HomeMy WebLinkAboutContract 59320-CO4FORT WORTH. City of Fort Worth
CSC No. 59320-004
Change Order Request
Project Namel 103664 - Grand Ave Ph2 Pt2 City Sec # l 59320 l
Client Project #(s)l 103664/103665/C00969
Project Description) This will be the continuation in Phase 2 which will include the installation of (3)-72" RCPs to connect the existing Grand Avenue line with the new outfall to the
West Fork downstream of the isolation gates II
Contractorl S.J. Louis Construction of Texas Change Order #1 4 1 Datel 2/27/2025
City Project Mgr.l Max Aransen, P.E. City Inspectorl Jeremy Koonce
Dept.
Storm Drain
Sewer
Water
Totals
Contract Time
(CD)
Original Contract Amount
$21,114,746.00
$1,635,338.50
$0.00
$22,750,084.50
400
Extras to Date
$0.00
$46,400.00
$206,792.00
$253,192.00
150
Credits to Date
$0.00
$0.00
Pending Change Orders (in M&C Process)
$0.00
$0.00
Contract Cost to Date
$21,114,746.00
$1,681,738.50
$206,792.00
$23,003,276.50
550
Amount of Proposed Change Order
$61,936.22
$0.00
$0.00
$61,936.22
59
Revised Contract Amount
$21,176,682.22
$1,681,738.50
$206,792.00
$23,065,212.72
609
Original Funds Available for Change Orders
$0.00
Remaining Funds Available for this CO
$0.00
$0.00
$0.00
Additional Funding (if necessary)
$61,936.22
$61,936.22
CHANGE ORDERS to DATE
(INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
1.39%
MAX ALLOWABLE
CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%)
$28,437,605.63
This change order will be for the work required for SJL to assist in the removal and replacement of the TLP for Atmos to remove their existing abandoned gas line. This will also
include work for SJL to repave the street after the line has been removed. This will also account for the delays caused by the Atmos line conflict starting in December 2024, to the
commencing of the removal by Atmos this year. The Asphalt Payment item is an already existing item within the contract and the quantities are pulled from the estimated trench
required to remove the existing Atmos line. The other items are for striping and pavement markings, and for labor and equipment to remove and replace the TLP. While they are
not existing items, the breakdown prices for the labor and fuel were compared to the crew, labor, and machinery prices from the existing Certified payroll reports and are shown
to be reasonable. The quantities of these two items have been reviewed by the Engineer, Project Manager, and Construction Manager and found to be reasonable based on the
estimated trench required to remove the Atmos line.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full
(both time and money) for all costs arising out of, or incidental to, the above Change Order. The Project/Program Manager signing below acknowledges that
he/she is the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements.
ontractor's Company Name Contractor (Name) CnintuirtRiignature Date
S.J. Louis Construction of Texas Adam Lunsford AdamLu�.4 Mar 25, 2025
Inspector/Inspection Supervisor
Date
Project and Contract Compliance Manager
Date
Ma,zb zozso,s4 o
M a r 26, 2025
^' o .....
o 56 pr
Mar 26, 2025
� �
Date
Mar 26, 2025
Se a roject Officer
- -
Date
Mar 26, 2025
Date
Director, Contracting Department (Dept)
Date
M a r 27, 2025„
M a r 27, 2025
Assistant City Attorne-M F
Date
Mar 31, 2025
Assistant City Manager
r-'0q. Q
Date
Apr 7. 2025
Off-C.-incil Action (it required)
4 vvanu M&C Number
T
POR�o�00
pTT�S�
oF
OVS o=4
Jannette Goodall, City Secretary
pOQ*ooe o�xd°
�aIl��= ooOO �4q
M&C Date Approved I
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
FORTWORTH
City of Fort Worth
Change Order Additions
Project Name 1 103664 - Grand Ave Ph2 Pt2
City Sec # 1 59320 1
Client Project# 1 103664/103665/C00969
I
Contractorl S.J. Louis Construction of Texas
PMI Max Aransen, P.E. I
Inspectorl Jeremy Koonce
Change Order Submittal # ®
Dale 1 2127/2025
ADDITIONS
ITEM DESCRIPTION
DEPT Qty
Unit Unit Cost
Total 1
34 Asphalt Pvmt Repair Beyond Defined Width, Industrial
Storm Drain 180.00000000
SY $145.00
$26,100.001
54 Striping and Pavement Marking
Storm Drain 1.00000000
LS $5,000.00
$5,000.001
55 Additional Labor, Equipment, and Fuel for TLP
Storm Drain 1.00000000
LS $30,836.22
$30,836.221
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
StorArain
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
$61,936.221
Sewer
$0.001
Water
$0.001
I
Sub Total Additions
I
$61,936.221
Change Order Additions Page 2 of 4
HEM
EM
FoR1 W�oRTH City of Fort Worth
Change Order Deletions
Project Name 103664 - Grand Ave Ph2 Pt2 City Sec # 59320
Client Project# 103664/1036651CO0969 I
Contractorl S.J. Louis Construction of Texas I PMI Max Aransen, P.E. I Inspectorl Jeremy Koonce
Change Order Submittal # ® Date 1 2127/2025 1
DELETIONS
UESUKIPIIUN UEPI Uty Unit Unit lost total
Storm brain $0.00�
Sewer $0.00 1
I Water $0.00 1
Change Order Deletions Page 3 of 4
Sub Total Deletions $0.00 1
M/SBE for this Chanae Order
M/SBE Sub I Type of Service I Amount for this CO
Total $0.00
Previous Change Orders
co # DATE AMOUNT
1 4/25/2024 $0.00
2 8/9/2024
11 /12/2024
$0.00
$253,192.00
Total I $253,192.00 I
Request for Proposal
Project Name
Grand Avenue Bypass Storm Drain (City Project #00969)
City of Fort Worth, Texas
Response Required By
Max Aransen, P.E.
200 Texas Street
Fort Worth, Texas 76102
Via Email
Max.Aransen(&,,fortworthtexas. Lyov
C.M.R. - Proposal No. Date
11
Transmitted By
Adam Birchfield
Project Manager
Signature
February 19, 2025
Descrintion of Work
This CMR is in reference to assisting the Atmos Gas Line Contractor in removal of the 24" line along Main St. and Grand Ave.
Pricing for this work includes: Removal of the liner plate next to the exavation (performed by others), re -install Liner plate once 24" gas
line is removed, asphalt overlay, striping, traffic control plan and installation. (60 Additional Days - 12/9-24 - 12/22/24 (11 Days) 1/6/25 -
2/23/25 (48 Days)}
Please review and let us know if you have any questions and / or require any additional information. Please process a project change
order so these costs can be reimbursed as the work is being completed.
Breakdown of'Proposal
Grand Avenue Bypass Storm Drain & Sanitary Sewer Improvements
Additional Costs/ 24" Atmos Gas Line Removal
Item Description Quantity Unit Price
15 Asphalt Pvmt Repair 180 SY $145.00
New - 1 Stripping and Pvmt Markings 1 LS $5,000.00
New - 2 Additional Labor, Equipment, and Fuel to Complete 1 LS $30,836.22
Net Change :
Additional Calendar Days
If acceptable, please provide an authorization signature below and return one (1) copy to our office.
S.J. Louis Construction Action
xc: S. J. Louis Project No. 22305
S.J. Louis Construction of Texas Ltd.
520 S. 6th Avenue
Mansfield, Texas 76063
(817) 477-0320 Office (817) 477-0552 Fax
Extension
$26,100.00
$5,000.00
$30,836.22
$61,936.22
59
6" Gravel Driveway
Grand Total
Cost
74651 $30,836.22
$4.13
103664 Grand Ave CO 4_updated
Final Audit Report 2025-03-27
Created: 2025-03-20
By: Sadie Ishmael (Sadie.Ishmael@fortworthtexas.gov)
Status: Signed
Transaction ID: CBJCHBCAABAAx4aC4lgLXPU-bNLDFtYWJNPgdTzxQsO
"103664 Grand Ave CO 4-updated" History
Document created by Sadie Ishmael (Sadie.Ishmael@fortworthtexas.gov)
2025-03-20 - 9:23:36 PM GMT- IP address: 204.10.90.100
6� Document approved by Sadie Ishmael (Sadie.Ishmael@fortworthtexas.gov)
Approval Date: 2025-03-20 - 9:29:51 PM GMT - Time Source: server- IP address: 204.10.90.100
Document emailed to adaml@sjlouis.com for signature
2025-03-20 - 9:29:53 PM GMT
`s Email viewed by adaml@sjlouis.com
2025-03-20 - 9:54:40 PM GMT- IP address: 104.28.116.107
Email viewed by adaml@sjlouis.com
2025-03-24 - 3:02:37 AM GMT- IP address: 104.28.32.100
Signer adaml@sjlouis.com entered name at signing as Adam Lunsford
2025-03-25 - 3:45:14 PM GMT- IP address: 63.145.51.2
0'o Document e-signed by Adam Lunsford (adaml@sjlouis.com)
Signature Date: 2025-03-25 - 3:45:16 PM GMT - Time Source: server- IP address: 63.145.51.2
7Document emailed to Jeremy Koonce (Jeremy.Koonce@fortworthtexas.gov) for signature
2025-03-25 - 3:45:18 PM GMT
ws Email viewed by Jeremy Koonce (Jeremy.Koonce@fortworthtexas.gov)
2025-03-26 - 12:54:02 PM GMT- IP address: 162.120.129.70
>Q, Document e-signed by Jeremy Koonce (Jeremy.Koonce@fortworthtexas.gov)
Signature Date: 2025-03-26 - 12:54:51 PM GMT - Time Source: server- IP address: 162.120.129.70
Document emailed to Max Aransen (max.aransen@fortworthtexas.gov) for signature
2025-03-26 - 12:54:53 PM GMT
FoRTWORTH, I P—e'b'
Adobe
Acrobat Sign
Email viewed by Max Aransen (max.aransen@fortworthtexas.gov)
2025-03-26 - 12:55:53 PM GMT- IP address: 97.75.74.58
Document e-signed by Max Aransen (max.aransen@fortworthtexas.gov)
Signature Date: 2025-03-26 - 12:56:29 PM GMT - Time Source: server- IP address: 97.75.74.58
Document emailed to Thanaa Maksimos (Thanaa.Maksimos@fortworthtexas.gov) for signature
2025-03-26 - 12:56:30 PM GMT
Email viewed by Thanaa Maksimos (Thanaa.Maksimos@fortworthtexas.gov)
2025-03-26 - 1:24:04 PM GMT- IP address: 208.184.124.181
Oo. Document e-signed by Thanaa Maksimos (Thanaa.Maksimos@fortworthtexas.gov)
Signature Date: 2025-03-26 - 1:24:23 PM GMT - Time Source: server- IP address: 208.184.124.181
-', Document emailed to Lissette Acevedo (Lissette.Acevedo@fortworthtexas.gov) for signature
2025-03-26 - 1:24:26 PM GMT
" s Email viewed by Lissette Acevedo (Lissette.Acevedo@fortworthtexas.gov)
2025-03-26 - 4:23:55 PM GMT- IP address: 204.10.90.100
Document e-signed by Lissette Acevedo (Lissette.Acevedo@fortworthtexas.gov)
Signature Date: 2025-03-26 - 4:24:37 PM GMT - Time Source: server- IP address: 204.10.90.100
Document emailed to Patricia Wadsack (patricia.wadsack@fortworthtexas.gov) for signature
2025-03-26 - 4:24:39 PM GMT
Q, Signer Patricia Wadsack (patricia.wadsack@fortworthtexas.gov) entered name at signing as Patricia L.
Wadsack
2025-03-27 - 4:05:09 PM GMT- IP address: 208.184.124.181
Q, Document e-signed by Patricia L. Wadsack (patricia.wadsack@fortworthtexas.gov)
Signature Date: 2025-03-27 - 4:05:11 PM GMT - Time Source: server- IP address: 208.184.124.181
Document emailed to Lauren Prieur (Lauren.Prieur@fortworthtexas.gov) for signature
2025-03-27 - 4:05:13 PM GMT
Email viewed by Lauren Prieur (Lauren.Prieur@fortworthtexas.gov)
2025-03-27 - 4:07:52 PM GMT- IP address: 76.227.105.128
Document e-signed by Lauren Prieur (Lauren.Prieur@fortworthtexas.gov)
Signature Date: 2025-03-27 - 4:08:24 PM GMT - Time Source: server- IP address: 76.227.105.128
Document emailed to tpw_sw_contracts@fortworthtexas.gov for approval
2025-03-27 - 4:08:26 PM GMT
FoRTWORTH, I P—e'b'
Adobe
Acrobat Sign
Email viewed by tpw_sw_contracts@fortworthtexas.gov
2025-03-27 - 6:25:01 PM GMT- IP address: 204.10.90.100
Signer tpw_sw_contracts@fortworthtexas.gov entered name at signing as Sadie Ishmael
2025-03-27 - 6:26:30 PM GMT- IP address: 204.10.90.100
Document approved by Sadie Ishmael (tpw_sw_contracts@fortworthtexas.gov)
Approval Date: 2025-03-27 - 6:26:32 PM GMT - Time Source: server- IP address: 204.10.90.100
Agreement completed.
2025-03-27 - 6:26:32 PM GMT
FoRTWORTH, I P—e'b'
Adobe
Acrobat Sign
FORT WORT
Routing and Transmittal Slip
Transportation
& Public Works Department
DOCUMENT TITLE:
Grand Ave Outfall Construction Change
Order 4
M&C: CPN:
103664,103665, CSO: 59320
DOC#:
C00969
Date:
To:
Name
Department Initials
Date Out
1
Adam Lunsford
Contractor AHL I L
Mar 25, 2025
AdamL@SJLouis.Com
2.
Jeremy Koonce
TPW - Inspector e em
M a r 26, 2025
3.
Max Aransen
TPW - Project Manager
Mar 26, 2025
4.
Thanaa H. Maksimos
TPW — Program Manager T TM
Mar 26, 2025
5.
Lissette Acevedo
TPW — Sr. CPO 9N
M a r 26, 2025
6.
Patricia Wadsack
TPW — Assistant Director PL'W'
M a r 27, 2025
7.
Lauren Prieur
TPW - Director x ev
Mar 27, 2025
8.
Doug Black
-
Legal - Assistant City Attorney
M a r 31, 2025
o
9.
Jesica McEachem
CMO — Assistant City Manager
Apr 7, 2025
10.
Jannette Goodall
CSO — City Secretary
Apr 7, 2025
11.
Allison Tidwell
CSO — City Secretary AT
Apr 7, 2025
12.
Tpw—SW—Contract
TPW Stormwater
Mar 27, 2025
CC: Program Manager — Thanaa Maksimos, Sr. CPO — Lissette Acevedo, TPW BSPAP Recon
Team — Cindy Sengathith
DOCUMENTS FOR CITY MANAGER'S SIGNATURE: All documents received from any and all
City Departments requesting City Manager's signature for approval MUST BE ROUTED TO THE
APPROPRIATE ACM for approval first. Once the ACM has signed the routing slip, David will review
and take the next steps.
NEEDS TO BE NOTARIZED: []YES ®No
RUSH: []YES ®No SAME DAY: []YES ®No NEXT DAY: ❑YES ®No
ROUTING TO CSO: ®YES ❑No
Action Required:
❑ As Requested
❑ For Your Information
® Signature/Routing and or Recording
❑ Comment
❑ File
❑ Attach Signature, Initial and Notary Tabs
Return to: tuw sw contracts(& fortworthtexas.uov Call 817-229-3283 with questions. Thank you!