Change Order Request
Facility and Project PSB Minicipal Building Roof Replacement
Description:
Funding (FID) No.(s)130100 0210410 5430101 104428 CAPEX 9999
Contractor: I Cowboys Roofing, LLC
City Project Mgr. IJuan Serrano
Phone Number: 1 (682) 352- 8186
CSC No. 61894-0O2
City Sec No. 61894
I City Proj. No 104428 1
Change Order # 0 Date: 1 3/19/2025 1
City Inspector: IJason Buchanan
Phone Number: 1(682) 201-1882
Contract Time
(CD)
Original Contract Amount ----------------------------------------------------------------------------------------------------------------------------- A
$685,716.40
120
Extrasto Date -------------------------------------------------------------------------------------------------------------------------------------------- 1
$42,000.00
20
Creditsto Date------------------------------------------------------------------------------------------------------------------------------------------A
0.00
0
Pending Change Orders (in M&C Process) ------------------------------------------------------------------------------------------------------- 1
0.00
0
Contract Cost to Date ---------------------------------------------------------------------------------------------------------------------------------- A
$727,-16.40
140
Amount of Proposed Change Order---------------------------------------------------------------------------------------------------------------A
336,681.00
15
Revised Contract Amount ----------------------------------------------------------------------------------------------------------------------------- 1
$64,397.40
155
Original Funds Available for Change Orders----------------------------------------------------------------------------------------------------A
,S80,000.00
Remaining Funds Available for this CO-----------------------------------------------------------------------------------------------------------I
$38,000.00
AdditionalFunding (if necessary)-------------------------------------------------------------------------------------------------------------------1
50.00
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
11.47 %
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%)
5857,145.50
JUSTIFICATION (REASONS) FOR CHANGE ORDER
The purpose for Change Order #2 will add scope of work to the project for PAR12, PAR13, and PAR14 to include the replacement of existing roof drains,
vertical drain lines, install scupper diverters, and clogged drained lines of the Public Safety Building.
Change Order #2 will add funds to the construction contract for PSB Minicipal Building Roof Replacement. An second increase of $36,681.00 to the original
contract amount ($685,716.40) for a revised contract amount of $764,397.40, a 11.47% increase to the original contract, approved by M&C 24-0584. This
results in an increase in project sum with an addtional 15 calendar days of project time. Cowboys Roofing, LLC was selected as the Contractor in July of 2024.
Funding is provided by PMD Facilities Capital Expendure.
It is understood and agreed that the acceptance of this Change Order by the contractor consitutes an accord and satisfaction and represents payment in full (both
time and money) for all costs arising out of, or incindental to the above Change Order.
Contractor's Comoanv Name Ior Nam
Cowboys Roofing, LLC Tim Ebel I Tim Ebel Mar 19, 2025
rim Ebel (Mar 19, 202513:30 CDT)
D I
Date
Assis at
A --
Mar 20,2025
Mar20,2025
JAun Buchanan (Mar20, 2025 07:10 CDT)
41 20 20251625 CDT
PMD Superintendent
Director Property Management DepartmAl
Mar 20, 2025
Mar 21, 2025
Project Manager
Sr. Assi�stga itt�City Attorney
�f
Mar 20,2025
9Mar24,2025
28 CDT
P1ro�/'ect Architec
Date
Assistant Ciity/ M�'anaa^
Mar 20,2025
Mar24,2025
iarold Stephens (Mart , 2025 10:50CDT)
Valerie Washington (Mar 24, 202515:44 CDT)
M&C Number
Contract Compliance Manager:
By signing I acknowledge that I am the person responsible
for the monitoring and adminstration of this contract, including
ensuring all performance and reporting requirements.
M&C Date Approved
OFFICIAL RECORD Nik if t1� 20, 202516:25 CDT)
Nikita Watts
CITY SECRETARY Sr. Capital Projects Officer
FT. WORTH, TX
Proposed Allowance # 12
Job # 24073
M40 *,k'
LUP
Project: PSB ROOF Date: 12/6/2024
Client: CFW
Attn: Harold Stephens
From Tim Ebel
Description: Roof C - Replace (2) drain inserts, vertical drain line to 90 deg elbow
and 5ft horizontal pipe for both drains.
Description Amount
Provide all necessary material, labor, equipment, supervision to remove two (2) vertical
steel pipe drain lines down to the first 90 degree elbow and five (5) feet of the horizontal
pipe for both drains. Includes two (2) new drain inserts. Access through existing plaster
ceiling will need to be opened by others. We are working to provide a quote to open a
4'x4' opening in the plaster ceiling. $ 10,851.00
ADD - $239 per ft to replace additional drain lines as needed.
Subtotal
$
10,851.00
Supervision
$
300.00
Subtotal
$
11,151.00
Overhead
0% $
-
Subtotal
$
11,151.00
Profit
0% $
-
Subtotal
$
11,151.00
Sales Tax
0.00% $
-
Total
$
11,151.00
Schedule impact: 5 Days
Accepted:
Rejected:
By:
Date
WAI 'I?ih laz
�i *0
Proposed Allowance # 13 ' •
Job # 24073
Project: PSB ROOF Date::1iai2025
Client: CFW
Attn: Harold Stephens
From Tim Ebel
Description:
Roof B - Provide and install Scupper Diverters.
Description
Amount
Provide all necessary material, labor, equipment, supervision to fabricate and install (4)
stainless steel scupper diverters on Roof B $ 1,120.00
Subtotal
$
1,120.00
Supervision
$
200.00
Subtotal
$
1,320.00
Overhead
0% $
-
Subtotal
$
1,320.00
Profit
0% $
-
Subtotal
$
1,320.00
Sales Tax
0.00% $
-
Total
$
1,320.00
Schedule impact: 5 Days
Accepted: ❑
Rejected: ❑
By:
Date
9
Proposed Allowance # 14 •
Job # 24073
Project: PSB ROOF Date: 1/14/2025
Client: CFW
Attn: Harold Stephens
From Tim Ebel
Description:
Roof C - Replace 90 If clogged horizontal roof drain lines.
Description Amount
Provide all necessary material, labor, equipment, supervision to remove 90 If horizontal
drain lines, haul away and replace with new pvc lines. 90 If x $239 per ft. $ 21,510.00
Provide all necessary material, labor, supervision to patch (2) Roof drains on Roof C.
This is due to cutting the roof drain verticals and discovering the horizontal lines need to
be replaced. Install (2) new retrofit drains after new drain line installation. $ 2,500.00
ROOF C CLOGGED DRAIN. '
REPLACE 90 LF HORIZONTAL
CLOGGED DRAIN LINE r_
Subtotal
$
24,010.00
Supervision
$
200.00
Subtotal
$
24,210.00
Overhead
0% $
-
Subtotal
$
24,210.00
Profit
0% $
-
Subtotal
$
24,210.00
Sales Tax
0.00% $
-
Total
$
24,210.00
Schedule impact: 5 Days