HomeMy WebLinkAboutContract 51989-PM1City SecretaryFORT WORTH
Contract No �j�j K
PROJECT MANUAL
FOR
THE CONSTRUCTION OF
SANITARY SEWER TO SERVE MILAM STREET
FROM WORKS STREET TO 3RD STREET
City Project No. 101901
Betsy Price David Cooke
Mayor City Manager
Steve Cooke
Interim Director, Transportation and Public Works
Christopher P. Harder, PE
Interim Water Director
Prepared for
The City of Fort Worth
2019
Q L 25 q MAS Civil Engineers
TBPE # 17018
s
/.. M .�.................... .......... i.... - -
iPAMELA L SALVADOR OONZALEZ�
j..................... .....................
�i 110252
tl10.o• ��cENs��•.
X-25801
00 0010-1
PROJECT RECORD DOCUMENTS FOR DEVELOPER AWARDED PROJECTS
Page 1 of 4
1 SECTION 00 00 10
2 TABLE OF CONTENTS
3 DEVELOPER AWARDED PROJECTS
4
5
6
Division 00
- General Conditions
7
00 42 43
Proposal Form Unit Price
8
04A 3-4-3
DidA3offd
10
0045 12
Prequalification Statement
11
90 1f i3
12
00 45 26
Contractor Compliance with Workers' Compensation Law
13
00 52 43
Agreement (As provided by Developer or City's DAP Version)
14
00 61 25
Certificate of Insurance (Use actual Acord Form)
15
0062 13
Performance Bond
16
0062 14
Payment Bond
17
0062 19
Maintenance Bond
t n 00 73 00
20
0073 10
Standard City Conditions of the Construction Contract for Developer Awarded
21
Projects
22
_
23
Division 01
- General Requirements
24
01 1100
Summary of Work
25
04-�o
c
26
01 31 19
Preconstruction Meeting
27
01 31 20
Rrejeet Meefiap
28
0! 32-45
-- 29
04-�3
30
013300
Submittals
31
0135 13
Special Project Procedures
_ 32
01 4523
Testing and Inspection Services
33
01 50 00
Temporary Facilities and Controls
34
01 55 26
Street Use Permit and Modifications to Traffic Control
35
01 57 13
Storm Water Pollution Prevention Plan
36
"S"
Tsrr-
37
01 60 00
Product Requirements
38
01 6600
Product Storage and Handling Requirements
39
0!-70 9
1104i4zeAiar. WA Rs��
40
01 71 23
Construction Staking
41
01 74 23
Cleaning
42
01 77 19
Closeout Requirements
43
01 78 23
Operation and Maintenance Data
44
01 7839
Project Record Documents
- 45
46
Technical Specifications
which have been modified by the Engineer specifically for this
47
Project; hard copies are included in the Project's Contract Documents
48
49
NONE
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 101901
Revised September 1, 2015
00 00 10- 2
PROJECT RECORD DOCUMENTS FOR DEVELOPER AWARDED PROJECTS
Page 2 of 4
1
2 Technical Specifications listed below are included for this Project by reference and can be
3 viewed/downloaded from the City's Buzzsaw site at:
4
5 htt)s://Droiectt)oint.buzzsaw.com/client/fortwortheov/Resources/02%20-
6%20Construction%2ODocumentS/Specifcations
7
8 Division 02 - Existing Conditions
9 82-41-13
10 02 41- 1Utility RemeyaMbaadefffaent
11 03 11 if Pewing Refney*1
12
13 Division 03 - Concrete
14- 03 30^-^00 C
15 03 34 i3 GeWferlea Lowvctfeagth Mat L )
16 03 34 it
17 03-80-09 ".
18
19 Division 31- Earthwork
20 31 1000 Site Clearing
21 3 23-! 5 L1aek%4ffk Nn"Iatieff
22 34-2-3-23 Beffew
23 31-�O Emba*kmef4s
24 3125 00 Erosion and Sediment Control
25 313609 Gabiexs
26 313709 Papfep
27
28 Division 32 - Exterior Improvements
29 3201 17 Permanent Asphalt Paving Repair
30 42-04- 4 'T__efnpe«afy Asphalt It Paving D epai
31
32 3244-�3 r
33 32 1-12 k r.
34 32 ! 1 33 Cement-Tr-eated yes
35 32!2!6
363244-;v Asphalt Paying Gmak Sealants
3,7 3 2 1'
38 32 13 20 Concrete Sidewalks, Driveways and Barrier Free Ramps
39 -3-19 73 Genefete Payingjeiat-de s
40 2 t
41 321613 - Gener-ete Garb and Guttefs and Valley „tEeFs
42— 3z'17-23 Nvefnew MeAiiags
43-32 3! !3 Chain Link >; enees and Gates
44 32 6 Wir-e Fenees and Gates
45 32
46
47 3291 19 Topsoil Placement and Finishing of Parkways
48 3292 13 Hydro -Mulching, Seeding, and Sodding
49 32-9---43 Trees and i hfubs
50
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS —DEVELOPER AWARDED PROJECTS CPN 101901
Revised September 1, 2015
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
00 00 10- 3
PROJECT RECORD DOCUMENTS FOR DEVELOPER AWARDEDPROJECTS
Page 3 of 4
Division 33 - Utilities
33 01 30
Sewer and Manhole Testing
33 01 31
Closed Circuit Television (CCTV) Inspection
33-04-10
joint Bending and Bleetr-ieftl lseleAie
33-01 , ,
33--0442
Magnesium
33-94-3o
T
33-04-40
gleaning Aeeeptanee Testing Mains
and efWater-
3305 10
Utility Trench Excavation, Embedment, and Backfill
33 95 12
3305 13
Frame, Cover and Grade Rings
3305 11
Adjusting Manholes, lnle4s, Valve Boxes, and 04hor-
3305 17 Concrete Collars
33-0-5-20 AageF BeFifrg
33-0-5-2 1 Tunnel
33052 Cteel Casing Pipe
334 -SQ1
I stallation- of caffier- Pi
33 05 26
Utility Markers/Locators
33- S40
3344-49
T48610 1FOR APO
l;vji
3-3 11 li , Steel Cyliador-:]�zp@
33 11 !1
93 1! it :'
33 Q 1-'_
!ALT AVat�
334-2-40
Resilient
334-2--2'_
33-Q 5
Oenneetien to Existing Watef Mains
3334
334-2-4fl
33 i2 50
344-2-60
Blew effValves
F:
33 31-12
is 21 11
-uXPE Pipe Fie; Sanitary Sewers (Gr-a;,43, and Force Mainol
33 31 20
Polyvinyl Chloride (PVC) Gravity Sanitary Sewer Pipe
33 31 21
Polyvinyl Chloride (PVC) Closed Arnfln Grayit3z Sanitary Sewer- Dire
3334,19
sir E>ip 1rr-4f+g
33-34-2-3
E
3331 50
Sanitary Sewer Service Connections and Service Line
3331 70
Combination A ir. Valve- fir Frnitfv
3339 10
Cast -in -Place Concrete Manholes
33 39 20
Precast Concrete Manholes
39--W40
Fiber -glass
33-39-49
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 101901
Revised September 1, 2015
0000 10-4
PROJECT RECORD DOCUMENTS FOR DEVELOPER AWARDEDPROJECTS
1 3449-b0
2 3.3-4 9 R
Page 4 of 4
3
33-4::1.
11PP9 Steffe Sewer- Pipe
4
33 A4-W
fi. AFft ge
5
33-46-01
0
6
34-46-02
Trenelr XR ifts
7
33-49 19
Cast in Plaee Manholes junetiea B&ies
and
8
33 49-20
✓xk rat? Pfep4ff1ets
9
33-49-40
f%,
10
11 Division 34 —Transportation
12 94 41 10
13
14 94-44 0 Roadway 111%fn4ia4ieff Assemblies
15 34-44--30 Aluminum Signs
16 3471 13 Traffic Control
17
18 Appendix
i 9 GG 01
23
GC-&". P
24
GE-6.0
25
GE-6 W-
26
GG-6:31
27
GR-01 60 00
28
29
Availability efbands
Subsuffeee and PhysieM Conditions
tir.AeFp&und-asili 4s
Hx
WageRttes
P
rl
Product Requirements
END OF SECTION
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS —DEVELOPER AWARDED PROJECTS CPN 101901
Revised September 1, 2015
i
FM
-10
r+r
w
rr
11111111
1"
0042 43
BID PROPOSAL
Page 1 of 1
SECTION 00 42 43
PROPOSAL FORM
UNIT PRICE BID
Bidder's Application
Project Item Information
Bidder's Proposal
id list Item
I Description
I Specification I
Unit of I
Bid
Unit Price
I Bid Value
o.
Section No.
Measure
Quantity
UNIT 1: Sanitary Sewer Improvements
1
3110.0101 Site Clearing
31 1000
LS
1
1 bW- 0L
� CL. DO Ij
2
3331.5310 8" PVC Sewer Pipe, 10' to 12' (Misc Only)
3331 20
LF
130
39. oo
rj(�r7(�, Do
3
3331.5307 8" PVC Sewer Pipe, 8'to 10' (Misc Only)
3331 20
LF
41
,31c -pD
1 ilqo, tip
4
3331.5304 8" PVC Sewer Pipe, 6' to 8' (Misc Only)
3331 20
LF
15
3(c, 01D
54o. pp
5
3331.3101 4" Sewer Service
3331 50
EA
3
)JW . OD
JD6 Sly, G
6
3331.3102 4" 2-Way Cleanout
3331 50
EA
3
1 S. m
525, w
7
3339,1001 4' Manhole
33 39 20
EA
1
W
.301:0.cs0
8
3339.1003 4' Extra Depth Manhole
33 39 20
VF
3
;-OD
(p1 S. 00
9
3305.0112 Concrete Collar Manhole Lid
3305 17
EA
1
10
3301,0101 Manhole Vacuum Testing
I
330130
EA
I
2
11L5L,()t�
S"j`j ✓
11
3201.0150 Asphalt Pvmt Repair, Sewer Service
32 01 17
LF
128
11 ,t7t7�(d
12
3301,0002 Post -CCTV Inspection
33 01 31
LF
186
1, 00
IAL�- LNO
13
3292.0100 Block Sod Placement
3292 13
SY ,
400
O
14
3291.0100 Topsoil
3291 19
CY
45
any
O
0
15
3305.0109 Trench Safety
3305 10
LF I
186
10. 110
1 0 0
16
0171.0101 Construction Stakinq
01 71 23
LS
1
O
1119too
O �K
17
0171.0102 As -Built Survey
01 71 23
LS
1
8
D
tIC
18
3471.0001 Traffic Control
3471 13
MO
1
0
19
3125,0101 Erosion Control
31 2500
LS
1
O
O
Subtotal Wastewater Improvements
I
1
Contingency
11.7%
Total Wastewater Improvements
I
„
I a,39j e. oo
BIDDER: -YM �n"0i� S2t Chi
�gnature)
TITLE: V \ cjLWe A 0i YN }-
DATE: \12-2-1I`t
END OF SECTION
` �( �G 7 G" r '�1 'M"t � /h eTv+r tl-f C �✓ 7jC r� t L I f((+/vw 1
AJ' Gv`St dliG/ INCI�1N ( T� U /'O
CITY OF FORT WORTH
i1111111110 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Fomi Revised 20120120 004100_004313_004243_004337_004512_003513_Bid Proposal Workbook.xls
0045 12
DAP PREQUALIFICATION STATEMENT
Page 1 of I
i SECTION 00 45 12
DAP — PREQUALIFICATION STATEMENT
Each Bidder is required to complete the information below by identifying the prequalified contractors
and/or subcontractors whom they intend to utilize for the major work type(s) listed. In the "Maior Work
Tvne" box provide the complete maior work tvpe and actual description as provided by the Water
Department for water and sewer and TPW for pavina.
Major Work Type Contractor/Subcontractor Company Name Prequalification
Expiration Date
uy&vvw-j h1 oonsvuettbn Se "iI em 04/ 3a/ZO) a
t_
MN
ti
The undersigned hereby certifies that the contractors and/or subcontractors described in the table above
are currently prequalified lfor the work hypes listed.
BIDDER:` y-0 fh J l�Yl� I► vlJ��bn ea'� ��'.2Q
BY: ilkkav�
�igniature�)
TITLE:Q k tt VyvQ 1&An %
DATE: P,ll 9
i
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION PREQUALIFICATION STATEMENT— DEVELOPER AWARDED PROJECTS Contract Book.doex
rl Form Version September 1, 2015
01 78 39 - 1
PROJECT RECORD DOCUMENTS
Page 1 of 1
SECTION 00 45 26
-- CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSATION LAW
Pursuant to Texas Labor Code Section 406.096(a), as amended, Contractor certifies that it provides
worker's compensation insurance coverage for all of its employees employed on City Project No. 101487.
Contractor further certifies that, pursuant to Texas Labor Code, Section 406.096(b), as amended, it will
provide to City its subcontractor's certificates of compliance with worker's compensation coverage.
CONTRACTOR:
em 0 15 lY utYb l I y: V . wo &t, #16 I -
Comp y (Please Print)
..0?34 F • IF ll i&)n 9 G Signature:
Address
UY 6no Title: _qjry— PYI!A ICat A+
City/State/Zip (Please Print)
THE STATE OF TEXAS §
COUNTY OF TARRANT §
BEFORE ME, the undersigned authority, on this day personally appeared
T l ra& ffl G ►d . known to me to be the person whose name is subscribed to
the fore ing instrument, pa�n�d� acknowledged tome that he/she executed the same as the act and deed of
n Xt Y, C" for the purposes and consideration therein expressed and in
th capacity therein stated.
GIVEN UNDER MY HAND AND SEAL OF OFFICE this ��r.4 day of
'IUnUc1ry .209.
U
rP�BGINGER FRANKLINMY COMMISSION EXPIRES 10/28/2021 Notary P lic in and for the State of Texas
OF
NOTARY ID: 1296086" -
14
END OF SECTION
i
CITY OF FORT WORTH Milatn Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS CPN 101901
Revised April 2, 2014
bob
4M
M
w,
mm
i
Oft
00 52 43 - 1
Developer Awarded Project Agreement
Page 1 of 4
l SECTION 00 52 43
2 AGREEMENT
3 [Text in Blue is for information or guidance. Remove all blue text in the project final document.]
4 THIS AGREEMENT, authorized on —is made by and between the Developer, The Peak Group, authorized
to d business in Texas ("Developer"), and
5 to n authorized to do business
6 in Texas, a tin by and through its duly authorized representative, ("Contractor").
7 Developer and Contractor, in consideration of the mutual covenants hereinafter set forth, agree as follows:
8 Article 1. WORK
9 Contractor shall complete all Work as specified or indicated in the Contract Documents for the Project
10 identified herein.
I Article 2. PROJECT
12 The project for which the Work under the Contract Documents may be the whole or only a part is
13 generally described as follows:
14 Milam Street Sanitary Sewer Extension
15 CPN 101901
16 Article 3. CONTRACT TIME
17 3.1 Time is of the essence.
18 All time limits for Milestones, if any, and Final Acceptance as stated in the Contract Documents are
19 of the essence to this Contract.
20 3.2 Final Acceptance.
21 The Work will be complete for Final Acceptance within 30 calendar days <ensure the days
22 shown match the days shown in the Proposal> after the date when the Contract Time commences
23 to run as provided in Paragraph 2.04 of the Standard City Conditions of the Construction Contract
24 for Developer Awarded Projects.
25 3.3 Liquidated damages
26 Contractor recognizes that time is of the essence of this Agreement and that Developer will suffer
27 financial loss if the Work is not completed within the times specified in Paragraph-3.2 above, plus
28 any extension thereof allowed in accordance with Article 10 of the Standard City Conditions of the
29 Construction Contract for Developer Awarded Projects. The Contractor also recognizes the delays,
30 expense and difficulties involved in proving in a legal proceeding the actual loss suffered by the
31 Developer if the Work is not completed on time. Accordingly, instead of requiring any such proof,
32 Contractor agrees that as liquidated damages for delay (but not as a penalty), Contractor shall pay
33 Developer <Insert amount in written words> Dollars ($X.XXX.XX) for each day that expires after
34 the time specified in Paragraph 3.2 for Final Acceptance until the City issues the Final Letter of
35 Acceptance.
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 101901
Revised April 2, 2014
wo
1W*
Oft
Rr r
i
MP
M
M
005243-2
Developer Awarded Project Agreement
Page 2 of 4
1 Article 4. CONTRACT PRICE
2 Developer agrees to pay Contractor for performance of the Work in accordance wi h the Contract
3 Documents an amount in current funds oAO h.1j A)11PygAAVJ npwars
4 ($ Q 2) cl 19.60 �.
5 Article 5. CONTRACT DOCUMENTS
6 5.1 CONTENTS:
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
A. The Contract Documents which comprise the entire agreement between Developer and
Contractor concerning the Work consist of the following:
1. ThisAgreement.
2. Attachments to this Agreement:
a. Bid Form (As provided by Developer)
1) Proposal Form (DAP Version)
2) Prequalification Statement
3) State and Federal documents (project specific)
b. Insurance ACORD Form(s)
c. Payment Bond (DAP Version)
d. Performance Bond (DAP Version)
e. Maintenance Bond (DAP Version)
f. Power of Attorney for the Bonds
g. Worker's Compensation Affidavit
h. MBE and/or SBE Commitment Form (If required)
3. Standard City General Conditions of the Construction Contract for Developer Awarded
Projects.
4. Supplementary Conditions.
5. Specifications specifically made a part of the Contract Documents by attachment or, if not
attached, as incorporated by reference and described in the Table of Contents of the
Project's Contract Documents.
6. Drawings.
7. Addenda.
8. Documentation submitted by Contractor prior to Notice ofAward.
9. The following which may be delivered or issued after the Effective Date of the Agreement
and, if issued, become an incorporated part of the Contract Documents:
a. Notice to Proceed.
b. Field Orders.
c. Change Orders.
d. Letter of Final Acceptance.
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 101901
Revised April 2, 2014
00 52 43 - 3
Developer Awarded Project Agreement
Page 3 of 4
Article 6. INDEMNIFICATION
2 6.1 Contractor covenants and agrees to indemnify, hold harmless and defend, at its own expense,
3 the city, its officers, servants and employees, from and against any and all claims arising out
4 of, or alleged to arise out of, the work and services to be performed by the contractor, its
5 officers, agents, employees, subcontractors, licenses or invitees under this contract. This
6 indemnification provision is sQecificallX intended to operate and be effective even if it is
7 alleged or proven that all or some of the damages being sought were caused. in whole or in
8 part. by any act. omission or negligence of the city. This indemnity provision is intended to
9 include, without limitation, indemnity for costs, expenses and legal fees incurred by the city in
10 defending against such claims and causes of actions.
11
12 6.2 Contractor covenants and agrees to indemnify and hold harmless, at its own expense, the city,
13 its officers, servants and employees, from and against any and all loss, damage or destruction
14 of property of the city, arising out of, or alleged to arise out of, the work and services to be
15 performed by the contractor, its officers, agents, employees, subcontractors, licensees or
16 invitees under this contract. This indemnification Qrovision is sQecifically intended to ollerate
17 and be effective even if it is alleged or nroven that all or some of the damages being sought
18 were caused, in whole or
19
20 Article 7. MISCELLANEOUS
21 7.1 Terms.
22
Terms used in this Agreement are defined in Article 1 of the Standard City Conditions of the
23
Construction Contract for Developer Awarded Projects.
24
7.2
Assignment of Contract.
25
This Agreement, including all of the Contract Documents may not be assigned by the Contractor
26
without the advanced express written consent of the Developer.
27
7.3
Successors and Assigns.
28
Developer and Contractor each binds itself, its partners, successors, assigns and legal
29
representatives to the other party hereto, in respect to all covenants, agreements and obligations
30
contained in the Contract Documents.
31
7.4
Severability.
32
Any provision or part of the Contract Documents held to be unconstitutional, void or unenforceable
33
by a court of competent jurisdiction shall be deemed stricken, and all remaining provisions shall
34
continue to be valid and binding upon DEVELOPER and CONTRACTOR.
35
7.5
Governing Law and Venue.
36
This Agreement, including all of the Contract Documents is performable in the State of Texas.
37
Venue shall be Tarrant County, Texas, or the United States District Court for the Northern District
38
of Texas, Fort Worth Division.
39
7.6
Authority to Sign.
40
Contractor shall attach evidence of authority to sign Agreement, if other than duly authorized
41
signatory of the Contractor.
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 101901
Revised April 2, 2014
M
i
PW
R
duo
i
ow
sm
mw
dM
W
005243-4
Developer Awarded Project Agreement
Page 4 of 4
1 IN WITNESS WHEREOF, Developer and Contractor have executed this Agreement in multiple
2 counterparts.
3
4 This Agreement is effective as of the last date signed by the Parties ("Effective Date").
5
Contractor: Devel per:
Bv: Bv:
(Signature) (Signature)
061 Y4
(Printed Name) (Printed Name)
Title: � �-ZAJXf Title: -t,44-,1`
Company Name: TYa?h J Cjn J j-ud�oki Company name:
Address:Address: -?e •. �� G
City/State/Zit):, Oa$
Date
Citv/State/Zin: 4-9 Al <:�-y " Z 6 l
Date
** CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 101901
Revised April 2, 2014
Bond No. 4424474
006125-1
PROJECT RECORD DOCUMENTS
Page 1 of 2
1 SECTION 00 62 13
2 PERFORMANCE BOND
3
4 THE STATE OF TEXAS §
5 § KNOW ALL BY THESE PRESENTS:
6 COUNTY OF TARRANT §
7 That we. Trophy Construction Services LLC , known as
8 "Principal". herein and SureTec Insurance Company a corporate
9 surety (sureties, if more than one) duly authorized to do business in the State of Texas, known as
10 "Surety" herein (whether one or more), are held and firmly bound unto the Developer, The
Peak Group, authorized to do business in Texas ("Developer") and the City of Fort Worth, a Texas
11 municippal corporation ("City"), in the penal sum of,
Twenty Three thousand nine hundred eighteen & No/100 23,918.00
12 Dollars (S ),
13 lawful money of the United States, to be paid in Fort Worth, Tarrant County, Texas for the
14 payment of which sum well and truly to be made jointly unto the Developer and the City as dual
15 obligees, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly
16 and severally, firmly by these presents.
17 WHEREAS, Developer and City have entered into an Agreement for the construction of
18 community facilities in the City of Fort Worth by and through a Community Facilities
19 Agreement, CFA Number CFA# 18-0177;and
20 WHEREAS, the Principal has entered into a certain written contract with the Developer
21 awarded the day of , 2018, which Contract is hereby referred to and
22 made a part hereof for all purposes as if fully set forth herein, to furnish all materials, equipment
23 labor and other accessories defined by law, in the prosecution of the Work, including any Change
24 Orders, as provided for in said Contract designated as Milam Street Sanitary Sewer Extension,
25 NOW, THEREFORE, the condition of this obligation is such that if the said Principal
26 shall faithfully perform it obligations under the Contract and shall in all respects duly and
27 faithfully perform the Work, including Change Orders, under the Contract, according to the plans,
28 specifications, and contract documents therein referred to, and as well during any period of
29 extension of the Contract that may be granted on the part of the Developer and/or City, then this
30 obligation shall be and become null and void, otherwise to remain in full force and effect.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised January 31, 2012
Milam Street Sangary Sewer Extension
CPN 101901
006125-2
PROJECT RECORD DOCUMENTS
Page 2 or2
I PROVIDED FURTHER, that if any legal action be filed on this Bond, venue shall lie in
_ 2 Tarrant County, Texas or the United States District Court for the Northern District of Texas, Fort
3 Worth Division.
4 This bond is made and executed in compliance with the provisions of Chapter 2253 of the
5 Texas Government Code, as amended;and all liabilities on this bond shall be determined in
6 accordance with the provisions of said statue.
7
8
9
10
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
IN WITNESS WHEREOF, the Principal and the Surety have SIGNED and SEALED
this instrument by duly authorized agents and officers on this the day of
January , 2019
ATTEST:
(Principal) cretary
Witness as to Frin tpal
4'��
Alba, EnaVlorado
Witness as eb Surety
PRINCIPAL:
Trophy Construction Services LLC
BY: —
Signature
a U) A, �&YA__Q P
Name and Title
Address: 236 E. Ellison St.
Burleson, TX 76028
SURETY:
SureTec Insurance Company
V
Signature
Patricia Ann Lyttle, Attorney -in -Fact
Name and Title
Address:1330 Post Oak Blvd., Suite 1100
Houston, TX 77056
Telephone Number: 713-812-0800
'Note: If signed by an officer of the Surety Company, there must be on file a certified extract
from the by-laws showing that this person has authority to sign such obligation. If
Surety's physical address is different from its mailing address, both must be provided.
The date of the bond shall not be prior to the date the Contract is awarded.
CITY OF FORT WORTH Milani Street Sanitary Sewer Extension
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS CPN 101"I
Revised January 31, 2012
Bond No. 442447
1
2
3
4 THE STATE OF TEXAS
5
6 COUNTY OF TARRANT
00 61 25 . 1
PROJECT RECORD DOCUMENTS
Page I of 2
SECTION 00 62 14
PAYMENT BOND
§ KNOW ALL BY THESE PRESENTS:
7 That we, Trophy Construction Services LLC known as
8 "Principal" herein, and SureTec Insurance Company
,a
9 corporate surety (or sureties if more than one), duly authorized to do business in the State of
10 Texas, known as "Surety" herein (whether one or more), are held and firmly bound unto the
l l Developer, The Peak Group, authorized to do business in Texas "(Developer"), and the City of
12 Fort Worth a Te><as mu ici al corpOjalto "City"), in the penal sum
Twenty three thousand nine hun�recpelghtee 1r ii� No%10t�
13 of Dollars ($ 23,918.00 �
14 lawful money of the United States, to be paid in Fort Worth, Tarrant County, Texas, for the
15 payment of which sum well and truly be made jointly unto the Developer and the City as dual
16 obligees, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly
17 and severally, firmly by these presents:
18 WHEREAS, Developer and City have entered into an Agreement for the construction of
19 community facilities in the City of Fort Worth, by and through a Community Facilities
20 Agreement, CFA Number CFA# 18-0177;and
21 WHEREAS, Principal has entered into a certain written Contract with Developer,
22 awarded the day of , 2018, which Contract is hereby referred
23 to and made a part hereof for all purposes as if fully set forth herein, to furnish all materials,
24 equipment, labor and other accessories as defined by law, in the prosecution of the Work as
25 provided for in said Contract and designated as Milam Street Sanitary Sewer Extension.
26 NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that if
27 Principal shall pay all monies owing to any (and all) payment bond beneficiary (as defined in
28 Chapter 2253 of the Texas Government Code, as amended) in the prosecution of the Work under
29 the Contract, then this obligation shall be and become null and void; otherwise to remain in full
30 force and effect.
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CITYCONDITIONS — DEVELOPER AWARDED PROJECTS CPN 1019D1
Revised January 31. 2012
00 61 25 - 2
PROJECT RECORD DOCUMENTS
Page 2 of 2
1 This bond is made and executed in compliance with the provisions of Chapter 2253 of the
_ 2 Texas Government Code, as amended, and all liabilities on this bond shall be determined in
3 accordance with the provisions of said statute.
4 IN WITNESS WHEREOF, the Principal and Surety have each SIGNED and SEALED
5 this instrument by duly authorized agents and officers on this the day of
` 6 January 2019
W
7
ATTEST:
���LAU ACA
(Nrincipal) ecretary
1P
Witness as to Principal
ATTEST:
(Surety) UN Ivia 151azar
Witness. tqSurety
Alba E'nardorado
8
PRINCIPAL:
Trophy Construction Services LLC
BY:
Signature
Name and Title
Address: 236 E. Ellison St.
Burleson, TX 76028
SURETY:
SureTec Insurance Company
Signature
Patricia Ann Lyttle, Attomey-in-Fact
Name and Title
Address: 1330 Post Oak Blvd., Suite 1100
Houston, TX 77056
Telephone Number: 713-812-0800
9 Note: If signed by an officer of the Surety, there must be on file a certified extract from the
10 bylaws showing that this person has authority to sign such obligation. If Surety's physical
1 l address is different from its mailing address, both must be provided.
12
13 The date of the bond shall not be prior to the date the Contract is awarded.
14 END OF SECTION
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS CPN 101901
Revised ]anuary 31, 2012
Bond No. 4424474
00 61 25. 1
PROJECT RECORD DOCUMENTS
Page 1 or 3
1 SECTION 00 62 19
2 MAINTENANCE BOND
3
4 THE STATE OF TEXAS §
5 § KNOW ALL BY THESE PRESENTS:
6 COUNTY OF TARRANT §
7 [Text in Blue is for information or guidance. Ren►ove all blue text in the project final document]
8 That we Trophy Construction Services LLC , known as
9 "Principal" herein and SureTec Insurance Company a corporate surety
10 (sureties, if more than one) duly authorized to do business in the State of Texas, known as
I 1 "Surety" herein (whether one or more), are held and firmly bound unto the Developer, The
Peak Group, authorized to do business in Texas ("Developer") and the City of Fort Worth, a Texas
12 municipal corporation ("City"), in the sum of Twenty three thousand nine hundred eighteen & No/100
13 Dollars ($ 23,918.00 ), lawful money of the United States, to be paid in Fort
14 Worth, Tarrant County, Texas, for payment of which suln well and truly be made jointly unto the
15 Developer and the City as dual obligees and their successors, we bind ourselves, our heirs,
16 executors, administrators, successors and assigns, jointly and severally, firmly by these presents.
18
19 WHEREAS, Developer and City have entered into an Agreement for the construction of
20 community facilities in the City of Fort Worth by and through a Community Facilities
21 Agreement, CFA Number CFAi118-0177; and
22 WHEREAS, the Principal has entered into a certain written contract with the Developer
23 awarded the day of , 20_, which Contract is
24 hereby referred to and a made part hereof for all purposes as if fully set forth herein, to furnish all
25 materials, equipment labor and other accessories as defined by law, in the prosecution of the
26 Work, including any Work resulting from a duly authorized Change Order (collectively herein,
27 the "Work") as provided for in said Contract and designated as Milam Street Sanitary Sewer Extension;
and
_"M
30 WHEREAS, Principal binds itself to use such materials and to so construct the Work in
31 accordance with the plans, specifications and Contract Documents that the Work is and will
32 remain free from defects in materials or workmanship for and during the period of two (2) years
33. after the date of Final Acceptance of the Work by the City ("Maintenance Period"); and
34
CRY OF FORT WORTH Milam Street Sanitary Sewer Extension
so STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS CPN 101901
Revised January 31, 2012
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
006123-2
PROJECT RECORD DOCUMENTS
Page 2 or 3
WHEREAS, Principal binds itself to repair or reconstruct the Work in whole or in pall
upon receiving notice from the Developer and/or City of the need thereof at any time within the
Maintenance Period.
NOW THEREFORE, the condition of this obligation is such that if Principal shall
remedy any defective Work, for which timely notice was provided by Developer or City, to a
completion satisfactory to the City, then this obligation shall become null and void; otherwise to
remain in full force and effect.
PROVIDED, HOWEVER, if Principal shall fail so to repair or reconstruct any timely
noticed defective Work, it is agreed that the Developer or City may cause any and all such
defective Work to be repaired and/or reconstructed with all associated costs thereof being borne
by the Principal and the Surety under this Maintenance Bond; and
PROVIDED FURTHER, that if any legal action be filed on this Bond, venue shall lie in
Tarrant County, Texas or the United States District Court for the Northern District of Texas, Fort
Worth Division; and
PROVIDED FURTHER, that this obligation shall be continuous in nature and
successive recoveries may be had hereon for successive breaches.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised January 31, 2012
Milam Street Sanitary Sewer Extension
CPN 101901
tea
00 6125 - 3
PROJECT RECORD DOCUMENTS
Page 3 of 3
l IN WITNESS WHEREOF, the Principal and the Surety have each SIGNED and
2 SEALED this instrument by duly authorized agents and officers on this the day of
3 January , 2019
4
5
6
8
10
IL
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
ATTEST:
(Principal) creta
Witness as to Pr�nc$al
PRINCIPAL:
Trophy Construction Services LLC
BY: /_ -�
Signature
Name and Title
Address: 236 E. Ellison St.
Burleson, TX 76028
SURETY:
SureTec Insurance Company
�gnature
Patricia Ann Lyttle, Attorney -in -Fact
ATTEST: Name and Title
Address:1330 Post Oak Blvd., Suite 1100
Elvin Salazar
(Surety) TvVif Houston, TX 77056
Witness as to urety Telephone Number: 713-812-0800
Alba Ena rado
If signed by an officer of the Surety Company, there must be on file a certified extract
from the by-laws showing that this person has authority to sign such obligation. If
Surety's physical address is different from its mailing address, both must be provided.
The date of the bond shall not be prior to the date the Contract is awarded.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS - DEVELOPER AWARDED PROJECTS
Revised January 31, 2012
Milam Street Seniory Sewer Extension
CPN 101901
FOAM 4221767
SureTec Insurance Company
LIMITED POWER OF ATTORNEY
Know All Men by These Presents, That SURETEC INSURANCE COMPANY (the "Company"), a corporation duly organized and
existing under the laws of the State of Texas, and having its principal office in Houston, Harris County, Texas, does by these presents
r` make, constitute and appoint
Bryan K. Moore, Gary W. Wheatley, Betty J. Reeh, Michael D. Hendrickson, Patricia Ann Lyttle
its true and lawful Attomey-in-fact, with full power and authority hereby conferred in its name, place and stead, to execute, acknowledge
and deliver any and all bonds, recognizances, undertakings or other instruments or contracts of suretyship to include waivers to the
conditions of contracts and consents of surety for, providing the bond penalty does not exceed
Fifteen Million and 00/100 Dollars ($15,000,000.00)
and to bind the Company thereby as fully and to the same extent as if such bond were signed by the President, sealed with the corporate
seal of the Company and duly attested by its Secretary, hereby ratifying and confirming all that the said Attomey-in-Fact may do in the
premises. Said appointment shall continue in force until 12131/2019 and is made under and.by authority of the following
" resolutions of the Board of Directors of the SureTec Insurance Company:
Be it Resolved that the President, any Vice -President, any Assistant Vice -President, any Secretary or any Assistant Secretary shall be and is
hereby vested with full power and authority to appoint any one or more suitable persons as Attomey(s)-in-Fact to represent and act for and on
behalf of the Company subject to the following provisions:
ON Attorney -in -Fact may be given full power and authority for and in the name of and of behalf of the Company, to execute, acknowledge and
deliver, any and all bonds, recognizances, contracts, agreements or indemnity and other conditional or obligatory undertakings and any and all
notices and documents canceling or terminating the Company's liability thereunder, and any such instruments so executed by any such
Attomey-in-Fact shall be binding upon the Company as if signed by the President and sealed and effected by the Corporate Secretary.
WIN Be it Resolved, that the signature of any authorized officer and seal of the Company heretofore or hereafter affixed to any power of attorney or
any certificate relating thereto by facsimile, and any power of attorney or certificate bearing facsimile signature or facsimile seal shall be valid
and binding upon the Company with respect to any bond or undertaking to which it is attached. (Adopted at a meeting held on 2e of April,
1999.)
In Witness Whereof, SURETEC INSURANCE COMPANY has caused these presents to be signed by its President, and its corporate seal
to be hereto affixed this 17th day of January , A.D. 2017 .
,tlpNIN1YIN�N SURETEC 7.,+re
ANY
� \aSVRA/ypF�
By:
w' W f D' John Knt
State of Texas ss: 7� ti .1
County of Harris '•••••-•••••
IYIM � n�M�
On this 17th day of January, A.D. 2017 before me personally came John Knox Jr., to me known, who, being by me duly sworn, did depose and say, that
he resides in Houston, Texas, that he is President of SURETEC INSURANCE COMPANY, the company described in and which executed the above
MP instrument; that he knows the seal of said Company; that the seal affixed to said instrument is such corporate seal; that it was so affixed by order of the
Board of Directors of said Company; and that he signed his name thereto by like order.
XENIA CHAVEZ
f� _Notary Public, State of TexasAlia
+mac Comm. Expires 09-10-2020°;,`Notary ID 129117659vez, Notary Public
_._._._____„o_..ssion expires September 10, 2020
I, M. Brent Beaty, Assistant Secretary of SURETEC INSURANCE COMPANY, do hereby certify that the above and foregoing is a true and correct copy
of a Power of Attorney, executed by said Company, which is still in full force and effect; and furthermore, the resolutions of the Board of Directors, set
out in the Power of Attorney are in full force and effect.
L �.} WBe1yy:Assisktant
Given under my hand and the seal of said Company at Houston, Texas thigx 7 , kdday C) A.D.
ry
M Any instrument issued in excess of the penalty stated above is totally void and without any validity.
For verification of the authority of this power you may call (713) 812-0800 any business day between 8:00 am and 5:00 pm CST.
SureTec Insurance Company
THIS BOND RIDER CONTAINS IMPORTANT COVERAGE INFORMATION
Statutory Complaint Notice
To obtain information or make a complaint: You may call the Surety's toll free telephone
number for information or to make a complaint at: 1-866-732-0099. You may also write to the
Surety at:
SureTec Insurance Company
9737 Great Hills Trail, Suite 320
Austin, Tx 78759
_ You may contact the Texas Department of Insurance to obtain information on companies,
coverage, rights or complaints at 1-800-252-3439. You may write the Texas Department of
Insurance at
PO Box 149104
Austin, TX 78714-9104
Fax#: 512-475-1771
PREMIUM OR CLAIM DISPUTES: Should you have a dispute concerning your premium or
about a claim, you should contact the Surety first. If the dispute is not resolved, you may
contact the Texas Department of Insurance.
Terrorism Risks Exclusion
The Bond to which this Rider is attached does not provide coverage for, and the surety shall
= not be liable for, losses caused by acts of terrorism, riot, civil insurrection, or acts of war.
Exclusion of Liability for
Mold, Mycotoxins, Fungi & Environmental Hazards
The Bond to which this Rider is attached does not provide coverage for, and the surety
= thereon shall not be liable for, molds, living or dead fungi, bacteria, allergens, histamines,
spores, hyphae, or mycotoxins, or their related products or parts, nor for any environmental
hazards, bio-hazards, hazardous materials, environmental spills, contamination, or cleanup,
nor the remediation thereof, nor the consequences to persons, property, or the performance
of the bonded obligations, of the occurrence, existence, or appearance thereof.
y
Texas Rider 010106
MP
On
am
ud
do
no
M
W.
wh
PEP
.W
W
STANDARD CITY CONDITIONS OF
THE CONSTRUCTION CONTRACT
FOR DEVELOPER AWARDED PROJECTS
CITY OF FORT WORTH Milam Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects CPN 101901
Revised December 20, 2012
on
ON
M"
i
i
mo
am
OW
STANDARD CITY CONDITIONS OF THE
CONSTRUCTION CONTRACT
FOR DEVELOPER AWARDED PROJECTS
TABLE OF CONTENTS
Page
Article 1 — Definitions and Terminology................................................................................................................ I
DefinedTerms........................................................................................................................................I
Terminology........................................................................................................................................ 5
Article2 —Preliminary Matters............................................................................................................................5
2.1 Before Starting Construction........................................................................................................... 5
2.2 Preconstruction Conference............................................................................................................. 6
2.3 Public Meeting................................................................................................................................. 6
Article 3 — Contract Documents and Amending................................................................................................. 6
3.1 Reference Standards........................................................................................................................ 6
3.2 Amending and Supplementing Contract Documents..................................................................... 6
Article4 — Bonds and Insurance........................................................................................................................... 6
4.1 Licensed Sureties and Insurers........................................................................................................ 6
4.2 Performance, Payment, and Maintenance Bonds........................................................................... 7
4.3 Certificates of Insurance.................................................................................................................. 7
4.4 Contractor's Insurance..................................................................................................................... 9
4.5 Acceptance of Bonds and Insurance; Option to Replace ............................... 12
..............................
Article 5 —Contractor's Responsibilities............................................................................................................12
5.1
Supervision and Superintendent....................................................................................................12
5.2
Labor; Working Hours...................................................................................................................13
5.3
Services, Materials, and Equipment.............................................................................................13
5.4
Project Schedule.............................................................................................................................14
5.5
Substitutes and "Or-Equals"..........................................................................................................14
5.6
Pre -Qualification of Bidders (Prime Contractors and Subcontractors).......................................16
5.7
Concerning Subcontractors, Suppliers, and Others......................................................................16
5.8
Wage Rates.....................................................................................................................................18
5.9
Patent Fees and Royalties..............................................................................................................19
5.10
Laws and Regulations....................................................................................................................19
5.11
Use of Site and Other Areas ..........................................................................................................19
5.12
Record Documents.........................................................................................................................20
5.13
Safety and Protection.....................................................................................................................
21
5.14
Safety Representative.....................................................................................................................
22
5.15
Hazard Communication Programs................................................................................................22
5.16
Submittals.......................................................................................................................................22
5.17
Contractor's General Warranty and Guarantee.............................................................................23
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects 101901
Revised December 20, 2012
5.18 Indemnification.............................................................................................................................. 24
5.19 Delegation of Professional Design Services.................................................................................24
5.20 Right to Audit.................................................................................................................................25
5.21 Nondiscrimination..........................................................................................................................26
Article6 - Other Work atthe Site.............................................................................................................. 26
6.01 Related Work at Site.............................................................................................................. 26
Article 7 -City's Responsibilities.....................................................................................................................26
7.1 Inspections, Tests, and Approvals.................................................................................................26
7.2 Limitations on City's Responsibilities..........................................................................................27
7.3 Compliance with Safety Program.................................................................................................27
Article 8 - City's Observation Status During Construction.............................................................................. 27
8.1 City's Project Representative.........................................................................................................27
8.2 Authorized Variations in Work.............................................................................................. 27
'^ 8.3 Rejecting Defective Work...................................................................................................... 28
8.4 Determinations for Work Performed............................................................................................28
Article9 - Changes in the Work................................................................................................................ 28
9.1 Authorized Changes in the Work........................................................................................... 28
9.2 Notification to Surety....................................................................................................................28
Article 10 - Change of Contract Price; Change of Contract Time ............................................... ...............28
10.1 Change of Contract Price............................................................................................................... 28
10.2 Change of Contract Time..............................................................................................................29
10.3 Delays.............................................................................................................................................29
Article I I - Tests and Inspections; Correction, Removal or Acceptance of Defective Work ....................... 29
11.1 Notice of Defects...........................................................................................................................29
11.2 Access to Work..............................................................................................................................29
11.3 Tests and Inspections..................................................................................................................... 29
11.4 Uncovering Work.................................................................................................................. 30
11.5 City May Stop the Work........................................................................................................ 30
11.6 Correction or Removal ofDefective Work............................................................................. 30
11.7 Correction Period........................................................................................................................... 31
11.8 City May Correct Defective Work......................................................................................... 32
Article12 - Completion.....................................................................................................................................32
12.1 Contractor's Warranty of Title...................................................................................................... 32
12.2 Partial Utilization...........................................................................................................................32
12.3 Final Inspection..............................................................................................................................33
..' 12.4 Final Acceptance............................................................................................................................33
Article13 - Suspension of Work................................................................................................................ 34
13.01 City May Suspend Work........................................................................................................ 34
Article14 - Miscellaneous.................................................................................................................................34
14.1 Giving Notice................................................................................................................................. 34
14.2 Computation of Times...................................................................................................................35
14.3 Cumulative Remedies....................................................................................................................35
14.4 Survival of Obligations..................................................................................................................35
14.5 Headings.........................................................................................................................................35
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - Developer Awarded Projects 101901
Revised December 20, 2012
0073 10- 1
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page I of 35
ARTICLE 1— DEFINITIONS AND TERMINOLOGY
1.1 Defined Terms
A. Wherever used in these General Conditions or in other Contract Documents, the terms listed below
have the meanings indicated which are applicable to both the singular and plural thereof, and words
denoting gender shall include the masculine, feminine and neuter. Said terms are generally
capitalized or written in italics, but not always. When used in a context consistent with the
definition of a listed -defined term, the term shall have a meaning as defined below whether
capitalized or italicized or otherwise. In addition to terms specifically defined, terms with initial
capital letters in the Contract Documents include references to identified articles and paragraphs,
and the titles of other documents or forms.
1. Agreement - The written instrument which is evidence of the agreement between Developer
and Contractor covering the Work
2. Asbestos - Any material that contains more than one percent asbestos and is friable or is
releasing asbestos fibers into the air above current action levels established by the United States
-" Occupational Safety and Health Administration.
3. Business Day - A business day is defined as a day that the City conducts normal business,
generally Monday through Friday, except for federal or state holidays observed by the City.
— 4. Buzzsaw - City's on-line, electronic document management and collaborationsystem.
5. Calendar Day - A day consisting of 24 hours measured from midnight to the next midnight.
6. City - The City of Fort Worth, Texas, a Texas home -rule municipal corporation, acting by, its
governing body through its City Manager, his designee, or agents authorized pursuant to its
duly authorized charter on his behalf.
7. Community Facilities Agreement (CFA) - A Contract between the Developer and the City for
the Construction of one or more following public facilities within the City public right -of- way
or easement: Water, Sanitary Sewer, Street, Storm Drain, Street Light, and Street Signs. A CFA
may include private facilities within the right-of-way dedicated as private right- of- way or
T easement on a recorded plat.
8. Contract - The entire and integrated written document incorporating the Contract Documents
between the Developer, Contractor, and/or City concerning the Work. The Contract supersedes
prior negotiations, representations, or agreements, whether written or oral.
9. Contract Documents - Those items that make up the contract and which must include the
Agreement, and its attachments such as standard construction specifications, standard City
Conditions, other general conditions of the Developer, including:
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects 101901
Revised December 20, 2012
00 73 10- 2
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 2 of 35
a. An Agreement
b. Attachments to the Agreement
i. Bid Form
ii. Vendor Compliance with State Law Non -Resident Bidder
iii. Prequalification Statement
C. Current Prevailing Wage Rates Table (if required by City)
d. Insurance Accord Form
e. Payment Bond
f. Performance Bond
g. Maintenance Bond
h. Power of Attorney for Bonds
i. Workers Compensation Affidavit
j. MWBE Commitment Form (If required by City)
k. General Conditions
1. Supplementary Conditions
M. The Standard City Conditions
n. Specifications specifically made part of the Contract Documents by attachment, if not
attached, as incorporated by reference and described in the Table of Contents of the
Project's Contract Documents
o. Drawings
P. Documentation submitted by contractor prior to Notice of Award.
q. The following which may be delivered or issued after the effective date if the
Agreement and, if issued become an incorporated part of the Contract Documents
i. Notice to Proceed
ii. Field Orders
iii. Change Orders
iv. Letters of Final Acceptance
r. Approved Submittals, other Contractor submittals, and the reports and drawings of
subsurface and physical conditions are not Contract Documents.
10. Contractor - The individual or entity with whom Developer has entered into the Agreement.
11. Day or day - A day, unless otherwise defined, shall mean a Calendar Day.
12. Developer - An individual or entity that desires to make certain improvements within the City
of Fort Worth
13. Drawings - That part of the Contract Documents prepared or approved by Engineer which
graphically shows the scope, extent, and character of the Work to be performed by Contractor.
Submittals are not Drawings as so defined.
14. Engineer - The licensed professional engineer or engineering firm registered in the State of
Texas performing professional services for the Developer.
15. Final Acceptance — The written notice given by the City to the Developer and/or Contractor
that the Work specified in the Contract Documents has been completed to the satisfaction of
the City.
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects 101901
Revised December 20, 2012
00 73 10- 3
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 3 of 35
16. Final Inspection — Inspection carried out by the City to verify that the Contractor has
completed the Work, and each and every part or appurtenance thereof, fully, entirely, and in
conformance with the Contract Documents.
17. General Requirements - A part of the Contract Documents between the Developer and a
Contractor.
18. Laws and Regulations - Any and all applicable laws, rules, regulations, ordinances, codes, and
orders of any and all governmental bodies, agencies, authorities, and courts having jurisdiction.
19. Liens - Charges, security interests, or encumbrances upon Project funds, real property, or
personal property.
20. Milestone - A principal event specified in the Contract Documents relating to an intermediate
Contract Time prior to Final Acceptance of the Work.
21. Non -Participating Change Order - A document, which is prepared for and reviewed by the
City, which is signed by Contractor, and Developer, and authorizes an addition, deletion, or
revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on or
after the Effective Date of the Agreement.
_ 22. Participating Change Order - A document, which is prepared for and approved by the City,
which is signed by Contractor, Developer, and City and authorizes an addition, deletion, or
revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on or
after the Effective Date of the Agreement.
23. Plans — See definition of Drawings.
24. Project Schedule - A schedule, prepared and maintained by Contractor, in accordance with the
General Requirements, describing the sequence and duration of the activities comprising the
Contractor's plan to accomplish the Work within the Contract Time.
25. Project - The Work to be performed under the Contract Documents.
26. Project Representative - The authorized representative of the City who will be assigned to the
Site.
27. Public Meeting — An announced meeting conducted by the Developer to facilitate public
participation and to assist the public in gaining an informed view of the Project.
28. Regular Working Hours — Hours beginning at 7:00 a.m. and ending at 6:00 p.m., Monday thru
Friday (excluding legal holidays).
29. Samples - Physical examples of materials, equipment, or workmanship that are representative
of some portion of the Work and which establish the standards by which such portion of the
Work will be judged.
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects 101901
Revised December 20, 2012
00 7310- 4
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 4 of 35
30. Schedule of Submittals - A schedule, prepared and maintained by Contractor, of required
submittals and the time requirements to support scheduled performance of related construction
activities.
31. Site - Lands or areas indicated in the Contract Documents as being filrnished by City or
Developer upon which the Work is to be performed, including rights -of -way, permits, and
easements for access thereto, and such other lands furnished by City or Developer which are
_. designated for the use ofContractor.
32. Specifications - That part of the Contract Documents consisting of written requirements for
materials, equipment, systems, standards and workmanship as applied to the Work, and certain
administrative requirements and procedural matters applicable thereto. Specifications may be
specifically made a part of the Contract Documents by attachment or, if not attached, may be
incorporated by reference as indicated in the Table of Contents (Division 00 00 00) of each
Project.
33. Standard City Conditions — That part of the Contract Documents setting forth requirements of
the City.
34. Subcontractor - An individual or entity having a direct contract with Contractor or with any
other Subcontractor for the performance of a part of the Work at the Site.
35. Submittals - All drawings, diagrams, illustrations, schedules, and other data or information
which are specifically prepared or assembled by or for Contractor and submitted by Contractor
to illustrate some portion of the Work.
36. Superintendent — The representative of the Contractor who is available at all times and able to
receive instructions from the City and/or Developer and to act for the Contractor.
37. Supplementary Conditions - That part of the Contract Documents which amends or
supplements the General Conditions.
38. Supplier - A manufacturer, fabricator, supplier, distributor, materialman, or vendor having a
direct contract with Contractor or with any Subcontractor to furnish materials or equipment to
be incorporated in the Work by Contractor or Subcontractor.
39. Underground Facilities - All underground pipelines, conduits, ducts, cables, wires, manholes,
vaults, tanks, tunnels, or other such facilities or attachments, and any encasements containing
such facilities, including but not limited to, those that convey electricity, gases, steam, liquid
petroleum products, telephone or other communications, cable television, water, wastewater,
storm water, other liquids or chemicals, or traffic or other control systems.
40. Weekend Working Hours — Hours beginning at 9:00 a.m. and ending at 5:00 p.m., Saturday,
Sunday or legal holiday, as approved in advance by the City.
41. Work - The entire construction or the various separately identifiable parts thereof required to
be provided under the Contract Documents. Work includes and is the result of performing
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS —Developer Awarded Projects 101901
Revised December 20, 2012
00 73 10- 5
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 5 of 35
or providing all labor, services, and documentation necessary to produce such construction
including any Participating Change Order, Non -Participating Change Order, or Field Order,
and furnishing, installing, and incorporating all materials and equipment into such
construction, all as required by the Contract Documents.
42. Working Day — A working day is defined as a day, not including Saturdays, Sundays, or legal
holidays authorized by the City for contract purposes, in which weather or other conditions not
under the control of the Contractor will permit the performance of the principal unit of work
underway for a continuous period of not less than 7 hours between 7
a.m. and 6 p.m.
1.2 Terminology
A. The words and terms discussed in Paragraph 1.02.B through D are not defined but, when used in
the Bidding Requirements or Contract Documents, have the indicated meaning.
B. Defective:
The word "defective," when modifying the word "Work," refers to Work that is
unsatisfactory, faulty, or deficient in that it:
a. does not conform to the Contract Documents; or
b. does not meet the requirements of any applicable inspection, reference standard, test, or
approval referred to in the Contract Documents; or
c. has been damaged prior to City's written acceptance.
C. Furnish, Install, Perform, Provide:
1. The word "Furnish" or the word "Install" or the word "Perform" or the word "Provide" or the
word "Supply," or any combination or similar directive or usage thereof, shall mean furnishing
and incorporating in the Work including all necessary labor, materials, equipment, and
everything necessary to perform the Work indicated, unless specifically limited in the context
used.
D. Unless stated otherwise in the Contract Documents, words or phrases that have a well-known
technical or construction industry or trade meaning are used in the Contract Documents in
accordance with such recognized meaning.
ARTICLE 2 — PRELIMINARY MATTERS
2.1 Before Starting Construction
Baseline Schedules: Submit to City in accordance with the Contract Documents, and prior to starting
the Work. New schedules will be submitted to City when Participating Change Orders or Non -
Participating Change Orders occur.
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS —Developer Awarded Projects 101901
Revised December 20, 2012
00 73 10- 6
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 6 of 35
2.2 Preconstruction Conference
Before any Work at the Site is started, the Contractor shall attend a Preconstruction Conference as
specified in the Contract Documents.
2.3 Public Meeting
Contractor may not mobilize any equipment, materials or resources to the Site prior to Contractor
attending the Public Meeting as scheduled by the City.
ARTICLE 3 — CONTRACT DOCUMENTS AND AMENDING
3.1 Reference Standards
A. Standards, Specifications, Codes, Laws, and Regulations
1. Reference to standards, specifications, manuals, or codes of any technical society, organization,
or association, or to Laws or Regulations, whether such reference be specific or by implication,
shall mean the standard, specification, manual, code, or Laws or Regulations in effect at the
time of opening of Bids (or on the Effective Date of the Agreement if there were no Bids),
except as may be otherwise specifically stated in the Contract Documents.
2. No provision or instruction shall be effective to assign to City, or any of its officers, directors,
members, partners, employees, agents, consultants, or subcontractors, any duty or authority to
supervise or direct the performance of the Work or any duty or authority to undertake
responsibility inconsistent with the provisions of the Contract Documents.
3.2 Amending and Supplementing Contract Documents
A. The Contract Documents may be amended to provide for additions, deletions, and revisions in the
Work or to modify the terms and conditions thereof by a Participating Change Order or a Non -
Participating Change Order.
B. The requirements of the Contract Documents may be supplemented, and minor variations and
deviations in the Work not involving a change in Contract Price or Contract Time, may be
authorized, by one or more of the following ways:
1. A Field Order;
2. City's or Engineer's review of a Submittal (subject to the provisions of Paragraph 5.16.C); or
3. City's written interpretation or clarification.
ARTICLE 4 — BONDS AND INSURANCE
4.1 Licensed Sureties and Insurers
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects 101901
Revised December 20, 2012
00 73 10- 7
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 7 of 35
All bonds and insurance required by the Contract Documents to be purchased and maintained by
Contractor shall be obtained from surety or insurance companies that are duly licensed or authorized
in the State of Texas to issue bonds or insurance policies for the limits and coverage so required. Such
surety and insurance companies shall also meet such additional requirements and qualifications as may
be provided Section4.04.
4.2 Performance, Payment, and Maintenance Bonds
A. Contractor shall furnish performance and payment bonds in the name of Developer and City, in
accordance with Texas Government Code Chapter 2253 or successor statute, each in an amount
equal to the Contract Price as security for the faithful performance and payment of all of
Contractor's obligations under the Contract Documents.
B. Contractor shall furnish maintenance bonds in the name of Developer and City in an amount equal
to the Contract Price as security to protect the City against any defects in any portion of the Work
described in the Contract Documents. Maintenance bonds shall remain in effect for two
s (2) years after the date of Final Acceptance by the City.
C. All bonds shall be in the form prescribed by the Contract Documents except as provided otherwise
by Laws or Regulations and shall be executed by such sureties as are named in the list of
"Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and as
Acceptable Reinsuring Companies" as published in Circular 570 (amended) by the Financial
Management Service, Surety Bond Branch, U.S. Department of the Treasury. All bonds signed by
an agent or attorney -in -fact must be accompanied by a sealed and dated power of attorney which
shall show that it is effective on the date the agent or attorney -in -fact signed each bond.
D. If the surety on any bond furnished by Contractor is declared bankrupt or becomes insolvent or its
right to do business is terminated in the State of Texas or it ceases to meet the requirements of
Paragraph 4.02.C, Contractor shall promptly notify City and shall, within 30 days after the event
giving rise to such notification, provide another bond and surety, both of which shall comply with
the requirements of Paragraphs 4.01 and 4.02.C.
4.3 Certificates of Insurance
Contractor shall deliver to Developer and City, with copies to each additional insured and loss payee
identified in these Standard City Conditions certificates of insurance (and other evidence of insurance
requested by City or any other additional insured) which Contractor is required to purchase and
maintain.
1. The certificate of insurance shall document the City, an as "Additional Insured" on all
liability policies.
2. The Contractor's general liability insurance shall include a, "per project" or `per location",
endorsement, which shall be identified in the certificate of insurance provided to the City.
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects 101901
Revised December 20, 2012
00 73 10- 8
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 8 of 35
3. The certificate shall be signed by an agent authorized to bind coverage on behalf of the insured,
be complete in its entirety, and show complete insurance carrier names as listed in the current
A.M. Best Property & CasualtyGuide
4. The insurers for all policies must be licensed and/or approved to do business in the State of
Texas. Except for workers' compensation, all insurers must have a minimum rating of A-: VII
in the current A. M. Best Key Rating Guide or have reasonably equivalent financial strength
and solvency to the satisfaction of Risk Management. If the rating is below that required,
written approval of City isrequired.
5. All applicable policies shall include a Waiver of Subrogation (Rights of Recovery) in favor of
the City. In addition, the Contractor agrees to waive all rights of subrogation against the
Engineer (if applicable), and each additional insured identified in these Standard City
Conditions. Failure of the City to demand such certificates or other evidence of full compliance
with the insurance requirements or failure of the City to identify a deficiency from evidence
that is provided shall not be construed as a waiver of Contractor's obligation to maintain such
lines of insurance coverage.
6. If insurance policies are not written for specified coverage limits, an Umbrella or Excess
Liability insurance for any differences is required. Excess Liability shall follow form of the
primary coverage.
7. Unless otherwise stated, all required insurance shall be written on the "occurrence basis". If
coverage is underwritten on a claims -made basis, the retroactive date shall be coincident with
or prior to the date of the effective date of the agreement and the certificate of insurance shall
state that the coverage is claims -made and the retroactive date. The insurance coverage shall
be maintained for the duration of the Contract and for three (3) years following Final
Acceptance provided under the Contract Documents or for the warranty period, whichever is
longer. An annual certificate of insurance submitted to the City shall evidence such insurance
coverage.
8. Policies shall have no exclusions by endorsements, which, neither nullify or amend, the
required lines of coverage, nor decrease the limits of said coverage unless such endorsements
are approved in writing by the City. In the event a Contract has been bid or executed and the
exclusions are determined to be unacceptable or the City desires additional insurance coverage,
and the City desires the contractor/engineer to obtain such coverage, the contract price shall be
adjusted by the cost of the premium for such additional coverage plus 10%.
9. Any self -insured retention (SIR), in excess of $25,000.00, affecting required insurance
coverage shall be approved by the City in regard to asset value and stockholders' equity. In lieu
of traditional insurance, alternative coverage maintained through insurance pools or risk
retention groups, must also be approved by City.
10. Any deductible in excess of $5,000.00, for any policy that does not provide coverage on a first -
dollar basis, must be acceptable to and approved by the City.
I
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects 101901
Revised December 20, 2012
00 73 10- 9
�. Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 9 of 35
11. City, at its sole discretion, reserves the right to review the insurance requirements and to make
reasonable adjustments to insurance coverage's and their limits when deemed necessary and
prudent by the City based upon changes in statutory law, court decision or the claims history
of the industry as well as of the contracting party to the City. The City shall be required to
provide prior notice of 90 days, and the insurance adjustments shall be incorporated into the
Work by Change Order.
12. City shall be entitled, upon written request and without expense, to receive copies of policies
and endorsements thereto and may make any reasonable requests for deletion or revision or
modifications of particular policy terms, conditions, limitations, or exclusions necessary to
conform the policy and endorsements to the requirements of the Contract. Deletions, revisions,
or modifications shall not be required where policy provisions are established by law or
regulations binding upon either party or the underwriter on any such policies.
13. City shall not be responsible for the direct payment of insurance premium costs for
Contractor's insurance.
4.4 Contractor's Insurance
A. Workers Compensation and Employers' Liability. Contractor shall purchase and maintain such
insurance coverage with limits consistent with statutory benefits outlined in the Texas Workers'
Compensation Act (Texas Labor Code, Ch. 406, as amended), and minimum limits for Employers'
Liability as is appropriate for the Work being performed and as will provide protection from claims
set forth below which may arise out of or result from Contractor's performance of the Work and
Contractor's other obligations under the Contract Documents, whether it is to be performed by
Contractor, any Subcontractor or Supplier, or by anyone directly or indirectly employed by any of
them to perform any of the Work, or by anyone for whose acts any of them may be liable:
1. claims under workers' compensation, disability benefits, and other similar employee benefit
acts;
2. claims for damages because of bodily injury, occupational sickness or disease, or death of
Contractor's employees.
3. The limits of liability for the insurance shall provide the following coverages for not less than
the following amounts or greater where required by Laws and Regulations
a. Statutory limits
b. Employer's liability
1) $100,000 each accident/occurrence
2) $100,000 Disease - each employee
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS —Developer Awarded Projects 101901
Revised December 20, 2012
00 7310-10
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 10 of 35
3) $500,000 Disease - policy limit
B. Commercial General Liability Coverage shall include but not be limited to covering liability
(bodily injury or property damage) arising from: premises/operations, independent contractors,
products/completed operations, personal injury, and liability under an insured contract. Insurance
shall be provided on an occurrence basis, and as comprehensive as the current Insurance Services
Office (ISO) policy. This insurance shall apply as primary insurance with respect to any other
insurance or self-insurance programs afforded to the City. The Commercial General Liability policy
shall have no exclusions by endorsements that would alter of nullify premises/operations,
products/completed operations, contractual, personal injury, or advertising injury, which are
normally contained with the policy, unless the City approves such exclusions in writing.
1. For construction projects that present a substantial completed operation exposure, the City may
require the contractor to maintain completed operations coverage for a minimum of no less than
three (3) years following the completion of the project
2. Contractor's Liability Insurance under this Section which shall be on a per project basis
covering the Contractor with minimum limitsof:
a. $1,000,000 each occurrence
b. $2,000,000 aggregate limit
3. The policy must have an endorsement (Amendment — Aggregate Limits of Insurance) making
the General Aggregate Limits apply separately to each job site.
4. The Commercial General Liability Insurance policies shall provide "X", "C", and "U"
coverage's. Verification of such coverage must be shown in the Remarks Article of the
Certificate of Insurance.
C. Automobile Liability. A commercial business auto policy shall provide coverage on "any auto",
defined as autos owned, hired and non -owned and provide indemnity for claims for damages
because bodily injury or death of any person and or property damage arising out of the work,
maintenance or use of any motor vehicle by the Contractor, any Subcontractor or Supplier, or by
anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone
for whose acts any of them may be liable.
1. Automobile Liability, Contractor's Liability Insurance under this Section, which shall be in an
amount not less than the following amounts:
a. Automobile Liability - a commercial business policy shall provide coverage on "Any
Auto", defined as autos owned, hired andnon-owned.
1) $1,000,000 each accident on a combined single limit basis. Split limits are
acceptable if limits are at least:
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects 101901
Revised December 20, 2012
00 73 10-11
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 11 of 35
2) $250,000 Bodily Injury per person
3) $500,000 Bodily Injury per accident /
4) $100,000 Property Damage
D. Railroad Protective Liability. If any of the work or any warranty work is within the limits of
railroad right-of-way, the Contractor shall comply with the following requirements:
1. The Contractor's construction activities will require its employees, agents, subcontractors,
equipment, and material deliveries to cross railroad properties and tracks owned and operated
by: none
2. The Contractor shall conduct its operations on railroad properties in such a manner as not to
interfere with, hinder, or obstruct the railroad company in any manner whatsoever in the use
or operation of its/their trains or other property. Such operations on railroad properties may
require that Contractor to execute a "Right of Entry Agreement" with the particular railroad
company or companies involved, and to this end the Contractor should satisfy itself as to the
requirements of each railroad company and be prepared to execute the right -of -entry (if any)
required by a railroad company. The requirements specified herein likewise relate to the
Contractor's use of private and/or construction access roads crossing said railroad company's
properties.
3. The Contractual Liability coverage required by Paragraph 5.04D of the General Conditions
shall provide coverage for not less than the following amounts, issued by companies
satisfactory to the City and to the Railroad Company for a term that continues for so long as
the Contractor's operations and work cross, occupy, or touch railroadproperty:
a. General Aggregate: none
b. Each Occurrence: none
4. With respect to the above outlined insurance requirements, the following shall govern:
a. Where a single railroad company is involved, the Contractor shall provide one insurance
policy in the name of the railroad company. However, if more than one grade separation
or at -grade crossing is affected by the Project at entirely separate locations on the line or
lines of the same railroad company, separate coverage may be required, each in the amount
stated above.
b. Where more than one railroad company is operating on the same right-of-way or where
several railroad companies are involved and operated on their own separate rights -of- way,
the Contractor may be required to provide separate insurance policies in the name of each
railroad company.
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects 101901
Revised December 20, 2012
w
00 7310-12
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 12 of 35
c. If, in addition to a grade separation or an at -grade crossing, other work or activity is
proposed on a railroad company's right-of-way at a location entirely separate from the
grade separation or at -grade crossing, insurance coverage for this work must be included
in the policy covering the grade separation.
d. If no grade separation is involved but other work is proposed on a railroad company's right-
of-way, all such other work may be covered in a single policy for that railroad, even though
the work may be at two or more separate locations.
5. No work or activities on a railroad company's property to be performed by the Contractor
shall be commenced until the Contractor has furnished the City with an original policy or
policies of the insurance for each railroad company named, as required above. All such
insurance must be approved by the City and each affected Railroad Company prior to the
Contractor's beginning work.
6. The insurance specified above must be carried until all Work to be performed on the railroad
right-of-way has been completed and the grade crossing, if any, is no longer used by the
Contractor. In addition, insurance must be carried during all maintenance and/or repair work
performed in the railroad right-of-way. Such insurance must name the railroad company as the
insured, together with any tenant or lessee of the railroad company operating over tracks
involved in the Project.
E. Notification of Policy Cancellation: Contractor shall immediately notify City upon cancellation or
other loss of insurance coverage. Contractor shall stop work until replacement insurance has been
procured. There shall be no time credit for days not worked pursuant to this section.
4.5 Acceptance of Bonds and Insurance; Option toReplace
If City has any objection to the coverage afforded by or other provisions of the bonds or insurance
required to be purchased and maintained by the Contractor in accordance with Article 5 on the basis
of non-conformance with the Contract Documents, the Developer and City shall so notify the
Contractor in writing within 10 Business Days after receipt of the certificates (or other evidence
requested). Contractor shall provide to the City such additional information in respect of insurance
provided as the Developer or City may reasonably request. If Contractor does not purchase or maintain
all of the bonds and insurance required by the Contract Documents, the Developer or City shall notify
the Contractor in writing of such failure prior to the start of the Work, or of such failure to maintain
prior to any change in the required coverage.
ARTICLE 5 — CONTRACTOR'S RESPONSIBILITIES
5.1 Supervision and Superintendent
A. Contractor shall supervise, inspect, and direct the Work competently and efficiently, devoting
such attention thereto and applying such skills and expertise as may be necessary to perform the
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects 101901
Revised December 20, 2012
00 7310-13
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 13 of 35
Work in accordance with the Contract Documents. Contractor shall be solely responsible for the
means, methods, techniques, sequences, and procedures of construction.
B. At all times during the progress of the Work, Contractor shall assign a competent, English-
speaking, Superintendent who shall not be replaced without written notice to City. The
Superintendent will be Contractor's representative at the Site and shall have authority to act on
behalf of Contractor. All communication given to or received from the Superintendent shall be
binding on Contractor.
C. Contractor shall notify the City 24 hours prior to moving areas during the sequence of construction.
5.2 Labor; Working Hours
A. Contractor shall provide competent, suitably qualified personnel to perform construction as
required by the Contract Documents. Contractor shall at all times maintain good discipline and
order at the Site.
B. Except as otherwise required for the safety or protection of persons or the Work or property at the
Site or adjacent thereto, and except as otherwise stated in the Contract Documents, all Work at the
Site shall be performed during Regular Working Hours. Contractor will not permit the performance
of Work beyond Regular Working Hours or for Weekend Working Hours without City's written
consent (which will not be unreasonably withheld). Written request (by letter or electronic
communication) to perform Work:
1. for beyond Regular Working Hours request must be made by noon at least two (2) Business
Days prior
2. for Weekend Working Hours request must be made by noon of the preceding Thursday
3. for legal holidays request must be made by noon two Business Days prior to the legal
- holiday.
5.3 Services, Materials, and Equipment
A. Unless otherwise specified in the Contract Documents, Contractor shall provide and assume full
responsibility for all services, materials, equipment, labor, transportation, construction equipment
and machinery, tools, appliances, fuel, power, light, heat, telephone, water, sanitary facilities,
temporary facilities, and all other facilities and incidentals necessary for the performance,
Contractor required testing, start-up, and completion of the Work.
B. All materials and equipment incorporated into the Work shall be as specified or, if not specified,
shall be of good quality and new, except as otherwise provided in the Contract Documents. All
special warranties and guarantees required by the Specifications shall expressly run to the benefit
of City. If required by City, Contractor shall furnish satisfactory evidence (including reports of
required tests) as to the source, kind, and quality of materials and equipment.
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects 101901
Revised December 20, 2012
00 73 10-14
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 14 of 35
C. All materials and equipment to be incorporated into the Work shall be stored, applied, installed,
_ connected, erected, protected, used, cleaned, and conditioned in accordance with instructions of the
applicable Supplier, except as otherwise may be provided in the Contract Documents.
5.4 Project Schedule
A. Contractor shall adhere to the Project Schedule established in accordance with Paragraph 2.01 and
the General Requirements as it may be adjusted from time to time as provided below.
1. Contractor shall submit to City for acceptance (to the extent indicated in Paragraph 2.01 and
the General Requirements) proposed adjustments in the Project Schedule.
2. Proposed adjustments in the Project Schedule that will change the Contract Time shall be
submitted in accordance with the requirements of Article 9. Adjustments in Contract Time for
projects with City participation shall be made by participating change orders.
5.5 Substitutes and "Or -Equals"
A. Whenever an item of material or equipment is specified or described in the Contract Documents
by using the name of a proprietary item or the name of a particular Supplier, the specification or
description is intended to establish the type, function, appearance, and quality required. Unless the
specification or description contains or is followed by words reading that no like, equivalent, or
"or -equal" item or no substitution is permitted, other items of material or equipment of other
Suppliers may be submitted to City for review under the circumstances described below.
1. "Or -Equal" Items: If in City's sole discretion an item of material or equipment proposed by
Contractor is functionally equal to that named and sufficiently similar so that no change in
related Work will be required, it may be considered by City as an "or -equal" item, in which
_ case review and approval of the proposed item may, in City's sole discretion, be accomplished
without compliance with some or all of the requirements for approval of proposed substitute
items. For the purposes of this Paragraph 5.05.A.1, a proposed item of material or equipment
will be considered functionally equal to an item so named if:
a. City determines that:
1) it is at least equal in materials of construction, quality, durability, appearance,
strength, and design characteristics;
2) it will reliably perform at least equally well the function and achieve the results
imposed by the design concept of the completed Project as a functioning whole; and
3) it has a proven record of performance and availability of responsive service; and
b. Contractor certifies that, if approved and incorporated into the Work:
so 1) there will be no increase in cost to the City or increase in Contract Time; and
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects 101901
Revised December 20, 2012
00 7310-15
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 15 of 35
2) it will conform substantially to the detailed requirements of the item named in the
`IM Contract Documents.
2. Substitute Items:
a. If in City's sole discretion an item of material or equipment proposed by Contractor does
not qualify as an "or -equal" item under Paragraph 5.05.A.1, it may be submitted as a
proposed substitute item.
b. Contractor shall submit sufficient information as provided below to allow City to determine
if the item of material or equipment proposed is essentially equivalent to that named and
an acceptable substitute therefor. Requests for review of proposed substitute items of
material or equipment will not be accepted by City from anyone other than Contractor.
c. Contractor shall make written application to City for review of a proposed substitute item
of material or equipment that Contractor seeks to furnish or use. The application shall
comply with Section 0125 00and:
1) shall certify that the proposed substitute item will:
i. perform adequately the functions and achieve the results called for by the general
design;
ii. be similar in substance to thatspecified;
iii. be suited to the same use as that specified; and
2) will state:
i. the extent, if any, to which the use of the proposed substitute item will prejudice
Contractor's achievement of final completion on time;
ii. whether use of the proposed substitute item in the Work will require a change in
any of the Contract Documents (or in the provisions of any other direct contract
with City for other work on the Project) to adapt the design to the proposed
substitute item;
T iii. whether incorporation or use of the proposed substitute item in connection with
the Work is subject to payment of any license fee or royalty; and
3) will identify:
i. all variations of the proposed substitute item from that specified;
ii. available engineering, sales, maintenance, repair, and replacement services; and
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS —Developer Awarded Projects 101901
Revised December 20, 2012
00 73 10-16
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 16 of 35
4) shall contain an itemized estimate of all costs or credits that will result directly or
indirectly from use of such substitute item, including costs of redesign and Damage
Claims of other contractors affected by any resulting change.
B. Substitute Construction Methods or Procedures: If a specific means, method, technique, sequence,
or procedure of construction is expressly required by the Contract Documents, Contractor may
furnish or utilize a substitute means, method, technique, sequence, or procedure of construction
approved by City. Contractor shall submit sufficient information to allow City, in City's sole
discretion, to determine that the substitute proposed is equivalent to that expressly called for by the
Contract Documents. Contractor shall make written application to City for review in the same
-. manner as those provided in Paragraph 5.05.A.2.
C. City's Evaluation: City will be allowed a reasonable time within which to evaluate each proposal
or Submittal made pursuant to Paragraphs 5.05.A and 5.05.B. City may require Contractor to
furnish additional data about the proposed substitute. City will be the sole judge of acceptability.
No "or -equal" or substitute will be ordered, installed or utilized until City's review is complete,
which will be evidenced by a Change Order in the case of a substitute and an accepted Submittal
for an "or -equal." City will advise Contractor in writing of its determination.
D. Special Guarantee: City may require Contractor to furnish at Contractor's expense a special
performance guarantee, warranty, or other surety with respect to any substitute. Contractor shall
indemnify and hold harmless City and anyone directly or indirectly employed by them from and
against any and all claims, damages, losses and expenses (including attorney's fees) arising out of
the use of substituted materials or equipment.
E. City's Cost Reimbursement: City will record City's costs in evaluating a substitute proposed or
submitted by Contractor pursuant to Paragraphs 5.05.A.2 and 5.05.B. Whether or not City approves
a substitute so proposed or submitted by Contractor, Contractor may be required to reimburse City
for evaluating each such proposed substitute. Contractor may also be required to reimburse City
for the charges for making changes in the Contract Documents.
F. Contractor's Expense: Contractor shall provide all data in support of any proposed substitute or
"or -equal" at Contractor's expense.
G. Substitute Reimbursement: Costs (savings or charges) attributable to acceptance of a substitute shall
be incorporated to the Contract by Participating Change Order.
5.6 Pre -Qualification of Bidders (Prime Contractors and Subcontractors)
A. The Contractor and any subcontractors are required to be prequalified for the work types requiring
pre -qualification
-- 5.7 Concerning Subcontractors, Suppliers, and Others
A. Minority and Women Owned Business Enterprise Compliance:
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects 101901
Revised December 20, 2012
0073 10-17
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 17 of 35
❑ Required for this Contract.
® Not Required for this Contract.
It is City policy to ensure the full and equitable participation by Minority and Women Business
Enterprises (MWBE) in the procurement of goods and services on a contractual basis. If the
Contract Documents provide for a MWBE goal, Contractor is required to comply with the intent
of the City's MWBE Ordinance (as amended) by the following:
1. Contractor shall, upon request by City, provide complete and accurate information regarding
actual work performed by a MWBE on the Contract and payment therefor.
2. Contractor will not make additions, deletions, or substitutions of accepted MWBE without
written consent of the City. Any unjustified change or deletion shall be a material breach of
Contract and may result in debarment in accordance with the procedures outlined in the
Ordinance.
3. Contractor shall, upon request by City, allow an audit and/or examination of any books, records,
or files in the possession of the Contractor that will substantiate the actual work performed by
an MWBE. Material misrepresentation of any nature will be grounds for termination of the
Contract. Any such misrepresentation may be grounds for disqualification of Contractor to bid
on future contracts with the City for a period of not less than three years.
B. Contractor shall be fully responsible to City for all acts and omissions of the Subcontractors,
Suppliers, and other individuals or entities performing or furnishing any of the Work just as
Contractor is responsible for Contractor's own acts and omissions. Nothing in the Contract
Documents:
1. shall create for the benefit of any such Subcontractor, Supplier, or other individual or entity any
contractual relationship between City and any such Subcontractor, Supplier or other individual
or entity; nor
2, shall create any obligation on the part of City to pay or to see to the payment of any moneys
due any such Subcontractor, Supplier, or other individual or entity except as may otherwise
be required by Laws and Regulations.
C. Contractor shall be solely responsible for scheduling and coordinating the Work of Subcontractors,
Suppliers, and other individuals or entities performing or furnishing any of the Work under a direct
or indirect contract with Contractor.
D. All Subcontractors, Suppliers, and such other individuals or entities performing or furnishing any
of the Work shall communicate with City through Contractor.
E. All Work performed for Contractor by a Subcontractor or Supplier will be pursuant to an
appropriate agreement between Contractor and the Subcontractor or Supplier which specifically
binds the Subcontractor or Supplier to the applicable terms and conditions of these Contract
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects 101901
Revised December 20, 2012
0073 10-18
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 18 of 35
Documents, Contractor shall provide City contract numbers and reference numbers to the
Subcontractors and/or Suppliers.
5.8 Wage Rates
❑ Required for this Contract.
® Not Required for this Contract.
A. Duty to pay Prevailing Wage Rates. The Contractor shall comply with all requirements of
Chapter 2258, Texas Government Code (as amended), including the payment of not less than the
rates determined by the City Council of the City of Fort Worth to be the prevailing wage rates in
accordance with Chapter 2258. Such prevailing wage rates are included in these Contract
Documents.
i B. Penaltyfor Violation. A Contractor or any Subcontractor who does not pay the prevailing wage
shall, upon demand made by the City, pay to the City $60 for each worker employed for each
calendar day or part of the day that the worker is paid less than the prevailing wage rates stipulated
�. in these contract documents. This penalty shall be retained by the City to offset its administrative
costs, pursuant to Texas Government Code 2258.023.
C. Complaints of Violations and City Determination of Good Cause. On receipt of information,
including a complaint by a worker, concerning an alleged violation of 2258.023, Texas
Government Code, by a Contractor or Subcontractor, the City shall make an initial determination,
before the 31 st day after the date the City receives the information, as to whether good cause exists
to believe that the violation occurred. The City shall notify in writing the Contractor or
Subcontractor and any affected worker of its initial determination. Upon the City's determination
that there is good cause to believe the Contractor or Subcontractor has violated Chapter 2258, the
City shall retain the full amounts claimed by the claimant or claimants as the difference between
wages paid and wages due under the prevailing wage rates, such amounts being subtracted from
successive progress payments pending a final determination of the violation.
- D. Arbitration Required if Violation Not Resolved. An issue relating to an alleged violation of Section
2258.023, Texas Government Code, including a penalty owed to the City or an affected worker,
shall be submitted to binding arbitration in accordance with the Texas General Arbitration Act
(Article 224 et seq., Revised Statutes) if the Contractor or Subcontractor and any affected worker
does not resolve the issue by agreement before the 15th day after the date the City makes its initial
determination pursuant to Paragraph C above. If the persons required to arbitrate under this section
do not agree on an arbitrator before the 1 lth day after the date that arbitration is required, a district
court shall appoint an arbitrator on the petition of any of the persons. The City is not a party in
the arbitration. The decision and award of the arbitrator is final and binding on all parties and may
be enforced in any court of competent jurisdiction.
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects 101901
Revised December 20, 2012
00 73 10-19
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 19 of 35
E. Records to be Maintained. The Contractor and each Subcontractor shall, for a period of three (3)
years following the date of acceptance of the work, maintain records that show (i) the name and
occupation of each worker employed by the Contractor in the construction of the Work provided
for in this Contract; and (ii) the actual per diem wages paid to each worker. The records shall be
open at all reasonable hours for inspection by the City. The provisions of Paragraph 6.23, Right to
Audit, shall pertain to this inspection.
F. Progress Payments. With each progress payment or payroll period, whichever is less, the
Contractor shall submit an affidavit stating that the Contractor has complied with the requirements
of Chapter 2258, Texas Government Code.
G. Posting of Wage Rates. The Contractor shall post prevailing wage rates in a conspicuous place at
all times.
H. Subcontractor Compliance. The Contractor shall include in its subcontracts and/or shall otherwise
require all of its Subcontractors to comply with Paragraphs A through G above.
5.9 Patent Fees and Royalties
A. To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and hold
harmless City, from and against all claims, costs, losses, and damages (including but not limited
to all fees and charges of engineers, architects, attorneys, and other professionals and all court or
arbitration or other dispute resolution costs) arising out of or relating to any infringement ofpatent
rights or copyrights incident to the use in the performance of the Work or resulting from the
incorporation in the Work of any invention, design, process, product, or device not specified in the
Contract Documents.
5.10 Laws and Regulations
A. Contractor shall give all notices required by and shall comply with all Laws and Regulations
applicable to the performance of the Work. Except where otherwise expressly required by
applicable Laws and Regulations, the City shall not be responsible for monitoring Contractor's
compliance with any Laws orRegulations.
T B. If Contractor performs any Work knowing or having reason to know that it is contrary to Laws or
Regulations, Contractor shall bear all claims, costs, losses, and damages (including but not limited
to all fees and charges of engineers, architects, attorneys, and other professionals and all court or
arbitration or other dispute resolution costs) arising out of or relating to such Work. However, it
shall not be Contractor's responsibility to make certain that the Specifications and Drawings are in
accordance with Laws and Regulations, but this shall not relieve Contractor of Contractor's
obligations under Paragraph 3.01.
5.11 Use of Site and OtherAreas
A. Limitation on Use of Site and Other Areas:
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects 10I901
Revised December 20, 2012
00 73 10- 20
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 20 of 35
1. Contractor shall confine construction equipment, the storage of materials and equipment, and
the operations of workers to the Site and other areas permitted by Laws and Regulations and
shall not unreasonably encumber the Site and other areas with construction equipment or other
materials or equipment. Contractor shall assume full responsibility for any damage to any such
land or area, or to the owner or occupant thereof, or of any adjacent land or areas resulting
from the performance of the Work.
2. At any time when, in the judgment of the City, the Contractor has obstructed or closed or is
carrying on operations in a portion of a street, right-of-way, or easement greater than is
necessary for proper execution of the Work, the City may require the Contractor to finish the
section on which operations are in progress before work is commenced on any additional area
of the Site.
3. Should any Damage Claim be made by any such owner or occupant because of the
performance of the Work, Contractor shall promptly attempt to resolve the Damage Claim.
4. Pursuant to Paragraph 5.18, Contractor shall indemnify and hold harmless City, from and
against all claims, costs, losses, and damages arising out of or relating to any claim or action,
legal or equitable, brought by any such owner or occupant against City.
B. Removal of Debris During Performance of the Work: During the progress of the Work Contractor
shall keep the Site and other areas free from accumulations of waste materials, rubbish, and other
debris. Removal and disposal of such waste materials, rubbish, and other debris shall conform to
applicable Laws and Regulations.
C. Site Maintenance Cleaning: 24 hours after written notice is given to the Contractor that the clean-
up on the job site is proceeding in a manner unsatisfactory to the City or Developer, if the
Contractor fails to correct the unsatisfactory procedure, the City may take such direct action as the
City deems appropriate to correct the clean-up deficiencies cited to the Contractor in the written
notice (by letter or electronic communication), and shall be entitled to recover its cost in doing so.
The City may withhold Final Acceptance until clean-up is complete and cost are recovered.
D. Final Site Cleaning: Prior to Final Acceptance of the Work Contractor shall clean the Site and the
Work and make it ready for utilization by City or adjacent property owner. At the completion of
the Work Contractor shall remove from the Site all tools, appliances, construction equipment and
machinery, and surplus materials and shall restore to original condition or better all property
disturbed by the Work.
E. Loading Structures: Contractor shall not load nor permit any part of any structure to be loaded in
any manner that will endanger the structure, nor shall Contractor subject any part of the Work or
adjacent property to stresses or pressures that will endanger it.
5.12 Record Documents
A. Contractor shall maintain in a safe place at the Site or in a place designated by the Contractor and
approved by the City, one (1) record copy of all Drawings, Specifications, Addenda, Change
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects 101901
Revised December 20, 2012
0073 10- 21
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 21 of 35
Orders, Field Orders, and written interpretations and clarifications in good order and annotated to
show changes made during construction. These record documents together with all approved
Samples and a counterpart of all accepted Submittals will be available to City for reference. Upon
completion of the Work, these record documents, any operation and maintenance manuals, and
Submittals will be delivered to City prior to Final Inspection. Contractor shall include accurate
locations for buried and imbeddeditems.
5.13 Safety and Protection
A. Contractor shall be solely responsible for initiating, maintaining and supervising all safety
precautions and programs in connection with the Work. Such responsibility does not relieve
Subcontractors of their responsibility for the safety of persons or property in the performance of
their work, nor for compliance with applicable safety Laws and Regulations. Contractor shall take
all necessary precautions for the safety of, and shall provide the necessary protection to prevent
damage, injury or loss to:
- 1. all persons on the Site or who may be affected by the Work;
2. all the Work and materials and equipment to be incorporated therein, whether in storage on or
off the Site; and
3. other property at the Site or adjacent thereto, including trees, shrubs, lawns, walks, pavements,
roadways, structures, utilities, and Underground Facilities not designated for removal,
relocation, or replacement in the course of construction.
B. Contractor shall comply with all applicable Laws and Regulations relating to the safety of persons
or property, or to the protection of persons or property from damage, injury, or loss; and shall erect
and maintain all necessary safeguards for such safety and protection. Contractor shall notify owners
of adjacent property and of Underground Facilities and other utility owners when prosecution of
the Work may affect them, and shall cooperate with them in the protection, removal, relocation,
and replacement of their property.
C. Contractor shall comply with the applicable requirements of City's safety programs, if any.
D. Contractor shall inform City of the specific requirements of Contractor's safety program, if any,
with which City's employees and representatives must comply while at the Site.
E. All damage, injury, or loss to any property referred to in Paragraph 5.13.A.2 or 5.13.A.3 caused,
directly or indirectly, in whole or in part, by Contractor, any Subcontractor, Supplier, or any other
- individual or entity directly or indirectly employed by any of them to perform any of the Work, or
anyone for whose acts any of them may be liable, shall be remedied by Contractor.
-� F. Contractor's duties and responsibilities for safety and for protection of the Work shall continue until
such time as all the Work is completed and City has accepted the Work
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects 101901
Revised December 20, 2012
00 73 10-22
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 22 of 35
5.14 Safety Representative
Contractor shall inform City in writing of Contractor's designated safety representative at the Site.
5.15 Hazard Communication Programs
Contractor shall be responsible for coordinating any exchange of material safety data sheets or other
hazard communication information required to be made available to or exchanged between or among
employers in accordance with Laws orRegulations.
5.16 Submittals
A. Contractor shall submit required Submittals to City for review and acceptance. Each submittal
will be identified as required by City.
'- 1. Submit number of copies specified in the General Requirements.
2. Data shown on the Submittals will be complete with respect to quantities, dimensions,
specified performance and design criteria, materials, and similar data to show City the services,
materials, and equipment Contractor proposes to provide and to enable City to review the
information for the limited purposes required by Paragraph 5.16.C.
3. Submittals submitted as herein provided by Contractor and reviewed by City for conformance
with the design concept shall be executed in conformity with the Contract Documents unless
otherwise required by City.
4. When Submittals are submitted for the purpose of showing the installation in greater detail,
their review shall not excuse Contractor from requirements shown on the Drawings and
Specifications.
5. For -Information -Only submittals upon which the City is not expected to conduct review or
take responsive action may be so identified in the Contract Documents.
6. Submit required number of Samples specified in the Specifications.
7. Clearly identify each Sample as to material, Supplier, pertinent data such as catalog numbers,
the use for which intended and other data as City may require to enable City to review the
submittal for the limited purposes required by Paragraph 5.16.C.
B. Where a Submittal is required by the Contract Documents or the Schedule of Submittals, any
related Work performed prior to City's review and acceptance of the pertinent submittal will be at
the sole expense and responsibility of Contractor.
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects 101901
Revised December 20, 2012
00 7310- 23
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 23 of 35
C. City's Review:
1. City will provide timely review of required Submittals in accordance with the Schedule of
Submittals acceptable to City. City's review and acceptance will be only to determine if the
items covered by the submittals will, after installation or incorporation in the Work, conform
to the information given in the Contract Documents and be compatible with the design concept
of the completed Project as a functioning whole as indicated by the Contract Documents.
2. City's review and acceptance will not extend to means, methods, techniques, sequences, or
procedures of construction (except where a particular means, method, technique, sequence, or
procedure of construction is specifically and expressly called for by the Contract Documents)
or to safety precautions or programs incident thereto. The review and acceptance of a separate
item as such will not indicate approval of the assembly in which the item functions.
3. City's review and acceptance shall not relieve Contractor from responsibility for any variation
from the requirements of the Contract Documents unless Contractor has complied with the
requirements of Section 01 33 00 and City has given written acceptance of each such variation
by specific written notation thereof incorporated in or accompanying the Submittal. City's
review and acceptance shall not relieve Contractor from responsibility for complying with the
requirements of the Contract Documents.
5.17 Contractor's General Warranty and Guarantee
A. Contractor warrants and guarantees to City that all Work will be in accordance with the Contract
Documents and will not be defective. City and its officers, directors, members, partners,
employees, agents, consultants, and subcontractors shall be entitled to rely on representation of
Contractor's warranty and guarantee.
B. Contractor's warranty and guarantee hereunder excludes defects or damage caused by:
1. abuse, modification, or improper maintenance or operation by persons other than Contractor,
Subcontractors, Suppliers, or any other individual or entity for whom Contractor is
responsible; or
2. normal wear and tear under normal usage.
C. Contractor's obligation to perform and complete the Work in accordance with the Contract
Documents shall be absolute. None of the following will constitute an acceptance of Work that is
not in accordance with the Contract Documents or a release of Contractor's obligation to perform
the Work in accordance with the Contract Documents:
1. observations by City;
2. recommendation or payment by City or Developer of any progress or final payment;
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects 101901
Revised December 20, 2012
0073 10-24
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 24 of 35
3. the issuance of a certificate of Final Acceptance by City or any payment related thereto by
City;
4. use or occupancy of the Work or any part thereof by City;
5. any review and acceptance of a Submittal by City;
6. any inspection, test, or approval by others; or
7. any correction of defective Work by City.
D. The Contractor shall remedy any defects or damages in the Work and pay for any damage to other
work or property resulting therefrom which shall appear within a period of two (2) years from the
date of Final Acceptance of the Work unless a longer period is specified and shall furnish a good
and sufficient maintenance bond, complying with the requirements of Article
4.02.13. The City will give notice of observed defects with reasonable promptness.
5.18 Indemnification
A. Contractor covenants and agrees to indemnify, hold harmless and defend, at its own expense, the
City, its officers, servants and employees, from and against any and all claims arising out of, or
alleged to arise out of, the work and services to be performed by the Contractor, its officers, agents,
employees, subcontractors, licenses or invitees under this Contract. THIS INDEMNIFICATION
PROVISION IS SPECIFICALLY INTENDED TO OPERATE AND BE EFFECTIVL
EVEN IF IT IS ALLEGED OR PROVEN THAT ALL OR SOME OF THE DAMAGES
MNG SOTJGHT WERE CAUSED, IN WHOLE OR iN PART. BY ANY ACT, OMISSION
OR NEGLIGENCE N OF THE C1TY. This indemnity provision is intended to include, without
limitation, indemnity for costs, expenses and legal fees incurred by the City in defending against
such claims and causes of actions.
B. Contractor covenants and agrees to indemnify and hold harmless, at its own expense, the City, its
officers, servants and employees, from and against any and all loss, damage or destruction of
property of the City, arising out of, or alleged to arise out of, the work and services to be performed
by the Contractor, its officers, agents, employees, subcontractors, licensees or invitees under this
Contract. THIS INDEMNIFICATION PROVISION IS SPECIFICALLY INTENDED TO
OPERATE AND BE EFFECTIVE EVEN IF IT IS ALL . ED OR PROVEN THAT ALL
OR SOME OF THE DAMAGES BEING SOUGHT WERE CAUSED, IN WHOL.. OR IN
PART. BY ANY ACT, OMISSION OR NEGLIGENCE OF THE CITY,
5.19 Delegation of Professional Design Services
A. Contractor will not be required to provide professional design services unless such services are
specifically required by the Contract Documents for a portion of the Work or unless such services
are required to carry out Contractor's responsibilities for construction means, methods, techniques,
sequences and procedures.
M
r.. CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects 101901
Revised December 20, 2012
00 73 10- 25
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 25 of 35
B. If professional design services or certifications by a design professional related to systems, materials
or equipment are specifically required of Contractor by the Contract Documents, City will specify
all performance and design criteria that such services must satisfy. Contractor shall cause such
services or certifications to be provided by a properly licensed professional, whose signature and
seal shall appear on all drawings, calculations, specifications, certifications, and Submittals
prepared by such professional. Submittals related to the Work designed or certified by such
professional, if prepared by others, shall bear such professional's written approval when submitted
to City.
C. City shall be entitled to rely upon the adequacy, accuracy and completeness of the services,
certifications or approvals performed by such design professionals, provided City has specified to
Contractor performance and design criteria that such services must satisfy.
D. Pursuant to this Paragraph 5.19, City's review and acceptance of design calculations and design
drawings will be only for the limited purpose of checking for conformance with performance and
design criteria given and the design concept expressed in the Contract Documents. City's review
and acceptance of Submittals (except design calculations and design drawings) will be only for the
purpose stated in Paragraph 5.16.C.
5.20 Right to Audit:
A. The City reserves the right to audit all projects utilizing City funds
B. The Contractor agrees that the City shall, until the expiration of three (3) years after final payment
under this Contract, have access to and the right to examine and photocopy any directly pertinent
books, documents, papers, and records of the Contractor involving transactions relating to this
Contract. Contractor agrees that the City shall have access during Regular Working Hours to all
necessary Contractor facilities and shall be provided adequate and appropriate work space in order
to conduct audits in compliance with the provisions of this Paragraph. The City shall give
Contractor reasonable advance notice of intended audits.
C. Contractor further agrees to include in all its subcontracts hereunder a provision to the effect that
the subcontractor agrees that the City shall, until the expiration of three (3) years after final
payment under this Contract, have access to and the right to examine and photocopy any directly
pertinent books, documents, papers, and records of such Subcontractor, involving transactions to
the subcontract, and further, that City shall have access during Regular Working Hours to all
Subcontractor facilities, and shall be provided adequate and appropriate work space in order to
conduct audits in compliance with the provisions of this Paragraph. The City shall give
Subcontractor reasonable advance notice of intended audits.
D. Contractor and Subcontractor agree to photocopy such documents as may be requested by the City.
The City agrees to reimburse Contractor for the cost of the copies as follows at the rate published
in the Texas Administrative Code in effect as of the time copying is performed.
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS —Developer Awarded Projects 101901
Revised December 20, 2012
00 73 10- 26
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 26 of 35
5.21 Nondiscrimination
A. The City is responsible for operating Public Transportation Programs and implementing transit -
related projects, which are funded in part with Federal financial assistance awarded by the U.S.
Department of Transportation and the Federal Transit Administration (FTA), without
discriminating against any person in the United States on the basis of race, color, or national origin.
B. Title VI, Civil Rights Act of 1964 as amended: Contractor shall comply with the requirements of
the Act and the Regulations as further defined in the Supplementary Conditions for any project
receiving Federal assistance.
ARTICLE 6 — OTHER WORK AT THE SITE
6.01 Related Work at Site
A. City may perform other work related to the Project at the Site with City's employees, or other City
contractors, or through other direct contracts therefor, or have other work performed by utility
owners. If such other work is not noted in the Contract Documents, then written notice thereof will
be given to Contractor prior to starting any such other work; and
B. Contractor shall afford each other contractor who is a party to such a direct contract, each utility
owner, and City, if City is performing other work with City's employees or other City contractors,
proper and safe access to the Site, provide a reasonable opportunity for the introduction and storage
of materials and equipment and the execution of such other work, and properly coordinate the Work
with theirs. Contractor shall do all cutting, fitting, and patching of the Work that may be required
to properly connect or otherwise make its several parts come together and properly integrate with
such other work. Contractor shall not endanger any work of others by cutting, excavating, or
otherwise altering such work; provided, however, that Contractor may cut or alter others' work
with the written consent of City and the others whose work will be affected.
C. If the proper execution or results of any part of Contractor's Work depends upon work performed
by others under this Article 7, Contractor shall inspect such other work and promptly report to
City in writing any delays, defects, or deficiencies in such other work that render it unavailable or
unsuitable for the proper execution and results of Contractor's Work. Contractor's failure to so
report will constitute an acceptance of such other work as fit and proper for integration with
Contractor's Work except for latent defects in the work provided by others.
ARTICLE 7 — CITY'S RESPONSIBILITIES
7.1 Inspections, Tests, and Approvals
�. City's responsibility with respect to certain inspections, tests, and approvals is set forth in Paragraph
11.03.
4"
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects 101901
Revised December 20, 20I2
00 73 10- 27
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 27 of 35
7.2 Limitations on City's Responsibilities
A. The City shall not supervise, direct, or have control or authority over, nor be responsible for,
Contractor's means, methods, techniques, sequences, or procedures of construction, or the safety
precautions and programs incident thereto, or for any failure of Contractor to comply with Laws
and Regulations applicable to the performance of the Work. City will not be responsible for
Contractor's failure to perform the Work in accordance with the Contract Documents.
B. City will notify the Contractor of applicable safety plans pursuant to Paragraph 5.13.
7.3 Compliance with Safety Program
While at the Site, City's employees and representatives shall comply with the specific applicable
requirements of Contractor's safety programs of which City has been informed pursuant to Paragraph
5.13.
ARTICLE 8 — CITY'S OBSERVATION STATUS DURING CONSTRUCTION
8.1 City's Project Representative
City will provide one or more Project Representative(s) during the construction period. The duties and
responsibilities and the limitations of authority of City's representative during construction are set forth
in the Contract Documents.
A. City's Project Representative will make visits to the Site at intervals appropriate to the various
stages of construction as City deems necessary in order to observe the progress that has been made
and the quality of the various aspects of Contractor's executed Work. Based on information
obtained during such visits and observations, City's Project Representative will determine, in
general, if the Work is proceeding in accordance with the Contract Documents. City's Project
Representative will not be required to make exhaustive or continuous inspections on the Site to
check the quality or quantity of the Work. City's Project Representative's efforts will be directed
toward providing City a greater degree of confidence that the completed Work will conform
�., generally to the Contract Documents.
B. City's Project Representative's visits and observations are subject to all the limitations on
_ authority and responsibility in the Contract Documents.
8.2 Authorized Variations in Work
City's Project Representative may authorize minor variations in the Work from the requirements of the
Contract Documents which do not involve an adjustment in the Contract Price or the Contract Time
and are compatible with the design concept of the completed Project as a functioning whole as
indicated by the Contract Documents. These may be accomplished by a Field Order and will be binding
on City Developer, and also on Contractor, who shall perform the Work involved promptly.
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects 101901
Revised December 20, 2012
r-1
00 73 10- 28
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 28 of 35
8.3 Rejecting Defective Work
City will have authority to reject Work which City's Project Representative believes to be defective or
will not produce a completed Project that conforms to the Contract Documents or that will prejudice
the integrity of the design concept of the completed Project as a functioning whole as indicated by the
Contract Documents. City will have authority to conduct special inspection or testing of the Work as
provided in Article 11, whether or not the Work is fabricated, installed, or completed.
8.4 Determinations for Work Performed
Contractor will determine the actual quantities and classifications of Work performed. City's Project
Representative will review with Contractor the preliminary determinations on such matters before
rendering a written recommendation. City's written decision will be final (except as modified to reflect
changed factual conditions or more accurate data).
ARTICLE 9 — CHANGES IN THE WORK
9.1 Authorized Changes in the Work
A. Without invalidating the Contract and without notice to any surety, City may, at any time or from
time to time, order Extra Work. Upon notice of such Extra Work, Contractor shall promptly
proceed with the Work involved which will be performed under the applicable conditions of the
Contract Documents (except as otherwise specifically provided). Extra Work shall be
_ memorialized by a Participating Change Order which may or may not precede an order of Extra
work.
B. For minor changes of Work not requiring changes to Contract Time or Contract Price on a
project with City participation, a Field Order may be issued by the City.
9.2 Notification to Surety
If the provisions of any bond require notice to be given to a surety of any change affecting the
general scope of the Work or the provisions of the Contract Documents (including, but not limited
to, Contract Price or Contract Time), the giving of any such notice will be Contractor's responsibility.
The amount of each applicable bond will be adjusted by the Contractor to reflect the effect of any
such change.
_ ARTICLE 10 — CHANGE OF CONTRACT PRICE; CHANGE OF CONTRACT TIME
10.1 Change of Contract Price
A. The Contract Price may only be changed by a Participating Change Order for projects with City
participation.
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects 101901
Revised December 20, 2012
00 73 10- 29
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 29 of 35
10.2 Change of Contract Time
A. The Contract Time may only be changed by a Participating Change Order for projects with City
participation.
10.3 Delays
A. If Contractor is delayed, City shall not be liable to Contractor for any claims, costs, losses, or
damages (including but not limited to all fees and charges of engineers, architects, attorneys, and
other professionals and all court or arbitration or other dispute resolution costs) sustained by
Contractor on or in connection with any other project or anticipated project.
ARTICLE 11— TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF
DEFECTIVE WORK
11.1 Notice of Defects
Notice of all defective Work of which City has actual knowledge will be given to Contractor.
Defective Work may be rejected, corrected, or accepted as provided in this Article 13.
11.2 Access to Work
City, independent testing laboratories, and governmental agencies with jurisdictional interests will have
access to the Site and the Work at reasonable times for their observation, inspection, and testing.
Contractor shall provide them proper and safe conditions for such access and advise them of
Contractor's safety procedures and programs so that they may comply therewith as applicable.
11.3 Tests and Inspections
A. Contractor shall give City timely notice of readiness of the Work for all required inspections, tests,
or approvals and shall cooperate with inspection and testing personnel to facilitate required
inspections or tests.
B. If Contract Documents, Laws or Regulations of any public body having jurisdiction require any of
the Work (or part thereof) to be inspected, tested, or approved, Contractor shall assume full
responsibility for arranging and obtaining such independent inspections, tests, retests or approvals,
pay all costs in connection therewith, and furnish City the required certificates of inspection or
approval; excepting, however, those fees specifically identified in the Supplementary Conditions
or any Texas Department of Licensure and Regulation (TDLR) inspections, which shall be paid as
described in the Supplementary Conditions.
C. Contractor shall be responsible for arranging and obtaining and shall pay all costs in connection
with any inspections, tests, re -tests, or approvals required for City's acceptance of materials or
equipment to be incorporated in the Work; or acceptance of materials, mix designs, or equipment
submitted for approval prior to Contractor's purchase thereof for incorporation in the Work.
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects 101901
Revised December 20, 2012
MR
00 73 10- 30
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 30 of 35
Such inspections, tests, re -tests, or approvals shall be performed by organizations approved by
City.
D. City may arrange for the services of an independent testing laboratory ("Testing Lab") to perform
any inspections or tests ("Testing") for any part of the Work, as determined solely by City.
1. City will coordinate such Testing to the extent possible, with Contractor;
2. Should any Testing under this Section 11.03 D result in a "fail", "did not pass" or other similar
negative result, the Contractor shall be responsible for paying for any and all retests.
Contractor's cancellation without cause of City initiated Testing shall be deemed a negative
result and require a retest.
3. Any amounts owed for any retest under this Section 11.03 D shall be paid directly to the Testing
Lab by Contractor. City will forward all invoices for retests to Developer/Contractor.
4. If Contractor fails to pay the Testing Lab, City will not issue a letter of Final Acceptance until
the Testing Lab is Paid
r. E. If any Work (or the work of others) that is to be inspected, tested, or approved is covered by
Contractor without written concurrence of City, Contractor shall, if requested by City, uncover such
Work for observation.
11.4 Uncovering Work
If any Work is covered contrary to the Contract Documents or specific instructions by the City, it must,
if requested by City, be uncovered for City's observation and replaced at Contractor's expense.
11.5 City May Stop the Work
If the Work is defective, or Contractor fails to supply sufficient skilled workers or suitable materials
or equipment, or fails to perform the Work in such a way that the completed Work will conform to the
Contract Documents, City may order Contractor to stop the Work, or any portion thereof, until the
cause for such order has been eliminated; however, this right of City to stop the Work shall not give
rise to any duty on the part of City to exercise this right for the benefit of Contractor, any
Subcontractor, any Supplier, any other individual or entity, or any surety for, or employee or agent of
any ofthem.
11.6 Correction or Removal of Defective Work
A. Promptly after receipt of written notice, Contractor shall correct all defective Work pursuant to an
acceptable schedule, whether or not fabricated, installed, or completed, or, if the Work has been
rejected by City, remove it from the Project and replace it with Work that is not defective.
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects 101901
Revised December 20, 2012
00 73 10- 31
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 31 of 35
Contractor shall pay all claims, costs, additional testing, losses, and damages (including but not
limited to all fees and charges of engineers, architects, attorneys, and other professionals and all
court or arbitration or other dispute resolution costs) arising out of or relating to such correction or
removal (including but not limited to all costs of repair or replacement of work of others). Failure
to require the removal of any defective Work shall not constitute acceptance of such Work.
B. When correcting defective Work under the terms of this Paragraph 11.06 or Paragraph 11.07,
Contractor shall take no action that would void or otherwise impair City's special warranty and
guarantee, if any, on said Work.
11.7 Correction Period
A. If within two (2) years after the date of Final Acceptance (or such longer period of time as may
be prescribed by the terms of any applicable special guarantee required by the Contract
Documents), any Work is found to be defective, or if the repair of any damages to the land or areas
made available for Contractor's use by City or permitted by Laws and Regulations as contemplated
in Paragraph 5.10.A is found to be defective, Contractor shall promptly, without cost to City and in
accordance with City's written instructions:
1. repair such defective land or areas; or
2. correct such defective Work; or
3. if the defective Work has been rejected by City, remove it from the Project and replace it
with Work that is not defective, and
4. satisfactorily correct or repair or remove and replace any damage to other Work., to the work
of others or other land or areas resulting therefrom.
B. If Contractor does not promptly comply with the terms of City's written instructions, or in an
emergency where delay would cause serious risk of loss or damage, City may have the defective
Work corrected or repaired or may have the rejected Work removed and replaced. All claims, costs,
losses, and damages (including but not limited to all fees and charges of engineers, architects,
attorneys, and other professionals and all court or other dispute resolution costs) arising out of or
relating to such correction or repair or such removal and replacement (including but not limited to
all costs of repair or replacement of work of others) will be paid by Contractor.
C. Where defective Work (and damage to other Work resulting therefrom) has been corrected or
removed and replaced under this Paragraph 11.07, the correction period hereunder with respect to
such Work may be required to be extended for an additional period of one year after the end of
the initial correction period. City shall provide 30 days written notice to Contractor and Developer
should such additional warranty coverage be required. Contractor's obligations under this
Paragraph 11.07 are in addition to any other obligation or warranty. The provisions of this
Paragraph 11.07 shall not be construed as a substitute for, or a waiver of, the provisions of any
applicable statute of limitation or repose.
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects 101901
Revised December 20, 2012
Lw�
00 7310- 32
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 32 of 35
11.8 City May Correct Defective Work
A. If Contractor fails within a reasonable time after written notice from City to correct defective Work,
or to remove and replace rejected Work as required by City in accordance with Paragraph 11.06.A,
or if Contractor fails to perform the Work in accordance with the Contract Documents, or if
Contractor fails to comply with any other provision of the Contract Documents, City may, after
seven (7) days written notice to Contractor and the Developer, correct, or remedy any such
deficiency.
B. In exercising the rights and remedies under this Paragraph 11.09, City shall proceed expeditiously.
In connection with such corrective or remedial action, City may exclude Contractor from all or
part of the Site, take possession of all or part of the Work and suspend Contractor's services related
thereto, and incorporate in the Work all materials and equipment incorporated in the Work, stored
at the Site or for which City has paid Contractor but which are stored elsewhere. Contractor shall
allow City, City's representatives, agents, consultants, employees, and City's other contractors,
access to the Site to enable City to exercise the rights and remedies under this Paragraph.
C. All claims, costs, losses, and damages (including but not limited to all fees and charges of
engineers, architects, attorneys, and other professionals and all court or other dispute resolution
costs) incurred or sustained by City in exercising the rights and remedies under this Paragraph
13.09 will be charged against Contractor, and a Change Order will be issued incorporating the
necessary revisions in the Contract Documents with respect to the Work; and City shall be entitled
to an appropriate decrease in the Contract Price.
D. Contractor shall not be allowed an extension of the Contract Time because of any delay in the
performance of the Work attributable to the exercise of City's rights and remedies under this
Paragraph 11.09.
ARTICLE 12 — COMPLETION
12.1 Contractor's Warranty of Title
- Contractor warrants and guarantees that title to all Work, materials, and equipment covered by any
Application for Payment will pass to City no later than the time of Final Acceptance and shall be
free and clear of all Liens.
12.2 Partial Utilization
A. Prior to Final Acceptance of all the Work, City may use or occupy any substantially completed
part of the Work which has specifically been identified in the Contract Documents, or which City,
determines constitutes a separately functioning and usable part of the Work that can be used by
City for its intended purpose without significant interference with Contractor's performance of
the remainder of the Work. City at any time may notify Contractor in writing to
i
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects 101901
Revised December 20, 2012
00 73 10- 33
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 33 of 35
permit City to use or occupy any such part of the Work which City determines to be ready for its
intended use, subject to the following conditions:
1. Contractor at any time may notify City in writing that Contractor considers any such part of
the Work ready for its intendeduse.
2. Within a reasonable time after notification as enumerated in Paragraph 14.05.A.1, City and
Contractor shall make an inspection of that part of the Work to determine its status of
completion. If City does not consider that part of the Work to be substantially complete, City
will notify Contractor in writing giving the reasons therefor.
3. Partial Utilization will not constitute Final Acceptance by City.
12.3 Final Inspection
A. Upon written notice from Contractor that the entire Work is complete in accordance with the
Contract Documents:
1. within 10 days, City will schedule a Final Inspection with Contractor.
2. City will notify Contractor in writing of all particulars in which this inspection reveals that
the Work is incomplete or defective. Contractor shall immediately take such measures as are
necessary to complete such Work or remedy such deficiencies.
- 12.4 Final Acceptance
A. Upon completion by Contractor to City's satisfaction, of any additional Work identified in the Final
Inspection, City will issue to Contractor a letter of Final Acceptance upon the satisfaction of the
following:
1. All documentation called for in the Contract Documents, including but not limited to the
evidence of insurance required by Paragraph 5.03;
2. consent of the surety, if any, to Final Acceptance;
3. a list of all pending or released Damage Claims against City that Contractor believes are
unsettled; and
4. affidavits of payments and complete and legally effective releases or waivers (satisfactory to
City) of all Lien rights arising out of or Liens filed in connection with the Work.
5. after all Damage Claims have beenresolved:
a. directly by the Contractoror;
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects 101901
Revised December 20, 2012
00 73 10- 34
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 34 of 35
b. Contractor provides evidence that the Damage Claim has been reported to Contractor's
insurance provider for resolution.
6. Issuing Final Acceptance by the City shall not relieve the Contractor of any guarantees or
other requirements of the Contract Documents which specifically continue thereafter.
ARTICLE 13 — SUSPENSION OF WORK
13.01 City May Suspend Work
A. At any time and without cause, City may suspend the Work or any portion thereof by written
notice to Contractor and which may fix the date on which Work will be resumed. Contractor shall
resume the Work on the date so fixed. During temporary suspension of the Work covered by these
Contract Documents, for any reason, the City will stop contract time on City participation projects.
B. Should the Contractor not be able to complete a portion of the Project due to causes beyond the
control of and without the fault or negligence of the Contractor, and should it be determined by
mutual consent of the Contractor and City that a solution to allow construction to proceed is not
Ir, available within a reasonable period of time, Contractor may request an extension in Contract Time,
directly attributable to any such suspension.
C. If it should become necessary to suspend the Work for an indefinite period, the Contractor shall
store all materials in such a manner that they will not obstruct or impede the public unnecessarily
nor become damaged in any way, and he shall take every precaution to prevent damage or
deterioration of the work performed; he shall provide suitable drainage about the work, and erect
temporary structures where necessary.
ARTICLE 14 — MISCELLANEOUS
14.1 Giving Notice
A. Whenever any provision of the Contract Documents requires the giving of written notice, it will
be deemedto have been validly given i£
1. delivered in person to the individual or to a member of the firm or to an officer of the
corporation for whom it is intended; or
2. delivered at or sent by registered or certified mail, postage prepaid, to the last business
address known to the giver of the notice.
B. Business address changes must be promptly made in writing to the other party.
C. Whenever the Contract Documents specifies giving notice by electronic means such electronic
notice shall be deemed sufficient upon confirmation of receipt by the receiving party.
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects 101901
Revised December 20, 2012
00 73 10- 35
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 35 of 35
14.2 Computation of Times
When any period of time is referred to in the Contract Documents by days, it will be computed to
exclude the first and include the last day of such period. If the last day of any such period falls on a
Saturday or Sunday or on a day made a legal holiday the next Working Day shall become the last day
of the period.
14.3 Cumulative Remedies
The duties and obligations imposed by these General Conditions and the rights and remedies available
hereunder to the parties hereto are in addition to and are not to be construed in any way as a limitation
of, any rights and remedies available to any or all of them which are otherwise imposed or available
- by Laws or Regulations, by special warranty or guarantee, or by other provisions of the Contract
Documents. The provisions of this Paragraph will be as effective as if repeated specifically in the
Contract Documents in connection with each particular duty, obligation, right, and remedy to which
they apply.
14.4 Survival of Obligations
All representations, indemnifications, warranties, and guarantees made in, required by, or given in
accordance with the Contract Documents, as well as all continuing obligations indicated in the
Contract Documents, will survive final payment, completion, and acceptance of the Work or
termination or completion of the Contract or termination of the services of Contractor.
14.5 Headings
Article and paragraph headings are inserted for convenience only and do not constitute parts of these
General Conditions.
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects 101901
Revised December 20, 2012
1
2
3 GENERAL
4 SUMMARY
SECTION 01 11 00
SUMMARY OF WORK
011100-1
DAP PROJECT RECORD DOCUMENTS
Pagel of 3
5 A. Section Includes:
6 1. Summary of Work to be performed in accordance with the Contract Documents
7 B. Deviations from this City of Fort Worth Standard Specification
8 1. None.
9 C. Related Specification Sections include, but are not necessarily limited to:
10 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the Contract
11 2. Division 1 - General Requirements
12 1.2 PRICE AND PAYMENT PROCEDURES
13 A. Measurement and Payment
14 1. Work associated with this Item is considered subsidiary to the various items bid.
15 No separate payment will be allowed for this Item.
16 1.3 REFERENCES [NOT USED]
17 1.4 ADMINISTRATIVE REQUIREMENTS
18 A. Work Covered by Contract Documents
19 1. Work is to include furnishing all labor, materials, and equipment, and performing
20 all Work necessary for this construction project as detailed in the Drawings and
21 Specifications.
22 B. Subsidiary Work
23 1. Any and all Work specifically governed by documentary requirements for the
24 project, such as conditions imposed by the Drawings or Contract Documents in
25 which no specific item for bid has been provided for in the Proposal and the item is
26 not a typical unit bid item included on the standard bid item list, then the item shall
27 be considered as a subsidiary item of Work, the cost of which shall be included in
28 the price bid in the Proposal for various bid items.
29 C. Use of Premises
30 1. Coordinate uses of premises under direction of the City.
31 2. Assume full responsibility for protection and safekeeping of materials and
32 equipment stored on the Site.
33 3. Use and occupy only portions of the public streets and alleys, or other public places
34 or other rights -of -way as provided for in the ordinances of the City, as shown in the
35 Contract Documents, or as may be specifically authorized in writing by the City.
36 a. A reasonable amount of tools, materials, and equipment for construction
37 purposes may be stored in such space, but no more than is necessary to avoid
38 delay in the construction operations.
CITY OF FORT WORTH Milam Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects 101901
Revised December 20, 2012
011100-2
DAP PROJECT RECORD DOCUMENTS
Page 2 of 3
1 b. Excavated and waste materials shall be stored in such a way as not to interfere
2 with the use of spaces that may be designated to be left free and unobstructed
3 and so as not to inconvenience occupants of adjacent property.
4 c. If the street is occupied by railroad tracks, the Work shall be carried on in such
5 manner as not to interfere with the operation of the railroad.
6 All Work shall be in accordance with railroad requirements set forth in Division
7 0 as well as the railroad permit.
8 D. Work within Easements
9 1. Do not enter upon private property for any purpose without having previously
10 obtained permission from the owner of such property.
11 2. Do not store equipment or material on private property unless and until the
12 specified approval of the property owner has been secured in writing by the
13 Contractor and a copy furnished to the City.
14 3. Unless specifically provided otherwise, clear all rights -of -way or easements of
15 obstructions which must be removed to make possible proper prosecution of the
16 Work as a part of the project construction operations.
17
4. Preserve and use every precaution to prevent damage to, all trees, shrubbery,
18
plants, lawns, fences, culverts, curbing, and all other types of structures or
19
improvements, to all water, sewer, and gas lines, to all conduits, overhead pole
20
lines, or appurtenances thereof, including the construction of temporary fences
21
and to all other public or private property adjacent to the Work.
22
5. Notify the proper representatives of the owners or occupants of the public or
23
private lands of interest in lands which might be affected by the Work.
24
a. Such notice shall be made at least 48 hours in advance of the beginning of
25
the Work.
26
b. Notices shall be applicable to both public and private utility companies and
27
any corporation, company, individual, or other, either as owners or
28
occupants, whose land or interest in land might be affected by the Work.
29
c. Be responsible for all damage or injury to property of any character
30
resulting from any act, omission, neglect, or misconduct in the manner or
31
method or execution of the Work, or at any time due to defective work,
32
material, or equipment.
33
6. Fence
34
a. Restore all fences encountered and removed during construction of the
35
Project to the original or a better than original condition.
36
b. Erect temporary fencing in place of the fencing removed whenever the
37
Work is not in progress and when the site is vacated overnight, and/or at all
38
times to provide site security.
39
c. The cost for all fence work within easements, including removal, temporary
40
closures and replacement, shall be subsidiary to the various items bid in the
41
project proposal, unless a bid item is specifically provided in the proposal.
CITY OF FORT WORTH Milam Street Sanitary Sewer Extensions
' STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects 101901
Revised December 20, 2012
01 11 00 - 3
DAP PROJECT RECORD DOCUMENTS
Page 3 of 3
1
1.5
SUBMITTALS [NOT USED]
2
1.6
ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
3
1.7
CLOSEOUT SUBMITTALS [NOT USED]
4
1.8
MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
5
1.9
QUALITY ASSURANCE [NOT USED]
6
1.10
DELIVERY, STORAGE, AND HANDLING [NOT USED]
7
1.11
FIELD [SITE] CONDITIONS [NOT USED]
8
1.12
WARRANTY [NOT USED]
9 PART 2 - PRODUCTS [NOT USED]
10 PART 3 - EXECUTION [NOT USED]
11 END OF SECTION
12
Revision Log
DATE NAME SUMMARY OF CHANGE
13
CITY OF FORT WORTH Milam Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects 101901
Revised December 20, 2012
006125-1
DAP PROJECT RECORD DOCUMENTS
Page 1 of 3
1 SECTION 013119
2 PRECONSTRUCTION MEETING
3 PART 1- GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Provisions for the preconstruction meeting to be held prior to the start of Work to
7 clarify construction contract administration procedures
8 B. Deviations from this City of Fort Worth Standard Specification
9 1. No construction schedule required unless requested by theCity.
10 C. Related Specification Sections include, but are not necessarily limited to:
11 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of theContract
12 2. Division 1 —General Requirements
13 1.2 PRICE AND PAYMENT PROCEDURES
14 A. Measurement and Payment
15 1. Work associated with this Item is considered subsidiary to the various items bid.
16 No separate payment will be allowed for this Item.
17 1.3 REFERENCES [NOT USED]
18 1.4 ADMINISTRATIVE REQUIREMENTS
19 A. Coordination
20 1. Attend preconstruction meeting.
21 2. Representatives of Contractor, subcontractors and suppliers attendingmeetings
22 shall be qualified and authorized to act on behalf of the entity each represents.
23 3. Meeting administered by City may be taperecorded.
24 a. If recorded, tapes will be used to prepare minutes and retained by City for
25 future reference.
26 B. Preconstruction Meeting
27 1. A preconstruction meeting will be held within 14 days after the delivery of the
28 distribution package to the City.
29 The meeting will be scheduled and administered by the City.
30 2. The Project Representative will preside at the meeting, prepare the notes of the
31 meeting and distribute copies of same to all participants who so request by fully
32 completing the attendance form to be circulated at the beginning of the meeting.
33 3. Attendance shall include:
34 a. Developer and Consultant
35 b. Contractor's project manager
36 c. Contractor's superintendent
37 d. Any subcontractor or supplier representatives whom the Contractor may
38 desire to invite or the City may request
39
CITY OF FORT WORTH Milam Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised August 30, 2013
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
006125-2
DAP PROJECT RECORD DOCUMENTS
Page 2 of 3
e. Other City representatives
f. Others as appropriate
4. Preliminary Agenda may include:
a. Introduction of Project Personnel
b. General Description of Project
c. Status of right-of-way, utility clearances, easements or other pertinent permits
d. Contractor's work plan and schedule
e. Contract Time
f. Notice to Proceed
g. Construction Staking
h. Progress Payments
L Extra Work and Change Order Procedures
j. Field Orders
k. Disposal Site Letter for Waste Material
1. Insurance Renewals
m. Payroll Certification
n. Material Certifications and Quality Control Testing
o. Public Safety and Convenience
p. Documentation of Pre -Construction Conditions
q. Weekend Work Notification
r. Legal Holidays
s. Trench Safety Plans
t. Confined Space Entry Standards
u. Coordination with the City's representative for operations of existing water
systems
V. Storm Water Pollution Prevention Plan
w. Coordination with other Contractors
x. Early Warning System
y. Contractor Evaluation
z. Special Conditions applicable to the project
aa. Damages Claims
bb. Submittal Procedures
cc. Substitution Procedures
dd. Correspondence Routing
ee. Record Drawings
ff. Temporary construction facilities
gg. MBE/SBE procedures
hh. Final Acceptance
ii. Final Payment
jj. Questions or Comments
CITY OF FORT WORTH Milam Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised August 30, 2013
006125-3
DAP PROJECT RECORD DOCUMENTS
Page 3 of 3
1 1.5
SUBMITTALS [NOT USED]
2 1.6
ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
3 1.7
CLOSEOUT SUBMITTALS [NOT USED]
4 1.8
MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
5 1.9
QUALITY ASSURANCE [NOT USED]
6 1.10
DELIVERY, STORAGE, AND HANDLING [NOT USED]
7 1.11
FIELD [SITE] CONDITIONS [NOT USED]
8 1.12
WARRANTY [NOT USED]
9 PART 2 - PRODUCTS [NOT USED]
10 PART 3 - EXECUTION [NOT USED]
11 END OF SECTION
12
13
Revision Log
DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH Milam Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised August 30, 2013
1
2
3 PART 1- GENERAL
4 1.1 SUMMARY
SECTION 0133 00
DAP SUBMITTALS
006125-1
DAP PROJECT RECORD DOCUMENTS
Pagel of 7
5 A. Section Includes:
6 1. General methods and requirements of submissions applicable to the following Work-
7 related submittals:
8 a. Shop Drawings
9 b. Product Data (including Standard Product List submittals)
10 c. Samples
11 d. Mock Ups
12 B. Deviations from this City of Fort Worth Standard Specification
13 1. None.
14 C. Related Specification Sections include, but are not necessarily limited to:
15 1. Division 0 —Bidding Requirements, Contract Forms and Conditions of theContract
16 2. Division 1 —General Requirements
17 1.2 PRICE AND PAYMENT PROCEDURES
18 A. Measurement and Payment
19 1. Work associated with this Item is considered subsidiary to the various items bid. No
20 separate payment will be allowed for this Item.
21 1.3 REFERENCES [NOT USED]
22 1.4 ADMINISTRATIVE REQUIREMENTS
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
A. Coordination
1. Notify the City in writing, at the time of submittal, of any deviations in the submittals
from the requirements of the Contract Documents.
2. Coordination of Submittal Times
a. Prepare, prioritize and transmit each submittal sufficiently in advance of performing
the related Work or other applicable activities, or within the time specified in the
individual Work Sections, of the Specifications.
b. Contractor is responsible such that the installation will not be delayed by processing
times including, but not limited to:
a) Disapproval and resubmittal (ifrequired)
b) Coordination with other submittals
c) Testing
d) Purchasing
e) Fabrication
f) Delivery
Similar sequenced activities
c. No extension of time will be authorized because of the Contractor's failure to
transmit submittals sufficiently in advance of the Work.
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised August 30, 2013
006125-2
DAP PROJECT RECORD DOCUMENTS
1
2
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
Page 2 of 7
d. Make submittals promptly in accordance with approved schedule, and in such
sequence as to cause no delay in the Work or in the work of any other contractor.
B. SubmittalNumbering
1. When submitting shop drawings or samples, utilize a 9-character submittal cross-
reference identification numbering system in the following manner:
a. Use the first 6 digits of the applicable Specification Section Number.
b. For the next 2 digits number use numbers 01-99 to sequentially number each
initial separate item or drawing submitted under each specific Section number.
c. Last use a letter, A-Z, indicating the resubmission of the same drawing (i.e.
A=2nd submission, B=3rd submission, C=4th submission, etc.). A typical
submittal number would be as follows:
03 30 00-08-B
1) 03 30 00 is the Specification Section for Concrete
2) 08 is the eighth initial submittal under this Specification Section
3) B is the third submission (second resubmission) of that particular shop
drawing
C. Contractor Certification
Review shop drawings, product data and samples, including those by
subcontractors, prior to submission to determine and verify the following:
a. Field measurements
b. Field construction criteria
c. Catalog numbers and similar data
d. Conformance with the Contract Documents
2. Provide each shop drawing, sample and product data submitted by the Contractor
with a Certification Statement affixed including:
a. The Contractor's Company name
b. Signature of submittal reviewer
c. Certification Statement
1) `By this submittal, I hereby represent that I have determined andverified
field measurements, field construction criteria, materials, dimensions,
catalog numbers and similar data and I have checked and coordinated each
item with other applicable approved shop drawings."
D. Submittal Format
1. Fold shop drawings larger than 8 '/2 inches x 11 inches to 8 '/z inches x 11 inches.
2. Bind shop drawings and product data sheets together.
3. Order
a. Cover Sheet
1) Description of Packet
2) Contractor Certification
b. List of items / Table of Contents
c. Product Data /Shop Drawings/Samples /Calculations
E. Submittal Content
1. The date of submission and the dates of any previous submissions
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised August 30, 2013
006125-3
DAP PROJECT RECORD DOCUMENTS
Page 3 of 7
1
2. The Project title and number
2
3. Contractor identification
3
4. The names of:
4
a. Contractor
5
b. Supplier
6
c. Manufacturer
7
5. Identification of the product, with the Specification Section number, page and
8
paragraph(s)
9
6. Field dimensions, clearly identified as such
10
7. Relation to adjacent or critical features of the Work or materials
11
8. Applicable standards, such as ASTM or Federal Specification numbers
12
9. Identification by highlighting of deviations from Contract Documents
13
10. Identification by highlighting of revisions on resubmittals
14
11. An 8-inch x 3-inch blank space for Contractor and City stamps
15
F. Shop Drawings
16
1. As specified in individual Work Sections includes, but is not necessarily limitedto:
17
a. Custom -prepared data such as fabrication and erection/installation (working)
18
drawings
— 19
b. Scheduled information
20
c. Setting diagrams
21
d. Actual shopwork manufacturing instructions
22
e. Custom templates
23
f. Special wiring diagrams
24
g. Coordination drawings
25
h. Individual system or equipment inspection and test reports including:
26
1) Performance curves and certifications
27
i. As applicable to the Work
28
2. Details
29
a. Relation of the various parts to the main members and lines of the structure
30
b. Where correct fabrication of the Work depends upon fieldmeasurements
_ 31
Provide such measurements and note on the drawings prior to submitting for
32
approval.
33
G. Product Data
34
1. For submittals of product data for products included on the City's Standard Product
35
List, clearly identify each item selected for use on the Project.
36
2. For submittals of product data for products not included on the City's Standard
37
Product List, submittal data may include, but is not necessarily limited to:
38
a. Standard prepared data for manufactured products (sometimes referred to as
39
catalog data)
40
1) Such as the manufacturer's product specification and installation instructions
41
2) Availability of colors and patterns
42
3) Manufacturer's printed statements of compliances and applicability
43
4) Roughing -in diagrams and templates
44
5) Catalog cuts
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS —DEVELOPER AWARDED PROJECTS 101901
Revised August 30, 2013
i
AM
w
MM
i
00 61 25 - 4
DAP PROJECT RECORD DOCUMENTS
Page 4 of 7
1 6) Product photographs
2 7) Standard wiring diagrams
3 8) Printed performance curves and operational -range diagrams
4 9) Production or quality control inspection and test reports and certifications
5 10) Mill reports
6 11) Product operating and maintenance instructions and recommended spare -parts
7 listing and printed product warranties
8 12) As applicable to the Work
9 H. Samples
10 1. As specified in individual Sections, include, but are not necessarily limited to:
11 a. Physical examples of the Work such as:
12 1) Sections of manufactured or fabricated Work
13 2) Small cuts or containers of materials
14 3) Complete units of repetitively used products color/texture/pattern swatches and
15 range sets
16 4) Specimens for coordination of visual effect
17 5) Graphic symbols and units of Work to be used by the City for independent
18 inspection and testing, as applicable to the Work
19 I. Do not start Work requiring a shop drawing, sample or product data nor any material to be
20 fabricated or installed prior to the approval or qualified approval of such item.
21 1. Fabrication performed, materials purchased or on -site construction accomplished which
22 does not conform to approved shop drawings and data is at the Contractor's risk.
23 2. The City will not be liable for any expense or delay due to corrections or remedies
24 required to accomplish conformity.
25 3. Complete project Work, materials, fabrication, and installations in conformance with
26 approved shop drawings, applicable samples, and product data.
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
J. Submittal Distribution
1. Electronic Distribution
a. Confirm development of Project directory for electronic submittals to be uploaded
to City's Buzzsaw site, or another external FTP site approved by the City.
b. Shop Drawings
1) Upload submittal to designated project directory and notify appropriate City
representatives via email of submittal posting.
2) Hard Copies
a) 3 copies for allsubmittals
b) If Contractor requires more than 1 hard copy of Shop Drawings returned,
Contractor shall submit more than the number of copies listed above.
c. Product Data
1) Upload submittal to designated project directory and notify appropriate City
representatives via email of submittal posting.
2) Hard Copies
a) 3 copies for all submittals
d. Samples
1) Distributed to the Project Representative
2. Hard Copy Distribution (if required in lieu of electronic distribution)
a. Shop Drawings
1) Distributed to the City
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised August 30, 2013
00 61 25 - 5
DAP PROJECT RECORD DOCUMENTS
MR
W
on
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
Page 5 of 7
2) Copies
a. 8 copies for mechanical submittals
b. 7 copies for all othersubmittals
c. If Contractor requires more than 3 copies of Shop Drawings returned,
Contractor shall submit more than the number of copies listed above.
b. Product Data
1) Distributed to the City
2) Copies
a) 4copies
c. Samples
1) Distributed to the Project Representative
2) Copies
a) Submit the number stated in the respective Specification Sections.
3. Distribute reproductions of approved shop drawings and copies of approved product
data and samples, where required, to the job site file and elsewhere as directed by
the City.
a. Provide number of copies as directed by the City but not exceeding the number
previously specified.
K. Submittal Review
1. The review of shop drawings, data and samples will be for general conformance with
the design concept and Contract Documents. This is not to be construed as:
a. Permitting any departure from the Contract requirements
b. Relieving the Contractor of responsibility for any errors, including details,
dimensions, and materials
c. Approving departures from details furnished by the City, except as otherwise
provided herein
2. The review and approval of shop drawings, samples or product data by the City does
not relieve the Contractor from his/her responsibility with regard to the fulfillment of
the terms of the Contract.
a. All risks of error and omission are assumed by the Contractor, and the City will
have no responsibility therefore.
3. The Contractor remains responsible for details and accuracy, for coordinating the Work
with all other associated work and trades, for selecting fabrication processes, for
techniques of assembly and for performing Work in a safe manner.
4. If the shop drawings, data or samples as submitted describe variations and show a
departure from the Contract requirements which City finds to be in the interest ofthe
City and to be so minor as not to involve a change in Contract Price or time for
performance, the City may return the reviewed drawings without noting an exception.
5. Submittals will be returned to the Contractor under 1 of the following codes:
a. Code 1
1) "NO EXCEPTIONS TAKEN" is assigned when there are no notations or
comments on the submittal.
a. When returned under this code the Contractor may release the equipment
and/or material for manufacture.
b. Code 2
1) "EXCEPTIONS NOTED". This code is assigned when a confirmation of the
notations and comments IS NOT required by the Contractor.
CITY OF FORT WORTH Milam Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised August 30, 2013
00 61 25 - 6
DAP PROJECT RECORD DOCUMENTS
Page 6 of 7
1
a. The Contractor may release the equipment or material for manufacture;
2
however, all notations and comments must be incorporated into the final
3
product.
4
c. Code 3
5
1) "EXCEPTIONS NOTED/RESUBMIT". This combination of codes is assigned
6
when notations and comments are extensive enough to require a resubmittal of
7
the package.
_ 8
a) The Contractor may release the equipment or material for manufacture;
9
however, all notations and comments must be incorporated into the final
10
product.
11
b) This resubmittal is to address all comments, omissions and non -conforming
12
items that were noted.
13
c) Resubmittal is to be received by the City within 15 Calendar Days of the
14
date of the City's transmittal requiring the resubmittal.
15
d. Code4
16
1) "NOT APPROVED" is assigned when the submittal does not meet the intent of
17
the Contract Documents.
18
a) The Contractor must resubmit the entire package revised to bring the
19
submittal into conformance.
20
b) It may be necessary to resubmit using a different manufacturer/vendor to
�* 21
meet the Contract Documents.
22
6. Resubmittals
23
a. Handled in the same manner as first submittals
24
1) Corrections other than requested by the City
25
2) Marked with revision triangle or other similar method
26
a) At Contractor's risk if notmarked
27
b. Submittals for each item will be reviewed no more than twice at the City's expense.
28
1) All subsequent reviews will be performed at times convenient to the City and at
29
the Contractor's expense, based on the City's or City Representative's then
30
prevailing rates.
31
2) Provide Contractor reimbursement to the City within 30 Calendar Days for all
32
such fees invoiced by the City.
33
c. The need for more than 1 resubmission or any other delay in obtaining City's
34
review of submittals, will not entitle the Contractor to an extension of Contract
35
Time.
36
7. Partial Submittals
37
a. City reserves the right to not review submittals deemed partial, at the City's
38
discretion.
39
b. Submittals deemed by the City to be not complete will be returned to the Contractor
—' 40
and will be considered "Not Approved" until resubmitted.
41
c. The City may at its option provide a list or mark the submittal directing the
42
Contractor to the areas that are incomplete.
43
8. If the Contractor considers any correction indicated on the shop drawings to constitute a
44
change to the Contract Documents, then written notice must be provided thereof to the
45
Developer at least 7 Calendar Days prior to release for manufacture.
46
9. When the shop drawings have been completed to the satisfaction of the City,the
47
Contractor may carry out the construction in accordance therewith and no further
48
changes therein except upon written instructions from the City.
CITY OF FORT WORTH Milam Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised August 30, 2013
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
006125-7
DAP PROJECT RECORD DOCUMENTS
Page 7 of 7
10. Each submittal, appropriately coded, will be returned within 30 CalendarDays
following receipt of submittal by the City.
L. Mock ups
1. Mock Up units as specified in individual Sections, include, but are notnecessarily
limited to, complete units of the standard of acceptance for that type of Work to be used
on the Project. Remove at the completion of the Work or when directed.
M. Qualifications
If specifically required in other Sections of these Specifications, submit a P.E. Certification
for each item required.
N. Request for Information (RFI)
1. Contractor Request for additional information
a. Clarification or interpretation of the contract documents
b. When the Contractor believes there is a conflict between Contract Documents
c. When the Contractor believes there is a conflict between the Drawings and
Specifications
1) Identify the conflict and request clarification
2. Sufficient information shall be attached to permit a written response without further
information.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 — PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
12/20/2012 D. Johnson 1.4.K.8. Working Days modified to Calendar Days
CITY OF FORT WORTH Milam Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised August 30, 2013
..
Mt
006125-1
DAP PROJECT RECORD DOCUMENTS
Page 1 of 7
1
SECTION 0135 13
2
SPECIAL PROJECT PROCEDURES
3
[Text in Blue is for information or guidance. Remove all blue text in the final project document.]
4
PART 1- GENERAL
5
1.1 SUMMARY
6
A. Section Includes:
7
1. The procedures for special project circumstances that includes, but is not limited to:
8
a. Coordination with the Texas Department of Transportation
9
b. Work near High Voltage Lines
10
c. Confined Space Entry Program
11
d. Air Pollution Watch Days
12
e. Use of Explosives, Drop Weight, Etc.
13
f. Water Department Notification
14
g. Public Notification Prior to Beginning Construction
15
h. Coordination with United States Army Corps ofEngineers
16
i. Coordination within Railroad permits areas
17
j. Dust Control
18
k. Employee Parking
19
1. [Coordination with North Central Texas Council of Governments Clean
20
Construction Specification [remove if not required])
21
B. Deviations from this City of Fort Worth Standard Specification
22
1. None.
23
C. Related Specification Sections include, but are not necessarily limited to:
24
1. Division 0 — Bidding Requirements, Contract Forms and Conditions of theContract
25
2. Division 1 —General Requirements
26
3. Section 33 12 25 — Connection to Existing WaterMains
27
.�
28
1.2 REFERENCES
29
A. Reference Standards
.�
30
1. Reference standards cited in this Specification refer to the current reference standard
31
published at the time of the latest revision date logged at the end of this Specification,
32
unless a date is specifically cited.
33
2. Health and Safety Code, Title 9. Safety, Subtitle A. Public Safety, Chapter 752. High
34
Voltage Overhead Lines.
35
3. North Central Texas Council of Governments (NCTCOG) — Clean Construction
36
Specification
37
1.3 ADMINISTRATIVE REQUIREMENTS
38
A. Coordination with the Texas Department of Transportation
39
1. When work in the right-of-way which is under the jurisdiction of the Texas Department
40
of Transportation (TxDOT):
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised August, 30, 2013
MN
M
,W
006125-2
DAP PROJECT RECORD DOCUMENTS
Page 2 of 7
1 a. Notify the Texas Department of Transportation prior to commencing any work
2 therein in accordance with the provisions of the permit
3 b. All work performed in the TxDOT right-of-way shall be performed in compliance
4 with and subject to approval from the Texas Department of Transportation
5 B. Work near High Voltage Lines
6 1. Regulatory Requirements
7 a. All Work near High Voltage Lines (more than 600 volts measured between
8 conductors or between a conductor and the ground) shall be in accordance with
9 Health and Safety Code, Title 9, Subtitle A, Chapter 752.
10 2. Warning sign
11 a. Provide sign of sufficient size meeting all OSHA requirements.
12 3. Equipment operating within 10 feet of high voltage lines will require the following
13 safety features
14 a. Insulating cage -type of guard about the boom or arm
15 b. Insulator links on the lift hook connections for back hoes ordippers
16 c. Equipment must meet the safety requirements as set forth by OSHA and the safety
17 requirements of the owner of the high voltage lines
18 4. Work within 6 feet of high voltage electric lines
19 a. Notification shall be given to:
20 1) The power company (example: ONCOR)
21 a) Maintain an accurate log of all such calls to power company and record
22 action taken in each case.
23 b. Coordination with powercompany
24 1) After notification coordinate with the power company to:
25 a) Erect temporary mechanical barriers, de -energize the lines, or raise or lower
26 the lines
27 c. No personnel may work within 6 feet of a high voltage line before the above
28 requirements have been met.
29 C. Confined Space Entry Program
30 1. Provide and follow approved Confined Space Entry Program in accordance with OSHA
31 requirements.
32 2. Confined Spaces include:
33 a. Manholes
34 b. All other confined spaces in accordance with OSHA's Permit Requiredfor
35 Confined Spaces
36 D. Use of Explosives, Drop Weight, Etc.
37 1. When Contract Documents permit on the project the following willapply:
38 a. Public Notification
39 1) Submit notice to City and proof of adequate insurance coverage, 24 hours prior
40 to commencing.
41 2) Minimum 24-hour public notification in accordance with Section 0131 13
42 E. Water Department Coordination
43
44 1. During the construction of this project, it will be necessary to deactivate, for a period of
45 time, existing lines. The Contractor shall be required to coordinate with the Water
46 Department to determine the best times for deactivating and activating those lines.
CITY OF FORT WORTH Milan Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised August, 30, 20I3
00 61 25 - 3
DAP PROJECT RECORD DOCUMENTS
Page 3 of 7
1 2. Coordinate any event that will require connecting to or the operation of an existing City
2 water line system with the City's representative.
3 a. Coordination shall be in accordance with Section 33 12 25.
4 b. If needed, obtain a hydrant water meter from the Water Department for use during
5 the life of named project.
6 C. In the event that a water valve on an existing live system be turned off and on to
7 accommodate the construction of the project is required, coordinate this activity
8 through the appropriate City representative.
9 1) Do not operate water line valves of existing water system.
10 a) Failure to comply will render the Contractor in violation of Texas Penal
11 Code Title 7, Chapter 28.03 (Criminal Mischief) and the Contractor will be
12 prosecuted to the full extent of the law.
13 b) In addition, the Contractor will assume all liabilities and responsibilities as
14 a result of these actions.
15 F. Public Notification Prior to Beginning Construction
16 1. Prior to beginning construction on any block in the project, on a block by block basis,
17 prepare and deliver a notice or flyer of the pending construction to the front door of each
18 residence or business that will be impacted by construction. The notice shall be prepared
19 as follows:
20 a. Post notice or flyer 7 days prior to beginning any construction activity on each
21 block in the project area.
22 1) Prepare flyer on the Contractor's letterhead and include the following
23 information:
24 a) Name ofProject
25 b) City Project No (CPN)
26 c) Scope of Project (i.e. type of construction activity)
27 d) Actual construction duration within the block
28 e) Name of the contractor's foreman and phone number
29 f) Name of the City's inspector and phone number
30 g) City's after-hours phone number
31 2) A sample of the `pre -construction notification' flyer is attached as Exhibit A.
32 3) Submit schedule showing the construction start and fmish time for each block
33 of the project to the inspector.
34 4) Deliver flyer to the City Inspector for review prior to distribution.
35 b. No construction will be allowed to begin on any block until the flyer is delivered to
36 all residents of the block.
37 G. Public Notification of Temporary Water Service Interruption during Construction
38 1. In the event it becomes necessary to temporarily shut down water serviceto
39 residents or businesses during construction, prepare and deliver a notice or flyer of
40 the pending interruption to the front door of each affected resident.
41 2. Prepared notice as follows:
42 a. The notification or flyer shall be posted 24 hours prior to the temporary
43 interruption.
44 b. Prepare flyer on the contractor's letterhead and include the following information:
45 1) Name of the project
46 2) City Project Number
47 3) Date of the interruption of service
48 4) Period the interruption will take place
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised August, 30, 2013
00 61 25 - 4
DAP PROJECT RECORD DOCUMENTS
Page 4 of 7
1 5) Name of the contractor's foreman and phone number
2 6) Name of the City's inspector and phone number
3 c. A sample of the temporary water service interruption notification is attached as
4 Exhibit B.
5 d. Deliver a copy of the temporary interruption notification to the City inspector for
6 review prior to being distributed.
7 e. No interruption of water service can occur until the flyer has been delivered to all
8 affected residents and businesses.
9 f. Electronic versions of the sample flyers can be obtained from the Project
10 Construction Inspector.
11 H. Coordination with United States Army Corps of Engineers (USACE)
12 1. At locations in the Project where construction activities occur in areas where USACE
13 permits are required, meet all requirements set forth in each designated permit.
14 I. Coordination within Railroad Permit Areas
15 1. At locations in the project where construction activities occur in areas where railroad
16 permits are required, meet all requirements set forth in each designated railroad permit.
17 This includes, but is not limited to, provisions for:
18 a. Flagmen
19 b. Inspectors
20 c. Safety training
21 d. Additional insurance
22 e. Insurance certificates
23 f. Other employees required to protect the right-of-way and property of the Railroad
24 Company from damage arising out of and/or from the construction of the project.
25 Proper utility clearance procedures shall be used in accordance with thepermit
26 guidelines.
27 2. Obtain any supplemental information needed to comply with the railroad's
28 requirements.
29 J. Dust Control
30 1. Use acceptable measures to control dust at the Site.
31 a. If water is used to control dust, capture and properly dispose of waste water.
32 b. If wet saw cutting is performed, capture and properly dispose ofslurry.
33 K. Employee Parking
34 1. Provide parking for employees at locations approved by theCity.
35 L. {Coordination with North Central Texas Council of Governments (NCTCOG) Clean
36 Construction Specification [if required for the project]
37 1. Comply with equipment, operational, reporting and enforcement requirements set forth
38 in NCTCOG's Clean Construction Specification.)
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised August, 30, 2013
006125-5
DAP PROJECT RECORD DOCUMENTS
Page 5 of 7
1
1.4
SUBMITTALS [NOT USED]
2
1.5
ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
3
1.6
CLOSEOUT SUBMITTALS [NOT USED]
4
1.7
MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
5
1.8
QUALITY ASSURANCE [NOT USED]
6
1.9
DELIVERY, STORAGE, AND HANDLING [NOT USED]
7
1.10
FIELD [SITE] CONDITIONS [NOT USED]
8
1.11
WARRANTY [NOT USED]
9 PART 2 - PRODUCTS [NOT USED]
10 PART 3 - EXECUTION [NOT USED]
11 END OF SECTION
12
13
Revision Log
DATE NAME SUMMARY OF CHANGE
1.3.13 — Added requirement of compliance with Health and Safety Code, Title 9.
8/31/2012 D. Johnson Safety, Subtitle A. Public Safety, Chapter 752. High Voltage Overhead Lines.
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised August, 30, 2013
006125-6
DAP PROJECT RECORD DOCUMENTS
Page 6 of 7
1 EXHIBIT A
2 (To be printed on Contractor's Letterhead)
3
4
5
6 Date:
7
8 CPN No.:
9 Project Name:
10 Mapsco Location:
11 Limits of Construction:
12
13
14
15
16
17 THIS IS TO INFORM YOU THAT UNDER A CONTRACT WITH THE CITY OF FORT
18 WORTH, OUR COMPANY WILL WORK ON UTILITY LINES ON OR AROUND YOUR
19 PROPERTY.
20
21 CONSTRUCTION WILL BEGIN APPROXIMATELY SEVEN DAYS FROM THE DATE OF
22 THIS NOTICE.
23
24 IF YOU HAVE QUESTIONS ABOUT ACCESS, SECURITY, SAFETY OR ANY OTHER
25 ISSUE, PLEASE CALL:
26
27
28 Mr. <CONTRACTOR'S SUPERINTENDENT> AT <TELEPHONE NO.>
29
30 OR
31
32 Mr. <CITY INSPECTOR> AT < TELEPHONE NO.>
33
34 AFTER 4:30 PM OR ON WEEKENDS, PLEASE CALL (817) 392 8306
35
36 PLEASE KEEP THIS FLYER HANDY WHEN YOU CALL
37
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised August, 30, 2013
00 61 25 - 7
DAP PROJECT RECORD DOCUMENTS
Page 7 of
I EXHIBIT B
2
FoR� x
Dole NO. Xj=
ftolm I.anw.
NOTICE OF TEMPORARY WATER SERVICE
INTERRUPTION
DUE TO UTILITY IMPROVEMENTS IN YOUR NEIGHBORHOOD, YOUR
WATER SERVICE WILL BE INTERRUPTED ON
BETWEEN THE HOURS OF AND
IF YOU HAVE QUESTIONS ABOUT THIS SHUT -OUT, PLEASE CALL:
MR. AT
(CONTRACTORS SUPERINTENDENT) (TELEPHONE NUMBER)
OR
MR. AT
(CITY INSPECTOR) (TELEPHONE NUMBER)
THIS INCONVENIENCE WILL BE AS SHORT AS POSSIBLE.
THANK YOU,
,CONTRACTOR
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised August, 30, 2013
006125-1
DAP PROJECT RECORD DOCUMENTS
Page 1 of 2
1 SECTION 0145 23
2 TESTING AND INSPECTION SERVICES
3 PART 1 - GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Testing and inspection services procedures andcoordination
7 B. Deviations from this City of Fort Worth Standard Specification
8 1. None.
9 C. Related Specification Sections include, but are not necessarily limited to:
10 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of theContract
11 2. Division 1 —General Requirements
12 1.2 PRICE AND PAYMENT PROCEDURES
13 A. Measurement and Payment
14 1. Work associated with this Item is considered subsidiary to the various Items bid.
15 No separate payment will be allowed for this Item.
16 a. Contractor is responsible for performing, coordinating, and payment ofall
17 Quality Control testing.
18 b. City is responsible for performing and payment for first set ofQuality
19 Assurance testing.
20 1) If the first Quality Assurance test performed by the City fails, the
21 Contractor is responsible for payment of subsequent Quality Assurance
22 testing until a passing test occurs.
23 a) Final acceptance will not be issued by City until all required payments
24 for testing by Contractor have been paid in full.
25 1.3 REFERENCES [NOT USED]
26 1.4 ADMINISTRATIVE REQUIREMENTS
27 A. Testing
28 1. Complete testing in accordance with the Contract Documents.
29 2. Coordination
30 a. When testing is required to be performed by the City, notify City, sufficiently
31 in advance, when testing is needed.
32 b. When testing is required to be completed by the Contractor, notify City,
33 sufficiently in advance, that testing will be performed.
34 3. Distribution of TestingReports
35 a. Electronic Distribution
36 1) Confirm development of Project directory for electronic submittals to be
37 uploaded to City's Buzzsaw site, or another form of distribution approved
38 by the City.
39 2) Upload test reports to designated project directory and notify appropriate
40 City representatives via email of submittal posting.
41 3) Hard Copies
CITY OF FORT WORTH Milam Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised August 30, 2013
at
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
006125-2
DAP PROJECT RECORD DOCUMENTS
Page 2 of 2
a) 1 copy for all submittals submitted to the Project Representative
b. Hard Copy Distribution (if required in lieu of electronic distribution)
1) Tests performed by City
a) Distribute 1 hard copy to theContractor
2) Tests performed by the Contractor
a) Distribute 3 hard copies to City's Project Representative
4. Provide City's Project Representative with trip tickets for each delivered
load of Concrete or Lime material including the following information:
a. Name of pit
b. Date ofdelivery
c. Material delivered
B. Inspection
1. Inspection or lack of inspection does not relieve the Contractor from obligation to
perform work in accordance with the Contract Documents.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
DATE NAME
END OF SECTION
Revision Log
SUMMARY OF CHANGE
CITY OF FORT WORTH Milam Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised August 30, 2013
006125-1
— DAP PROJECT RECORD DOCUMENTS
Page 1 of 4
1 SECTION 0150 00
2 TEMPORARY FACILITIES AND CONTROLS
3 PART 1- GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Provide temporary facilities and controls needed for the Work including, but not
7 necessarily limited to:
8 a. Temporary utilities
9 b. Sanitary facilities
10 c. Storage Sheds and Buildings
11 d. Dustcontrol
12 e. Temporary fencing of the construction site
13 B. Deviations from this City of Fort Worth Standard Specification
14 1. None.
15
C. Related Specification Sections include, but are not necessarily limited to:
- 16
1. Division 0 - Bidding Requirements, Contract Forms and Conditions of the Contract
17
2. Division 1 -General Requirements
18
1.2 PRICE AND PAYMENT PROCEDURES
19
A. Measurement and Payment
20
1. Work associated with this Item is considered subsidiary to the various Items bid.
- 21
No separate payment will be allowed for this Item.
22
1.3 REFERENCES [NOT USED]
_ 23
1.4 ADMINISTRATIVE REQUIREMENTS
24
A. Temporary Utilities
25
1. Obtaining Temporary Service
26
a. Make arrangements with utility service companies for temporary services.
27
b. Abide by rules and regulations of utility service companies or authorities
28
having jurisdiction.
- 29
c. Be responsible for utility service costs until Work is approved for Final
30
Acceptance.
31
1) Included are fuel, power, light, heat and other utility services necessary for
32
execution, completion, testing and initial operation of Work.
33
2. Water
34
a. Contractor to provide water required for and in connection with Work to be
- 35
performed and for specified tests of piping, equipment, devices or other use as
36
required for the completion of the Work.
37
b. Provide and maintain adequate supply of potable water fordomestic
38
consumption by Contractor personnel and City's Project Representatives.
39
c. Coordination
40
1) Contact City 1 week before water for construction is desired
41
CITY OF FORT WORTH Milam Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised JULY 1, 2011
re
006125-2
DAP PROJECT RECORD DOCUMENTS
Page 2 of 4
1 d. Contractor Payment for Construction Water
2 1) Obtain construction water meter from City for payment as billed by City's
3 established rates.
4 3. Electricity andLighting
5 a. Provide and pay for electric powered service as required for Work, including
6 testing of Work.
7 Provide power for lighting, operation of equipment, or other use.
8 b. Electric power service includes temporary power service or generatorto
9 maintain operations during scheduled shutdown.
10 4. Telephone
11 a. Provide emergency telephone service at Site for use by Contractor personnel
12 and others performing work or furnishing services at Site.
13 5. Temporary Heat andVentilation
14 a. Provide temporary heat as necessary for protection or completion of Work.
15 b. Provide temporary heat and ventilation to assure safe workingconditions.
16 B. Sanitary Facilities
17 1. Provide and maintain sanitary facilities for persons onSite.
18 a. Comply with regulations of State and local departments of health.
19 2. Enforce use of sanitary facilities by construction personnel at job site.
20 a. Enclose and anchor sanitary facilities.
21 b. No discharge will be allowed from these facilities.
22 c. Collect and store sewage and waste so as not to cause nuisance or health
23 problem.
24 d. Haul sewage and waste off -site at no less than weekly intervals andproperly
25 dispose in accordance with applicable regulation.
26 3. Locate facilities near Work Site and keep clean and maintained throughout Project.
27 4. Remove facilities at completion ofProject
28 C. Storage Sheds and Buildings
29 1. Provide adequately ventilated, watertight, weatherproof storage facilities withfloor
30 above ground level for materials and equipment susceptible to weather damage.
31 2. Storage of materials not susceptible to weather damage may be on blocks off
32 ground.
33 3. Store materials in a neat and orderlymanner.
34 a. Place materials and equipment to permit easy access for identification,
35 inspection and inventory.
36 4. Equip building with lockable doors and lighting and provide electrical service for
37 equipment space heaters and heating or ventilation as necessary to provide storage
38 environments acceptable to specified manufacturers.
39 5. Fill and grade site for temporary structures to provide drainage awayfrom
40 temporary and existing buildings.
41 6. Remove building from site prior to Final Acceptance.
42 D. Temporary Fencing
43 1. Provide and maintain for the duration or construction when required in contract
44 documents
45 E. Dust Control
CITY OF FORT WORTH Milam Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised JULY 1, 20I 1
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
00 61 25 - 3
DAP PROJECT RECORD DOCUMENTS
Page 3 of 4
1. Contractor is responsible for maintaining dust control through the duration of the
project.
a. Contractor remains on -call at all times
b. Must respond in a timely manner
F. Temporary Protection of Construction
1. Contractor or subcontractors are responsible for protecting Work from damage due
to weather.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION
3.1 INSTALLERS [NOT USED]
3.2 EXAMINATION [NOT USED]
3.3 PREPARATION [NOT USED]
3.4 INSTALLATION
A. Temporary Facilities
1. Maintain all temporary facilities for duration of construction activities as needed.
3.5 [REPAIR] / [RESTORATION]
3.6 RE -INSTALLATION
3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED]
3.8 SYSTEM STARTUP [NOT USED]
3.9 ADJUSTING [NOT USED]
3.10 CLEANING [NOT USED]
3.11 CLOSEOUT ACTIVITIES
A. Temporary Facilities
1. Remove all temporary facilities and restore area after completion of the Work,
to a condition equal to or better than prior to start of Work.
CITY OF FORT WORTH Milam Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised JULY 1, 2011
00 61 25 - 4
DAP PROJECT RECORD DOCUMENTS
Page 4 of 4
1 3.12 PROTECTION [NOT USED]
2 3.13 MAINTENANCE [NOT USED]
3 3.14 ATTACHMENTS [NOT USED]
4 END OF SECTION
5
Revision Log
DATE NAME SUMMARY OF CHANGE
6
MW
mm CITY OF FORT WORTH Milam Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised JULY 1, 2011
01 55 26 -1
DAP PROJECT RECORD DOCUMENTS
Page 1 of 2
1 SECTION 0155 26
2 STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
3 PART 1- GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Administrative procedures for:
7 a. Street Use Permit
8 b. Modification of approved traffic control
9 c. Removal of Street Signs
10 B. Deviations from this City of Fort Worth Standard Specification
T 11 1. None.
12 C. Related Specification Sections include, but are not necessarily limited to:
13 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of theContract
14 2. Division 1 —General Requirements
15 3. Section 34 71 13 —Traffic Control
16 1.2 PRICE AND PAYMENT PROCEDURES
17 A. Measurement and Payment
18 1. Work associated with this Item is considered subsidiary to the various Items bid.
19 No separate payment will be allowed for this Item.
20 1.3 REFERENCES
21 A. Reference Standards
22 1. Reference standards cited in this specification refer to the current reference standard
23 published at the time of the latest revision date logged at the end of this
24 specification, unless a date is specifically cited.
25 2. Texas Manual on Uniform Traffic Control Devices(TMUTCD).
26 1.4 ADMINISTRATIVE REQUIREMENTS
27 A. Traffic Control
28 1. General
29 a. When traffic control plans are included in the Drawings, provide Traffic
30 Control in accordance with Drawings and Section 34 71 13.
31 b. When traffic control plans are not included in the Drawings, prepare traffic
32 control plans in accordance with Section 34 71 13 and submit to City for
33 review.
34 1) Allow minimum 10 working days for review of proposed Traffic Control.
35 B. Street Use Permit
36 1. Prior to installation of Traffic Control, a City Street Use Permit isrequired.
37 a. To obtain Street Use Permit, submit Traffic Control Plans to City
38 Transportation and Public Works Department.
39 1) Allow a minimum of 5 working days for permit review.
CITY OF FORT WORTH Milam Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised July 1, 2011
so
M
on
ow
l.J
P,
01 55 26 - 2
DAP PROJECT RECORD DOCUMENTS
Page 2 of 2
1 2) Contractor's responsibility to coordinate review of Traffic Control plans for
2 Street Use Permit, such that construction is not delayed.
3 C. Modification to Approved Traffic Control
4 1. Prior to installation traffic control:
5 a. Submit revised traffic control plans to City Department Transportation and
6 Public Works Department.
7 1) Revise Traffic Control plans in accordance with Section 34 71 13.
8 2) Allow minimum 5 working days for review of revised Traffic Control.
9 3) It is the Contractor's responsibility to coordinate review of Traffic Control
10 plans for Street Use Permit, such that construction is not delayed.
11 D. Removal of Street Sign
12 1. If it is determined that a street sign must be removed for construction, then contact
13 City Transportation and Public Works Department, Signs and Markings Division to
14 remove the sign.
15 E. Temporary Signage
16 1. In the case of regulatory signs, replace permanent sign with temporary sign meeting
17 requirements of the latest edition of the Texas Manual on Uniform Traffic Control
18 Devices (MUTCD).
19 2. Install temporary sign before the removal of permanentsign.
20 3. When construction is complete, to the extent that the permanent sign canbe
21 reinstalled, contact the City Transportation and Public Works Department, Signs
22 and Markings Division, to reinstall the permanent sign.
23 F. Traffic Control Standards
24 1. Traffic Control Standards can be found on the City's Buzzsaw website.
25
1.5
SUBMITTALS [NOT USED]
26
1.6
ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
27
1.7
CLOSEOUT SUBMITTALS [NOT USED]
28
1.8
MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
29
1.9
QUALITY ASSURANCE [NOT USED]
30
1.10
DELIVERY, STORAGE, AND HANDLING [NOT USED]
31 1.11 FIELD [SITE] CONDITIONS [NOT USED]
32 1.12 WARRANTY [NOT USED]
33 PART 2 - PRODUCTS [NOT USED]
34 PART 3 - EXECUTION [NOT USED]
35 END OF SECTION
Revision Log
DATE NAME SUNDAARY OF CHANGE
CITY OF FORT WORTH Milam Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised July 1, 2011
006125-1
DAP PROJECT RECORD DOCUMENTS
Page 1 of 3
1 SECTION 0157 13
2 STORM WATER POLLUTION PREVENTION
3 PART 1- GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Procedures for Storm Water Pollution Prevention Plans
7 B. Deviations from this City of Fort Worth Standard Specification
8 1. None.
9 C. Related Specification Sections include, but are not necessarily limited to:
10 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
11 2. Division 1 —General Requirements
12 3. Section 3125 00 — Erosion and Sediment Control
13 1.2 PRICE AND PAYMENT PROCEDURES
14 A. Measurement and Payment
15 1. Construction Activities resulting in less than 1 acre ofdisturbance
16 A. Work associated with this Item is considered subsidiary to the variousltems
17 bid. No separate payment will be allowed for this Item.
18 2. Construction Activities resulting in greater than 1 acre ofdisturbance
19 Measurement and Payment shall be in accordance with Section 3125 00.
20 1.3 REFERENCES
21 A. Abbreviations and Acronyms
22 1. Notice of Intent: NOI
23 2. Notice of Termination: NOT
24 3. Storm Water Pollution Prevention Plan: SWPPP
25 4. Texas Commission on Environmental Quality: TCEQ
26 5. Notice of Change: NOC
27 B. Reference Standards
28 1. Reference standards cited in this Specification refer to the current reference
29 standard published at the time of the latest revision date logged at the end ofthis
30 Specification, unless a date is specifically cited.
31 2. Integrated Storm Management (iSWM) Technical Manual for Construction
32 Controls
33 1.4 ADMINISTRATIVE REQUIREMENTS
34 A. General
35 1. Contractor is responsible for resolution and payment of any fines issued associated
36 with compliance to Stormwater Pollution Prevention Plan.
37
38 B. Construction Activities resulting in:
CITY OF FORT WORTH Milam Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised July 1, 2011
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
00 61 25 - 2
DAP PROJECT RECORD DOCUMENTS
Page 2 of 3
1. Less than 1 acre ofdisturbance
a. Provide erosion and sediment control in accordance with Section 3125 00 and
Drawings.
2. 1 to less than 5 acres ofdisturbance
a. Texas Pollutant Discharge Elimination System (TPDES) General Construction
Permit is required
b. Complete SWPPP in accordance with TCEQrequirements
1) TCEQ Small Construction Site Notice Required under general permit
TXR150000
a) Sign and post at job site
b) Prior to Preconstruction Meeting, send 1 copy to City Department of
Transportation and Public Works, Environmental Division, (817) 392-
6088.
2) Provide erosion and sediment control in accordance with:
a) Section 3125 00
b) The Drawings
c) TXR150000 General Permit
d) SWPPP
e) TCEQrequirements
3. 5 acres or more ofDisturbance
a. Texas Pollutant Discharge Elimination System (TPDES) General Construction
Permit is required
b. Complete SWPPP in accordance with TCEQrequirements
1) Prepare a TCEQ NOI form and submit to TCEQ along with required fee
a) Sign and post at job site
b) Send copy to City Department of Transportation and Public Works,
Environmental Division, (817) 392-6088.
2) ' TCEQ Notice of Change required if making changes or updates to NOI
3) Provide erosion and sediment control in accordance with:
a) Section 3125 00
b) The Drawings
c) TXR150000 General Permit
d) SWPPP
e) TCEQrequirements
4) Once the project has been completed and all the closeout requirements of
TCEQ have been met a TCEQ Notice of Termination can be submitted.
a) Send copy to City Department of Transportation and Public Works,
Environmental Division, (817) 392-6088.
39 1.5 SUBMITTALS
40
41
42
43
44
45
46
47
A. SWPPP
Submit in accordance with Section 0133 00, except as statedherein.
a. Prior to the Preconstruction Meeting, submit a draft copy of SWPPP to the City
as follows:
1) 1 copy to the City Project Manager
a) City Project Manager will forward to the City Department of
Transportation and Public Works, Environmental Division for review
CITY OF FORT WORTH Milam Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised July 1, 2011
00 61 25 - 3
DAP PROJECT RECORD DOCUMENTS
Page 3 of 3
1
B. Modified SWPPP
2
1. If the SWPPP is revised during construction, resubmit modified SWPPP to the City
3
in accordance With Section 01 33 00.
4
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
5
1.7 CLOSEOUT SUBMITTALS [NOT USED]
6
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
7
1.9 QUALITY ASSURANCE [NOT USED]
8
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
9
1.11 FIELD [SITE] CONDITIONS [NOT USED]
10
1.12 WARRANTY [NOT USED]
11
PART 2 - -PRODUCTS [NOT USED]
12
PART 3 - EXECUTION [NOT USED]
13
END OF SECTION
14
Revision Log
DATE NAME SUMMARY OF CHANGE
15
M
CITY OF FORT WORTH Mil am Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised July 1, 2011
i
PM
.w
C J
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
006125-1
DAP PROJECT RECORD DOCUMENTS
Page I of 2
SECTION 0160 00
PRODUCT REQUIREMENTS
PART 1- GENERAL
1.1 SUMMARY
A. Section Includes:
1. References for Product Requirements and City Standard Products List
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 — Bidding Requirements, Contract Forms and Conditions of theContract
2. Division 1 —General Requirements
1.2 PRICE AND PAYMENT PROCEDURES [NOT USED]
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. A list of City approved products for use is located on Buzzsaw as follows:
1. Resources\02 - Construction Documents\Standard ProductsList
B. Only products specifically included on City's Standard Product List in these Contract
Documents shall be allowed for use on the Project.
1. Any subsequently approved products will only be allowed for use upon specific
approval by the City.
C. Any specific product requirements in the Contract Documents supersede similar
products included on the City's Standard Product List.
The City reserves the right to not allow products to be used for certain projects even
though the product is listed on the City's Standard Product List.
D. Although a specific product is included on City's Standard Product List, notall
products from that manufacturer are approved for use, including but not limited to, that
manufacturer's standard product.
E. See Section 01 33 00 for submittal requirements of Product Data included on City's
Standard Product List.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
CITY OF FORT WORTH Milam Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised April 7, 2014
00 61 25 - 2
DAP PROJECT RECORD DOCUMENTS
Page 2 of 2
1 1.12 WARRANTY [NOT USED]
2 PART 2 - PRODUCTS [NOT USED]
3 PART 3 - EXECUTION [NOT USED]
4 END OF SECTION
5
Revision Log
DATE NAME SUMMARY OF CHANGE
10/12/12 D. Johnson Modified Location of City's Standard Product List
4/7/2014 M.Domenech Revised for DAP application
.f
6
i
R�
PM
CITY OF FORT WORTH Milam Street Sanitary Sewer Extensions
PM STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised April 7, 2014
an 1
2
on
T
w
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
016600-1
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 1 of 3
SECTION 0166 00
PRODUCT STORAGE AND HANDLING REQUIREMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Scheduling of productdelivery
2. Packaging of products fordelivery
3. Protection of products against damage from:
a. Handling
b. Exposure to elements or harsh environments
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 — Bidding Requirements, Contract Forms and Conditions of theContract
2. Division 1 —General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY AND HANDLING
A. Delivery Requirements
1. Schedule delivery of products or equipment as required to allow timely installation
and to avoid prolonged storage.
2. Provide appropriate personnel and equipment to receive deliveries.
3. Delivery trucks will not be permitted to wait extended periods of time on the Site
for personnel or equipment to receive the delivery.
4. Deliver products or equipment in manufacturer's original unbroken cartons or other
containers designed and constructed to protect the contents from physical or
environmental damage.
5. Clearly and fully mark and identify as to manufacturer, item and installation
location.
CITY OF FORT WORTH Milam Street Sanitary Sewer Extensions
"� STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised April 7, 2014
M"
i
,M
M
01 66 00 - 2
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 2 of 3
1 6. Provide manufacturer's instructions for storage andhandling.
2 B. Handling Requirements
3 1. Handle products or equipment in accordance with these Contract Documentsand
4 manufacturer's recommendations and instructions.
5 C. Storage Requirements
6 1. Store materials in accordance with manufacturer's recommendations and
7 requirements of these Specifications.
8 2. Make necessary provisions for safe storage of materials andequipment.
9 a. Place loose soil materials and materials to be incorporated into Work to prevent
10 damage to any part of Work or existing facilities and to maintain free access at
11 all times to all parts of Work and to utility service company installations in
12 vicinity of Work.
13 3. Keep materials and equipment neatly and compactly stored in locations that will
14 cause minimum inconvenience to other contractors, public travel, adjoining owners,
15 tenants and occupants.
16 a. Arrange storage to provide easy access for inspection.
17 4. Restrict storage to areas available on construction site for storage of materialand
18 equipment as shown on Drawings or approved by City's Project Representative.
19 5. Provide off -site storage and protection when on -site storage is notadequate.
20 a. Provide addresses of and access to off -site storage locations for inspection by
21 City's Project Representative.
22 6. Do not use lawns, grass plots or other private property for storage purposes without
23 written permission of owner or other person in possession or control of premises.
24 7. Store in manufacturers' unopened containers.
25 8. Neatly, safely and compactly stack materials delivered and stored along line of
26 Work to avoid inconvenience and damage to property owners and general public
27 and maintain at least 3 feet from fire hydrant.
28 9. Keep public and private driveways and street crossings open.
29 10. Repair or replace damaged lawns, sidewalks, streets or other improvementsto
30 satisfaction of City's Project Representative.
31 a. Total length which materials may be distributed along route of construction at
32 one time is 1,000 linear feet, unless otherwise approved in writing by City's
33 Project Representative.
34 1.11 FIELD [SITE] CONDITIONS [NOT USED]
35 1.12 WARRANTY [NOT USED]
36 PART 2 - PRODUCTS [NOT USED]
37 PART 3 - EXECUTION
38 3.1 INSTALLERS [NOT USED]
39 3.2 EXAMINATION [NOT USED]
40 3.3 PREPARATION [NOT USED]
41 3.4 ERECTION [NOT USED]
CITY OF FORT WORTH Milan Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised April 7, 2014
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
+ 22
23
24
25
26
016600-3
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 3 of 3
3.5 REPAIR / RESTORATION [NOT USED]
3.6 RE -INSTALLATION [NOT USED]
3.7 FIELD [OR] SITE QUALITY CONTROL
A. Tests and Inspections
1. Inspect all products or equipment delivered to the site prior to unloading.
B. Non -Conforming Work
1. Reject all products or equipment that are damaged, used or in any otherway
unsatisfactory for use on the project.
3.8 SYSTEM STARTUP [NOT USED]
3.9 ADJUSTING [NOT USED]
3.10 CLEANING [NOT USED]
3.11 CLOSEOUT ACTIVITIES [NOT USED]
3.12 PROTECTION
A. Protect all products or equipment in accordance with manufacturer's written directions.
B. Store products or equipment in location to avoid physical damage to items while in
storage.
C. Protect equipment from exposure to elements and keep thoroughly dry if required by
the manufacturer.
3.13 MAINTENANCE [NOT USED]
3.14 ATTACHMENTS [NOT USED]
DATE NAME
4/7/2014 M.Domenech
END OF SECTION
Revision Log
SUMMARY OF CHANGE
Revised for DAP application
CITY OF FORT WORTH Milam Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised April 7, 2014
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
01 74 23 - 1
DAP CLEANING
Page 1 of 3
SECTION 0174 23
CLEANING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Intermediate and final cleaning for Work not including special cleaning of closed
systems specified elsewhere
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 — Bidding Requirements, Contract Forms and Conditions of theContract
2. Division 1 —General Requirements
3. Section 32 92 13 — Hydro -Mulching, Seeding and Sodding
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Scheduling
1. Schedule cleaning operations so that dust and other contaminants disturbedby
cleaning process will not fall on newly painted surfaces.
2. Schedule final cleaning upon completion of Work and immediately prior to final
inspection.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 STORAGE, AND HANDLING
A. Storage and Handling Requirements
1. Store cleaning products and cleaning wastes in containers specifically designed for
those materials.
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
CITY OF FORT WORTH Milam Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised April 7, 2014
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
01 74 23 - 2
DAP CLEANING
Page 2 of 3
PART2-PRODUCTS
2.1 OWNER -FURNISHED [oR] OWNER-SUPPLIEDPRODUCTS [NOT USED]
2.2 MATERIALS
A. Cleaning Agents
1. Compatible with surface beingcleaned
2. New and uncontaminated
3. For manufactured surfaces
a. Material recommended by manufacturer
2.3 ACCESSORIES [NOT USED]
2.4 SOURCE QUALITY CONTROL [NOT USED]
PART 3 - EXECUTION
3.1 INSTALLERS [NOT USED]
3.2 EXAMINATION [NOT USED]
3.3 PREPARATION [NOT USED]
3.4 APPLICATION [NOT USED]
3.5 REPAIR / RESTORATION [NOT USED]
3.6 RE -INSTALLATION [NOT USED]
3.7 FIELD [oR] SITE QUALITY CONTROL [NOT USED]
3.8 SYSTEM STARTUP [NOT USED]
3.9 ADJUSTING [NOT USED]
3.10 CLEANING
A. General
1. Prevent accumulation of wastes that create hazardous conditions.
2. Conduct cleaning and disposal operations to comply with laws and safety orders of
governing authorities.
3. Do not dispose of volatile wastes such as mineral spirits, oil or paint thinnerin
storm or sanitary drains or sewers.
4. Dispose of degradable debris at an approved solid waste disposal site.
5. Dispose of nondegradable debris at an approved solid waste disposal site or in an
alternate manner approved by City and regulatory agencies.
6. Handle materials in a controlled manner with as few handlings aspossible.
7. Thoroughly clean, sweep, wash and polish all Work and equipment associated with
this project.
8. Remove all signs of temporary construction and activities incidental to construction
of required permanent Work.
9. If project is not cleaned to the satisfaction of the City, the City reserves the right to
have the cleaning completed at the expense of the Contractor.
10. Do not burn on -site.
CITY OF FORT WORTH Milani Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS —DEVELOPER AWARDED PROJECTS 101901
Revised April 7, 2014
01 74 23 - 3
DAP CLEANING
Page 3 of 3
1 B. Intermediate Cleaning during Construction
2 1. Keep Work areas clean so as not to hinder health, safety or convenience of
3 personnel in existing facility operations.
4 2. At maximum weekly intervals, dispose of waste materials, debris and rubbish.
5 3. Confine construction debris daily in strategically locatedcontainer(s):
6 a. Cover to prevent blowing by wind
7 b. Store debris away from construction or operational activities
8 c. Haul from site at a minimum of once per week
9 4. Vacuum clean interior areas when ready to receive finish painting.
10 a. Continue vacuum cleaning on an as -needed basis, until Final Acceptance.
11 5. Prior to storm events, thoroughly clean site of all loose or unsecured items, which
12 may become airborne or transported by flowing water during the storm.
13 C. Exterior (Site or Right of Way) Final Cleaning
14 1. Remove trash and debris containers fromsite.
15 a. Re -seed areas disturbed by location of trash and debris containers in accordance
16 with Section 32 92 13.
17 2. Sweep roadway to remove all rocks, pieces of asphalt, concrete or any other object
18 that may hinder or disrupt the flow of traffic along the roadway.
19 3. Clean any interior areas including, but not limited to, vaults, manholes, structures,
20 junction boxes and inlets.
21 4. If no longer required for maintenance of erosion facilities, and upon approvalby
22 City, remove erosion control from site.
23 Clean signs, lights, signals, etc.
24 3.11 CLOSEOUT ACTIVITIES [NOT USED]
25 3.12 PROTECTION [NOT USED]
26 3.13 MAINTENANCE [NOT USED]
27 3.14 ATTACHMENTS [NOT USED]
28
29
30
31 END OF SECTION
32
Revision Log
DATE NAME SUMMARY OF CHANGE
4n12014 M.Domenech Revised for DAP application
33
CITY OF FORT WORTH Milam Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised April 7, 2014
017719-1
—
DAP CLOSEOUT REQUIREMENTS
Page 1 of 3
—1
SECTION 0177 19
2
CLOSEOUT REQUIREMENTS
3
PART 1- GENERAL
4
1.1
SUMMARY
5
A. Section Includes:
6
1. The procedure for closing out acontract
i 7
B. Deviations from this City of Fort Worth Standard Specification
8
1. None.
9
C. Related Specification Sections include, but are not necessarily limited to:
10
1. Division 0 — Bidding Requirements, Contract Forms and Conditions of theContract
11
1. Division 1 —General Requirements
12
1.2
PRICE AND PAYMENT PROCEDURES
13
A. Measurement and Payment
14
1. Work associated with this Item is considered subsidiary to the various Items bid.
15
No separate payment will be allowed for this Item.
16
1.3
REFERENCES [NOT USED]
17
1.4
ADMINISTRATIVE REQUIREMENTS
18
A. Guarantees, Bonds and Affidavits
19
1. No application for final payment will be accepted until all guarantees, bonds,
i 20
certificates, licenses and affidavits required for Work or equipment as specified are
21
satisfactorily filed with the City.
22
B. Release of Liens or Claims
23
1. No application for final payment will be accepted until satisfactory evidence of
24
release of liens has been submitted to the City.
25
1.5
SUBMITTALS
26
A. Submit all required documentation to City's Project Representative.
27
1.6
INFORMATIONAL SUBMITTALS [NOT USED]
28
1.7
CLOSEOUT SUBMITTALS [NOT USED]
29
PART 2 - PRODUCTS [NOT USED]
30 PART 3 - EXECUTION
31 3.1 INSTALLERS [NOT USED]
32 3.2 EXAMINATION [NOT USED]
33 3.3 PREPARATION [NOT USED]
CITY OF FORT WORTH Milam Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised April 7, 2014
i
9"
No
Em
EW
01 77 19 - 2
DAP CLOSEOUT REQUIREMENTS
Page 2 of 3
1 3.4 CLOSEOUT PROCEDURE
2 A. Prior to requesting Final Inspection, submit:
3 1. Project Record Documents in accordance with Section 01 78 39
4 2. Operation and Maintenance Data, if required, in accordance with Section 01 78 23
5 B. Prior to requesting Final Inspection, perform final cleaning in accordance with Section
6 01 7423.
7 C. Final Inspection
8 1. After final cleaning, provide notice to the City Project Representative that the Work
9 is completed.
10 a. The City will make an initial Final Inspection with the Contractor present.
11 b. Upon completion of this inspection, the City will notify the Contractor, in
12 writing within 10 business days, of any particulars in which this inspection
13 reveals that the Work is defective or incomplete.
14 2. Upon receiving written notice from the City, immediately undertake the Work
15 required to remedy deficiencies and complete the Work to the satisfaction ofthe
16 City.
17 3. Upon completion of Work associated with the items listed in the City's written
18 notice, inform the City, that the required Work has been completed. Uponreceipt
19 of this notice, the City, in the presence of the Contractor, will make asubsequent
20 Final Inspection of the project.
21 4. Provide all special accessories required to place each item of equipment in full
22 operation. These special accessory items include, but are not limited to:
23 a. Specified spare parts
24 b. Adequate oil and grease as required for the first lubrication of the equipment
25 c. Initial fill up of all chemical tanks and fuel tanks
26 d. Light bulbs
27 e. Fuses
28 f. Vault keys
29 g. Handwheels
30 h. Other expendable items as required for initial start-up and operation of all
31 equipment
32 D. Notice of Project Completion
33 1. Once the City Project Representative finds the Work subsequent to Final Inspection
34 to be satisfactory, the City will issue a Notice of Project Completion (Green Sheet).
35 E. Supporting Documentation
36 1. Coordinate with the City Project Representative to complete the following
37 additional forms:
38 a. Final Payment Request
39 b. Statement of ContractTime
40 c. Affidavit of Payment and Release of Liens
41 d. Consent of Surety to Final Payment
42 e. Pipe Report (if required)
43 f. Contractor's Evaluation of City
44 g. Performance Evaluation ofContractor
CITY OF FORT WORTH Milam Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised April 7, 2014
M�
Md
no
E.
+w
0177 19 - 3
DAP CLOSEOUT REQUIREMENTS
Page 3 of 3
1 F. Letter of Final Acceptance
2
1. Upon review and acceptance of Notice of Project Completion and Supporting
3
Documentation, in accordance with General Conditions, City will issue Letter of
4
Final Acceptance and release the Final Payment Request for payment.
5
3.5
REPAIR / RESTORATION [NOT USED]
6
3.6
RE -INSTALLATION [NOT USED]
7
3.7
FIELD [OR] SITE QUALITY CONTROL [NOT USED]
8
3.8
SYSTEM STARTUP [NOT USED]
9
3.9
ADJUSTING [NOT USED]
10
3.10
CLEANING [NOT USED]
11
3.11
CLOSEOUT ACTIVITIES [NOT USED]
12
3.12
PROTECTION [NOT USED]
13
3.13
MAINTENANCE [NOT USED]
14
3.14
ATTACHMENTS [NOT USED]
15
END OF SECTION
16
Revision Log
DATE NAME SUMMARY OF CHANGE
4n12014 M.Domenech Revised for DAP application
CITY OF FORT WORTH Milwn Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised April 7, 2014
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
M
017823-1
DAP OPERATION AND MAINTENANCE DATA
Page 1 of 5
SECTION 0178 23
OPERATION AND MAINTENANCE DATA
PART 1- GENERAL
1.1 SUMMARY
A. Section Includes:
1. Product data and related information appropriate for City's maintenance and
operation of products furnished under Contract
2. Such products may include, but are not limitedto:
a. Traffic Controllers
b. Irrigation Controllers (to be operated by the City)
c. Butterfly Valves
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 — Bidding Requirements, Contract Forms and Conditions of theContract
2. Division 1 —General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Schedule
1. Submit manuals in final form to the City within 30 calendar days ofproduct
shipment to the project site.
1.5 SUBMITTALS
A. Submittals shall be in accordance with Section 0133 00. All submittals shallbe
approved by the City prior to delivery.
1.6 INFORMATIONAL SUBMITTALS
A. Submittal Form
1. Prepare data in form of an instructional manual for use by City personnel.
2. Format
a. Size: 8 '/2 inches x 11 inches
b. Paper
1) 40 pound minimum, white, for typed pages
2) Holes reinforced with plastic, cloth or metal
c. Text: Manufacturer's printed data, or neatly typewritten
d. Drawings
1) Provide reinforced punched binder tab, bind in with text
MW CITY OF FORT WORTH Milam Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised April 7, 2014
01 78 23 - 2
DAP OPERATION AND MAINTENANCE DATA
Page 2 of 5
1 2) Reduce larger drawings and fold to size of text pages.
2 e. Provide fly -leaf for each separate product, or each piece of operating
3 equipment.
4 1) Provide typed description of product, and major component parts of
5 equipment.
6 2) Provide indexed tabs.
7 f. Cover
8 1) Identify each volume with typed or printed title "OPERATING AND
9 MAINTENANCE INSTRUCTIONS".
10 2) List:
11 a) Title ofProject
12 b) Identity of separate structure as applicable
13 c) Identity of general subject matter covered in themanual
14 3. Binders
15 a. Commercial quality 3-ring binders with durable and cleanable plastic covers
16 b. When multiple binders are used, correlate the data into relatedconsistent
17 groupings.
18 4. If available, provide an electronic form of the O&MManual.
19 B. Manual Content
20 1. Neatly typewritten table of contents for each volume, arranged in systematic order
21 a. Contractor, name of responsible principal, address and telephone number
22 b. A list of each product required to be included, indexed to content of thevolume
23 c. List, with each product:
24 1) The name, address and telephone number of the subcontractor or installer
25 2) A list of each product required to be included, indexed to content of the
26 volume
27 3) Identify area of responsibility of each
28 4) Local source of supply for parts and replacement
29 d. Identify each product by product name and other identifying symbols as set
30 forth in Contract Documents.
31 2. Product Data
32 a. Include only those sheets which are pertinent to the specific product.
33 b. Annotate each sheetto:
34 1) Clearly identify specific product or part installed
35 2) Clearly identify data applicable to installation
36 3) Delete references to inapplicable information
37 3. Drawings
38 a. Supplement product data with drawings as necessary to clearly illustrate:
39 1) Relations of component parts of equipment and systems
40 2) Control and flow diagrams
41 b. Coordinate drawings with information in Project Record Documents to assure
42 correct illustration of completed installation.
43 c. Do not use Project Record Drawings as maintenance drawings.
44 4. Written text, as required to supplement product data for the particular installation:
45 a. Organize in consistent format under separate headings for different procedures.
46 b. Provide logical sequence of instructions of eachprocedure.
47 5. Copy.of each warranty, bond and service contractissued
48 a. Provide information sheet for City personnel giving:
CITY OF FORT WORTH Milam Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised April 7, 2014
01 78 23 - 3
DAP OPERATION AND MAINTENANCE DATA
M
i
i
..
i
Page 3 of 5
1) Proper procedures in event of failure
2 2) Instances which might affect validity of warranties or bonds
3 C. Manual for Materials and Finishes
4 1. Submit 5 copies of complete manual in final form.
5 2. Content, for architectural products, applied materials and finishes:
6 a. Manufacturer's data, giving full information on products
7 1) Catalog number, size, composition
8 2) Color and texture designations
9 3) Information required for reordering special manufactured products
10 b. Instructions for care andmaintenance
11 1) Manufacturer's recommendation for types of cleaning agents and methods
12 2) Cautions against cleaning agents and methods which are detrimental to
13 product
14 3) Recommended schedule for cleaning and maintenance
15 3. Content, for moisture protection and weather exposure products:
16 a. Manufacturer's data, giving full information on products
17 1) Applicable standards
18 2) Chemical composition
19 3) Details of installation
20 b. Instructions for inspection, maintenance andrepair
21 D. Manual for Equipment and Systems
22 1. Submit 5 copies of complete manual in final form.
23 2. Content, for each unit of equipment and system, as appropriate:
24 a. Description of unit and component parts
25 1) Function, normal operating characteristics and limiting conditions
26 2) Performance curves, engineering data and tests
27 3) Complete nomenclature and commercial number of replaceable parts
28 b. Operating procedures
29 1) Start-up, break-in, routine and normal operating instructions
30 2) Regulation, control, stopping, shut -down and emergency instructions
31 3) Summer and winter operating instructions
32 4) Special operating instructions
33 c. Maintenance procedures
34 1) Routine operations
35 2) Guide to "trouble shooting"
36 3) Disassembly, repair and reassembly
37 4) Alignment, adjusting and checking
38 d. Servicing and lubrication schedule
39 1) List of lubricants required
40 e. Manufacturer's printed operating and maintenance instructions
41 f. Description of sequence of operation by control manufacturer
42 1) Predicted life of parts subject to wear
43 2) Items recommended to be stocked as spare parts
44 g. As installed control diagrams by controls manufacturer
45 h. Each contractor's coordination drawings
46 1) As installed color -coded piping diagrams
47 i. Charts of valve tag numbers, with location and function of each valve
CITY OF FORT WORTH Milam Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised April 7, 2014
i
0"
M
01 78 23 - 4
DAP OPERATION AND MAINTENANCE DATA
Page 4 of 5
1 j. List of original manufacturer's spare parts, manufacturer's current prices, and
2 recommended quantities to be maintained in storage
3 k. Other data as required under pertinent Sections ofSpecifications
4 3. Content, for each electric and electronic system, as appropriate:
5 a. Description of system and component parts
6 1) Function, normal operating characteristics, and limiting conditions
7 2) Performance curves, engineering data and tests
8 3) Complete nomenclature and commercial number of replaceable parts
9 b. Circuit directories ofpanelboards
10 1) Electrical service
11 2) Controls
12 3) Communications
13 c. As installed color -coded wiring diagrams
14 d. Operating procedures
15 1) Routine and normal operating instructions
16 2) Sequences required
17 3) Special operating instructions
18 e. Maintenance procedures
19 1) Routine operations
20 2) Guide to "trouble shooting"
21 3) Disassembly, repair and reassembly
22 4) Adjustment and checking
23 f. Manufacturer's printed operating and maintenance instructions
24 g. List of original manufacturer's spare parts, manufacturer's current prices, and
25 recommended quantities to be maintained in storage
26 h. Other data as required under pertinent Sections of Specifications
27 4. Prepare and include additional data when the need for such data becomes apparent
28 during instruction of City's personnel.
29 1.7 CLOSEOUT SUBMITTALS [NOT USED]
30 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
31 1.9 QUALITY ASSURANCE
32 A. Provide operation and maintenance data by personnel with the followingcriteria:
33 1. Trained and experienced in maintenance and operation of describedproducts
34 2. Skilled as technical writer to the extent required to communicate essential data
35 3. Skilled as draftsman competent to prepare required drawings
36 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
37 1.11 FIELD [SITE] CONDITIONS [NOT USED]
38 1.12 WARRANTY [NOT USED]
39 PART 2 - PRODUCTS [NOT USED]
40 PART 3 - EXECUTION [NOT USED]
CITY OF FORT WORTH Milam Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised April 7, 2014
1
2
ki
17823-5
DAP OPERATION AND MAINTENANCE DATA
Page 5 of 5
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
8/31/2012 D. Johnson 1.5.A.1—title of section removed
4/7/2014 M.Domenech Revised for DAP Application
CITY OF FORT WORTH Milam Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised April 7, 2014
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
01 78 39 -1
DAP PROJECT RECORD DOCUMENTS
Page 1 of 4
SECTION 0178 39
PROJECT RECORD DOCUMENTS
PART 1- GENERAL
1.1 SUMMARY
A. Section Includes:
1. Work associated with the documenting the project and recording changes to project
documents, including:
a. Record Drawings
b. Water Meter Service Reports
c. Sanitary Sewer Service Reports
d. Large Water Meter Reports
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 — Bidding Requirements, Contract Forms and Conditions of theContract
2. Division 1 —General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]
1.5 SUBMITTALS
A. Prior to submitting a request for Final Inspection, deliver Project Record Documents to
City's Project Representative.
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE
A. Accuracy of Records
1. Thoroughly coordinate changes within the Record Documents, makingadequate
and proper entries on each page of Specifications and each sheet of Drawings and
other Documents where such entry is required to show the change properly.
2. Accuracy of records shall be such that future search for items shown in the Contract
Documents may rely reasonably on information obtained from the approved Project
Record Documents.
CITY OF FORT WORTH Milam Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS I01901
Revised April 7, 2014
i
MIP
M"
01 78 39 - 2
DAP PROJECT RECORD DOCUMENTS
Page 2 of 4
1 3. To facilitate accuracy of records, make entries within 24 hours after receiptof
2 information that the change has occurred.
3 4. Provide factual information regarding all aspects of the Work, both concealed and
4 visible, to enable future modification of the Work to proceed without lengthy and
5 expensive site measurement, investigation and examination.
6 1.10 STORAGE AND HANDLING
7 A. Storage and Handling Requirements
8 1. Maintain the job set of Record Documents completely protected from deterioration
9 and from loss and damage until completion of the Work and transfer of all recorded
10 data to the final Project Record Documents.
11 2. In the event of loss of recorded data, use means necessary to again secure the data
12 to the City's approval.
13 a. In such case, provide replacements to the standards originally required by the
14 Contract Documents.
15 1.11 FIELD [SITE] CONDITIONS [NOT USED]
16 1.12 WARRANTY [NOT USED]
17 PART 2 - PRODUCTS
18 2.1 OWNER -FURNISHED [OR] OWNER -SUPPLIED PRODUCTS [NOT USED]
19 2.2 RECORD DOCUMENTS
20 A. Job set
21 1. Promptly following receipt of the Notice to Proceed, secure from the City, atno
22 charge to the Contractor, 1 complete set of all Documents comprising the Contract.
23 B. Final Record Documents
24 1. At a time nearing the completion of the Work and prior to Final Inspection, provide
25 the City 1 complete set of all Final Record Drawings in the Contract.
26 2.3 ACCESSORIES [NOT USED]
27 2.4 SOURCE QUALITY CONTROL [NOT USED]
28 PART 3 - EXECUTION
29 3.1 INSTALLERS [NOT USED]
30 3.2 EXAMINATION [NOT USED]
31 3.3 PREPARATION [NOT USED]
32 3.4 MAINTENANCE DOCUMENTS
33 A. Maintenance of Job Set
34 1. Immediately upon receipt of the job set, identify each of the Documents withthe
35 title, "RECORD DOCUMENTS - JOB SET".
CITY OF FORT WORTH Milam Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised April 7, 2014
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
01 78 39 - 3
DAP PROJECT RECORD DOCUMENTS
Page 3 of 4
2. Preservation
a. Considering the Contract completion time, the probable number of occasions
upon which the job set must be taken out for new entries and for examination,
and the conditions under which these activities will be performed, devise a
suitable method for protecting the job set.
b. Do not use the job set for any purpose except entry of new data and for review
by the City, until start of transfer of data to final Project Record Documents.
c. Maintain the job set at the site of work.
3. Coordination with Construction Survey
a. At a minimum clearly mark any deviations from Contract Documents
associated with installation of the infrastructure.
4. Making entries onDrawings
a. Record any deviations from Contract Documents.
b. Use an erasable colored pencil (not ink or indelible pencil), clearly describe the
change by graphic line and note as required.
c. Date all entries.
d. Call attention to the entry by a "cloud" drawn around the area or areas affected.
e. In the event of overlapping changes, use different colors for the overlapping
changes.
5. Conversion of schematic layouts
a. In some cases, on the Drawings, arrangements of conduits, circuits, piping,
ducts, and similar items, are shown schematically and are not intended to
portray precise physical layout.
1) Final physical arrangement is determined by the Contractor, subject to the
City's approval.
2) However, design of future modifications of the facility may require
accurate information as to the final physical layout of items which are
shown only schematically on the Drawings.
b. Show on the job set of Record Drawings, by dimension accurate to within 1
inch, the centerline of each run of items.
1) Final physical arrangement is determined by the Contractor, subject to the
City's approval.
2) Show, by symbol or note, the vertical location of the Item ("under slab", "in
ceiling plenum", "exposed", and the like).
3) Make all identification sufficiently descriptive that it may be related
reliably to the Specifications.
c. The City may waive the requirements for conversion of schematic layouts
where, in the City's judgment, conversion serves no useful purpose. However,
do not rely upon waivers being issued except as specifically issued in writing
by the City.
B. Final Project Record Documents
Transfer of data to Drawings
a. Carefully transfer change data shown on the job set of Record Drawings to the
corresponding final documents, coordinating the changes as required.
b. Clearly indicate at each affected detail and other Drawing a full descriptionof
changes made during construction, and the actual location of items.
c. Call attention to each entry by drawing a "cloud" around the area or areas
affected.
CITY OF FORT WORTH Milam Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised April 7, 2014
W
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
01 78 39 - 4
DAP PROJECT RECORD DOCUMENTS
Page 4 of 4
d. Make changes neatly, consistently and with the proper media to assure
longevity and clear reproduction.
2. Transfer of data to otherpocuments
a. If the Documents, other than Drawings, have been kept clean during progress of
the Work, and if entries thereon have been orderly to the approval of the City,
the job set of those Documents, other than Drawings, will be accepted as final
Record Documents.
b. If any such Document is not so approved by the City, secure a new copy ofthat
Document from the City at the City's usual charge for reproduction and
handling, and carefully transfer the change data to the new copy to the approval
of the City.
3.5 REPAIR / RESTORATION [NOT USED]
3.6 RE -INSTALLATION [NOT USED]
3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED]
3.8 SYSTEM STARTUP [NOT USED]
3.9 ADJUSTING [NOT USED]
3.10 CLEANING [NOT USED]
3.11 CLOSEOUT ACTIVITIES [NOT USED]
3.12 PROTECTION [NOT USED]
3.13 MAINTENANCE [NOT USED]
3.14 ATTACHMENTS [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/ 2014 M.Domenech Revised for DAP Application
CITY OF FORT WORTH Milam Street Sanitary Sewer Extensions
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 101901
Revised April 7, 2014
APPENDIX
[Text in Blue is for information or guidance. Remove all blue text in the Project final documentation]
GG 4.01 Availability of Lands <Provide current statement of record(s) legal title and legal descriptions
for lands upon which the Work is to be performed>
<Provide reports andlor drawings relative to subsurface
conditions at the Project Site (excluding Underground Facilities)>
<Provide drawings andlor documents that provide information for
Underground Facilities at or contiguous to the Project Site>
GR-01 60 00 Product Requirements
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS 10190I
Revised July 1, 2011
M
ftN
no
GR-01 60 00 Product Requirements
THIS PAGE LEFT INTENTIONALLY BLANK
11
CITY OF FORT WORTH Milam Street Sanitary Sewer Extension
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS 101901
Revised July 1, 2011
Ow
Ia
a4
car
NON
W
n
IN
W
am
CITY
OF
FORT WORTH WATER DEPARTMENTS
STANDARD PRODUCTS LIST
UPDATED: MIS-2018
Approval
Spec No.
Clausification
Manufacturer
Model No.
National Spec
Size
WASTEWATER
Manhole Inserts
- Field Ooerations Use Only -(Rev 2/3/16
•
330513
Manhole Insert
Kennon Ente�P''
MademOrder-Aube
ASTMD 1248
For24"dia.
•
330513
Manhole 1pert --- ----- --- _----
--So. Wertem Paclagin. -
-- — Made m Order -Mean.
ASTMD 1248
For24"din.
•
330513
Manhole bsert
Nofic -hollow
Made to Order -pl fi.
ASTM D 1248
For 24'di,
09/23/96
33 05 13
Manhole Insert
S. west nor &Saba, Ine.
U&Sava- Sninl m SWl
For7A" du.
0923/96
330513
Manhole heed
Sauthweatem ng&SWe, Irc
TeOwrLok- Stainl mStrel
For24"dia
•
M�gy�h+��) 5
33 M�
r nr¢4,Cover2tgng9.l�r 33-05-13 (Rev 2/3/16
IFMnbde �remeaand Ww I — Woke, Bam&Hay. Fmmdry
1001
24"x40'WD
Manholes &
3ases/Framea& Covers/Standard JRoune l 33-05-13 (Rev 2/3/16)
•
33913
Manhole Fnam and Coven
Ueeem ImnVA.. Bass iflpa Foundry
30021
24"Ile
•
33 05 13
Menhole Fnenes and Coven
McIGNev I= Wor( IncA
24 AM
24" Dora.
•
33 05 13
Manhole Frames and Coven
Neenah Cortina
24' Die
3305 13
Manhole Freres and Coven
SigngdCoroorg4an
MH-144N
3305 13
a
Coven - -
-- _— -- SicmaCrajpyranm
-- MH-143N
330513
PE
Coven
1\}��an A�-(.�
GTS-STD
24"du.
330513
Coven
nmnerrt:mtieg
24'dia.
10"31/06
3305 13
Manhole Frarce and Conn. mceed) - - _- - - - _
- - - Foweneel --
- -Hnaed Ductile he. Man h le
ASTM A536
24" Ora
7/25/03
3305 13
MMale Francs and Coven I
Und-Gobs A�/4� tin (Pamaex/—
RE32-REFS
30" Di.
01/31/06
330513
30" DI MH Ring and Cover 1
Fin Jo Innn wake
V1432-2 and V1493 Cast
AASHTO M30644
30"Dior
30"tors
330513
30' DI MH 9w and C.—
Simryl 11ppqq((tnon
_--
MH1651FWN&MH1654.2
0/02/1O
07/19/11
330513
30"DIMHRrgarad Covm
Ste Pnaduw
MH32FTWSSDC
30"Die
Os/Ipll
330513
30'DI MHR Rand Cover
�" sat
220700Hw thG 1Rmg
30"Dior
10/14/13
330513
30" DI MHRra and CoverGR� &Lmkeble)
Emt Jordan hoe Wake
with Cemiack/f.IPIC/T-Geeket
ASSHTOM105&ASTMA536
30"Dior
0"01/I7
340513
30"DI MH Rng and C.—(Fhnged&I.ackat, )CI
_ _
SEP fdustna
2280 32"
ASTMA48
30'Pa.
MII I
3305.301
30" DI MH Rna and Cova(Wnae&Look) Co ft
SewoeaCover
and Cover w/Lock HIYFRP Comooaite
30"Dior.
Manl(plesA..
Bases/FraMjl;APpvers/Water Tight & Pressure Tight 33-05-13 (Rev 2/3/16
'
330513
Nonhoc Face aM Cavan----------Pont-A-T&
Amnaht
24-Dior
'
3305 13
Manhole Fnmu and Coven
Nemuh Caen9�n
24" Di..
•
----330513
_
Manhole Franca and Coven
We— lore Worka,Bw£Hay. Famdr,
-- — -- 300-24P
24"Dia.
•
330513
Manhole Fnameaand Coven
McKid Ilmn Worm In. _—
- WPA24AM
24-Dior.
03/WOO
330513
Manhole Fneeaed Coven
Accucut
RCf00
ASTMA48
24"Aa.
04tMOI
330513
Manhole Framea and Coven
(SU-Sen anon In hwhice Pnvate Ltd.
3M24-23 75 m and C..
ASTM A 48
24' Pa.
Manholes & BasesRgr�w/ComrUjrRtg33-39-10 (Rev 2/3/16)
07t"97
3305 13
Urellene d he W.Inee,
Mali Koµva K K.
Ad*. 131tn-SW P-201
ASTM D2240/D412/D792
04/2N00
3305 13
OIF t ]a'nt for4' Diem. MH
Henon Cacnk Pmducn
Dnwi�'8JJ 35-004&001
042NOO
330513
Profile Gaakea In,4' Dien MH
AW em-SGasket Com.
2 Gasket
ASTM C-443/C-361
SS MH
1/2699
330513
HDPE MaNeIe Ad Inman Ringo
Wes
Ladtmh, Inc
HDPE AdivalmentR�
IWnoidSW Svetem
Non-beai. ance
5/13/05
330513
Manhole ExterW
Cenum-CPS
McNnole Fnra- ben
Manholes
B /Pr Concrete R v1/8/13)
•
333910
blanhole, Cocrete
Hyypro Cordat Co p
I SPL Item #49
ASTM C 478
48"
•
333910
Manhole, Precast Conerde
Wall Comrete Ca Inc
ASTM C-443
48"
'
333910
Manhole, Prmaa Corners.
Fo��fonnerly OifibN-IGII, Hanson)
I
ASTM C478
48"
0426/00
333910
SI'jPle Offet S.) Joint
Fonmm(E.mcrly Giffni-HJI, Hwon)
TMF 35-004&001
ASTM C 478
48"Dien MH
09/23196
333910
h�anhole. Preens Corcrcre
Concrete Adduct Inc.
48"IU law/32"Coro
ASTM C 478
48"w/32"cone
1Q27/06
333910
Merdwlq\PrcWCaeefe
gdeWePracul Le.
48 "ID. Manhole w/2A'Cane
AS7MC478
48"Diamw24'Ring
06b9/10
3339 l0
MWn1e, Yrecas[(ReiN'aa Polymer)Corcren
UB Comsoeite Pix
Reinfacad Polymer Corcsen
ASTM G76
48'to 72"
7
ManholesB e /Fiberglass 33-39-13 jl/8/131
1.
333913
MaNele
Auid Canrainnsnt,Irc.
Flownn
ASTM 3753
Non -resit see
08/30/06
333913
Manhole I
L.F.Wufamnng
Non-betRc area
•
Manhole &
B 4. h vct�m i . mentitio as
Q adex
EI-14
Manhole Rehab Slatene
04/23/01
EI-14
Maohde Rehab Svstene
8tandand Cement Mendah,Irc.
Rehaer MSP
EI-14
Manhole Rehab System. I
AP/M PemWbnn
4n0/Ol
5/12/03
EI-14
EI-14
Manhole Rehabs1� I
MaNwle Rehab Syslem (LinW I
S Cc
Pol �N ixlrmlagiea
S) SW MS2A Rehab S�(stem
Mtl 1ppaj yaduet 1p ebOtranon
ASTM D5813
08G0/06
GeneN Concrete Recau
FI rae Tochmlosiee
vaster iteoalr uct
Mix Us
J�t��{�.�I; mem 3ases/Rehab Svstes/NonCentitious
0520/96
EI-14
Manhole Rehab SMv*j����^^ 1
S J�
Som Wall Polvuretlene Cortina
ASTM D639/D'790
•
EI-la
Manhole Rehab Sysie� I
_ _ _
Sun
ForExtericeCmtingof
12/14/01
Catifa for Cortai{�ra
��(��ted
a)
ERTECH
--- - -
Sena 20230 and 2100 �i b. Emulsion)
Corcneae stneteree ONy
07/31/06
Comnp fa Carouse
I
�on
Cheatertun
i Are 7911 SI� Sl. S2
Acd RasetanceTen
Sewer Appl—ficne
en&2006
Cosljpga f Conow
If:
_- -- I
Waron Envimmrcnnl_ _
S-301 and 301- - - - - -
I
- - -- _ _
Sewer Ay Plicatiau
O&WQ6
Caabnp C__aim Protmtion I
Cind'I __ _
SLS-W id. Enna
Sewer Q0.1i.atiom
33 05 16,33 39
I
RR&CDampp—tingNon-Fibend Spy On le
For Exteror Casting of
03/19/18
10,333920
Coatingl Conde—antecnon(Eece—)
Sherwin Wdlrams
(A..haic Emlaiaa)
C.ronefeshne—Only
PR ew/Ce,
ttrifi1 1 �C ct Fi6eralaas Reinforced Pine
33-31-13(1/8/13)
7n197
�! 31 13
Cent. L'..r -
- - - --Hobo PioeUSA. Inc. -
I Hobss Moe (,rH` Prawn)
ASTM D3262/D3754
032210
333 13
Fi 11m P
Ameron
Bondetratd RPMP Moe
ASTM D3262/D3754
10/30/93
r�-,rI4.�� n\ear Rip PolYtrAne ..
_—.__.- Amitech USA _
_yjFlowtite _
- _ASTM D3262/D3754
4/14/95
06,09/10
_
Polvmer m°n e Pi(({{yy - - - -
Pine -- - --
U
--
/M- Aoe
ASTM C33. A276, F477
- - - -
B" to 102", Clam V
Et-9
R—forced Palvnner Caerete
IB (nnucch
AM
ReiN ,cad i]lvmcr nerete Pine
ASTM C-76
Pinef.l�y/Concrete
•
�'1 -04
EI-04
Con.. Piewfonxd
—
ICmr. Pine Co Inc_
-
T-------_
AS7MC76
•
EI-04
Corc. Pim�Reinbrced - -- --
I-lvdro Condt Co titian_
_ llamy
- Flacon C... Praducn
Clam III T&G SPL Item M77
S. M., .N98-Asa
ASTM C 76
ASTMC76
•
EI-01
Coma Pipe. Rcinforoa l - _
Concrete Pi_a: & Pmducta Co. Ine
—
ASTM C 76 _
Pines/NeW/D
lj the Iron 33-11-10(1/8/13)
•
331110
Due6klmn Pipe I
Griffin Am Prochxt Co.
I
S.—Bmun Aem ell-Tite lwcbl.I—Prepe, Cl
AWWA CM, C151
3"d-24"
331110
Ductile hoe Pjpp_
AmeriunDmtilelron Pine Co
I Amwiun Fmbte Pia
AWWA CISO,CI51
4",8"&10"
•
33
- _ ._
Ductile Icon AJ�pe
2.
U S. Pico and Faundny Co
- _- - - -__— - - _—
___ _
AWWA CISO,C15t
--- --�
•
331110
------ I
Dutilelmn
_ _
Mew —Can Iron Pine Co_
I
AWWA CI50, C151
Note: All water w eesar
pipe larger than 15'shall be appoved /or use by be Water
Deperanere m Pr*etepgy80 b—. spatial beedinp may be -lured tar epee plpea. PrepereA 61152018
Pepe 1
aIEW
+•F
M
ONE
w
San
SEE
aaalF
NEW
saw
Cfry
OF
FORT WORTH WATER DEPARTMENTS
STANDARD PRODUCTS LIST
UPDATED 0615-2018
Approval
Spec No. C7aateification
Manufacturer
Model No.
National Spec
Size
PinesR).m/PVC(Pressur,l 33-11-12(4/l/13)-
j 12MI l
�� �j-��
+4 �Aeaame �Ipe
Pi/{� fe Je strewn
PVC Prtame Pipe
AWWA C900
4" Ow 12"
l Iw=14
I
33-11-12
DR-14 C P__ Npe - --
- - - Roy.l BuildmB Product,
Revd Seat PVC Pressure Ape
AWWA C900
4" Ouu 12"
Pi/HOPE
Pi Je Burstina/SliDlinin ) 33-31"23 1/8/13)
- -
„II
" IPfre%pa _
em o�pa
PhillicsDnscepim,Inc
Aexm Inc
0_oscoreDucmePolyethyl-Am
ASTM D1248
ASTM D 1248
8"
I 8"
1Gqll /.�
II(I
ens pa I
1
PoII Pio�� Ire
-- -
McConnellAm Enhounrent
ASTMD1218
ASTMD 1249
8"
IEA
plt-demrty not emmpa
CSRFIA Co�dt II -Systems
-- -
PjrXhB 4ew/PVCa 33-31-?�Q(7/1/13)
•
I
3}31-20 PVC SewerA
3}31-20 PVC Beaver
Grtdo-Teed Prcduen Cat
Na
ASIMD3034
ASTM D 3034, D 1794
4"thm 15"
4"&8"
i •
33.31-00 FVC Sewer pa
=
I-M Mmuficimina Co., Ire. VE.0c)
ASTMD3034
4"-15"
12/73/97•
33-31-20 PVC SewerP pe
Diamond Auties hors
SDR-26W SDR-35
ASTMF789,ASTMD3034
4: duu 15"
I •
33-31-20 PVC Bever Are - -
_ - Lmson Vvlan F�
ASTM F 789
4" tlw IS'
33.31_- FVC Sewer A�
BuildrlPw�Pm _
In
Rovd Seel Solid Wall Am SDR 26 & 35
ASTM 3034
4" 8vu 15"
j 01/1&18
3}31-20 PVC Sewer Ape
4ech PVL Pine
P'es
Grevi Sews
"S"
ASTM D3034
ASTM F 679
4"tluu l5"
18" .27
11/11/98
•
33-31.20 PVC Sewer A
33-31-20 PVC S_ re
D a wnd Clm��non
I-M Manutemrin G 1 (IMEagle)
0nv V plee
ASTMF 679
18"-27"
09/11/12
33-31-20 PVC Sewer Pine
Aoeh7fe net Stream
SDW26adSD05
ASTM F-679
18"
05/06/05
33-31.20 PVC Solid Wall Pipe
Diamond Phaties Comorehon
PS 46 ASTM F679
18" to 48"
04/7/06
33-31.20 PVC Sewer Fi���^B8
Its-
SDR-26 ad SDR-35 Gaaket Altman
ASTMD-3034,D1784,em
4"-15"
I
3}31.20 PVC Sewer Filtiogs
Pluhe Tronde,I..c
Gukckd PVCSewer Main Fdhryrs
ASTM D 3034
11/17/99
EI00-2 Cl-d Aefile PVC Pipe
D-nod Plastics Comorahon
ASTM 18034 7%
18" to 48"
3/192018
333120 PVC Sewer Apf
Pio�f. Jet Strewn
SDR35
ASTM F679
IB"-24"
I 3/19201/
333120 PVC Sewer Am
Amilib Jet 3tresm
SDR 26
ASTM D3034
4"-15"
Pipe;:/Ribbed Open Profile Larae Diameter
092691
E700-2 PVCS—Pim,Ribbed
Iameon Vylon AJ
Gdon V%� HC.CIaud Profile Ape,
ASTMF679
18"m 48"
09/W91
E100-2 PVC Sense, P, bbed
Extrudes Tmhmlgpa.
Ultra-Ri60pan Profile Sewer Pia
ASTMF679
18"m48"
I1/10/10
E700-2 PVC SawarPi Ribbd
(EIW-2) Polypmpylem Sewer Pjre, Double Wdl
UoQt EI7 Company
Tky ge SyeWro(ADS)
S.alTrm HP Double WdI(aC gad)
ASTMF 2736
24"-30"
I1/10/10
(E7(62) lyq Rojo Triple Wall
Ad"ncad Dm (ADS)
SIo Tits BP Trifle W Itl Am
AST" F 2764
30" m 60'
05/INI l
Steel �vethvle Piro
- -
--Adven«d
a
ConTech Conelrmtlon Produrb
Dimmza
ASTM F 2562
24"
Pioea/Rehab/CIPP 33-31-12 (01/18/13)
•
Cured in Agee P a
Insimf Tcxark, Inc
ASIM F 1216
O5/ON99
Curd in Place Ape
NabOrol EnImuseh Groin
Norno Liner, (SPL)Iem#27
ASTM���Dj813
0529/96
Curd in Pram Ate _
Revmlds hrlbinmr Techodgy (Itt- USA)
/ntimr Tx 1 s;
J S i�id
I
Pi
lm
110398
Fold cad F«m Ate
F. andFaro Pine
Cullum A[[�� Svalemn,
Instuf imhm pe
Ineituf "NuPles'
ASTMF-1504
120400
Fold and Faro Pipe
\Ito.
American Piff�Iee & i ce, lne.
1871, 1867
Dcmo. Purpose Only
06/09/03
Fold and FaroAyF
Fold and Faro Pike
UI aian
Miller Apdim Grp
Utralim PVCAtooyyPpanto a
EX Meth6d
ASTM F-1504,
ASIMF-1504,F-1947
Up to 18"dioneW
I
I
Pipe Enlarament System(Method)33-31-23(01118/13)
PIM System -----
McComell Systems
PBviC�ro�ration
McIat Dorndrmtron
,PoI eth hem
Polyye[h��em
PIMC[,,AseataWay,NJ.
Houston, Trews
1�Wr��dPravusaayy
App-.P-inusly
TRS S"tor
'1'rerdhkae Replacement SyeWn
Pofvethylene
Glgany, Cando
Appnwd Prenoesly
P _Qmina �macers 33-05-24 (07/01/13)
1 10l/O4/@
Sted Gard C 'rS Spacers
Ad"ncd Products and Systems, Ins.
Ceft. steel Spa Model SI
1 02/%J93
SW Steel Cunry Spacer
Advucsd Prducb and SyeWn, Ito.
stainless Steel Spaoey Modal SSI
1 04rM87
Gaim Spacers
Cawde Waterworks Manufacturing
Casing Spann
1 M/14/70
stand -Steel Cuing Spacer
nmhns Sod Insulator
Sbideu StmI Guirgl Spacer
Up to 48" <7>m
1 09/IM10
Coined Steel Casio Spann
Apdim Swl Ludamr
Coated Sted Cass. Spacers
Up 48' <I>Q>
1 05/10/11
Standee Steel Casing ea Spe
Powmsesl
4810 Po —hock
Up to 48" <I>m
I 03/19/18
Gung Sp—
BWM
SS-12 Curry{ Sncer(SWden Sorel)
03/IW18
Cuing Spacers
BVIM
F&]2 Casing Spur(Codd Carbon Steel) for
Nonyreuure Pipe and Groaned Cuing
CoatjnpS/Bogw 33-39-60 (01/08/13),
0=902
Lidgt System 1
Sauereiseo Ito
SewerGad 21 ORS
LA Gurrty #210-133
1
12/14/Ot
�Lidu j ahem I
Ertsh Tmhmcd Coatings
P tmh 2m0 ad 2100 Same
04/14/05
_
tenoyyorDmhe .Am Cntina 1
indumn
Aotscto401
ASTM&117
Dmtrle Iron Pipaady
01131/06
forum
- --
Chealenon
-- Arc791.SIHB.SI.S2
Acid Reaahnm Ten
I Seaver APdicaOme
828/2006
eaun8e� on tom non -
_
Wrtren11-viro—tat
_
S-301 and M-301
_
1 Sewer Applicatrma
I
I
1
L%9�n$s/Yol; ttrethane
I
1
Combinabo it v. r . 1f
WATER
Pipes/33-31-70 (01108/13)
AWWA C900, AWWA 0605.
01//208 33-11-12 PVCPneasure PiQQGe I _ View IT CAA ASTMD1784 4"-12"
1 3/192018 331112 PVC Preruie P11 l R t( '�ream DR14 AWWA C900 4%12"
1 3/192018 331112 PVC P--Pine _--- - 1--R�II'e to Sbeem -- - --- -- MI�t---- AWWA C900 --- - - 16"-24"
• Ei-t l Combintim AiI'd— Val" GA Industries, Ito Empire Anr ad Vumm Vat", Mudd 935 ASTM A 126 0aes B, ASTMA 1' & 2"
Crispin Au sod Vacuum V.]-, Model No A5,
• EI-11 Combintion Au Rd —Vat" MdtiVex Manuf7,tc. A70&A20 1/2",1"&2"
• EI-11 GmbnWien Air Release V.I. Valveed Armor Gm Ak0#l43C_iI45Cad M147C 1-,2-&3"
P�j'/,{'J v `F-iJ�}��n aq/-tr�'Ctile Iron -Fjing8,_33-if-11101/08/131
072'i/92 El file Lon it8rea _ SW Are Products. Ito
•
EI-07
Dmele IronA rgo
GntSn Pine Produ-,Co
•
EI-07
_ _ _
Duetilelmn Fir
mewan%Tvler Pi`e/Udon Uelmee Dinnon_
08/11/98
EI-07
Ductitlmn At(tga
SInn.G
02W14
E7.07
MIFinJPg+
_
Accuses•
05/14/98
EI-07
Ductile Iron Joint Restraint-
Ford Mctr Box GNni-Ftnge
05/1498
EI-24
_-
PVCJoint Renoir
_--
Fod Meter Box GNd-Fine
11/09/04
EI-07
Dudlelme Joint Resuaint
On Butt, Ito j
02rMI2
33-I1-11
Ductile leon Piqq��Maehuecat Joint Reatratnt
EBAA Iron, Inc. I
02t29/12
33-11-I1_
PVC Pine Mechutinl 7dntlieahatnt
_ _
EBAAhpe. Ito. 1
011/05/04
El-07
Mechmcd 7ddRaWner Glada(PVC) _
__-- Siems.co
08DS/D4
EI-07
Meeiameal Joint Refiner Glada(PVC)
SIYnn Co
Mechanical Jmnt Fit"
AWWAC153&CII0
Mxharkd Joint Fittings
AWWAC 110
Mecladcal7dnt Fi SSB CIaea 350153,C
110,C 111
_
Mechardcal Jdd Fi' SSB Clw 351
I AWWAC153,CIIO,C112
= SO Cl. "J FF ttina
I AW WA CI53
4%12"
Ud 3arare )es 1400
AWWACIIIIC153
4`m36"
UF 99F Sdes 1500 Cireh L-k
T WA CI AW I I/CI53
4' W 24" <A>
Zd-XRestrained Joint FitorB
I AWWACIII/CI16/C153
4"to 12"
Series I1-(f DI Ape)
I AWWACIII/C116/C753
4"w42"
B Series 2W0(fa PVC Ate)
AWWACIII/CII6/C153
Van 24"
' pup Orn-Lek SLC4-BLCId
AWWA CIII/CI53
4"to 10"
SnpmeOroL&SLCE
I AWWACIII/C153
12"to24"
Note: All water or waxer pipe I&W Btan 15'shell be approved for lee by the Water
Departrnera m projed epdk beat. Special bedding may be requred for across paps. Prepared (3/752018
Pape 2
w
CITY
OF
FORT WORTH WATER DEPARTMENTS
STANDARD PRODUCTS UST
UPDATED: 06152018
sw A����al puee�No. Qasssification Manufacturer Model No. National Spec Size
0&lom �EI-07 MJFitfingKDIP) Sienna, Co. Sim.One-Lok SLDE AWWAC153 4'-24"
Balidog System around Lek 21 & JM Ergb
1011210 EI.24 Interior R.trained Joint Syebm S& B Toehneid Product, 1-900) ASTMF-1624 4'. 12'
09/16/06 EI-07 Mech,nicd J-rdF is �( ) Mecherricd loim Fitti9� AWWAC153 4'w24"
It/07/16 33-I1-11 Mechedcal Joint Re6iner Gland, I mol� ludo, Inoue PVCSMr¢rio Zoe 4Q60 ASTMA536AWWACIII
11/97/16 33.11.11 M.MaW Jam ReWuer Glerds I SMr Pine Pmdwts,Im DIPS Sena 3000 ASTMA536AWWACIII
03/19/19 33.11.11 Meeluded Jam Rattto Olends SIPineranmwe duslnee(S) FZ Grip Jdm R.ua (EZD) Black For DIP ASTMA536AWWACIII 3"49"
1 03/19/18 33•11.11 MaclMmed Jam Rd. ner Glad, SIP Induetsim(SermWwe) EZGrip Joint Itsifixint4�RD) Red for C900 ASTMA536AWWACIII 4"-12"
DR11 I 0Y1.1. 3}1141 Mxhanicd Jwm Reterrcr Gluda SIP[EZ Gripkim Restraint(FM) Red for C900 ASTMA536AVIWACIII 16%24"
DR18 PVC Pi.
I _
I
-S.AND _gAASKETS33-11-05(01/08/131_ -- - - ---- _ --
Pinee/ValVell slResilimt Sewed Gate Valve"
I --(i_12_I(p;413/1 LI
GaKlvew/Got. A Coohol --Sarin 25MDrawint p 94-20247 16"Redad
1213 02 R.Miem W e Gab Valve Atueriean Flow Comm) I Sarin 2530 and Seri. 2536 AW WA C515 30' and 36"
0871/99 - Rmilieo Wedge Gab Valve American Flow Control Sarin 2520&2524(SD 94-20255) AWWA C515 20'.024"
05/19,99 R.iliem W/�p�` Ga a Valve Amer can Flow Control
'"r I eaa- - ooSAWWA C5515 16"
Idawoo E146 RdliemWGeVdveArnemenFlwCmml WC55 4"b
2"
42s48"A AWWAC15 2"ad48"08A04 Resilient WdeGateVvAmercan Flow Cntrol w �I
-.-
05/73/91 fit-26 ReriliemW pe Gate Vdve Amenoan AVK Comoeny Ameican AVK Realr.t Sedd GV AWWA C509 4"w12'
1 01/2A/02 El pn et .ale},:- American AVK Campary I 20"ad anedler
' El•26_ call ate Vdve - - Ke1v 4"-12"
• EI.26 I=N Gab Valy<------ - - k(&H - - - 4". 12"
EI.26 Redliem Seatd Gate Valve Mueller Co. 4" -12"
I I/C:m Redliem eW,GbVdve _MwII,r Co Sah..A2361�SD664n AWWACS15 16"
wSnAI24C.517�) 05/13/05 RlimW _eGVdvMueller Co. Mueller 5 AWWA C515 ad 36'
OIeVve 3& AWAC42'ad 46"/31/06 RedliMwiaCo li 25 5a
OlrAm EI.26 P. icm
11/2•9/04 eJE-
Vdvee Clow Valve Ca. kal _ AWWA C509
101ovw ianVdAWWA C514' 16'
11A89EI-26 RRedmVdClClw VwdCwo. AWWAC15 Nam
2"e
la
1ResilimV.N. ClwVdvCw Clw30"&iG515 AWWA C55 30'and 36"(Na4e 3)
11GW12 Rel intVdve ClwVdvCa. Clow Viol. Maid 26A AWWAC515 24' l0 48- (Note 3)
05A I EI.26 Cei iad 6. OVdve Stockhaor V.I-&Fi I^�'AC5oe.4a4AAS7atl 4 12"
UEI.26 Rcali.t Stated Gab Valve EddwMxevva120.m.a sPx74 1't 16'
10/26/16 33.12.2Rmili.t Sealed Gate Valve EJ od
_ _ e_JFbwMwuOab_Vdw&Bose.
Fjo8a.fy_q.,t Fitting Ott`
s/Rubba eated Butterfly VaIV a 33_]2.21 (07/10/14` -
• 81.3Rubber Sealed Butterfly ��ve _-_ AWWA C-504 24"
AEI.30 Rubber Soared Hunev Valveler Co. I I AWWA
G504 24"ad auto let
111;/99 EI.30 Rubber Seated Buttertly Valve Deaunk Valve. Co I AWWA C-504 24' and lacer
06/12103 E20 V.- A.9v Valve ytatic valve and Manufactu incam. Valrom lve AWWA C-504 Up w ga" diaec
8.s ea04/06/07 30 bber Vve M&H V.I. AWWA C-504 24" to 48"
ON19113 331221 Rubber Seated Butterfly Valve G. A. Ind.ttr. (Golden Anderem) AWWA C504 Butterfly Valve AWWA C-504 te
30"-54"
� I S-em�olin-¢--Sty nn I
3/1296 Wae Sartolf.stafi. W.WPI. B20 Water Samoline Station 1
1
Bartel Fire Hvdrpujs 33-12-40 (01/15/14
IW E•1.12 1 I American -De Valve Dr1_ 9018608, 94-I8560 AWWA G502 I
j re I Amaicar DelSY Vdve pI1H a{No. �Q¢"18791 AWWA C-502 I 03G ! [1-'l int 1 Clow�rr -- - ti'hoo�No.ii19095 AWWA G502 1
01/12/93 1-�1j - F.. Arrmcan 2700 AW WA C-502 I
O8?AI88 1.12 lbrttl Fire 1 Clow q8 Ors j D20436, B20506 I AWWA G502 I
I.12 Berm Firc rant �_ _ IT7I�yhlveDell7RiFW I AWWA GSM 1
092NB7 U1.12 I Bs`JFue rant M&H perm I mNa. 13476- ---I AWWA G502 III
110 14 87 E 1-12 D He el Fire Hvdnnt Mueller Comeary 42 Centurion �1 AWWA C-502
Shop Dnvdng FH-12
01/15/88 EI-12 Hertel FircH t M.IIer Camp AA23 SumCenhuion 200 AWWA C..
1 10/09/87 B.rrcl J t U.S. Pia & Fo ry S No. 960250 AWWA C-502
0911N$$// Fj11•�(q�j t. (1af t Watemlla Cp��o�0y Sh p8ff,� .SK740803 AWWA C-502
0&1'L(6 Ji12.40 uylienel l%irc vnot PJ (Fad brdan lroriWwks) I Mader 5CD25o I
A aztx ADDIut ances 33-12-11)(07101/13) I
51/18/18 33.12-10 Double Sin Saddle -- --�� Remac _ I 202NSNf� Coated I AWWA C800 I"-2"SVC, up b24'Pipe
0&28101 p at�pRa la - - Smith Blair I X317 Nlgn Ce.te9 Dou IeS S 1
1 07/23/12 33.12.10 M $[� Yervi. Saddle Muellm Can DR6 Double SS 5 f)(S.dNe a AWWA COW I 1"-2"SVC. wow 24"Pipe
1Q27//py� i sto�lp�I _a''� Meter Y-:. �-,r,5a"}gy ral - If I� ¢Ij�ry�`j1}F,, IOMT - -- " ad 1^
1Ql'Y7/87 Curb Stove-BdI Mao Vdvm eM Tlrns 146039. f5M 11Y1M. b1(aTMaM 6101M 1'i: ud 2"
012N00 C.bd Ta S.M. with Double SS St.. KM Id.tnes. tc. p406Ibu a $S Saddle -- - - - 1'-2' Ty�gl yj to 12`
015/21112 33.12-25 T.on��5� Caned Btedt fC`h(�tgrr.iris, Inc 0 Sleeve EIS AWWA Gam- [)o w 3lN' w/12" Out
OS/10/11 I.gI Ta 'fit I-rinle.Steal) Poxen.l 34SVA ( jl&3490MJ 4"-8"ed 16"
/12 j3//gjj-I1Iy�'7jjj (�� 1 te.1 Rom¢ 240 - - - - AW��/J�/jp,A G2]/ U to 42" w24' OW
/12 33-IZ2-§ �� ' peveJBTLNed Steel) Rom.c eaa Ske � AW WA C� w 24" w/12" Qrt
8 eery (Sad'den S ) Routs 'deaf S A A e 3 w 30" w/12- QII
05/10/11 1j CI - - - - - - Povmmed -- 2 'nl - - --- 4'.30"
�l5a.ti 'ic Lid UFW pl,au.Irc.._ '-21EPA FW
{{{5Lid D Haea'. Inc. '�IEPAF F4
1i Lid DFW Plastic. im. % I4-iEp/.A- ��� y Claa A"
��yy B��ejja!l & jHjb{.kyyva i I-�LB11122'11118 LII19
Corarcte Meb/FSox 5•I165 527 L769 1
p,I,,�'yia,+ - 1-10 (Ol/08/131
�u�E��)[•1. ,Fq�q�/y/rr Fle,aol Pecksp'p¢ _ Fwd E ss AWWACI05 8rdl LLD
I lil•13 Ibv i 1a - - ----M°wWn Sialm Pte.ti. and AEPJnd. Alj'Vj'AICO 8-1 LLD
v-re ---- ------ - AEP Industries Bullsamnd -(.o---- It&Oaaka I A AC03 final LLD
Not: An welar «enamor plpe IWW man 15'NWI be ttpprwed M toe by filer Water
DW.Orneni m Proiamepedk bees. Spedal betidlrl0 may be repind for a.rlel ppers. Prepared 6115=18 Pepe 3
CITY
OF
"
FORT WORTH WATER DEPARTMENT'S UPDATED! 06-15-2018
STANDARD PRODUCTS LIST
Approval SNo.
Classification I Manufacturer Model No. National Spec I Size
I�ptsS
E701-5
I _AIn�( �� I
.___ M._' (XMI ve V'et 3,4•116•
ICI1 WWI/(b
M eVMe�Oeal Turbine
al
AWW
I IJOTFS •
<I>
From 'Biro) Standard Produets List ___
Grtier I.D.
I __
I m
4>
Above Pprvoed on�"�y pv Saae buffs
np-in • I - -
1 W
b36^Hodevm
Protlu� A b 36 c9os we Pioe ie one eomoved no m at,"
1--prNwnt's',aududPr
wt. Lrrt hm ban developp.M mi.—tlie. Lm-flel revt m-Wp-m-ducb wtuch meetth FoutWoM Water Uep—t-e BtWud Specrtiationeaunng utility corobachon prgacb. wnen lac 1
Spa4ficuioro forspecifiepmdtleb, a a included u padoftheC n0—fi nConbsat Docuncnb, dic.quianeubafBe Technical Spmfimfi—All overri&tWort WoMWaWDeprtrrcrd's Standard SpaiScatiau.nd the FortWoM Water Rpvhrard'e
1-1--ni,
Stud Andmrs Listand approvalofthespecific pmducbrill W bead on the regui—boftbc Technical Spaificiiii tvlcd—rottheepei6opmdatmeet,the Fort Worth Wales Depwnem'aStudard Sp-li—.roorisestheFonWodhW.-
er
DepMrmd'eStendWP dtnb Lid.
S
NoW AD water a ilm— pipe larger drort 1S WM be apPwed for tee by 8a Water
D%Mrbnem m Rgea specl k belie. SpedW Wd'arq may be required br sane pipes. Prepared N15=18 Pape 4