Change Order Request
Project Name:
Project No.(s):�
Project Description:
Contractor:
City Project Mgr.1
Phone Number:I
Lake Arlington Lift Station Sanitary Sewer Gravity Mains I City Sec No.: 1 58322
56021/0700430/001480 1 NTP I N/A I City Proj. No.: l 101311
Construction of a new gravity sanitary sewer main upstream of Lake Arlington Lift Station (South Line) and downstream of
Lake Arlington Force Main (North Line)
S.J. Louis Construction of Texas, Ltd Change Order # 3 I Date:
April Rose Escamilla City Inspector: Shane Behn
817-392-8455 Phone Number: 817-392-2190
Dept. I Base Bid Alternate-B I Totals
Original Contract Amount
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date
Amount of Proposed Change Order
Revised Contract Amount
Original Funds Available for Change Orders
Remaining Funds Available for this CO
Additional Funding (if necessary)
$15,059,130.11 $1,494,410.00
$788,958.94
$807,600.00
$16,553,540.11
$788,958.94
$807,600.00
$15,848,089.05
$686,810.00
$16,534,899.05
-$14,735.69
$14,735.69
$0.00
$15,833,353.36
$701,545.69
$16,534,899.05
$248,303.00
0.00
$248,303.00
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT -0.11 %
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%) $20,691,925.14
JUSTIFICATION (REASONS) FOR CHANGE ORDER
9/6/2024
Contract Time
(Callender days)
we
Change Order No. 3 provides for the following:
• The acquisition and hauling of materials (items 70-72; 75-80; 82-83) for junction structures that were removed from this project scope due
to Oncor not relocating its facility in time to allow for the construction of these appurtenances. The materials included in this change order will
be used in future construction projects CPNs 100995 and C01961 that will incorporate the proposed design of the junction structures.
• The installation of 42-inch, 60-inch and 66-inch end caps (items 38, 42, 48, 50, 73, 74, and 80) for the installed sewer pipe. The end caps
are needed due to the removal of the junction structures from the project scope.
• The deletion of pay item quantities that are no longer necessary on the project.
Staff concurs for the constractor's request for an additional 190 days of the project for the numerous modifications to the original plans that
were necessary during construction of the project.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full (both time and money) for all costs arising out of, or incidental to, the above Change Order.
Contractor's Company Name Contractor Name I fi..&ntractoif ignature Date
S.J. Louis Construction of Texas, Ltd Adam Lunsford I of 4111L
Dii ector (Wat r Dept) donstruction Supervisor (Water Dept)11
christapher /� r �Tr T 5 Sep 17, 2024
Assistant City A orney '�' a e Is an anag -
- Sep 17, 2024 1 - I Sep 17, 2024
Council Action (If Required) OFFICIAL RECORD
M&C Number N/A M&C Date Approved N/A CITY SECRETARY
FT. WORTH, TX
FORT "RTH City of Fort Worth
Change Order Additions
Project Name Lake Arlington Lift Station Sanitary Sewer Gravity Mains
City Sec No.:
58322
Project No.(s): 56021/0700430/001480 1 DOE No.1 N/A
City Proj. No.:
101311
Project
Construction of a new gravity sanitary sewer main upstream of Lake Arlington Lift Station (South Line)
and downstream
of
Description
Lake Arlington Force Main (North Line)
Contractor S.J. Louis Construction of Texas, Ltd Change Order: 0
Date: 1 9/6/2024
City Project Mgr. April Rose Escamilla City Inspector I Shane Behn
ADDITIONS
DEPT
I Qty
JUnit
JUnit Cost I
Total
38 Wire Mesh Fence, Metal Posts (16' Welded Wire Cattle Panels w/ T-Posts) Base Bid 257.00 LF
$25.00
$6,425.00
42 Seeding, Hydromulching Base Bid 90.00 SY
$0.60
$54.00
48 Trench Safety Base Bid 219.00 LF
$0.01
$2.19
50 Imported Embedment/ Backfill, CLSM Base Bid 18.00 CY
$200.00
$3,600.00
70 66" SN 72 Fiberglass Sewer Pipe 25 PSI (20' Joint) (Material Only) Base Bid 20.00 LF
$447.35
$8,947.00
71 42" SN 72 Fiberglass Sewer Pipe 2S PSI (20' Joint) (Material Only)
Base Bid 20.00 LF $241.50 $4,830.00
72 36" SN 72 Fiberglass Sewer Pipe 25 PSI (20' Joint) (Material Only)
Base Bid
40.00
LF
$195.50
73 66" End Cap (Material and Installation Cost)
Base Bid
1.00
EA
$5,207.57
74 42" End Cap (Material and Installation Cost)
Base Bid
1.00
EA
$3,796.93
75 5' Manhole (Material Only)
Base Bid
1.00
LS
$11,271.15
76 North Line Frame, Cover, and Accessories (Material Only)
Base Bid
1.00
LS
$43,212.40
77 North Stop Log, Guide Frame, and Accessories (Material Only)
Base Bid
1.00
LS
$186,507.00
78 Rebar and Steel Fabrication (Material Only)
Base Bid
1.00
LS
$90,631.50
79 60" SN72 Fiberglass Sewer Pipe 25 PSI (2-20' Joints) (Material Only)
Base Bid
28.00
LF
$424.35
80 60" 25 PSI Elbow, 3 Miter (Material Only)
Base Bid
1.00
EA
$12,908.75
81 60" End Cap (Material and Installation Cost)
Base Bid
1.00
EA
$5,106.00
82 5' Type A Manhole (Material Only)
Alternate-B
1.00
EA
$14,735.69
83 South Line Frame, Cover, and Accessories (Material Only)
Base Bid
1.00
LS
$8,684.80
lBase Bid
lAlternate-B
$7,820.00
$5,207.57
$3,796.93
$11,271.15
$43,212.40
$186,507.00
$90,631.50
$11,881.80
$12,908.75
$5,106.00
$14,735.69
$8,684.80
$410,886.09
$14,735.69
Page 1 of 3 lAdditions Sub Total 1$425,621.78
FC]12T WoRTH City of Fort Worth
Change Order Deletions
Project Name I Lake Arlington Lift Station Sanitary Sewer Gravity Mains City Sec No.: 58322
Project No.(s): I 56021/0700430/001480 1 DOE No. I N/A City Proj. No.: 101311
Project Description I Construction of a new gravity sanitary sewer main upstream of Lake Arlington Lift Station (South Line) and
downstream of Lake Arlington Force Main (North Line)
Contractor I S.J. Louis Construction of Texas, Ltd Change Order: � Date I 9/6/2024
City Project Mgr. I April Rose Escamilla City Inspector: I Shane Behn
DELETIONS
ITEM IDESCRIPTION I DEPT I Qty JUnit I Unit Cost ITotal
3 66" Fiberglass Sewer Pipe (Class SN 72) (With Acceptable Backfill) Base Bid 20.00 LF $1,098.00 $21,960.00
4 60" Fiberglass Sewer Pipe (Class SN-72) (With Acceptable Backfill) Base Bid 20.00 LF $1,118.00 $22,360.00
15 Sanitary Sewer Junction Box (Sta. 32+90.62) Cast -in -Place (CIP) Base Bid 1.00 LS $378,000.00 $378,000.00
43 Post -CCTV Inspection Base Bid 1.14 LF $2.00 $2.28
68 Trash/ Debris Disposal to Landfill Base Bid 50.00 TN $65.99 $3,299.50
(Base Bid $425,621.78
(Alternate-B $0.00
Deletions Sub Total $425,621.78
Page 2 of 3
MMBE Breakdown for this Change Order
MWBE Sub I Type of Service Amount for this CO
Total $0.00
Previous Change Orders
CO # DATE I AMOUNT
Total I $0.00 I
Page 3 of 3
9/17/2024
Lake Arlington Lift Station Sanitary Sewer Gravity Mains
CSC: 58322
CPN:101311
Change Order 3 Notes
Staff has reviewed the requested prices and considers them to be fair and reasonable.
Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
A4 s
Signature
April Rose Escamilla
Name of Employee
Senior Professional Engineer
Title po�f�Rtopda
�o
ATTEST: 000/�oo
l I % ,.��� aaIla aEo454p
Jannette S. Goodall
City Secretary