Loading...
HomeMy WebLinkAboutContract 58683-CO4Docusign Envelope ID: C6F21D60-985D-4021-9207-842CBE78D5BE CSC No. 58683-CO4 FORT WORTH City of Fort Worth Change Order Request Project Name:l Village Creek WRF Digester Mixing, Flare, Dome Improvements Phase 1 I City Sec No.: I 58683 Project No.(s):l 56021/0700430/5740010/001780 I M&C: 1 22-1046 I City Proj. No.:l 102652 Project Description:) Digester mixing, flare, and dome improvements, new digeseter gas dryers, and new hydrogen sulfide scrubbers. Contractor:) Eagle Contracting, LLC l Change Order# l 4 1 Date: I 10/21/2024 l City Project Mgr. I Suzy Abbe City Inspector: l Kevin Sidebottom Phone Number:) 817-392-8209 Phone Number:) 817-991-0629 Dept. Sewer Totals Contract Time (Calender days) Original Contract Amount $39,773,000.00 $39,773,000.00 1,095 Extras to Date $411,634.00 $411,634.00 Credits to Date Pending Change Orders (in M&C Process) Contract Cost to Date $40,184,634.00 $40,184,634.00 1,095 Amount of Proposed Change Order $758,116.00 $758,116.00 141 Revised Contract Amount $40,942,750.00 $40,942,750.00 1,236 Original Funds Available for Change Orders $318,184.00 $318,184.00 Remaining Funds Available for this CO $208,771.00 $208,771.00 Additional Funding (if necessary) $758,116.00 $758,116.00 CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT 1 2.94% MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%) $49,716,250.00 JUSTIFICATION (REASONS) FOR CHANGE ORDER Change Order No. 4 will provide for the following (refer to attached notes for additional detail): • Addition of 2" p-traps with insulation, heat tracing, and jacketing on H2S vessel drain lines. • Credit for downsizing wire needed for Transformers PA-9 & PA-10. • Removal of an additional 109 dry tons of solids from Digesters 7 and 8. • Additional repairs at dome supports. • Lead abatement for Digester 3 and 4 domes. • Changes to above ground piping at the chillers and dryers resulting to redesign of the chillers. • Installation of a second chemical injection port at each of Digesters 9 -14. • Sealing interior joints between radial beams and steel dome plates at Digesters 1 - 8 • Installation of two City furnished 14" low pressure digester gas valves to allow future isolation of the gas compressor building. • Installation of a 6-inch tap on new 24" high pressure digester gas line to tie-in to an existing 6-inch gas line. • 43 calendar days to Milestone 1 for City review time on submittals and the installation of two 14" low pressure digester gas valves. • 125 calendar days to Milestone 2 to address the redesign of the chillers. • 141 calendar days to Milestone 3 for rain days that affected critical path work, the change to the annular seal installation method, repairs to digester dome supports, additional sludge removal from Digesters 7 and 8, lead abatement, and joint sealant in digester domes. It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order. l Contractor's Company Name Contractor Name sijO a#fmctor Signature Date Eagle Contracting, LLC I Mike Partridge I I AA 11, p, 110/22/2024 Inspector /`-"- Director (Water Dept) CH✓iSI-00her Ifarder �ntopgern raeii)uctle 441431 Lu 1) r 'en r stant Ity Attome r M&C Number 1 24-0859 1 I ' Date Project Ma a er 5a0E520F21e6... 1 U/21/24 Date Construction �u ervisor (Water. Dept) Date As �tntityager -06 Council Action (If Required) M&C Date Approved 10/15/2024 Date 10/22/2024 Date IP- 2z-Al Date 3W OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX Docusign Envelope ID: C6F21D60-985D-4021-9207-842CBE78D5BE FORT WORTH City of Fort Worth Change Order Additions Project Name Village Creek WRF Digester Mixing, Flare, Dome Improvements Phase 1 City Sec No.: 58683 Project No.(s): 56021/0700430/5740010/001780 1 DOE No.1 22-104q City Proj. No.: 102652 Project I Digester mixing, flare, and dome improvements, new digeseter gas dryers, Description and new hydrogen sulfide scrubbers. Contractor Eagle Contracting, LLC Change Order: ® Date: 1 10/21/2024 City Project Mgr. Suzy Abbe City Inspector Kevin Sidebottom ADDITIONS HEM f_M DESGRIPHON DEPT Qty Unit Unit Cost Total 33 CMR-10 Add p-traps with heat tracing and insulation to 1-12S scrubber drains Sewer 1.00 LS $31,260.00 $31,260.00 34 CMR-22 Additional sludge removal at Digesters 7 and 8 Sewer 109.00 TN $1,000.00 $109,000.00 35 CMR-23 Additiona repairs at dome supports Sewer 1.00 LS $2,326.00 $2,326.00 36 CMR-24 Lead abatement for Digester 3 and 4 domes Sewer 1.00 LS $157,341.00 $157,341.00 37 CMR-25 Chiller pipe modifications Sewer 1.00 LS $25,309.00 $25,309.00 38 CMR-26 Installation of second chemical injection port in Digesters 9-14 Sewer 1.00 LS $16,620.00 $16,620.00 39 CMR-27 Sealing interior joints after finish coats are applied to Digesters 1-8 Sewer 1.00 LS $400,698,00 $400,698.00 40 CMR-28 Installation of two City furnished 14" digester gas valves Sewer 1.00 LS $21,672.00 $21,672.00 41 CMR-30 Installation of 6" tap on new high pressure digester gas header Sewer 1.00 LS $2,882.00 $2,882.00 42 CMR-18 Downsize wire at PA9 and 10 Sewer 1.00 LS -$8,992.00 -$8,992.00 Sewer $758,116.00 Page 1 of 1 Additions Sub Total $758,116.00 Docusign Envelope ID: C6F21D60-985D-4021-9207-842CBE78D5BE FORT WORTH_[ City of Fort Worth Change Order Deletions Project Name I Village Creek WRF Digester Mixing, Flare, Dome Improvements Phase 1 City Sec No.: I 58683 Project No.(s): I 56021/0700430/5740010/001780 1 DOE No. I 22-101 City Proj, No.: I 102652 Project Description Digester mixing, flare, and dome improvements, new digeseter gas dryers, and new hydrogen sulfide scrubbers. Contractor I Eagle Contracting, LLC I Change Order: ® Date 10/21/2024 City Project Mgr. Suzy Abbe City Inspector: I Kevin Sidebottom DELETIONS ITEM DESCRIPTION DEPT My Unit Unit Cost Total Sewer Page 1 of 1 Deletions Sub Total Docusign Envelope ID: C6F21D60-985D-4021-9207-842CBE78D5BE MIWBE Breakdown for this Change Order MWBE Sub Type of Service Amount for this CO Total $0.00 Previous Change Orders co# I DATE I AMOUNT Total $0.00 1 Page 1 of 1 Docusign Envelope ID: C6F21D60-985D-4021-9207-842CBE78D5BE 10/21/2024 CPN 102652 Digester Mixing, Flare, Dome Improvements Phase 1 Change Order 4 Notes • CMR-10C: Addition of 2" p-traps with insulation, heat tracing, and jacketing on H2S vessel drain lines. Includes insulating and heat tracing 4" drain below tanks. Heat tracing was not initially recommended by manufacturer during design. Manufacturer subsequently required it after requesting p-traps be added to the drain lines to prevent gas release. The price was adjusted upward after the initial proposal because the proposal did not include explosion proof electrical components. • CMR-1813: Credit for downsizing wire needed for Transformers PA-9 & PA-10. • CMR-22A: Removal of an additional 109 dry tons of solids from Digesters 7 and 8. Solids removal is paid by the dry ton, and the actual removal exceeded the bid quantity. 10 days of additional contract time are recommended to cover the extra work. • CMR-23: Additional repairs at dome supports per details in Field Order No. 14 and RFI-057. • CMR-2413: Lead Abatement for Digester 3 and 4 domes. Lead abatement for Digester 8 took approximately two weeks. The contractor is asking for a total of 28 days for Digesters 3 and 4. The City agrees to add 14 days for Digester 3. Additional time for Digester 4 is not granted at this time because the work is not on critical path. • CMR-256: Changes to above ground piping at the chillers and dryers per Field Order No. 9. The changes resulted from a manufacturer redesign of the chillers resulting in larger service water pipe and longer runs of pipe. • CMR-26: Installation of a second chemical injection port at each of Digesters 9 - 14 per Field Order No. 13 including insultation repair. Two ports are needed Digesters 9 - 14 to allow better dispersal of chemical into a digester. Only one port was included in the original design. • CMR-27A: Sealing interior joints between radial beams and steel dome plates with single bead of sealant after finish coatings are applied at Digesters 1- 8. Sealing of the interior joints was recommended by the manufacturer after a series of holiday test failures at joints. Staff concurs with the contractor's request of 40 additional calendar days to complete the work. • CMR-28: Installation of two City furnished 14" low pressure digester gas valves to allow future isolation of the gas compressor building from digester gas. • CMR-30: Installation of a 6" tap on new 24" HDG line to tie-in to an existing 6" HDG as directed in RFI-73. The tap was not originally shown on the plans. • Contract Time: After a detailed review of work activities, staff recommends additional calendar days be added to the contract as follows: o Milestone 1: 43 calendar days for owner submittal review times exceeding time allowed in contract. o Milestone 2: 125 calendar days to cover half of the chiller and dryer submittal period which was in part extended due to a redesign. o Milestone 3: 154 calendar days to cover the 64 days summarized in Table 1 plus 17 rain days that delayed critical path activities, 20 days for digester 8 lead abatement, 39 days for the change to the annular seal installation method, and 14 days for repairs to the digester dome supports prior to the installation of the annular seal. Only 141 days were Docusign Envelope ID: C6F21D60-985D-4021-9207-842CBE78D5BE mistakenly requested in the M&C for Change Order No. 4. 13 additional days will be added to the next change order to cover the full amount. Labor hours, material costs, and quantities in the contractors' proposal were reviewed. Approved CMR's are saved in E-builder. A summary of negotiations is provided in Table 1. Table 1- CMR Price Negotiations CMR Days Original Proposal COF Counter Approved Price CMR-10C 0 $ 14,346.00 $ - $ 31,260.00I CMR-18B 0 $ (1,847.00) $ - $ (8,992.00) CMR-22A 10 $ 116,147.00 $ - $ 109,000.00I CMR-23 0 $ 2,326.00 $ - $ 2,326.00 CMR-24B 14 $ 153,257.00 $ - $ 157,341.00 CMR-25B 0 $ 29,484.00 $ - $ 25,309.00 CM R-26A 0 $ 16,620.00 $ - $ 16,620.00 CM R-27A 40 $ 390,306.00 $ - $ 400,698.00 CMR-28 0 $ 21,672.00 $ - $ 21,672.00 CMR-29 0 $ 2,882.00 $ - $ 2,882.00I Total 65 I $745,193.00 $0.00 $ 758,116.00I Contract Compliance Manager By signing I acknowledge that I am the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements. .^,.�44�- Signature Suzanne Abbe Name of Employee Senior Engineer, Capital Project Delivery Title 400vo4p� a f�RTIlad ATTEST: p-o oxd /� d�a� nEXA?oa Jannette Goodall City Secretary Docusign Envelope ID; C6F21D60-985D-4021-9207-842CBE78D5BE CITY COUNCIL AGENDA Create New From This M&C official site of the City of Fort Worth, Texas FORT�TII REFERENCE **M&C 24- 60VCWRF DIGESTER MIXING - DATE: 10/15/2024 NO.: 0856 LOG NAME: FLARE -DOME IMPROVP1CO4- EAGLE CODE: C TYPE: CONSENT PUBLIC NO HEARING: SUBJECT: (CD 5) Authorize Execution of Change Order No. 4 in the Amount of $776,100.00 to a Contract with Eagle Contracting, LLC., for the Village Creek Water Reclamation Facility's Digester Improvements Project RECOMMENDATION: It is recommended that the City Council authorize execution of Change Order No. 4 in an amount of $776,100.00 to City Secretary Contract No. 58683 with Eagle Contracting, LLC, for the Village Creek Water Reclamation Facility's Digester Improvements project (City Project No. 102652) for a revised contract amount of $40,960,734.00. DISCUSSION: On December 13, 2022, Mayor and Council Communication (M&C) 22-1046, the City Council authorized a contract with Eagle Contracting, LLC. for construction of the Village Creek Water Reclamation Facility (VCWRF) Digester Improvements project for an amount of $39,773,000.00. The contract was subsequently revised by Change Order No. 1 with a net total amount of $13,120.00 after deducts administratively authorized November 29, 2023, that provided for adjustments to piping and concrete pads due to utility conflicts, replacement of door hardware in a control building with panic hardware, changes to pressure sensing piping at the proposed flares to reduce pressure swings at the digesters, Change Order No. 2 with a net total amount of $302,221.00 after deducts authorized by the City Council on April 23, 2024, (M&C 24-0355) that provided an additional cleanout in a 14-inch digested sludge line, the inclusion of a layer of asphalt in the annular seals for Digesters 1 through 8 for a longer lasting and robust gas seal, adjustments to the chiller concrete pad and piping, bracket and additional concrete repairs for Digesters 7 and 8, and lead remediation for Digester 8, and Change Order No. 3 with a total amount of $96,293.00 after deducts administratively authorized July 9, 2024, that provided for bypass piping to redirect digester gas during a tie-in. Change Order No. 4 in the amount of $776,100.00 will provide for the following that are necessary on the project. The addition of p-traps with insulation, heat tracing, and jacketing on H2S (Hydrogen Sulfide) vessel drain lines; credit for downsizing wire needed for Transformers PA-9 & PA-10; removal of an additional 109 dry tons of solids from Digesters 7 and 8; additional repairs at dome supports; lead abatement for Digesters 3 and 4 domes; changes to above ground piping at the chillers and dryers resulting in redesign of the chillers; installation of a second chemical injection port Digesters 9 through 14; sealing interior joints between at the steel dome Digesters 1 through 8 after coating; installation of two City furnished 14" low pressure digester gas valves; and installation of a 6-inch tap on new 24 inch high pressure digester gas line. Additionally, staff recommends the addition of 43 calendar days to Milestone 1, 125 calendar days to Milestone 2, and 141 calendar days to Milestone 3. This M&C will be funded with current remaining balances in the Sewer Capital Legacy Fund -refer to M&C 23-0498. Funding for VCWRF Facility's Digester Improvements project is depicted below: Fund Existing Additional project Total* ( Appropriations I Appropriations Docusign Envelope ID: C6F21D60-985D-4021-9207-842CBE78D5BE W&S Rev Bonds Series 2021 - $1,020,150.00 $0.00 $1,020,150.00 Fund 56019 _ W&S Rev Bonds Series 2022 - $2,218,432.00 $0.00 $2,218,432.00 Fund 56020 W&S Rev Bonds _ Series 2023 - $25,302,221.00 $0.00 $25,302,221.00 Fund 56021 Water/Sewer Gas Lease Cap $16,763,858.00 $0.00 $16,763,858.00 Proj - Fund 53004 W&S Capital---- ---- --- —-------- --- Projects - Fund $4,122,829.54 $0.00 $4,122,829.54 56002 Sewer Capital Legacy - Fund $1,284,942.08 $0.00 $1,284,942.08 59607 Project Total $50,712,432.62 $0.00 $50,712,432.62 *Numbers rounded for presentation purposes. The Business Equity Division placed a 5.67 percent business equity goal on this contract. Eagle Contracting LLC., submitted a Good Faith Effort (GFE) with supporting documentation, which is in accordance with the City's Business Equity Ordinance. The project is located in COUNCIL DISTRICT 5. FISCAL INFORMATION/CERTIFICATION: The Director of Finance certifies that funds are currently available in the Digester Improvement project within Sewer Capital Legacy Fund to support the approval of the above recommendation and execution of the change order. Prior to an expenditure being incurred, the Water Department has the responsibility of verifying the availability of funds. TO Fund Department Account Project Budget Reference # Amount ID I I ID I Program I Activity I Year I (Chartfield 2) FROM Fund Department Account Project Program Activity Budget Reference # Amount ID I I ID I I Year I (Chartfield 2) Submitted for Citv Manaqer's Office bv: Fernando Costa (6122) Originating Department Head: Chris Harder (5020) Additional Information Contact:, Suzanne Abbe (8209) Docusign Envelope ID: C6F21D60-985D-4021-9207-842CBE78D5BE ATTACHMENTS 24-0102652 Compliance Memo Approved-NS Updated.pdf (CFW Internal) 60VCWRF DIGESTER MIXING -FLARE -DOME IMPROVP1 CO4- EAGLE Updated FID table (WCF 08.05.24).xlsx (CFW Internal) 60VCWRF DIGESTER MIXING -FLARE -DOME IMPROVP1CO4-EAGLE&HAZE NS MAP,pdf (Public) 60VCWRF DIGESTER MIXING -FLARE -DOME IMPROVP1CO4-EAGLE funds availability..pdf (CFW Internal) Form 1295.pdf (CFW Internal) PBS CPN 102652.Ddf (CFW Internal) SAM.gov search Eagle Contracting, LLC.pdf (CFW Internal) FIDs (Budget) Rec # Fund Dept # Account Project Activity Budget CF 2 Program Amount Purpose Xfer �ID Year Rec # Fund Dept # Account Project Activity Budget CF 2 Program Amount Purpose Xfer ID Year M MMWE FIDs REVENUE or EXPENSE - IVo KK or 3L Entries Needed Rec # Fund Dept # Account Project Activity Budget CF 2 Program Amount Purpose Xfer �ID Year