Loading...
HomeMy WebLinkAboutIR 7645 INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 7645 11T�� September 29, 1992 opw 0To the Mayor and Members of the City Council Subject: SYCAMORE CREEK GOLF COURSE REOPENING DELAY In 1986, $15 million dollars in General Obligation Bonds were approved for the redevelopment of the Sycamore Creek Golf Course. On August 28, 1990 the City Council voted to approve a contract with Poe Engineers, Inc. for site analysis, golf course routing plans and construction documents. This contract authorized the development of plans and specifications and provided for construction observation for the abandonment of the existing nine holes and construction of a new nine holes with double sets of tee boxes (thus allowing the golfer to play the layout twice, from slightly different perspectives). Prior to letting the contract, three public meetings were held to gain citizen input as to the type of operation the citizens felt was needed for the Sycamore Creek Golf Course. The regulation length nine hole golf course was chosen over two other options including a training center or an eighteen hole, par three course. Several additional tracts of land were acquired from individual landowner;, TU Electric Company and the Tarrant County Water Control and Improvement District No. 1. In total,seven additional parcels of land were acquired after which final construction drawings were completed. Public bidding on the project was advertised on January 9 and 16,1992 and bids were opened on February 6, 1992. M&C C-13256, awarded a contract to Randall and Blake Inc. for a low bid of$1,286,040 with a contract time period of 210 calendar days (later extended to 228 days with change orders). The contract time began on April 3, 1992. From April through June, demolition of the existing site and construction of the major earthwork was undertaken by the contractor. As the major earthwork neared completion, the irrigation system and installation of cart trails began in June. By late June, the City began to express concerns to the contractor about meeting the planting date in August. At that time, the contractor provided assurances that they would complete the grassing within the specified time period of August 15, 1992. On July 20, 1992 the City formally sent correspondence expressing its concerns about the planting of the grass as per specifications. After consulting with Dr. Milton Engelke of the Texas A&M Agricultural Extension Service, on July 28, 1992 the contractor was granted a two week extension to complete the grassing with a final deadline of September 4, 1992. That deadline passed without the contractor grassing the golf course. Park and Recreation and Legal Department staff met with the contractor, who proposed to provide a temporary grass cover of winter ryegrass to hold the soil and to return next April to complete the project. This proposal was reviewed by staff and the engineering consultant and a response was sent on September 10,1992 to the contractor with the City's conditions to accept the contractor's proposal. These include planting winter ryegrass across the entire golf course,sodding certain areas around sand traps, grass bunkers,greens and slopes, and fertilization in both the fall and the spring. The contract time will be stopped at such time when all construction/installation aspects of the plans and specifications are completed and the stand of temporary grass is established and accepted. Park and Recreation staff will assume beneficial occupancy throughout the winter to preform on-site improvements and maintenance. Once spring grass sprigging begins, contract time will resume until such time that the contractor has completed all sprigging operations and is in total compliance with contract documents. ISSUED BY THE CITY MANAGER FORT WORTH,TEXAS INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 7645 September 29, 1992 To the Mayor and Members of the City Council Page 2 of 2 Subject: SYCAMORE CREEK GOLF COURSE REOPENING DELAY Prior to establishing the alternative work plan,Park and Recreation Department and Law Department staff had concluded that the Contractor was in default with regards to the grassing schedule and that the City had two options: 1)To default the contractor and make demand upon the bonding company to perform in accordance with the performance bond, or 2)work with the contractor to complete the project. It was considered that option #1 would require an inordinate amount of time to resolve, and that this option would postpone the completion of the project even longer than the current delay. Option#2 was considered the most viable solution to complete the project within next year's growing season. As of September 23, 1992, the Contractor has used 174 days out of the 228 days of the contract time, including change orders. A response has been received from the Contractor and they have agreed to the City's conditions as outlined above in working toward completion of the course. Once the contract is complete, Park and Recreation Department staff and the City Attorney will review and determine the options for assessment of liquidated damages and lost revenue due the City, if any. If the contractor exceeds the specified contract time the City will pursue any and all liquidated damages of $420 per day, for construction beyond the amount of days allowed per the contract. In addition, the City will pursue a negotiated amount of projected lost revenue for the facility for days the golf course would have been open had the Contractor met the specified grassing deadline. Due to the required grow-in period to establish a viable grass cover,the initially projected reopening date of April or May, 1993 will be delayed. At this time, the projected reopening of Sycamore Creek Golf Cours i estimated for August or September of 1993. City b �Mana r BT-vr ISSUED BY THE CITY MANAGER FORT WORTH,TEXAS