HomeMy WebLinkAboutOrdinance 27189-09-2024Ordinance No. 27189-09-2024
AN ORDINANCE ADJUSTING APPROPRIATIONS IN THE WATER AND
SEWER COMMERCIAL PAPER FUND BY INCREASING APPROPRIATIONS
IN LAKE ARLINGTON LIFT STATION, FORCE MAIN, AND SANITARY
SEWER MAINS PROJECT (CITY PROJECT NO. 100995) IN THE AMOUNT OF
$63,066,715.00 AND DECREASING APPROPRIATIONS IN THE W&S
COMMERCIAL PAPER PROJECT (CITY PROJECT NO. UCMLPR) BY THE
SAME AMOUNT; PROVIDING FOR A SEVERABILITY CLAUSE; MAKING
THIS ORDINANCE CUMULATIVE OF PRIOR ORDINANCES; REPEALING
ALL ORDINANCES IN CONFLICT HEREWITH; AND PROVIDING AN
EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS:
SECTION 1.
That the budget of the City of Fort Worth for Fiscal Year 2023-2024, as enacted by Ordinance 26453-09-
2023, as amended, is hereby further amended to make the following adjustments to appropriations in the
Water and Sewer Commercial Paper Fund by increasing appropriations in the Lake Arlington Lift Station,
Force Main, and Sanitary Sewer Mains project (City Project No. 100995) in the amount of $63,066,715.00
and decreasing appropriations in the W&S Commercial Paper project (City Project No. UCMLPR) by the same
amount.
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
forany reason by a court ofcompetent jurisdiction, such decision, opinion orjudgment shall in no way impair
the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 26453-09-2023 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY:
or.. . - ..Oct 4, 2074 M09 CDTi - -
Douglas W. Black
Sr. Assistant City Attorney
ADOPTED AND EFFECTIVE: September 17, 2024
CITY SECRETARY
Jannette S. Goodall
City Secretary
MAYOR AND COUNCIL COMMUNICATION
60LARFMP1 AND2-BELTANDFNI
. W&V&-
7�
z WILLIE ST
0
a ELGIN ST �
w
o
u
w
O
O
Lu
w
CAROL AVE
Y
w
w
U
w
c�
a
J
1
FORT WORTH
287
w
a
MARTIN ST
w
J
J
ti]
SUN VALLEY DR
w
z
WILLARD
a
.
Q
0
4Q le
9
FOREST HILL
0
n r:
� p c
FORT WORTH;., rFREEMAN R �-
i
FORT WORTH
on =
RpSEpgLE
S'
. 1 PART 1
PART 2
E LANCASTER AVE
IL
rr -
ARLINGTON
\H 2a
1 ,
� I
<LgNIA AVE I
KENNEDALE i z
w
Source Esri. Maxar. Earlh5•; ti c crr
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 09/17/24 M&C FILE NUMBER: M&C 24-0844
LOG NAME: 60LARFMPIAND2-BELTANDFNI
S UBJF.CT
(CD 5 and City of Kennedale) Authorize Execution of a Contract with Belt Construction of Texas, LLC in the Amount of $59,657,497.33 for Lake
Arlington Lift Station, Force Main, and Sanitary Sewer Mains Project. Authorize Execution of Amendment No. 6, in the Amount of $1.511,941.00,
to an Engineering Agreement with Freese & Nichols, Inc. for the Lake Arlington Lift Station, Force Main and Sanitary Sewer Mains Project Parts
and 2. Provide for Project Costs for a Project Total in the Amount of $63,066,715.00, Adopt Resolution Expressing Official Intent to Reimburse
Expenditures with Proceeds of Future Debt, and Adopt Appropriation Ordinance to Effect a Portion of Water's Contribution to the Fiscal Years
2024-2028 Capital improvement Program
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize execution of a contract with Belt Construction of Texas, LLC in the amount of $59,657,497.33 for the Lake Arlington Litt Station,
Force Main, and Sanitary Sewer Mains Project Parts 1 and 2;
2. Authorize execution of Amendment No. 6 to City Secretary Contract No. 50312, an Engineering Agreement with Freese & Nichols, Inc., in
the amount of $1,511,941.00 for construction support services for the Lake Arlington Lift Station Force Main, and Sanitary Sewer Mains
project for a revised contract amount of $6,134,322.00 (City Project No. 100995);
3. Adopt the attached Resolution expressing official intent to reimburse expenditures with proceeds from future debt for the Lake Arlington Lift
Station, Force Main, and Sanitary Sewer Mains project; and
4. Adopt the attached Appropriation Ordinance adjusting appropriations in the Water and Sewer Commercial Paper Fund by increasing
appropriations in Lake Arlington Lift Station, Force Main, and Sanitary Sewer Mains project (City Project No. 100995) in the amount of
$63,066,715.00 and decreasing appropriations in the W&S Commercial Paper project (City Project No. UCMLPR) by the same amount, to
effect a portion of Water's contribution to the Fiscal Years 2024-2028 Capital Improvement Program.
DISCUSSION:
On January 30, 2018, Mayor and Council Communication (M&C) C-28566 authorized an engineering agreement with Freese and Nichols, Inc.,
(City Secretary Contract No. 50312) in the amount of $3,099,361.00 for the preparation of plans and specifications for the Lake Arlington Lift
Station and Force Main project. The agreement was subsequently revised by Amendment No.1 in the amount of $229,755.00 (M&C C-29067,
March 19, 2019) that provided for the design of 1,000 linear foot aerial crossing of the force main across Lake Arlington and additional
geotechnical investigations at 8 locations along the force main; Amendment No. 2 in the amount of $366,004.00 (M&C C-29178, June 25, 2019)
that provided for the preparation of plans and specifications for additional tunneling design, archeological surrey, additional survey along Quail
Road, lead testing along lift station access road and design for erosion improvements on Village Creek Tributary near Salt Road; Amendment No.
3 in the amount of $211,344.00 (M&C 20-0137, March 3, 2020) that provided for preparation of additional temporary and permanent easement
documents, urban forestry permit application, and additional subsurface utility engineering (SUE) services, Amendment No. 4 in the amount of
$392,668.00 (M&C 20-0460, June 32, 2020) that provided for resident project representation (RPR) and start up assistance on Lake Arlington Lift
Station; and Amendment No. 5 in the amount of $329,249.00 (M&C 22-0290) April 12, 2022 that provided for additional easement acquisition
assistance, plan redesigns, aerial crossing design and additional resident project representation support.
Amendment No. 6 provides for construction management, resident project representative, and construction support services including shop
drawings, submittal reviews, change order review, archeological monitoring tracking, and record drawings.
Construction of the project was advertised for bid on June 06, 2024 and June 13, 2024 in the Fort Worth Star -Telegram. On July 18, 2024 the
following bids were received:
Bidder
Part 1
Part 2
Total Bid
Contract
Time
Belt
Construction
$35,986,607.33
$23,670,890.00
$59,657,497.33
900
Calendar
of Texas,
Days
LLC
McKee
Utility
$36,959,969.77
$22,689,137.50"
$59,649,107.27
Contractors,
LLC
S.J. Louis
��
Construction
of Texas,
$40,895,831.09
$27,303,573.25�$68,199,404.34
LLC
Mountain
Cascade of
$40,470,088.17
$33,209,454.00
$76,679,542.17
Texas, LLC
*The bid submitted by McKee Utility Contractors, LLC for Part 2 has been determined to be non -responsive due to failure to submit the required
MI BE documentation within the required time period after bid submittal.
The project was advertised in two parts with the City reserving the right to award contracts to the respective responsive low bidders of Parts 1 and
2 or to the responsive bidder of both parts combined. Staff recommends the award of the combined project to Belt Construction of Texas, LLC in
the amount of $59,657,497.33.
In addition to the contract cost, $1,356,717.00 is required for project management and inspection and $540,559.00 is provided for project
contingency.
This project will have no impact on the Water Department operating budget when complete.
Available cash within the Water and Sewer portfolio and the City's portfolio along with the appropriation authority authorized under the Callable
Commercial paper Program (CP) will be used to provide interim financing for this project until debt is issued. Once debt associated with this
project is sold, bond proceeds will be used to reimburse the Water and Sewer portfolio and the City's portfolio in accordance with the attached
Reimbursement Resolution. Under federal law, debt must be issued within approximately three years in order for these expenses to be
reimbursable. Adoption of the attached resolution does not obligate the City to sell bonds, but preserves the ability of the City to reimburse itself
from tax-exempt bond proceeds.
It is the practice of the Water Department to appropriate its Capital Improvement Program (CIP) plan throughout the Fiscal Year, instead of within
the annual budget ordinance, as projects commence, additional funding needs are identified, and to comply with bond covenants. The actions in
the M&C will appropriate funds in support of the Water's portion of the City of Fort Worth's Fiscal Years 2024-2028 Capital Improvement Program.
Funding for Lake Arlington Lift Station and Force Main is depicted below:
60LARFMP1 AND2-BE LTANDFN I
Capital
Fund
Project
Name
FY2024 CIP
Appropriations
Authority
Budget Change
(IncreaselDecrease]
Revised
FY2024
Name
Budget
56023-
W&S
Commercial
100995-
Lake
Arington,
$0.00
This M&C
$63,066,715.00
$63,066,715.011
Paper Fund
FM LS
and SS
Funding is budgeted in the Commercial Paper Project within the W&S Commercial Paper Fund for the purpose of the Lake Arlington Lift Station
and Force Main after the sale of Water and Sewer Bonds.
Funding for the Lake Arlington Lift Station and Force Main project is depicted below:
Existing
Additional
Fund
Appropriations
Appropriations
Project Total*
W&S Capital
Projects --Fund
$34,608.40
$0.00
$34,608.40I
56002
W&S Capital
Project 2018- Fund
$9,629,958.00
$0.00
$9,629,958.00
56014
W&S Rev Bonds
Series 2021—Fund
56019
$11,064,526.00
$0.00$11,064.526.001
i
W&S Commercial
Paper Fund 56023
$0.00
$63,066,715.00
$63,066,715.00
Project Total
$20,729,092.40
$63,066,715.00
$83,795,807.40
*Numbers rounded for presentation purposes.
Business Equity: The Business Opportunity Division placed a 16 percent business equity goal on this solicitation/contract. Belt Construction of
Texas, LLC, has agreed/committed to utilize 16.68 percent business equity subcontractor participation for the scope of work, meeting the City's
Business Equity Ordinance. Any changes in subcontractors will be reviewed by the Business Equity Division.
Business Equity: Business Equity placed a 12.90 percent business equity goal on this project. Freese and Nichols, Inc., is committing to, 3.63
percent MWBE participation, and Good Faith Effort (GFE) with supporting documentation was submitted, which is in accordance with the City`s
Business Equity Ordinance. Any changes in subcontractors will be reviewed by the Business Equity Division.
The project is located in COUNCIL DISTRICTS 5 and City of Kennedale.
FISCAL INFORMATION / CERTIFICATION:
The Director of Finance certifies that funds will be available in the Commercial Paper project within the W&S Commercial Paper Fund and upon
approval of the above recommendations and adoption of the attached appropriation ordinance, funds will be available in the W&S Commercial
Paper Fund for the Lake Arlington FM, LS and SS project to support the above recommendations and execution of the construction contract and
amendment to the engineering agreement. Prior to any expenditure being incurred, the Water Department has the responsibility to validate the
availability of funds.
Submitted for City Manager's Office by: Fernando Costa 6122
Originating Business Unit Head: Chris Harder 5020
Additional Information. ontact; April Escamilla 8455