HomeMy WebLinkAboutOrdinance 27446-02-2025Ordinance No. 27446-02-2025
AN ORDINANCE ADJUSTING APPROPRIATIONS IN THE 2018 BOND
PROGRAM FUND, BY INCREASING APPROPRIATIONS IN THE GOLDEN
TRIANGLE BOULEVARD FROM I-35W TO MISTY REDWOOD TRAIL
PROJECT (CITY PROJECT NO. 101013) IN THE AMOUNT OF $5,636,956.59, AND
DECREASING APPROPRIATIONS IN THE AUTHORIZED - NOT
APPROPRIATED PROJECT (CITY PROJECT NO. U34018) BY THE SAME
AMOUNT; PROVIDING FOR A SEVERABILITY CLAUSE; MAKING THIS
ORDINANCE CUMULATIVE OF PRIOR ORDINANCES; REPEALING ALL
ORDINANCES IN CONFLICT HEREWITH; AND PROVIDING AN EFFECTIVE
DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,
TEXAS:
SECTION 1.
That the budget of the City of Fort Worth for Fiscal Year 2024-2025, as enacted by Ordinance 27107-09-
2024, as amended, is hereby further amended to make the following adjustments to appropriations in the 2018
Bond Program Fund, by increasing appropriations in the Golden Triangle Boulevard from 1-35W to Misty
Redwood Trail project (City Project No. 101013) in the amount of $5,636,956.59, and decreasing
appropriations in the Authorized - Not Appropriated project (City Project No. U34018) by the same amount.
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way impair
the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 27107-09-2024 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY:
Douglas Black (Feb 24, 2015 15-25 CST)
Assistant City Attorney
ADOPTED AND EFFECTIVE: February 11, 2025
CITY SECRETARY
3annette S. Goodall
City Secretary
4�aG��Zi.
4oRro���
1
1� g 00
�d 000
00
�� a�,�TEXpg`f�
Mayor & Council Map I CPN#101013 FORT WORTH.
Golden Triangle Boulevard & Harmon Road
CD #4,10
• M CIP Project Extent` r
Council Districts
16
4 - Charles Lauersdorf
10_ , Alan'��
10 - Alan Ma lock
y rr, �-c .Ulaylock �� r
I ,f
- # NAB _
r
Vr r•s. -' 7r �°i� - -c .._ram•• � ' , r : � r , , � r , � f f.
y
GELDDN;lZTR ANGLE o .
'i
�. t
F►C [ N
GOLDEN*HEIGHT�5-RD 1 4 i� f , _ �' s, +►
�-
webw
'` d,.�•^ MCRACKERNDFA,
`I • i
• l`Pir A f(i I
Fir
Cffla ries �.
.�OW
LL La�uT�e*r's�dorf
✓' - i � • � ''.� —� • 3 .ems' • 3 I -
,ML
�r 1
Data Source. GFW GIS, NearMap Map generated December 2024
n L n l n TPW Business Support SerNces
V 600 1,200 Copyrisht®2024 City of Fart Worth. Unauthorised reproduction is a violaficn of
appEicabk laws. This data Este be use farsmphica1representa6nn any The accuracy
is not to be takerA and as data produced for Engineering purposes or bya registered
Feet nm(essiomlland st=rnyar- The City of Fort Vdb th aswmesm responsibifi Vf rthe
�' accuroryo(widdata.
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 02111 /25
M&C FILE NUMBER: M&C 25-0118
LOG NAME: 20GOLDEN TRIANGLE BOULEVARD FROM 1-35W TO MISTY REDWOOD TRAIL
SUBJECT
(CD 4 and CD 10) Authorize Execution of a Contract with McMahon Contracting and Construction, LLC, dlbla McMahon Contracting, L.P. in the
Amount of $10,824,277.43 for the Golden Triangle Boulevard from Interstate-35W to Misty Redwood Trail Project, Adopt Appropriation
Ordinances, and Amend the Fiscal Years 2025-2029 Capital Improvement Program (2018 Bond Program)
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize execution of a contract with McMahon Contracting and Construction, LLC, dlbla McMahon Contracting, L.P., in the amount of
$10,824,277.43, for the construction of the Golden Triangle Boulevard from Interstate-35W to Misty Redwood Trail project (City Project No.
101013);
2. Adopt the attached appropriation ordinance adjusting appropriations in the 2018 Bond Program Fund, by increasing appropriations in the
Golden Triangle Boulevard from Interstate-35W to Misty Redwood Trail project (City Project No. 101013) in the amount of $5,636,956.59,
and decreasing appropriations in the Authorized - Not Appropriated project (City Project No. U34018) by the same amount;
3. Adopt the attached appropriation ordinance adjusting appropriations in the 2018 Bond Program Fund, by increasing appropriations in the
Golden Triangle Boulevard from Interstate-35W to Misty Redwood Trail project (City Project No. 101013) in the amount of $963,043.41, and
decreasing appropriations in the Hannon Road Design ROW project (City Project No. 100459) by the same amount; and
4. Amend the Fiscal Years 2025-2029 Capital Improvement Program.
DISCUSSION:
This Mayor and Council Communication (M&C) recommends authorization for execution of a contract with McMahon Contracting and
Construction, LLC, dlbla McMahon Contracting, L.P., in the amount of $10,824,277.43, for the construction of the Golden Triangle Boulevard from
Interstate-35W to Misty Redwood Trail project. The project will widen the existing 2-lane asphalt road to a 4-lane concrete arterial road, which will
include traffic signals, drainage and water improvements, 10 foot shared use paths, and a concrete median.
The following table demonstrates the total budget for the project.
Capita[ Fund Name
Project Name
Existing
Funding
Additional
Funding
Project Total
34018 - 2018 Bond
Program
1013 - Golden Triangle 135-
OstyRwood
$2,870,000.DD
$6,6Q0,000.00
$9,470,000.00
30108 -Transportation
101013 - Golden Triangle [35-
Impact Fee Cap
MistyRwood
$2,973,967.49
$0.00
$2,973,967.49
30104 - Developer
101013 - Golden Triangle 135-
$353,801.00
$0.00
$353,801.00
Contribution
MistyRwood
101013 - Golden Triangle 135-
34017 - TaxNote2017
MistyRwood
$200,000.00
$0.00
$200,000.00
39008-Trans Impact Fee
101013-Golden Triangle 135-
$1,526,032.51
$0.00
$1,526,032.51
Cap Legacy
MistyRwood
Project Total
$7,923,801.00
$6,600,000.00
$14,523,801.00
The project was advertised for bid on October 9, 2024 and October 16, 2024 in the Port Worth Star -Telegram. On November 21, 2024, the
following bids were received:
IBidders
u Amount
McMahon Contracting, L.P.
$10,824,277.43
McClendon Construction Co., Inc.
$10,971,977.55
DDM Construction Corp.
$11,395,703.74
Jackson Construction, Ltd.
$11,415,968.00
Tiseo Paving =F
$11,473,436.85
Construction for this project is expected to start in early 2025.
Funding for this project was not included in the FY2025-2029 Capital Improvement Program (CIP) because construction cost estimates were not
complete at the time of CIP development. The action in this M&C will amend the FY2025-2029 Capital Improvement Program.
Funding is budgeted in the Authorized, Not Appropriated and Harmon Rd Design ROW projects within the 2018 Bond Program Fund and in the
Transportation Impact Fee Cap, Developer Contribution and Trans Impact Fee Cap Legacy Funds for the purpose of funding the Golden Triangle
135-MistyRwood project.
Business Equity Office - The Business Equity Division placed a 9.22% business equity goal on this solicitation/contract. McMahon Contracting,
L.P., has agreed/committed to utilize 9.22% business equity subcontractor participation for the scope of work, meeting the City's Business Equity
Ordinance. Any changes in subcontractors will be reviewed by the Business Equity Division.
The project is located in COUNCIL DISTRICTS 4 and 10.
FISCAL INFORMATION 1 CERTIFICATION:
The Director of Finance certifies that funds are currently available in the Authorized, Not Appropriated and Harmon Rd Design ROW projects within
the 2018 Bond Program Fund and upon approval of the above recommendations and adoption of the attached appropriation ordinances, funds
will be available in the 2018 Bond Program, Transportation Impact Fee Cap, Developer Contribution and Trans Impact Fee Cap Legacy Funds for
the Golden Triangle 135-MistyRwood project to support the above recommendations and execution of the contract. Prior to an expenditure being
incurred, the Transportation and Public Works Department has the responsibility of verifying the availability of funds.
Submitted for City Managereess Office by. Jesica McEachern 5804
Originating Business Unit Head: Lauren Prieur 6035
Additional Information Contact: Monty Hall 8662