HomeMy WebLinkAboutIR 25-0043NFORMAL REPORT TO CITY COUNCIL MEMBERS
No. 25-0043
To the Mayor and Members of the City Council March 4, 2025
Page 1 of 8
i
i7 Y
SUBJECT: STORMWATER PROGRAM FY24 CAPITAL DELIVERY AND
rrn MAINTENANCE ACCOMPLISHMENTS
The purpose of this Informal Report is to highlight capital delivery and maintenance
accomplishments of the Stormwater Utility during Fiscal Year (FY) 2024 and provide a look ahead
at potential needs for FY 2026.
The Stormwater Utility was created by City Council in 2006 in response to loss of life and
devastating flooding to homes and businesses within the City of Fort Worth (City). The
Stormwater Program's (Program) mission is to protect people and property from harmful
stormwater runoff.
As an enterprise fund, the Stormwater Program is funded primarily through the Stormwater Utility
Fee, which is paid by property owners in the City, with a few exceptions, based on the amount of
impervious cover on each individual property, because impervious cover directly impacts
stormwater runoff.
FY24 Capital Delivery Accomplishments
The Stormwater Capital Program is funded by pay -go (cash) and revenue bonds. In October of
2019, City Council passed a 6.5% Stormwater Utility Fee increase for FY20, becoming effective
in January of 2020, to accelerate the delivery of high priority capital improvements. This provided
the Program with the ability to issue $53M of revenue bonds in FY21 and $43.25M of revenue
bonds in FY23.
Like many other City projects, delivery has been impacted by inflation, material and labor cost
increases, supply chain issues, and overall supply and demand issues due to the number of
projects and shortage of contractors. However, during FY24, higher interest rates have resulted
in the Stormwater Utility recognizing additional revenue in excess of $7M from interest earnings.
This additional revenue will be used to advance Stormwater capital projects and is reflected in the
goal delivery estimates shown on the bar chart below. The bar chart shows how many projects in
each project category are undergoing project development, are in design or construction, and
have been completed.
ISSUED BY THE CITY MANAGER FORT WORTH, TEXAS
NFORMAL REPORT TO CITY COUNCIL MEMBERS No. 25-0043
To the Mayor and Members of the City Council March 4, 2025
i
Page 2 of 8
i7 Y
SUBJECT: STORMWATER PROGRAM FY24 CAPITAL DELIVERY AND
rrn MAINTENANCE
ACCOMPLISHMENTS
Project Delivery Progress
$96.25M Debt Issuance, Interest Earned, and P?�tGo
Updated goals
As of 2/2025 57 locations
55 projects 1.61 miles 4 Project Phases
_ ■ Project
loose
Development
90%
■ In Design
90%
7M
■ In Construction
e0%
5°%
■ Com pi eted
40%
30%
20%
10%
D%
Hazardous Roadway
Pipe Rehab Channel Restoration Flood Mitigation
Overtopping
Mitigation
Note: lnitial2019 goal estimates have been updated due to T. actual debt issuances, 2. higher project costs (considering inflation, supply chain issues, material
and labor cost increases, and overall supply and demand
for contractors), 3. project development refinement of initial cast estimates which were based on high
level planning, 4. Changing how pipe rehab delivery is
measured, and 5. Aug. 2022 flooding showing need for large scale flood mitigation improvement delivery
During FY24, the following number
of projects within each category were substantially completed
(actual project list attached).
Project Category
Category Definition
Substantially Completed
in FY24
Hazardous Road Overtopping
Major projects reduce road
2 major projects
Mitigation (HROM)
overtopping
Safety/minor projects improve
10 safety/minor projects
warning and safety during road
flooding
Storm Drain Pipe Rehabilitation
Mitigate sinkhole risk and ensure
5 projects
continued conveyance of stormwater
Channel Restoration
Protect adjacent infrastructure and
0.76 miles
property by restoring severely
eroded channels
NFORMAL REPORT TO CITY COUNCIL MEMBERS
No. 25-0043
To the Mayor and Members of the City Council March 4, 2025
Page 3 of 8
i
i7 Y
SUBJECT: STORMWATER PROGRAM FY24 CAPITAL DELIVERY AND
rrn MAINTENANCE ACCOMPLISHMENTS
Reactive Any type of stormwater project, but 6 projects led by
smaller in scale and identified over Stormwater
the course of each fiscal year
through partnership opportunities 2 partnerships with other
and in response to rain events and City projects completed in
emergency needs FY24 and 16 currently in -
progress
In October of 2023, City Council approved a 15% Stormwater Utility Fee increase for FY24,
becoming effective in January of 2024, to be evenly divided between capital flood mitigation
projects and maintenance service level improvements.
The capital portion of the fee increase is funding the initial phase of delivery for three large flood
mitigation projects over a 15-year timeframe: Upper Lebow, Linwood/W. 71" Street, and
Berry/McCart. See Budget Response Memo No. 24-017, dated Sept. 7, 2023, and Informal
Report No. 23-0759, dated October 10, 2023, for more information on the FY24 fee increase.
Over the last FY, the Program has advanced these projects in the following ways:
Upper Lebow:
• Began project development phase working on preliminary channel design, utility
coordination, and property acquisition;
• Submitted two Federal Emergency Management Agency (FEMA) grant applications (for
more information see M&C 23-1058, dated December 12, 2023);
• Submitted a State grant application to the Texas Water Development Board (TWDB) Flood
Infrastructure Fund (for more information see Informal Report No. 24-1828, dated April 2,
2024, and M&C 24-0280, April, 9, 2024); and
• Began property acquisition needed to construct future improvements.
Linwood/W. 7cn.
• Updated the model of the existing drainage system to better understand the current flood
risk and allow for accurate evaluation and project development of flood mitigation
alternatives;
• Held meetings with the Tarrant Regional Water District (TRWD) to understand the impacts
of potential outfall improvements to the Trinity River water levels and water quality
regulations; and
• Evaluated potential detention and conveyance improvements to identify alternatives to
advance into project development.
ISSUED BY THE CITY MANAGER FORT WORTH, TEXAS
NFORMAL REPORT TO CITY COUNCIL MEMBERS
No. 25-0043
To the Mayor and Members of the City Council March 4, 2025
Page 4 of 8
i
i7 Y
SUBJECT: STORMWATER PROGRAM FY24 CAPITAL DELIVERY AND
rrn MAINTENANCE ACCOMPLISHMENTS
Berry/McCart:
• Began project development phase on future drainage improvements along Sandage
Avenue -land
• Collaborated with Texas Christian University regarding potential partnership opportunities.
Additionally, the Program continues to support the Fort Worth Central City Project through the
relocation of existing drainage pipe infrastructure in four (4) locations to allow for the future
construction of the Trinity River bypass channel by the U.S. Army Corps of Engineers.
FY24 Maintenance Accomplishments
As mentioned above, half of the FY24 Stormwater Utility fee increase is going toward
maintenance service level improvements. Implementation of a five-year plan for maintenance
service level improvements is underway.
During FY24, Stormwater Field Operations kicked off a proactive City-wide culvert inspection
program to improve the prioritization of culvert cleaning needs. The City is responsible for
approximately 4,000 culverts. This new program is the outcome of previously unidentified culvert
maintenance concerns creating flood risks.
Five new staff were hired for this program in FY24 and as of December 2024, 666 culverts have
now been inspected and 586 culverts have been cleaned through this program, exceeding the
City's initial projections for the program's first year. The table below shows the estimated annual
culvert inspection and cleaning capacity before and after the recent service level improvements.
Estimated Annual
Estimated Annual
Culvert Inspection
Culvert Cleaning
number of culverts
number of culverts
Before Service Level Improvements
200
360
After Service Level Improvements
1,400
500
The second Stormwater maintenance program service level improvement in FY24 was focused
on the drainage pipe condition assessment program. A new seven -person team was created to
inspect, clean, and proactively plan ahead for drainage pipe condition assessments. This
program accelerates the condition assessment process, which enables the City to more quickly
identify, prioritize, and rehabilitate locations in need of rehab, keeping the community safer from
sinkholes. The work also accelerates the removal of trash and debris from the City's drainage
pipe system, which improves stormwater conveyance, mitigating the risk of flooding due to debris
build up in the storm drain system. The table below shows the estimated annual pipe inspection
and cleaning capacity before and after the recent service level improvements.
ISSUED BY THE CITY MANAGER FORT WORTH, TEXAS
NFORMAL REPORT TO CITY COUNCIL MEMBERS
No. 25-0043
To the Mayor and Members of the City Council March 4, 2025
Page 5 of 8
i
i7 Y
SUBJECT: STORMWATER PROGRAM FY24 CAPITAL DELIVERY AND
rrn MAINTENANCE ACCOMPLISHMENTS
Estimated Annual
Pipe Inspection
Estimated Annual
Pipe Cleaning
Before Service Level Improvements
132,000 feet / 25 miles
25,400 feet / 5 miles
After Service Level Improvements
264,000 feet / 50 miles
9,200 feet / 15 miles
During FY 24, in addition to the expanded service levels in the above two programs, Stormwater
Field Operations:
• Maintained 5.8 miles of engineered channels through silt removal and re-establishing
grade;
• Maintained 5.1 miles of bar ditches through regrading and silt removal to improve
drainage;
• Restored 1.4 miles of engineered channels by rebuilding highly eroded channel slopes;
• Mowed 1,665 acres of right-of-way to ensure effective stormwater conveyance;
• Inspected and cleaned 6,691 of the total 30,000 inlets City-wide;
• Performed closed circuit television inspection (CCTV) condition assessment on 12.4 miles
of drainage pipe to proactively identify and prioritize rehabilitation needs; and
• Removed and replaced 1,807 square yards of damaged concrete storm drain
infrastructure.
W#1*1111 WeTel .7_1
The Stormwater Utility Fee increases in FY20 and FY24 and the recently approved FY25 fee
increase, which became effective in January of 2025, are significantly advancing the City's efforts
to keep its residents, homes, and businesses safer from flood risks and reducing emergency
response needs associated with flooding. Overall, however, known needs continue to exceed the
Program's available resources. The table below shows the Program's key asset types, estimated
costs to address critical capital and maintenance needs, and current capital and maintenance
funding levels.
ISSUED BY THE CITY MANAGER FORT WORTH, TEXAS
NFORMAL REPORT TO CITY COUNCIL MEMBERS
No. 25-0043
To the Mayor and Members of the City Council March 4, 2025
Page 6 of 8
i
i7 Y
SUBJECT: STORMWATER PROGRAM FY24 CAPITAL DELIVERY AND
rrn MAINTENANCE ACCOMPLISHMENTS
Estimated Cost
Estimated
Annual
Asset Type
Units
to Address
FY25-29
Annual
Maintenance
Critical Capital
Paygo + Bond
Maintenance
Funding
Needs
Needs
Road culverts at
-r4,000
$24.34M
$1 M
$500,000
channels/creeks
$265M - $345M
Storm Drain Pipes*
-r1,085
>$113
$110.86M
$2.7M
$1.3M
miles
Engineered
-r230.7
$150M -$190M
$5M
$6.8M
$2.6M
Channels
miles
Total
>$1.5B
$140.2M
$10.5M
$4.4M
As of February 2025
*Includes flood mitigation capacity and drainage pipe rehabilitation needs
Considering the recent accomplishments discussed above and continued needs, the Program is
now considering how additional funding for channel restoration could benefit the community.
Additionally, the Program is also evaluating the amount of funding allocated toward heavy
equipment replacement each fiscal year to ensure the Program's Field Operations team is able to
effectively maintain stormwater infrastructure and provide emergency response during flood
events.
The Program recently kicked off the development of a 20-year Stormwater Strategic Plan. This
effort will evaluate Program needs to determine the best ways to accomplish the Program's
mission in a way that aligns with City Council Strategic Goals and is in the best interest of the
community. The strategic planning effort will identify stakeholder priorities, assess Stormwater
Program needs and service gaps, estimate future funding needs, recommend a corresponding
funding strategy, and prepare a business case justification for funding needs and a roadmap of
implementable actions to close funding gaps. The strategic effort will also assess the current
functions and structure of the Stormwater Program to identify and make recommendations for
possible opportunities for optimization.
ISSUED BY THE CITY MANAGER FORT WORTH, TEXAS
NFORMAL REPORT TO CITY COUNCIL MEMBERS
No. 25-0043
To the Mayor and Members of the City Council March 4, 2025
Page 7 of 8
i
i7 Y
SUBJECT: STORMWATER PROGRAM FY24 CAPITAL DELIVERY AND
rrn MAINTENANCE ACCOMPLISHMENTS
More information on the Program needs be presented to the City Council at a later date after
further evaluation.
For additional information, please contact Jennifer Dyke, Transportation and Public Works
Assistant Director, Stormwater Management Program, at 817-392-2714.
Jesus "Jay" Chapa
City Manager
ISSUED BY THE CITY MANAGER
FORT WORTH, TEXAS
NFORMAL REPORT TO CITY COUNCIL MEMBERS
No. 25-0043
i
i7 Y
*a
rrn
Capital Project
Number (CPNI
103050
To the Mayor and Members of the City Council March 4, 2025
Page 8 of 8
SUBJECT: STORMWATER PROGRAM FY24 CAPITAL DELIVERY AND
MAINTENANCE ACCOMPLISHMENTS
Attachment
FY24 Stormwater Completed Projects
ProjM Name CouncilProject Category1Cost
Westcreek Channel Rehab 6 Channel Rehab $ 2,8D4,469.40
104181
Blue Bonnet Circle Storm Drain Rehab
9
Pipe Rehab
$
615,194.91
102931
2022 Bond Year 1- Contract5- E Vickery Blvd
8
Reactive
$
105,973.00
104621
Jacqueline Road Storm Drain Improvements
11
Reactive
$
203,809.47
CO2722
Sa n ita ry Sewe r Rehabilitation Contract 101- Winton Terrace
9
Pipe Rehab
$
426,685.00
104857
TO 13 - Southeast HROM Safety
S, 11
Safety
$
593,256.14
Old Mansfield Road at Sycamore Creek
8
Safety
5029 Nell St
11
Safety
4590 Miller Avenue
11
Safety
512E Shackleford Street @ VC-2
11
Safety
15W Oak Grove East
8
Safety
105055
W 6th & Carroll Storm Drain Rehab
9
Pipe Rehab
$
41,452.11
105059
8511 Bryson Lane Drainage Improvements
7
Reactive
$
138,257.33
105039
S Cravens Closure HROM Safety
5
Safety
$
90,539.98
105357
Pafford -Cockrell Ave Repair
9
Reactive
$
44,523.75
105059
1501 Rio Grande Drainage Improvements
9
Reactive
$
113,524.01
105607
Fort Worth Zoo
9
Reactive
$
120,432.41
103077
Judy Lane
11
Pipe Rehab
$
355,350.77
103056
7th St at BurnettStorm Drain Rehab
9
Pipe Rehab
$
896,405.96
103055
Altamesa Blvd Edgecliff Channel Rehab
6
Channel Rehab
$
3,1340.43
103052
McCart Krauss Baker Channel Rehab
5
Channel Rehab
$
2,767.83
104260
TO #12 Multiple Sites Safety HROM
2,8
Safety
$
622,920.14
4200 Hardy at WF-4
2
Safety
5D40 Mark IV Parkway @ Little Fossil Creek
2
Safety
39W Ohio Garden
2
Safety
2300 E. Berry St. @SC-3
S
Safety
103396
HROM Comanche Trail
7
HROM
$ 2,850,988.52
10305Z
28th Str at Decatur HRCM
2
HROM
$ 5,530,414.03
HROM— Hazardous Road Overtopping Mitigation
ISSUED BY THE CITY MANAGER
FORT WORTH, TEXAS