To the Mayor and Members of the City Council October 20, 1992
Subject: 1993 CAPITAL IMPROVEMENT PROGRAM
On May 19, 1992, the City Council directed staff to proceed with
the planning for a three year Capital Improvement Program for
streets, storm drains and related projects, only. During June and
July a total of 38 Capital Improvement Program meetings were held
throughout the City. About 1500 citizens attended those meetings.
Additionally, several citizen groups also held their own meetings
to discuss the Capital Improvement Program.
During those meetings, citizens were asked to submit suggested
street and storm drainage projects for consideration. As a result,
staff received 413 suggested projects. Staff has investigated each
of those suggestions. Attached to this Informal Report is ( 1) the
1993 Capital Improvement Program Staff Recommendation, (2) a
listing of all suggested street projects and (3) a listing of all
suggested storm drainage projects. The information that was
determined for each is included in the listings. The street project
listings are sorted by City Council District, Recommended Capital
Improvement Program Projects, Recommended Maintenance or Street
Division Projects and Recently Suggested Projects - Not In
Recommended Project Listing. The Drainage Projects are similarly
000, listed.
All suggested street projects were first investigated by staff
engineers to determine ( 1) correct limits, (2) likelihood of
assessments, (3) availability of CDBG funds to offset assessments,
(4) current condition, (5) length, (6) width, (7) cost and (8)
expressed citizen support. The Director of Transportation and
Public Works then personally visited each project. Using all
available information, the Director of Transportation and Public
Works and his staff sorted the suggested projects into projects to
be recommended for the 1993 program and the remainder to be
deferred. The prioritization of projects was based on street
condition, benefits to the neighborhood, expressed citizen suppor't
and cost, generally in that order.
In some instances, staff determined that the suggested project was
on a section of street that is maintainable or where no work is
currently required. Those sections are noted on the attached
listing. In those instances where maintenance is appropriate,
staff will schedule maintenance during the next couple of years as
needed.
Each of the suggested storm drainage projects were also
investigated by staff. Each investigation included ( 1) an analysis
of the problem, (2) a simplified determination of the best and most
economical method of solving the problem, (3) benefits to be gained
from doing the project, (4) amount of expressed citizen support and
(5) the preparation of a cost estimate. Staff then prioritized
ISSUED BY THE CITY MANAGER FORT WORTH,TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 7654
October 20, 1992
To the Mayor and Members of the City Council Page 2 of 2
rrrri Subject: 1993 CAPITAL IMPROVEMENT PROGRAM
projects based on severity of problem, benefits to be gained, cost
and perceived citizen support.
STAFF RECOMMENDATIONS
The results of the meetings and staff analysis are contained in the
attached pages. It should be noted that the suggested street
projects are listed by the currently adopted City Council Districts
and staff is not recommendinT an equal distribution of funds by
City Council District. Instead, smaller programs are recommended
in City Council Districts 3 and 6 to reflect the better overall
street conditions in those two districts. Greater emphasis will be
placed on asphalt overlay projects in those areas to maintain and
enhance street quality.
Although staff believes that every recommended project needs to be
done, there are certainly many other projects worthy of
consideration. Some of those other projects are included on the
attached sheets. Should the City Council wish to consider projects
0011 not listed, staff will be most happy to gather the information
necessary for the City Council to make a decision.
The staff sincerely hopes that the meetings that were held, the
investigations that were conducted and the recommendations
contained in this I.R. have been consistent with the process, plan
and schedule expressed to the citizens when we began this process.
Should the City Council have any questions or wish any additional
information, it will be furnished upon request.
C
Bob Terrell
City Manager
Attachments
ISSUED BY THE CITY MANAGER FORT WORTH,TEXAS
1993 CAPITAL IMPROVEMENT PROGRAM
STAFF RECOMMENDATIONS
1. STREET PROJECTS $34,000,000
a. Council District 2 $4,688,000
b. Council District 3 $3,422,000
c. Council District 4 $4,599,000
d. Council District 5 $4,711,000
e. Council District 6 $2,640,000
f. Council District 7 $4,624,000
g. Council District 8 $4,677,000
h. Council District 9 $4,639,000
2. STORM DRAINAGE $8,250,000
3. MISCELLANEOUS R.O.W. & OTHER IMPROVEMENTS $2,000,000
a. Intersection Revisions $700,000
b. Curb & Gutter Replacement $350,000
c. Concrete Valley Gutters $600,000
d. Railroad Crossings $250,000
e. Protective R.O.W. Purchase $100,000
4. TexDOT MATCHING FUNDS $8,750,000
a. Alta Mesa: Will Rogers to Campus $220,000
b. Rosedale: Forest Park to 1-35W $6,000,000
c. Montgomery: Mattison to W. 7th $30,000
d. ISTEA Matching Funds $500,000
5. STREET LIGHTS & TRAFFIC SIGNALS $3,000,000
a. Street Lighting $1,000,000
b. New & Replacement Traffic Signals $1,500,000
c. Computer Signal System Expansion $500,000
6. DRIVES, PARKING & DRAINAGE IN PARKS $1,000,000
7. PROJECTS IN NEWLY DEVELOPING AREAS $3,000,000
TOTAL $60,000,000
001 NOTE: Engineering design,surveying, inspection, testing and admin*istration is included in projects as
required.