPENING
FRAME WIDTH
PROFILE VIEW - FRAME
CONCRETE COLLAR AS
REQUIRED PER MANHOLE
LID ASSEMBLY DETAILS
COLLAR SHALL EXTEND
AT LEAST 3" MIN.
BELOW MANHOLE TOP
OUTSIDE DIAMETER SHALL BE
GREATER THAN OR EQUAL TO
OUTSIDE DIAMETER OF FRAME
AND LESS THAN OR EQUAL TO
OUTSIDE DIAMETER OF
MANHOLE CONE OR TOP
INSIDE DIAMETER SHALL BE
EQUAL TO INSIDE DIAMETER
OF FRAME
PLAN VIEW - GRADE RINGS
NOTES:
1. PROVIDE HINGED FRAME AND COVER
WHERE INDICATED IN THE DRAWINGS
AND ON DETAILS.
2. LIDS SHALL BE INTEGRALLY MARKED
INDICATING "WATER", "SANITARY
SEWER", OR "STORM DRAIN" AS
DESIGNATED ALONG WITH FORT WORTH
LOGO PER SECTION 33 05 13.
3. ALL HINGED FRAMES AND COVERS
SHALL REQUIRE A WATER -TIGHT
GASKET.
4. FOR WATER AND SANITARY SEWER,
ALL TYPES OF FRAMES SHALL ALLOW
MINIMUM 30-INCH OPENING, UNLESS
OTHERWISE SPECIFIED IN THE
DRAWINGS.
5. FOR STORM DRAIN ALL TYPES OF
FRAMES SHALL ALLOW MINIMUM
24-INCH OPENING PER SECTION 33 05
13, UNLESS OTHERWISE SPECIFIED IN
THE DRAWINGS.
IF LID IS IN PAVEMENT,
ORIENT HINGE TOWARD
ONCOMING TRAFFIC
FRAME
MAX.
COVER
MAXIMUM OF 3 -�
GRADE RINGS
ALLOWED
IN TRAFFIC AREAS GRADE
RINGS SHALL BE CONCRETE,
OTHERWISE HDPE WILL ALSO
BE PERMITTED
MANHOLE OR VAULT
PER DRAWINGS
FORT WORTH CITY OF FORT WORTH, TEXAS
WATER -TIGHT HINGED MANHOLE FRAME,
COVER AND GRADE RINGS
RAM-NEK OR
EQUIVALENT (TYP.)
REVISED: 08-31-2012
33 05 13-D008
PLAN VIEW - FRAME AND COVER
PLAN VIEW - GRADE RINGS
iiiuuii/I
PROFILE VIEW - COVER
OPENING
'RAME WIDTH
PROFILE VIEW - FRAME
CONCRETE COLLAR AS
REQUIRED PER MANHOLE
LID ASSEMBLY DETAILS
COLLAR SHALL EXTEND
AT LEAST 3" MIN.
BELOW MANHOLE TOP
OUTSIDE DIAMETER SHALL BE
GREATER THAN OR EQUAL TO
OUTSIDE DIAMETER OF FRAME
AND LESS THAN OR EQUAL TO
OUTSIDE DIAMETER OF
MANHOLE CONE OR TOP
INSIDE DIAMETER SHALL BE
EQUAL TO INSIDE DIAMETER
OF FRAME
FORT WORTH
FRAME
12"
MAX.
NOTES:
1. PROVIDE STANDARD FRAME AND COVER
WHERE NOT OTHERWISE INDICATED IN
THE DRAWINGS OR ON THE DETAILS.
2. LIDS SHALL BE INTEGRALLY MARKED
WITH "WATER", "SANITARY SEWER", OR
"STORM DRAIN" AS DESIGNATED ALONG
WITH FORT WORTH LOGO PER SECTION
33 05 13.
3. FOR WATER AND SANITARY SEWER,
ALL TYPES OF FRAMES SHALL ALLOW
MINIMUM 30-INCH OPENING, UNLESS
OTHERWISE SPECIFIED IN THE
DRAWINGS.
4. FOR STORM DRAIN ALL TYPES OF
FRAMES SHALL ALLOW MINIMUM
24-INCH OPENING PER SECTION 33 05
13, UNLESS OTHERWISE SPECIFIED IN
THE DRAWINGS.
COVER
MAXIMUM OF 3
GRADE RINGS
ALLOWED
IN TRAFFIC AREAS GRADE
RINGS SHALL BE CONCRETE,
OTHERWISE HDPE WILL ALSO
BE PERMITTED
MANHOLE OR VAULT 'H
PER DRAWINGS
CITY OF FORT WORTH, TEXAS
MANHOLE FRAME, COVER
AND GRADE RINGS
RAM-NEK OR
/ EQUIVALENT (TYP.)
\•
REVISED: 10-16-2012
33 05 13-D009
EXISTING HMAC
PAVEMENT
ririr rli riirri
rP rr<r� r\�
2' MIN
(TYP.)
UNDISTURBED z�
EXISTING SUBGRADE V .,•;•;
TREATED �j;,
SUBGRADE
ACCEPTABLE BACKFILL \•.'•
OR AS REQUIRED BY 2 '
DRAWINGS PER SECTION
33 05 10
FORT WORTH
CONCRETE
COLLAR
PLAN VIEW
PROPOSED HMAC
PAVEMENT REPAIR
FRAME AND COVER AS
INDICATED IN THE DRAWINGS
SECTION VIEW
EXISTING HMAC
PAVEMENT
PAVEMENT REPAIR PER
ASPHALT PAVEMENT
TRENCH REPAIR DETAILS
AS INDICATED IN THE /
DRAWINGS
,r'r'r'r'r`
\i\i\A /\/\i,
MANHOLE OR VAULT
PER DRAWINGS
NOTES:
1. THIS DETAIL TO BE USED ONLY WHERE
SPECIFIED ON THE DRAWINGS IN
COMBINATION WITH PROPOSED MANHOLE
OR VAULT IN THE SAME LOCATION.
2. IF GRADE RINGS ARE USED, THEY SHALL
BE NO LESS THAN 2" THICK, AND SHALL
NOT EXCEED 12" IN TOTAL HEIGHT. NO
MORE THAN 3 TOTAL GRADE RINGS.
SHALL BE ALLOWED.
3. MEASUREMENTS ARE TYPICAL FOR ALL
SIDES OF MANHOLE/VAULT LID
ASSEMBLY.
CITY OF FORT WORTH, TEXAS
MANHOLE LID ASSEMBLY - EXISTING
HMAC PAVEMENT (CONE)
REVISED: 08-31-2012
33 05 13-D010
n{, _ j.�.�.y: .C�^ :`,J i .j...� 1'.i .�L. :L S� .1:'a�i
..1 �n_ _
'>"..
_ � fi.•�.�'
� - .•;�.�
�} �
, ��..: t
. �' Y'
• {�
.r� .
.{ i�_
. J •, 1
' �'..
, y�:
...ti :�
.JT !yy ::.
'r`�
�{?.• �K"�".
i�,,` �
_ .t ,
}'�„�f'• _ •4'�
... r'.`�`• ! y'',' ~ ; �y ,-
- - .i., '
`��~,
- ";:. . .
. f •�'��.•�.,a
.l V.�.,.i`"[
v�� •.
_ •.` .f,
.�:
�
�
:�r . �.,;
<:a:: : j.
- �:i� a'
' i� +
: {'r
-%� " - 8— 4 BARS 4' :'*�l
<:
:r= ;`_��
�
:1`• •Fr:�-<�� ��,_� �' ;.`;;.�:
�r`: .i t= `.�� 'LONG TIE TO .t: •'1:, a}; -i":
..n�, i4'• r'i '.�f �
' �. •: I '' .t. -
�'j`• � � 4 BARS •.•r• . r', e `
•'i•'. LONGITU 1
`� ',•i� D NAL AND
•,1 ti. ..5.'�4:+
_ •:�'
�'1<•' - �f •i'
.i: '�:" �`y;' '' z'
TRANSVERSE �,x
f.t: Y' ..e�: y'
! ti. y '�2 : - :'(.;" r
�.] f'1'a_ ..ii .. .
.i`.':�,.t,^.:� � �'F��. 4' �i4'"
- .l'�•:+�i� -�9:= �•REWFORCEMENT ��`•
��f'•- - '�� < �: a � � <'r , r � • _ • ;'j s � a;;••'� . .,- :"4`�.
.� 4 .( �. ,< !; , Y ;t,
°a�' `f: _ 'f.>. _ :.t...i'' .1J
..`.j• .y�s,i: :6�:• _ .�y .�+•• ��• >i:�:-�1,��.
'b� '{i~ I fl'"1. , ft
-. J.�j: �:.:n.tj' : f.',;.�v � f f.i
�1�. ^ �.j : •S'.•< •'1 r
'i�� �,'i"��1��< - YI;� ��
:�j /�' �1��� � .'�r 1', _
,r �;�1.�.' �f' :i�
•ra"' . �
'�N': . 2. : C� . 1.: `,f.
_ .i .:
. �.
. S' ' }: /�-
t4' 'X:y� �.f:��.l
y�r`. �;f•4 ���!
' t. .K� i
',.:y..� ` f:. '.` �.�.
.X" , !`•
•�ri �� .S �
.i..�:l �#.
) : :� �, �_
. `� �
t'i'�• - •L::^::.i ,�h�•
j•. �t�' s.i� .1f ..l•..
4 t..AV..f•.... . ta�:: - ;.'"� '�
{ :<' if..
:.t•i ii,� ! ' �4t' ,('^
4. � ��
:��
�• f"i
�.4':::
;�.'a
� L:
•.'( .
; �. � .��
•<< .2 i:
_ _ ).• � •'Sr .
��^. . ', ir � �'t:
.�g� .if; '.f� f �i. .•J:...�
•(r i .s.f. "fi� :f.li;,�:J ^��
'�1. •>,�'�{Y..}`�:~� � ..1� .1:."a"n�:.:"
��ti �L'� �r�� ���.
,'I' ,i.:?%i.• �J.:. ••Y _ ���:
��4" F! ':.S . �5 �'y •��i`�`. . ��i:.
,^c. :r: ..i '�ti� .a-,^<'.:ss�.�.�:
. - .�. ��'' .S,
'�s�.' `,?.: '-#_ ,..t �. ,.z.. l �. . . •.'.g.'; .,� -
' ,dF - �.y�... ' i a. { .1«+,. ,?� , `., I ,s. ; �:y. ` �,' .
:k.-_ �2" MIN. • -.��t:r `�7:
..,�,, '..�;•. '•y :i: _ :
-•;>�!��; ' SEPARATION' . � ` o�:
.V,' •.Ci', f• :�f.:' : .E: .;vw+���
•J'• ii::=„ -y' DISTANCE �� ` �f
:i� - - .i�, �;4`'3;�-'Z' �'y'.<
` i: ;'�,'rt,,� .F•
- � �F� •.� � ' y'.
; �', '•1.•~ - '•}' .h�' 4' YE y�., •
,,f. ..k.;1•: �%(.�.� �St�', •�y_. �cl��`
�{c . .! 1, ''7•. :;y,.<"8i .
. �t� .-�" .A.. .
.I � �t.' i .`�
' `�{ :j � :,t'.�'�-.•'
: ?..,� •;�;,,• J � • - � _
.,x�; �r.r' �� - ,` ai'
- �x�.` �i. .� ?�<t;:.:.': �•�'`
, r�. . - -
�;F�� �. .I. �.�:.�� �.�ti � �
.'.i,. .�, '.S'+"y syr�' _ _ i;�..`,'�
. �.r�,^ `i_t8" " '
..� `f•�. .A, %
•f: � ,'@.�-
- DOWEL BARS �
- :<-I. '<C'�y�'�.. .Yµ ��.i 1
- ii: •� 7
~ia.r �l�i :.•'C•.' � i:.G _ :!`�r ",.>. e
. d'. ��.' F i.i: _
.f�' i..'.:..
1 : `�t '
��.i. l �''� -. �I4•: -
a i : '. �i'
._ • �
.r��,'!
�•i,
. f+ _ �y * •
� l :a: -�: :
+i._i.• :i'• -u•
�.;... .. ,. ..
, ,, f ;.. ,... . . .. ...,:. , +, �
. .
,5.(. >r` _ '..l. ' :•Yf^�:`'' '�ic.
.,`.+ ;
'�t {:•a '
_ •�iz
' 'rl. vti• �.A'
`_« :4.
� `�c�, µi: ' f: .
f•
, j �� Y s
f., � .. � :
3;.
"%�
': �'.
:.i' �`, . ' ' ' .
f%.
:,> �•.
. `Y", �Y , •'�
.i • ii: '� .
-4
: �Y � . t � 'Y �i- .
.w+:: :i.' Si` �f�`J '��`,F•�:
:":� -
�1'��
x:��
S ` ' `J3
i�3•s' �)..
� .1 `�I.
'N: �
, g.
;'ti � -
- 'i
:�J ,
;j •r `.
�L .
' 2 �' �' 7
af., j-:t�::. �
:{� � �1
. \•���'
:<a
c.=4 .l.�ir''
'7" 1'�' .i.��
e.flK r�:.
! J..�
't '
+: �'y; .
J�i
:r�
. �w � .'Y!':.
;'�'
; �t:�e: . : �� _
� q� : j•.
_ : f�: �
' ^.\
•�.�i�
�4:.:.- /Y:�.
^'t
"•4, �
�1 - ,e'.a
b •�.'� ��Pti �.
v%'": C'i .
.a.� . i ' :5:
:� ;•�.
� f �•
' 's'% .l
..i �'<'. ::r•:: ::�
_ - ;,r,: -'t.c'' .
... .< <s.�.... .. . ; <
.. • �• • .
,_o<� .. ' . .-'., r ..:>: .: +- �'
., . .�..!�::
.;i ra
- .' (.,. ,�::;; ..� _ :. �'•. i��.'!.;� ;
� �`� ; �..Y�., . [. : •. �r. v' i �'Q-,., .',:i;:. .. -
!i. ti:�:.]�• �, J., �
•'{ • • Y
j..` '•A '^nw ' i1��:,•
.P' • S',
..4 ' �.'� �. ,.Z .
�i
.'i.' a
e� . _
' S'• �I��
.. �:
I~4. : i •
1�.� :
ll
.Y : <•t`•
_ t,� �� :
ir
_ .f� .
.. � . . , i . y..
4�
.., .. t . . . . . . . • i'�•
. . . . . , , t '�s' .
. . . . ..a .. . .., t v..> :�=\•-.:.... .. . .. � . . ... . . ... � v .. . ..«- .
PLAN VIEW ��PROPOSED'CONCRETE
PAVEMENT REPAIR EXISTING
CONCRETE
FOR CONCRETE STREETS CONSTRUCTION JOINT PAVEMENT
< 10 1RS OLD REPAIR PER 32 13 13—�511
ENTIRE PANEI,
OTHERWISE 3' MIN. (TYP.) 8AR SPACING AND
EXISTING PAVEMENT THICKNESS
CONCRETE SHALL BE PER CONCRETE
FRAME AND COVER AS PAVEMENT TRENCH REPAIR
PAVEMENT INDICATED IN THE DRAWINGS DETAILS AS INDICATED IN
THE DRAWINGS
t`y.} : t• %: 't.3` � %.:t;: s :5; ' , :t . ,.�„'.:...t.;;,> ,.4 . .
•} �. '.S^ •L,sA,�.. •~ r:i'�'y:. Y; .I•.ti.,�
~ { �`x 3. �. �• . � �. . �'' : t
. � 'S �� �" i.':�
� c. •'. i;' `:i"i`K - .Y GROUT FACE . - '�+�• : T
._J' �S�•.4Nit.fe :Jf, A:.$: " .l..�•
'•r'?''�'� �';'- SMOOTH (TYP.) ,"3 :=.~� ''3„ MIN. ((TYP�) • �':;:;
'�l�l%t��;�l�'`S ..• : � 12" MAX. ` -'.<, i'c ; f .
� t i t r �` �� ',�' ;r. .,.' .< -.�:' _ �'=��'e -" t' , .. -,��-. ` r�`��r,��A�� �/r
/ / ! ! I I , -4'�{ �� ^t: ' �I . � ,� .,;� ��: � .� :.l�. ( / / �
/ � a . '4..:.:;i.. .�s''; ,r
�\��� ` �.'. , .'.','.'.`.'a'.' _ 2 ROWS RAM—NEK OR ..�i , `•', '.i, '.', a', � � �
.. •.: '.� >> ♦ /\\/\\�
/\\�/\\ /\` \�/�,�/��/\�/� 4. `-- EQUI VA�EN T (TYP. ) :{ '����/\�/\�/\��\�/\�
UNDISTURBED � ; �=�'� ;.y� ''.•��:�a;: *;�;�:���;° � MANHO�E OR
EXISIING SUBGRADE � . -�=' �'
TREATED •�d-''.9"=� ``i ` + \ VAULT PER
SUBGRADE � : �t'' ":; / DRAWINGS
/ ' _•'*� �h :; ::: ;•;� � ��
� �j •' '�`r�
ACCEPTABLE BACKFILL \ �;
OR AS REQUIRED BY °�':+>-,t �
DRAWINGS PER SECTION
33 OS 10
NOTES:
SECTION VIEW �� T��S DETAII TO 8E USEO ONIY WHERE SPECIFIED
ON THE DRAWINGS IN COMBINAliON WITH PROPOSED
MANHOLE OR VAUITIN THE SAME IOCATION.
2. A�� MEASUREMENTS ARE TYPICAL FOR ALL SIDES
OP MANHOIE/VAULT UD ASSEMB�Y.
3. IF GRADE RINGS ARE USED, THEY SNALL BE NO
LESS TNAN 2" THICK, AND SHAL� NOT EXCEED 12"
IN TOTAI HEIGHT. NO MORE THAN 3 TOTAL GRADE
RINGS. SHALL 8E ALLOWED.
4. FOR CONCRETE S7REETS LESS THAN 10 YEARS OLD,
ENTIRE PANEI SHAL� 8E REPLACED, OTHERWISE
REPLACEO CONCRETE SHALL EXTEND A MINIMUM OF
3' BEYOND MANHOLE IN ALL DIRECTIONS.
5. CONCRETE PAVING SHALL BE PAID AS A SEPARATE
ITEM.
FORT WORTH CITY OF FORT WORTH, TEXAS REVISED: 08-31-2012
MANHOLE LID ASSEMBLY - EXISTING '-'
CONCRETE PAVEMENT (CONE) 33 05 13-D012
:;�.:
:�
:�• •;
`:��::
�A�•3H;
r +�
�: y:rr�:
}� ..-��
.,�r
. s;
; .o: s!.
VARIES
(TYP.)
�------
:! l: ��. �4. :.• �. - �` !'•. ;'/': .j el'% " •e y .' �
a�I.,J�� •.y. ♦f. ''.ly..•V�.:i.rµf:T.
_.t • .4', :f � �<I.... i c! ^.5� '
r��ir�i��rr�rr�i�rrr '�' `'.
'��\`\\�\\/\\ i ' ''� •� �:�;
/i�/i� i�/i�/i�/i /i /�\ � .'.'. , �:;:r•��,.
..,.,7�.
.• �i�'<.'...i;.:
TREATED ��.:.'.'... +,i::.....
SUBGRADE /\;'�`'' `''', ', ' "`. «
• . i t t!..�f.�i
��.'.���.�.•«'.;':� `i:`;
ACCEPTABLE BACKFILL �� •i'.`.'� `';" ;:�"'
OR AS REQUIREO BY %�i�« f ;�=
DRAYJINGS PER SECTION ��'.'.'»'{•.`.;�«�;:.i;%
33 05 10 \\:��`�
� ' j,rF"`'%:'.
MANHOLE OR / ' ' . �'�R �;"•'i
VAULT PER ��+����'•; �:•".':.
DRAWINGS �\�.�•±.;.' ;;":� ;
\\�.��y.�• y•+r,•
�i * , :.ti}n.�
�\.�.�.�. siT;�.
��'�.�.� I'`�::'.
��'. .;`t':'
��•. .
1 l-/-1 I V Y I L Y Y
VPER 32 13v13—D511
F.'�
:�:d• '
BAR SPACING, PAVEMENT
FRAME AND COVER AS THICI(NESS, SLAB SPACING,
INDICATED iN THE ORAWINGS ETC. SHALL BE PER
DRAWINGS
�— GROUT FACE —
12" MAX. SMOOTH (TYP.)
2 ROWS
VARIES PER RAM—NEK OR
SUBGRADE EQUIVALENT
TREATMENT (TYP.)
REQUIREMENTS,
SEE NOTE 4
� GROUT FACE
SMOOTH (T1P.)
(4) #4 BARS DRIILED INTO
MANHOLE CONE 3" MIN.
BOTH OIRECTIONS
SECTION VIEW
"]�;�3•, MIN. (T1P.); - •,,�i`.
r~f� :��• �,:f".S• :N'•'
�, '. i.�i.a.�'�� �'�.�..' �i•+:•;
,.�N'. i�~�s��-a.is�>f
�;. ; .' �.`.`. '« .'.°, . . . . « . .
�:�., •,�,•;•,•i�`����:������:
�����'«'•'.'.�.,,//.//. /. i
.,�.' 8" MIN. �`��
•'-`.- (TYP.) �✓� NOTES:
'�y j; y,.,*,�, �,+�� 1. THIS DE
�,'..i:.'.',',','.a \/ 7oHE DR
':::Z 'a
.,:,- ,, ,+;�� COMBIN
t;'= �. y.'.'« . {f �j PROPOS
;i'.•�?: ' ' ' ' VAULT I
'''�� ' ' ' ' � / LOCATIO
a.':��:; ;'�'�'{'+;�% 2. ALL ME
!.r;'�,';:.'.'.'.'. � / TYPICAL
''�\ MANHOI.
�''"',f�.' .'«'. .'. \ ASSEMB
�•,:.�,,, ���,i�. �` 3. IF GRAD
�:�;%'✓.,�.�.�.�`�� THAN 2'
"$�;'' ��'«'i� NOT EX
�' '�.;: a• '''�'�\ NEIGNT.
'::i"'•: ��'�'��!\ TOTAI
". �.; ` ; � • BE AL�
i`':;* ''.'`*�, \/ 4. CONE M
�'S'�' '••.'y TERMIN
FO�T WORTH CITY OF FORT WORTH, TEXAS
��MANHOLE LID ASSEMBLY - PROPOSED
CONCRETE PAVEMENT (CONE)
TAIL TO BE USED
HERE SPECIFIED ON
AWINGS IN
ATION WITH
ED MANHOLE OR
N THE SAME
N.
ASUREMENTS ARE
FOR ALL SIDES OF
E/VAULT LID
LY.
E RINGS ARE USED
HALL BE NO LESS
' THICK, AND SHALL
CEED 12" IN TOTAL
NO MORE THAN 3
GRADE RINGS. SHALL
OWED.
ANHOLES SHA�I
ATE AT SUFFICIENT
DEPTH TO ALIOW FOR
MIXING AND COMPACTION AS
NECESSARY FOR ROAD
CONSTRUCTION. RISER
SECTION SHALI BE
CAST—IN—PIACE PER
SEC710N 33 39 10.
5. CONCRETE PAVWG SNAI� BE
PAID AS A SEPARATE ITEM.
� REVISED:08-31-2012
33 05 13-D014
2" MIN. SEPARATION
DISTANCE (TYP.) \
�- 6" MIN.
`//.//, //�\\//, //, %\%�\l'
1' MIN. ACCEPTABLE /\/ :'
,/ BACKFILL OR 6" MINA j //•;.
\/ REQUIRED BY DRAWINGCSS OR CLSM AS S �:•.
PER SECTION 33 05 10 \ \
/ f/% ff/f% f L /
x/ + + +
4- +
\\ \\ \/\\/ \ \\/\\s'
\ //+ + ++ +
/fey �++ +++ +
G\�/+++++ 30.
/,\/AAAA/�/'++++++ .;
(4) #4 BARS DRILLED N/>++1. + +
INTO MANHOLE CONE 3" �� +++++++
MIN. BOTH DIRECTIONS, \/ F +
SEE NOTE 6
F24oIH
CONCRETE
COLLAR
12" MAX.
}
NOTES:
1. THIS DETAIL TO BE USED ONLY WHERE
SPECIFIED ON THE DRAWINGS IN
COMBINATION WITH PROPOSED
MANHOLE OR VAULT IN THE SAME
LOCATION.
2. ONLY FLAT TOP MANHOLES SHALL BE
ALLOWED FOR UNIMPROVED SURFACES.
CONE MANHOLES WILL NOT BE
ALLOWED.
3. IF GRADE RINGS ARE USED THEY
SHALL BE NO LESS THAN 2" THICK,
AND SHALL NOT EXCEED 12" IN TOTAL
HEIGHT. NO MORE THAN 3 TOTAL
GRADE RINGS. SHALL BE ALLOWED.
4. ALL MEASUREMENTS ARE TYPICAL FOR
ALL SIDES OF MANHOLE/VAULT LID
ASSEMBLY.
5. MANHOLE FLAT TOP SHALL EXTEND 6"
MIN. ABOVE HIGHEST ADJACENT
UNIMPROVED SURFACE WHEN RAISED
MANHOLE IS INDICATED IN THE
DRAWINGS.
6. PROVIDE REINFORCEMENT TYING
COLLAR TO MANHOLE.
7. WHERE POSSIBLE, RING AND FRAME
MAY BE INTEGRALLY CAST INTO FLAT
TOP, PROVIDED ALL OTHER SPACING
REQUIREMENTS ARE MET.
8. WHEN USED, CONCRETE COLLARS
SHALL BE POURED TO EXTENTS OF
CONCRETE FLAT TOP.
9. MANHOLE SHALL BE RAISED OR FLUSH
AS INDICATED ON THE DRAWINGS.
EXISTING
UNIMPROVED
SURFACE
FRAME AND COVER
AS INDICATED IN
THE DRAWINGS
GROUT FACE
SMOOTH (TYP.)
2 ROWS RAM-NEK OR
EQUIVALENT (TYP.)
MANHOLE OR
VAULT PER
DRAWINGS
(4) #4 BARS
DRILLED INTO
MANHOLE CONE
3" MIN. BOTH
DIRECTIONS, SEE
NOTE 6
RAISED SECTION VIEW
CONCRETE
COLLAR
FRAME AND COVER AS
INDICATED IN THE DRAWINGS
2 ROWS RAM-NEK OR - ;-
EQUIVALENT (TYP.)
FLUSH SECTION VIEW
3/4" CHAMFER
(TYP.)
TOP -SOIL
6"
MIN.
;;./ /off%/f%\ff%\ff%ff%
+ + + j\
+ + +
+ + +//
+ + +
+ + +
TOP -SOIL
MIN.
++++++>
+\
CITY OF FORT WORTH, TEXAS
MANHOLE LID ASSEMBLY -
UNIMPROVED SURFACE (FLAT TOP)
MIN. ACCEPTABLE
BACKFILL OR 6" MIN CSS
OR CLSM AS REQUIRED
BY DRAWINGS PER
SECTION 33 05 10
REVISED: 08-31-2012
33 05 13-D015
ITIORTHOR
6" MIN. AND
12" MAX.
INITIAL BACKFILL
UTILITY SAND PER
SECTION 33 05 10
6" MIN. AND \
12" MAX.
BEDDING r
BACKFILL
TRENCH GEOTEXTILE
FABRIC
CRUSHED ROCK PER
SECTION 33 05 10
illy rill" I�iii�l
6" MIN. TRENCH
% WALL CLEARANCE
(TYP.)
NO GROUND GROUND WATER
WATER PRESENT PRESENT
CITY OF FORT WORTH, TEXAS
EMBEDMENT FOR WATER LINES
12-INCH AND SMALLER
REVISED: 08-31-2012
33 05 10-D101
FORT WORTH
1" MIN.
1" MIN.
BACKFILL AND
SURFACE REPAIR TO
MATCH WATER MAIN
l iUTILITY SAND PER
SECTION 33 05 10
-I I IIIIi1IIIIIIIIIlI11�.l1I1111
CITY OF FORT WORTH, TEXAS
DATE: 08-31-2012
EMBEDMENT FOR WATER SERVICES
33 05 10-D104
PROPERTY LINE
PLASTIC OR CONCRETE
METER BOX PER 33
12 10—D113/0116
20"
SIDEWALK
• - '.-:••••• • .:4:411411L-Lliffiilif \
F.Z,11:4:11-,411,2,44=Liii:FiLl1=4=IiIgfiL117g1111
1THi
SEAL BRASS NIPPLE
WITH CAP OR PLUG
=Id
TAPPING SADDLE
SADDLE
(ONLY DUCTILE IRON MAY
BE TAPPED DIRECTLY)
WATER MAIN BEHIND CURB
NOTE:
1. PLASTIC METER BOXES SHALL BE
USED IN NON —PAVED AREAS.
2. CONCRETE METER BOXES SHALL
BE USED IN PAVED AREAS.
3. METER SHALL NOT BE PARTIALLY
PLACED IN DRIVEWAYS OR
SIDEWALKS.
4. USE PURPLE METER BOX LIDS
FOR RECLAIMED WATER METERS.
WATER
METER
1=111=11 f= i=k1= ii=11 I=I 1=111=111=n
=11i=!1=LIE111E1111..±:111E111E111E111E111—
El I 1E I IL111.111:311E111_111=111-Z
2' MIN. RADIUS, OR USE A 90'
MALE THREAD BY FLARE
BRASS FITTING IF NECESSARY
s"
STANDARD CURB
STOP WITH FLARE
CONNECTION
2MIN.
BLUE VINYL
TAPE, 3" WIDE,
6" ABOVE GROUND
CURB
Fri-4-114,',
: 1:L.-.1 I El •- • • ,
F_=_•=1 i 1 , lal--i •:•2 " ',. •
1=1I1=1
,1 1 I--,1 1 1.7•;• •... ••,•••,,,,.
• ------ ...LI., --,:..,FrE,......••••:. • •••,_ •
.7.-ef 1 1L-71 IE
1=111=1
1/
//
//
77
77
FORT WORTH
STANDARD CORPORATION
STOP WITH CC THREAD
BY FLARE CONNECTION
z
1" TYPE K COPPER
SERVICE LINE
PAVEMENT
SERVICE LINE FOR
WATER MAIN ON
OPPOSITE SIDE
TAPPING SADDLE (ONLY
DUC11LE IRON MAY BE
TAPPED DIRECTLY)
STANDARD CORPORATION
STOP WITH CC THREAD
BY FLARE CONNECTION
WATER MAIN IN STREET
CITY OF FORT WORTH, TEXAS REVISED: 08-31-2012
1-INCH WATER SERVICE
331210-D111
SIDEWALK
PLASTIC OR CONCRETE
METER BOX PER 33
12 10-D114/D117
SEAL BRASS NIPPLE
WITH CAP OR PLUG
TAPPING SADDLE (ONLY
DUCTILE IRON MAY BE
TAPPED DIRECTLY)
WATER MAIN BEHIND CURB
NOTE:
1. PLASTIC METER BOXES SHALL BE
USED IN NON -PAVED AREAS.
2. CONCRETE METER BOXES SHALL
BE USED IN PAVED AREAS.
3. METER SHALL NOT BE PARTIALLY
PLACED IN DRIVEWAYS OR
SIDEWALKS.
4. USE PURPLE METER BOX LIDS
FOR RECLAIMED WATER METERS.
20"
I 9
ANGLE STOP WITH
FLARE CONNECTION
17"
/
/
/
/
/
/
/
11"
[2' MIN. r CURB
BLUE VINYL TAPE, 3"
WIDE, 6" ABOVE GROUND
II-1i1-1i
HELEH
IEETFEk
1.5" OR 2" TYPE K
COPPER SERVICE LINE
\\- STANDARD CORPORATION
STOP WITH CC THREAD
BY FLARE CONNECTION
FORT WORTH
ti
PAVEMENT-\
\\\\\\\\\\\\\\\\\\\\\\\\\\\\\
SERVICE LINE FOR
WATER MAIN ON
OPPOSITE SIDE
TAPPING SADDLE (ONLY -
DUCTILE IRON MAY BE
TAPPED DIRECTLY)
STANDARD CORPORATION
STOP WITH CC THREAD
BY FLARE CONNECTION
WATER MAIN IN STREET
CITY OF FORT WORTH, TEXAS
1%2 & 2-INCH WATER SERVICE
REVISED: 08-31-2012
33 12 10-D112
SNAP LOCK J
POCKET, SEE
NOTE #4
METER BOX LID
. WORK AREA
N
i
3/8" WALL
\I
17 7/8"
19-1/8" I.D. WORK AREA
21"
METER BOX
NOTE:
1. USE THIS METER BOX IN NON —PAVED AREAS ONLY.
2. DIMENSIONS ± 1/8" U.N.O.
3. WALL THICKNESS: 3/8"
4. SNAP LOCK POCKET WILL RECEIVE AMR/AMI DEVICE
ENDPOINT. SNAP LOCK SLOT IS 1.80" ± .015" TO
ALLOW FOR A FINGER FORCE INSTALL. POCKET
HEIGHT IS 15/16" FOR MIN 1/8" AIR GAP.
PICK HOLE POCKET
3" x 9/16"x THRU HOLE
WITH 3/160 304SS ROD
N
11"
pepepepepeeouoeoeoeo
=0-1-0-0-0 METER 0=00a
1-0-0=4——o=D e=o==0=0
=0=0=1
�pT�ToTo04T�oo
o=o=D�D�D=
iTUTUT4TUT T4
1•000000
1T T Tpe a oo a o pep"
'�o�____—ooeaeeepep J
F
\I
14 3/4"
rTh
I/
FORT WORTH CITY OF FORT WORTH, TEXAS
1—INCH STANDARD PLASTIC METER BOX
(3/4 & 1-INCH METERS)
REVISED: 08-31-2012
331210-D113
Co
to
6-5/16" I.D. WORK AREA —
3/8" WALL
34-1/8"
NOTE:
1. USE THIS METER BOX IN NON —PAVED AREAS
ONLY.
2. DIMENSIONS ± 1/8" U.N.O.
3. WALL THICKNESS: 3/8"
4. SNAP LOCK POCKET WILL RECEIVE AMR /AMI
DEVICE ENDPOINT. SNAP LOCK SLOT IS 1.80" ±
.015" TO ALLOW FOR A FINGER FORCE INSTALL.
POCKET HEIGHT IS 15/16" FOR MIN 1/8" AIR
GAP.
SNAP LOCK
POCKET, SEE
NOTE #4
0-0-0-0-0-0—o
—o—o—o—o-0-0
0 0-0-0-0-0-0
00-0-0
0-0-0— —0-0-0-0-0
—0-0-0 00 0-0
0-0-0-0-0-0-0-0-0
—0-0-0-0 —0-0-0-
0-0-0-0-0-0-0-0-0
—0-0-0— 0-0-0-
0-0-0-0 00 0
-ncc-0-0--070701E-
miTiTIT-TITA2m°
-rn-
JLTITiTi-iTiTI330.1
0—o-0-0 0 0— —o-0
—0-0 0 —0 0-
0-0-0-0-0-0-0-0-0
—0-0-0— 0-0-0-
0-0'=0 • • O`A=0
•=0=0=' CITY OF n_n_fl ,FORT WORTH fl_n_n
LO-LO 00 1'1'0 ''1'0A
0-0-0-0 pit 0-0-4--K"--- 0
TIII°1171 0 °VT°
17 3/4"
METER BOX LID
METER BOX
1/2" BOW
21-1/4"
\
17 1 /2"
18-1/2"
CITY OF FORT WORTH, TEXAS
FORTWORTH 2-INCH STANDARD PLASTIC METER BOX
(1-Y2 & 2-INCH METERS)
0
1/2" REBAR (2)
PICK HOLE POCKET
3" x 9/16"x THRU HOLE
WITH 3/160 304SS ROD
REVISED: 08-31-2012
33 12 10-D114
1/2" REBAR (2)
SNAP LOCK J 1-3/4"
POCKET, SEE
NOTE #2
18"
16 3/4"
8" --
22-3/4"
IL H/I
N
�-- 20" I.D. WORK AREA ---1
21-1/2"
METER BOX LID
PICK HOLE POCKET
3" x 9/16"x THRU HOLE
WITH 3/160 304SS ROD
-pTBTo-•- -0Tp=
0-8-1 00-0 T°1
D�D�D=D 0=0=0=0
pope a -0- TO�
DAD CITY OF DST
g D p FORTwORTH p'p
o°o—a°0T-TT—o°o
aaaaT�T000
wopoDopopopom=
oQopToD000aoomo
0-0-8 00-0-0-0
oDDODOD0-0DOD0-
47171717-71710
11'
7j=0e0-1=1=4aeoavevae,,=41
18�O 'OiD»DMETERT00p0•
METER BOX
NOTE:
1. USE THIS METER BOX IN PAVED AREAS ONLY.
2. SNAP LOCK POCKET WILL RECEIVE AMR/AMI DEVICE ENDPOINT.
SNAP LOCK SLOT IS 1.80" ± .015" TO ALLOW FOR A FINGER
FORCE INSTALL. POCKET HEIGHT IS 15/16 FOR MIN 1/8" AIR
GAP.
°0T0T0T0T0-0 0-
° 0-0 - 0 0 0-0-0-
p=pepe0-0-0-0-
I-0-0-pepopaa aaoaa-0-0-
0a0a0Q000001:131dnnoo0o09,
15-1/4"
1
13 1/2"
12" I.D. WORK AREA
FORT WORTH CITY OF FORT WORTH, TEXAS REVISED: 08-31-2012
1-INCH STANDARD CONCRETE METER BOX
(3�4 & 1-INCH METERS) 33 12 10-D116
SNAP LOCK
POCKET, SEE
NOTE #2
0-0" =0=0=0—o
0� DOU00 17°T00
00000000 0 0''0 —0
-00 0000 00000
0°0°0°0°0°0°0°0°0
Ou30-0 0 °T "'0 0-0 0
Q�0TOT0� OTO"mom
0.000o0o0-000000
i000000000 0000000
0-0 0-0— _ 0-0-0
00000o CHY OF 0-0-0
—T0 jj0ToT0
0 U 0 0 0 FORT WORTHI 00
010�0�0 0-0-
0-0-0-0
0000000000000p°�
26 7/8"
25 3/4"
32 1/2"
o�'�� o-o-o o-o-
000°" T°T°T°T°T°o
o—o— 0-0-0-0-0-0
o—o O—o—o—o—o
o—o— O—o o—o—o—o
0000 0000 00-00000
-cc— 0 0� ' 0-0—
W0000-00 OOOOOmO
O1 0 0 0 0-0'0—i0
0Q00±o00000g0 3 0
0000000000000-000
0000 jj0000000 000
O 0 O O�IFORT WORTH O O O
OOOOo0.007000
000 00 000000
�— 17 3/4"
28" I.D. WORK AREA
31"
NOTE:
1. USE THIS METER BOX IN PAVED AREAS ONLY.
2. SNAP LOCK POCKET WILL RECEIVE AMR/AMI
DEVICE ENDPOINT. SNAP LOCK SLOT IS 1.80"
± .015" TO ALLOW FOR A FINGER FORCE
INSTALL. POCKET HEIGHT IS 15/16 FOR MIN
1/8" AIR GAP.
F2IORTH
METER BOX LID
1 '
METER BOX
•
1 = -0
PICK HOLE POCKET
3" x 9/16"x THRU HOLE
WITH 3/160 304SS ROD
20 1/2"
11
17" I.D. WORK AREA
20"
CITY OF FORT WORTH, TEXAS
2—INCH STANDARD CONCRETE
METER BOX (1-%2 & 2-INCH METERS)
REVISED: 08-31-2012
33 12 10—D117
MJ CONNECTION WITH ANCHOR TEE
OR ANCHOR COUPLING FOR DUCTILE
IRON OR PVC PIPE WATER MAIN
6" FIRE HYDRANT%'"•:`...;<r
LEAD LINE (PVC
OR DIP)////
RETAINER
GLAND
WATER MAIN
HORIZONTAL BLOCKING
PER 33 11 00-D130
BACKFILL SAME AS
WATER MAIN PER
SECTION 33 05 10
PAVEMENT OR
OTHER SURFACE
HORIZONTAL -' Q '''c
THRUST \'
BLOCKING PER :
33 11 00-D130
•
WATER MAIN
MJ ANCHOR TEE OR
MJ ANCHOR COUPLING
6" MJ GATE VALVE
PER 33 12 20-D126
NOTE:
1. DO NOT LOCATE FIRE HYDRANT IN SIDEWALK.
2. PROVIDE FOUR (4) FOOT CLEARANCE AROUND FIRE
HYDRANT.
3. EXTENSION SECTIONS MAY BE USED AS REQUIRED
AND INSTALLED AS PER MANUFACTURER'S
INSTRUCTIONS.
4. FOR CONCRETE PRESSURE PIPE OR BURIED STEEL
PIPE, PROVIDE AN ISOLATION KIT AND WAX
PETROLATUM TAPE COATING PER SECTION 33 04 10
AND FLxMJ GATE VALVE.
FORT WORD
�r STANDARD FIRE HYDRANT (STRAIGHT)
PAVEMENT OR
OTHER SURFACE
PLAN VIEW
EXISTING OR -\
PROPOSED CURB
EXISTING OR SIDEWALK
PROPOSED
CURB
BOTTOM
REST
HORIZONTAL
THRUST
FIRE BLOCKING PER
HYDRANT 33 11 00-D130
2'-6" FROM BACK
OF CURB (MAX. 9')
,./-
-18" MIN.
/La� t,, I :•::•::. : .
2" MIN.
r 6" MAX.
cr�y.-r:k sue; i�"+•`"rf.=i
6" FIRE HYDRANT LEAD
LINE (PVC OR DIP)
SAND EMBEDMENT PER
SECTION 33 05 10
RETAINER
GLAND
ELEVATION VIEW
SET FIRE
HYDRANT
PLUMB
BREAKER RING
W/BREAKER STEM
_ 3'-6" MIN.
7'-0" MAX.
%<
MINIMUM 0.3 C.Y. CRUSHED
ROCK PROPORTIONALLY
AROUND BASE. DO NOT
COVER WEEP HOLE.
HORIZONTAL BLOCKING
PER 33 11 00-D130
CONCRETE REST
12"x12"x6"
RETAINER
GLAND
CITY OF FORT WORTH, TEXAS
REVISED: 08-31-2012
33 12 40-D120
HORIZONTAL BLOCKING
PER 33 11 00—D130
RETAINER GLAND
FIRE HYDRANT
ANCHOR TEE
RETAINER GLAND
EXISTING OR
PROPOSED CURB
MJ CONNECTION WITH
FIRE HYDRANT TEE FOR
DUCTILE IRON OR PVC
PIPE WATER MAIN
\L 6—INCH GATE VALVE
ANCHOR BY MJ PER
33 12 20—D126
3' (MIN)
BOTTOM REST
HORIZONTAL BLOCKING
PER 33 11 00—D130
FIRE HYDRANT
PAVEMENT —7 PLAN VIEW
BACKFILL SAME AS
WATER MAIN PER
SECTION 33 05 10
SAND EMBEDMENT PER
SECTION 33 05 10
FIRE HYDRANT
ANCHOR TEE
6" MJ GATE VALVE
PER 33 12 20-0126
NOTE:
1. DO NOT LOCATE FIRE HYDRANT IN
SIDEWALK.
2. PROVIDE FOUR (4) FOOT CLEARANCE
AROUND FIRE HYDRANT.
3. EXTENSION SECTIONS MAY BE USED AS
REQUIRED AND INSTALLED AS PER
MANUFACTURER'S INSTRUCTIONS.
4. USE THIS DETAIL FOR 12" AND SMALLER
MAINS ONLY.
FORT WORTH
SET FIRE
HYDRANT
PLUMB
BREAKER RING
W/BREAKER STEM
3'-6" MIN.
7'-0" MAX.
vn
CONCRETE REST
12"x12"x6"
RETAINER GLAND
6" FIRE HYDRANT LEAD
LINE (PVC OR DIP)
RETAINER GLAND
ELEVATION VIEW
CITY OF FORT WORTH, TEXAS
STANDARD FIRE HYDRANT (ELL)
MINIMUM 0.3 C.Y. CRUSHED
ROCK PROPORTIONALLY
AROUND BASE. DO NOT
COVER WEEP HOLE.
HORIZONTAL BLOCKING
PER 33 11 00—D130
REVISED: 08-31-2012
33 12 40-D121
BLOCKING SHALL
BE AGAINST \\
UNDISTURBED /-
EARTH
HORIZONTAL
BLOCKING PER
33 11 00-D130
\\
POLYETHYLENE
ENCASEMENT PER
SECTION 33 11 11
BLOCKING SHALL
BE AGAINST \
UNDISTURBED
EARTH
i/
HORIZONTAL-�
BLOCKING PER >'.A
33 11 00-D130
REMOVE
j// EXISTING PIPE
AS NECESSARY
/// //:///Y/A//
11 y. - ""'- 71 '
THY/��i5 >/_/>.
EXIS ING
FLANGED END
BLIND FLANGE WITH
PETROLATUM TAPE
CPP. STEEL PIPE AND
DIP FLANGED END
PRESSURE PLUG
NOTES:
1. ALL ABANDONMENT SHALL BE PER SECTION 02 41 14.
2. SURFACE REPAIR SHALL BE PER SECTIONS 32 01 17,
32 01 29 OR 32 14 16 DEPENDING ON EXISTING
SURFACE AND AS DESIGNATED ON THE PLANS.
3. CAST -IN -PLACE CONCRETE SHALL BE PER SECTION
03 30 00.
4. ALLOW CONCRETE BLOCKING TO CURE FOR 24 HOURS
PRIOR TO PRESSURIZING WATER LINE.
:...... ° • L /,\//%//,v4<, /,//
RETAINER GLAND
DUCTILE IRON MJ CAP
PVC AND DUCTILE
IRON PLAIN END
PRESSURE PLUG
BLOCKING SHALL
BE AGAINST
UNDISTURBED \
EARTH
FIELD CUT AND REMOVE
EXISTING PIPE AS
NECESSARY PER SECTIONS
33 11 11 OR 33 11 12
/ ,.p\\/\ FIELD CUT AND REMOVE
>\' ' \/\/�\ / EXISTING PIPE AS
/�'"''�/�//j/////< NECESSARY PER SECTIONS
HORIZONTAL -�./",
BLOCKING PER
33 11 00-D130
BUMPED
HEAD
WELDED BUTT STRAP, BUTT
WELD, JOINT HARNESS OR
EQUIVALENT PER SECTION
33 11 13 OR 33 11 14
CPP AND STEEL
PLUG PLAIN END
PRESSURE PLUG
FORT WORTH PVC, DUCTILE IRON, CONCRETE PRESSURE
AND BURIED STEEL PIPE PRESSURE PLUGS
CITY OF FORT WORTH, TEXAS
REVISED: 08-31-2012
02 41 14-D123
2' 0" I
CONCRETE COLLAR
(ASPHALT)
2'-0"
%" CHAMFER
(TYP.)
2' 0"
CONCRETE COLLAR
(UNIMPROVED SURFACES)
PAVED AREAS
CONCRETE COLLAR
8" TYP.
AWWA THREE-PIECE
VALVE BOX OR
APPROVED EQUAL
P
Ye"x45' CHAMFER
2" SQUARE STOCK
W/ 1" DIA. HOLE
DRILLED THROUGH
1 "0 SOLID
ROUND STOCK
2" SQUARE STOCK
W/ 1" DIA. HOLE
DRILLED THROUGH
2Y2" SQUARE
TUBING W/ Y4"
THICK WALL
8-#4
BARS
(TYP.)
8-#4
BARS
(TYP.)
3" CHAMFER (TYP.)
FOR UNIMPROVED
SURFACES ONLY
CONCRETE COLLAR
(RECLAIMED WATER - ALI. I °CATIONS).
UNPAVED AREAS
GATE VALVE
3/4" CHAMFER (TYP.)
3" MIN.
IF VALVE OPERATING NUT IS
MORE THAN 3' BELOW
PAVEMENT SURFACE, PROVIDE
EXTENSION STEM TO 1' BELOW
PAVEMENT SURFACE.
8
USE RETAINER GLANDS
FOR VALVE RESTRAINT
2" ±o
VARIES
2"444
r -o
II'
VALVE STEM EXTENSION
- 4"-0
NOTE:
1. GATE VALVES SHALL BE
RESILIENT SEATED.
2. PROVIDE 3" MIN. OF COVER
OVER REINFORCEMENT IN
ALL DIRECTIONS.
3. COLLARS SHALL BE 4,000
PSI CONCRETE PER SECTION
03 30 00.
NOTE:
1. 1" ROUND SOLID BAR & 2" SQUARE
PER ASTM A-108-81. SAE 1020,
COLD DRAWN OR BETTER.
2. 2-YZ" SQUARE TUBING PER ASTM
A-512-79, SAE 1020, COLD DRAWN
OR BETTER.
3. ALL WELDS SHALL COMPLY WITH A.W.S.
CODE FOR PROCEDURE, APPEARANCE
AND QUALITY OF WELDS.
!24oRTH CITY OF FORT WORTH, TEXAS REVISED: 08-31-2012
WATER DISTRIBUTION GATE VALVE & BOX
(12" AND SMALLER) 33 12 20-D126
NOTE:
ONLY C-303 PIPE OR
STEEL MAY BE CONNECTED
AT MID -JOINT
FLANGE CONNECTION,
PROVIDE ISOLATION KIT AND
PETROLATUM TAPE COATING
PER SECTION 33 04 10
TO EXISTING PLAIN END CPP PTPE OR
BURIED STEEL PIPE
-r -----
(____
EXISTING BELLxPE
CONCRETE PRESSURE
PIPE OR BURIED STEEL
PIPE SPOOL PIECE
BELLxFL STEEL
SPOOL PIECE
EXISTING CPP
OR BURIED
STEEL PIPE
LENGTHS AS
DESIGNATED
ON DRAWINGS
1
1
1
1
1
MJ SOLID SLEEVE
LRESTRAINED WITH
RETAINER GLANDS
— FLxPE DUCTILE
IRON SPOOL PIECE
PROPOSED
- DUCTILE
IRON PIPE
CON BELL OF CCPPECTING TIOR BURIEDIPcS TO EEL PIPETING
FLANGE CONNECTION,
PROVIDE ISOLATION KIT AND
PETROLATUM TAPE COATING
PER SECTION 33 04 10
PExFL STEEL SPOOL
PIECE TO MATCH OD OF
EXISTING PIPE BELL
X
(-)
EXISTING CONCRETE -
PRESSURE PIPE OR
BURIED STEEL PIPE
FLxPE DUCTILE
IRON SPOOL PIECE
EXISTING CPP
OR gURIED
STEEL PPE
PROPOSED -\
DUCTILE
IRON PIPE
LENGTHS AS DESIGNATED
ON DRAWINGS
1
I
1
I
PROPOSED
- DUCTILE
IRON PIPE
MJ SOLID SLEEVE
RESTRAINED WITH
RETAINER GLANDS
PROPOSED
DUCTILE
IRON PIPE
FORT WORTH
CONNECTION TO EXISTING WATER MAINS 33 12 25-D129
NOTE:
THIS DETAIL MAY BE USED IN
REVERSE WHEN CONNECTING
PROPOSED CPP TO EXISTING
BURIED STEEL PIPE
PROVIDE BELLxFL OR
SPIGOTxFL CONCRETE
PRESSURE PIPE AS
INDICATED ON PLANS
n
r/
EXISTING CONCRETE
PRESSURE PIPE
PROVIDE FLANGE ISOLATION
KITS WHEN CALLED FOR ON
THE DRAWINGS
CONNECTING BURIED STEEL PIPE TO
EXISTING CONCRETE PPFSURE PIPE
EXISTING
CONCRETE
PRESSURE PIPE
PROPOSED
BURIED
STEEL PIPE
PINN 0' X STING DUCTILE RI IRONED PIPE
LENGTH AS DESIGNATED
ON DRAWINGS
MJ SOLID SLEEVE
RESTRAINED WITH
RETAINER GLANDS
1
I
EXISTING
DUCTILE
IRON PIPE
FLxPE DUCTILE
IRON SPOOL PIECE
EXISTING
DUCTILE
IRON PIPE
LENGTHS AS DESIGNATED
ON DRAWINGS
CONNECT SPOOL PIECE
TO STEEL PIPE WITH
WELDED BUTT STRAP
PER SECTION 33 11 14
PExFL STEEL
PROPOSED
SPOOL PIECE BURIED
STEEL PIPE
FLANGED CONNECTION
WRAPPED IN
PETROLATUM TAPE O
FLANGE CONNEC1ON,
PROVIDE ISOLATION KIT AND
PETROLATUM TAPE COATING
PER SECTION 33 04 10
PROPOSED CONCRETE J
PRESSURE PIPE OR
BURIED STEEL PIPE
PROPOSED CPP
- OR BURIED
STEEL PIPE
CITY OF FORT WORTH, TEXAS
REVISED: 08-31-2012
I.,
RESTRAINED
PLUG OR CAP
X
BLOCKING SHALL
EXTEND TO
UNDISTURBED EARTH
F24OIH
L• • •
ALL DUCTILE IRON FITTINGS
SHALL BE WRAPPED IN
POLYETHYLENE PER
SECTION 33 11 11
TEE
PLAN VIEW
BLOCKING SHALL EXTEND
TO UNDISTURBED EARTH
-IOR ZONTAL THRUST BLOCKING TABLE
PLUGS,
TEES, 90' BENDS 45' BENDS 22.5' BENDS 11.25' BENDS
PIPE "X" DEAD -ENDS
SIZE DIM.** MIN. AREA MIN. AREA MIN. AREA MIN. AREA MIN. AREA
(SF) (SF) (SF) (SF) (SF)
6" 1'-6" 4.00* 4.50 4,00* 4.00* 4.00*
8" 1'-6" 5.65 8.00 4.33 4.00* 4.00*
10" 1'-6" 8.84 12.50 6.76 4.00* 4.00*
12" 1'-6" 12.72 17.99 9.74 4.96 4.00*
16" 2'-O" 22.62 31.99 17.31 8.83 4.43
20" 2'-0" 35.34 49.98 27.05 13.79 6.93
24" 2-0" 50.89 71.97 38.95 19.86 9.98
*MINIMUM THRUST BLOCKING SURFACE AREA SHALL BE 4 SQUARE FEET.
**DIMENSION "X" TO BE A MINIMUM OF ONE FOOT AND SIX INCHES, BUT IS
TO BE INCREASED WHERE NECESSARY TO PROVIDE BEARING AGAINST
UNDISTURBED TRENCH WALL.
NOTES:
1. THRUST BLOCKING AREAS SHOWN ARE BASED ON:
1.1. 225 PSI TEST PRESSURE
1.2. 3,000 PSF HORIZONTAL OR LATERAL BEARING PRESSURE FOR ACCEPTABLE
SOILS
1.3. MINIMUM COVER OF 42"
1.4. A SAFETY FACTOR OF 1.5.
2. THE ENGINEER SHALL PROVIDE A SEPARATE BLOCKING TABLE WHEN THE CONDITIONS
DO NOT MEET THE ABOVE ASSUMPTIONS.
3. THE CONTRACTOR IS REQUIRED TO PROVIDE THRUST RESTRAINT BY MEANS OF
THRUST BLOCKING FOR ALL PIPES. THIS ITEM SHALL BE CONSIDERED SUBSIDIARY TO
THE VARIOUS ITEMS BID.
4. ALL MJ FITTINGS SHALL BE ADDITIONALLY RESTRAINED WITH RETAINER GLANDS.
5. BLOCKING FOR WATER LINES LARGER THAN 24" SHALL BE DESIGNED FOR THE
SPECIFIC LOCATION AND SHOWN ON THE DRAWINGS.
6. ALL DUCTILE IRON FITTINGS SHALL BE WRAPPED IN POLYETHYLENE ENCASEMENT
PRIOR TO PLACING OF BLOCKING.
CITY OF FORT WORTH, TEXAS REVISED: 08-31-2012
HORIZONTAL THRUST BLOCKING
33 11 00-D130
FORT WORTH
CONCRETE CRADLE d �I `\%
SHALL EXTEND TO
UNDISTURBED EARTH
PROFILE VIEW
CONCRETE CRADLE TABLE
PIPE "X"
SIZE DIM.**
90' BENDS 45' BENDS 22.5' BENDS 11.25' BENDS
MIN. AREA MIN. AREA MIN. AREA MIN. AREA
(SF) (SF) (SF) (SF)
6" 1'-6" 4.50 4.00* 4.00* 4.00*
8" 1'-6" 8.00 4.33 4.00* 4.00*
10" 1'-6" 12.50 6.76 4.00* 4.00*
12" 1'-6" 17.99 9.74 4.96 4.00*
16" 2'-0" 31.99 17.31 8.83 4.43
20" 2'-0" 49.98 27.05 13.79 6.93
24" 2'-0" 71.97 38.95 19.86 9.98
*MINIMUM THRUST BLOCKING SURFACE AREA SHALL BE 4 SQUARE FEET.
**DIMENSION "X" TO BE A MINIMUM OF ONE FOOT AND SIX INCHES, BUT
IS TO BE INCREASED WHERE NECESSARY TO PROVIDE BEARING AGAINST
UNDISTURBED TRENCH BOTTOM.
NOTES:
1. THRUST BLOCKING AREAS SHOWN ARE BASED ON:
1.1. 225 PSI TEST PRESSURE
1.2. 3,000 PSF HORIZONTAL OR LATERAL BEARING PRESSURE FOR ACCEPTABLE SOILS
1.3. MINIMUM COVER OF 42"
1.4. A SAFETY FACTOR OF 1.5.
2. THE ENGINEER SHALL PROVIDE A SEPARATE BLOCKING TABLE WHEN THE CONDITIONS DO NOT
MEET THE ABOVE ASSUMPTIONS.
3. THE CONTRACTOR IS REQUIRED TO PROVIDE THRUST RESTRAINT BY MEANS OF THRUST
BLOCKING FOR ALL PIPES. THIS ITEM SHALL BE CONSIDERED SUBSIDIARY TO THE VARIOUS
ITEMS BID.
4. ALL MJ FITTINGS SHALL BE ADDITIONALLY RESTRAINED WITH RETAINER GLANDS.
5. CRADLES FOR WATER LINES LARGER THAN 24" SHALL BE DESIGNED FOR THE SPECIFIC
LOCATION AND SHOWN ON THE DRAWINGS.
6. ALL DUCTILE IRON FITTINGS SHALL BE WRAPPED IN POLYETHYLENE ENCASEMENT PRIOR TO
PLACING OF BLOCKING.
CITY OF FORT WORTH, TEXAS REVISED: 08-31-2012
CONCRETE CRADLE
33 11 00-D131
WIDTH SHALL BE 8"
MIN. FOR 2 BAR
APPLICATIONS,
OTHERWISE 6" MIN.
PLAN VIEW
6" MIN.
11E—DOWN BARS
AS DESIGNATED
ON TABLE
REINFORCING MAT
SHALL BE #4 BARS
® 6" OCEW /
BLOCKING SHALL
BE AGAINST
PIPE BACKFILL PER UNDISTURBED
� .':.'.`�`_.;' �`.'.`('.'� .'.'.`. EARTH
DRAWINGS AND .�,p
SECTION 33 05 10 .•.• a'fi"^ ��ezawr HOOK TIE DOWN
BARS INTO
PIPE EMBEDMENT �: £ N REINFORCING
PER DRAWINGS AND - ti� u MAT (TYP.)
SECTION 33 05 10
REINFORCING MAT,
#4 BARS CO 6" OCEW
FORT WORTH
6" MIN.
c.. r -" .r0:5
PROFILE VIEW
6" MIN.
SECTION VIEW
BLOCKING SHALL
BE AGAINST
UNDISTURBED
EARTH
VERTICAL TIE -DOWN BLOCKING TABLE
PIPE
SIZE
12"
90' BENDS 45' BENDS 22.5' BENDS 11.25' BENDS
ALL 90'
BENDS
SHALL BE
ESTRAINtu
MIN. MIN. MIN. MIN. MIN. MIN.
VOLUME #4 VOLUME #4 VOLUME #4
(CF) BARS (CF) BARS (CF) BARS
48.69 1 24.82 1 12.47 1
86.56 2 44.13 1 22.17 1
135.25 3 68.95 2 34.64 1
194.76 4 99.29 2 49.88 1
NOTES:
1. VERTICAL T1E—DOWN BLOCKING VOLUMES SHOWN ARE BASED ON:
1.1. 225 PSI TEST PRESSURE
1.2. 150 PCF CONCRETE DENSITY
1.3. A SAFETY FACTOR OF 1.5.
2. BAR QUANTITIES ARE BASED ON:
2.1. 30 KSI #4 STEEL REINFORCEMENT BAR
2.2. A FACTOR OF SAFETY OF 1.5
2.3. "L" SHALL BE A MINIMUM OF 18".
3. THE ENGINEER SHALL PROVIDE A SEPARATE VERTICAL TIE —DOWN BLOCKING TABLE
WHEN THE CONDITIONS DO NOT MEET THE ABOVE ASSUMPTIONS.
4. THE CONTRACTOR IS REQUIRED TO PROVIDE THRUST RESTRAINT BY MEANS OF
VERTICAL TIE —DOWN BLOCKING FOR ALL PIPES. THIS ITEM SHALL BE CONSIDERED
SUBSIDIARY TO THE VARIOUS ITEMS BID.
5. ALL MJ FITTINGS SHALL BE ADDITIONALLY RESTRAINED WITH RETAINER GLANDS.
6. WIDTHS, LENGTHS AND DEPTHS MAY VARY BUT SATISFACTION OF ABOVE MINIMUM
VOLUMES MUST BE DEMONSTRATED.
7. KEEP CONCRETE CLEAR OF PIPE JOINTS AND BOLTS.
8. VERTICAL 11E—DOWN BLOCKING FOR LINES 16" AND LARGER SHALL BE DESIGNED FOR
THE SPECIFIC LOCATION AND SHOWN ON THE DRAWINGS.
9. ALL DUCTILE IRON FITTINGS SHALL BE WRAPPED IN POLYETHYLENE ENCASEMENT
PRIOR TO PLACING OF BLOCKING.
CITY OF FORT WORTH, TEXAS REVISED: 08-31-2012
VERTICAL TIE -DOWN BLOCKING
33 11 00-D132
4 CURB STOP PER
SECTION 33 12 10
2" GALVANIZED PIPE
EXISTING SERVICE LINE
FORT WORTH
3/4" TUBING
ADAPT AS REQUIRED
// /..//A /A AY
j% %/ _hill
EXISTING PRIVATE SERVICE
TO HOUSE OR BUILDING
NOTES:
1. CONTRACTOR SHALL BE REQUIRED TO COVER
METER VAULT WITH PROTECTIVE GUARD.
2. METER SHALL BE REMOVED BY THE
CONTRACTOR. CONNECTION FROM BY-PASS
TO PRIVATE SERVICE SHALL BE MADE BY
CONTRACTOR.
CITY OF FORT WORTH, TEXAS REVISED: 08-31-2012
TEMPORARY SERVICE CONNECTION
33 04 30-D133
EXISTING
PAVEMENT
z
ASPHALT COVER
N.MI-..-z\f4X-41e1
15# ROOFING FELT
36" MIN.
2" GALVANIZED
PIPE
2—STANDARD
FINISHED
2"X6" BOARDS
FORTWORTH INTERSECTION & DRIVEWAY APPROACH
CROSSING FOR TEMPORARY WATER SERVICE
CITY OF FORT WORTH, TEXAS REVISED: 08-31-2012
33 04 30-D134
6" MIN. AND
12" MAX.
INITIAL BACKFILL
6" MIN. AND
12" MAX.
BEDDING
TRENCH GEOTEXTILE
FABRIC
CRUSHED ROCK PER
SECTION 33 05 10
/ 12" MIN. TRENCH WALL
CLEARANCE (TIP.)
CITY OF FORT WORTH, TEXAS
EMBEDMENT FOR SANITARY SEWER
ALL SIZES
REVISED: 08-31-2012
33 05 10-D201 I
FORT WORTH
BACKFILL AND
SURFACE REPAIR TO
MATCH SEWER MAIN
2" MIN.
2" MIN.
TRENCH GEOTEXTILE
FABRIC
CRUSHED ROCK
PER SECTION
33 05 10
CITY OF FORT WORTH, TEXAS
EMBEDMENT FOR SANITARY SEWER
SERVICES
REVISED: 08-31-2012
33 05 10-D202
NOTE TO DESIGNER:
PIPE LARGER THAN 42"
TO BE CASED IN STEEL
SHALL BE DESIGNED BY
ENGINEER
NOTE:
1. SEWER CARRIER PIPE SHALL BE
CENTERED IN CASING PIPE OR
TUNNEL LINER PLATE, BUT
VARIATIONS MAY BE ALLOWED TO
ACHIEVE PROPOSED GRADE ON
DRAWINGS.
2. CASING AND TUNNEL LINER PLATE
DIAMETERS SHOWN ARE TO MEET
MINIMUM INSTALLATION
REQUIREMENTS. LARGER CASING
SIZES AS INDICATED IN THE
DRAWINGS SHALL GOVERN. CASING
SIZES MAY BE INCREASED TO
ALLOW FOR CASING INSTALLATION
TOLERANCE VARIABILITY.
CARRIER
PIPE
CARRIER PIPE
MOUNTED ON
SKID
STEEL
CASING
PIPE
CELLULAR
GROUTING IN
ANNULAR SPACE
PER SECTION 33
05 24
COATED STEEL CASING
SPACERS PER SECTION
33 05 24
SANITARY SEWER PIPE
WITH STEEL CASING
STEEL SKID
GROUT
SANITARY SEWER PIPE
36" AND LARGER WITH
TUNNEL LINER PLATE
TUNNEL LINER
PLATE OUTSIDE
DIAMETER
TUNNEL LINER
PLATE INSIDE
DIAMETER
CELLULAR
GROUTING IN
ANNULAR SPACE
PER SECTION 33
05 24
BOTTOM
NOMINAL CARRIER
PIPE SIZE
10"
12"
15'
16"
18"
20"
21"
24"
2T'
30"
36'
42"
SDR 26 PVC PIPE
BELL OD
9.692'
12.116"
14.424"
17.652"
CASING PIPE SCHEDULE
MIN CASING STEEL
ID
16"
20"
20"
24"
DI PIPE BELL 0D
11,16"
13.25"
15.22"
19.86"
22.16'
24.28"
28.50"
34.95"
41.37"
48.2T'
MIN CASING STEEL
ID
16"
20"
20"
24"
30'
30"
36"
42"
48"
TUNNEL LINER PLATE SCHEDULE
NOMIPINALPE CARRIER
DI PIPE BELL OD I NOMINAL TLP 0
18" 22.16'
20"
21"
24"
27"
30"
36"
42"
48"
54"
60"
66'
72"
78"
84"
90"
96"
24.28"
28.50"
34.95"
41.3T'
48.27"
48"
48"
48"
48"
52"
58"
66"
SS FIBERGLASS
PIPE COUPLING OD
21.3"
23.4"
27,6"
29.8"
33.9"
40.2"
46.5"
52.9"
59.4"
65.5"
72"
78.3"
84.T'
90.2"
97.8"
103.1"
FIBERGLASS PIPE
COUPLING OD
21.3"
23.4"
27,6"
29.8"
33.9"
40.2"
46.5"
NOMINAL TLP 0
48"
48"
48"
48"
52"
52"
62'
68"
76"
82"
88"
94"
100"
106"
114"
118"
MIN CASING STEEL
ID
30"
30"
36"
36"
42"
48"
54"
FORT WORTH CITY OF FORT WORTH, TEXAS REVISED: 08-31-2012
SANITARY SEWER CARRIER PIPE INSTALLATION
IN STEEL CASING AND TUNNEL LINER PLATE 33 05 24-D203
CRUSHED ROCK
EMBEDMENT PER
SECTION 33 05 10
+ + v vvvvv o
44aa 44444444a44V4a4 V O4444
�4\\0a0494049944444444a P944
�"J?VO4V99944444044VOV49999•
4V440490444444OVVVVVV
4V VVVV44VVVVVVVVVVVVVVVVV
TV4444V 4V 9V TV 4V TV 94444
VVVV VVVV99VVVVVVVVVVV
4 VV V 4 V VV 4 V V V V V V V V 4 4 4 4 4 4 a 4 4
00009VVVVVVVVVVV7070VV9174
9VVVOVVVVV4V44V90VV099444
1 EXTENTS gqF)J_AUNCH OR
L RECIEVNG PIT
♦ ♦ ♦ ♦ ♦ ♦ + ♦ ♦ ♦ + ♦♦ f ♦ • ♦♦ .
}
.+♦. ♦ ♦ •+. jai
♦ « +
} ♦ i+i
+}r 1 i ♦i+ri +i++
PIPE BACKFILL PER
SECTION 33 05 10
AS INDICATED ON
THE DRAWINGS
CARRIER
PPE
^v4444ovvvova vv Fi did - - -�'•W •��/�
r'.'4Wif9WArtiVON V V 0 ANV7ifkt"
444444444V044444VVV VVV "WWyI{� ♦ ,� ��..
/V44444440VVV044V044444440 �'-^"'
/V V 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 V V 4 V 4 4 4
944444 TV 4V TV499044444444? 6" '\//\/%\//\//
\�OOOO a4444444444940004044•
,,/./voyvvvvvvvvvvvvvvarvvvvy MAX
777/47"
\\//.\//.\//,\//,://\//,\./,\//.\�
CLSM FROM BOTTOM AND
LIMITS OF LAUNCH OR
RECIEVING PIT TO 6"
ABOVE CASING PIPE OR
TUNNEL LINER PLATE TO
PROTECT END SEAL
12" MAX (TYP.)
CELLULAR GROUTING
OF ANNULAR SPACE
STEEL CASING PIPE
OR TUNNEL LINER
PLATE
FOR ALL CARRIER PIPE 48"
AND LARGER, CASING
SPACER SPACING SHALL BE
DESIGNED BY ENGINEER
FOR CASING BY OPEN CUT,
EMBEDMENT SHALL BE SAND
PER SECTION 33 05 10
CASING
SPACER
//\/X/\/ /�/�/�/*Vn/
1
SPACING BETWEEN J
CASING SPACERS
SHALL BE NO MORE
THAN 6' MAX (TYP.)
CONTACT GROUT PER
SECTION 33 05 23 IF
PPE JACKING OR
HAND TUNNELING
J
CASING SPACERS
ON BOTH SIDES OF
BELL AND SPIGOT
FORT WORTH CITY OF FORT WORTH, TEXAS REVISED: 08-31-2012
SANITARY SEWER PIPE IN STEEL CASING
& TUNNEL LINER PLATE PROFILE 33 05 24-D204
A
A
PLAN VIEW
SECTION B-B
ORT WORT
4-#3 DOWEL
BARS SPACED
EVENLY
SEE NOTE 4
#3 DOWEL CENTERED
BETWEEN BENCH
AND DROP THROUGH
RADIUS
(TYP.)
GROUTED DROP
THROUGH PER
SECTION 03 30 00
PRE -CAST OR
CAST -IN -PLACE
MANHOLE PER 33
39 10/20-D208
r.,
j-3I4 I.D. GROUTED
j DROP
THROUGH
PER SECTION
03 30 00
SECTION
3/4 I.D.
A -A
7
PRE -CAST OR
CAST -IN -PLACE
MANHOLE PER 33
39 10/20-D208
SLOPE BENCH TO
FLOW TO TROUGH
+ry PROVIDE Y4 INVERT
DEPTH VERT FO
ALL STANDARD
MANHOLES
CONCRETE TROUGH PER
SECTION 03 30 00
NOTES:
1. DROP THROUGH SHALL BE POURED
MONOLITHICALLY WITH
CAST -IN -PLACE BENCH, OR
DOWELED AND GROUTED TO
PRE -CAST BENCH.
2. DROP THROUGH SHALL EXTEND
INTO MAIN -LINE TROUGH Y2 THE
INNER DIAMETER OF LATERAL.
3. WHERE LATERAL FLOW -LINE TO
MAIN FLOW -LINE IS GREATER THAN
24" AN EXTERNAL DROP SHALL BE
REQUIRED PER 33 39 10/20-D209
4. "X" SHALL BE NO MORE THAN 24"
FROM FLOW -LINE TO FLOW -LINE.
"Y" SHALL BE THE GREATER OF
HALF OF "X" OR 6".
CITY OF FORT WORTH, TEXAS REVISED: 08-31-2012
i
1
1
1
HYDRAULIC SLIDE
33 39
10/20-D207
NOTES:
1. MANHOLE TOP SHALL BE PER MANHOLE LID ASSEMBLY DETAILS AS
INDICATED IN THE DRAWINGS.
2. FOR CAST —IN —PLACE MANHOLES, CURE FOR THREE DAYS BEFORE
BACKFILLING AROUND STRUCTURE
3. IF SOIL CONDITIONS OR GROUND WATER PREVENT USE OF COARSE
AGGREGATE BASE A 2—INCH MUD SLAB MAY BE SUBSTITUTED.
4. CAST —IN —PLACE CONCRETE SHALL BE PER SECTOIN 03 30 00.
5. PRE —CAST JOINTS SHALL CONFORM TO ASTM C478.
6. UNLESS OTHERWISE INDICATED IN THE DRAWINGS, 4'0 MANHOLES SHALL
BE USED FOR 21" AND SMALLER SANITARY SEWER LINES AND 5'0
MANHOLES SHALL BE USED 24" UP TO 36" SANITARY SEWER LINES.
+ + + + + + + 1 +
+ + + + + + + +
+ + + + + + + +
+ + + + + + 4. +
++++++++ 3" MIN. +++
+ + + + (Typ,) + +
+ + + + + + +
4 + + + + + + + +
+ + + + + + + + +
+ + + + + + + + +
+ + + [- + + + + +
ACCEPTABLE. ++++++++++++
BACKFILL AROUND + + + + + + +
MANHOLE (TYP.) PER' + + + + + +
SECTION 33 05 10.+++++++++++++
+ + + + + + + + 4
+ + + + + + +
+ + + + + + +
+ + + + + + +
+ + + + + + + +
+ + + + + + +
+ + + + + + + +
+ + + + + + + +
+ + + + + + +
+ + + + + + +
+ + + + + + + +
+ + + + 4- + + +
+ + + + + + + +
+ + + + + + + +
+ + + + + + + +
+ + + + + + + +
+ + + + + + + +
+ + + + + + + +
+ + + + + + + +
+ + + + + + + +
+ + + + 4 + + +
+ + + + + + + + •
+ + + + + + + + _•�L
+ + + + + + + + .
+ + + + + + + +
+ + + + + + + +
+ + + + + + + +
+ + + + + + + +
+ + + + + + + +
+ + + + + + + +
+ + + + + + + +
EMBEDMENT SHALL BE + + I.
+
SAME AS MAIN (TYP.) + + + + +
PER SECTION 33 05 10 + + + + '.
+ + + + +
+T+T+ + + + + +-•
FRAME AND COVER
AS INDICATED ON
THE DRAWINGS
PRE -CAST I CAST -IN -PLACE
a;
8" MIN.
RUBBER GASKETS
AT ALL PRECAST
JOINTS
5" MIN. FOR 4'0
6" MIN. FOR 5'0
7" MIN. FOR 6'0
4',5'OR6'0
AS INDICATED IN
THE DRAWINGS
SLOPE BENCH
TOWARDS
DOWNSTREAM
DIRECTION
PROVIDE 3/4
DEPTH INVERT
(TYP.)
ADJUST GROUT INVERT\\\!\C\/\\ A
W/OFFSET TO MATCH PIPE \ -
FLOWLINE AS NEEDED 6" — 8" — k V\ V�/ ' V\ \• ‹ �\
APPLY INTERIOR
CORROSION
PROTECTION IF
REQ'D (TYP.) PER
SECTION 33 39 60
GROUT
AROUND
PIPE
PENETRATION
+ + + + + + +
+ + + + + +
+ + + + + + +
++++ + + •
+ MANHOLE LID
+ + + + + ASSEMBLY, SEE
+ + + + + + NOTE 1
+ + + + + + + +
+ + + + + + + + +
+ + + + + + + +
+ + + + + + + + +
++++++ +PROVIDE EXTERNAL
+ + + COATING IN
+ + +ACCORDANCE WITH
• +++++ASTM D4258 AND
+ + + D4259
+ + + + + + +
+ + + + + +
+ + + + + + +
+ + + + + +
+ + + + + + +
+ + + + + +
+ + + + + + +
+ + + + + +
+ + + + + + +
+ + + + + +
+ + + + + +
+ + + + + +
8" MIN. - + + + + + + +
+ + + + + +
• + + + + + + +
+ + + 4 + + +
• + + + + + + +
+ + + + + + +
▪ • + + + + + + +
+ + + + + + +
+ + + + + + +
•• : + + + + + + +
- 4 + + + 4 + + +
+ + + + + + +
+ + + + + + +
+ + + + + + +
„+ + + + + + +
i+ + + + + + +
•{+ + + + + + +
+ + + + + + +
• ' + + + + + + +
• + + + + + + +
+ + + + + + +
+ + + + + + +
+ + + + + + +
4 + + + + + + + +
+- + + + + + + +
+ + + + + + +
+ + + + + + +
+ + + + + + +
+ + + + + + +
MIN. MIN.
8" —
CRUSHED ROCK BELOW UNDISTURBED
MANHOLE BASE (TYP)
PER SECTION 33 05 10
FORT WORTH
EARTH
CITY OF FORT WORTH, TEXAS
STANDARD MANHOLE
REVISED: 08-31-2012
33 39
10/20-D208
a^
J
CO
a�
NOTES:
1. MANHOLE TOP SHALL BE PER MANHOLE LID
ASSEMBLY DETAILS AS INDICATED IN THE
DRAWINGS.
2. CLSM OR CSS BACKFILL AROUND DROP PIPING
SHALL BE A MINIMUM OF 24" IN ALL DIRECTIONS.
3. NO PLUG SHALL BE PLACED ON TEE.
+++++++++++++++
+ + + + + + + + + + + + + + +
++++++++++++++++
+ + + + + + + + + + + + + + +
+ + + + + + + + + + + + + + + +
+++++++++++++++
++++++++++++++++
+ + + + + + + + + + + + + + + +
++++++++++++++++
+ + + + + + + + + + + + + + + +
+ + + + + + + + + + + + + + + +
++++++++++++++++
++++++++++++++++
+ + + + + + + + + + + + + + + +
+ + + + + + + + + + + + + + + + +
+ + + + + + + 4- + + + +- + + + +
+ + + + + + + + + + + + + + + 4'+ + + + + + + + + + + + + + +
+ + + + + + + + + + + + + + + +
++++ ++ +CRUSHED ROCK +++++�-++++
+ + + + EMBEDMENT PER + + •+ •+ •+ •+
+ + + + SECTION 33 05 10 + + + + +
+ + + + ,- + + + + + + + + 4
+ + + + 1-++ + +++ + + + + + + +
EXCAVATION
LIMITS
CLSM OR CSS
DROP PIPE
EMBEDMENT
PER SECTION
33 05 10
vvvvvvvvv,
vvvvVvv'„vv
vvvvvvv2. v^
v v v v v v v v v v
J� v
vvv,•
vvvv
vvvv
vvvv=I
vvvv
vvvvv
vvvv
SDR-26
SWEEP TEE
v v V G -,
vvv *
v vv-.:
vvvv-'":
vvv '
vvvv•:
FFORT WORTH
STANDARD 4'DIAMETER DROP MANHOLE
� j\
vvvv vvvv .
vvvvv vvv
v VVVN V VVG ----�
-vvvvv 'vvv
Vvvv.-.
vvvvv vvv/
VV v v v
/�VVVv o I 'vvv .,
vvvvNwo vvvv,
vvvvv m('vVV .
VVVVsa VVVG.'
vvvv a 'vvv
vvvvs> vvVV-0.',
vvVv 'vvv ••
VVVVN V V V - -;••
VVV vvv
vvvv VVG
vvvv
vvvv
vvvv
SDR-26 1
V V V V V V v V V V
vvvvvvvvvv
vvvvvvvvvv
vvvvvvvvl-
MANHOLE LID
ASSEMBLY,
SEE NOTE 1
2"_6„
ALL DROP MANHOLES
SHALL REQUIRE INTERIOR
CORROSION PROTECTION
PER SECTION 33 39 60
GROUT FILL TROUGH
TO DIRECT FLOW
VERTICAL TO TOP
POINT OF PIPE
+ + + + + + +
+ + + + + + +
+ + + + + + +
+ + + + + + +
++++++
+++++++
+ + + + + + +
+ + + + + + + +
+++++++
++++++++
+ + + + + + + +
+ + + + + + + +
+ + + + + + +
+ + + + + + 4- +
+ + + + + + + +
+ + + + + + + +
+ + + 4- + + +
+ + + + + + + +
+ + + + + + +
+ + + + + + +
+ 4- 4- + + + +
+ + + + + + +
+ + + + + + +
._I+ + + + + + + +
+ + + + + + +
+ + + + + +
+ + + + + + + +
+ + + + + + t
.I+ + + + + + + +
+ + + + + +
+ + + + + + + +
+ + + + + + +
+ + + + + + + +
+ + + + + +
+ + + + + +
+ + + + + +
+ + + + + + + +
+ + + + + + +
+ + + + + + +
+ + + + + +
+ + + + + + + +
+ + + + + + + +
+ + + + + + +
+ + + + + + + +
+ + + + + + +
+ + + + + + + +
'+ + + + + + + +
+ + + + + + + +
+ + + STANDARD
+++++ MANHOLE PER 33
• • ++++ 39 10/20-D208
+ + + + + + +
+ + + + + + +
+ + + + + + + +
+ + + + + + +
+ + + + + + +
+ + + + + + +
+ + + + + + + +
+ + + + + + +
+ + + + + + +
+ + + + + + + +
+ + + + + + +
+ + + + + + +
+ + + + + + +
+ + + + + + +
+ + + + + + +
\
\\\\\\�i\\\ri\\`i\
CITY OF FORT WORTH, TEXAS REVISED: 08-31-2012
33 39
10/20-D209
SPACE HOOKS
EVENLY AROUND
FLANGE
FRAME AND COVER AS
INDICATED IN THE DRAWINGS
SURFACE RESTORATION
AS INDICATED IN THE
DRAWINGS
REDUCER SHALL BE FABRICATED
AND FACTORY BONDED TO
MANHOLE BARREL AND SAFELY
SUPPORT H-20 LOADING PER
AASHTO REQUIREMENTS
FIBERGLASS
REINFORCED
PIPE MANHOLE
MANHOLE LID
ASSEMBLY, SEE
NOTE 1
j///////
++++ :0p
O O
BACKFILL AND EMBEDMENT - ` +}++°+,°o0po
18" MIN. AROUND MANHOLE -t++ + + °O°O°
WITH CSS PER SECTION 33-+++++++++'0 0°0
0510 ;+.+r+++'0°0°0
+++ +++++,0p000
BACKFILL SHALL BE SAME AS ` -- +«++:04°0O°0O
SANITARY SEWER MAIN AS -++++« 00000
INDICATED ON THE DRAWINGS .+++++r+++:0QOo0
PER SECTION 33 05 10 •+++++++r« O O O
+ .++++++++ 0p 0p 0
+ +++++« 000°0
+ t + + + 0°0°0
++++ 'O O 0
.++++++++« ' 0° 0° 0
0�0�0
OOI
PIPE EMBEDMENT
SHALL BE CRUSHED
ROCK PER SECTION
33 05 10
#4 BARS EMBEDDED
HALFWAY INTO MANHOLE
BASE AND HOOKED OVER
MANHOLE FLANGE (TYP.)
CRUSHED ROCK PER SECTION 33
05 10, WHERE GROUNDWATER IS
PRESENT A 2" MUD SLAB WILL BE
PERMITTED IN PLACE OF ROCK
FORT WORTH
PLAN VIEW
PAVED I UNIMPROVED
AREAS 1 SURFACES
4'0 - 21" AND
SMALLER SEWER PIPE
5'0 - 24" TO 36"
SEWE PIPE
i
MANHOLE SHALL
EXTEND PAST GRADE
RINGS MIN. 1"
+ t i + k + +
+ + a r + + a #k a
4 + + i t i + +
} + r + + + }
4 + i + } t # + t
+ + a r } + r
+ + + r a + + r +
• t+ r i t k t+
+ + + a + + + +
k + + r + t + +
• k + + + + + k
+ k i k+ t i e
+ + + + + + r +
• + k + + k + +
i} k k k k++
+ + # + + + k
+ k + k i k + +
+ r a r a r++ a
k i+ i k+ k
+ + # a r a + + +
+ + + r a r +
r + r + r + + + +
NOTES:
1. MANHOLE TOP SHALL
BE PER MANHOLE LID
ASSEMBLY DETAILS
AS INDICATED IN THE
DRAWINGS.
2. ALL CONNECTIONS
SHALL BE TESTED
FOR WATER TIGHT
SEALS PRIOR TO
BACKFILLING.
3. ANY CUT EDGES FOR
LATERALS OR
STUB -OUTS SHALL
BE SEALED WITH
RESIN.
4. FIBERGLASS
MANHOLES SHALL
ONLY BE USED AT
THE DISCRETION OF
THE CITY.
5. FOR PAVED AREAS
SURROUND MANHOLE
WITH 18" MIN. CSS
BACKFILL AND
EMBEDMENT.
6. FOR UNIMPROVED
SURFACES BACKFILL
AND EMBEDMENT
SHALL EXTEND TO
MANHOLE.
6" MIN.
TOPSOIL
WRAP JOINT WITH EXTERNAL
x�
� \ SEALING MATERIAL A MINIMUM ��\' OF 12" ON EITHER SIDE OF
CONCRETE BASE CONNECTION TO ENSURE
SIZING SHALL BE PER PROTECTION AGAINST
33 39 10/20-D208 LEAKAGE
PROFILE VIEW
CITY OF FORT WORTH, TEXAS
REVISED: 08-31-2012
FIBERGLASS MANHOLE
33 39 30-D212
W U
J lL
2¢14
O,ONLAN
( FVIEW1
PROPERTY
LINE
4" CONCRETE
COLLAR
FOR NEWS
DEVELOPMENT, CAP
RISER 1' BELOW
GRADE (CAST IRON).
MARK W/RED VINYL
TAPE 3" WIDE Sc 6"
ABOVE GROUND
RUBBER SLEEVE COUPLING
REQUIRED IF EXISTING
SERVICE IS PRESENT.
OTHERWISE PLUG END.
s.
�2—WAY
CLEANOUT TEE
EXIST, OR PROP. — — 6" MIN. — — 6" MIN
SEWER SVC
CITY OF FORT WORTH
STD. CLEANOUT W/CAST
IRON OR POLYETHYLENE
CAP
COLD JOINT
REQUIRED
STANDARD
PARKWAY i"/FT.
f fff
•
—ACCEPTABLE+'+'
BACKFILL PER"« ++"+ +"+"++"+ ++"r
33 05 10—D001`"
}" STAINLESS STEEL
BOLTS
POLYETHYLENE
1.5"
0—RING
lU
7.5"
PVC CI FIANOUT W/5.5. BQt TS
AN P LY.TH F'NF LI
FOR UN— AV?� AREAS_
r 1.5"
�u
1
" STAINLESS STEEL
BO�CAST IRON
—O—RING
u) CAST IRON
CAST IRON CI FANOUT W/S.S.
rOIRTS PAqAVF� AREAS
FORT WORTH
«++
+"+"+
NOTES:
1. PIPE AND FITTINGS MUST BE SDR-35 OR SDR-26
PVC MATERIAL OR DUCTILE IRON WITH CERAMIC
EPDXY LINING PER SECTIONS 33 11 10 AND 33 11
11 AS INDICATED IN THE DRAWINGS.
2. PROVIDE RUBBER SLEEVE COUPLINGS WITH
STAINLESS STEEL DOUBLE —BAND REPAIR SLEEVES
TO CONNECT TO EXISTING SERVICE. TIGHTEN
SLEEVES TO THE TORQUE RECOMMENDED BY THE
MANUFACTURER.
3. USE 5—SACK, 3,000 PSI CONCRETE AROUND
CLEANOUT ASSEMBLY.
4. SEWER SERVICE SHALL INCLUDE ALL
APPURTENANCES FROM SEWER MAIN UP TO AND
INCLUDING RUBBER SLEEVE COUPLING OR PLUG.
5. THE LONG DIMENSION OF THE CONCRETE
CLEANOUT COLLAR SHOULD BE PARALLEL TO THE
STREET.
SEWER SERVICE MATERIAL
AS INDICATED IN
DRAWINGS, SLOPE VARIES.
+ '`f"i �•�i ACCEPTABLE
.fri i+i +r .
i+ BACKFILL PER
SECTION 33 05 10
EXTEND CONCRETE
ENCASEMENT 6" MIN. FROM
BOTH ENDS OF 2—WAY
CLEANOUT TEE
PROPERTY UNE
SIDEWALK
///`N// A
STANDARD TEE
CRUSHED ROCK
EMBEDMENT PER
SECTION 33 05 10
7CAST IRON CLEANOUT
W/LID AND CONCRETE
COLLAR MUST BE
EITHER COMPLETELY
INSIDE OR OUTSIDE OF
SIDEWALK
PROPERTY LINE
DRIVEWAY
APPROACH
STREET
CAST IRON CLEANOUT BOOT
W/CAST IRON LID FOR PAVED
AREAS
CURB &
GUTTER
CITY OF FORT WORTH, TEXAS
SIDE
PVC CLEANOUT W/LID
AND CONCRETE COLLAR
MUST BE EITHER
COMPLETELY INSIDE OR
OUTSIDE OF SIDEWALK
7CURB &
GUIILR
STREET
PVC CLEANOUT BOOT
W/POLYETHYLENE LID FOR
NON —PAVED AREA
REVISED: 10-08-2012
SANITARY SEWER SERVICE
33 31 50-D214
PROPERTY/R.O.W. LINE
BACKFILL SAME AS SANITARY SEWER -r►
MAIN AS INDICATED IN THE DRAWINGS
PER SECTION 33 05 10
+ + \
N .' A
+ + + + + + + + 4 + + + + + + + + + + +
• + + + + + + + + 4 + Z+ + + + + + + + + i+
+ 4 4 + + + + 4 4 4 4 - + + + + + + + + +
• + + + + 4 + + 4 4 + + + + + + + 4 + + 4 +
•4 +4++4++++++++++++4++N)++•
+ 45' ++++ ++ 4+
+ + + + + + + + + + + + + •VERTICAL+ + + +
+++4+4+++444+++444+4++++++• BEND + + 4, + +
• + + + + + + + + + + + + + + + +
Zr + + + + + + + + + + r + + + +
• r + + + + + + + + + + + + + +
• ++;+ + + + + + + r + + + +
+ + + + + + + + + + + t.
+ + + + + + + + + + + +
+ + + + + + + + + + + r.-
•
++ ++ + ++ + + +
+
+++
• + + + + + + ++
r4++++++++
+ + + + + + + Ito '1.e`
+ + r + + + 't \
4..1,/�-.. /\y
P
ER
+
/,/ /)j
PAST THIS POINT
+ + + 4 4 4 4
• + 4 4 4 4 4
+ + 4 4 4 4
UNDISTURBED SOIL
PROPERTY/R.O.W. LINE
SIDEWALK
r
FORT WORTH
CURB
STREET
PLAN VIEW IN
NON -PAVED
AREAS
+ • + + + + + + + + + + + + + +
\/\\
45' 60'
SANITARY
SEWER MAIN
-TWO-WAY
CLEANOUT TEE
EXIST
SERVICE
LINE
/
NOTE:
1. USE THIS SERVICE ONLY
WITH PERMISSION FROM THE
CITY OF FORT WORTH.
PVC CI EANOUT W/S.S. B01 TS
POL LID
FOR UN -PAVED
CLEANOUT W/LID AND
CONCRETE COLLAR MUST BE
EITHER COMPLETELY INSIDE
OR OUTSIDE OF SIDEWALK
STREET
DRIVEWAY
APPROACH
PLAN VIEW IN
PAVED AREAS
SIDEWALK
PROPERTY/R.O. W.
LINE
DRIVEWAY
CITY OF FORT WORTH, TEXAS REVISED: 08-31-2012
DEEP SANITARY SEWER SERVICE
33 31 50-D215
11
\I
EXISTING PIPE
RUBBER SLEEVE
COUPLING (TYP.)
FORT WORTH
PROPOSED PIPE EXISTING PIPE
CITY OF FORT WORTH, TEXAS
SANITARY SEWER POINT REPAIR
(4" TO 12")
REVISED: 08-31-2012
33 31 23-D217
ASPHALT TO
SAW -CUT BE PLACED IN
(TYP.) TWO LIFTS
EXISTING TREATED
SUBGRADE (IF ANY)
(
PROVIDE DENSITY AND
THICKNESS TES11NG
PER SEC110N 32 12 16
PART 3.6
TACK COAT
I ! 1 111'1
TRENCH REPAIR LIMIT::
CONCRETE BASE MATERIAL
FOR TRENCH REPAIR PER
SECTION 03 34 16
NAN IgcriNab"),)
+ + 4 + + + + + + + + + + 1
+ + + + + + + + + + + + + +
+ + + + + + + + + + + + + + -
+ + + + . + +.
+++ 4: 1 1
+ + + + + + + . I
+ + + + + • L-4
++++++++
BACKFILL MATERIAL
OICIL4re JVORT
TRENCH
WALL
EXISTING
HMAC
PAVEMENT
;VW
UNDISTURBED
SUBGRADE
CITY OF FORT WORTH, TEXAS
ASPHALT PAVEMENT TRENCH REPAIR -
ARTERIAL & INDUSTRIAL STREETS
REVISED: 08-31-2012
32 01 17-D520
SAW —CUT
(TYP.)
EXISTING TREATED
SUBGRADE (IF ANY)
PROVIDE DENSITY AND
THICKNESS TESTING
PER SECTION 32 12 16
PART 3.6
II lii2l
ITS
TRENCH REPAIR LIMITI
CONCRETE BASE MATERIAL
FOR TRENCH REPAIR PER
SECTION 03 34 16
ORT WORT
BACKFILL MATERIAL
1-12a
+a+-
+ + + + a13
+ + + + +
a + + + + 4
+ + + +
+ + +
TRENCH
WALL
EXISTING
HMAC
PAVEMENT
/
VARIES/
UNDISTURBED
SUBGRADE
CITY OF FORT WORTH, TEXAS
ASPHALT PAVEMENT TRENCH REPAIR -
RESIDENTIAL STREETS
REVISED: 08-31-2012
32 01 17-D521
•
CONSTRUCTION JOINT WITH
SILICONE JOINT SEALANT
PER 32 13 13-0518 (TYP.)
EXISTING TREATED
SUBGRADE (IF ANY)
STRENGTH AND
THICKNESS TESTING
SHALL BE PERFORMED
PER SECTION 32 13 13
CLASS 'H' CONCRETE
PAVING PER SECTION 32
13 13 OR 'HES' IF
DESIGNATED ON DRAWINGS
I! X i
BACKFILL MATERIAL
TRENCH REPAIR LIMITS
JOINTING SHALL MATCH
EXISTING LOCATIONS
AND TYPES AS
CLOSELY AS POSSIBLE
#4 BARS ® 12" O.C.E.W.
TRENCH
WALL
- #4x18" DEFORMED BARS
DOWELED AND EPDXYED MIN.
6" INTO EXISTING PAVEMENT
12" 0.C. (TYP.)
EXISTING
CONCRETE
PAVEMENT
1s111=111 )
I I \_. UNDISTURBED
1J� SUBGRADE
NOTE:
• FOR CONCRETE STREETS < 10
YRS OLD DIMENSION "X" SHALL
EXTEND TO END OF PANEL,
OTHERWISE "X" SHALL BE 12"
SORT WORTH CITY OF FORT WORTH, TEXAS
CONCRETE PAVEMENT TRENCH REPAIR -
ARTERIAL & INDUSTRIAL STREETS
REVISED: 08-31-2012
32 01 29-D522
CONSTRUCTION JOINT WITH
SILICONE JOINT SEALANT
PER 32 13 13-D518 (TYP.)
EXISTING TREATED
SUBGRADE (IF ANY)
if (-4
CLASS 'H' CONCRETE
PAVING PER SECTION 32
13 13 OR 'HES' IF
DESIGNATED ON DRAWINGS
STRENGTH AND -j
THICKNESS TESTING �J
SHALL BE PERFORMED
PER SECTION 32 13 13
TRENCH REPAIR LIMIT
JOINTING SHALL MATCH
EXISTING LOCATIONS
AND TYPES AS
CLOSELY AS POSSIBLE
#4 BARS , ® 18" 0.C.E.W.
+ + + + + + + + + + + + +
+ + + + + + + + + + + + + +
+ + + + + + + + + + + + + + -
+ + + + + + + + + + + + +•
+ + + t + t + + + +III
BACKFILL MATERIAL
TRENCH
WALL
#4x18" DEFORMED BARS
DOWELED AND EPDXYED MIN.
6" INTO EXISTING PAVEMENT
® 18" 0.C. (TYP.)
EXISTING
CONCRETE
PAVEMENT
UNDISTURBED
SUBGRADE
NOTE:
• FOR CONCRETE STREETS < 10
YRS OLD DIMENSION "X" SHALL
EXTEND TO END OF PANEL,
OTHERWISE "X" SHALL BE 12"
FORT WORTH CITY OF FORT WORTH, TEXAS REVISED: 08-31-2012
CONCRETE PAVEMENT TRENCH REPAIR -
RESIDENTIAL STREETS 32 01 29-D523
NOTES TO DESIGNER:
1. FILL IN BLANKS AND/ OR VERIFY ALL TEXT IN BLUE.
2. SPECIFY CURB HEIGHT TO MATCH EXISTING CONDITION.
SEE NOTE 1
PROPOSED PAVEMENT PER
TYPICAL ROADWAY SECTION
OR PAVEMENT REPAIR DETAIL
GRADE PER
1YP SECTION
PROPOSED STEEL PER
TYPICAL ROADWAY
SEC11ON
NOTES:
1. CITY APPROVAL REQUIRED FOR USE OF CURB MULE
WITH DIMENSIONS THAT VARY FROM DETAIL.
2. MATCH STREET SAWED JOINTS FOR SAWED JOINTS IN
CURB.
FORT WORTH
-6"_y
Ca
UdZ
0
w
0a_
•
PROPOSED SUBGRADE
PER TYPICAL ROADWAY
SEC11ON OR PAVEMENT
REPAIR DETAIL
2.
-•--_ 12"
_
TAMPED TOPSOIL
PER SECTION
32 91 19
COMPACTED ACCEPTABLE
NATIVE BACKFILL PER
SECTION 31 24 00
MINIMUM EXCAVATION
OUTLINE FOR STREET
CONSTRUC11ON
CITY OF FORT WORTH, TEXAS REVISED: 08-31-2012
STANDARD MONOLITHIC CURB
32 13 13-D525
NOTES TO DESIGNER:
1. DETAIL DEFINES PAY LIMITS OF HMAC TRANSITION SUBSIDIARY TO THE CONCRETE VALLEY GUTTER CONSTRUCTION.
EXPANSION
JOINTS
PER
32 13 13-D513
/ 24" HMAC
TRANSITION
/ PER SECTION
A 32 12 16
A\\\\\\\\ \\\\\\\\
/
,,, „ „, „ „
9" HMAC -�
TRANSITION
PER SECTION
32 12 16
--•-•9„y
SEE
NOTE 4
COMPACTED
SUBGRADE
(SEE NOTE 2)
NOTES:
0
/ // / / / / / / / /j/ / //
#4 BARS
18" O.C.B.W.
PLAN VIEW
EXPANSION
JOINTS
PER
32 13 13-0513
/ / / / / /
SEE NOTE 4-
INTERSECTING VALLEY
1" MAX OR AS DIRECTED BY
THE ENGINEER
8'-0" MIN.
(RESIDENTIAL STREETS)
SECTION A -A
9„--
SEE
NOTE 4
1. THE 7" REINFORCED CONCRETE VALLEY SHALL REPLACE THE TOP 7" OF THE PAVEMENT WITH THE REMAINING
PORTION OF PAVEMENT TO BE CONSTRUCTED INCLUDING SUBGRADE TREATMENT, IN ACCORDANCE WITH THE TYPICAL
PAVING SECTION.
2. 6" FLEX BASE, TYPE A, GR-1 OR MATCH THE PREPARED SUBGRADE REQUIREMENTS FOR THE PAVEMENT SECTION.
TYPE D OR TYPE B ASPHALT OR PREPARED SUBGRADE MAY BE USED.
3. PAY LIMITS FROM EXPANSION JOINT TO EXPANSION JOINT.
4. 9" AND 24" HMAC TRANSITION SUBSIDIARY TO CONCRETE VALLEY GUTTER. CITY MAY APPROVE ADDITIONAL HMAC
TRANSITION BEYOND THESE LIMTS UNDER SEPARATE PAY ITEM FOR HMAC TRANSITION PER SECTION 32 12 16.
5. GUTTER TO BE SHAPED TO CONFORM WITH CONCRETE VALLEY (OR PAVEMENT).
FORT WORTH
CITY OF FORT WORTH, TEXAS REVISED: 08-31-2012
CONCRETE VALLEY GUTTER
32 16 13-D530
-
NOTES TO DESIGNER:
1. FILL IN BLANKS AND/ OR VERIFY ALL TEXT IN BLUE.
2. SET GRADES TO CONVEY STORMWA TER 'WITHIN R.O.W. OR EASEMENTS,
3. REVISE DETAIL AS NECESSARY TO MATCH ACTUAL ROADWAY DESIGN.
4. MODIFY OETAIL TO MEET SPECIFIC CONDITIONS.
PROPOSED ASPHALT
PAVING PER TYPICAL
SECTION
STABILIZED SUBGRADE
PER PAVING TYPICAL
SECTION
10" PER FT.
TIP
6'
1'-4 Y."
J..
G
#4 BARS
NEW CONSTRUCTION
6'
TAMPED TOPSOIL.
PER SECTION
2 91 19
c
c
I L-1 11"-1 I._ i (- _1-
12"
COMPACTED ACCEPTABLE
NATIVE BACKFILL PER
SECTION 31 24 00
MINIMUM EXCAVATION
OUTLINE FOR STREET
CONSTRUCTION
#4 x 24' SMOOTH
DOWEL
TOP OF CURB —\
TOP OF PAVEMENT
PROPOSED
SUBGRADE
PER TYPICAL
ROADWAY
SECTION
12'
ASPHALT
EXISTING SUBGRADE
EXPANSION JOINT, FORMED GROOVE
ROUNDED TO X.." RADIUS WITH Yi"
PREMOLDED EXPANSION JOINT AND
SIUCONE JOINT SEALANT
14- MIN.
CLEARANCE
2" MIN
BAR STOP
DOWEL SLEEVE OR CAP
TO FIT DOWEL AND BE
SECURED
CURB AND GUTTER EXPANSION JOINT
FORT WORTH
STANDARD CURB AND GUTTER
9' HMAC
TRANSITION
PER 32 12 16
SEAL WITH
JOINT FILLER
10' PER FT.
6'
6" OR
CURB
17 T/2
PROPOSED
!.=.l;.lrr,U-TPEFE.11.!1.I SUBGRADE
PER TYPICAL
ROADWAY
SECTION
SEE NOTE 1
a Y.'
EE
EXISTING STREET
NOTE'
1. 200 LF MAXIMUM SPACING BETWEEN CURB
AND GUTTER EXPANSION JOINTS.
6'
3'
4
NOTF,
1. MINIMUM WIDTH IS 2'-0".
MATCH EXISTING WIDTH UP TO 2'-6'
12"
TAMPED TOPSOIL
PER SECTION
32 91 19
COMPACTED ACCEPTABLE
NATIVE BACKFILL PER
SECTION 31 24 00
MINIMUM EXCAVATION
OUTLINE FOR STREET
CONSTRUCTION
CITY OF FORT WORTH, TEXAS REVISED: 08-31-2012
32 16 13-D534