HomeMy WebLinkAboutOrdinance 27263-10-2024Ordinance No. 27263-10-2024
AN ORDINANCE ADJUSTING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE WATER AND SEWER REVENUE BONDS SERIES
2021 FUND, BY DECREASING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE NORTHSIDE II WATER TRANSMISSION MAIN
EXTENSION NORTHLAKE PROJECT (CITY PROJECT NO. 103968) IN THE
AMOUNT OF $984,219.00 AND INCREASING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE UNSPECIFIED -ALL FUNDS PROJECT (CITY
PROJECT NO. UNSPEC) BY THE SAME AMOUNT; PROVIDING FOR A
SEVERABILITY CLAUSE; MAKING THIS ORDINANCE CUMULATIVE OF
PRIOR ORDINANCES; REPEALING ALL ORDINANCES IN CONFLICT
HEREWITH; AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,
TEXAS:
SECTION 1.
That the budget of the City of Fort Worth for Fiscal Year 2024-2025, as enacted by Ordinance 27107-09-
2024, as amended, is hereby further amended to make the following adjustments to estimated receipts and
appropriations in the Water and Sewer Revenue Bonds Series 2021 Fund, by decreasing estimated receipts
and appropriations in the Northside 11 Water Transmission Main Extension Northlake project (City Project
No. 103968) in the amount of $984,219.00 and increasing estimated receipts and appropriations in the
Unspecified -All Funds project (City Project No. UNSPEC) by the same amount.
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way impair
the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 27107-09-2024 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY:
Denis McElroy
Sr. Assistant City Attorney
ADOPTED AND EFFECTIVE: October 29, 2024
CITY SECRETARY
Jannette S. Goodall
City Secretary
a4�M,
mod O R T >Z�
o� F °00°o°00
tya��
v o C
0 0
°°o° *b
°°°0°°° C
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 10129/24 M&C FILE NUMBER: M&C 24-0938
LOG NAME: 60WATER HILLWOOD FUNDS APPROPRIATION
SUBJECT
(CD 10, CD 2 and CD 7) Adopt Appropriation Ordinances to Replace $10,851,796.96 in Previously Appropriated Funds with Eligible Restricted
Revenues Received from Hillwood Development Corporation for Projects Benefiting the Town of Westlake to Effect a Portion of Water's
Contribution to the Fiscal Years 2025-2029 Capital Improvement Program
RECOMMENDATION:
It is recommended that City Council:
1. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Water & Sewer Community
Facilities Agreement Fund in the Northside II Water Main Along State Highway 170 project (City Project No. 100261) by $9,867,577.96 and
in the Northside Il Water Transmission Main Extension Northlake project (City Project No. 103968) by $984,219.00 from available Hillwood
Development Corporation contributions within the Westlake-Hillwood project (City Project No.102518) for the purpose of funding eligible
projects ben efitting the Town of Westlake;
2. Adopt the attached appropriation ordinance decreasing estimated receipts and appropriations in the Northside 11 Water Main Along State
Highway 170 project (City Project No. 100261) within the Water and Sewer Capital Projects Fund in the amount of$1,969,820.96, for the
purpose of substituting funding sources and to make revenues available for other eligible Water and Sewer projects;
3. Adopt the attached appropriation ordinance adjusting estimated receipts and appropriations in the Water and Sewer Revenue Bonds 2022
Fund by increasing estimated receipts and appropriations in the Unspecified -All Funds project (City Project No. UNSPEC) in the amount of
$5,398,659.00 and decreasing estimated receipts and appropriations in the Northside 11 Water Main Along State Highway 170 project (City
Project No. 100261) by the same amount for the purpose of substituting funding sources and to make debt proceeds available for other
eligible Water and Sewer projects;
4. Adopt the attached appropriation ordinance decreasing estimated receipts and appropriations in the Northside II Water Main Along State
Highway 170 project (City Project No. 100261) within the Water Capital Fund by $2,499,098.00, for the purpose of substituting funding
sources and to make revenues available for other eligible Water and Sewer projects;
5. Authorize the move of available PayGo residuals within the Unspecified -AEI Funds project (City Project No. UNSPEC) in the Water Capital
Fund in the amount of $2,499,098.00 to the Unspecified -All Funds project (City Project No. UNSPEC) in the Water & Sewer Capital Projects
Fund in order to facilitate the clean-up and close-out of the City's legacy capital project funds; and
6. Adopt the attached appropriation ordinance adjusting estimated receipts and appropriations in the Water and Sewer Revenue Bonds
Series 2021 Fund by increasing estimated receipts and appropriations in the Unspecified -All Funds project (City Project No. UNSPEC) in
the amount of $984,219.00 and decreasing estimated receipts and appropriations in the Northside 11 Water Transmission Main Extension
Northlake project (City Project No. 103968) by the same amount for the purpose of substituting funding sources and to make debt proceeds
available for other eligible Water and Sewer projects to effect a portion of Water's contribution to the Fiscal Years 2025-2029 Capital
Improvement Program.
In late 1998, as part of an agreement settling multiple lawsuits that included the Town of Westlake, the City of Fort Worth, and Hillwood
Development Corporation and related entities, Hillwood Development Corporation assumed an obligation to make a series of payments over the
course of multiple years to provide funds to the City of Fort Worth for improvements to the City's water system to provide additional capacity to
serve the Town of Westlake in accordance with a water contract executed between Fort Worth and Westlake.
As of July 2024, a total of $11,741,427.00 exists in the Westlake-Hillwood project (City Project No.102518) as a result of this agreement.
Approval of this Mayor & Council Communication (M&C) and adoption of the attached ordinances will (i) appropriate $10,851,796.96 of these
funds to two projects that meet the criteria of the settlement and benefit the Town of Westlake: the Northside II Water Main Along State Highway
(SH)170 and the Northside 1124" Extension Northlake projects; and (ii) free up the funds that had originally been appropriated for these projects so
that they may be utilized for other eligible Water and Sewer projects.
City Project No. 100261 - Northside If Water Main Alona SH170
The Northside 11 Water Main Along SH170 project (City Project No. 100261), was originally approved for a 30-inch Water Transmission Main along
highway 170 (SH170) from N. Beach Street to US377 on November 8, 2016 with M&C C 27985. Existing amended wholesale water contracts
with Trophy Club Municipal District No.1 (City Secretary Contract 41111) and the Town of Westlake (City Secretary Contract No. 41112) require the
wholesale customer to cost participate toward the additional capacity from future Fort Worth water transmission mains which serve their
communities (approved per M&C C-27783 on June 21, 2016). These wholesale customers requested increased capacity from the Northside 11
30-inch water main and have participated in the cost of the project accordingly.
The project was expanded to cover 0.5 miles east of Interstate Highway 35W to Trophy Club Lake Drive to accommodate the Texas Department of
Transportation's construction of the SH 170 four main lanes and associated improvements which required relocation of four water mains at Beach
Street, Alta Vista Road, Westport Parkway and Independence Parkway (per M&C 20-0168 approved on April 7, 2020). The projecfs scope had
to subsequently be amended to include the relocation at these four conflict locations.
Hillwood Development Corporation funds in the amount of $9,867,577.96 will now be used to replace previous City appropriations.
This project is located in COUNCIL DISTRICT 10.
City Project No. 103968 - Northside II Water Transmission Main Extension Northlake
Due to increased growth and demand for additional water, the Town of Northlake requested additional connection points and water supplies. An
amendment to their wholesale contract was executed on January 10, 2023, M&C 23-0047. The City is currently participating in costs related to the
design and easements. An M&C will be submitted in the future to include the City participation for the construction costs.
Hillwood Development funds in the amount of $984,219.00 will now be used to replace previous City's appropriations.
This project is located in COUNCIL DISTRICTS 2 and 7.
Project Appropriations Before and After This M&C*
Northside II Water Main along SH170 project:
Existing
Adjustments --
Fund
Appropriations
Increasesl(Decreases)
Project Total*
from this M&C
W&S
Community
Facilities
$0.00
$9,867,577.96
$9,867,577.96
Agmt —
Fund
56008
W&S
Capital
Projects—
$1,969,820.96
($1,969,820.96)
$0.00
Fund
56002
W&S Rev
Bonds
Series
$5,398,659.00
($5,398,659.00)
$0.00Fund
2022 —
56020
Water
Capital--
$8,372,830.03
($2,499,098.00)
$5,873,732.03**
Fund
59601
Project
$.16,741,309.99
$0.00
$15,741,309.99
Total
**These previously appropriated funds, which will remain in the project following adoption of this M&C, represent contributions from other customer
cities who also benefit from this project.
Northside Il 24" Water Transmission Main Extension Northlake project:
Existing
Adjustments --
Project
Fund
Appropriations
Increasesl(Decreases)
Total*
from this M&C
W&S
Community
FacilityAgmt --
$0.00
$984,219.00
$984,219.00
Fund 56008
W&S Rev
Bonds Series
2021 — Fund
$984,219.00
($984,219.00)
$0.00
56019
Project Total
$984,219.00
$0.00
$984,219.00
*Numbers in charts may be rounded for presentation purposes.
The project is located in COUNCIL DISTRICTS 2, 7 and 10.
A Form 1295 is not required because: This M&C does not request approval of a contract with a business entity.
FISCAL INFORMATION 1 CERTIFICATION:
The•Director of Finance certifies that funds are currently available in the Westlake-Hillwood project within the W&S Community Facilities Agmt
Fund and upon approval of the above recommendations and adoption of the attached appropriation ordinances, funds will be available in the W&S
Community Facilities Agmt Fund for the NSII Water Main Along SH170 and NSII 24 WTM Exten. Northlake projects. Priorto any expenditure being
incurred, the Water Department has the responsibility of verifying the availability of funds.
Submitted for City Manag-ees Office by: Fernando Costa 6122
Originating Husine§A Unit Head: Chris Harder 5020