HomeMy WebLinkAboutContract 61189-A2CSC No. 61189-A2
AMENDMENT No . 2
TO CITY SECRETARY CONTRACT No. 61189
WHEREAS, the City of Fort Worth (CITY) and CDM Smith, Inc. (ENGINEER)
made and entered into City Secretary Contract No. 61189, (the CONTRACT)
which was authorized M&C 24-0172 on the 27 day of February, 2024, in the
amount of $3,695,990.00; and
WHEREAS, the CONTRACT was subsequently revised by: Amendment No.1 in
the amount of $0.00 administratively authorized on July 16, 2024; and
WHEREAS, the CONTRACT involves engineering services for the following
project:
Eagle Mountain Water Treatment Plant Expansion, CPN 105176; and
WHEREAS, it has become necessary to execute Amendment No. 2 to the
CONTRACT to include an increased scope of work and revised fee.
NOW THEREFORE, CITY and ENGINEER, acting herein by and through their
duly authorized representatives, enter into the following agreement, which
amends the CONTRACT:
1.
Article I of the CONTRACT is amended to include the additional
engineering services specified in proposal attached hereto and incorporated
herein. The cost to City for the additional design services to be performed
by Engineer totals $11,149,078.00.
2.
Article II of the CONTRACT is amended to provide for an increase in
the fee to be paid to Engineer for all work and services performed under
the Contract, as amended, so that the total fee paid by the City for all
work and services shall be an amount of $14,845,068.00.
3.
All other provisions of the Contract, which are not expressly amended
herein, shall remain in full force and effect.
EXECUTED and EFFECTIVE as
designated Assistant City Manager.
APPROVED:
City of Fort Worth, Texas
Prof Services Agreement Amendment Template
Revision Date: 12/08/2023
Page 1 of 2
of the date subscribed by the City's
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
Eagle Mountain Water Treatment Plant Expansion
CPN 105176
City of Fort Worth
7;1-LCa.—
Fernando Costa
Assistant City Manager
DATE: Sep 6, 2024
ATTEST:
Jannette Goodall
City Secretary
Qovoopq
a F�RT��d
�o
PVo o=d
l
aaIlIl nEXA`go4p
APPROVAL RECOMMENDED:
Christopher Har4er (Sep 6, 2024 08:53 CDT)
Christopher Harder, P. E.
Director, Water Department
Contract Compliance Manager:
ENGINEER
CDM Smith, Inc.
Jessica L. Veach, P.E.
Associate
DATE: 09-03-2024
By signing, I acknowledge that I am the person responsible for the
monitoring and administration of this contract, including ensuring all
performance and reporting requirements.
mew ; v
Ja sMCDon ald(Sep 4,202414:42 CDT)
James W. McDonald, P.E.
Project Manager
APPROVED AS TO FORM AND LEGALITY:
fj�
Douglas Black (Sep 6, 202412:53 CDT)
Douglas W. Black
Sr. Assistant City Attorney
City of Fort Worth, Texas
Prof Services Agreement Amendment Template
Revision Date: 12/08/2023
Page 2 of 2
M&C No.#: 24-0729
M&C Date: August 27, 2024
Form 1295: 2024-1187896
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
Eagle Mountain Water Treatment Plant Expansion
CPN 105176
Smith
July 16, 2024
Mr. James McDonald, P.E.
Project Manager
City of Fort Worth Water Department
1000 Throckmorton Street
Fort Worth, TX 76102
Subject: Eagle Mountain Water Treatment Plant Expansion
Amendment No. 2
CDM Smith Project No.: 0515-294565
City Secretary No. 61189 - City Project No. 105176
Dear Mr. McDonald:
This letter is in reference to a contract between Consultant (CDM Smith Inc.) and the City of Fort Worth
(the City) dated February 27, 2024 referred to herein as the "Contract." CDM Smith is pleased to submit
our Amendment No. 2 for the City's Eagle Mountain Water Treatment Plant Phase IV Expansion —
Project No. 105176.
CDM Smith was requested to complete final design through bid phase services for the Eagle Mountain
WTP Phase IV Expansion. We request an amendment to our current contract for performing these
additional services. The attached scope of work provides a more detailed explanation for these
additional services. Also attached is our fee proposal table developed for the additional scope of work.
The requested fee for base services is $ 11,149,078.00.
Table 2 below summarizes our revisions to the total contract
Table 2 — Total Contract:
Description
Original Contract
Amendment No. 1
Amendment No. 2
Modified Contract
Amount
$3,695,990.00
$0.00
$11,149,078.00
$14,845,068.00
75 State Street, Suite 701, Boston, Massachusetts 02109 1 tel: 617 452-6000
CDM
Smith
Mr. McDonald
July 16, 2024
Page 2
We appreciate the opportunity to be of continued service to the City. Please contact us if we need to
provide any further information.
Sincerely,
Jessica Veach, P.E.
Associate / Client Service Leader
CDM Smith Inc.
Copy to: Sarah Stewart, P.E., CDM Smith
Tony Sholola, P.E. City of Fort Worth
75 State Street, Suite 701, Boston, Massachusetts 02109 1 tel: 617 452-6000
ATTACHMENT
DESIGN SERVICES FOR
EAGLE MOUNTAIN WATER TREATMENT PLANT PHASE IV EXPANSION
CITY PROJECT NO.: 105176
ATTACHMENT A
Scope for Enaineerina Design Related Services for Water and/or Sanitary Sewer
Improvements
DESIGN SERVICES FOR
EAGLE MOUNTAIN WATER TREATMENT PLANT
PHASE IV EXPANSION
AMENDMENT 2
CITY PROJECT NO.: 105176
The scope set forth herein defines the work to be performed by the ENGINEER in
completing the project. Both the CITY and ENGINEER have attempted to clearly define the
work to be performed and address the needs of the Project.
WORK TO BE PERFORMED
Task 1. Design Management - Amended
Task 2. Conceptual Design — Original Contract, No Change
Task 3. Preliminary Design — Original Contract, Amended
Task 4. Equipment Pre -Selection - Amended
Task 5. Final Design — Included
Task 6. Bid Phase Services — Included
Task 7. Construction Phase Services — Not Included
Task 8. Funding and Permitting Assistance - Amended
Task 9. Field Services - Amended
Task 10. Plan Submittal Checklists — Original Contract, No Change
TASK 1. DESIGN MANAGEMENT
ENGINEER shall endeavor to efficiently and effectively use the ENGINEER's and CITY's
time and resources.
ENGINEER shall manage change,
■ communicate effectively,
■ coordinate internally and externally as needed, and
■ proactively address issues with the CITY's Project Manager and others as
necessary to make progress on the work.
1.1. Managing the Team — No change to scope language. Duration is extended through
Final Design and Bid Phase Services.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 07.23.2012
Page 1 of 13
ATTACHMENT
DESIGN SERVICES FOR
EAGLE MOUNTAIN WATER TREATMENT PLANT PHASE IV EXPANSION
CITY PROJECT NO.: 105176
1.2. Communications and Reporting — Additional Scope Items below. The original scope
remains in full effect with extended duration through Final Design and Bid Phase
Services.
• Conduct in -person review meetings with the CITY at the end of each design phase,
for this scope at the Final Design 60%, 90% and Final Design Milestones.
• Conduct an operability and safety review in person a full day review between the
60% and 90% project milestones.
• Conduct a half day in -person meeting to review Control Narratives and Processes
around the 60% design milestone.
• Conduct two-hour virtual progress meetings twice a month to discuss project
progress and design development goals and decisions through Final Design.
• Conduct one -hour virtual progress meetings twice a month during Bid Phase
services.
ASSUMPTIONS
• 14, 2-hour virtual progress meetings during Final Design and six 1-hour virtual
progress meetings during Bid Phase Services
• Two in -person meetings/workshops with City Staff
DELIVERABLES
A. Meeting agendas and meeting summaries for virtual and in -person meetings and
workshops as amended above.
B. Action Item and Decision Log to be maintained through the project.
C. 9 Monthly invoices, M/WBE Reports, and Monthly progress reports
D. Baseline design schedule and monthly schedule updates with schedule narrative
describing any current or anticipated schedule changes
E. Monthly M/WBE Report Form and Final Summary Payment Report Form
TASK 2. CONCEPTUAL DESIGN (10% Design Milestone) — No revisions to original
contract.
TASK 3. PRELIMINARY DESIGN (30% Design Milestone) — No revisions from
Amendment 1.
TASK 4. EQUIPMENT PRE -SELECTION AND PRE -PROCUREMENT
Task 4.1 - Membrane Pre -Selection — No change.
Task 4.2 - Ozonation System Pre -Selection — No change.
Task 4.3 - Electrical Pre -Procurement — Added in Amendment 2.
Large electrical equipment across the country has a lengthy delivery schedule following
receipt of a purchase order that can impact construction schedules. To reduce the overall
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.1.2014
Page 2 of 13
ATTACHMENT
DESIGN SERVICES FOR
EAGLE MOUNTAIN WATER TREATMENT PLANT PHASE IV EXPANSION
CITY PROJECT NO.: 105176
construction schedule risk, the Engineer will prepare pre -procurement documents for long -
lead electrical gear, specifically transformers and switchgear.
Engineer will prepare front end technical specifications and associated drawings and figures
necessary for the pre -procurement of electrical gear to be provided for the EMWTP
expansion design. The proposal documents will include requirements for capital costs and
warranty provisions.
Owner will submit proposal documents to qualified equipment manufacturers. Engineer will
answer questions from the electrical equipment manufacturers, prepare required addenda,
and attend proposal opening.
Engineer will evaluate the received proposals with Owner and provide a recommendation of
award for the pre -selection equipment.
DELIVERABLES:
A. Draft and Final Pre -procurement Proposal Documents. An electronic copy of the
draft and final package will be submitted of these documents for review.
B. Addenda to the documents.
C. Evaluation Spreadsheet Tabulation and Recommendation for Award. Electronic
deliverables only.
Task 4.4 — Plate Settler Pre -Procurement — Added in Amendment 2.
To improve the project schedule and reduce packaging concerns, the Engineer will prepare
pre -procurement documents for plate -settler. Engineer will prepare front end technical
specifications and associated drawings and figures necessary for the pre -procurement of
the plate settlers to be provided for the EMWTP expansion design. The proposal
documents will include requirements for capital costs and warranty provisions.
Owner will submit proposal documents to qualified equipment manufacturers. Engineer will
answer questions from the plate settler manufacturers, prepare required addenda, and
attend proposal opening.
Engineer will evaluate the received proposals with Owner and provide a recommendation of
award for the pre -selection equipment.
DELIVERABLES:
A. Draft and Final Pre -procurement Proposal Documents. An electronic copy of the
draft and final package will be submitted of these documents for review.
B. Addenda to the documents.
C. Evaluation Spreadsheet Tabulation and Recommendation for Award. Electronic
deliverables only.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.1.2014
Page 3 of 13
ATTACHMENT
DESIGN SERVICES FOR
EAGLE MOUNTAIN WATER TREATMENT PLANT PHASE IV EXPANSION
CITY PROJECT NO.: 105176
TASK 5. FINAL DESIGN (60- and 90-PERCENT) AND FINAL CONSTRUCTION
DOCUMENTS (100-PERCENT). — Added in Amendment 2.
Upon approval of the PDR, ENGINEER will develop EMWTP Expansion Project design
documents (plans and specifications) for submittal to TCEQ for approval and for bidding to
General Contractors.
Task 5.1— 60% Plans and Specifications. The plans, opinion of probable construction
cost (prepared in accordance with AACE guidelines), and specifications for the EMWTP
expansion will be completed to a 60% level and submitted to City for review and comment.
The 60% review shall be defined and consist of the minimum level of completion by the
following disciplines:
• Task 5.1.1 — Process Mechanical. This includes General/Standard Sheets (70%),
Process Mechanical design, specification and hydraulics (70%).
• Task 5.1.2 — Instrumentation and Control (I&C): This includes PIDs (90%),
Instrumentation specifications (50%) and control narratives (30%).
• Task 5.1.3 — Structural: This includes structural design drawings and specifications
to 60% level of completion.
• Task 5.1.4 — Geotechnical: This includes geotechnical design and foundation design
calculations advanced to 60% level of completion.
• Task 5.1.5 — Architectural: This includes architectural plans and specification to 60%
level and completion and code analysis to 90%.
• Task 5.1.6 - Building Mechanical. This includes design specifications and drawings
for building mechanical and fire protection to 50% level of completion. This also
includes code analysis to 90%.
• Task 5.1.7— Electrical. This includes design progression for specifications and plans
to 50% level of completion.
• Task 5.1.8 - Civil — This includes civil design for grading, pavement, drainage and
yard piping to 70% of completion for drawings and specifications.
Task 5.1.9 Miscellaneous Design and Quality Tasks: This task includes a 60% cost
opinion, 60% construction schedule, 60% technical review committee and general
specifications, 90% sheet list, 60% constructability review, and 60% red -yellow -green
quality reviews.
Task 5.2 — 90% Plans and Specifications. The plans and specifications for the EMWTP
will be completed to a 90% and submitted to City for review and comment. An OPCC will be
updated at this milestone. The 90% review shall be defined and consist of the minimum
level of completion by the following disciplines:
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.1.2014
Page 4 of 13
ATTACHMENT
DESIGN SERVICES FOR
EAGLE MOUNTAIN WATER TREATMENT PLANT PHASE IV EXPANSION
CITY PROJECT NO.: 105176
• Task 5.2.1 — Process Mechanical. This includes General/Standard Sheets (95%),
Process Mechanical design, specification and hydraulics (95% ).
• Task 5.2.2 — Instrumentation and Control (I&C): This includes PIDs (95%),
Instrumentation specifications (80%) and control narratives (80%).
• Task 5.2.3 — Structural: This includes structural design drawings and specifications
to 90% level of completion.
• Task 5.2.4 — Geotechnical: This includes geotechnical design and foundation design
calculations advanced to 90% level of completion.
• Task 5.2.5 — Architectural: This includes architectural plans and specification to 90%
level and completion and code analysis to 100%.
• Task 5.2.6 - Building Mechanical. This includes design specifications and drawings
for building mechanical and fire protection to 90% level of completion. This also
includes code analysis to 100%.
• Task 5.2.7— Electrical. This includes design progression for specifications and plans
to 80% level of completion.
• Task 5.2.8 - Civil — This includes civil design for grading, pavement, drainage and
yard piping to 95% of completion for drawings and specifications.
• Task 5.2.9 Miscellaneous Design and Quality Tasks: This task includes a 90% cost
opinion, 90% construction schedule, 90% technical specialist review of
specifications, 100% sheet list, 90% constructability review, and 90% red -yellow -
green quality reviews.
Task 5.3 — Final Plans and Specifications. The plans and specifications for the EMWTP
expansion will be finalized based on comments from City. An OPCC will be updated at this
milestone. Engineer shall update plans and specifications with any final comments prior to
finalizing for Construction. Engineer will seal and sign the completed documents.
• Task 5.3.1 — Process Mechanical: This includes General/Standard Sheets (95%),
Process Mechanical design, specification and hydraulics (100% ).
• Task 5.3.2 — Instrumentation and Control (I&C): This includes PIDs (100%),
Instrumentation specifications (100%) and control narratives (100%).
• Task 5.3.3 — Structural: This includes structural design drawings and specifications
to 100% level of completion.
• Task 5.3.4 — Geotechnical: This includes geotechnical design and foundation design
calculations advanced to 100% level of completion.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.1.2014
Page 5 of 13
ATTACHMENT
DESIGN SERVICES FOR
EAGLE MOUNTAIN WATER TREATMENT PLANT PHASE IV EXPANSION
CITY PROJECT NO.: 105176
• Task 5.3.5 — Architectural: This includes architectural plans and specification to
100% level and completion and code analysis to 100%.
• Task 5.3.6 - Building Mechanical: This includes design specifications and drawings
for building mechanical and fire protection to 100% level of completion. This also
includes code analysis to 100%.
• Task 5.3.7— Electrical. This includes design progression for specifications and plans
to 100% level of completion.
• Task 5.3.8 - Civil — This includes civil design for grading, pavement, drainage and
yard piping to 100% of completion for drawings and specifications.
• Task 5.3.9 - Miscellaneous Design and Quality Tasks: This task includes a 100%
cost opinion, 100% construction schedule, 100% technical specialist review of
specifications, 100% sheet list.
ASSUMPTIONS
• Owner will return to the Engineer one set of consolidated comments within two
weeks of submittal.
CDM Smith assumes the control system network design for the Phase 4 expansion
facilities will be an isolated extension with a dedicated fiber optic network connection
directly to the existing plant SCADA control system network. No additional external
or outside connections will be provided for this network extension. The new network
connection point will be to an existing network port in the Phase 3 network room as
directed by the City. CDM Smith has not included any engineering efforts for
assessment or evaluation of the existing SCADA system network architecture with
regards to cybersecurity or access of outside communications to the existing network
system. CDM Smith assumes any required cybersecurity effort to connect and
protect the new Phase 4 network to the existing network will be performed by
internally by the City with their own resources in accordance to internal policies and
procedures.
CDM Smith cost opinions will follow the AACE International cost estimating
guidelines for the appropriate milestone submittal.
DELIVERABLES
A. Five sets of 1/2-size drawings and five specifications will be delivered for the 60-percent
design package.
B. Five sets of 1/2-size drawings and five specifications will be delivered for the 90-percent
design package.
C. Five sets of/2-size drawings and five specifications will be delivered for the 100-percent
Design package.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.1.2014
Page 6 of 13
ATTACHMENT
DESIGN SERVICES FOR
EAGLE MOUNTAIN WATER TREATMENT PLANT PHASE IV EXPANSION
CITY PROJECT NO.: 105176
D. A DWF file for the 100% Design will be created from design CAD drawings and will be
uploaded to the project folder in.
E. Detailed opinion of probable construction costs at 60-, 90- and 100-percent designs.
F. Original cover mylar for the signatures of authorized CITY officials.
TASK 6. BID PHASE SERVICES. — Added in Amendment 2.
ENGINEER will support the bid phase of the project as follows.
6.1 Bid Support
• The ENGINEER shall upload all plans and contract documents onto the City's
web -based document management system (e-Builder) for access to potential
bidders.
• Contract documents shall be uploaded in a .xIs file.
• Plan Sets are to be uploaded to e-Builder in two formats, .pdf and AM files.
The .pdf will consist of one file of the entire plan set. The AM will consist of
individual files, one for each plan sheet, and will be numbered and named in
a manner similar to that of the plan set index.
• The ENGINEER shall sell contract documents and maintain a plan holders list on
e-Builder from documents sold and from Contractor's uploaded Plan Holder
Registrations in e-Builder.
The ENGINEER will develop and implement procedures for receiving and
answering bidders' questions and requests for additional information. The
procedures shall include a log of all significant bidders questions and requests
and the response thereto. The log shall be housed and maintained in the
project's e-Builder folder titled Request for Information. The ENGINEER will
provide technical interpretation of the contract bid documents and will prepare
proposed responses to all bidders' questions and requests, in the form of
addenda. The ENGINEER shall upload all approved addenda onto e-Builder and
mail addenda to all plan holders.
• Attend the prebid conference in support of the CITY.
• Assist the CITY in determining the qualifications and acceptability of prospective
contractors, subcontractors, and suppliers.
• When substitution prior to award of contracts is allowed in the contract
documents, the ENGINEER will advise the CITY as to the acceptability of
alternate materials and equipment proposed by bidders.
• Attend the bid opening in support of the CITY.
• Tabulate and review all bids received for the construction project, assist the CITY
in evaluating bids, and recommend award of the contract. A copy of the Bid
Tabulation and the CFW Data Spreadsheet created utilizing CFW Bidtools only
are to be uploaded into the project's Bid Results folder on e-Builder.
6.2 Final Design Drawings
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.1.2014
Page 7 of 13
ATTACHMENT
DESIGN SERVICES FOR
EAGLE MOUNTAIN WATER TREATMENT PLANT PHASE IV EXPANSION
CITY PROJECT NO.: 105176
• Final Design Drawings shall be submitted in both Adobe Acrobat PDF format
(version 6.0 or higher) format and DWF format. There shall be one (1) PDF file
and one (1) DWF file for the TPW plan set and a separate PDF and DWF file for
the Water plan set. Each PDF and DWF file shall be created from the original
CAD drawing files and shall contain all associated sheets of the particular plan
set. Sinqular PDF and DWF files for each sheet of a plan set will not be
accepted. PDF and DWF files shall conform to naming conventions as follows:
8. TPW file name example — "W-1956—org47.pdf" where "W-1956" is the
assigned file number obtained from the CITY, "_org" designating the file is
of an original plan set, "47" shall be the total number of sheets in this file.
Example: W-0053_org3.pdf and K-0320_org5.pdf
II. Water and Sewer file name example — "X-35667_org36.pdf" where "X-
35667" is the assigned file number obtained from the CITY, "_org"
designating the file is of an original plan set, "36" shall be the total number of
sheets in this file.
Example: X-12755_org18.pdf
Both PDF and DWF files shall be uploaded to the project's Final Drawing folder in
e-Builder.
2) In addition to the PDF and DWF files, the ENGINEER shall submit each plan sheet
as an individual DWG file with all reference files integrated into the sheet. If the plans
were prepared in DGN format, they shall be converted to DWG prior to uploading.
The naming convention to be used for the DWG files shall be as follows:
8. TPW files shall use the W number as for PDF and DWF files, but shall
include the sheet number in the name — "W-1956_SHT01.dwg", "W-
1956_SHT02.dwg", etc.
II. Water and Sewer file names shall use the X number as for PDF and
DWF files, but shall include the sheet number in the name — "X-
12155_SHT01.dwg", "X-12755_SHT02.dwg", etc.
For information on the proper manner to submit files and to obtain a file number for
the project, contact the Department of Transportation and Public Works Vault at
telephone number (817) 392-8426. File numbers will not be issued to a project
unless the appropriate project numbers and fund codes have been assigned and
are in the Department of Transportation and Public Works database.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.1.2014
Page 8 of 13
ATTACHMENT
DESIGN SERVICES FOR
EAGLE MOUNTAIN WATER TREATMENT PLANT PHASE IV EXPANSION
CITY PROJECT NO.: 105176
ASSUMPTIONS
• The project will be bid only once and awarded to one contractor.
• 10 sets of construction documents will be sold to and made available on e-
Builder for plan holders and/or given to plan viewing rooms.
• 10 sets of 1/2 size and 5 sets of full size drawings and 10 specifications
(conformed, if applicable) will be delivered to the CITY.
• PDF, DWF and DWG files will be uploaded to e-Builder.
DELIVERABLES
A. Addenda
B. Bid tabulations
C. Recommendation of award
D. Construction documents (conformed, if applicable)
TASK 7. CONSTRUCTION PHASE SERVICES — Not Included.
TASK 8. PERMITTING AND FUNDING COORDINATION —Amended as follows.
ENGINEER will coordinate with the following permitting and funding stakeholders for this
project:
• Texas Water Development Board (TWDB) — For project funding.
• Texas Commission on Environmental Quality (TCEQ) — To obtain approvals for the
EMWTP expansion and necessary exceptions to the Rules and Regulations.
• Please note that coordination activities with these agencies will extend past the PDR
completion deadlines and into the Final Design schedule and future amendment
work.
8.1 Stakeholder Coordination Meetings — Modified in Amendment 2.
Coordinate with the identified agencies and entities as necessary for the design of the
proposed infrastructure and provide and obtain information needed to prepare the design.
This includes two coordination meetings with TCEQ (one near the start of the project, one at
30% design) and TWDB.
With respect to coordination with permitting authorities, ENGINEER shall communicate with
permitting authorities such that their regulatory requirements are appropriately reflected in
the designs. ENGINEER shall work with regulatory authorities to obtain approval of the
designs, and make changes necessary to meet their requirements, as part of the design
scope.
8.2 PDR Submittal — No change from original scope.
8.3 CT Study — No change from original scope.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.1.2014
Page 9 of 13
ATTACHMENT
DESIGN SERVICES FOR
EAGLE MOUNTAIN WATER TREATMENT PLANT PHASE IV EXPANSION
CITY PROJECT NO.: 105176
8.4 Membrane System Approval — Added in Amendment 2.
CITY will procure additional membrane equipment for installation as part of the EMWTP
expansion.
ENGINEER will coordinate with the selected membrane filter manufacturer to obtain
operating parameters of the new system and submit necessary information to TCEQ for
approval. The parameters and operations to be confirmed include: number of membrane
units and modules installed; square footage of modules; pre-treatment train processes;
membrane backwash cycle procedure; membrane enhanced filtrate maintenance wash
procedure; minimum membrane chemical CIP frequency and duration; and filtrate flux rate.
ENGINEER will also confirm membrane rack and module characteristics and properties
related to direct integrity testing (DIT) calculations. This information will be submitted to
TCEQ for approval.
8.5 Final Design Submittal — Added in Amendment 2.
Engineer will review and submit documents to be in compliance with Texas Commission on
Environmental Quality (TCEQ) Rules and Regulations. Engineer will meet with TCEQ in
Austin as part of Task 7.1 to review specific critical design items for the Eagle Mountain
WTP to facilitate timely review and approval. Upon receipt of plan review comments,
ENGINEER will respond in writing and make necessary changes to the contract documents
and resubmit a 100-percent set of signed and sealed bid documents.
8.6 TDLR Submittal - Added in Amendment 2.
Engineer will submit documents to TDLR for review of the administrative spaces for review
of applicable areas of the project.
8.7 Environmental Permitting and TWDB Report Documents - Added in Amendment
1. No change here.
8.8 Fort Worth Development Services - Added in Amendment 2.
The Consultant will coordinate with the City of Fort Worth Development Services in order to
meet the required criteria for site development of the EMWTP site. This scope includes
coordination of the following:
A. Perform drainage study for the existing drainage channel and up to two (2)
alternatives and stormwater retention basin. Submit draft and final iSWM plan to
the City of Fort Worth.
B. Infrastructure Plan Review Center coordination and review documents in
accordance with City requirements
C. Urban Forestry review, coordination and permitting
D. Stormwater quality design and coordination meeting requirements of
Development Services
E. Documentation to facilitate a grading permit by the Contractor
The Consultant is not responsible for building permits or other permitting with the City of Fort
Worth Development Services outside these listed.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.1.2014
Page 10 of 13
ATTACHMENT
DESIGN SERVICES FOR
EAGLE MOUNTAIN WATER TREATMENT PLANT PHASE IV EXPANSION
CITY PROJECT NO.: 105176
TASK 9. FIELD SERVICES — Amended as follows.
Task 9.1 Geotechnical Engineering — No change from original contract.
Task 9.2 Survey and Subsurface Utility Engineering Services. — No change from original
contract.
Task 9.3 — Physical Modelling — Added in Amendment 2.
Physical modelling for Membrane Feed Pumps and Biologically Activated Filter Backwash
Pumps will be provided to verify the design geometry of the Backwash Tank and Pump
Inlets will be compliant with Hydraulic Institute Standards. The scope includes building a
physical, scaled model of the design and testing the model with dye -testing and other
methods to evaluate performance and minimum, average, and maximum day flows.
Recommendations for changes to the Break Tank Geometry or other measures to provide
optimized flow distribution to the pumps will be provided to guide the completion of design.
DELIVERABLES
A. An electronic draft and final report regarding the testing performed and
recommended results of the physical modelling. A video of the testing will also
be made available to Owner for their records.
TASK 10. PLAN SUBMITTAL CHECKLISTS — Not included.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.1.2014
Page 11 of 13
ATTACHMENT
DESIGN SERVICES FOR
EAGLE MOUNTAIN WATER TREATMENT PLANT PHASE IV EXPANSION
CITY PROJECT NO.: 105176
ADDITIONAL SERVICES NOT INCLUDED IN THE EXISTING SCOPE OF SERVICES
Additional Services not included in the existinq Scope of Services — CITY and
ENGINEER agree that the following services are beyond the Scope of Services described in
the tasks above. However, ENGINEER can provide these services, if needed, upon the
CITY's written request. Any additional amounts paid to the ENGINEER as a result of any
material change to the Scope of the Project shall be agreed upon in writing by both parties
before the services are performed. These additional services include the following:
• Equipment Pre -procurement and Pre -selection other than ozone and membrane
equipment
• Construction and Start-up Services for the Project.
• Conformed Documents after Bid Phase
• Any design work or confirmation of Raw Water Pump station hydraulics and capacity
past the Conceptual Design Report.
• Public Information Meetings and Renderings
• Permitting Activities and Funding Support past the Bid Phase Services
• Negotiation of easements or property acquisition including temporary right -of -entries.
• Services related to development of the CITY's project financing and/or budget.
• Services related to disputes over pre -qualification, bid protests, bid rejection and re-
bidding of the contract for construction.
• Construction management and inspection services
• Design phase public meetings, unless otherwise shown in the Scope of Work.
• Performance of materials testing or specialty testing services.
• Services necessary due to the default of the Contractor.
• Services related to damages caused by fire, flood, earthquake or other acts of God.
• Services related to warranty claims, enforcement and inspection after final
completion.
• Services related to submitting for permits in excess of Task 8
• Services related to Subsurface Utility Engineering
• Services related to Survey Construction Staking
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.1.2014
Page 12 of 13
ATTACHMENT
DESIGN SERVICES FOR
EAGLE MOUNTAIN WATER TREATMENT PLANT PHASE IV EXPANSION
CITY PROJECT NO.: 105176
• Services related to acquiring real property including but not limited to easements,
right-of-way, and/or temporary right -of -entries.
• Services to support, prepare, document, bring, defend, or assist in litigation
undertaken or defended by the CITY.
• Services related to the preparation of Texas Water Development Board (TWDB)
State Revolving Fund (SRF) loan documents or administering an SRF loan during
design or construction outside of those described in Task 8 above.
• Performance of miscellaneous and supplemental services related to the project as
requested by the CITY.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.1.2014
Page 13 of 13
0
w
m
e.B...L..+R
e000.
e...... ....
00 " .om �0000Q000
o��o o o1. Rl. o000o
y
eoo
eoo
7�0000M000�
Q0000„000R
'" '"
7000
o:0000 .I.o .000000
„
00
e.o
e.l.
R�0000r000p
m0000�000„
ry0000R000C
.I.. .......
..I m
_..
...q....g...„
�....g.o.„
,.�.o..
RI. . .I< ... .......
..
..
--.00
eol000�00000�
goo�00000�
moo,`�o
oo. .......
v
u Z
a p w
o
�00300.o
eoo e000ci
mr m nZ
olo
RCo
r o00 . Boo800
oB
yoogo
o� .mo .000p
of �
x c
of
Ra'u
�r
olo
�M
a o0o m Roo�oo
080000
„„ e000.
w
S.R
���0000�000
N�000
o8mm �.8 .000p
T
=al
:e000
eolo
�q„0000S000
�r00008�000
,�.,00000R...
^..
I S
'=o
•no
7
:90�8000008 . o
ryo.�o 00
08
�
Boo+o
.0000
000p{`�
1 I^
8
s
...........
.........
..........
sB
a m E eel
2
em
x
E
c
c
g
„4d
«alo
?ddFdFFddF �Fdd��d�id
dd!?ddFdF
`ad `d#%d4d
«al
EXHIBIT B-2
Level of Effort Spreadsheet
TASK/HOUR BREAKDOWN
Design Services for
Eagle Mountain Phase IV Expansion - Amendment No. 2
City Project No. 105176
rw: a
ieam momue (JJ 0 0 0 3z
t 2a6,730 s
I mauan camonw oavaamll o 0 0 o
s z6,96�yt
�Pw;aeuP�curemPchxurtmem a l a l a �� D l a IL D I
ashs,�
J
T ok�rl%lo ^pm-so.9o, wos[mnmumlon
oawmann
�
3r,u>—S _ rpoa.9�15
o vk �kscenfimums
procex me< ni
5 zsspai 5
racksTasks lz
racks l3
IaL
5 5
s s
racks 2a
cai 1
��
coo
5 5
lrali)Js
racks is
racks 27
sullai
k
s
5 s3.sod5
T 111
w7luellaneous 1—ana ouallry racks 1s z6 1s a s 12 o e 1 as o eo
1ss1
5 am.os� s
I
rars.z Saw rma,amsa«m ma,
s 3. Gs
rack s z 1
smress raec nl
Isf
lz.
s =cz.zj s
Tasks za
or.ssoo�ddJS
Tasks x6
Tasks z 7
I Tasks xs
smlai<�
M—
11
Miscellaneous D.-ana-1a mocks o 35 16 5 a 21 a a eo as o sa
x
1526
5 s'.rof
5 388.3 15
Tasks 3l sra«ss mec ni 5 L1— 5
I Tasks 33 a laL 5 1.ae�)J 5
Tasks 34 1 5 7.x3d 5
Tasks 3s sullai mraLI "Io o o o o o
_ s .o li))s
Tasks 37 k 5 ws.saJS
. 111 mla�Ilaa�oaaDaam�aaaDaamvmaka S 26 16 9 o , a o 6a ao o as 1176 s z27.13d s
71
I'a=k6 9aak 5emcea Daa,kaD,.w° II D D a 1x 1 D o D oOo D D 5 x1.
71
�Ti`keaz mmeane wnaliu mominanan sea naeeemasJ S 2s $
—1, 7n vmmAonravalll/) $ 9..11 $
Iran: a7 o,<. n�mmre I s�z.eJJ
ITaakSa fiev s 39.240� lase. o 0 0 0 0
rn siml naoeeivaa sonT 716 sae 1538 13sa 114 22a 2ao - 1xo H. ssa 3993 I S 1.6a5.52�15
63,6s2ows sLaaoarls 6.z3z ss 5 s zaaascs
5
used 5 I s s 5 - I S u3,23s/ 5
2}un61.77 5
0 5
Lw3 se`o0
+9 931 57.,S
'As
eaPS1A1195
9, x S
30 221v
c
5
3s,aaQ 5
1.8sJ 5
5
5
6250
6,2Df 5
5
eas 5
07 5
6E3!
- 5
5
J 5
�Lx9( 9$
e.aD%
- s
- s
- s
21,..d s
:J s
43s :os6
3.73E-s
:ems
i�aaD6
$
41.75� $
26,006 s
ssa,f s
o9,<!
s
s
307.30Y
- 5
-
s
5 2—d 5 26,0�, 5 4u.34d
2�S
io,
5
5 x2.
.ozd
2 7.2xJ s
- s
7
6
$ 7
s -
s
s
s
s
s "d
26.oDss E6,
13
Is 3.13d
5,a 6
9. 09 L93ii
3s. I5
5 aaaaoo115
AJ
�15
5 f
's.Da((15
s .eS
- 5
5 s.uuJ�S
77:Z
s
s
oaGl
5 21s.5
s` xos6
$
s
$
5 6.999
5 26.z
s 6
s
-
- s
-
s
s
s
$ .Sab
• Tofal Hours
39,939
Total Labor
$7.645.920
Total E qqpp
MBE/SBE Subwnsultant
$3.504.433
1 451 957
Non-MBE/SBE Subconsul[ant
1.796.241
5% Sub Marlcu0.
163.235
MBE/SBE Paniu' lion
13.0%
Total Proled Cosl
$11,149,078
s -,74d
303ZZL—s IS 3Lu3.mQ
'01th
Page 2 of 2
II
I
I
I
I
I
I
I
I
I
V7m�;
Professional Services Invoice Project Manager: (James McDonald
Project: IEa �lle Mountain Water Treatment Plant Expansion
City Project #: 110517$ 1
City Sec Number: 161189
Company Name: ICDM Smith, Inc.
Supplier's PM: 1Stewart, Sarah PE
Supplier Invoice #: 1
Payment Request #: 1
Service Date:From 1
Service Date:To 1
Invoice Date: 1
Summary
1 Supplier Instructions:
Fill in green cells including Invoice Number, From and To Dates and the included worksheets.
When your Invoice is complete, save and close, start Buzzsaw and Add your invoice to the
Consultant folder within Project's folder.
1 email: stewartsa(a)cdmsmith.com I
1 Office Address 801 Cherry Street, Unit 33, Suite 1820, Fort Worth, Texas 76102
1 Telephone: 1816-412-3129 1
1 Fax: I I
I
1 Remit Address:115036 CollectionsCenter Drive, Chicago, IL 60693
Sheet FID and Work Type Description
Work Type 1 Water Treatment Design 56022-0600430-5330500-105176-001430
Work Type 2
Work Type 3
Work Type 4
Work Type 5
Work Type 6
Totals This Invoice
Agreement LTD
Agreement Amendment Amount to Completed Percent ($) Invoiced Current
Amount Amount Date Amount Spent Previously Invoice
$3,695,990.00 $11,149,078.00 $14,845,068.00 $3,302,906.68 22.24918525% $3,302,906.68
$3.695.990.00 $11.149.078.00 $14.845.068.00 $3.302.906.68
Overall Percentage Spent: 22.24918525%
$3.302.906.68
Remaining
Balance
$11,542,161.32
$11.542.161.32
Professional Services Invoice Project Manager: James McDonald
Project: Eagle Mountain Water Treatment Plant Expansio
City Project #: 105176
Work Type Desc: Water Treatment Design Supplier Instructions:
FID: 56022-0600430-5330500-105176-001430
City Sec Number: 61189 Fill in green cells including Percent Complete and Invoiced Previously Quanities
Purchase Order: I FW060-0000027988 I When your Invoice is complete, save and close, start Buz saw and Add your invoice to the
Consultant folder within Project's folder.
Company Name: CDM Smith, Inc
Supplier's PM: Stewart, Sarah PE
Supplier Invoice #:
Payment Request #:
Service Date:From
Service Date:To
Invoice Date:
email: stewartsa@cdmsmith.com
Office Address: 801 Cherry Street, Unit 33, Suite 1820, Fort Worth, Texas 76102
Telephone: 816-412-3129
Fax:
Remit
Pay Items
Description
30 - Design Water Treatment Design
30 - Design Water Treatment Design - Final Design
through Bid Phase Services
15036 CollectionsCenter Drive, Chicago, IL 60693
Agreement
LTD
Agreement
Amendment
Amendment Amount to
Completed
Percent
Amount
Number
Amount Date
Amount
Spent
$3,695,990.00
1 ($0 Amendment)
$ - $3,695,990.00
$3,302,906.68
89.36460002%
2
$11,149,078.00 $11,149,078.00
($) Invoiced Current
Previously Invoice
$3,302,906.68
Remaining
Balance
$393,083.32
$11,149,078.00
Totals This Unit: $3,695,990.00 $11.149.078.00 $14.845.068.00 $3,302,906.68 $3,302,906.68 $11,542,161.32
Overall Percentage Spent: 22.24918525%
City of Fort Worth, Texas
Mayor and Council Communication
DATE: Tuesday, August 27, 2024 REFERENCE NO.: **M&C 24-0729
LOG NAME: 60EAGLEMWTPEXPA2-CDM
SUBJECT:
(CD 7)Authorize Execution of Amendment No. 2 in the Amount of $11,149,078.00 to an Engineering
Agreement with CDM Smith, Inc. for the Final Design of the Eagle Mountain Water Treatment Plant 35
Million Gallons per Day Expansion and Adopt Appropriation Ordinance to Effect a Portion of Water's
Contribution to the Fiscal Years 2024- 2028 Capital Improvement Program
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize execution of Amendment No. 2 to an Engineering Agreement with CDM Smith, Inc. in the
amount of $11,149,078.00.00 for the Final Design of Eagle Mountain Water Treatment Plant 35
Million Gallons per Day Expansion and Pump Station 2 project (City Project No. 105176) for a
revised contract amount of $14,845,068.00; and
2. Adopt the attached appropriation ordinance adjusting estimated receipts and appropriations in the
Water & Sewer Revenue Bonds Series 2024 Fund by increasing estimated receipts and
appropriations in the Final Design of Eagle Mountain Water Treatment Plant 35 Million Gallons per
Day Expansion and Pump Station 2 project (City Project No. 105176) in the amount
of $11,395,918.00 and decreasing estimated receipts and appropriations in the W&S Commercial
Paper project (City Project No. UCMLPR) by the same amount, to effect a portion of Water's
contribution to the Fiscal Years 2024-2028 Capital Improvement Program.
DISCUSSION:
On February 27, 2024, Mayor and Council Communication (M&C 24-0172), the City Council authorized
an engineering agreement in the amount of $3,695,990.00 with CDM, Smith Inc. (City Secretary Contract
No. 61189) for the Preliminary design of the Eagle Mountain Water Treatment Plant 35 Million Gallons per
day (MGD) expansion project.
The agreement was subsequently revised by Amendment No. 1 with a net total amount of $0.00
administratively authorized on July 16, 2024 that allowed for replacing the work task for unit process
evaluation with the work task for Environmental Permitting and Texas Water Development Board report
document.
This Mayor and Council Communication (M&C) is to authorize the final Design of Eagle Mountain Water
Treatment Plant 35 MGD Expansion and Pump Station 2 project. The proposed expansion project will
increase the plant's design capacity from between 35 and 50 million gallons per day and master plan the
site for a future ultimate build out of 200 million gallons per day.
CDM Smith, Inc., proposes to provide the necessary services for a fee not to exceed $11,149,078.00. Staff
considers the proposed fee to be fair and reasonable for the scope of services proposed.
In addition to the contract amount, $246,840.00 is required for staff project management costs.
It is the practice of the Water Department to appropriate its CIP plan throughout the Fiscal Year (FY),
instead of within the annual budget ordinance, as projects commence, additional funding needs are
identified, and to comply with bond covenants. The actions in the M&C will appropriate funds in support of
the Water's portion of the City of Fort Worth's Fiscal Years 2024-2028 Capital Improvement Program.
Funding for the Preliminary Design of Eagle Mountain Water Treatment Plant 35 MGD Expansion and
Pump Station 2 project is depicted below:
60EAGLEMWTPEXPA2-CDM
Capital
Fund Project Name
Name
4"�Y1Mi
W&S 105176-
Rev EMWTP35MGDEXP
Bonds Series AND PS2
2024
FY2024 CIP Authority Budget Change
Appropriations (Increase/Decrease)
Revised
FY2024
Budget
$3,757,990.00 This M&C $11,395,918.00 $15,153,908.00
Funding is budgeted in the Commercial Paper project within the W&S Rev Bonds Series 2024 Fund for
the purpose of funding the EMWTRP 35MGD EXPAND PS2 project.
Funding for the Design of EMWTRP 35MGD EXP. AND PS2 project is depicted below:
Fund Existing Additonal Project Total*
Appropriations Appropriations
W&S Rev
Bonds Series
Bond Fund $3,757,990.00 $11,395,918.00 $15,153,908.00
56022
Project Total I $3,757,990.00 $11,395,918.0011$15,153,908.00
*Numbers rounded for presentation purposes.
This project will have no impact on the Water Department's operating budget when complete.
Business Equity: CDM Smith, Inc. agrees to maintain its initial M/WBE commitment of 10 percent that it
made on the original agreement and extend and maintain that same M/WBE commitment of 10 percent to
all prior amendments up to and inclusive of this Amendment No. 2. Therefore CDM Smith, Inc. remains in
compliance with the City's M/WBE Ordinance and attests to its commitment by its signature on the
Acceptance of Previous M/WBE Commitment form executed by an authorized representative of its
company.
The project is located in COUNCIL DISTRICT 7.
FISCAL INFORMATION / CERTIFICATION:
The Director of Finance certifies that funds are currently available in the Commercial Paper project within
the W&S Rev Bonds Series 2024 Fund and upon approval of the above recommendations and adoption of
the attached appropriation ordinance, funds will be available in the W&S Rev Bonds Series 2024 Fund for
the EMWTRP 35MGD EXP. AND PS2 project to support the above recommendations and execution of the
amendment. Prior to an expenditure being incurred, the Water Department has the responsibility of
verifying the availability of funds.
FUND IDENTIFIERS (FIDs).:
TO
Department IAccounti Project
Programll ctivityl
Budget I
Reference #
mount
(Fund
ID I
ID
l
Year
(Chartfield 2)
FROM
Fund
Department
Account Project
Programl
ctivity
Budget
Reference #
l�mount!
ID
I
I ID
I
Year f
(Chartfield 2)
CERTIFICATIONS:
Submitted for City Manager's Office by.
Originating Department Head:
Additional Information Contact:
Fernando Costa (6122)
Chris Harder (5020)
James McDonald (4982)
ATTACHMENTS
1. 60EAGLEMWTPEXPA2-CDM FID TABLE.xlsx (CFW Internal)
2. 60EAGLEMWTPEXPA2-CDM Map.pdf (Public)
3. 60EAGLE MWTPEXPA2-CDM.docx (CFW Internal)
4. Acceptance of Previous MWBE Committment Form (APCF) 2021
5. Entitvinformation CDM Smith., Inc..pdf (CFW Internal)
6. Form 1295 Certificate FtWorth EMWTP Ph IV Amend 2 JV.pdf
7.ORD.APP 60EAGLEMWTPEXPA2-CDM 56022 AO24(r2).docx
(38) 10%.pdf (CFW Internal)
(CFW Internal)
(Public)
60EAGLEMWTPEXPA2-CDM FID TABLE
2 and 3) 56022 0600430 5110101 105176 001430 9999 $246,840.00 Staff Costs
1 56022 0600430 5330500 105176 001430 9999 $11,149,078.00 Contract