HomeMy WebLinkAboutContract 59217-A2AMENDMENT NO.2 TO AGREEMENT Fort Worth Convention Center — Phase 1 STATE OF TEXAS CITY SECRETARY CONTRACT NO. 59217-A2 COUNTY OF TARRANT WHEREAS, The City of Fort Worth and Hunt -Byrne -Smith, a Joint Venture of the City of Dallas, County of Dallas, State of Texas (Contractor) made and entered into City Secretary Contract No. 59217 (The Contract) which was authorized by the City Council by M&C 24-0494, the 11th day of June 2024, for City of Fort Worth's Convention Center Phase 1; and WHEREAS, further amendment is necessary to support contractors' ability to deliver against the additional scope of work for the Fort Worth Convention Center Phase 1 and related costs refer to Attachment A; and NOW THEREFORE, City and Contractor, acting herein by and through their duly authorized representatives, enter into the following agreement which amends the Contract: Paragraph 7 of the contract is amended as follows: "The agreed upon estimated construction budget amounts shall be a total of not -to - exceed $82,212,681.00. These amounts include the City's "Owner's Contingency" (7.5%) for use by the OWNER only and any Savings, Contingency, Buy Out Savings and Allowances remaining at the end of construction will be retained by the OWNER. Notwithstanding anything herein to the contrary, the estimated budget amounts are not guaranteed by the Contractor. Only the Guaranteed Maximum Price, once established via mutual agreement of the parties, will be guaranteed by the Contractor. This addition will cover the areas of scope listed in Attachment A: 1. M&C 24-0494 2. Phase 1 Final GMP Estimate City of Fort Worth, Texas Standard Agreement for Professional Services AMENDMENT Revision Date: 3/20/2020 Page 1 of 2 Executed effective as of the date signed by the Assistant City Manager below. FORT WORTH: City of Fort Worth '7�� �3e p 9 Cc � By: Dana Burghdoff (Sep 9, 2024 5 CDT) Name: Dana Burghdoff, AICP Title: Assistant City Manager Date: Sep 19, 2024 Approval Recommended: By: Name: Marilyn Marvin Title: Interim Director Property Management Attest: By: U Name: Jannette Goodall Title: City Secretary Contractor: Hunt -Byrne -Smith, A Joint Venture cuSigned by: F�6" By: Name: Robert F. Hart Title: President, Hunt Construction Group, Inc. Date: 09-11-2024 1 9:09 AM PDT City of Fort Worth, Texas Standard Agreement for Professional Services AMENDMENT Revision Date: 3/20/2020 Page 2 of 2 Contract Compliance Manager: By signing I acknowledge that I am the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements. By: ll n-ow�.. 4• (q V Name: Brian Glass Title: City Architect Approved as to Form and Legality: fj� Douglas Black (Sep 13, 202417:14 CDT) By: Name: Douglas Black Title: Sr. Assistant City Attorney Contract Authorization: M&C: 24-0494 Page 1 of 3 CITA COUNCIL AGEND Create New From This M&C DATE: 6/11/2024 REFERENCE NO.. CODE: C TYPE: M&C 24-0494 LOG NAME: NON- PUBLIC CONSENT HEARING: Official site of the City of Fort Worth, Texas Foy WORTH 21 FORT WORTH CONVENTION CENTER CMAR AMENDMENT 2 NO SUBJECT: (CD 9) Authorize Execution of Amendment No. 2 of the Construction Manager at Risk Contract with Hunt/Byrne/Smith, a Joint Venture, in an Amount Not to Exceed $9,212,681.00, Including an Owner's Construction Contingency Allowance, for a Total Contract Value of $82,212,681.00, for Phase 1 of the Fort Worth Convention Center Renovation and Expansion Project RECOMMENDATION: It is recommended that the City Council authorize execution of Amendment No. 2 of the construction manager at risk contract with Hunt/Byrne/Smith, a joint venture, in an amount not to exceed $9,212,681.00, for a total contract value of $82,212,681.00, including an owner's construction contingency allowance, for phase 1 of the Fort Worth Convention Center Renovation and Expansion project (City Project No. 102582). DISCUSSION: On November 29, 2022, City Council authorized the execution of a Construction Manager at Risk (CMAR) contract with Hunt/Byrne/Smith, a Joint Venture, in an amount not to exceed $30,000,000.00 for the Fort Worth Convention Center Renovation and Expansion project while the design was being finalized. The original Mayor & City Council Communication (M&C) 22-0971 stated that the project would advance through incremental Notices to Proceed for various tasks. This allowed the contractor to order materials with long lead times, and initiate other tasks. The M&C also stated that other amendments to this contract would be required and would be recommended to the City Council for approval. On September 12, 2023, City Council authorized (M&C 23-0768) the execution of a Construction Manager at Risk (CMAR) Amendment No. 1 with Hunt/Byrne/Smith, a Joint Venture, in an amount not to exceed $43,000,000.00, for the anticipated Phase 1 construction. As designed and construction progressed final work items were defined. Staff recommends execution of Amendment No. 2, in the amount of $9,212,681.00, for the final portions of work associated with Phase 1. The overall project costs are expected to be as described in table below: PROJECT COST TOTAL Professional Services (Project $9,606,588.00 Management & Design Contracts CMAR Construction Contract (Including $30,000,000.00 Owner's Construction Contingency Allowance) CMAR Amendment #1 $43,000,000.00 http://apps.cf\vnet.org/council_packet/mc—review.asp?ID=32201 &councildate=6/11/2024 6/20/2024 M&C Review Page 2 of 3 Docusign Envelope ID: 5EDF56D1-BB9F-435C-ADOE-EE8924BO91DC CMAR Construction Contract Amendment $9,212,681.00 #2 Administrative Costs (Staff Time, $1,685,423.00 Additional ITS, AV, Security, Building Infrastructure, Major Maintenance, FF&E, and Moving Costs) Waiver of Building Permit Fees - In Project Contingency $1,495,308.00 accordance with the City Code of TOTAL $95,000,000.00 Ordinances, Part II,Chapter 7-1 Fort Worth Building Administrative Code, Section 109.2.1, Exception 2; "Work by non -City personnel on property under the control of the City of Fort Worth shall be exempt from the permit fees only if the work is for action under a contract that will be or has been approved by City Council with notes in the contract packages stating the fee is waived." DIVERSITY AND INCLUSION BUSINESS EQUITY OFFICE: Hunt -Byrne -Smith, a Joint Venture agrees to maintain its initial M/WBE commitment of 30\% that it made on the original contract and extend and maintain that same M/WBE commitment of 30\% to all prior change orders up to and inclusive of this Change Order No. 2. Therefore Hunt -Byrne -Smith, a Joint Venture remains in compliance with the City's M/WBE Ordinance and attests to its commitment by its signature on the Acceptance of Previous M/WBE Commitment form executed by an authorized representative of its company. The Fort Worth Convention Center is located in COUNCIL DISTRICT 9 and will benefit all council districts. FISCAL INFORMATION/CERTIFICATION: The Director of Finance certifies that funds are available in the current capital budget, as previously appropriated, in the Certificate of Obligation 2023 Fund for the ARPA FWCC Expansion & Prj Mgmt project to support the approval of the above recommendation and execution of the amendment to the contract. Prior to any expenditure being incurred, the Public Events Department has the responsibility to validate the availability of funds. TO Fund Department Account Project ID ID FROM Fund Department Account Project ID ID Submitted for Citv Manaaer's Office bv: Oriainatina Department Head: Additional Information Contact: Program Activity Budget Reference # Amount Year (Chartfield 2) Program Activity Budget Reference # Amount Year (Chartfield 2) Dana Burghdoff (8018) Marilyn Marvin (7708) Brian Glass (8088) Nikita Watts (2028) http://apps.cfwnet.org/council_packet/mc review.asp?ID=32201&councildate=6/11/2O24 6/20/2024 M&C Review Docusign Envelope ID: 5EDF56D1-BB9F-435C-ADOE-EE8924BO91DC Page 3 of 3 ATTACHMENTS 21 FORT WORTH CONVENTION CENTER CMAR AMENDMENT 2 FID TABLE.xlsx (CFW Internal) 21 FORT WORTH CONVENTION CENTER CMAR AMENDMENT 2 funds availabilitv.Ddf (CFW Internal) 24-Acceptance of Previous MWBE Committment Form Final-CC.Ddf (CFW Internal) Form 1295 Certificate 101198211 - Executed.Ddf (CFW Internal) SAM E J Smith Construction & Engineering Inc.Ddf (CFW Internal) SAM Hunt Construction Group Inc.Ddf (CFW Internal) SAM Thos S Bvrne Ltd.Ddf (CFW Internal) http://apps.cfwnet.org/council_packet/mc review.asp?ID=32201&councildate=6/11/2O24 6/20/2024 Docusign Envelope ID: 5EDF56D1-BB9F-435C-ADOE-EE8924B091DC Home Legislation Calendar City Council Departments D RS$ i,Y Alerts i Details Reports File #: M&C 24-0494 Version: 1 Name: Type: Award of Contract - Report of CM Status: Passed File created: 6/5/2024 In control: City of Fort Worth - Action Details On agenda: 6/11/2024 Final action: Details (CD 9) Authorize Execution of Amendment No. 2 of the Constru File #: MC 240494 Version: 1 Title: Exceed $9,212,681.00, Including an Owner's Construction Cont Convention Center Renovation and Expansion Project Type: Award of Contract - Report of CM Attachments: 1. M&C 24-0494 Title: (CD 9) Authorize Execution of Amendment No. 2 of the Construction P Hunt/Byrne/Smith, a Joint Venture, in an Amount Not to Exceed $9,21 History (1) Text Construction Contingency Allowance, for a Total Contract Value of $82 1 record Group Export Fort Worth Convention Center Renovation and Expansion Project Mover: Elizabeth M Beck Seconder: Chris Ne Date Ver. Action By Action Result: 6/11/2024 1 CITY COUNCIL Apprm Agenda note: Minutes note: Action: Approved Action text: Council Member Beck made a motion, seconded by Council Member N approved. Motion passed 10-0, Council Member Crain absent. Votes (0:0) 0 records Person Name No records to display. Vote