NOTICE OF PROJECT COMPLETION
(Developer Projects)
The Transportation and Public Works Department upon the recommendation of the Project
Manager has accepted the following project as complete:
Project Name: Retreat at Fossil Creek Phase 2
City Project No.: 103149
Improvement Type(s): x❑ Paving ❑x Drainage
Original Contract Price:
Amount of Approved Change Order(s):
Revised Contract Amount:
Total Cost of Work Complete:
I&,
Arturo Sa nce n (Nov 5. 202416:13 CST)
Contractor
Superintendent
Title
Conatser Construction TX., LP.
Company Name
Project Inspector
Pont Ti wa ri (Nov 6, 2024 11:15 CST)
Project Manager
_U41^
Rebecca Owen (Nov 6.202411:28 CST)
CFA Manager
TPW Director
Asst. City Manager
x❑ Street Lights ❑ Traffic Signals
$3,131,708.50
$24,375.00
$3,156,083.50
$3,156,083.50
Nov 5, 2024
Date
Nov 5, 2024
Date
Nov 6, 2024
Date
Nov 6, 2024
Date
Nov 6, 2024
Date
Nov 6, 2024
Date
OFFICIAL RECORD
CITY SECRETARY Page 1 of 2
FT. WORTH, TX
Notice of Project Completion
Project Name: Retreat at Fossil Creek Phase 2
City Project No.: 103149
City's Attachments
Final Pay Estimate x❑
Change Order(s): ❑x Yes ❑ N/A
Contractor's Attachments
Affidavit of Bills Paid
Consent of Surety
Statement of Contract Time
Contract Time 230 WD Days Charged: 211 WD
Work Start Date: 12/12/2022 Work Complete Date: 10/22/2024
Completed number of Soil Lab Test: 958
Completed number of Water Test: 38
Page 2of2
FoRTWORTH
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name RETREAT AT FOSSIL CREEK PHASE 2
Contract Limits
Project Type DRAINAGE, PAVING & STREETLIGHT IMPROVE
City Project Numbers 103149
DOE Number 3149
Estimate Number 1 Payment Number 1 For Period Ending 10/22/2024
WD
City Secretary Contract Number Contract Time 23WD
Contract Date 9/12/2022 Days Charged to Date 211
Project Manager NA Contract is 100.00 Complete
Contractor CONATSER CONSTRUCTION TxLP
5327 WICHITA ST
FORT WORTH, TX 76119
Inspectors M. GLOVER / E. WALKER
Tuesday, November 5, 2024 Page 1 of 5
City Project Numbers 103149 DOE Number 3149
Contract Name RETREAT AT FOSSIL CREEK PHASE 2 Estimate Number I
Contract Limits Payment Number 1
Project Type DRAINAGE, PAVING & STREETLIGHT IMPROVEMENTS For Period Ending 10/22/2024
Project Funding
UNIT III: DRAINAGE IMPROVEMENTS
Item
Description of Items
Estimated Unit
Unit Cost
Estimated
Completed
Completed
No.
Quanity
Total
Quanity
Total
1
TRENCH SAFETY
5466 EA
$1.00
$5,466.00
5466
$5,466.00
2
10' CURB INLET
40 EA
$3,400.00
$136,000.00
40
$136,000.00
3
15' CURB INLET
3 EA
$4,400.00
$13,200.00
3
$13,200.00
4
54" RCP, Class lII
166 LF
$215.00
$35,690.00
166
$35,690.00
5
48" RCP, Class lII
104 LF
$180.00
$18,720.00
104
$18,720.00
6
42" RCP, Class III
1127 LF
$155.00
$174,685.00
1127
$174,685.00
7
36" RCP, Class lII
907 LF
$115.00
$104,305.00
907
$104,305.00
8
30" RCP, Class lII
585 LF
$95.00
$55,575.00
585
$55,575.00
9
27" RCP, Class lII
428 LF
$85.00
$36,380.00
428
$36,380.00
10
24" RCP, Class lII
1313 LF
$75.00
$98,475.00
1313
$98,475.00
11
2 1 " RCP, Class lII
836 LF
$70.00
$58,520.00
836
$58,520.00
12
4' Storm Junction Box
I I EA
$5,000.00
$55,000.00
11
$55,000.00
13
5' Storm Junction Box
5 EA
$6,000.00
$30,000.00
5
$30,000.00
14
6' Storm Junction Box
I EA
$7,000.00
$7,000.00
1
$7,000.00
15
Remove 4' Drop Inlet
I EA
$2,500.00
$2,500.00
1
$2,500.00
16
12" Rock Riprap
1607 SY
$125.00
$200,875.00
1607
$200,875.00
17
Concrete Collar
5 EA
$1,000.00
$5,000.00
5
$5,000.00
18
Inlet Protection
43 EA
$150.00
$6,450.00
43
$6,450.00
19
2 1 " Sloped End Headwall
1 EA
$3,500.00
$3,500.00
1
$3,500.00
20
2 1 " Sloped End Headwall
1 EA
$5,000.00
$5,000.00
1
$5,000.00
21
Connection to Existing 24" RCP
1 EA
$1,000.00
$1,000.00
1
$1,000.00
22
Connection to Existing 54" RCP
1 EA
$1,500.00
$1,500.00
1
$1,500.00
23
Concrete Rip Rap
315 SY
$160.00
$50,400.00
315
$50,400.00
Sub -Total of Previous Unit $1,105,241.00 $1,105,241.00
UNIT IV: PAVING IMRPOVEMENTS
Item Description of Items
Estimated Unit
Unit Cost
Estimated
Completed
Completed
No.
Quanity
Total
Quanity
Total
1 6" Lime Treatment (30#/SY) (CO 2)
0 SY
$3.00
$0.00
0
$0.00
2 8" Lime Treatment (36#/SY) (CO 2)
0 SY
$3.50
$0.00
0
$0.00
3 Hydrated Lime (CO 2)
694 TN
$195.00
$135,330.00
694
$135,330.00
Tuesday, November 5, 2024 Page 2 of 5
City Project Numbers 103149
Contract Name RETREAT AT FOSSIL CREEK PHASE 2
Contract Limits
Project Type DRAINAGE, PAVING & STREETLIGHT IMPROVEMENTS
Project Funding
DOE Number
3149
Estimate Number
1
Payment Number
1
For Period Ending
10/22/2024
4
6" Cone Pvmt
30050 SY
$37.00
111,850.00
30050 1,111,850.00
5
5' Conc Sidewalk
7826 SF
$4.50
$35,217.00
7826
$35,217.00
6
6' Conc Sidewalk
11049 SF
$4.50
$49,720.50
11049
$49,720.50
7
Barrier Free Ramp, TypeR-1
8 EA
$1,500.00
$12,000.00
8
$12,000.00
8
Barrier Free Ramp, Type P-1
22 EA
$1,600.00
$35,200.00
22
$35,200.00
9
Furnish/Install Alum Sign Ground Mount City Std. -
21 EA
$750.00
$15,750.00
21
$15,750.00
Name
10
Furnish/Install Alum Sign Ground Mount City Std. -
16 EA
$850.00
$13,600.00
16
$13,600.00
Stop
11
Topsoil
151 CY
$24.00
$3,624.00
151
$3,624.00
12
Seeding, Hydromulch
1356 SY
$6.00
$8,136.00
1356
$8,136.00
13
7.5" Cone Pvmt
4610 SY
$46.00
$212,060.00
4610
$212,060.00
14
Remove Barricade & Connect to Existing Header
2 EA
$1,500.00
$3,000.00
2
$3,000.00
15
Construct Header and Barricade
2 EA
$2,200.00
$4,400.00
2
$4,400.00
16
6" Lime Treatment (36#SY) (CO 2)
32050 SY
$3.00
$96,150.00
32050
$96,150.00
17
8" Lime Treatment (48#SY) (CO 2)
4880 SY
$3.50
$17,080.00
4880
$17,080.00
Sub -Total of Previous Unit
$1,753,117.50
$1,753,117.50
UNIT V: STREETLIGHT IMPROVEMENTS
Item
Description of Items
Estimated Unit
Unit Cost
Estimated
Completed Completed
No.
Quanity
Total
Quanity
Total
1
2" CONDT PVC SCH 80(T)
3755 LF
$15.00
$56,325.00
3755
$56,325.00
2
TYPE 11 STREET LIGHT POLE
52 EA
$2,250.00
$117,000.00
52
$117,000.00
3
TYPE 33 B STREET LIGHT ARM
52 EA
$650.00
$33,800.00
52
$33,800.00
4
TYPE 11 STREET LIGHT FOUNDATION
52 EA
$1,250.00
$65,000.00
52
$65,000.00
5
TYPE R2 LUMINAIRE
48 EA
$500.00
$24,000.00
48
$24,000.00
6
TYPE R4 LUMINAIRE
4 EA
$400.00
$1,600.00
4
$1,600.00
Sub -Total of Previous Unit
$297,725.00
$297,725.00
Tuesday, November 5, 2024 Page 3 of 5
City Project Numbers 103149
Contract Name RETREAT AT FOSSIL CREEK PHASE 2
Contract Limits
Project Type DRAINAGE, PAVING & STREETLIGHT IMPROVEMENTS
Project Funding
Contract Information Summary
Original Contract Amount
Change Orders
Change Order Number 2
DOE Number
3149
Estimate Number
1
Payment Number
1
For Period Ending
10/22/2024
$3,131,708.50
$24,375.00
Total Contract Price $3,156,083.50
Total Cost of Work Completed $3,156,083.50
Less % Retained $0.00
Net Earned $3,156,083.50
Earned This Period $3,156,083.50
Retainage This Period $0.00
Less Liquidated Damages
Days @ / Day
LessPavement Deficiency
Less Penalty
Less Previous Payment
Plus Material on Hand Less 15%
Balance Due This Payment
$0.00
$0.00
$0.00
$0.00
$0.00
$3,156,083.50
Tuesday, November 5, 2024 Page 4 of 5
City Project Numbers 103149 DOE Number 3149
Contract Name RETREAT AT FOSSIL CREEK PHASE 2 Estimate Number I
Contract Limits Payment Number 1
Project Type DRAINAGE, PAVING & STREETLIGHT IMPROVEMENTS For Period Ending 10/22/2024
Project Funding
Project Manager NA City Secretary Contract Number
Inspectors M. GLOVER / E. WALKER Contract Date 9/12/2022
Contractor CONATSER CONSTRUCTION TxLP Contract Time 230 WD
5327 WICHITA ST Days Charged to Date 211 WD
FORT WORTH, TX 76119 Contract is .000000 Complete
CITY OF FORT WORTH
SUMMARY OF CHARGES
Line Fund Account Center Amount Gross Retainage Net
Funded
Total Cost of Work Completed $3,156,083.50
Less % Retained $0.00
Net Earned $3,156,083.50
Earned This Period $3,156,083.50
Retainage This Period $0.00
Less Liquidated Damages
0 Days @ $0.00 / Day
$0.00
LessPavement Deficiency
$0.00
Less Penalty
$0.00
Less Previous Payment
$0.00
Plus Material on Hand Less 15%
$0.00
Balance Due This Payment
$3,156,083.50
Tuesday, November 5, 2024 Page 5 of 5
DEVELOPER -AWARDED -PROJECT CHANGE ORDER
PROJECT NAME:
Retreat at Fossil Creek Phase 2 ORDER
OR
CONTRACT:
Water, Sewer, Drainage, Pavinq, Street Liqhts NO:
CFA #
IPRC21-0055 CITY PARTICIPATION: No
CITY PROJECT*
103149
DOE #
NIA 1
FID #
30114-0200431-103149-EO7685
FILE #
W-2784, X-26952
INSPECTOR: Eddie Walker Phone (469) 658-5100
No:
PROJECT MANAGER: Ram Tiwari Phone (817) 392-2237
No:
CONTRACT UNIT
WATER
SEWER
PAVING
DRAINAGE J
STREET LIGHTS
CONTRACT
Developer
Developer
I
Developer `- �""' -
(Coat
DAYS
Cost Ci COst
Cost City Cost
Developer Cost Ciry Cost
Developer Cost City Crest
i
City Cost
ORIGINAL CONTRACT $900,996.00
$892.847.00
$1.728.742.0
$1,105,241.00
I $297,726.00
200
EXTRAS TO DATE
CREDITS TO DATE
_
CONTRACT TO DATE $900,986.00 SQ,99
$892,847.00 $0.00
$1,728,742.60 $0.00 _
$1,105,241.00 50.00
$297,725.00 I 50.00
200
AMOUNT OF PROP. CHANGE ORDER $ 10,150.00
$ 4,660.00
I
_
REVISED CONTRACT AMOUNT $911,136.00 I S0.00
$897,397.00 I 50.00
$1,728,742.60 $0.00
$1,106,241.00 ! $0.00
$297.725.00 I S0.00
I 200
TOTAL REVISED CONTRACT AMOUNT
PER UNIT $911,136.00
$897.397.00
$1,728,742.60
$1,105,241.00
$297,726.00
REVISED COST SHARE Dev. Cost:
$4,940,241.50
�rrx wc�
City =tr
4 S0.00
TOTAL REVISED CONTRACT
$4,940,241.50
Revised: 10-12-2011 Page 1
You are directed to make the followinoPanoes in theyontract documents
CITY BID ITEM
PAY ITEM #
#
QUANTITY
UNIT
ITEM DESCRIPTION
UNIT PRICE
TOTAL
Unit 1: Water Improvements
f
5
3312.0001
1
EA
3312.0001 Fire Hxdrant Assembly)
$ 4,750.00
$ 4.750.00
`10
3312.2203
1
EA
3312.2203 7' Watervervice
$ 2,000.00
$ 2.000.00
*11
9999,0014
1
EA
9999.0014 4" Irrigation Sleeve
$ 1,500.00
$ 1,500.00
*12
9999.0015
1
EA
9999.0015 6" Irrigation Sleeve
$ 1,900.00
$ 1,900.00
WATER SUBTOTAL
$ 10,150.00
Unit II: Sanitary Sewer Improvements
`11
3331.3301
1
EA
3331,3301 8" Sewer Service
$2,050.00
$ 2,050.00
`12
9999.0016
1
EA
9999.0016 Connection to Existino Manhole
$2,500.00
$ 2,500.00
SEWER SUBTOTAL:
$ 4,550.00
TOTAL
$ 14.700.00
REASONS FOR CHANGE ORDER
.Addition of water and sewer services,
as well as fire hydrant, to serve amenity center lot. Irrigation sleeves added to provide irrigation to open spaces.
NO CITY FUNDS INVOLVED IN THIS CONTRACT. DEVELOPER IS RESPONSIBLE FOR 100% OF THE CHANGE ORDER COST AND NO
REIMBURSEMENT FROM THE CITY WILL BE SOUGHT BY THE DEVELOPER
RECOMMENDED:
LJA Engineering, Inc.
By:
Name: Andrew Kubiak
Title: Proiect Manaaer
APPROVED:
sil Creek, f .
B.
Name: Max Miller
Tide: Director
APPROVED:
Conaster Construction TX, L.P.
By:��
Name: Adam mBG s
Title: Manager
REVIEWED
By TIWARIR at 4:19 pm, Feb 14, 2024
Revised: 10-12-2011 Page 2
DEVELOPER -AWARDED -PROJECT CHANGE ORDER
PROJECT NAME: Retreat at Fossil Creek Phase 2 IORDE t
ORDER
CONTRACT: Water, Sewer, Drainaqe, Pavina, Street Lights No:
CFA # IPRC21-0055 CITY PARTICIPATION: No
CITY PROJECT # 103149
DOE # NIA
FID # 30114-0200431-103149-EO7685
FILE # W-2784, X-26952
INSPECTOR: Eddie Walker Phone (469) 658-5100
No:
PROJECT MANAGER: Ram Tiwari Phone (817) 392-2237
No:
CONTRACT UNIT
I
WATER
SEWER
PAVING
DRAINAGE
STREET LIGHTS
I CONTRACT DAYS
Developer
Developer
I
Developer
I
Cost Clty Cott
Cost Co'"
Developer Cost Cljy Cost
Developer Cost City Cost Cost City Cost
ORIGINAL CONTRACT
5900,986.00
$892,847.00
$1.728.742.50
$1,105,241.00 I
$297,725.00
200
(EXTRAS TO DATE
$10,150.00
$4,550.00
i
I
(CREDITS TO DATE
CONTRACT TO DATE
$911,136.00 S0.00
$897,397.00 S0
$1,728„742.50 $0.00
$1,105,241.00 I $0.00
$297,725.00 I SO.00
200
(AMOUNT OF PROP. CHANGE ORDER
$24,376.00
REVISED CONTRACT AMOUNT
$911,136.00 $0.00
$897,397.00
$1,753,117.50 I $0.00
$1,106,241.00 I $0.00
$297,725.00 $0.00
200
TOTAL REVISED CONTRACT AMOUNT
PER UNIT
$911,136.00
$897,397.00
$1,763,117.50
$1,105,241.00
$297,725.00
S0.00
REVISED COST SHARE Dev. Cost:
$4,964,616.50 City Cost:
TOTAL REVISED CONTRACT
$4,964,616,50
Revised: 10-12-2011 Page 1
You are directed to make the foilowinr changes in the contract documents:
CITY BID ITEM
PAY ITEM #
#
QUANTITY
UNIT
Unit IV: Pavinq Improvements
1
3211.0501
-32050
SY
2
3211.0502
-4880
SY
3
3211.04
125
TON
`16
3211.0501
32050
SY
*17
3211.0502
4880
SY
TOTAL
REASONS FOR CHANGE ORDER
Update of time
treatment pounds per square yard.
ITEM DESCRIPTION
3211.0501 6" Lime Treatment �(30#/SY)'�
3211.0502 8" Lime Treatment &#/SY)
3211.0400 Hydrated Lime
3211.0501 6" Lime Treatment (36WSY)
3211.0502 8" Lime Treatment (48#/SY)
UNIT PRICE TOTAL
I $
3.00
$
(96.150.00)
$
3.50
$
t17.080.00)
$
195.00
$
4,375.00
S
3.00
$
96,150.00
$
3.50
$
17,080.00
$24, 375.00
NO CITY FUNDS INVOLVED IN THIS CONTRACT. DEVELOPER IS RESPONSIBLE FOR 100 % OF THE CHANGE ORDER COST AND NO
REIMBURSEMENT FROM THE CITY WILL BE SOUGHT BY THE DEVELOPER.
RECOMMENDED:
LJA Engineering, Inc.
Name: Andrew Kubiak
Tittle: Proiect Manacer
APPROVED:
Retreat F _ Craek, Ltd.
By:
Name: Max Miller
Title: Director
APPROVED:
ConasterConstruction TX, L.P.
By:
Name: Brock Huggins
Title: President
REVIEWED
By TiwariR at 3:14 pm, Mar 18, 2024
Revised: 10-12-2011 Page 2
FORTWORTH.
TRANSPORTATION AND PUBLIC WORKS
October 22, 2024
CONATSER CONSTRUCTION ,TX.,LP
5327 WICHTIA STREET
FORT WORTH,TX. 76119
RE: Acceptance Letter
Project Name: RETREAT AT FOSSIL CREEK PHASE 2
Project Type: Water, Sewer, Paving, Drainage & Street Light Improvements
City Project No.: 103149
To Whom It May Concern:
On October 22, 2024 a final inspection was made on the subject project. There were no punch list items
identified at that time. The final inspection indicates that the work meets the City of Fort Worth
specifications and is therefore accepted by the City. The warranty period will start on October 22, 2024,
which is the date of the final inspection and will extend of two (2) years in accordance with the Contract
Documents.
If you have any questions concerning this letter of acceptance, please feel free to contact me at 817-
392-2237.
Sincerely,
AZAX1 ;_14Z51�
Ram Tiwari (Nov 6, 202411:15 CST)
Ram Tiwari, Project Manager
Cc: Eddie Walker, Inspector
Mike Glover, Inspection Supervisor
Daniel Roy, Senior Inspector
Andrew Goodman, Program Manager
UA Engineering, Inc., Consultant
CONATSER CONSTRUCTION ,TXJP, Contractor
BENCHMARK ACQUISITIONS, LLC,KYLE KIRKLAND, Developer
File
E-Mail: TPW_Acceptance@fortworthtexas.gov
Rev. 08/20/19
Fl. to"WII1
STATE OF TEXAS
COUNTY OF TARRANT
Before me, the undersigned authority, a Notary Public in the state and county aforesaid,
on this day personally appeared Brock Huggins, President of Conatscr Ivlanagcnient Group, Inc.,
general partner of Conatscr Construction 'I"X, IT, known to me to be a credible person, who
hiring by me duly sworn, upon his outh deposed and said:
That all persons, /hens, associations, corporations or other organizations furnishing
labor and/or materials have been paid in fu11.
That the wage scale established by the City Council in the City of Fort Worth, has
been paid in full; and
Mat there are no claims pcnding for personal injury and/or property damages;
On Contract described as;
RETREAT AT FOSSIL CREEK PH. 2
WATER, SANITARY SEWER, DRAINAGE, PAVING
& STREET LIGHT IMPROVEMENTS
CFA PKf # 22-0062
CITY PROJECT # 103149
CITY OF FORT WORTH
STATE OF TEXAS
C'ONA1`SER CONSTRUCTION TX, LP
Brock Huggin
Subscribed and sworn to before me this 291" day of October, 2024.
KCLX-A-J—
NDLW PAk. s[w el 72"Ma
Ira i334M3 Notary Public in Tarrant County, Tf as
ray cMw,81W E20-
CONSENT OF
SURETY COMPANY
TO FINAL PAYMENT
Contorms with the Amancnn tnstisute of
Architects, AtA Documvirit G707
PROJECT:
(name, address)Foss" Creek, Pt+ase 2
Fart Worth, TX
TO i0wrierl
OWNER
❑
ARCHITECT
❑
CONTRACTOR
❑
SURETY
❑
OTHER
RETREAT AT FOSSIL CREEK. 00. AND THE CITY
OF FORT WORTH
1000 Throd ftwir rM
L' Worth TX 761 D2
CONTRACTOR! CONATSER CONSTRUCTION TX L P
134O No 0247469
ARCHITECT'S PROJECT NO: cFA No 22-o062
CONTRACT FOR-
aler. Sewer, l'Mlwr+g. and amnage Imonm" is for Reveal a1
Foser Creek - I't=o 2
CONTRACT DATE
In *wxedznm %vkh the provisions of the Contract between the Owner aad the C.oiebor m indicated above, the
owe k*W Wnip M0 840pn of SLWNy Carnwyl
EERXLEY rNSORANCE COMPANY
475 Steamhaal Road
Greernwch CT 06830 SURETY COMPANY
inn bored of ft ri i wn na rno Wvd ne&y.r or CDt Vai;100
CONAT5ER CONSTRUCTION TX. L.P.
5327 W'aChita SI
Fort Wort1-r TX 781IM035
,CONTRACTOR,
hereby approves of the final payment to the Con"ctur, and agroe5 that rural payment to the C.troll not relieve
the Surety Company of any of its obligations to IIMM InMrt n+m, w+d �brhMs o+r.r+.�}
RETREAT AT FOSSIL CREEK. LTD AND THE CITY OF FORT WORTH
10DO ttirockmortcr,
Fort Worth TX 76102 , OWNER
as Set forth in the said Surety Company's bond.
IN WITNESS, WHEREOF,
the Surety Company has hereunto set its Rand this
Attest:+
(Seal :
28th day of OCtoW. =A
BERKLEY INSURANCE COMPANY
Surety Company
Signature of Authorized Representative
Rabb MCrades _ A!torrreY.;rt-Fad
Title