HomeMy WebLinkAboutOrdinance 27056-08-2024Ordinance No. 27056-08-2024
AN ORDINANCE INCREASING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE WATER AND SEWER CAPITAL PROJECTS FUND
IN THE AMOUNT OF $242,000.00, TRANSFERRED FROM AVAILABLE PAYGO
FUNDS IN THE WATER AND SEWER FUND, FOR THE PURPOSE OF FUNDING
THE WATER & SANITARY SEWER REPL CONTRACT 2019 WSM-I PROJECT
(CITY PROJECT NO. 103415); PROVIDING FOR A SEVERABILITY CLAUSE;
MAKING THIS ORDINANCE CUMULATIVE OF PRIOR ORDINANCES;
REPEALING ALL ORDINANCES IN CONFLICT HEREWITH; AND PROVIDING
AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,
TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2023-2024 in the
Budget of the City Manager, there shall also be increased estimated receipts and appropriations in the Water
and Sewer Capital Projects Fund in the amount of $242,000.00, transferred from available PayGO funds in
the Water and Sewer Fund, for the purpose of funding the Water & Sanitary Sewer REPL Contract 2019
WSM-I project (City Project No. 103415).
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way impair
the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 26453-09-2023 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY: CITY SECRETARY
(Oct 1, 2024 10:44 FDT)
Douglas W. Black
Senior Assistant City Attorney
ADOPTED AND EFFECTIVE: August 13, 2024
Janette S. Goodall
City Secretary
U 5tlX30
9 * °°4,7 ° �° °o
C 000 0
¢ � 00y
�► �0 00 �4:7
O JJ
00ZY
00000000 O4'
�da/fj QwOQ�4
MAYOR AND COUNCIL COMMUNICATION
60RIVERSIDE BRIDGE WATERLOC AFA AND APPROPRIATION
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 08/13/24 M&C FILE NUMBER: M&C 24-0680
LOG NAME: 60RIVERSIDE BRIDGE WATTERLOC AFA AND APPROPRIATION
SUBJECT
(CD 11) Ratify Execution of an Advance Funding Agreement with the Texas Department of Transportation in the Amount of $2,330,000.00 for
Voluntary Utility Relocation Contributions for the Riverside Drive Bridge Over Trinity River Project, Authorize Execution of Amendment No.1 to the
Advance Funding Agreement to Reduce the Amount by $2,160,000.00 to $170,000.00 and Adopt Appropriation Ordinance to Effect a Portion of
Waters Contribution to the Fiscal Years 2024 2028 Capital Improvement Program
RECOMMENDATION:
It is recommended that the City Council:
1. Ratify execution of an Advance Funding Agreement (CSJ 0902-90-298) with the Texas Department of Transportation in the amount of
$2,330,000.00 for Voluntary Utility Relocation Contributions for the Riverside Drive Bridge project;
2. Authorize execution of Amendment No. 1 to the Advanced Funding Agreement with the Texas Department of Transportation for Voluntary
Utility Relocation Contributions for the Riverside Drive Bridge project reducing the cost by $2,160,000.00 to the amount of $170,000.00; and
3. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Water and Sewer Capital Projects Fund
in the amount of $242,000.00, transferred from available PayGo funds within the Water and Sewer Fund, for the purpose of funding the Water
& Sanitary Sewer REPL Contract 2019 WSM-I project (City Project No. 103415) to effect a portion of Water's contribution to the Fiscal Years
2024-2028 Capital Improvement Program.
DISCUSSION:
The original Advanced Funding Agreement (AFA) for City voluntary contributions (CSJ 0902-90-298, CSC No. Pending) was routed directly to the
City Manager's Office by Texas Department of Transportation (TXDOT) and inadvertently executed on May 16, 2023 prior to a Mayor and Council
Communication (M&C) authorizing said action. This M&C serves to rectify the error by ratifying the CMO's execution of that AFA and, since the
project's scope has radically changed in the interim, authorize an amendment to said AFA greatly reducing the cost to the city.
The amendment to the Advanced Funding Agreement being presented here will provide reduced city funding for the removal of the 12-inch water
main, attached to the Riverside Drive Bridge, in conjunction with TXDOT's rehabilitation of the Riverside Drive Bridge. The estimated cost for the
water main's removal is $170,000.00. In addition to the estimated construction cost, $72,000.00 is required for project management, material
testing and inspection. This project will have no impact to the Water Department's operating budget when completed.
On September 12, 2017, M&C C 28365 authorized execution of an Advance Funding Agreement with the Texas Department of Transportation for
the Reconstruction of the Riverside Drive Southbound Bridge Deck over Trinity River (City Secretary Contract No. 50229, CSJ No. 0902-90-019).
Subsequently, TXDOT has required that the segment of the water main currently attached to south bound deck of the Riverside Drive Bridge be
removed.
On November 30, 2021, M&C 21-0924 authorized execution of an Engineering Agreement with Kimley-Hom and Associates, Inc. (City Secretary
Contract No. 56816) for the Water and Sanitary Sewer Replacement Contract 2019 WSM-I, project which includes the removal and relocation of
the water main from Riverside Drive to Booker Street. TXD07s contractor under contract for the bridge rehabilitation project will perform this work.
This M&C will also appropriate the required funding for the project. No funds have been transferred to TXDOT.
It is the practice of the Water Department to appropriate its CIP plan throughout the Fiscal Year, instead of within the annual budget ordinance, as
projects commence, additional funding needs are identified, and comply with bond covenants. The actions in the M&C will appropriate funds in
support of the Water's portion of the City of Fort Worth's Fiscal Years 2024-2028 Capital Improvement Program, as follows:
60RIVERSIDE Bridge WATERRELOC AFA AND APPROPRIATION
Capital
Fund
Name
Project
Name
FY2024 CIP
Appropriations
Authority
Budget Change
(IncreaselDecrease}
Revised
FY2024
Budget
W&S
103415-
Capital
WISS
Projects
Repl
Contract
$0,00
This M&C
$242,000.00
$242,000.00
Fund -Fund
56002
2019
WSM_I
FY2024 - Water PAYGO Appropriations per City Ordinance 264SM9-2023
FY2024
Amended
PY2024
PayGo
(includes any
YTD PayGo
FY2024
Original
council
Approved
This M&C
Remaining
Adopted
actions
for/Moved to
PayGo
PayGo
subsequent to
Capital Projects
Balance
budget
adoption)
$84,505,035.00
$84,505,035.00
$(75,362,626.38)
$(242,000.00)
$8,900,408.62
Note: There may be other pending actions or recently approved actions that are not reflected in the table due to timing
Appropriations for the WISS Repl Contract 2019 WSM-1 project are as depicted in the table below.
Fund
Existing
11 Additional
Project Total"
Appropriations
Appropriations
2022 Bond
Program- Fund
$70,000.00
$0.00
$70,000.00
34027
&S Capital
Projects - Fund
56002
$1,257,971.00
$242,000.00
$1,499,971.00
Project Total
$1,327,971.D0
$242,000.00
$1,569,971.00
Funding is budgeted in the Transfer to Water/Sewer account within the Water & Sewer Fund for the purpose of funding the WISS Repl Contract
2019 WSM-1 project within the Water & Sewer Capital Projects Fund.
;Numbers rounded for presentation purposes.
This project is located in COUNCIL DISTRICT 11.
A Form 1295 is not required because: This M&C does not request approval of a contract with a business entity.
FISCAL INFORMATION 1 CERTIFICATION;
The Director of Finance certifies that funds are currently available in the Water and Sewer Fund, and upon approval of the above recommendations
and adoption of the attached appropriation ordinance, funds will be available in the W&S Capital Projects Fund for the WISS REPL Contract 2019
WSM-I project to support the above recommendations and execution of the Advance Funding Agreement. Prior to any expenditure being incurred,
the Water Department has the responsibility of verifying the availability of funds.
Submitted for Cily Manager's Office by: Fernando Costa 6122
Originating Business Unit Head: Chris Harder 5020
Additional Information Con a : April Escamilla 8455