AMENDMENT No . 3
TO CITY SECRETARY CONTRACT No. 56483
WHEREAS, the City of Fort Worth (CITY) and Teague Nall & Perkins,
Inc., (ENGINEER) made and entered into City Secretary Contract No. 56483,
(the CONTRACT) which was authorized by M&C 21-0756 on the 28th day of
September, 2021 in the amount of $456,745.00; and
WHEREAS, the CONTRACT was subsequently revised by Amendment No. 1 in
the amount of $10,440.00 administratively authorized on September 5, 2023
and Amendment No. 2 in the amount of $7,500.00 administratively
authorized on January 19, 2024; and
WHEREAS, the CONTRACT involves engineering services for the
following project:
Historic Southside Improvements; and
WHEREAS, it has become necessary to execute Amendment No. 3 to the
CONTRACT to include an increased scope of work and revised fee.
NOW THEREFORE, CITY and ENGINEER, acting herein by and through
their duly authorized representatives, enter into the following
agreement, which amends the CONTRACT:
1.
Article I of the CONTRACT is amended to include the additional
engineering services specified in proposal attached hereto and
incorporated herein. The cost to City for the additional design services
to be performed by Engineer totals $21,00.00 (Sewer).
2.
Article II of the CONTRACT is amended to provide for an increase in
the fee to be paid to Engineer for all work and services performed under
the Contract, as amended, so that the total fee paid by the City for all
work and services shall be an amount of $495,685.00.
3.
All other provisions of the Contract, which are not expressly
amended herein, shall remain in full force and effect.
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
Prof Services Agreement Amendment Template
Revision Date: November 23, 2021 [Historic Southside Improvements]
Page 1 of 2 [CPN 102932]
EXECUTED and EFFECTIVE as
designated Assistant City Manager.
APPROVED:
City of Fort Worth
William Johnson (0 t 29, 202413:36 CDT)
William Johnson
Assistant City Manager
DATE: 10/29/2024
APPROVAL RECOMMENDED:
chi-1 torher 1fader
Christopher HarQer (Oct 28, 202414:43 CDT)
Chris Harder, P.E.
Director, Water Department
Contract Compliance Manager:
of the date subscribed by the City's
ENGINEER
Teague Nall & Perkins, Inc.
Jonathan Bengfort, P.E.
Director of Engineering
Services, Associate Principal
DATE: 10/22/2024
By signing, I acknowledge that I am the person responsible for the
monitoring and administration of this contract, including ensuring all
performance and reporting requirements.
'*6. KC
Preeti KC, P.E.
Project Manager
APPROVED AS TO FORM AND LEGALITY:
4U�c
Douglas Black (Oct 29, 202412:18 CDT)
Douglas W. Black
Senior Assistant City Attorney
annn
of ........ T ➢�
p �0*0y
ATTEST:
��*'� /� adBn nezpsa4
Jannette S. Goodall
City Secretary
M&C : N/A
Date: N/A
Form 1295: N/A
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
Prof Services Agreement Amendment Template
Revision Date: November 23, 2021 [Historic Southside Improvements]
Page 2 of 2 [CPN 1029321
Contract Amendment No. 3
To:
Preeti KC, PE — City of Fort Worth
From:
Ryan Jones, PE
CC:
Jessica Hilscher, PE; Jonathan Bengfort, CFM, PE
Date:
October 17, 2024
RE:
Additional Professional Services
Historic Southside Improvements (Project No. 102932)
Mtn
1W I i www.tnpinc.com
engineers
surveyors
landscape architects
TEXAS
FORT WORTH
DENTON
ALLEN
KATY
Preeti, per the City's request, we offer this contract amendment for additional sanitary sewer design
services associated with the Historic Southside Improvements project. The City has requested TNP to
expand the scope of the project to include approximately 600 LF additional sewer line replacement
along the alley between E Cannon St and E Leuda St from S Kentucky Ave to New York Ave.
The additional efforts associated with this contract amendment include the following:
SEWER - 600 LF
1. E. Cannon Alley Sewer: Final Design and plan preparation for approximately 600 LF of 6" VC
sanitary sewer line replacement with 6" PVC sanitary sewer. ($15,000)
2. Survey Services: Collection of field data and preparation of CAD file for use in design. ($6,000)
FEE ADJUSTMENT
Based on the additional effort identified above, TNP is requesting a contract fixed fee amendment
amount of $21,000:
ORIGINAL CONTRACT AMOUNT:
CONTRACT AMENDMENT #1 AMOUNT:
CONTRACT AMENDMENT #2 AMOUNT:
CONTRACT AMENDMENT #3 AMOUNT:
TOTAL REVISED CONTRACT AMOUNT:
Sincerely,
tnp
League nail & perkins
Ryan Jones, P.E.
$456,745.00
Lump Sum Services
$10,440.00
Lump Sum Services
$7,500.00
Lump Sum Services
$21,000.00
Lump Sum Services
$495,685.00
Lump Sum Services
TNP Firm * Registrations
Texas Board of Professional Engineers and Land Surveyors I Engineering Firm No. F-230 I Surveying Firm No. 1001 1600 1 101 94381 1 10011601
Georgia Board of Professional Engineers Firm No. PEF007431 I Texas Board of Architectural Examiners Firm No. BR 2673
Level of Effort Spreadsheet
AMENDMENT 3 - TASK/HOUR BREAKDOWN
Water Department Additional Design Services for E. Cannon Alley 6" PVC Sanitary Sewer
HISTORIC SOUTHSIDE IMPROVEMENTS
City Pro,ect No. 102932
Labor (hours
Task No. Task Description
Principal
Project
Mona a
I Project
En m
EIT
CADD
RPLS
Survey
Tech
Survey
Crew
SUE Crew
Total Lobar
Rate $250
$175
$160
$135
$'125
$195
$140
$200
$200
4.0 Final Design
0
8
i6
30
40
2
0
8
0
$ 15,0
Sewer Desr Final Construction Plans and Specs
42 E. Cannon lay 6" PVC Sanitary Sewer Replacement (600 LF)
161
3
4
11
$1
I Subconsultant Ex
Subconsultant 9%rse Total Expense Task Sub Total I % Complete Remaining
Reprotluction Cost Buoget
0% $15,000
Total Hours
104
Total Labor
$21,000
Total Expense
$0
M/WBE Subconsultanf
$0
Non-M/WBE Subconsultanf
$0
5% Sub Markup
$0.00
MBE/SBE Parli 'p�tion
0 0%
Total Praia�[DO��
121,000,
Design Services
LOE Spreadsheet - Amendment 2