HomeMy WebLinkAboutContract 59910-AR1CSC No. 59910-AR1
FORT WORTH,
Project Name New Main Street Outfall Storm Drain
Client Project #(s)I 103666
City of Fort Worth
Construction Allowance Request
City Sec # I 59910
Projectl This project will reroute existing storm drain systems and install a new outfall, at 8th St. and Calhoun in preparation for the USACE North
Description I Bypass Channel
Contractorl Circle C Construction I CA#I 1 I Datel 8/19/2024
City Project Mgr. I Max Aransen
UNIT or DEPT
Original Contract Amount
Extras to Date
Credits to Date
Current Contract Amount
)Amount of Proposed Allocation
Original Allowance Available to Allocation
Allowance Funds Previously Allocated
Revised Allowance Balance
City Inspector) James Ruiz
TPW
$9,242,595.00
UNIT 2 or Dept UNIT 3 or Dept UNIT 4 or Dept
I Totals
$9,242,595.00
9,242,595.00
$9,242,595.00
43,250.00
0.00
$0.00
0.00
43,250.00
50,000.00
50,000.00
$0.00
6,750.00
$0.00
$0.00
------fo-.00I
$6,750.00
JUSTIFICATION (REASONS) FOR CONSTRUCTION ALLOWANCE
This Construction Allowance request is for 3 sanitary sewer service line reconnections to be added as they were not identified in design. These reconnections were needed and
were not identified till the contractor mobilized onsite. These service connections were connected into the proposed 18" main. These items will be new under this contract. Per
the review of the design engineer, project manager, and construction manager in conjunction with the invoices from the fitting supplier and records of bid items from similar city
projects, the costs for these unique items seemed fair and reasonable.
It is understood and agreed that the acceptance of this Construction Allowance Request by the contractor constitutes an accord and
satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to, the above Construction
Allowance Request. The Project/Program Manager signing below acknowledges that he/she is the person responsible for the monitoring and
administration of this contract, including ensuring all performance and reporting requirements.
Circle C Construction
Keegan Jonkers IK°�-?-I-
Sep 9, 2024
Inspector/Inspection Supervisor
Date
Project and Contract Compliance Manager
Date
T_„ _
Sep 10, 2024
-Ad-
Sep 10, 2024
Program Manager
Date
Senior Capital Project Officer
Date
�� ed
Sep 10, 2024
Sep 16, 2024
Assistant Director Dept
Date
Director, Contracting Department (Dept)
Date
Sep 17, 2024
Sep 17, 2024
City Attorney
Date
Assistant City Manager
Date
Sep 18, 202
\��Af_
Sep 20, 2024
CF F�Rfu�pd
ATTEST:
T �0 8=A
Jannette Goodall, City Secretary Pp * * a°
pdaa4 nERVoS�pd
OFFICIAL RECORD
CITY SECRETARY
Construction Allowance SUMMARY FT. WORTH, TX
Page 1 of 4
FORT WORTH. City of Fort Worth
Construction Allowance Additions
Project Name I New Main Street Outfall Storm Drain 1L ity Sec # 1 59910 1
Client Project # I 103666 1
Contractorl circle C Construction PM1 Max Aransen I Inspector) James Ruiz
Construction Allowance Submittal # 0 Date 1 8/19/2024 1
ADDITIONS
ITEM
DESCRIPTION
DEPT
Oty
Unit
Unit Cost
Total
4" Service with 18" by 6" P401 Tee, 6" by 4" P401 Reducer, 4"
21
P401 Pipe
TPW
2.00
EA
$10,000.00
$20,000.00
22
5' Manhole
TPW
1.00
EA
$15,000.00
$15,000.00
23
4" Sanitary Sewer Cleanout
TPW
3.00
EA
$1,000.00
$3,000.00
24
4" Lateral Cleanout Top
TPW
3.00
EA
$750.00
$2,250.00
25
4" Service Reconnection
TPW
3.00
EA
$1,000.00
$3,000.00
i �w
$43,250.00
UNIT 2 or Dept
$0.00
UNIT 3 or Dept
$0.00
UNIT 4 or Dept
$0.00
Total Additions
$43,250.00
Construction Allowance Additions
Page 2 of 4
FORT WORTH,. City of Fort Worth
Construction Allowance Value
Project Name I New Main Street Outfall Storm Drain City Sec # 1 59910 1
Client Project # 1 103666 1
Contractorl Circle C Construction I PM I Max Aransen I Inspectorl James Ruiz
Construction Allowance Submittal # = Date 1 8/19/2024
CONSTRUCTION ALLOWANCE VALUE BEING USED
ITEM DESCRIPTION Qty Unit Unit Cost Total
20 9999.0013 Construction Allowance (Sewer) 1.00 LS $50,000.00 $50,000.00
Note to Preparers Delete example information in cells and add the CONSTRUCTION ALLOWANCE contract
bid item number being used, description, UNIT or DEPT, Qty, Unit and Unit Cost in the lines above. Three
lines are provided for those cases when up to 3 different Construction Allowance types are being impacted.
In most cases only one Construction Allowance type will be impacted. Delete these instructions from the
form.
Construction Allowance Value
3of4
M/SBE for this Construction Allowance Request
M/SBE Sub I Type of Service I Amount for this CAR
Total $0.00
Previous Construction Allowance Requests
CAR # DATE I AMOUNT
Total I $0.00 1
Construction Allowance MSBE Data
Page 4 of 4
circle C Construction
New Main Street Outfall Change Order One
Additions:
Item No.
1
2
3
4
5
Deletions:
1
Description
4" Service with 18" by 6" P401 Tee, 6" by 4"
P401 Reducer, 4" P401 Pipe
5' Manhole
4" Cleanout
4" Lateral Cleanout Top
4" Service Recconnection
Keegan Jonkers
Quantity Cost
2. $ 10,000.00
1 $ 15,000.00
3 $ 1,000.00
3 $ 750.00
3 $ 1,000.00
Total Additions
Unit Total
EA $ 20,000.00
EA $ 15,000.00
EA $ 3,000.00
EA $ 2,250.00
EA $ 3,000.00
$ 43,250.00
4'StandardManhole 1 $(10,500.00) EA $(10,500.00)
Total Dedutions $ (10,500.00)
Change Order Total $ 32,750.00
Please add 20 days to the project for the Tee option or 10 days for the manholes.
500 W TRAMMEL AVE FORT WORTH, TEXAS 76140
T 817-293-1863
PIPE & SUPPLY
ACT PIPE AND SUPPLY, INC.
2585 NE 28TH STREET
FORT WORTH, TX 76111
817-831-1663
Fax 817-831-1953
BILL TO:
CIRCLE C CONSTRUCTION
P.O. BOX 40328
FORT WORTH, TX 76140
III III i i iiiIIi ii i i i ii i ii i i Ili III
Invoice
INVOICE DATE INVOICE NUMBER
07/16/2024 S101106300.002
PAGE NO.
REMIT TO:
ACT PIPE AND SUPPLY, INC.
PO OX 301282
DAALBLAAS, TX 75303-1282 1 of 1
SHIP TO:
NEW MAIN STREET OUTFALL
900 N MAIN ST
FORT WORTH, TX 76164
CUSTOMER NUMBER
CUSTOMER PO NUMBER JOB NAME / RELEASE NUMBER
SALESPERSON
195063
NEW MAIN STREET
Mat Sanders
WRITER
SHIP VIA TERMS
SHIP DATE
ORDER DATE
Mat Sanders
WILL CALL NET 30 DAYS
07/16/2024
07/09/2024
ORDER QTY SHIP QTY
PART#
DESCRIPTION
UNIT PRICE
EXT PRICE
2ea 2ea
66853
22011806L 18" X 6" DI COMPACT MJ
2213.690/ea
4427.38
TEE C153 LINED
3ea 3ea
26395
22060604L 6" X 4" DI COMPACT MJ
312.720/ea
938.16
REDUCER C153 LINED
6ea 6ea
16050
SGDP06 6" STAR SERIES 3000 STARGRIP
42.890/ea
257.34
JOINT RESTRAINT FOR DIP
6ea 6ea
3253
2260060OF 6" DI COMPACT MJ BLUE
25.110/ea
150.66
BOLT & GASKET SET C153 FOREIGN
3ea 3ea
16044
SGDP04 4" STAR SERIES 3000 STARGRIP
35.290/ea
105.87
JOINT RESTRAINT FOR DIP
3ea 3ea
3245
2260040OF 4" DI COMPACT MJ BLUE
18.680/ea
56.04
BOLT & GASKET SET C153 FOREIGN
Subtotal -------
5935.45
Prior Deposit on 08/09/2024-5935.45
Invoice is due by 08/15/2024 Subtotal
5935.45
Past Due invoices may be subject to 1.50% late charge. S&H Charges
0.00
Tax
0.00
Payments
-5935.45
Amount Due
0.00
Printed By: BETO on 8/12/2024 1:39:32 PM
FORT WORTM,
Routing and Transmittal Slip
Transportation & Public Works Department
DOCUMENT TITLE: New Main St. Outfall Construction Allowance
Request
M&C:
Date:
CPN: 103666 CSO: 59910
To:
Name
Keegan Jonkers
1'
k.jonkers@circlecconstruction.com
2.
James Ruiz
3.
Max Aransen
4.
Thanaa H. Maksimos
5.
Lissette Acevedo
6.
Patricia Wadsack
7.
Lauren Prieur
g.
Doug Black
9.
Jesica McEachern
10.
Jannette Goodall
11.
Allison Tidwell
Department Initials
Contractor Kc�
TPW - Inspector
TPW - Project Manager
TPW — Program Manager
M
TPW — Sr. CPO
TPW — Assistant Director
I>LW
TPW - Director
Legal - Assistant City Attorney
CMO — Assistant City Manager a`
CSO — City Secretary
CSO — City Secretary
1►�—
DOC#:
1
Date Out
Sep 9, 2024
Sep 10, 2024
Sep 10, 2024
Sep 10, 2024
Sep 16, 2024
Sep 17, 2024
Sep 17, 2024
Sep 18, 2024
Sep 20, 2024
Sep 20, 2024
Sep 20, 2024
12. Tpw—SW—Contract TPW Stormwater "I s/ Sep 17, 2024
CC: Program Manager — Linda Young, Sr. CPO — Lissette Acevedo, TPW BSPAP Recon Team —
Cindy Sengathith
DOCUMENTS FOR CITY MANAGER'S SIGNATURE: All documents received from any and all
City Departments requesting City Manager's signature for approval MUST BE ROUTED TO THE
APPROPRIATE ACM for approval first. Once the ACM has signed the routing slip, David will review
and take the next steps.
NEEDS TO BE NOTARIZED: DYES ®No
RUSH: DYES ®No SAME DAY: DYES ®No NEXT DAY: ❑YES ®No
ROUTING TO CSO: ®YES ❑No
Action Required:
❑ As Requested
❑ For Your Information
® Signature/Routing and or Recording
❑ Comment
❑ File
❑ Attach Signature, Initial and Notary Tabs
Return to: tpw sw contracts(d.fortworthtexas.2ov Call 817-229-3283 with questions. Thank you!