HomeMy WebLinkAboutContract 61577-AR1CSC No. 61577-AR1 FORT WORTH . City of Fort Worth Construction Allowance Request Project Namel Park Vista Boulevard -Keller Haslet Road to Timberland Boulevard Client Project #(s) l 103281 I City Sec # 161577 Project Park Vista Boulevard -Keller Haslet to Timberland -Roadway, Drainage and Illumination Improvements Description Contractorl McClendon Construction Company, Inc. I CA#I 1 I Datel 11/6/2024 City Project Mgr.I Mitch Alton I City Inspectorl Steve Johnson UNIT or DEPT Original Contract Amount Extras to Date Credits to Date Current Contract Amount JAmount of Proposed Allocation Original Allowance Available to Allocation Allowance Funds Previously Allocated Revised Allowance Balance Unit I - Paving $3,309,611.75 Unit II - Storm $572,305.00 I Totals $3,881,916.75 $3,309 611.75 $572,305.00 $3 881 916.75 $25 589.27 $0.00 $0.00 $0.00 $25 589.27 $300,000.00 $0.00 $300,000.00 $0.00 $274,410.73 $0.00 $0.00 $0.00 1 $274 410.73 NMI JUSTIFICATION (REASONS) FOR CONSTRUCTION ALLOWANCE IN ACCORDANCE WITH THIS CONSTRUCTION ALLOWANCE REQUEST, THE CONTRACT SHALL: An irrigation line owned/operated by the HOA at Rustic Timbers Dr and Park Vista Blvd was cut off and needs to be repaired as well as relocated to clear the proposed pavement. The proposed price for the Irrigation work comprising 108 LF irrigation pipe and appurtenances is a LS of $4,589.24 for approximately $42.49/LF. On Project 102101 Trinity Boulevard, the irrigation cost was $932,756.83 LS for approximately $25.50/LF, however this is all new installation and it has economies of scale. Staff deems the proposed price reasonable. Additionally, the plans didn't call for the illumination and signal poles to be powder -coated black. The existing Keller Haslet and Park Vista traffic signal poles at the project's north end are powder -coated black. For consistency, poles will be powder coated for an extra $21,000. The proposed price for the powder coating is $18,750.00 for 13 Illumination poles and $2,250.00 for 2 signal poles, for a total cost of $21,000.00 and an average of $1,615/pole. On Project 101009-2 Bonds Ranch and FM 156, 7 signal poles and 4 mast arms were powder -coated black through a change order for $24,220.00 or an average of $2,201/piece. Staff deems the proposed price reasonable. It is understood and agreed that the acceptance of this Construction Allowance Request by the contractor constitutes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to, the above Construction Allowance Request. The Project/Program Manager signing below acknowledges that he/she is the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements. McClendon Construction Company, Inc. I Justin Blair Va4— Nov 19, 2024 Inspector/Inspection Supervisor Date Project and Contract Compliance Manager Date s+e✓e .Tah,Io Nov 17, 2024 Mitchell Aitm Nov 15, 2024 Program Manager Date Senior Capital Project Officer Date - ---- - - Nov 19, 2024 'AU Nov 19, 2024 Assistant Director (Dept) Date Director, Contracting Department (Dept) Date yatrioia L, wad5acK Nov 19, 2024 de-7— Nov 19, 2024 Assi§jgnt City Attorney Date er Date Nov 21, 2024 Nov 26, 2024 'F fo ATTEST:w Jannette Goodall, City Secret ry Construction Allowance SUMMARY Page 1 of 4 OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX FORT WORTH, City of Fort Worth Construction Allowance Additions Project Name I Park Vista Boulevard - Keller Haslet Road to Timberland Boulevard pity Sec # 1 61577 1 Client Project # 1 103281 1 Contractorl McClendon Construction Company, Inc. PMI Mitch Alton Inspector) Steve Johnson Construction Allowance Submittal # 0 ate I 11/b/"ZU24 I ADDITIONS ITEM DESCRIPTION DEPT Qty Unit Unit Cost 74A 9999.0000 Rustic Timbers Irrigation Repair Unit I - Paving 1.0000 LS $4,589.24 74B 3441.3352 Furnish/Install Rdway Illum TY 18 Pole (Add Powder Coat Black Finish) Unit I - Paving 13.00000000 EA $1,442.31 74C 3441.1615 Furnish/Install Type 45 Signal Pole (Add Powder Coat Black Finish) Unit I - Paving 2.00000000 EA $1,125.00 Unit I - Paving Unit II - Storm Total Additions Total 1 $4,589.241 $18,750.031 $2,250.001 $25,589.271 $0.001 $0.001 $0.001 Construction Allowance Additions Page 2 of 4 FORT WORTH. City of Fort Worth Construction Allowance Value Project Name I Park Vista Boulevard - Keller Haslet Road to Timberland Boulevard I City Sec # I b15// Client Project # 1 103281 1 Contractor McClendon Construction Company, Inc. I PM1 Mitch Aiton I Inspector) Steve Johnson Construction Allowance Submittal # Date I 11/6/2U24 I CONSTRUCTION ALLOWANCE VALUE BEING USED ITEM DESCRIPTION Qty Unit Unit Cost Total Unit 1 Item 70 9999.0000 Construction Allowance 0.085298 LS $300,000.00 $25,589.27 Construction Allowance Value 3of4 MISBE for this Construction Allowance Request MISBE Sub I Type of Service I Amount for this CAR Total $0.00 I Previous Construction Allowance Requests CAR # I DATE I AMOUNT Total 1 $0.00 I Construction Allowance MSBE Data Page 4 of 4 REQUEST FOR INFORMATION REPORT (RFI) CONTRACT Park Vista - Keller Haslet to Timberland 1.0 1 • PRIME CONTRACTOR 61577 McClendon Construction Company BJ Blair Project Manager McClendon Const 817-829-0251 10/11/24 DECREASE IN COST DECREASE IN TIME # of Days = An irrigation line for the HOA at Rustic Timbers and Park Vista needs to be repaired and relocated out of the way of the paving. CONTRACTOR RECOMMENDATION McClendon's sub will repair the line and relocate as necessary to continue with the paving. Mitch Aiton I Sr Professional Engineer 682-715-9424 Relocate the irrigation as necessary. The proposed price for the Irrigation work comprising 108 LF irrigation pipe and appurtenances is a LS of $4,589.24 for approximately $42.49/1-F. On Project 102101 Trinity Boulevard, the irrigation cost was $932,756.83 LS for approximately $25.50/1-F, however this is all new installation and it has economies of scale. Staff deems the proposed price reasonable. 10/11/24 No Schedule Impact 10/11/24 Mitch Aiton, Sr Professional Engineer I 10/16/24 1 0 1. M.. ml. 4 rm En • «oux,. ,�:«,,,« ,n",hww".�zoa LEOEND -- ,.,ao Mrw:,, F».s o. ,no. �••`.• ,no. aRw"µ F.w»; ox r a ----- gz �«"_ --- --w� �=g `'--------------- VMT Irrigation o LAT_- -- ------ _ , repair and relocate for o PERDEnDN 13,3 F._r .. PER CONC P a]2 iE3 13 -� paving. FRER � ...... `' ''' PEre TERIAL '' DECno�^"'zRo;Tls' AR s/aTRCIresPaNT /' . /, Bldl st bem De -notion Spec No. Unit Qly N zaa ea 's a / Item No. Number pEa sccnory iz ii zo coxc #`ELEV nze4o I} 20 3123.0101 Unclassified Excavation by Plan 312316 CY 1774 sTry zzs 11__ ExST STORM SEE SHEETVt2. ?I 513' OT 36'4 ,6 = 120 11' LE OS0 0 Ib PC sT,STA = i9+ea.ss G l N 1 21 3124.0101 Embankment by Plan 312400 CY 7 ® 4" coxc sioEwALK 10646) 24 3211.0400 Vdmted Lime 3211 29 TN 40 PER SECTION 32 13 zo SEE TSHEE �12 Q 25 3211.0502 Lime Treatment 321129 SY 1646 m _ 1V)7 28 3213.0106 11"Coot PvNt 321313 SY 855 vLoreCs SOD PLA EMENT nETR T .. 3' 2D C 71 W 27 3213.0206 11"Coot Pvm1 FES 321313 SV 667 PER sEcnory 3z 91 19 ;EE SHEET 12 r 9 �, . ?jj « •�' Z 28 3213.0301 4" Conc Sidevalk 321320 SF 6695 . 30 3213.0506 Bamer Free Ramp, TWO P-1 321320 EA 2 CONTROL POINT --STA 1H+7644 10 1 IT 42 3291.0100 6�TDsot 329119 CY 208 srA 1e+4s 61 to.50 RT J I _ U 43 3292.0100 Block Sod Placement 329213 SV 1246 Q� 69 9999.0001 5" Colored Textured Concrete 999999 SF 697 TA8,4(559,1fi992H "PARK VISTA BOULEV D MATCH Es*T'P27224. MATCHE t (CONCRETE) w 0 " I------------------- - - - - - - - - - - ------I CAIJTI I I I NOER. G N I I BENCHMARKS I 1■■■■■■ 1■■■■■■ 1■■■■■■� 1■■■■■�U �.. 1■■■■I■ 1■■■■■■ I■■■A■■ 1■��■■■■ II■■■■■ .■■NOON ��■■■■■■■ ■■■■■■■■ ■■■■■■■■ ■NOON■ ■■■■■■■■ ■■■■■■■■ ■■■■■■■■ ■■■■■■■■■ ■■■■■■■■■ ■■■p■■■■■■ ■■■� ■■■■■■ NOON■■ ■■■■■E ■ ■ MONOMERS ■■■■■■■■ ■■■■EMEM 10■■■■■■■ . . NOON■■ ■■NEON ■ ■ ■■■■■■■■ ■■■■■■■■ ■■■■■■■■, ■■■■■■■■ NOON■■ ■ ■■■■■■■■ ■■■■■■■■. ` 1■■■■■■ 1■■■■■■ 1■■■■■■ 1■■■■■■ FA� 1mom ■■■ NOON■■ ■ ■■■■■■■■ ■■■■■■■■ ■MOON■ No ■■■■■■ No ■ ■ ■ ■■■■■■■■ ■■■■■■■■ ■■■■■■■■ ■■■■■■■■ ■■■■■■■■ ■■■■■■■■ ■■■■■■�■1■■■■mo11■I■■■■■■■■ I■■■■no I■■■E■■ ■■■■■■ ■ ■■EN■■■■ ■■■■■■■■ NOON■■ ■ ■■■■■■■■ ■■■■■■■■ 105M14itiii 1■■■■�■: I■■■■■■ IIC■ 1■■■■■■ E�IC iiG■■N m am{am■::ma Em■a■mmE Y3■■■■■ ■ ■■■■■■■■ ■■■■■■■■ NOON■■ ■ Edo Eiiii • Niii■iiiiiiE ■■ ■� ■■■■■■ ■■■■■■■■■■■� ■ ■■■ ■■■■MEMO ■■■■■■■■ ■■■■■■■■■ -. 1■■■■■■ �■�■■■■ 1■■■■■■ IE■NONE 1■■ENE■ �... " 1■ENNEN 1■■■■■■ 1■ENNEN I■■■■■■. ■■■■■■■■ ■■■■■■■■ ■■■■MEMO■ ■■■ ■■■■■■■■ ■ ■■■■■■■■ ■■■■■■1 ■■■■■■■■■ ■ONION■MEN .■E■E■E■E MEN ■■■■■■■■ ■E■E■E■E ■E■E■E■E ■■■■■■■■ ■■■■■■■■. .■E■E■E■E ■■■■■■■■ ■E■E■E■E ■E■E■E■E ■E■■E■E■ ■■■■■■■■. 0 ■■■■■■■■■ ■EN■■■NEE ■E■■E■E■E ■EN■■■NE®' ■■■■■■■■�1 ■■■■■■■■E9 19,50 20+ 0 20+50 ON EAST SIDE OF PARK VISTA ON BACK OF CURB INLET NSOUORTH rvOF PANCOLIINDfi 310' NORTH OF TREEFERN DR, 16 EASTING - 234,1r423382 ONMWEST SIDE OF PARK VISTA 966NORTHEAST OF KELLER HASTMr TOO 'T OAF FERN VALLEY DR NORELE AmNN 23'S039 t03 *+y N cNEss �s cT L E�2rc �oxA `4- 06 REV N Y TOLD RENEW DESCRIPTION 6% %2024 ORTWORT CITY OF FORT WORTH, TX TRANSPORTATION & PUBLIC WORKS PARK VISTA BOULEVARD IMPROVEMENTS PAVING PLAN & PROFILE PARK VISTA BOULEVARD STA 17+00 TO STA 20450 re Raeies io: �°;., weti�mm z,e,oz T�Re'A�Mmexo" No F-,o46 DESIGNED CJK DATE PROJECT NO Sleet DRAWN. SHAF 21 CHECKED CWG FEB 2024 10)32-01 0 128 GRISSOM'S IRRIGATION SERVICE 5025 Mill Creek Tr. Fort Worth, Tx. 76179 817-966-2844 Bill To McCLENDON CONSTRUCTION CO., INC P.O. BOX 999 BURLESON TX 76097 Quantity P.O. No. Park Vista Description Date 8/30/2024 0 IcaY 1 1 1-1/2" ELBOW PVC 1 1-1/2" x 1-114" REDUCER BUSHING PVC l 1-1/4" X I" REDUCER BUSHING I I" CAP PVC 1 1-1/4" CAP SLIP PVC 1 14/4" 90 SLIP PVC 2 1-1/4" CS 200 PVC PIPE PER FOOT 2 l" CLASS 200 PVC PIPE PER FOOT 2 LABOR LOCATE ,MAP AND REMOVE SPRINKLER HEADS ALONG CURB AT THE MEDIAN ON PARK VISTA PORT WORTH TEXAS Total $4,172.04 + 10%=�$4,589.24 Total Cost Terms Due on receipt Rate 2.90 2.35 1.80 1.25 3.01 2.24 1.25 1.26 225.00 0.00 Invoice Invoice 2940 Project Amount 2.90 2.35 1.80 1.25 3.01 2.24 2.50 2.52 450.00 0.00 Thank you for choosing Grissom's Irrigation Service Total $468.57 GRISSOM'S IRRIGATION SERVICE 5025 Mill. Creep Tr. Fort Worth, Tx. 76179 817-966-2844 Bill To McCLENDON CONSTRUCTION CO., INC P.O. SOX 999 BURLESON TX 76097 IP.O. No. PARK VISTA Quantity Description 2 3/4" 90 SLIP PVC 2 3/4"CAP PVC 4 3/4" CLASS 200 PVC PER FOOT 2 LABOR LOCATE ,MAP AND REMOVE SPRINKLER HEADS ALONG CURS AT PARK VISTA AND PANGOLAN DR FORT WORTT3 TEXAS Invoice Date Invoice # 10/31/2024 2993 Terms Due on receipt Rate 1..47 0.92 0.98 225.'00 0.00 Project Amount 2.94 1.84 3.92 450.00 0.00 Thank you for your business. Total $458.70 FORTWORTH. Routing and Transmittal Slip Transportation & Public Works Department DOCUMENT TITLE: Park Vista CA #1 M&C: N/A CPN: 103281 CSO: 61577 DOC#: N/A Date: 11/11/2024 To: Name Department Initials Date Out 1. Jessica Rodriguez TPW - Review Nov 15, 2024 2. Mitch Aiton TPW - Signature 11ARA Nov 15, 2024 3. Justin Blair McClendon - Signature �a Nov 19, 2024 4. Steve Johnson TPW — Signature s, ss Nov 17, 2024 5. Raul Lopez TPW - Signature Nov 19, 2024 6. Lissette Acevedo TPW — Signature C�v Nov 19, 2024 7. Patricia Wadsack TPW — Signature PL'W' Nov 19, 2024 8. Lauren Prieur TPW — Signature I 'gyp Nov 19, 2024 9. Doug Black Legal — Signature Nov 21, 2024 10. Jesica McEachern CMO — Signature Nov 26, 2024 11. Jannette Goodall CSO - Signature sG Nov 26, 2024 12. TPW Contracts CC: Program Manager, Sr. CPO, TPW BSPAP Recon Team, TPW Records Room, TPW Contracts DOCUMENTS FOR CITY MANAGER'S SIGNATURE: All documents received from any and all City Departments requesting City Manager's signature for approval MUST BE ROUTED TO THE APPROPRIATE ACM for approval first. Once the ACM has signed the routing slip, David will review and take the next steps. NEEDS TO BE NOTARIZED: ❑YES ®No RUSH: ❑YES ❑No SAME DAY: ❑YES ❑No NEXT DAY: ❑YES ®No ROUTING TO CSO: ®YES ❑No Action Required: ❑ Attach Signature, Initial and Notary Tabs ❑ As Requested ® For Your Information ® Signature/Routing and or Recording ® Comment ❑ File Return To: Please notify TPWContractsnu,fortworthtexas.gov for pickup when complete. Call ext. 7233 or ext. 8363 with questions. Thank you! GRISSOM`S IRRIGATION SERVICE 5025 Mill Creek Tr. Fort Worth, Tx. 76179 817-966-2844 Bill To MCCLENDON CONSTRUCTION CO., INC P.O. BOX 999 BURLESON TX 76097 P.O. No. PARK VISTA Quantity Description 4 2-1/2" ELBOW PVC 60 2-1/2" CLS 200 PVC PIPE PER FOOT 2 2-1/2" COUPLING PVC 40 4" SCH 40 PVC PER FOOT 6 3/4" 90 SLIP PVC 1 3/4" COUPLINGPVC 315 14 GAUGE VALVE CONTROL WIRE PER FOOT 14 LARGE WATERPROOF WIRE NUTS SILICONE FILLED EACH II LABOR LOWER SPRINKLER MAIN LINE IN GRADE AT PARK VISTA AND RUSTIC TIMBERS FORT WORTH TEXAS Thank you for choosing Grissom's Irrigation Service Terms Due on receipt Invoice Date Invoice # 10/31/2024 2994 Project Rate Amount 13.41 53.64 3.60 216.00 7.85 15.70 4.29 171.20 1.47 8.82 1.31 1.31 0.76 239.40 4.55 63.70 225.00 2,475.00 Total $3,244,77 REQUEST FOR INFORMATION REPORT (RFI) Park Vista - Keller Haslet to Timberland 1.1 1 • PRIME CONTRACTOR 61577 M Clendon Construction Company BJ Blair Project Manager M Clendon Const 817-829-0251 SECTION(S) Powder Coat Signal and Illumination Poles POTENTIAL COST• NO CHANGE i NO CHANGE INCREASE IN COST $ 21,000.00 INCREASE IN TIM DECREASE IN COST DECREASE IN TIM of Days = of Days = 10/23/24 The plans didn't call out for powder coated signal and illumination poles. Keller Haslet and Park Vista traffic signal is powder coated black, would you like to match. We can provide galvanized at bid cost or powder coated for extra $21,000. $18,750.00 for 13 illumination poles and $2,250.00 for the 2 signal poles. Mitch Aiton I Sr Professional Engineer 682-715-9424 Powder coat the poles at $21,000. The proposed price for the powder coating is $18,750.00 for 13 Illumination poles and $2,250.00 for 2 signal poles for a total cost of $21,000.00. On Project 101009-2 Bonds Ranch and FM 156, 7 signal poles and 4 mast arms were powder coated black through a change order for total cost of $24,220.00. Staff deems the proposed price is reasonable. 10/23/24 No Schedule Impact 11/05/24 \ / ,maa sI.:W,m Dms M i ,m°..,.wr•,..,as oR I m ,m°. sDwrw aNMa M I LEQEND PROPOSED STREET LIGHT 240/430V METERED PEDESTAL =& � sR.mrx Fnms wn • - PROPOSED POWER POLE CONDUIT BORE asxu rox muu,s\ \ wLw\ // CONDUIT TRENCH vow uaJ -- --.. M2awxMmr TYPE D GRDDND BD. Ye/ mxu ew----------- - 6 E%ISTNG STREET LIGHT .ate. a°x + Bidlist Item tern No. Number Description Spec No Unit Qly N 14 2605.3015 2"CONDT PVC SCH 80� 260533 LF 235 52 3441.1405 NO 2 Insulated Elec Co r 344110 LF 705 oO - y r - -' - - - W FurnisI /Install Ground Box Type B, Z 55 3441.1502 344110 LF 1 aFamx oa�x s.w. �1p J w/APfOn ..ww s°x .nmm, skx 57 3441.1645 Fumis[VInstallTge 33AArm 344120 EA 4 U FunrislVirstall LED Lighirg Fixture P1C1A aIm F 61 3441.3051 34 41 20 EA 4 ((1I 7 watt AT82 Cobra Head]j -- PARK VISTA BOULEVARD Rdwy ilium Foundation TY 3,5,6, 62 3441.3302 and 8 34 41 20 EA 2 63 3441.3352 Furn sI Vlnstali Rdmy Ilium TY 18 34 41 20 EA 2 Pole - — - - — NI CONCRETE FOUNDATION T IO TO BE mm `--- �- TDN---- CTFU IN Illumination Poles to °�CREEF°°"°ATI°NFDR=REET°°HT .T rM. / t I u"DERacERourvo i 2 sENTENEREs W1THIn MEDIANS MUST BE wsrALLED r t Powder Coat Black. (2) 3 CZ18STREE1";N"�R a�` o L "E° B m LIGHT GG CONSTRUCTION N DINO s.+uL wx:/ / u.a roxc.x m a xsv ,oim.,: Tn mT mA-4-mniCONDUITS HALL BE SCH LE BURIE f CONDUITS 5 AT A TOP DEPTH OF 36°EDFROM FIINISHEDO STREET GRAD eYMMMYOF CONDYITNHD CAOIEe FOR eTA I i 5 STREET LIGHTEFWNDATgJs SHALL BE C OU' R ,zmz sOoear RX.. I z I ew I N I I ®° 9 i ASSETSEO 5 MINIMUM FROM ALL WATER corvouR I ,mla xPOWN,xMa M I a .,. , a,°a iUw`�.A.s M I ,mm a,DPwv rnwa m I ,zam °^ 11°� N015 °t PROYEDNBY GttW MATERIALS MUSTBE RUN s� LB i�H rRirRicltism oN cro m I I -9 6 QL� UGHTNG APPROVED PRODUCTS LIST) 1 s m i I s I MRING/CABLES MUST BE COPPER j ° 4,---I------- -----° -- ` Oxe BT Mm umr nx \vkw -� tF.OFHH. BNE sRTux.w rw.s xw n COxouITTOTx �mm Fuw mc. Mw BID SUMMNRYOFROA YMETING O UANTmESAT \ wlTn ExISE IN `�n j STA 17a97T017+00 =- --- - STUB OUiTING ue H -aa QI ATBO P303 MVOLTR 10 •/ SEE NOTE B ROIM]BOXES e. ' _IMPNRETYPE 3KFPNl_ M O n REV DESCRIPTION BY DATE �Ol1hDATpNTY_ 3 �- R I _ ---- -=H6a6p-_--_ JIMINAIRE HEPDSy----_-- -� to+oo - -__ ---_- 3SAD SY]L1M IbMACTOR - N _ — - � - Y� `-'i--..«--- -- F- '6 IrypAETEREOPEOESTAL - W 0 CITY OF FORT WORTH, TX �pry�(�1V4�c 33A Z wsm-__-__ T-D, --L--_-__------------- ORT WORT TRANSPORTATION & iVlln nunnmry a ---------. - 41 -- - — - ----- _ T-Dz --- Z PUBLIC WORKS ate° PARK VISTA BOULEVARD > - - _-- U PARK VISTA BOULEVARD IMPROVEMENTS SCHEDULE OF ILLUMMATN)M RDODNMY ASSEMBLIES H — STA—To w NI Q - POLE No. TAi TR ILLUMINATION P/eKuroA iM]fl86 ifia)837 —roc— _ nres�FT�� n v _ - — - -.trc�Fw�r - PARK VISTA BOULEVARD r,�x��x.i� T— --- ------Ftrz - --x- a - A 10.00 TO STA 17.00 _ m...,T.� ST w<w _�- o: FOUNT pRgN 3 3 __ 11r LUMINARE A7BUP30_UD ATBDPM3YWLi -y--- - I I 0 GOUND I-eeTaeixe. w.w epenv mm jBx zTetpl —E R23KMPNLP]AD R23KMPNLP]AD I I I UN PER I wsn. TO epatrexon rv°F-loos DRLL F➢Z,3Yl! R1D2e, I I I II DATE PROJECT N0. Sheet oEscNEo ss DRAWN. SNAP 77 oaNTLL.T I ,mm I m.,..,aa... �xam1e�1I.T FEB z°za ioT3z-oi 8 e I CHECKED BGE P 12R SUMMARY OF ROADWAY LIGHTING DU.11111 AT STA -00 TO 20.50 ATBO P303 N10 LT AZ _UMHMf TPf 3K LIP NL PTA➢ ?IIM UNAR NEID Bf i a u I M GUPNTTY oPeoesT I to x. I ,:,a. mMw,x ..� xx,�� ,w,Iw.xF I ,z-w,l ..,ten= .YR m SCMmULE OF LLUY,TA,T«rozom NAT OADWAY Ox R ws: F:FOR RD BNDT.G. m - - — T a - ARMTYPR Z �F-�O O _--._----.- 33e 18i00 ATDOT>3Da M.oLr wTlm F3m MOLT �I /--� _ - "'-- PARK VISTA BOULE corouT NO d� AEI _ ` _ _ _ _ - =i.-ter— �- IRS— usr I , "- B-1 - I I I -- I n e'xFIUIT T »n T N�I,FI ,arse iw,xm 1 x 1 � e w o u w, I SCHEDULE OF ILLUMINATION ROADWAY ASSEMBLIESFOR TA20.50TO24.50 POLE N0. T-05 TL6 T-0) DII ,n,e mTwxw -. on I —wx I I F-B IM I G- mmrx FMus Iw I 1-1 PARK VISTA 21-40.21 Z369.07 2M3797 —ON _ R --AIL-- BIT BIT LT POLETYPE 18 18 18 FOUNDATION N 3 3 3 TYPE ARM ttPE 33A 334 S. LLMNUFE ATBO P313 M. ATBOP303MVOLT ATBO P303 MVO LT TYPE R23K MP KP/A0 R23K 3K w MP NLP]AO R2MPPl AO RF2'YYf)92 RF MPRFm377]Rl DRLL SH' DI0. 2P 2f 2V DRLLSFIAFT 8 8 8 IENGTHIPTI — (T— �t r:q-i�yt LO 0 LV N _z1 z — — J 2 SUMMARY OF ROADWAY LIGHTING GUANTITIESAT SFA2D,50TO24*50 DIE DINMT' 3 ATBO P3aT MVOLT R2 _IMNVRE TYPE 3K MPNL RFD322). 92-OLMATIDNTYPF TVPF3 �RmIMBOXES fTY Bf 2 UAMMIRE FEA 8 ?AD MDIM E RED PEDR AOM80V METERED M TYPY E4re a:,x, Vi �A 2z+oo PARK VISTA BOULEVARD (CONCRETE) LEGEND PROPOSED STREET LIGHT —/430V METERED PEDESTAL • PROPOSED POMER POLE CONDUT POPE 0 CONDUIT TRENCH TYPE B GROUND BOX EXISTING STREET LIGHT Bidlist Item No. Item Number Description spec No Unit Oty 14 2605.3015 2" CONDT PVC SCH 80 26 05 33 LF 760 52 3441.1405 NO2 Insulated Elec Con r 34 41 10 LF 2280 55 3441.1502 FurnistVlnstall Grrpound Box Tvpe B, 3441 10 LF nstall Ty 33A Arm 3441 20 EA 10 61 3441.1645 FurnisIlInstall 3441 20 II EA 62 3441.3302 R Ilium FpundatlonM7V 3,S,6,rarq 34 41 20 FA 5 - I1 63 3441.3352 FLrrns,/Install R tway Ilium TY 18 Pol 34 41 20 EA 5 --- OMS Illumination Poles to N I CONCRETE FOUNDATION FOR STREET LIGHT STRUCTURE NS MUST BE ry I CENTERETING S I EIDIANABE INSTALLED Y Powder Coat Black. (5) NYGo Fo wDRT„PRE-WALImEDB x omx'1u, ( I SUMMRYOF ONDUITANI SFOR STA20.50TOIH50 / CO�r CONDLIC R NO. RON NO. S. LENGTH RE(B) LT) H(r) PROP EMT 2- 25 1 3 -8 2- BO T 3 RA 2- 5 T \ 3 R-10 Y 150 T 3 - R-11 7 1M T 3 R-12 7 15 T 3 SHEET SHEET CONDOR TOTAL HO CABLE 1Z70 (LF),. TOTAL ILF) C _ _ - a x aw� Tr zwx"nR max. ZG cc non W o I I I NOLF ec«ourvo I I I w v I I I I I I W I ~ I x.51P,zro, Fvwv In R,. ,x,R mv.,, uNm um mxwn,x xm. ,nn mnxr m 15 ,m, Foxwx In �� ,xm mvw m ,� 3 CALL 817C999-79T UGHT CONSTRUCTIONRPRI TO AN' STREUDING CONDUITS 6 CONDUITS SHALL BE SCHEDULE 80 BURIED AT A TOOP BEEPTH OF 36- FROM FINISHED STREET 5 STREET DGHTEFOUNDAn011S SHALL BE ASSETSED 5 MINIMUM FROM ALL WATER u G TNGl BE W"ARIMEMATERALS MUSTNT ((-7 ALL UH /LABESMU ST APPROVED PRODUCTS LIST) PDO rzPno REV OESCRIPmON BYF� DATE 04 V) =� H to Z ORTWORT CITY OF FORT WORTH, TX TRANSPORTATION & = PUBLIC WORKS QPARK VISTA BOULEVARD IMPROVEMENTS ILLUMINATION PARK VISTA BOULEVARD STA 17+00 TO STA 24+50 x-BBTASIU3o. w.w �exemm.,A'. MI>E,axR�menxx rvx - DESIGNED SS DATE PROJECT NO Sheet DRAWN. SH/LF 78 CHECKED BGE FEB 2024 1 10732-01 1128 SUNIMARY OF UGNRUR AND CABLES FOR STA-50 TO za oD I I I LU I CONDUCTOR 1 'xm I 1 ' w w I Iusn axis CONDUR N0. I ,nw srtwxw rwlrs w I 'm« srnoxm rxms w I ,mu sleuwx Nus w 0 ,moo sleuwx rxms w I ,xw slMexw rnaa on RUN I Z sn® wn w s{x No. BIZ: LENGTH RE (B) I J o I DF) TREND. OI Mn .O `. PROP E%LST 0 R 12 2 111 SHEET CONDUIT TOT 3 R-14 2 ww d SHEET noa x wr,u ,xem rxw sa,n nw sm�wrx rwus wn TAL ,mss oux xn. nw (lFi � TOL1L"ISLE(LF) 1U60 SUMMARY OF ROADWAY LIGHTING QUANTITIES AT STA 24-50 TO 28-00 I ND PROPOSED STREET LIGHT • 240/480V METERED PEDESTAL IRS ---• __ S R POLE CONDUITBORE - - - - - - - CONDUIT TRENCH a TYPE B GROUND BOX C EXIST STREET LIGHT I � Lf)i - O - a N DD N ¢ ¢ Bidlist Rem No. Item Number Description Spec No. Unit Oty N----------------- �'-- �y�- z/.DD _ z. _ 14 2605.3015 2'C`OjJD P CS H80 (T) �1 260533 LF 710 W ---__ -� W 52 3441.1405 2 ( nd NO reu ated lec o r 344110 LF 2130 Z-� Z o--------------------- 55 3441.1502 Ground Box Type B, 3441 10 LF 2 U U 57 3441.1645 w/Apronlrlstall FurnisIVIrstall Twe 33AArm 344120 EA 4 H PARK VISTA BOULEVARD H FurnisNinstall LED LI 1,1'n, Fixture < (ODNCRLTE) 61 34413051 1137 waH AT62 Cobra Head) 344120 EA 4 62 34413302 Rdd8111um Foundation TY 3,5,6, 344120 EA 2 POLE QUANTITY LUMNAIRE TYPE - — _I_ — _ ".'cu-Tpicom�uT —__FOUNDATIONTYPE GROUND BoxES(NB) 2 LUMNAIRE HEADS ARM QUANTITY - uxn raw rn I ,,Tv ro ,6 1 IxA ran.. m 1 -., rax. m ' SCHEDULE OF ILLUMINATIO N ROAD WAY I I I I ASSEMB.IESFOR STA28-00TO 31.50 POLE NO T 08 T 09 I 13XX suoWx r'"la N, 1 ,ma sTuomx rmrs °" 1 1.11 sTriowx —B w I I— scwx.x rNne o PARK VISTA CL STATION 28+9831 30+%.98 OFFSET OFFSET Sh1E 7.5 RT 1 2.6 I RT POLE TYPE 18 18 FOUNDATION TYPE 3 3 ARMTYPE 33A 1 33A LUMINARE ATBO P303 NNOLT ATBO P303 MVOLT TYPE R23K UP NL P7 AO RFD322792 R23K M3 NL P7 AO I RFD322792 DRLL SHAFT D A P4. I 24- DRILL SHAFT LENGTH(FT1 8 I 8 SUMMARY OF ROADWAY LIGHTING QUANTITIES AT STA 28+00 TO 31+50 -1-----J---------------- O O 04 N H � o0 z_________ x H PARK VISTA BOULEVARD (GGNGREIE) F°` = L 63 3441.3352 FurnsWInstall 2dmyI1Ium TY18Po344120 EA 2 Illumination Poles to Powder Coat Black. (2) m. 1�rnY. « ' a 1 rxns oa 1 ,mm nT.Pxx rx.s w I POLE QUANTITY 2 w. ATBO P303 MVDLT R2 -- wxwwroF coxourr ANoueLBswR arAaworo s1-w LUMINAIRE TYPE 3K MP NL P7 AO -" w - CO R c R r RFD322792 - TY /- — _ _ _ _ _ _ _ _ _ _ _ _ _ __ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ FOUNDATION TYPE TYPE 31-- - = -L^^' wx GROUND BOXES(TY 81 I III w -F 3 LUMINAIRE HEADS 4 I JI = �— PAD MOUNT CONTACTOR - J-------- �_,�__ caunary 15 I 3 STEREO PEDESTAL \ UNOERCE'OUND AI 33A oxw oTAEIT m QUANTITY 4 ,mv xN T-owx D Irsl R aFl NOTES 1 CONCRETE WIE FOUNDATION FOR STREET LIGHT C RES WITHIN MEDIANS MUST BE CENTERED WITHIN MEDIAN LEE AFCIttGOF FORT WORRTH PRE-WALIRED TA D BY 3 STREETCALL LIINTO TNST PRIOR TIO TINCLUDINGY ONDUIR a CONDUITS SHALL BE SCHEOUrE 80 BURIED AT A TOOP DEPTH OF 36" FROM FINISHED STREET5 STREET DGHTEFOUNDATIONS SHALL BE INSTALLED 5 MINIMUM FROM ALL WATER ASTS SYSTEM MATERIALS GXTNINT ((m UGH ING PROVED PRODUCTS LIST) RE x zW. REV DESCRIPTION11 DATE ORTWORT CITY OF FORT WORTH, TX TRANSPORTATION & PUBLIC WORKS PARK VISTA BOULEVARD IMPROVEMENTS ILLUMINATION PARK VISTA BOULEVARD STA 24+50 TO STA 31+50 Tea a *N:-11 Zm�mm zTsxm I.I E'gealmennn rvn - DESIGNED SS DATE PROJECT N0. Sheet DRAWN. SH/LF ]9 CHECKED ESE FEB 2024 t0732-01 1128 SCHEDULE OF ILLUMINATION ROADVAY ASSEMB LIES FOR STAM-5DT0354)0 POLE NO. T-I T-tt PARKVE:TA n sTAnnN 32I 98 34.56.98 OFFSET OFFSET -DE 25 RF 25 FIT POLE TYPE 18 18 FOUEINTION TYPE 3 3 MUTYPF LUAI 33A ATBO P303MVOLT ATBO P303 MOLT TYPE R23K MP NLP7 AO RFD3Yll92 R23K MEW P7 AO RFD —No DRILL. SHOFT Dl4 24, 24• DRILL SHAFT LENGTH IFTI I 8 8 SUMMARY OF ROADVAY LIGHTING DUANTm ES AT STA 3I+SDTO 35.00 ATBO P303 NVOLT R2 -UAINNRETYPE 3KLPNLP7AO RJEOM 92 -OUNJATp NTYPF NPF3 �ROLW BOXES lIY Bl 'l1A NMRF HFArR d �AD MOUNT LOMACTOR - d0148W METERED PEDESTAL RN nI MNmY d� SCHEDULE OF ILLUMINATIDN ROADMAY ASSEMBLIES FOR STA 354M TO 38*OD POLE ND. T-12 PARKMSTA 36+56.98 --CAL STATION OFFAL 2.5 RT POLETVF'E 18 FOLNDATION 8 TYPE ARMTYPE 334 LUMNNRE ATBOP303%OLT TYPE R23K MP It P7 AD RFD322792 DRILL 24• SHAFT DIA DRILL SHAFT 8 LENGTH(Fn IZ. moa I I "" mw :1M R MNs ce I ,zaw :1M R ..ms ce I aw mMMw MRx, oR f zw W ..R,s ce I ,w: z,mm w ..wa ce I ,za E -. oR I ,mm mT�,Rce .Nmz ce O DO r%3 F (n -1 32+OD --------------------------- Z J F Q SUMMARY OF ROADWAY LIGHTING QUANTITIES AT STA 35x00 TO 38-00 LEGEND gZ— )* PROPOSED STREET LIGHT Illumination Poles to µ m \ Powder Coat Black. (3) 33+00 —1 34+00 __________________________________________ PARK VISTA BOULEVARD (CONCRETE) I DER NL FlBER I ,moe wux wv amo I uR.TCT "''a' I I I I 1 ,zwo R,mcew .� ce I 1°0• ""01iX fABB ce I ,moe nmww n� ce I ,m,z „F.nxw MMz ce I ,m,< s,mww M.m ce I ,mm:T:wlw, .No-x ce O / O M H 35 J 2 Q _ w W W cONoaT co1D�TOR 3 rq. s� LFxBIx HE.( BO nn 1ttELcxlT, # R-18I PRaP w1T l z — T 0 aere'LFlwR orx 0ta TrnAe`,"' tab —z— • 240/HBOV METERED PEDESTAL 110 CONDUT E BGRE •--- CONDUITPOLE o TYPE B GROUND BOX G EXISTING STREET LIGHT Item ern No. Item No. Number Description Spec No. URI Qly 14 2605.3015 2" CONDT PVC SCH 80 2611533 LF 860 52 3441.1.5 N021rsulated Elec Con r 344110 LF 1980 57 3441.1645 FumisIF/I stall Tyq� 33A Ann 34 41 20 EA 6 61 3441 3051 FumislVlrstall LED Lighting Fixture 344120 EA 6 (137 waft ATB2 Cobra Head 62 Rdwy lllum Foundation TY 3, ,6, 3441.3302 and 8 34 41 20 EA 3 63 3441.3352 FumisIF/I stall Rdway Illum TY 18 34 41 20 EA 3 Pole NOTES 1. CONCRETE FOUNDATION FGR STREET LIGHT CENTEREDEWTHIN IMEDIANANS MUST BE 3 AFC ttGOF FURT WORTH PRE GUALFIED BY H71 G CONTRACTOR 3 EFEEEC CUNDUT15.i RE CONSTRUCTONTNCL`%NG 4. CONDUITS SHALL BE SCHEDULE 80 BURIED AT A TOP DEPTH OF 36" FROM FINISHED STREET GRADE IN STALED s MINIMUM FROM AL WATER B ALL RE APPROMEDNBYSCFW LIYSTEMGHTING "AIR(DEPARTMEMUSTNT (Am ucn WRING/CABLES MUST BECOPPER R T DCusT) 7 SUMMARY OF CONDUIT AND CABLES FOR STA35-W TO 38R00 CONDUCTOR aocx ..o.,m r_______ CONDUCT NO *AZ.•' ,.,t�.A rzr NO. SIZELENGTH BORE (B) ,PxTxse3eB �.xp% (III TRENCH (TI PROP E%BT w I„o;; E. R-19 7 180 T 3 `�n-12 � O R-19 Y 14.5 T 3 O SHEET SHEET CONDUIT TOTAL CABLE ) 705 915 REV DESCRIPTION BYFw DATE III (LF ): TOTAL ILA 37+00 W z ORTWORT CITY OF FORT WORTH, TX TRANSPORTATION AD PUBLIC WORKS F Q PARK VISTA BOULEVARD IMPROVEMENTS PARK VISTA BOULEVARD (Ca ETL) POLE QUANTITY 1 ATBO F303 MVOLT RZ �-- - - LUMNAIRETYPE 3K MP NL P7 AO FOUNDATION TYPE RFD322792 TYPE —_--__—__ __—___ GROUND BOXES(fl' B) -n� LUMNAIRE HEADS 2 Dirv`D /^UND/B`G/R TWOORUNO FARK FIBER E2408D51gUETAL - �7 33A CITY QUANTITY 2 ce ,, mR INN ILLUMINATION PARK VISTA BOULEVARD STA 31+50 TO STA 38400 TB Reeia�iao. �eFm�mn?z Te+m Pe aRMmRno� rvo E-1oAe DESIGNED SS DATE PROJECT N0. Sheet DRAWN. SH/LF 80 CHECKED BGE FEB 202a 10732-01 1128 SCHEDULE OF ILLUMINATION - - m«� Wr._ I I 1181R a,t, a"' f / LE{iEND ROADWAYASSEM3LIESFORSTA vaPam- uw oa \ 1�x w I Him rrm .m. uw r 38+00 TO 39+9725 \ I I 1� POLE NO. T-13 - - „am °w""oi�`Ba- I �T - � �z�r �(--� �( PROPOSED STREET LIGHT PARK VISTA 38+57.00 _ o-w .m" "8103 / CL STATION _ _ _ 4o/4aav METERED PEDESTAL OFFSET jjFT &36 _ _ _ — _ _ _ — / -_---- OFFSET$D� LT wL - - / PROPOSED POWER POLE aremx.x awxs xow _ POLE TYPE 18_ corvouir BORE roc —rocs-- _ "o„'• I I _ - p _ _ ___ __ FOUNDATION 3------------------------T---Tom`--5- I ,wx. _-_ -i _ / Fa .oc TYPEI.�'-+E>� ARM TYPE 93A—__T_T—__—___��I� / _�_ _______ carvOUIT TRENCH _z I -z , wMNMRE ATB2-7YP2-137W- cnunoN NW OR APPROVED T-13 q-----------� T,<Na� ovErenEAo --- 0 TYPE YI ..w ELEc1RIc m„ TE B GRourvo Box EQUAL DRILL 24" O O # EXISTING STREET LIGHT SHAFT D W DRILLSHAFT } LENGTH (FT) 8 DD PARK VISTA BOULEVARD n (CONCRETE) 9" Q - _--___ p 39+97 vxivK�i N OD LLl - mow.-awa,sm Z _ __ J - - - - _ _ _ --__-. ISUMAMY OF CONDUIT AND CABLE S FOR STA 3F-OD TO3a9].25 NO COI,IMAf CONDJCTOR Q RUN N0. E. LENGTH BORE(S) --_------- DF) TRENCHIT) tt SUMMARY OF ROADMYLIGHTING DUMITLTIE SAT J O PROP STA 38w00 TO 39-7525 R-19 2- 60 T 3 ~ �au m POLE Ol1ANf8Y 1 _ _ l ..o w \ R-21 2- 30 T 3 ATBB P303 MOLT R2 \ �` BBBL `,,, .,,,., R-21 2- 35 T 3 WMIARE TYPE 3KWNLP7AD \ Q a o.>« � I R-22 2' 45 T 3 NOTES RFD322792 ,+ \ _- I R-23 2• 15 T 3 , CONCRETE FOUNDATION FOR STREET LIGHT FOUNDATIONTVPE TYPE3 l cnunoN �� I R-2d 2- 75 B 3 TRUCTUREs WITRIN MEDIANS MUST DE (iiOURD BDXES{TYHi 5 DE GENOUND �, 1 I W /' REM 2• 21 T 3 CENTERED wITHN DID AN WMJgRE FfiAD 2 I W / RE. 2• 10 T 3 2 Fw ucnnit sys To BE rvsTALLED aY PADI CONTACTOR - / /' :raP ,o. A�CTY OF FORRT W 11H PRE ODALBED EIT TERFO PFOFSTAL 1 Y SNEET CONOUR TOTAL CABLE 3 STRFBMUGINI Hi9CONSTUCTTO llncwo ,Q�IJITIPE 33A // UISO F): 2� TOTAL CONDUITS NlMnI IaJrrtv 2 nMaEreEwD PArex Hoo a.Ma xma, pm I I - / 4 CONDUITS SHALL BE SCHEDULE 80 BURIED AT A TOP DEPTH OF 36• FROM FINISHED BldSTREE I'd I�Sm De- Spec No. Unit Oly 5 STREET LIGHTEFOUNDAROIS SHALL BE I No. Number s MINIMUM FROM ALL WATER ALI MUST BE 14 28053015 2"CONDT PVC SCH ao� 280533 LF 215 n55ET5ED 15 2605. 3116 2" BONET PVC SCH (B1 26 OS 33 LF 15AR'EBGnTRGICPARIMENT Illumination Poles to N021nsulated El-mR cAaaR MUPRODUCT 52 3441 .1605 34 41 10 LF 870 Contlr (gym LIGNG/cnBLEs MUST sT BE COPPER usT) +34411502 Funi.WITSISII Grourxl Box Type B, 344110 LF 5 Powder Coat Black. (1) F'An,S -- 5] 3441 .1645 AUmniah/In stall Type 33A y/ 41 20 EA 2 Fumi6MlnSIS11240-410 V10 Single 80 34411772 P1,A-Tan—IMAMetSed 344120 EA 1 Pedestal A F"DISNlnstall LED Lighting R. SNE,;••••••••••••••••••� 61 34413051 344120 EA 2 ,P.rxExse3ea (137 xatt ATB2 Cobra Head) •W� tlwy Ilium Foundation TY vA,°ss/iEO'2= 62 1441.3102 entl 8 34 41 20 EA 1 3 5 8 3491.3352 Furnish/Install RdwdV ilium TY lB Pole 39413D EA 1 `��� REV DESCRIPTION BYe� DATE ORTWORT CITY OF FORT WORTH, TX TRANSPORTATION & PUBLIC WORKS PARK VISTA BOULEVARD IMPROVEMENTS ILLUMINATION PARK VISTA BOULEVARD STA 38+00 TO END Aad= No F-,O4a DESIGNED SS I DATE PROJECT N0. Sheet DRAWN SH/LF 81 CHECRED BGE FEB 2024 10]32-01 0 128 SIGNAL I I i I E(1ENO LAYOUT J m m z g � PROPOSED SIGNAL HEAD ��E] ���� % I SPEED IMIT 0 I�N I'.�. MAST ARM mvoLE OOOO❑OO SIGNAL AND RED I 10 11 12 8 9 — — MAST ARM SIGN INTERMENT TO BE I I LATER LED AT A r � PEDESTRIAN 9GNAL HEAD INSTALLED OO — DATE � I I I-- P-01 RED POLE AND EQUIPMENT TO BE \11 E R R � T-02 I I I INSTALLED AT A LATER DATE °w—°Nr O - 5 - - - - - - PEDESTRIAN RDBH BD TGN PED" I I _,aracroc—mc—a—.oc- - --- cououlT eoRE PHIS 4 \ I — —mr—me—mc —rac CONDUIT TRENCH --- *FOR FUTURE INSTALL �`� R w i - -R,, ,; - � TrPE B cnanD Box _ __-----_ __—_ -- __ __ __ __ _ PTE CAMERA — Bi No Xem _ -- P PROP ROADSIDE SIGN Rem ND. Number Descdption Spec No Unit ON I _ _ -u vai 14 2605.3015 2"CCNDT PVC SCH 80 260533 LF 75 I - R-e 1 l EASTING POWER SOURCE 15 2605.3016 2"CCNDTPVCSCH80 260533 LF 3151 52 2 n II Signal Poles to Powder 16 2605.3025 3"CONDTPVC SCH 80 260533 LF 60 MNST ) NTURE CONTROL CABINET 17 2605.3033 4"CONDTPVC CH 80 260533 LF 100 I / Coat Black. /�` - 18 2605.3034 9" TIC' H80 260533 LF 315 ARM (1 ^� / I Coat LJ U i� ` / PROP 120/2aov METEREU PEDESTAL 53 3441.1410 F(O fO insula{edB.C. r 344110 LF 580 I 54 3441.1414 N08 Bare Elec Condr 344110 LF 7651 I O _ III / NTURE PAVEMENT MARNING 55 3441.1502 PAIe� Mrs�ll Type 45 Signal a 344110 LF 6 OIi _ O O _ _ _PCP -,— - V — No�iunil'AN LIRcuMINaREs sIIA PP AD FumisMnstaIIG rxl Box Type B, 5 56 3441.1613 344110 EA 2 - INSTALLED WITH 57 3441.1645 FumisFNretaII TY`(ce 33AA- 344120 EA 2 1 1+ RFoai Rz aK MP BILL BE ATaD PaD� 58 3441.1704 TY 5 Signal ROMr�dtlOn 3441 30 EA 2 I I I k`h 1.2. ALL LUMINaREs SHALL BE UMC 59 3441,1771 FumishArsta11120-240 VoX Single 344120 EA 1 I PRoaosco Mnsi ARM, PEDESTRIAN HYBRID Plsmse Metered Pedestal I s AND PEDESTRIAN 61 3441.3051 Furnish/Install LED Lighting Fixture 344120 EA 2 I I I ��P^ NSTaLLEDT AT NNRE OATE2TO BE } P-Dt -E S RI EWIPMENTANDP TO02 BE I'NSTALLEDHPE AiAN A FUTURE - ► /Is _-- /—_... 'I 5 CONDUITS AND ST �+ \\ 4 REO PEDESTAL TO BE 26iG0 GRO ND II - -- -- --II--�tF -- . 28+0( G B TE DRAT ABI ACCOMPANYING INSTALLED AT /I —ES TO BE INSTALLED NET TO BE MSTALLED AT A �rl I 7. CONDUITS SHADEPIH SCHEDULE FROM AND TOP OF t « I ��� _- _-_- -" y o -- w. - FINISHED STREET GRADE 8 CROSS WALK ANO STOP BAR MARKINGS -S I 52' 11 ACROSS PANGOLIN DR FOR FUNRE INSTALL O i i MAST IARM PARK VISTA BOULEVARD--------------- =s'' 2 w 11 (1 1 O.W.) — e pg•R•'° I IIO SPEED LIMIT: 40 MPH2. ' —ra—roc R_y oc —ra, Ap//cII roc Pc ra� _r� -----'---- -cv 6—c6a Nc—ucrucc NWIIcr \ / '^' me rocrac `. REV DESCRIPTON BY DATE Fi Y ��� \\R_2 A � - \ _ \ 4 9 PB5 coNCRET I \ 7- 5 Y OF FORT WORTH X --------------- 1RI RBB B�,� O _---------- ORTWORT 0 �,. ' —°w �— ' CITY WORKS & T Row. _ 6❑ - Row PUBLIC WORKS a + - - - ------ - - - -- - '� p 51 r PARK VISTA BOULEVARD IMPROVEMENTS I I 0 M m Z 0 I IY ~ PHB SIGNAL LAYOUT / O i PANGOLIN DRIVE AT PARK VISTA BOULEVARD - I Z d I w.:;, weti�mm z,a,m (n I TBRe aim a n�F-,o4e PED POLE AND EQUIPMENT TO BE P 02 — 1 P EQUIPMENT TO T 0 SIGNAL AND ED EQ INSTALLED AT A LATER DATE Q^ I BE INSTALLED AT A LATER DATE DESIGNED BGEa I DATE PROJECT NO Sh11t I A. DRAWN. aGE 82 CHECKED B E 1 FFR 2024 10732-01 P 128