HomeMy WebLinkAboutContract 62404-CO162404-COI
FoxT�W�ORTH .
Project Name 2025 Asphalt Resurfacing Contract 2
Client Project #(s)1 105638
Project Description
Contractor
City Project Mgr.1
Sunmount Paving
Iretomiwa Otuyelu
Dept.
Original Contract Amount
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date
Amount of Proposed Change Order
Revised Contract Amount
Original Funds Available for Change Orders
Remaining Funds Available for this CO
Additional Funding (if necessary)
TPW
$2,875,570.00
$2,875,570.00
$86,162.50
$2,961,732.50
$287,557.00
$287,557.00
City of Fort Worth
Change Order Request
Asphalt Resurfacing at various locations
I� Change Order #I
I
City Sec # j 62404
Datel 3/10/2025
City Inspectorl Kevin Jackson
Contract Time
Totals (CD)
$2,875,570.00 210
$2,875,570.00 210
$86,162.50 30
$2,961,732.50 240
$287,557.00
$287,557.00
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT 3.00%
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%) $3,594,462.50
JUSTIFICATION (REASONS) FOR CHANGE ORDER
This change order adds new items for a more comprehensive subgrade treatment at N Tarrant Parkway due to unforeseen subgrade issues encountered at the Westbound
roadway. Upon reassessment of the street during construction, it was found that the subgrade under the pavement is unstable, and the initial procedure of removing and
replacing the top 3-inch asphalt surface will not be sufficient. To ensure a more stable subgrade, staff proposes pulverizing and treating the subgrade to 12 inches below the
existing pavement and resurfacing the street with 4 inches of Asphalt. As a result, this change order will add new bid items for the latest procedure and reduce quantities for some
items related to the old procedure. The prices of the new items have been compared to prices on similar contracts and are deemed reasonable.
The staff also supports the contractor's request for an additional 30 days, which accounts for the necessary time to route and approve the change order and the additional time
the contractor requires to complete the new procedure.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full
(both time and money) for all costs arising out of, or incidental to, the above Change Order. The Project/Program Manager signing below acknowledges that
he/she is the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements.
Contractor's Company Name IContractor (Name) Contract Signature Date
Eurovia Atlantic Coast John Rauer Mar 14, 2025
Inspector/Inspection Supervisor
Date
Project and Contract Compliance Manager
Date
=wti
Mar14,2025
Mar 13, 2025
Program Manager
Date
Senior Capital Project Officer
Date
Ze(&(et-1 Aa
Mar14,2025
Mar14,2025
Assistant Director (Dept)
Date
Director, Contracting Department (Dept)
Date
P ricia 4 wadsacK
Mar 14, 2025
Mar 14, 2025
ty Attorney
Date
Assistant City Manager
Date
Mar 17, 2025
\
Mar20, 2025
Council Action (if required)
M&C Number M&C Date Approved
ATTEST:
�...... a .Aim...
Jannette Goodall, City Secretary
FORTWORTH
—1r1---
City of Fort Worth
Change Order Additions
Project Name 1 2025 Asphalt Resurfacing Contract 2
City Sec # 1 62404 1
Client Project # 1 105638
1
Contractorl Surmount Paving
PMI Iretomiwa Otuyelu
Inspectorl Kevin Jackson
l
Change Order Submittal # 0
Date 1 3/10/2025
ADDITIONS
I I EM
DESCRIP I ION
DEP I Oty
Unit Unit Cost
I otal 1
16
3211.0601 CEMLIME @32 LBS/SY
TPW 230.00000000
TN $340.OU
$78,200.001
36
0241.1700 Pavement Pulverization 9"
I PW 14,150.00000000
SY $19.25
$272,387.501
37
3212.0501 2" Asphalt Pvmt Type B (DG-B)
TPW 14,150.00000000
SY $20.50
$290,075.001
38
3212.0304 2" Asphalt Pvmt Superpave SP-D
TPW 14,150.00000000
SY $21.00
$297,150.001
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
TPW
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
$937,812.501
1
Sub Total Additions
1
1
$937,812.501
Change Order Additions Page 2 of 4
FORT WORTH
City of Fort Worth
V'IF"
Change Order Deletions
Project Name 1 2025 Asphalt Resurfacing Contract 2
City Sec #
62404
Client Project # 1 105638
1
Contractorl Sunmount Paving
I PMI Irelomiwa Otuyelu I
Inspeclorl Kevin Jackson l
Change Order Submittal # 0
Dale 1 3/10/2025
DELETIONS
ITEM DESCRIPTION
DEPT Oty
Unit Unit Cost
Total
10 3212.0900 Asphalt Crack Sealant
I PW bu.0000000u
GA $201.00
$10,050.001
11 3212.0600 Asphalt Pavement Level -Up
TPW 500.00000000
TN $175.00
$87,500.001
12 3124.0101 Asphalt Pavement Base Repair
TPW 1,100.00000000
CY $311.00
$342,100.001
15A 9999.1001 3" Asphalt Pvmt Superpave SP-D (PG 70-22 Superpave SP-D) TPW 16,000.00000000
SY $25.75
$412,000.001
TF W $851,650.001
1
1
1
Sub Total Deletions $851,650.001
Change Order Deletions Page 3 of 4
M/SBE for this Change Order
MISBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
co # DATE I AMOUNT
Total 1 $0.00 I
FORT WORTH.
Routing and Transmittal Slip
Transportation & Public Works
Department
DOCUMENT TITLE: 2025 ASPHALT RESURFACING CONTRACT 2 — CO 1
M&C: 24- 1027 CPN: 105638 CSO: 62404 DOC#: 1
Date:
To:
Name
1
LaKeshia Lynch
2.
Sunmount Paving Company
3.
Kevin Jackson
4.
Iretomiwa Otuyelu
5.
Zelalem Arega
6.
Mary Hanna
7.
Patricia Wadsack
8.
Lauren Prieur
9.
Doug Black
10.
Jesica McEachern
11.
Jannette Goodall
12.
TPW Contracts
Department
Initials
Date Out
Bus-Sppt
Mar 14, 2025
Vendor
Mar 14, 2025
TPW Inspector
K.I. J.okson
Mar 14, 2025
TPW
� • S•
Mar 13, 2025
TPW
1?4
Mar 14, 2025
TPW
m�
Mar 14, 2025
TPW AD
C" L
Mar 14, 2025
TPW Director
a f� PH —
Mar 14, 2025
Legal
Mar 17, 2025
Doug
CMO
,�<Eac„efn
Mar 20, 2025
CSO
7
Mar 20, 2025
TPW
CC: Program Manager, Sr. CPO, TPW BSPAP Recon Team, TPW Records Room, TPW Contracts
ALSO List: - Bus Sppt: LaKeshia Lynch; Prg Mgr.: Zelalem Ane a; Sr CPO — Mary Hanna
DOCUMENTS FOR CITY MANAGER'S SIGNATURE: All documents received from any and all
City Departments requesting City Manager's signature for approval MUST BE ROUTED TO THE
APPROPRIATE ACM for approval first. Once the ACM has signed the routing slip, David will review
and take the next steps.
NEEDS TO BE NOTARIZED: ❑YES ®No
RUSH: ❑YES ®No SAME DAY: ❑YES ❑No NEXT DAY: ❑YES ❑No
ROUTING TO CSO: ®YES ❑No
Action Required:
❑ As Requested
❑ For Your Information
® Signature/Routing and or Recording
❑ Comment
❑ File
❑ Attach Signature, Initial and Notary Tabs
Return To: Please notify TPWContractsnn,fortworthtexas.Lrov for pickup when complete. Call ext. 7233 or ext.
8363 with questions. Thank you!