HomeMy WebLinkAboutContract 59320-CO3CSC No. 59320-CO3
Fc� RT Wn R'r H City of Fort Worth
- W - Change Order Request
Project Name: FWCC -Grand Avenue Bypass Storm Drain and Sanitary Sewer Improvements City Sec No.: I 59320
Project No.(s):l 103665/103664100969 1 DOE No. I N/A City Proj. No.:, �00969
Project Descrlpllon] Storm drain and sanitary sewer Improvements on N. Commerce, N. Calhoun and N.E.10th Streets.
Contractor S.J. Louis Construction of Texas, Ltd. Change Order 11 3 1 Dale:
City Project Mgr.l Liam Conlon City Inspector: Jeremy Koonce
Phone Number.1 (817) 392-6824 Phone Number (817) 675-1574
1111312024 1
Dept, Storm Water Sewer (FWCC) Water (FWCC) Totals Contract Time
(FWCC) (Calender days)
Original Contract Amount $21,114,746.00 $1.635,338.50 $0.00 $22,750,084.50 400
Extras to Date
Credits to Dale
Pending Change Orders (in M&C Process)
Contract Cost to Dale
$21,114,746.00
$1,635,338.60
$0.00
JAmount of Proposed Change Order
$0.00
$46,400.00
$206,792.00
Revised Contract Amount
$21,114,746.00
$1,681,738,50
$206,792,00
Original Funds Available for Change Orders
$1,055,737.30
$81,767.00
$0.00
Remaining Funds Available for this CO
$1,055,737.30
$81,767.00
$0.00
Additional Funding (if necessary)
CHANGE ORDERS to DATE
(INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRACTAMOUNT (ORIGINAL CONTRACT
COST+ 25%)
JUSTIFICATION (REASONS) FOR CHANGE ORDER
0150
$22,750,064.50 550
$253,192.00
$23,003,276.60 650
$1,137,504.30
$1,137,604.30
1.11%
$28,437,605.63
Change Order No. 3 provides pay items quantities for the following that are necessary on the project:
The relocation of an existing 6-inch water main on Calihoun Street that was found to be In direct conflict with a
project storm drain box culvert, and by other than open cut Installation of a 40 foot segment of a 12-Inch project
sewer main across an AT&T manhole.
It Is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and salisfactlon and represents payment In
full (both time and money) for all costs arising out of, or Incidental to, the above Change Order.
Contractor's company Name Contractor Name C ractor SAhature Date
S,J. Louis Construction of Texas, Ltd, I Adam Lunsford I 1WA6 ,I� I 11/142H
Insp�ctar�J
<reclorlWer Dept)
I Chrif-fooher Ifarder T S
�h`M'16'raAdesIM9h(Vq Af16Vney
Do gh, B,,A(Dec4,20241454CST)
M&C Number 24-1003
Dale
Pro ecoanager IF
�ii 1 r�rnn� fit„
t
a
DAI)a*te
bate
,n.s
Constr llo u rvl PW Dept)
12/04/2024
t 1 / 19 /a4
Date
Assistan y Manlag6r
Date
19/04/2024
---1,
12/05/2024
Council Action (if
William Johnson (D c 5.2024%�14:14 CST(
Required)
M&C Date Approved 1 11/1212024
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
Fo) P,-r Wo PT
City of Fort Worth
"t�`- Change
Order Additions
Project Name FWCC - Grand Avenue Bypass Storm Drain and Sanitary Sewer Improvements
City Sec No.: 1
59320
Project No.(s): 103665/103664/00969
j DOE No.1 N/A
City Proj, No.: I
C0`0969
Project I Storm drain and sanitary sewer improvements
Description
on N. Commerce, N. Calhoun and
N,E,10th Sheets,
Contractor S.J. Louis Construction of Texas, Ltd,
Change Order:31
Dale:
j 11113/2024 1
City
Project Mgr, I Liam Conlon
I, City Inspector
James Ruiz
R
ADDITIONS
IfEIVi
DESCRIFf ION
DEPT
City Unit
'Unit Cost
Total
1
6" Water Pipe
Water (FWCC)
512
LF
$190,0C,
$97,280.00
2
6" Gate Valve
Water (FWCC)
1
EA
$1,700.00
$1,700.00
3
Fire Hydrant
Water(FWCC)
1
EA
$6,000.00
$6,000.00
4
Ductile Iron Fittings wl Restraint
Water (FWCC)
0.8
TN
$10,000.00
$8,000.00
5
1"WalerService
Water(FWCC)
1
EA
$3,000.00
$3,000.00
6
1" Water Service, Meter Reconnection
Water (FWCC)
1
EA
$700.00
$700.00
7
Connect to Existing 4"-12" Water Main
Water (FWCC)
2
EA
$4,000.00
$8,000.00
8
Salvage Fire Hydrant
Water(FWCC)
1
EA
$500.00
$500.00
9
Remove 8" Water Valve
Water (FWCC)
1
EA
$500.00
$500.00
10
Remove Existing Water Line
Water (FWCC)
512
LF
$50.00
$25,600.00
11
Trench Safety
Water(FWCC)
512
LF
$1.00
$512.00
12
' 6" Abandonment Plug
Water FWCC
1
EA
$900.00
$900.00
13
8" Abandonment Plug
Water FWCC
1
EA
$1,100.00
$1,100.00
14
Water Line Lowering (Under Proposed Structures)
Water FWCC
2
EA
$25,000.00
$50,000.00
15
Survey/Construction StakinglAsbuill Survey (6" Water)
Water (FWCC)
1
LS
$1,000.00
$1,000.00
16
Traffic Control
Water FWCC)
1
LS
$1,000.00
$1,000.0C,
17
SWPPP
Water (FWCC)
1
LS
$1,000.00
$1,000.00
37
3305.3004 12" Sewer Carrier Pipe (Materials)
Sewer FWCCI
40
LF
$88.74
$3,549.6C.
38
3305.3004 12" Sewer Carrier Pipe (Installation)
Sewer�FWCC�
40
LF
$532.26
$21,290,4C,
3
3305.1104 24" Casing By Other Than Open Cut
Sewer (FWCC)
40
LF
$1,124.00
$44,960.00
_Storm Water (FWCC)
Sewer (FWCC) $69,800.00
Water (FWCC) $206,792.00
Page 2 of 5 Additions Sub Total $276,592.00
FOP,-F WOR-r H City of Fort Worth
;y- Change Order Deletions
Project Name FWCC - Grand Avenue Bypass Storm Drain and Sanitary Sewer Improvements City Sec No.: 59320
Project No.(s): 103666/103664/00969 1 DOE No. N/A City Pro], No.: C00969
Project Description Storm drain and sanitary sewer Improvements on N. Commerce, N. Calhoun and N.E,10th Streets.
Contractor S.J. Louis Construction of Texas, Ltd. Change Order: a Dale 11/1312024
City Project Mgr. Liam Conlon City Inspector: I James Ruiz
_ DELETIONS
ITEM DESCRIPTION DEPT City Unit Unit Cost Total
1 3331.4208 12" Sewer Pipe (Materials) Sewer (FWCC) 40 LF $30.88 $1,235.20
2 3331.4208 12" Sewer Pipe (Materials) Sewer (FWCC) 40 LF $554.12 $22,164.80
(Storm Water (FWCC)
(Sewer (FWCC) $23,400.00
Water (FWCC)
Page 3 of 5 ;Deletions Sub Total $23,400.00
MIWBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
CO# DATE AMOUNT
Total $0.00
Page 4 of 5
City of Fort Worth, Texas
Mayor and Council Communication
DATE: Tuesday, November 12, 2024 REFERENCE NO,: "M&C 24-1003
LOG NAME: 60SWM FWCC GRAND AVE CONSTRUCTIONC03WATER-SJL
SUBJECT:
(CD 2) Authorize Execution of Change Order No. 3 in the Amount $253,192,00 to a Contract with S.J. Louts
Construction of Texas, LTD, for the Trinity River Vision, Phase 1 Project, Adopt Resolution Expressing
Official Intent to Reimburse Expenditures with Proceeds of Future Debt, and Adopt Appropriation
Ordinance to Effect a Portion of Waler's Contribution to the Fiscal Years 2025-2029 Capital Improvement
Program
RECOMMENDATION:
It Is recommended Ihal Ilia City Council:
1. Authorize execution of Change Order No. 3 In the amount of $263,192.0D to City Secretary No.
59320, a contract with S.J. Louis Construction of Texas, LTD, for the Trinity River Vision, Phase 1
project for sanitary sewer Improvements projects on N. Commerce, N. Calhoun, & N.E. 101h
streets for a revised contract amount of $23,003,276.60;
2. Adopt the attached resolution expressing official Intent to reimburse expenditures with proceeds from
future debt and/or annual payments from the Tarrant Regional Water District for the Fort Worth
Central City Water & Sewer Relocations project; and
3. Adopt the attached appropriation ordinance adjusting appropriations In the Water & Sewer
Commercial Paper Fund by Increasing appropriations In the Trinity River Vision Phase 1 project (City
Project No, C00969) In the amount of $253,192.00, and decreasing appropriations in the Commercial
Paper Fund (City Project No. UCMLPR) by the same amount to effect a portion of Water's
contribution to the Fiscal Years 2025-2029 Capital Improvement Program.
DISCUSSION:
On April 251h, 2023 by Mayor and Council Communication (M&C) 23-0321, the City Council authorized a
construction contract with S,J. Louts Construction of Texas, LTD In the amount of $22,760,084.50 for Fort
Worth Central City Grand Avenue Phase 2 Parl 2 and Fort Worth Central City Grand Avenue Phase 2 Part 3
& Trinity River Vision, Phase 1. The contract was subsequently revised by Change Order No. 1 with a net
total amount of $0.00 administratively authorized on April 6, 2024 that provided for swapping out a
discontinued manufactured slormceplor model that was called for at the time of bid opening with a newer
model and Change Order No, 2 with a net total of $0.00 administratively authorized September 3, 2024 that
provided an additional 150 calendar days on the project for multiple revisions to the USACE package
submittal which delayed the construction start time of the project.
Change Order No. 3 In the amount of $263,192.00 (Water $206,792.00, Sewer $46,400.00) will provide pay
Items quantities for the following that are necessary on the project: The relocation of an existing 6-Inch
water main on Calhoun Street that was found In direct conflict with a project storm drain box culvert, and
other then open cut Installation to Install a 40 fool segment of a 12-Inch project sewer main across an AT&T
Manhole.
This project Is anticipated to be repaid from a series of annual reimbursements from the Tarrant Regional
Water District (TRWO) as part of the Fort Worth Central City Water & Sewer Relocations project, In the
event any bond -eligible costs are not fully reimbursed by TRWD, those costs would be anticipated to be
Included In a future revenue bond Issue for the Water & Sewer Fund. Available cash within the Water and
Sewer portfolio and the City's portfolio along with the appropriation authority authorized under the Callable
Commercial Paper Program (CP) will be used to provide Interim financing for this project until the debt Is
Issued. Once payment Is received from TRWD and/or debt associated with the unrelmbursed portions of
this project Is sold, those funds will be used to reimburse the Water and Sewer portfolio and the City's
portfolio In accordance with the attached reimbursement resolution. Under federal law, debt must be Issued
within approximately three years in order for these expenses to be reimbursable. Adoption of the attached
resolution does not obligate the City to sell bonds but preserves the ability of the City to reimburse itself
from lax -exempt bond proceeds.
It Is the practice of the Water Department to appropriate Its CIP plan throughout the Fiscal Year, Instead of
within the annual budget ordinance, as projects commence, additional funding needs are Identified, and to
comply with bond covenants. The actions In the M&C will appropriate funds in support of the Water's portion
of the City or Fort Worth's Fiscal Years 2025.2029 Capital Improvement Program.
Appropriations for the Trinity River Vision Phase 1 project is depicted below:
Capital Project FY2025 CIP Authority
Fund Name Name Appropriations
56002- J C00969
W l &-Trinil
a er y
sewer River
M&C 60WATER FY2023
�
$0.00 !FY2024 FWCC REIMB
Capital
Vision,
IRecom 113
Projects
Phase
[Fund
1
M&C 60
$0.00 WSSRFWCCS1P10C01-
CIRCLE C
- - ---' Budget � --
Change Budget
(Inc/Dec) Change Budget Change (InclDec) Revised
60WATER (Inc/Doc) 60SWM FWCC GRAND AVE FY2026
FY2023 AND 60WSSRFWCC CONSTRUCTIONCO2WATER- Budget
FW2024 FWCC CIRCLE
C SJL
REIMB CIRCLE C
AND
$8,466,861.96 $0.00
$0.00 ($22,629.00,
I-
$8,466,851,96
($22,629.00;
�C009691
I
56005- - Trinity,
Water/Sewer River
M&C 60WATER FY2023 AND
Vision,
$0.00
FY2024 FWCC REIMB
($880,824.03 )
$0,00
$0.00 ($080,824.03;
Bond 2018
Phase
Recom 115
1
�
1
M&C 60WATER FY2023 AND
$0.00
FY2 224 FWCC REIMB
($3,865,117.59)
$0.00
$0.00 ($3,865,117.69)
R_ecom_#5
M&C 60 - -
- --
$0.00
WSSRFWCCS1P10C01-
$0.00
($245,930.86)
$0.00 ($245,930.86)
CIRCLE C
ater - WTrinity
Water & River
M&C 60WATER FY2023 AND
Sewer Bond (Vision,
$0.00
FY2024 FWCC REIMB
($2,249,571.96)
$0.00
$0.00 $2,249,571.96;
Phi
ase
2-
Recom 116
-- - 1
i
M&C 60
$0.00]WSSRFWCCS1P10001-
$0.00,($1,083,136.00)
$0.00
($1,063,136,00;
CIRCLE C
56019 -
Rev
M&C 60
Bond
$0.00 WSSRFWCCS1P10C01-
$0.00
($443,312.00)
$0.00
($443,312.00)
Series 2021
'CIRCLE C
156020-W&S
I
M&C 60
- -
Rev Bonds
$0.00 WSSRFWCCS1P10C01-
$0.00
($407,022.00)
$0.00
($407,022.00)
Series 2022
CIRCLE C
C00969
56023- -Trinity
Commercial River
Paper Vision,
(Phase
1
F-1
M&C 60WATER FY2023 AND
$0.00 FY2024 FWCC REIMB
Recom 114
M&C 60
$0.00 WSSRFWCCS1P10C01-
CIRCLE C
60SWM FWCC GRAND AVE
$0.00 CONSTRUCTIONCO2WATER-
SJL
C00969
59601 -
-Trinity
Rlver
M&C 60WATER FY2023 AND
Water
$0.00
Vision,
FY2024 FWCC REIMB
Capital
Phase
Recom #7
1 _
00969
-
Sewer
Sewer
-Trinity
River
M&C 60WATER FY2023 AND
Capital
Vision, $0.00
FY2024 FWCC REIMB
Legacy
Phase
Recom 118
($777,632.61)i $0.00
$0.00 $2,698.901.65
$0.00 $0.00
is
($7,750.00)! $0.0G.
I
($37,274.00)I $0.00
M&C 60WATER FY2023 AND ,
$0.00 FY2024 FWCC REIMB ($571,599.21) $0.00
Recom #8
M&C 60
$0.00 WSSRFWCCS1P10C01- $0.00 ($31.608.79)
CIRCLE C
L I
-
$77,002.66!- $465,263.00
Funding for the Trinity
River Vision, Phase 1 project Is depicted below;
60WATER
60WSSRFWCC0&WM
6FWCC
j
Current FY2023
S1P10001-
GRANDAVE
Total Funding
Funding AND FY2024
CIRCLEC
CONSTRUCTION
_
FWCC REIMB
CO2WATER-SJL
I
56002 W&S
I !
Capital
$2,457,887.00 $8,466,851.96
$(22,629.00)
$0.00
+$10,902,109.96
Projects
56005
Water/Sewer
$6,855,400.00 $(4,745,941.62)
$(245,930.86)I
$0.00I
$1,863,627.52
Bond 2016
56007 Water
!
I
& Sewer
$6.167,422.45
$(2,249,571.96)
$(1,083,136.00)
$0.00
$2,834,714.49
Bond 2015A
$0.00 ($777,632.61,,
$0.001 $2,698,901.66
$263,192.00 $253,192.00
$0.001 ($7,750.00)
$0,001 ($37,274.00;
$0.001 ($571,599.21)
$0.001 ($31,608.79)
$253,192.001 $795,537.69
'56019 W&S
Rev Bonds $443,312.00 $0.00 $(443,312.00) $0.00 $0.00
Series 2021
56020 W&S -
Rev Bonds $407,022.00 $0.00, $(407,022.00) $0.00 $0.00
Series 2022
56023 W&S- — - - r --- ---- ---
Commercial $1,618,400.00 $(777,632,61) $2,698,901.65 $253,192.00 $3,692,861.04I
Paper
Funded $5,852,657.94 $0.00 $0.00 $0.00 $5,852,657.94
Projects _
59601 Water I -
Capital $14,404,708.40 $(7,760.00)i $0.00 $0.00 $14,396,95B,40�
59607 —
Sewer t
—$7.769,673.12 _$(608,673.21)�$(31,608.79
)7$253,1]9200- -
$7,128,191.12
Legacy
L$45676,402,91 $77,002.56 $465,263.00
$46,672,020.471
A portion of the water line In the amount of $206,792.00 of this Change Order Is considered Trinily River
Visions (TRV)-relocated work. The sanitary sewer $46.400,00 amount of this Change Order is considered
(TRV)-relocated work, are eligible for funding from Tax Increment Reinvestment Zone No. 9 (TRVA TIF)
pursuant to the TRVA Project Plan. Having met Its $26.6 million commllmenl to the TRV Project, the City will
be reimbursed the water line amount of $206,792.00 and the sanitary sewer amount of $46,400.00 by
Tarrant Regional Water District (TRWD) on an annual basis, in accordance with provisions of the executed
Interlocal Agreement between the City and the TRWD (City Secretary Contract No. 43425 as amended).
The TRV Program Manager In the FW Lab Department will be responsible for collecting the full
reimbursement from TRWD at the end of each Fiscal Year.
Business Equity - S,J, Louis Construction of Texas, LTD agrees to maintain Its Initial MIWBE commitment of
14 percent that It made on the original contract and extend and maintain that same MMBE commitment of
14 percent to all prior change orders up to and Inclusive of this Change Order No. 3. Therefore S.J. Louis
Construction of Texas, LTD remains In compliance with the City's MIWBE Ordinance and attests to Its
commitment by signature on the Acceptance of Previous M/WBE Commitment form executed by an
authorized representative of Its company.
This project is located In COUNCIL DISTRICT 2.
FISCAL INFORMATION I CERTIFICATION:
The Director of Finance certifies that funds are currently available In the Commercial Paper project within
the W&S Commercial Paper Fund and upon approval of the above recommendations and adoption of the
attached appropriation ordinance, funds will be available In [lie W&S Commercial Paper Fund for the Trinity
River Vision, Phase 1, project to support the approval of the above recommendations and execution of the
change order. Prior to any expenditure being Incurred, the Water Department has the responsibility to
validate the availability of funds,
FUND IDENTIFIERS (FlDs);
TO
IFund l Department (Account) Project (Program' ctivltyl Budget I Reference It I mount
ID I ID II Year (Charlfleld 2)
FROM
Fund Department ccount Project ctivity ProgramBudget Reference 1f mount`
ID I ID I P I Year I (Charlfield 2)
CERTIFICATIONS:
Submitted for City -Ma nager's Office bys William Johnson (6006)
Or g atl g Denartment Heart: Chris Harder (6020)
Additional Information Contact: Llam Conlon (6824)
ATTPCHMENTS - - -- - -- - - -- .
1. FOSWJyi FWCC GRAND AVE CONSTRUCTIONC03WATER-SJL FID f WCF 10.06.24).XLSX (CFW
nlarno
2. FOrrS�W�M FWCC GRAND AVE CONSTRUCTIONC03WATER-SJL funds nvailahllity pdf (CFW Internal)
3. �OWMF CC GRAND AVE CONSTRUCTIONCO2WATER-SJL.pr)_f (Public)
4. Acceptance of PrevlousMWBE Commilimenl Form FWCC CO 3 SJL Signed RL•pd (CFW Inlornal)
5. Commerr,Ial Parjer as of 0.08 2024.x1sx (CFW Intornaq
6. Form 1295 Car dicate 1072024.i''jdf (CFW Inlernap
7, ORD.APP 60SM FWCC GR/.ND AVE CONSTRUCTIONC03WATER-SJL 56023_AO2.6(r3),
(I) ecx (Public)
8, PBS CPN CO09f9 pol (CFW Internal)
9. F�as�60SWM Pl(t�CE GRAND AVE CONSTRUCTIONC03WATER-SJL.docx (Public)
10. SAM•gov searrh S,J. Louis Cons Iruction .pdf (CFW Internal)
605WM FWCC GRAND AVE CONSTRUCTIONCO3WATER-SJL FID Table
1 56023 0600430 5740010 C00969 C01780 •9999
1 156023 0700430 5740010 C00969 C01780 9999
I I I
I I I I I I
I I I I I I I
I I I I
I I I I I I I I
�206,792.00 jAward of contract
$46,400.00 jAward of contract
I
I
I
I
I
Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
Signature
Liam Conlon
Name of Employee
Project Manager
Title
ATTEST:
Jannette Goodall
City Secretary