HomeMy WebLinkAboutContract 61025-CO1CSC No. 61025-COl
FC]RT WoP,-rm City of Fort Worth
Change Order Request
Project Name:Sanitary Sewer Replacements Contract 111
I City Sec No,: 61025
Project No,(s):l 5600210700430/5740010
NTP 1 5/13/2024 City Proj. No.: 102784
Project Description:
I The work under this contract consists of the replacement of existing water pipe and sanitary sewer pipe, replacement of existing
residential water services, temporary pavement repair, and pulverization and overlay of three residential streets,
Contractor: R & D Bums Brothers, Inc.
Change Order# 1 Date: 1 9/1612024
City Project Mgr.1 Lawrence Hamilton
City Inspector: Joshua Manry
Phone Number: 817-392-2626
Phone Number: 817-392-8306
Dept. Water Main
Sewer Main Paving Totals Contract Time
(Calender days)
Original Contract Amount $1,461,515.00
$3,065,074.00 $714,160.00 $5,240,739.00 200
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date $1,461,516,00
$3,065,074.00 $714,150.00 $5,240,739.00 200
Amount of Proposed Change Order $0.00
$86,217.00 $0.00 $86,217.00 030
Revised Contract Amount $1,461,515.00
$3,151,291.00 $714,160.00 $5,326,956.00 230
Original Funds Available for Change Orders $172,992.00
$296,444.00 $0.00 $469,436.00
Remaining Funds Available for this CO $172,992.00
$296,444.00 $469,436.00
Additional Funding (if necessary)
CHANGE ORDERS to DATE (INCLUDING THiS ONE) AS % OF ORIGINAL CONTRACT
1.65%
MAXALLOWABLE CONTRACTAMOUNT(ORiGINAL CONTRACT COST+ 25%)
$6,550,923.76
JUSTIFICATION (REASONS) FOR CHANGE ORDER
Change Order No.1 will provide compensation for the following that are necessary on the project:
• The installation of grout in abandoned sewer.
• The installation of 12-inch DI pipe to replace abandoned concrete sewer pipe.
• The placement of 12-inch grouted rip rap to protect stream from eroding a close -by 12-inch DI sewer pipe.
• Concrete encasement.
• 8-Inch pipe enlargement.
• Installation of drop manhole.
Staff concurs with the contractor's request for 30 additional calendar days for the change order,
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
In full (both time and money) for all costs arising out of, or Incidental to, the above Change Order.
Contractor's Company Name
R & D Burns Brothers, Inc.
Contractor Name
Donald Burns
Contractor Signature
'.? �, (I( ,1 -- --r—
I Date
C?
Ins actor _
Date
9-24-2024
Pr91ject Manager
1% j
Date A
q-dy -a"
Irector (Writer Deppt
to Gce �t ae
Date
T S.
Construction Supervisor (TPW Dept)
7Yoti
Date
9-24-2024
Assl ant �t"Attomey
Date
AssI nv Manager
- Date_.
I
vougmn oiacK w¢ a, �ueti u.o3 �� i �
W IwaYn ion nson tuft 8, L01414:39 t,U I)
Council Action (If Required)
M&C Number NiA
M&C Date Approved NiA
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
FORT WO R-F 14 City of Fort Worth
i _ ' - Change Order Additions
Project Name Sanitary Sewer Replacements Contract 111 City Sec No.: 1 61025
Project No,(s): 56002/0700430/5740010 DOE No.j N/A City Proj. No.: 1 102784
Project I The work under this contract consists of the replacement of existing water pipe and sanitary sewer pipe, replacement of existing
Description residential water services, temporary pavement repair, and pulverization and overlay of three residential streets.
Contractor R & D Burns Brothers, Inc. I Change Order:1 1 Date:1 9/16/2024
City Project Mgr. Lawrence Hamilton City Inspector I Joshua Manry
ADDITIONS
1 I LIVI
ULbUKIN I IUN
DEPT
Qty Unit Unit Cost
Total
18
Drop Manhole
Sewer Main
1.00 EA $14,000.00
$14,000.00
58
12-inch DIP 401 Lined Sewer
Sewer Main
268.00 LF $260.00
$69,680.00
59
Pipe Grouting
Sewer Main
16.00 CY $625.00
$10,000.00
60
12-inch Grouted Rip Rap
Sewer Main
220.00 SY $175.00
$38,500.00
61
Concrete Encasement
Sewer Main
65.00 LF $135.00
$8,775.00
62
8" Pipe Enlargement
Sewer Main
499.00 LF $138.00
$68,862.00
lWater gain
Sewer Main
$209,817.00
Paving
Page 2 of 4
Additions Sub Total
$209,817.00
FOI.:T WO P,-F H City of Fort Worth
Change Order Deletions
Project Name Sanitary Sewer Replacements Contract 111 City Sec No.: I 61025
Project No.(s): 56002/070043015740010 DOE No. I N/A City Proj. No.: I 102784
Project Description The work under this contract consists of the replacement of existing water pipe and sanitary sewer pipe, replacement of existing
residential water services, temporary pavement repair, and pulverization and overlay of three residential streets.
Contractor I R & D Burns Brothers, Inc. Change Order: I I Date I 9/16/2024
City Project Mgr. Lawrence Hamilton City Inspector: I Joshua Manry
ITEM DESCRIPTION
1 12-Inch PVC SDR-26 Sewer Pipe
57 Sanitary Sewer Construction Allowance
DELETIONS
DEPT Qty Unit Unit Cost
Sewer Main 268.00 LF $200.00
Sewer Main 0.875 LS $80,000.00
Page 3 of 4
(Water Main
Sewer Main
(Paving
Deletions Sub Total
Total
$53,600.00
$70,000.00
$123,600.00
$123,600.00
MWWBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
co # DATE AMOUNT
Total $0.00
Page 4 of 4
10/4/2024
Sanitary Sewer Replacements Contract 111
CSC: 61025
CPN 102784
Change Order 1 Notes
Staff has reviewed the requested prices and days and considers them to be fair and
reasonable.
.Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
Signature
Lawrence Hamilton
Name of Employee
Senior Professional Engineer
Title bt�4FOR�L
P 000-
c
moo
ATTEST: p v o
o
Pa*o60000000000,
A ,� �nEXAS
Jannette Goodall
City Secretary
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX