HomeMy WebLinkAboutContract 58921-A1FP1FORT WORTHa
FP1
City Secretary
Contract No. 58921-A1
Date Received 11/4/2024
AT
NOTICE OF PROJECT COMPLETION
(Developer Projects)
The Transportation and Public Works Department upon the recommendation of the Project
Manager has accepted the following project as complete:
Project Name:: Wellington Area 3 North Ph. 1A
City Project No.: 103805
Improvement Type(s): x❑ Paving ❑x Drainage x❑ Street Lights
Original Contract Price: $6,422,669.00
Amount of Approved Change Order(s):-$78,262.00
Revised Contract Amount: $6,344,407.00
Total Cost of Work Complete: $6,344,407.00
Jav Iell (Oct 19. 202413:21 CDT) Oct 19, 2024
Contractor Date
Project manager
Title
Conatser Construction
Company Name
❑ Traffic Signals
Oct 19 2024
Richard la den (Oct 19. 202418:28 CDP
Project Inspector
Date
Nov 3, 2024
Project Manager
Date
i�
Nov 4, 2024
Rebecca Owen (Nov 4. 202408:06 CST)
CFA Manager
Date
le&�
Nov 4, 2024
TPW Director
Date
Nov 4, 2024
Asst. City Manager
Date
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
Page 1 of 2
Notice of Project Completion
Project Name:: Wellington Area 3 North Ph. 1A
City Project No.: 103805
City's Attachments
Final Pay Estimate x❑
Change Order(s): ❑x Yes ❑ N/A
Contractor's Attachments
Affidavit of Bills Paid
Consent of Surety
Statement of Contract Time
Contract Time:239 WD Days Charged: 229 WD
Work Start Date: 4/24/2023 Work Complete Date: 7/2/2024
Completed number of Soil Lab Test: 2525
Completed number of Water Test: 38
Page 2of2
FoRTWORTH
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name WELLINGTON AREA 3 NORTH PHASE lA
Contract Limits
Project Type DRAINAGE IMPROVEMENTS
City Project Numbers 103805
DOE Number 3805
Estimate Number 1 Payment Number 1
City Secretary Contract Number
Contract Date 3/2/2023
For Period Ending
Project Manager NA
Contractor CONATSER CONSTRUCTION TxLP
5327 WICHITA ST
FORT WORTH, TX 76119
Inspectors G. DEYON / J. RUIZ
Contract Time
Days Charged to Date
Contract is 100.00
7/2/2024
WD
23WD
229
Complete
Wednesday, October 9, 2024 Page 1 of 6
City Project Numbers 103805 DOE Number 3805
Contract Name WELLINGTON AREA 3 NORTH PHASE lA Estimate Number I
Contract Limits Payment Number 1
Project Type DRAINAGE IMPROVEMENTS For Period Ending 7/2/2024
Project Funding
UNIT III: DRAINAGE IMPROVEMENTS
Item
Description of Items
Estimated Unit
Unit Cost
Estimated
Completed
Completed
No.
Quanity
Total
Quanity
Total
1
0000.3305 Trench Safety
9480 LF
$2.00
$18,960.00
9480
$18,960.00
2
3137.0101 12" Concrete Riprap
624 SY
$120.00
$74,880.00
624
$74,880.00
3
3 341.020121" RCP, Class lII
802 LF
$65.00
$52,130.00
802
$52,130.00
4
3341.0205 24" RCP, Class III
3597 LF
$70.00
$251,790.00
3597
$251,790.00
5
3341.0208 27" RCP, Class 111
333 LF
$75.00
$24,975.00
333
$24,975.00
6
3341.0302 30" RCP, Class III
25 LF
$85.00
$2,125.00
25
$2,125.00
7
3341.0309 36" RCP, Class 111
143 LF
$110.00
$15,730.00
143
$15,730.00
8
3341.0402 42" RCP, Class III
298 LF
$145.00
$43,210.00
298
$43,210.00
9
3341.0409 48" RCP, Class lII
1093 LF
$180.00
$196,740.00
1093
$196,740.00
10
3341.0502 54" RCP, Class III
618 LF
$230.00
$142,140.00
618
$142,140.00
11
3341.1203 5x5 Box Culvert
506 LF
$320.00
$161,920.00
506
$161,920.00
12
3341.1403 7x5 Box Culvert
455 LF
$460.00
$209,300.00
455
$209,300.00
13
3341.1502 8x5 Box Culvert
80 LF
$490.00
$39,200.00
80
$39,200.00
14
3341.1602 9x5 Box Culvert
837 LF
$610.00
$510,570.00
837
$510,570.00
15
3341.1603 9 x 6 Box Culvert
462 LF
$650.00
$300,300.00
462
$300,300.00
16
3341.1604 9x7 Box Culvert
231 LF
$710.00
$164,010.00
231
$164,010.00
17
3349.0001 4'Storm Junction Box
12 EA
$5,500.00
$66,000.00
12
$66,000.00
18
3349.0002 5' Storm Junction Box
4 EA
$6,500.00
$26,000.00
4
$26,000.00
19
3349.0003 6' Storm Junction Box
3 EA
$8,500.00
$25,500.00
3
$25,500.00
20
3349.0102 4' Manhole Riser
5 EA
$4,500.00
$22,500.00
5
$22,500.00
21
3349.0105 5-Sided Manhole
1 EA
$11,500.00
$11,500.00
1
$11,500.00
22
3349.5001 10' Curb Inlet
24 EA
$3,400.00
$81,600.00
24
$81,600.00
23
3349.5002 15' Curb Inlet
21 EA
$4,400.00
$92,400.00
21
$92,400.00
24
3349.7001 4' Drop Inlet
2 EA
$5,500.00
$11,000.00
2
$11,000.00
25
9999.0007 6-9'x5' 4:1 PW-1 Wingwall
2 EA
$85,000.00
$170,000.00
2
$170,000.00
26
9999.0008 9'x5' 4:1 PW-1 Wingwall
1 EA
$35,000.00
$35,000.00
1
$35,000.00
27
9999.0009 3-9'x7' & 6-9'x6' 4:1 FW-S Wingwall
2 EA
$235,000.00
$470,000.00
2
$470,000.00
28
9999.0010 Inlet Protection
47 EA
$150.00
$7,050.00
47
$7,050.00
29
9999.0012 27" 4:1 Sloped End Headwall
1 EA
$3,500.00
$3,500.00
1
$3,500.00
30
9999.0016 Concrete Apron
1058 SY
$120.00
$126,960.00
1058
$126,960.00
Wednesday, October 9, 2024 Page 2 of 6
City Project Numbers 103805
Contract Name WELLINGTON AREA 3 NORTH PHASE lA
Contract Limits
Project Type DRAINAGE IMPROVEMENTS
Project Funding
DOE Number 3805
Estimate Number 1
Payment Number 1
For Period Ending 7/2/2024
Sub -Total of Previous Unit $3,356,990.00 $3,356,990.00
-------------
UNIT IV: PAVING IMPROVEMENTS
Item
Description of Items
Estimated Unit
No.
Quanity
1
3211.0400 Hydrated Lime (Streets)
825 TN
2
3211.0400 Hydrated Lime (Alleys)
2 TN
3
3213.0101 6" Cone Pvmt (Streets)
48354 SY
4
3213.0101 6"Conc Pvmt (Alleys)
83 SY
5
3211.0501 6" Lime Treatment (32#/SY) (Streets)
51578 SY
6
3211.0501 6" Lime Treatment (32#/SY) (Alleys)
91 SY
7
3213.0302 5' Conc Sidewalk (CO #2)
58700 SF
8
3213.0501 Barrier Free Ramp, Type R-1
8 EA
9
3213.0506 Barrier Free Ramp, Type P-1
32 EA
10
3292.0201 Utility Service Surface Restoration
577 SY
Seeding
11
3471.0001 Traffic Control
1 MO
12
3291.0100 Topsoil (CO #2)
0 CY
13
3292.0400 Seeding, Hydromulch (CO #2)
0 SY
14
9999.0017 8' Conc Sidewalk (CO #2)
4705 SF
15
9999.0020 Furnish/Install Sign Post & Foundation
27 EA
16
9999.0021 Stop Sign (RI-1)
22 EA
17
9999.0022 Street Name Blade
96 EA
18
9999.0023 Sawcut and Match Existing Pavement
125 LF
19
9999.0024 Stamped or Stained Concrete Paver
1895 SF
20
6' Concrete Sidewalk
2909 SF
Sub -Total of Previous Unit
-------------------
UNIT V: STREET LIGHTING IMPROVEMENTS
Unit Cost
Estimated
Completed
Completed
Total
Quanity
Total
$210.00
$173,250.00
825
$173,250.00
$210.00
$420.00
2
$420.00
$37.50
-,813,275.00
48354
1,813,275.00
$38.50
$3,195.50
83
$3,195.50
$3.25
$167,628.50
51578
$167,628.50
$3.50
$318.50
91
$318.50
$4.50
$264,150.00
58700
$264,150.00
$1,800.00
$14,400.00
8
$14,400.00
$1,800.00
$57,600.00
32
$57,600.00
$8.00
$4,616.00
577
$4,616.00
$3,500.00
$3,500.00
1
$3,500.00
$32.00
$0.00
0
$0.00
$2.00
$0.00
0
$0.00
$5.50
$25,877.50
4705
$25,877.50
$500.00
$13,500.00
27
$13,500.00
$500.00
$11,000.00
22
$11,000.00
$250.00
$24,000.00
96
$24,000.00
$40.00
$5,000.00
125
$5,000.00
$23.50
$44,532.50
1895
$44,532.50
$5.50
$15,999.50
2909
$15,999.50
$2,642,263.00 $2,642,263.00
Item Description of items
Estimated Unit
Unit Cost
Estimated
Completed
Completed
No.
Quanity
Total
Quanity
Total
1 2605.3015 2" CONDT PVC SCH 80 (T)
8053 LF
$14.00
$112,742.00
8053
$112,742.00
2 3441.1408 NO 6 Insulated Elec Condr
8053 LF
$4.00
$32,212.00
8053
$32,212.00
3 3441.1701 TY 7 Signal Foundation
91 EA
$1,200.00
$109,200.00
91
$109,200.00
Wednesday, October 9, 2024 Page 3 of 6
City Project Numbers 103805
Contract Name WELLINGTON AREA 3 NORTH PHASE lA
Contract Limits
Project Type STREET LIGHTING IMPROVEMENTS
Project Funding
4 Furnish/Install Wash. Postline Series Luminaire Full
Cutoff LED & Pole
DOE Number 3805
Estimate Number 1
Payment Number 1
For Period Ending 7/2/2024
91 EA $1,000.00 $91,000.00 91 $91,000.00
Sub -Total of Previous Unit $345,154.00 $345,154.00
Wednesday, October 9, 2024 Page 4 of 6
City Project Numbers 103805
Contract Name WELLINGTON AREA 3 NORTH PHASE lA
Contract Limits
Project Type STREET LIGHTING IMPROVEMENTS
Project Funding
Contract Information Summary
Original Contract Amount
Change Orders
Change Order Number 2
DOE Number 3805
Estimate Number 1
Payment Number 1
For Period Ending 7/2/2024
$6,422,669.00
($78,262.00)
Total Contract Price $6,344,407.00
Total Cost of Work Completed $6,344,407.00
Less % Retained $0.00
Net Earned $6,344,407.00
Earned This Period $6,344,407.00
Retainage This Period $0.00
Less Liquidated Damages
Days @ / Day
LessPavement Deficiency
Less Penalty
Less Previous Payment
Plus Material on Hand Less 15%
Balance Due This Payment
$0.00
$0.00
$0.00
$0.00
$0.00
$6,344,407.00
Wednesday, October 9, 2024 Page 5 of 6
City Project Numbers 103805
Contract Name WELLINGTON AREA 3 NORTH PHASE lA
Contract Limits
Project Type STREET LIGHTING IMPROVEMENTS
Project Funding
Project Manager NA
Inspectors G. DEYON / J. RUIZ
Contractor CONATSER CONSTRUCTION TxLP
5327 WICHITA ST
FORT WORTH, TX 76119
DOE Number 3805
Estimate Number 1
Payment Number 1
For Period Ending 7/2/2024
City Secretary Contract Number
Contract Date
3/2/2023
Contract Time
239 WD
Days Charged to Date
229 WD
Contract is .000000
Complete
CITY OF FORT WORTH
SUMMARY OF CHARGES
Line Fund Account Center Amount Gross Retainage Net
Funded
Total Cost of Work Completed $6,344,407.00
Less % Retained $0.00
Net Earned $6,344,407.00
Earned This Period $6,344,407.00
Retainage This Period $0.00
Less Liquidated Damages
0 Days @ $0.00 / Day
$0.00
LessPavement Deficiency
$0.00
Less Penalty
$0.00
Less Previous Payment
$0.00
Plus Material on Hand Less 15%
$0.00
Balance Due This Payment
$6,344,407.00
Wednesday, October 9, 2024 Page 6 of 6
DEVELOPER -AWARDED -PROJECT CHANGE ORDER
PROJECT NAME:
Wellinqton Area 3 North Phase 1A
CHANGE
CONTRACT:
Water, Sewer, Drainage, Pavinq, and Street Liqht Improvements
ORDER No:
CFA #
22-0158 CITY PARTICIPATION:
No
CITY PROJECT #
103805
FID #
30114-0200431-103805-EO7685
X #
X-27264
FILE #
W-2823
INSPECTOR:
James Ruiz Phone No:
817-205-1256
PROJECT MANAGER:
Sandip Adhikari Phone No:
817-392-8424
CONTRACT UNIT
WATER SEWER
PAVING DRAINAGE
I STREET LIGHTS
I CONTRACT DAYS
I
b eveloper
Developer Cost
City Cost
Developer Cost
City Cost
Developer Cost
City Cost
Developer Cost
City Cost
Cost
City Cost
ORIGINAL CONTRACT
$1,152,710.00
I $1,132,611.00
$2,720,525.00 I I $3,356,990.00
$345,154.00
239
EXTRAS TO DATE
CREDITS TO DATE
CONTRACT TO DATE
$1,152,710.00
$0.00 I $1,132,611.00
$0.00
$2,720,525.00 I $0.00 I $3,356,990.00
$0.00
$345,154.00
$0.00
239
AMOUNT OF PROP. CHANGE ORDER
$23,750.00
I
I I
0
REVISED CONTRACT AMOUNT
$1,176,460.00
$0.00 I $1,132,611.00
$0.00
$2,720,525.00 I $0.00 I $3,356,990.00
$0.00
$345,154.00
$0.00
239
TOTAL REVISED CONTRACT AMOUNT
PER UNIT
$1,176,460.00
$1,132,611.00
$2,720,525.00
$3,356,990.00
$345,154.00
REVISED COST SHARE
Dev. Cost: $8,731,740.00
City Cost:
$0.00
TOTAL REVISED CONTRACT
$8,731,740.00
REVIEWED
By Sandip Adhikari at 3:27 pm, Sep 29, 2024
Revised: 10-12-2011 Page 1
Asterisk (') indicates New Pay Item
You are directed to make the following
changes in the contract documents:
UNIT I: WATER IMPROVEMENTS
CITY BID ITEM
PAY ITEM #
# QUANTITY UNIT
I 12
3312.3003 1 EA
I 20'
9999.0020 7 EA
TOTAL
REASONS FOR CHANGE ORDER 2" Irrigation services added to plans. Added one 8" Gate Valve
RECOMMENDED:
LJA Engineering
By: /!
Name: Andrew Kubiak. P.E.
Title: Sr. Proiect Enaineer
ITEP SEf CoalveON
8"x2" Irrigation Tao
APPROVED:
HPC Wellington Nance Development Corporation
By: 1� Z_zaQ
Name: Ben Luedtke
Title: Executive Vice President
UNIT PRICE
$ 1,350.00 $
$ 3,200.00 $
$
APPROVED:
Conatser Can TX
�cttiio%n
Name:
Brock Huggins
Title:
PreqWent
REVIEWED
By Sandip Adhikari at 11:38 am, Aug 28, 2024
TOTAL
1,350.00
2 400.00
2 ,750.00
Revised: 10-12-2011 Page 2
PROJECT NAME:
CONTRACT:
CFA #
CITY PROJECT #
FID #
X#
FILE #
INSPECTOR:
PROJECT MANAGER:
ORIGINAL CONTRACT
EXTRAS TO DATE
CREDITS TO DATE
CONTRACT TO DATE
AMOUNT OF PROP. CHANGE ORDER
REVISED CONTRACT AMOUNT
TOTAL REVISED CONTRACT AMOUNT
PER UNIT
REVISED COST SHARE
TOTAL REVISED CONTRACT
DEVELOPER -AWARDED -PROJECT CHANGE ORDER
Wellinqton Area 3 North Phase 1A
Water, Sewer, Drainage, Pavinq, and Street Liqht Improvements
22-0158 CITY PARTICIPATION
103805
30114-0200431-103805-EO7685
X-27264
W-2823
James Ruiz Phone No
Sandip Adhikari Phone No
WATER I SEWER
Developer Cost City Cost Developer Cost
$1,152,710.00 I $1,132,611.00
$23,750.00
$1,176,460.00
$0.00
1 $1,132,611.00
$1,176,460.00
$0.00
I $1,132,611.00
No
817-205-1256
817-392-8424
CONTRACT UNIT
PAVING
Cost Developer Cost City Cost
$2,720,525.00
$0.00
$1,176,460.00 $1,132,611.00
Dev. Cost: $8,653,478.00
CHANGE
ORDER No:
2
I
DRAINAGE I STREET LIGHTS I CONTRACT DAYS
beveloper
)eveloper Cost City Cost Cost City Cost
$3,356,990.00 $345,154.00 239
$2,720,525.00 1 $0.00 1 $3,356,990.00 $0.00 $345,154.00 $0.00 239
$ (78,262.00)I I 0
$2,642,263.00 I $0.00 I $3,356,990.00 $0.00 $345,154.00 $0.00 239
$2,642,263.00 $3,356,990.00 $345,154.00
City Cost: $0.00
$8,653,478.00
REVIEWED
By Sandip Adhikari at 3:46 pm, Sep 29, 2024
Revised: 10-12-2011 Page 1
Asterisk (*) indicates New Pay Item
You are directed to make the following
changes in the contract documents:
UNIT IV: PAVING IMPROVEMENTS
CITY BID ITEM
PAY ITEM #
#
QUANTITY
7
3213.0302
13,305
14
3291.0100
-1.182
15
3292.0400
-10.635
16
9999.0014
-17 Z80
22*
9999.0021
2,609
UNIT
ITEM DESC eeTIOyy
UNIT PRICE
TOTAL
SF
5' Concreteldewalk
$ 4.50
$
59,872.50
CY
SY
TqF pil
Seeding. F^^�� romulch
$ 32.00
$ 2.00
$
$
824.00)
570.00)
E.040.00)
SF
8' Concrete Sidewalk
$ 5.50
$
SF
6' Concrete Sidewalk
$ 5.50
$
15 999.50
TOTAL
$
(78562.00)
REASONS FOR CHANGE ORDER Sidewalk changes due to updated landscape plans. Topsoil/Seeding changes due to alternate method provided by Contractor and approved by COFW.
RECOMMENDED:
LJA Engineering
By: (� iIe
Name: Andrew Kubiak, P.E.
Title: Sr. Proiect Enoineer
APPROVED:
HPC Wellington Nance Development Corporation
By: i Z-Z�
Name: Ben Luedtke
Title: Executive Vice President
APPROVED:
Conatser,' rstmction TX
By.
Name: Brock Huggins
Title: President
REVIEWED
By Sandip Adhikari at 11:39 am, Aug 28, 2024
Revised: 10-12-2011 Page 2
FORTWORTH.
TRANSPORTATION AND PUBLIC WORKS
October 3, 2024
Conatser Construction TX. L.P
5327 Wichita St
Forest Hill, TX 76119
RE: Acceptance Letter
Project Name: Wellington Area 3 North Ph 1A
Project Type: Water, Sewer, Drainage, Paving & Street Light
City Project No.: 103805
To Whom It May Concern:
On July 2, 2024 a final inspection was made on the subject project. There were no punch list items
identified at that time. The final inspection indicates that the work meets the City of Fort Worth
specifications and is therefore accepted by the City. The warranty period will start on July 2, 2024,
which is the date of the final inspection and will extend of two (2) years in accordance with the Contract
Documents.
If you have any questions concerning this letter of acceptance, please feel free to contact me at . Sr.
Professional Engineer, T: 817.392.8424.
Sandip Adhikari, Project Manager
Cc: Richard Walden, Inspector
Gary Deyon, Inspection Supervisor
Edward Davila, Senior Inspector
Andrew Goodman, Program Manager
UA Engineering, Inc, Consultant
Conatser Construction TX, L.P., Contractor
Hanover Property Company, Developer
File
E-Mail: TPW_Acceptance@fortworthtexas.gov
Rev. 08/20/19
AFFIDAVIT
STATE OF TEXAS
COUNTY OF TARRANT
Before me, the undersigned authority, a Notary Public in the state and county aforesaid,
on this day personally appeared Brack Huggins, President of Conatser Management Group, Inc_,
general partner of C-onatser Construction TX. LP, known to me to be a credible person, who
being by me duly sworn, upon his oath deposed and said.
That all persons, firms, associations, corporations or other organizations furnishing
labor and/or materials have been paid in full;
That the wage scale established by the City Council in the City of Fart Worth, has
been paid in full; and
That there are no claims pending for personal injury and/or property damages;
On Contract described as:
WELLINGTON pRRdl 3 NORTH PH. lA
WATER, SANITARY SEWER, DRAINAGE,
PAYING, & STREET LIGHT IMPROVEMENTS
CFA PRJ #. 22-0I58
CITY PROJECT #:103805
CITY OF FORT WORTH
STATE OF TEXAS
CONATSER CONSTRUCTION TX, LP
Brock Hug
Subscribed and sworn to before me this 22"d day of April, 2024.
Top
pywt Um of
Notary Public in Tarrant. County, Texas
CONSENT OF
SURETY COMPANY
TO FINAL PAYMENT
Conforms with the American Institute of
ArctdtecU. AIA Document G707
PROJECT:
(name, addreSS)Wellington Area 3 North Phase 1A
Fort Worth, TX
TO (Owner)
OWNER
❑
ARCHITECT
CONTRACTOR
❑
SURETY
❑
OTHER
Band No 0256223
HP VVELLINGT0N NAMCE DEVELORMENT i ARCHITECT'S PROJECT NO: CFA Nn zz-o15s
CORPORATION AND THE CrTY OF FORT MRTH CONTRACT FOR:
-IM1 Knox St_. Suite 445 Vlieltirgton Area 3 ;Norh Phase 1A - Water. Sewer. Paving. Dramage.
a Jtr9'{ 1.Ight IMPTUVer*7ern'5
1101I3S TX 75205 J CONTRACT DATE;
CONTRACTOR: CONATSER CONSTRUCTION TX. L.P
In accordance with the provisions of the Contract between the Owner and the Contractor as indicated above, the
pun i tmn :tame and address of Surety Comuonyl
BERXLEY INSURANCE COMPANY
475 Steamboat Raab
Greerlw r,h CT C6830 , SURETY COMPANY
on bond of (hers insert name end addrass of CCnInwi-or)
CONATSER CONSTRUCTION TX, L P
5327 V► ichda St
Fort Worth TX 76119-6035
, CONTRACTOR.
hereby approves of the Final payment to the Contractor, and agrees that final payment to the Contractor shall not relieve
the Surety Company of any of its obligations to Mwo r5art nine afld sddrm of Ownafi
HP WELLINGTON NANCE DEVELOPMENT CORPORATION AND THE CITY OF FORT WORTH
3001 Knox St.. Suite 405
Dallas TX 75205
as set forth in the said Surety Company's bond.
IN WrrNESS, WHEREOF,
the Surety Company has hereunto set its hand this
Attest:
(Seal):
19th day of April. 2024
BERKLEY INSURANCE COMPANY
Surety Company
Signature of Authorized Representative
i orates
Title
, OWNER,
Attorney -in -Fact
NOTE: This form is to be usea as a :umpar`an docurnart ,o ALA DOWMENT G705, CONTRACTOR'S AFFQAVIT OF PAYMENT OF DEBTS AND CLAMS.
Currant Edition
ONE PAGE