FORT WORTH., City of Fort Worth
Change Order Request
Project Name 2022 Bond Year 2 Contract 10
Client Project #(s)l 104243
Project Descriptioni Water, pavement and sidewalk improvements on various streets
Contracto'lMcClendon Construction Company, Inc
City Project Mgr.1 Christian Cardona
Dept. Unitl: Water
Original Contract Amount
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date
Amount of Proposed Change Order
Revised Contract Amount
Original Funds Available for Change Orders
Remaining Funds Available for this CO
Additional Funding (if necessary)
$2,117.965.00
City Sec # 1 61864
Change Order#I 1 I Datel 11/8/2024
City Inspectorl Kevin Jackson
Unit 2:TPW Unit 3:Storm Contract Time
Water Totals (CD)
$5,004,703.25 $151,568.00 $7,274,236.25 400
$2,117,965.00 $5,004,703.25 $151,568.00 $7,274,236.25 400
$0.00 $0.00 $0.00
$2,�7,965.00 $5,004,703.25 $151,568.00 $7,274,236.25 407
$0.00
$0.00 $0.00
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT 0.00%
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%) $9,092,795.31
This change order will add bid items to replace the 40-year-old 12" ductile iron water pipe and gate valve along NW 24th Street and Houston Street. The existing 12' water
line was found during construction at a depth of T, which does not meet the minimum depth coverage requirements of 4'. The installation of the new 12' gate valve will allow
the contractor to isolate the water system more effectively, preventing multiple businesses in the Stockyards area from shutting down to make new water pipe connections.
This change order will also reduce the water construction allowance bid item, to pay for these new bid items. Staff have compared the pricing of this work with similar
projects and determined them to be fair and reasonable.
Additionally, the staff concurs with the contractor's request for 7 additional days to perform this work.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in
full (both time and money) for all costs arising out of, or incidental to, the above Change Order. The Project/Program Manager signing below
acknowledges that he/she is the person responsible for the monitoring and administration of this contract, including ensuring all performance and
reporting requirements.
Contractor's Company Name Contractor (Name) Contract Signature
Date
McClendon Construction Company, Inc. Justin Blair 9
Nov 13, 2024
pection Supery
Date
Project and Contract Compliance Manager
Date
�-
Nov 12, 2024
Nov 12, 2024
Hager
Date
Nov 13, 2024
Senior Capital Project Officer
Date
Nov 13, 2024
Assistant Director (Dept)
Date
Director, Contracting Department (Dept)
Date
n . wok
Nov 13, 2024
Nov 13, 2024
Assistant City Attorney
Date
JAssistant City Manager
Date
Nov 15, 2024
1
1 Nov 20, 2024
Council Action (if required)
ovvvpp
FOR?- 4 M&C Number N/A
M&C Date Approved NIA
ATTEST:
'A
of........
'- O o
u
p�qe °o �1 d
AVo So
Jannette Goodall, City Secretary
ddQ* _°° ,°°*�°
OFFICIAL RECORD
PaIluuoEx
asbp
CITY SECRETARY
FT. WORTH, TX
City of Fort Worth
Change Order Additions
Project Name 1 2022 Bond Year 2 Contract 10
Client Project # 1 104243
Contraclorl McClendon Construction Company, Inc
I I EM UESUKIN I IUN
41 3311.U4151 12" PVC Water Flipe (UK14) by Upen Cut
42 3312.300512" Gate Valve
43 3305.000512" Water Line Lowering
City Sec # 61864
1
PMl Christian Cardona l Inspectorl Kevin Jackson
Change Order Submittal # 0 Date j 11/8/2024
ADDITIONS
UEN I Uty Unit Unit Cost I otal
Unitl: Water 85.000UUUUU LF $11i5.0 $14,U'LS.UU
Unitl: Water 2.00OOOOOU EA $5,300.0 $10:600.00
Unitl: Water 1.00000000 EA $14,000.0 $14000.001
j
1
1
1
j
I
j
j
1
I
1
j
1
j
I
I
I
j
1
1
1
1
1
1
1
1
1
1
I
I
1
1
Unitl: Nater $38,625.001
Unit 2: TPW $0.001
Unit 3: Storm Water $0.001
Sub Total Additions $38,625.001
Change Order Additions Page 2 of 5
FORT WORTH City of Fort Worth
1V1--- Change Order Deletions
Project Name 1 2022 Bond Year 2 Contract 10
Client Project # 1 104243
Contractorl McClendon Construction Company, Inc
I I tM DtSCKIP I ION
4U 9999.0002 Construction Allowance (Water)
City Sec # 61864
1
PMl Christian Cardona l Inspectorl Kevin Jackson l
Change Order Submittal # = Date 1 11/8/2024 1
DELETIONS
DtP I Oty Unit Unit Cost I otal
Umt1: Water U.3862b= LS $1UU,000.UU $38,62b.UU
Unit1: Rater
$38,625.00
Unit 2: TPW
$0.00
Unit 3: Storm Water
$0.00
Sub Total Deletions
$38,625.00
Change Order Deletions Page 3 of 5
MISBE for this Change Order
M/SBE Sub Type of Service Amount for this CO
Not Applicable Not Applicable Not Applicable
Total $0.00
Previous Change Orders
CO # DATE I AMOUNT
Total 1 $0.00 I
FORT WORTH.
Routing and Transmittal Slip
Transportation & Public Works Department
DOCUMENT TITLE• Change order #1— 2022 Bond Year 2 — Contract 10
M&C:
Date:
To: Name
1. Sophia Flores
2. Justin Blair
CPN: 104243 CSO: 61864
Department Initials
TPW - initials 71-*—
McClendon Construction
- signature
DOC#:
Date Out
Nov 12, 2024
Nov 13, 2024
3.
Kevin Jackson
TPW - signature
?
Nov 12, 2024
4.
Clayton Torrance
WD - initials
CTNov
13, 2024
5.
Christian Cardona
TPW - signature
cc
Nov 12, 2024
6.
Gregory Robbins
TPW - signature
GR�
Nov 13, 2024
7.
Mary Hanna
TPW - signature
m
Nov 13, 2024
8.
Patricia Wadsack
TPW - signature
�L
Nov 13, 2024
9.
Lauren Prieur
TPW - signature
?�
Nov 13, 2024
10.
Doug Black
Legal - signature
Dena
Nov 15, 2024
11.
Jesica McEachern
CMO - signature
,
Nov 20, 2024
12.
Jannette Goodall
CSO - signature
7-141-
Nov 20, 2024
13.
TPW Contracts
DOCUMENTS FOR CITY MANAGER'S SIGNATURE:
All documents received from any
and all City Departments requesting City Manager's signature for approval MUST BE ROUTED
TO THE
APPROPRIATE ACM
for approval first. Once the ACM has signed the routing slip,
David
will review and take the next steps.
NEEDS TO BE NOTARIZED: ❑YES ®No
RUSH: ®YES []No SAME DAY: ❑YES ❑No NEXT DAY: ❑YES ®No
ROUTING TO CSO: ®YES ❑No
Action Required:
❑ As Requested
❑ For Your Information
® Signature/Routing and or Recording
❑ Comment
❑ File
❑ Attach Signature, Initial and Notary Tabs
Return To: TPWContracts(a�FortWorthTexas.2ov at ext. 7233 for pick up when completed.
Thank you!