HomeMy WebLinkAboutIR 7785 INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 7785
To the Mayor and Members of the City Council December 21 , 1993
Subject:
AWARD OF SLUDGE DEWATERING AND LAND
APPLICATION CONTRACT
Sludge or biosolids produced at the Village Creek Wastewater Treatment
Plant were originally disposed in lagoons at the plant site . In 1969
sludge drying beds were constructed to dewater the sludge and the City
began a cooperative program with the Texas Department of Highways and
Transportation to utilize highway rights of way for disposal . In the late
1970 ' s and early 1980 ' s , citizen complaints concerning odors emanating
from the plant and sludge drying beds and other considerations caused the
City to plan a sludge only landfill and an onsite mechanical sludge
dewatering facility at that site . Construction of the sludge-only
landfill was completed in 1989 .
Ever changing economic conditions , environmental regulations , as well as
unprecedented rainfall prompted a review of the sludge handling plan in
1991 which led to a short term contract for the privatized operation of
dewatering facilities and benefical use of the biosolids on farm and ranch
lands with Oscar Renda Construction Contracting, Inc . (ORC) Inasmuch as
no similar arrangement of comparable size existed in Texas , this contract
approach was somewhat innovative . Factors such as land permitting delays ,
community acceptance , landowner interest , etc . were not fully known to the
City. A "privatized" contract approach was selected .
Success of the program led to City Council approval of a contract
extension in June , 1992 for the continued operation of the dewatering
facilities and beneficial use of biosolids on agricultural land. This
contract was subsequently extended in June , 1993 for three months to
continue the operation until bids could be received and another contract
awarded.
While the privatization contract for biosolids handling had been highly
successful , the City staff believed that a reintroduction of competition
would lower the prices being paid. The original 1991 contract with ORC
included a bid price of $403/ton for non-pathogen reduced sludge .
Subsequent change order extensions lowered the unit price for similar
sludge to $210/ton. In total , more than $17 million has been paid to ORC
under the initial contract and extensions .
In August , 1993 , Alan Plummer and Associates completed contract documents
for a five-year dewatering and disposal contract similar to the original
contract . The contract was similar except that the dewatering facilities
would be located at the sludge-only landfill , the contractor would be
required to process 100% of the biosolids , not 50% of the production, and
that the constructed facilities would be transferred to City ownership at
the end of the contract term (5 years minimum to 10 years maximum) .
Concurrently , contract documents were prepared for a "bridging" or interim
arrangement to permit continued sludge processing upon expiration of the
original contract about October 1 , 1993 and before the long term contract
facilities could be constructed and placed into operation . -
I.— ISSUED BY THE CITY MANAGER FORT WORTH,TEXAS
INFORMAL REPORT TO CRY COUNCIL MEMBERS No. 7785
T,E—% December 21 ,. 1993
To the Mayor and Members of the City Council Page 2 of 6
XIXA Subject: AWARD OF SLUDGE DEWATERING AND LAND
TM APPLICATION CONTRACT
During the development of the concept and details of the long-term sludge
contract , several meetings were conducted with prospective interested
bidders to identify opportunities and to solicit opinions . A
prequalif Ication process for bidders was required to inform the staff and
Engineer of prior experience on similar projects as well as financial
capability. A panel of national experts was brought in to review the
contract documents , specifications and prequalification requirements .
On September 30 , 1993 bids were received concurrently on both the interim
(nine month) contract as well as the long-term (five year) contract . The
low responsive bidder on the interim project was Oscar Renda Contracting
with a unit price of $160/ton of processed sludge . This contract was
awarded by the City Council on October 12 , 1993 (M&C C-14042) .
Since bids were received in late September , the staff has been working
with the Texas Natural Resource Conservation Commission to resolve any
regulatory permit or plan review issues which could complicate the long-
term contract arrangement . In addition, the project Engineer and City
staff have been carefully evaluating references for the apparent low
responsible bidder , the Professional Services Group, Inc . (PSG) of
Houston, Texas . On December 8 , 1993 the Commission granted the City a
permit amendment for the sludge processing operation despite a protest
filed by the City of Arlington. Also on December 2 , 1993 the Commission
staff approved the contract documents , and specifications and plans for
the construction of dewatering facilities .
ff Shown below is a tabulation of the bids received on September 30 , 1993 for
the long-term project :
DESCRIPTION BIDDER
Professional
Service Oscar BioGro BFI
Group Renda
Total Base Bid $ 26 .42 $ 30 .44 $ 33 .49 $ 59 . 10
— (million dollars)
Unit Price $129 . 95 $152 .00 $168 . 70 $309 .00
$/Ton
ISSUED BY THE CITY MANAGER FORT WORTH,TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 7785
December 21 , 1993
To the Mayor and Members of the City Council Page 3 of 6
Subject: AWARD OF SLUDGE DEWATERING AND LAND
APPLICATION CONTRACT
Due to the complexity of the project (build, own operate , transfer) as
well as economic attractiveness of the venture , some of the bidders have
raised questions about the process , clarity of the bid documents , and
qualifications of other bidders . The staff has diligently investigated
the allegations to ensure that the competitive process was fair and open,
the documents were clear as to intent , and that there are no other factors
which should disqualify a recommended bidder.
Some of the concerns and allegations are itemized below:
Issue The contract documents were vague and unclear and
therefore it is impossible to fairly compare bids .
Response Alan Plummer and Associates , its subconsultants , and
the staff have reviewed the bidding documents and find
no basis to reject the bids due to vagueness . Some of
the reasoning for this conclusion includes the fact
that all bidders had opportunity to provide input into
the basis upon which the documents were developed .
Some bidders requested that the document provide
flexibility . The Engineer and City staff made a
deliberate effort to avoid unnecessary and restrictive
contract requirements that could result in higher
costs .In addition some of the allegedly "vague"
requirements were also found in the 1991 initial
project and 1993 interim project documents and no
concerns were raised by bidders . The staff also
believes that the prices bid are reasonably close for
the three lowest bidders . The attractive prices , as
reflected by comments of officials in other cities , in
the opinion of staff reflects clarity of the scope of
work.
Issue The prequalification submittal did not require
submitters to list any uncompleted work or pending
lawsuits .
Response The prequal if i cation document was intended to provide
information to the City to evaluate comparable
experience and fianancial strength. Reference checks
have been utilized to evaluate contract performance on
other contracts . Direct contact with other cities was
considered to be the most direct means to verify
contract compliance concerns .
ISSUED BY THE CITY MANAGER FORT WORTH,TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 7785
December 21 , 1993
To the Mayor and Members of the City Council Page 4 of 6
Subject: AWARD OF SLUDGE DEWATERING AND LAND
APPLICATION CONTRACT
Issue The City should pursue the alternative disposal option
for Class A sludge because of changing regulatory
climate .
Response Only one bidder submitted a price for the Class A
alternative . BioGro bid $53 , 714, 750 .00 to process the
sludge to a higher level of treatment . The Class A
alternative was included in the bidding documents
because the staff believed that the incrementally
higher treatment costs may be offset by lower costs
for regulatory monitoring and more accessible disposal
sites . Some Council members likewise expressed an
interest in evaluating this option . Inasmuch as the
base bid item for beneficial use of sludge is being
actively promoted by the EPA as an environmentally
attractive option to landfilling and since it has been
so successful to date , the higher prices do not appear
to warrant pursuit of the Class A alternative .
Issue It is alleged that one bidder , falsified its
prequalification submittal by failing to report a
South African Business connection by its parent
company.
Response The bidder in question , PSG, is a wholly-owned
subsidiary of Anjou International, Inc . , an American
company. Anjou is a wholly-owned subsidiary of
Compagnie General de Eaux (CGE) , a publicly traded
French company. CGE is a large company with 2 ,200
independent subsidiaries throughout the world.
This allegation was thoroughly investigated by the New
Orleans Sewerage and Water Board ' s independent counsel
in 1991 who concluded that the alleged relationship
with PSG and a joint venture was too tenuous to be in
violation of their anti-apartheid statute .
PSG further has certified that the parent company has
no known South African connections at this time . The
City Council on December 14, 1993 lifted the City's
South African policy.
ISSUED BY THE CITY MANAGER FORT WORTH,TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 7785
M-%do— December 21 , 1993
To the Mayor and Members of the City Council Page 5 of 6
0
NX Subject: AWARD OF SLUDGE DEWATERING AND LAND
Im APPLICATION CONTRACT
Issue The issuance of Addendum 412 and Addendum #3 to the bid
documents required the bidders to assume additional
risks due to possible changes in permits and
regulations prior to the award of the contract .
Response The permitting process with the State took longer than
anticipated. The two referenced addendums did indeed
require the bidders to evaluate the risk of regulatory
changes during the time before contract award . In the
final amended permit approved by the State , however ,
no additional requirements were placed on the bidders.
The City staff working with Alan Plummer and Associates has diligently
pursued the competitive bidding of biosolids dewatering and land
application as outlined in the March 1993 briefing to the City Council .
The objective of this project was to implement a long term contractural
relationship with a private contractor and to lower the cost of the sludge
operations . The use of the competitive bidding process has resulted in a
significant opportunity to achieve cost reductions . As you will recall ,
an anticipated disadvantage of this approach was bidding disputes and
protests and, accordingly, the City Council agreed to prohibit
communication involvement between bidders, and the Council prior to the
award of a contract .
The bid documents anticipated that 90 days should be allowed by bidders
for the City to make a decision . The 90 day period that bidders agreed to
honor bids expires on December 28 , 1993. Bidders have been requested in
writing to extend until January 31 , 1994 the bids submitted on this
project .
The City Council has several options to proceed on this project including:
1 . Award the contract to the low bidder, Professional
Services Group (PSG)
2 . Reject all bids and negotiate with one or all bidders .
3 . Accept the Alternate Class A bid of BioGro .
4 . Reject all bids and rebid the project .
OOW
ISSUED BY THE CITY MANAGER FORT WORTH,TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 77AS
December 21 , 1993
,,,,r;d& > To the Mayor and Members of the City Council Page 6 of 6
xa Subject; AWARD OF SLUDGE DEWATERING AND LAND
yen APPLICATION CONTRACT
The City staff requested that the Engineer review the bid documents and
bid protests and recommend award of contract . APAI recommended award of
contract to PSG, the low bidder . The staff anticipates a formal
recommendation for action by the City Council on the January 4 , 1994
agenda based on further review of the consultants recommendation and the
other potential options which may be in the best interest of the City.
There is a significant cost savings associated with a long-term contracted
arrangement and Qn toward this objective should be taken as soon as
possi0 e.
1
Bob Terrell
City Manager
OPOI
ISSUED BY THE CITY MANAGER FORT WORTH,TEXAS