HomeMy WebLinkAboutContract 61810-FP2FORT WORTH.
-FP2
City Secretary
Contract No. 61810
Date Received 11/13/2024
AT
NOTICE OF PROJECT COMPLETION
(Developer Projects)
The Transportation and Public Works Department upon the recommendation of the Project
Manager has accepted the following project as complete:
Project Name: Wellington Area 3 North Ph.1 B
City Project No.: 105028
Improvement Type(s): x❑ Paving ❑X Drainage x❑ Street Lights ❑ Traffic Signals
Original Contract Price: $3,078,646.00
Amount of Approved Change Order(s):-$32,980.50
Revised Contract Amount: $3,045,665.50
Total Cost of Work Complete: $3,045,665.50
A./�AL Nov 12 2024
Jay Ir ri e I I (Nov 12, 202414:52 CST)
Contractor Date
Project manager
Title
Conatser Construction, TX L.P.
Company Name
Rid wAaHt�
Nov 12 2024
Richard Walden (Nov 12. 202415:15 CST)
Project Inspector
Date
,�%
Nov 13 2024
Ram Ti—ri (Nov 13. 202411:18 CST)
Project Manager
Date
Nov 13, 2024
Rebe<:c:a,0 en(Nov 13, 202412:08 CST)
CFA Manager
Date
Nov 13 2024
Lauren Prieur (Nov 13. 202410:14 PST)
TPW Director
Date
OFFICIAL RECORD
Nov 13, 2024
CITY SECRETARY
Asst. City Manager
Date FT. WORTH, Tx
Page 1 of 2
Notice of Project Completion
Project Name: Wellington Area 3 North Ph.1 B
City Project No.: 105028
City's Attachments
Final Pay Estimate x❑
Change Order(s): ❑x Yes ❑ N/A
Contractor's Attachments
Affidavit of Bills Paid
Consent of Surety
Statement of Contract Time
Contract Time 375 WD Days Charged: 136 WD
Work Start Date: 4/24/2023 Work Complete Date: 9/18/2024
Completed number of Soil Lab Test: 0
Completed number of Water Test: 0
Page 2of2
FoRTWORTH
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name WELLINGTON AREA 3 NORTH PHASE I
Contract Limits
Project Type DRAINAGE, PAVING & STREETLIGHTS
City Project Numbers 105028
DOE Number 5028
Estimate Number 1 Payment Number 1 For Period Ending 9/18/2024
WD
City Secretary Contract Number Contract Time 37WD
Contract Date Days Charged to Date 136
Project Manager NA Contract is 100.00 Complete
Contractor CONATSER CONSTRUCTION TxLP
5327 WICHITA ST
FORT WORTH, TX 76119
Inspectors G DEYON / R WALDEN
Tuesday, November 12, 2024 Page 1 of 5
City Project Numbers 105028
Contract Name WELLINGTON AREA 3 NORTH PHASE 1B
Contract Limits
Project Type DRAINAGE, PAVING & STREETLIGHTS
Project Funding
UNIT III: DRAINAGE IMPROVEMENTS
Item
Description of Items
Estimated Unit
No.
Quanity
1
TRENCH SAFETY
6201 LF
2
12" CONCRETE RIPRAP
1086 SY
3
2 1 " RCP, CLASS lII
2327 LF
4
24" RCP, CLASS III
1732 LF
5
27" RCP, CLASS lII
543 LF
6
30" RCP, CLASS III
354 LF
7
42" RCP, CLASS lII
296 LF
8
48" RCP, CLASS lII
949 LF
9
4' STORM JUNCTION BOX
8 EA
10
Y STORM JUNCTION BOX
6 EA
11
10' CURB INLET
26 EA
12
15' CURB INLET
2 EA
13
10' TYPE 2 INLET
8 EA
14
INLET PROTECTION
36 EA
15
24" 4:1 CH-FW-O HEADWALL
I EA
16
30" 6:1 SLOPED END HEADWALL
1 EA
17
36" 4:1 SLOPED END HEADWALL
I EA
18
48" 4:1 SLOPED END HEADWALL
1 EA
Sub -Total of Previous Unit
-------------------
UNIT IV: PAVING IMPROVEMENTS
Item
Description of Items
Estimated Unit
No.
Quanity
1
HYDRATED LIME (STREETS)
559 TN
2
HYDRATED LIME (ALLEYS)
112 TN
3
6" CONC PVMT (STREETS)
32723 SY
4
6" CONC PVMT (ALLEYS)
6046 SY
5
6" LIME TREATMENT (32#SY)(STREETS)
34898 SY
6
6" LIME TREATMENT (32#SY)(ALLEYS)
7009 SY
7
5' CONC SIDEWALK (CO 1)
4858 SF
8
BARRIER FREE RAMP, TYPE R-1
8 EA
DOE Number 5028
Estimate Number 1
Payment Number 1
For Period Ending 9/18/2024
Unit Cost Estimated
Total
$2.00 $12,402.00
$120.00 $130,320.00
$65.00 $151,255.00
$70.00 $121,240.00
$75.00 $40,725.00
$85.00 $30,090.00
$145.00 $42,920.00
$180.00 $170,820.00
$5,500.00 $44,000.00
$6,500.00 $39,000.00
$3,400.00 $88,400.00
$4,400.00 $8,800.00
$3,800.00 $30,400.00
$150.00 $5,400.00
$3,000.00 $3,000.00
$4,000.00 $4,000.00
$4,500.00 $4,500.00
$5,500.00 $5,500.00
Completed Completed
Quanity Total
6201 $12,402.00
1086 $130,320.00
2327 $151,255.00
1732 $121,240.00
543 $40,725.00
354 $30,090.00
296 $42,920.00
949 $170,820.00
8 $44,000.00
6 $39,000.00
26 $88,400.00
2 $8,800.00
8 $30,400.00
36 $5,400.00
1 $3,000.00
1 $4,000.00
1 $4,500.00
1 $5,500.00
$932,772.00
$932,772.00
Unit Cost
Estimated
Completed
Completed
Total
Quanity
Total
$210.00
$117,390.00
559
$117,390.00
$210.00
$23,520.00
112
$23,520.00
$37.50
227,112.50
32723
1,227,112.50
$38.50
$232,771.00
6046
$232,771.00
$3.25
$113,418.50
34898
$113,418.50
$3.50
$24,531.50
7009
$24,531.50
$4.50
$21,861.00
4858
$21,861.00
$1,800.00
$14,400.00
8
$14,400.00
Tuesday, November 12, 2024 Page 2 of 5
City Project Numbers 105028
Contract Name WELLINGTON AREA 3 NORTH PHASE 1B
Contract Limits
Project Type DRAINAGE, PAVING & STREETLIGHTS
Project Funding
DOE Number 5028
Estimate Number 1
Payment Number 1
For Period Ending 9/18/2024
9
BARRIER FREE RAMP, TYPE P-1
16 EA
$1,800.00
$28,800.00
16
$28,800.00
10
TOPSOIL (CO 1)
0 CY
$32.00
$0.00
0
$0.00
11
SEEDING, HYDROMULCH (CO 1)
0 SY
$2.00
$0.00
0
$0.00
12
8' CONC SIDEWALK (CO 1)
0 SF
$5.50
$0.00
0
$0.00
13
PAVEMENT HEADER (29")
1 EA
$1,000.00
$1,000.00
1
$1,000.00
14
INSTALL EOR BARRICADE
1 EA
$1,000.00
$1,000.00
1
$1,000.00
15
FURNISH/INSTALL SIGN POST AND
14 EA
$500.00
$7,000.00
14
$7,000.00
FOUNDATION
16
STOP SIGN (R1-1)
12 EA
$500.00
$6,000.00
12
$6,000.00
17
STREET NAME BLADE
48 EA
$250.00
$12,000.00
48
$12,000.00
18
6' CONCRETE SIDEWALK (CO 1)
14866 SF
$5.50
$81,763.00
14866
$81,763.00
Sub -Total of Previous Unit
$1,912,567.50
$1,912,567.50
- - - - - - - - - - - - - - - -
UNIT V: STREET LIGHTING IMPROVEMENTS
- - -
Item
Description of Items
Estimated Unit
Unit Cost
Estimated
Completed
Completed
No.
Quanity
Total
Quanity
Total
1
2" CONDT PVC SCH 80 (T)
3307 LF
$14.00
$46,298.00
3307
$46,298.00
2
NO 6 INSULATED ELEC CONDR
3307 LF
$4.00
$13,228.00
3307
$13,228.00
3
TY 7 SIGNAL FOUNDATION
64 EA
$1,200.00
$76,800.00
64
$76,800.00
4
FURNISH/INSTALL WASHINGTON POSTLINE
64 EA
$1,000.00
$64,000.00
64
$64,000.00
SERIES
Sub -Total of Previous Unit
$200,326.00
$200,326.00
Tuesday, November 12, 2024 Page 3 of 5
City Project Numbers 105028
Contract Name WELLINGTON AREA 3 NORTH PHASE 113
Contract Limits
Project Type DRAINAGE, PAVING & STREETLIGHTS
Project Funding
Contract Information Summary
Original Contract Amount
Change Orders
Change Order Number 1
DOE Number 5028
Estimate Number 1
Payment Number 1
For Period Ending 9/18/2024
$3,078,646.00
($32,980.50)
Total Contract Price $3,045,665.50
Total Cost of Work Completed $3,045,665.50
Less % Retained $0.00
Net Earned $3,045,665.50
Earned This Period $3,045,665.50
Retainage This Period $0.00
Less Liquidated Damages
Days @ / Day
LessPavement Deficiency
Less Penalty
Less Previous Payment
Plus Material on Hand Less 15%
Balance Due This Payment
$0.00
$0.00
$0.00
$0.00
$0.00
$3,045,665.50
Tuesday, November 12, 2024 Page 4 of 5
City Project Numbers 105028
Contract Name WELLINGTON AREA 3 NORTH PHASE 1B
Contract Limits
Project Type DRAINAGE, PAVING & STREETLIGHTS
Project Funding
Project Manager NA
Inspectors G DEYON / R WALDEN
Contractor CONATSER CONSTRUCTION TxLP
5327 WICHITA ST
FORT WORTH, TX 76119
DOE Number 5028
Estimate Number 1
Payment Number 1
For Period Ending 9/18/2024
City Secretary Contract Number
Contract Date
Contract Time 375 WD
Days Charged to Date 136 WD
Contract is .000000 Complete
CITY OF FORT WORTH
SUMMARY OF CHARGES
Line Fund Account Center Amount Gross Retainage Net
Funded
Total Cost of Work Completed $3,045,665.50
Less % Retained $0.00
Net Earned $3,045,665.50
Earned This Period $3,045,665.50
Retainage This Period $0.00
Less Liquidated Damages
0 Days @ $0.00 / Day
$0.00
LessPavement Deficiency
$0.00
Less Penalty
$0.00
Less Previous Payment
$0.00
Plus Material on Hand Less 15%
$0.00
Balance Due This Payment
$3,045,665.50
Tuesday, November 12, 2024 Page 5 of 5
PROJECT NAME:
CONTRACT:
CFA #
CITY PROJECT #
FID #
X#
FILE #
INSPECTOR:
PROJECT MANAGER:
ORIGINAL CONTRACT
EXTRAS TO DATE
CREDITS TO DATE
CONTRACT TO DATE
AMOUNT OF PROP. CHANGE ORDER
REVISED CONTRACT AMOUNT
TOTAL REVISED CONTRACT AMOUNT
PER UNIT
REVISED COST SHARE
TOTAL REVISED CONTRACT
DEVELOPER -AWARDED -PROJECT CHANGE ORDER
Wellinqton Area 3 North Phase 1 B
Water, Sewer, Drainage, Pavinq, and Street Liqht Improvements
23-0122 CITY PARTICIPATION
105028
30114-0200431-105028-EO7685
X-27897
W-2950
James Ruiz Phone No
Ram Tiwari Phone No
No
817-205-1256
817-392-2237
CONTRACT UNIT
WATER I SEWER I PAVING
Developer Cost City Cost Developer Cost City Cost Developer Cost City Cost
$938,098.00 I $989,161.00 $1,945,548.00
$938,098.00 $0.00 I $989,161.00
$938,098.00 $0.00 I $989,161.00
$938,098.00 I $989,161.00
Dev. Cost: $4,972,924.50
$1,945,548.00 I $0.00
$ (32,980.50)I
$1,912,567.50 I $0.00
$1,912,567.50
City Cost:
$4,972,924.50
CHANGE
ORDER No:
1
DRAINAGE
I STREET LIGHTS
I
I CONTRACT DAYS
beveloper
eveloper Cost City Cost
Cost City Cost
$932,772.00
$200,326.00
136
$932,772.00 $0.00
$200,326.00 $0.00
136
0
$932,772.00 $0.00
$200,326.00 $0.00
136
$932,772.00
$200,326.00
$0.00
REVIEWED
By TiwariR at 3:22 pm, Oct 22, 2024
Revised: 10-12-2011 Page 1
Asterisk () indicates New Pay Item
You are directed to make the following
changes in the contract documents
UNIT N: PAVING IMPROVEMENTS
CITY BID ITEM
PAY ITEM 0
a
QUANTITY
7
3213.0302
358
12
3291.0100
-176
13
3292.D400
-1585
14
"99,0011
-19\`555
19,
9999.0017
14.866
UNIT
ITEM DE� e�TtO
UNIT PRICE
TOTAL
SF
5 txlCte
$ 4.50
$
1.611.00
CY
5FSeeding,
f
T99q oil
j lyi4rornuk:h
�pncrekedewalk
$ 32.00
$ 2.00
$ 5.50
S
$
S
(5\ 00
f3 7..
Itt5j�26
SF
TOTAL
V Concrete Sidewalk
S 5.50
S
$
81 M.00
Milli . )
Asterisk(*) Indicates New Pay Item
REASONS FOR CHANGE ORDER Sidewalk changes due to updated landscape plans TopsoiUSeeding changes due to alternate method provided by Contractor and approved by COFW
RECOMMENDED: APPROVED: APPROVED:
LJA Engineenng HPC �gtonevelop rporatron Conatser Const ron TX
By: ti By'.' By:
Name: Andrew Kubiak. P.E. Name: Ben Luedtke Name: Brock Huggins
Title: Sr. Proiect Engineer Title. Executive Vice President TitlePresident
REVIEWED
By TiwariR at 3:22 pm, Oct 22, 2024
Revised. 10-12.2011 Page 2
DEVELOPER -AWARDED -PROJECT CHANGE ORDER
PROJECT NAME:
Wellinqton Area 3 North Phase 1 B
CHANGE
CONTRACT:
Water, Sewer, Drainage, Pavinq, and Street Liqht Improvements
ORDER No:
CFA #
23-0122 CITY PARTICIPATION:
No
CITY PROJECT #
105028
FID #
30114-0200431-105028-EO7685
2
X #
X-27897
FILE #
W-2950
INSPECTOR:
James Ruiz Phone No:
817-205-1256
PROJECT MANAGER:
Ram Tiwari Phone No:
817-392-2237
CONTRACT UNIT
WATER SEWER
PAVING DRAINAGE
I STREET LIGHTS
I CONTRACT DAYS
I
b eveloper
Developer Cost
City Cost
Developer Cost
City Cost
Developer Cost
City Cost
Developer Cost
City Cost
Cost
City Cost
ORIGINAL CONTRACT
$938,098.00
I $989,161.00
$1,945,548.00 I I $932,772.00
$200,326.00
136
EXTRAS TO DATE
I
($32,980.50)
CREDITS TO DATE
CONTRACT TO DATE
$938,098.00
$0.00 I $989,161.00
$0.00
$1,912,567.50 I $0.00 I $932,772.00
$0.00
$200,326.00
$0.00
136
AMOUNT OF PROP. CHANGE ORDER
$5,400.00
I
I I
0
REVISED CONTRACT AMOUNT
$943,498.00
$0.00 I $989,161.00
$0.00
$1,912,567.50 I $0.00 I $932,772.00
$0.00
$200,326.00
$0.00
136
TOTAL REVISED CONTRACT AMOUNT
PER UNIT
$943,498.00
$989,161.00
$1,912,567.50
$932,772.00
$200,326.00
REVISED COST SHARE
Dev. Cost: $4,978,324.50
City Cost:
$0.00
TOTAL REVISED CONTRACT
$4,978,324.50
REVIEWED
By TiwariR at 3:23 pm, Oct 22, 2024
Revised: 10-12-2011 Page 1
Asterisk (") indicates New Pay Item
You are directed to make the following changes In the contract documents:
UNIT I: WATER IMPROVEMENTS
CITY BID ITEM
PAY ITEM # # QUANTITY UNIT
10" 9999.0018 1 EA
11" 9999.0019 2 EA
REASONS FOR CHANGE ORDER 1"& 2" Irrigation services added to plans.
RECOMMENDED:
LJA Engineering
Name: Andrew Kubiak, P.E.
Title: Sr. Protect Engineer
ITE� DF��RCVIPTION
8"x /11 1, Tap
8"x1" Irrigation Tap
TOTAL
APPROVED:
HPC Wellington Nance Development Corporation
By: 4gd-�Z. / e
Name: Ben Luedtke
Title: Executive Vice President
UNIT PRICE
$ 3,200.00 $
$ 1,100.00 $
S
APPROVED:
Conatser Co
truction TX `
By:
Name:
Brock Huggins
Title:
President
TOTAL
3,200.00
2,200.00
5,400.00
REVIEWED
By TiwariR at 3:23 pm, Oct 22, 2024
Revised: 10-12-2011 Page 2
FORTWORTH.
TRANSPORTATION AND PUBLIC WORKS
October 31, 2024
Conatser Construction TX. L.P
5327 Wichita St
Forest Hill, TX 76119
RE: Acceptance Letter
Project Name: Wellington Area 3 North Ph 1B
Project Type: Water, Sewer, Drainage, Paving & Street Light
City Project No.: 105028
To Whom It May Concern:
On September 18, 2024 a final inspection was made on the subject project. There were punch list items
identified at that time. The punch list items were completed on October 18, 2024. The final inspection
and the corrected punch list items indicate that the work meets the City of Fort Worth specifications and
is therefore accepted by the City. The warranty period will start on October 18, 2024, which is the date
of the punch list completion and will extend of two (2) years in accordance with the Contract
Documents.
If you have any questions concerning this letter of acceptance, please feel free to contact me at Ram
Tiwari ram.tiwari@fortworthtexas.gov.
Sincerely,
le %I .'
Ram Tmari (Nov 13, 202411:18 CST)
Ram Tiwari, Project Manager
Cc: Richard Walden, Inspector
Gary Deyon, Inspection Supervisor
Edward Davila, Senior Inspector
Andrew Goodman, Program Manager
LJA Engineering, Inc, Consultant
Conatser Construction TX, L.P., Contractor
Hanover Property Company, Developer
File
E-Mail: TPW_Acceptance@fortworthtexas.gov
Rev. 8/20/19
AFFIDAVIT
STATE OF TEXAS
COUNTY OF TARRANT
Before me, the undersigned authority, a Notary Public in the state and county aforesaid,
on this day personally appeared Brock Huggins, President of Conatser Management Group, Inc.,
general partner of Conatser Construction TIC. LE known to me to be a credible person, who
being by me duly sworn, upon his oath deposed and said:
That all persons, firms, associations, corporations or other organizations fumishi,ng
labor and/or materials have been paid in full;
That the wage scale established by the City Council in the City of Fort Worth, has
been paid in full; and
That there are no claims pending for personal injury and/or property damages;
On Contract described as:
WELLINGTON AREA 3 NORTH PH. 1B
WATER, SANITARY SEWER, DRAINAGE, PAVING
& STREET LIGHT IMPROVEMENTS
CFA PRJ # 23-0122
CITY PROJECT # 105028
CITY OF FORT WORTH
STATE OF TEXAS
CONATSER CONSTRUCTION TX,1,P
Brock HuggigR
Subscribed and sworn to beforoe me this 15'' day of October, 2024.
R&I-!�
r+ P„� S,rrarT,us. .. � %`big" . Notary Public in Tarrant County, Texas
YCMTOJOM :prsR
• N(Neenii M, IM
S
CONSENT OF
SURETY COMPANY
TO FINAL PAYMENT
Conforms with the American Institute of
Architects, AIA Document G747
PROJECT:
(name, address)WelllnO" Area 3 north Phase 1B
Fort worth, Tx
TO (Owrterl
OWNER
Li
ARCHITECT
❑
CONTRACTOR
❑
SURETY
❑
OTHER
Bond No 0256224
HP VVEO-1NGTON NANCE DEVELOPMENT ARCHITECT'S PROJECT NO: CFA va. 23-0,22
CORPORA71ON AND THE CITY OF FORT WORTH CONTRACT FOR:
300t Knox St , Sude405 Wel gton Area 3 North Phase 11; - VN`ater. Sewer. Pawng, drainage,
a Street Light Improvements
lianas TX 75205 J CONTRACT DATE:
CONTRACTOR: CONATSER CONSTRUCTION TX. L P
In accaordance with the provisions of the Contract between the OvsT1eT and the Contractor as indicated above, the
Own itt"z% n*mp and address of surety Ccer:parrld
BERKLEY )N5URANCE COMPANY
475 Steamboat Road
GreenvAch CT L�E30 . SURETY COMPANY
on bond of Thera inwt name end address of con trectorf
CONATSER CONSTRUCTION TX. L.P
5327 vVchfta St.
Fort 1Nartrl TX 76119-6435
,CONTRACTOR,
hereby approves of the final payment to the Contractor, and agrees that final payment to the Contractor shall not relieve
the Surety Company of any of its obligations to there -nsan name and address of Owned
HP WELLINGTON NANCt= DEVELOPMENT CORPORATION AND THE CITY OF FORT WORTH
3WI Knox $t., Suite 405
Dallas TX 75205
as set forth in the said Surety Company's bond.
IN WITNESS, WHERECIF,
the Starcty Company has hereunto set its hated this
Attest:
(Seal):�-
14M day of October, 2024
BERKLEY INSURANCE COMPANY
Surety Company
Signature of Authorized Representative
Rotti Morales
Title
OWNER,
Attornev-in-Fact
MOTE_ This farm is to he used as a comoaninn danumemt to AIA DOCUMENT G706, CONTRACTOR'S AFFIDAVIT OF PAYMENT OF DEBTS AND CLAIMS,
Current Ed9tion
ON1E PAGE