HomeMy WebLinkAboutContract 60542-CO2CSC No. 60542-CO2 FORT W"KTH City of Fort Worth A Change Order Request Project Name: 1 Southside IV Flow Transfer Station at Summer Creek Drive I City Sec No.: 1 60542 1 Project No.(s): 56003 0600430 5740010103116 001680 1 DOE No. I N/A I City Proj. No.: l 103116-2 1 Project Description: I New flow transfer station and waterline and valve connections to support service to the new southside IV pressure plane. Contractor: 1 Circle H Contractors, LP Change Order # 2 I Date: 12/24/2024 City Project Mgr" 1 Suzanne Abbe City Inspector: Ronnie Cardenas Phone Number:1 817-392-8209 Phone Number: 682-309-3761 Dept. Water I Totals Contract Time Calender days) Original Contract Amount $1,341,236.00 $1,341,236.00 80 Extras to Date $0.00 090 Credits to Date Pending Change Orders (in M&C Process) Contract Cost to Date $1,341,236.00 $1,341,236.00 Amount of Proposed Chanqe Order $33,638.00 $33,638.00 120 Revised Contract Amount $1,374,874.00 $1,374,874.00 390 Original Funds Available for Change Orders $67,062.00 $67,062.00 Remaining Funds Available for this CO $67,062.00 $67,062.00 Additional Funding (if necessary) CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT 2.51 % MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 2551o) $1,676,545.00 JUSTIFICATION (REASONS) FOR CHANGE ORDER - — Change Order No. 2 provides for: • Addition of reflective bollard covers to make bollards visible from road. • Top soil removal and addition of compacted flexbase at flow transfer station to facilitate access during wet weather,. • Addition of a flexbase access road to provide all weather access to the site. Staff recommends an addition of 120 calendar days to cover coordination needed to start up the flow transfer station. Contractor's Company Name I Contractor Name Wractor Signature Date Circle H Contractors, LP Brad Owens C /� lns D e �ro ect Manage I Date 1 /9/2025 Director (Vllater Dept) pate Con ;ruction Su rvlsor Water Dept) Date n es' a� ev T.S. 01/13/2025 1-8-25 Se. or sistant City Attorney Date an i I er Date 01/13/2025 _ 01 /14/202 Council Action (if Required) OFFICIAL RECORD M&C Number N/A M&C Date Approved N/A I CITY SECRETARY FT. WORTH, TX FORT W"P,TH City of Fort Worth —�~ ! Change Order Additions Project Name I Southside IV Flow Transfer Station at Summer Creek Drive City Sec No.: 1 60542 Project No.(s): 56003 0600430 5740010103116 001680 DOE No.1 N/A City Proj. No.: 1 103116-2 Project I New flow transfer station and water line and valve connections to support service to the new southside IV pressure Description plane. Contractor Circle H Contractors, LP Change Order: 2 Date:1 12/24/2024 City Project Mgr. I Suzanne Abbe City Inspector I Ronnie Cardenas ADDITIONS I I tM Uhb(;KIF I IUN 41 Bollards 42 7-Inch Flexbase Access Road 43 Top Soil Removal and 4-Inch Flexbase at Flow Transfer Station DEPT Qty Unit Unit Cost Total Water 18.00 EA $190.00 $3,420.00 Water 1,050.00 SY $40.00 $42,000.00 Water 1.00 LS $34,200.00 $34,200.00 J I � � Water $79,620.00 Page 1 of 1 Additions Sub Total $79,620.00 F0iR-r WORTH City of Fort Worth —� & �— Change Order Deletions Project Name ! Southside IV Flow Transfer Station at Summer Creek Drive City Sec No.: ! 60542 Project No.(s): ! 56003 0600430 5740010103116 001680 I DOE No. I N/A City Proj. No.: 103116-2 Project Description I New flow transfer station and water line and valve connections to support service to the new southside IV pressure plane. Contractor I Circle H Contractors, LP Change Order: 0 Date I 12/24/2024 City Project Mgr. j Suzanne Abbe City Inspector: I Ronnie Cardenas ! ITEM DESCRIPTION 39 Construction Allowance DELETIONS DEPT Qty Unit Unit Cost Total Water 0.92 EA $50,000.00 $45,982.00 ! ! i Water 1$45,982.00 Deletions Sub Total I$45,982.00 Page 1 of 1 MWWBE Breakdown for this Change Order MWBE Sub I Type of Service I Amount for this CO CrGE Previous Change Orders DATE Total Total AMOUNT $0.00 Page 1 of 1 1/2/2024 CPN 103116-2 Southside IV Flow Transfer Station at Summer Creek Drive Chanee Order 2 Notes Change Order No. 2 provides for: • Addition of reflective bollard covers to make bollards visible from road. The bollards were specified as galvanized steel. During inspection, plant operations noted the bollards needed to be safety yellow with reflective tape. This change orders provides for plastic bollards covers with reflective coating. The proposed price covers material, delivery, and installation. The installed cost is reasonable relative to published costs. • Top soil removal and compacted flexbase at the flow transfer station to facilitate access during wet weather. The original contract included gravel but the gravel surface did not hold up to work performed at the site during wet weather. Compacted flexbase is a more suitable material for all weather access. Most of the proposed cost is associated with labor and soil disposal, and not materials. The proposed lump sum price is comparable to the bid price for flexbase at the NSIV flow transfer station. • Addition of a flexbase access road to provide access to the site during wet weather. The contract did not include all weather access to the station. This change order provides for approximately 600 feet of a 15-foot wide compacted flexbase road to the site from the Summer Creek Drive dead end. Access from the Fogata Lane cul de sac was not considered due to the risk of disrupting drainage around the cul de sac. The proposed price of $40/SY for 7-inch flex base (accounting for an additional average depth of 1 inch due to the crown) is in line with the low end of recent bid process for 6-inch flex base of $35 to $58/SY. Staff recommends an addition of 120 calendar days to cover internal coordination needed to start up the flow transfer station. Contract Compliance Manager By signing I acknowledge that I am the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements. Signature Suzanne Abbe Name of Employee Senior Engineer, Capital Project Delivery Title dgU40Q� p o� FORT�a�a ATTEST: c �° oP° o *_° (� � aaa TEXA`�ob ��URRd44 Jannette Goodall City Secretary OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX