pF wgrw To the Mayor and Members at the City Council April 18, 1995
ok z
'873 Subtect:
re73 SAMUELS AVENUE BRIDGE OVER THE WEST FORK
OF THE TRINITY RIVER
TxDOT has notified Transportation and Public Works of additional problems with the
rehabilitation of the Samuels Avenue bridge over the West Fork of the Trinity River. The
contractor has encountered deteriorated bridge decking in excess of the indications from
previous testing. The extent of the additional failed areas, in conjunction he with c to request
the safety of workers on the bridge and the general public, has promoted weeks4 The original
total closure of the bridge for a period of approximately ks The closure will begin on Wednesday,
contract called for a total closure of six (6)
April 19, 1995.
This additional work is estimated to increase the City's share of the project cost by $12,000 -
$15,000. Mor ccurate cost figures will be available as work progresses on the bridge.
�r
Bob rrell
City Manager