HomeMy WebLinkAboutContract 62450-CO1CSC No. 62450-COI
FORT WORTH,.,
Project Name I 2025 Concrete Restoration Contract 1
Client Project #(s) I 105046
Project
Description
Contractor) Urban Infraconstruction, LLC
City Project Mgr.l Tariqul Islam
Dept. TPW
Original Contract Amount $3,156,248.00
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date
Amount of Proposed Change Order
Revised Contract Amount
Original Funds Available for Change Ordei
Remaining Funds Available for this CO
Additional Funding (if necessary)
City of Fort Worth
Change Order Request
I City Sec # 1 62450
Panel Replacement at Trinity Blvd and Meacham Blvd
Change Order#I 1 I Date 3/17/2025
City Inspector Ben Weaverling
Contract Time
Totals (CD)
$3,156,248.00 300
$3,156,248.00
$3,156,248.00 300
5
$3,156,248.00 305
$157,812.00
$157,812.00
$0.00
$3,156,248.00
$157,812.00
$157,812.00
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT I0.00%
MAXALLOWABLECONTRACTAMOUNT (ORIGINAL CONTRACT COST +25%) 1 $3,945,310.00
JUSTIFICATION (REASONS) FOR CHANGE ORDER
This change order will add a new 4-inch subdrain item to the contract. The 4-inch subdrain will be installed behind the curb along a 340-foot section of
Trinity Boulevard to address a groundwater issue encountered during panel replacement. The subdrain will collect groundwater and discharge it into a
nearby curb inlet, preventing damage to the pavement structure and ensuring long-term durability. The project team reviewed a quote for the subdrain
installation and deemed it reasonable based on comparable recent bids. The construction allowance pay item will be used to cover the cost of this change
To do this additional work, 5 days are proposed to add to the contract.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full
(both time and money) for all costs arising out of, or incidental to, the above Change Order. The Project/Program Manager signing below acknowledges that
he/she is the person responsible for the monitorine and administration of this contract. includine ensurine all nerformance and reoortine requirements.
Contractor's Company Name
Contractor (Name)
Contract Signature
Da
Urban Infraconstruction, LLC
Anup Tamrakar
o,,„,,,.,, n,
Apr 10, 2025
Inspector/Inspection Supervisor
WDate
Project and Contract Compliance Manager
Date
pzs�oz�o.�
Apr 14, 2025
Apr 14, 2025
r 6.Date
Senior Capital Project Officer
Date
lgp,,,,z—,,OZCp
Apr 14, 2025
M
Apr 14, 2025
Assistant Director Dept)
Date
Director, Contracting Department (Dept)
Date
R"""l-- ( '
Apr 14, 2025
11 m.�
pr 14, 2025
ity Attorn
Date
ager
Date
:po.e1Y� .p, s zpz �� �1 _.
Apr16,2025
pr20,2025
Council Action (if required)
00 oonq M&C Number NA I
M&C Date Approved NA
ATTEST: OFFRTaO
d
FVo °=4
Jannette Goodall, City Secretary pPprt.
dawn dEXaogp4v
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
FORTWORTH City of Fort Worth
'---- Change Order Additions
Project Name 2025 Concrete Restoration Contract 1 City Sec # 62450
Client Project# i 105046 1
Contractor I Urban Infraconstruction, LLC PM I Tariqul Islam Inspectorl Ben Weaverling
Change Order Submittal # C1� Date 1 3/17/2025
ADDITIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
New-41 4 inch subdrain TPW 340.00000000 LF $30.47 $10,359.80
TP N $10,359.80
Sub Total Additions $10,359.80
Change Order Additions Page 2 of 4
FOR_ TT WIO� City of Fort Worth
Change Order Deletions
Project Name 1 2025 Concrete Restoration Contract 1 City Sec # 1 62450
Client Project# 1 105046
Contractor I Urban Infraconstruction, LLC I PM J Tariqul Islam Inspectors Ben Weaverling
Change Order Submittal # Date 3/17/2025
DELETIONS
ITEM DESCRIPTION DEPT City Unit Unit Cost Total
40 Paving Construction Allowance TPW 0.10359800 EA �100,000.0t7 510,359.80
TP N $10,359.80
Sub Total Deletions $10,359.80
Change Order Deletions Page 3 of 4
M/SBE for this Change Order
M/SBE Sub Type of Service Amount for this CO
Not Applicable
Not Applicable
Not Applicable
Total $0.00
Previous Change Orders
CO # DATE I AMOUNT
Not Applicable
Not Applicable
Total I $0.00 I
105046-CNCO-2025 Concrete Restoration
Contract 1, CO 1
Interim Agreement Report
Created: 2025-04-08
By: Andrea Munoz (Andrea. M u noz@fortworthtexas.gov)
Status: Out for Signature
Transaction ID: CBJCHBCAABAAu1A9wDmb54rS-XnomevxD1tEtivFe vk
Agreement History
2025-04-14
Agreement history is the list of the events that have impacted the status of the agreement prior to the final signature. A final audit report will
be generated when the agreement is complete.
"105046-CNCO-2025 Concrete Restoration Contract 1, CO 1"
History
Document created by Andrea Munoz (Andrea.Munoz@fortworthtexas.gov)
2025-04-08 - 4:02:46 PM GMT- IP address: 204.10.90.100
Document emailed to Crystal Greene (crystal.greene@fortworthtexas.gov) for filling
2025-04-08 - 4:23:28 PM GMT
Document emailed to anup@urbaniconstruct.com for signature
2025-04-08 - 4:23:29 PM GMT
Document emailed to Ben Weaverling (Ben.Weaverling@fortworthtexas.gov) for signature
2025-04-08 - 4:23:29 PM GMT
Andrea Munoz (Andrea. Munoz@fortworthtexas.gov) added alternate form filler Alexandra
Ripley (Alexandra.Ripley@fortworthtexas.gov). The original form filler Crystal Greene
(crystal.greene@fortworthtexas.gov) can still fill the form.
2025-04-08 - 4:23:46 PM GMT- IP address: 204.10.90.100
Document emailed to Alexandra Ripley (Alexandra.Ripley@fortworthtexas.gov) for filling
2025-04-08 - 4:23:46 PM GMT
Email viewed by anup@urbaniconstruct.com
2025-04-08 - 4:30:46 PM GMT- IP address: 67.200.196.10
Email viewed by Alexandra Ripley (Alexandra.Ripley@fortworthtexas.gov)
2025-04-09 - 5:23:46 PM GMT- IP address: 204.10.90.100
FORTWORTHy I "'by
Adobe
Acrobat Sign
C� Form filled by Alexandra Ripley (Alexandra.Ripley@fortworthtexas.gov)
Form filling Date: 2025-04-09 - 5:32:49 PM GMT - Time Source: server- IP address: 204.10.90.100
Email viewed by Ben Weaverling (Ben.Weaverling@fortworthtexas.gov)
2025-04-09 - 8:57:47 PM GMT- IP address: 107.115.171.69
Signer anup@urbaniconstruct.com entered name at signing as Anup Tamrakar
2025-04-11 - 0:51:15 AM GMT- IP address: 107.115.171.41
Document e-signed by Anup Tamrakar (anup@urbaniconstruct.com)
Signature Date: 2025-04-11 - 0:51:17 AM GMT - Time Source: server- IP address: 107.115.171.41
40 Document e-signed by Ben Weaverling (Ben.Weaverling@fortworthtexas.gov)
Signature Date: 2025-04-14 - 1:52:17 PM GMT - Time Source: server- IP address: 47.189.253.24
�'y Document emailed to Daniel Roy (daniel.roy@fortworthtexas.gov) for signature
2025-04-14 - 1:52:21 PM GMT
4' Document emailed to Tariqul Islam (Tariqul.Islam@fortworthtexas.gov) for signature
2025-04-14 - 1:52:21 PM GMT
f) Email viewed by Tariqul Islam (Tariqul.Islam@fortworthtexas.gov)
2025-04-14 - 1:53:09 PM GMT- IP address: 208.184.124.181
&0 Document e-signed by Tariqul Islam (Tariqul.Islam@fortworthtexas.gov)
Signature Date: 2025-04-14 - 1:57:34 PM GMT - Time Source: server- IP address: 208.184.124.181
Email viewed by Daniel Roy (daniel.roy@fortworthtexas.gov)
2025-04-14 - 2:02:34 PM GMT- IP address: 204.10.90.100
JIG Document e-signed by Daniel Roy (daniel.roy@fortworthtexas.gov)
Signature Date: 2025-04-14 - 2:02:54 PM GMT - Time Source: server- IP address: 204.10.90.100
Cry Document emailed to Zelalem Arega (Zelalem.Arega@fortworthtexas.gov) for signature
2025-04-14 - 2:02:57 PM GMT
FDRTW❑RTHg I P--d6y
Adobe
Acrobat Sign
105046-CNCO-2025 Concrete Restoration
Contract 1, C01
Interim Agreement Report 2025-04-14
Created: 2025-04-14
By: Andrea Munoz (Andrea. M unoz@fortworthtexas.gov)
Status: Out for Signature
Transaction ID: CBJCHBCAABAAKvRBNK8xv2SpTew7SzpcHgYfFGwlOaCU
Agreement History
Agreement history is the list of the events that have impacted the status of the agreement prior to the final signature. A final audit report will
be generated when the agreement is complete.
"105046-CNCO-2025 Concrete Restoration Contract 1, COV Hi
story
Document created by Andrea Munoz (Andrea.Munoz@fortworthtexas.gov)
2025-04-14 - 5:35:21 PM GMT- IP address: 204.10.90.100
Document emailed to Zelalem Arega (Zelalem.Arega@fortworthtexas.gov) for signature
2025-04-14 - 5:57:10 PM GMT
Email viewed by Zelalem Arega (Zelalem.Arega@fortworthtexas.gov)
2025-04-14 - 6:05:56 PM GMT- IP address: 208.184.124.181
FORTW❑RTHg I Paw m"Y
Adobe
Acrobat Sign
FORT WORTH.
Routing and Transmittal Slip
Transportation and Public Works
Department
DOCUMENT TITLE: 2025 Concrete Restoration Contract 1, CO 1
M&C CPN 105046
CSO # 62450
DOC#
DATE:
INITIALS
DATE OUT
To: 1. Crystal Greene (Business Supporter
Apr 9, 2025
2.Urban Infraconstruction LLC— Anup
Apr 10 2025
Tamrakar
s. Ben Weaverling (Inspector)
8W
Apr 14, 2025
4. Daniel Roy (Sr. Inspector)
,Roy
Apr 14, 2025
5.Tariqul Islam (PM)
Targullslam
Apr 14, 2025
6 Zelalem Arega (PGM)
Z�
Zelalem Areea
Apr 14, 2025
7. Mary Hanna (SCPO)
N�/'
Apr 14, 2025
s. Patricia Wadsack (AD)
PLIA/
Apr 14, 2025
9. Lauren Prieur (Director)
de9p UY
Apr 14, 2025
Doug Black (ACA)
0
OF
Apr 16, 2025
•
Douglas Black
11.Jesica McEachern (ACM)
CA
Apr 20, 2025
12. Jannette Goodall (CS) JG ya Apr 21, 2025
DOCUMENTS FOR CITY MANAGER'S SIGNTURE: All documents received from any and all City
Departments requesting City Manager's signature for approval MUST BE ROUTED TO THE
APPROPRIATE ACM for approval first. Once the ACM has signed the routing slip, Jay will review
and take the next steps.
NEEDS TO BE NOTARIZED: U Yes ❑✓ No
RUSH: ❑ Yes ❑✓ No SAME DAY: ❑ Yes ❑✓ No NEXT DAY: ❑Yes ❑✓ No
ROUTING TO CSO: ❑✓ Yes ❑No
Action Reauired:
❑ As Requested ❑ Attach Signature, Initial and Notary Ta
■ Signature/Routing and or Recording
❑ Comment
❑ File
Return to: Please call
at ext. for pick up when completed. Thank you.