HomeMy WebLinkAboutContract 60661-FP2FORT WORTH.
-FP2
City Secretary 60661
Contract No.
Date Received 5/12/2025
AT
NOTICE OF PROJECT COMPLETION
(Developer Projects)
The Transportation and Public Works Department upon the recommendation of the Project
Manager has accepted the following project as complete:
Project Name: Southeastern Freight Lines
City Project No.: 104862
Improvement Type(s): Water ❑x Sewer ❑
Original Contract Price: $3,550.00
Amount of Approved Change Order(s): $0.00
Revised Contract Amount: $0.00
Total Cost of Work Complete: $3,550.00
Ryan Kopf-kvuer
Rvan Korthauer (Mav2, 2025 10:19 CDT)
Contractor
Project Executive
Title
Schwob Building Co. LLC
Company Name
Steve Johnson 0av2.202514:01 CDT)
Project Inspector
Project Manager
Kandira Marrirk ( Mav 19 909514-n') CDTI
CFA Manager
Lauren Prieur (Mav 12, 202514:11 CDT)
TPW Director
05/01/2025
Date
05/02/2025
Date
05/02/2025
Date
05/12/2025
Date
05/12/2025
Date
05/12/2025
Asst. City Manager Date
OFFICIAL RECORD
CITY SECRETARY Page 1 of 2
FT. WORTH, TX
Notice of Project Completion
Project Name: Southeastern Freight Lines
City Project No.: 104862
City's Attachments
Final Pay Estimate FKI
Change Order(s): ❑ Yes IN N/A
Pipe Report: ❑ Yes ® N/A
Contractor's Attachments
Affidavit of Bills Paid
Consent of Surety +?
Statement of Contract Time
Contract Time: 119 WD Days Charged: 78 WD
Work Start Date: 7/15/2024 Work Complete Date: 3/31/2025
Completed number of Soil Lab Test: 23
Completed number of Water Test: 0
Page 2 of 2
FORT WORTH
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name SOUTHEASTERN FREIGHT LINES FORT WORTH ADDITION
Contract Limits
Project Type WATER
City Project Numbers 104862
DOE Number 4862
Estimate Number 1 Payment Number 1 For Period Ending 3/31/2025
WD
City Secretary Contract Number Contract Time 114JD
Contract Date Days Charged to Date 78
Project Manager NA Contract is 100.00 Complete
Contractor SCHWOB BUILDING COMPANY, LTD.
2349 GLENDA LN
DALLAS, TX 75229
Inspectors D. WATSON / S. JOHNSON
Monday, April 21, 2025 Pagel of 4
City Project Numbers 104862
Contract Name SOUTHEASTERN FREIGHT LINES FORT WORTH ADDITION
Contract Limits
Project Type WATER
Project Funding
UNIT I: WATER IMPROVEMENTS
Item Description of Items Estimated Unit
No. Quanity
----------------------
1 WATER LINE GROUTING 0.5 CY
2 4"-12" ABANDONMENT PLUG 1 EA
3 ABANDONMENT 6" WATER VALVE 1 EA
Sub -Total of Previous Unit
DOE Number 4862
Estimate Number 1
Payment Number 1
For Period Ending 3/31/2025
Unit Cost
Estimated
Completed
Completed
Total
Quanity
Total
----------------
$3,500.00
$1,750.00
0.5
$1,750.00
$1,000.00
$1,000.00
1
$1,000.00
$800.00
$800.00
1
$800.00
$3,550.00
$3,550.00
Monday, April 21, 2025 Page 2 of 4
City Project Numbers 104862
Contract Name SOUTHEASTERN FREIGHT LINES FORT WORTH ADDITION
Contract Limits
Project Type WATER
Project Funding
Contract Information Summary
Original Contract Amount
Change Orders
Total Contract Price
DOE Number 4862
Estimate Number 1
Payment Number 1
For Period Ending 3/31/2025
$3,550.00
$3,550.00
Total Cost of Work Completed $3,550.00
Less % Retained $0.00
Net Earned $3,550.00
Earned This Period $3,550.00
Retainage This Period $0.00
Less Liquidated Damages
Days @ / Day
LessPavement Deficiency
Less Penalty
Less Previous Payment
Plus Material on Hand Less 15%
Balance Due This Payment
$0.00
$0.00
$0.00
$0.00
$0.00
$3,550.00
Monday, April 21, 2025 Page 3 of 4
City Project Numbers 104862
Contract Name SOUTHEASTERN FREIGHT LINES FORT WORTH ADDITION
Contract Limits
Project Type WATER
Project Funding
Project Manager NA
Inspectors D. WATSON / S. JOHNSON
Contractor SCHWOB BUILDING COMPANY, LTD,
2349 GLENDA LN
DALLAS, TX 75229
DOE Number 4862
Estimate Number 1
Payment Number 1
For Period Ending 3/31/2025
City Secretary Contract Number
Contract Date
Contract Time 119 WD
Days Charged to Date 78 WD
Contract is .000000 Complete
CITY OF FORT WORTH
SUMMARY OF CHARGES
Line Fund Account Center Amount Gross Retainage Net
Funded
Total Cost of Work Completed
$3,550.00
Less % Retained
$0.00
Net Earned
$3,550.00
Earned This Period $3,550.00
Retainage This Period $0.00
Less Liquidated Damages
0 Days @ $0.00 / Day
$0.00
LessPavement Deficiency
$0.00
Less Penalty
$0.00
Less Previous Payment
$0.00
Plus Material on Hand Less 15%
$0.00
Balance Due This Payment
$3,550.00
Monday, April 21, 2025 Page 4 of 4
FORTWORTH.
M"
TRANSPORTATION AND PUBLIC WORKS
March 31, 2025
Schwob Building Company,LLC
1350 Lakeshore Dr.
Coppell, Texas 75019
RE: Acceptance Letter
Project Name: Southeastern Freight Lines
Project Type: Water, Paving
City Project No.: 104862
To Whom It May Concern:
On March 31, 2025 a final inspection was made on the subject project. There were no punch list items
identified at that time. The final inspection indicates that the work meets the City of Fort Worth
specifications and is therefore accepted by the City. The warranty period will start on March 31, 2025,
which is the date of the final inspection and will extend of two (2) years in accordance with the Contract
Documents.
If you have any questions concerning this letter of acceptance, please feel free to contact me at
(817)770-3664.
Sincerely,
Sandip Adhikari, Project Manager
Andrew Goodman, Program Manager
Cc: Steven Johnson, Inspector
Donald Watson, Inspection Supervisor
Aaron Ybarra, Senior Inspector
Andrew Goodman, Program Manager
Weir and Associats, Consultant
Schwob Building Company,LLC., Contractor
Weir and Associats, Developer
File
E-Mail: TPW_Acceptance@fortworthtexas.gov
Rev. 08/20/19
1350 Lakeshore Dr. Ste 160
Coppell, TX 75019
972.243.7674 Phone
Schwob
BUILDING COMPANY, LLC
CONDITIONAL WAIVER AND RELEASE ON FINAL PAYMENT
Project
Self Fort Worth
Job No. 2403
Schwob Bldg Co.
On receipt by the signer of this document of a check from (maker of
check) in the sum of $26208.50 payable to Moss utilities, payee or payees of check) and
when the check has been properly endorsed and has been paid by the bank on which it
is drawn, this document becomes effective to release any mechanic's lien right, any right
arising from a payment bond that complies with a state or federal statute, any common law
payment bond right, any claim for payment, and any rights under any similar ordinance,
rule, or statute related to claim or payment rights for persons in the signer's position that
the signer has on the property of southeastern r g{ t 11AM& at Ft Worth, TX (location)
to the following extent: Site Utilities, . (job description).
This release covers the final payment to the signer for all labor, services,
equipment, or materials furnished to the property or to south easte(pEfreWlMii*er6hom
signer contracted).
Before any recipient of this document relies on this document, the recipient should
verify evidence of payment to the signer.
The signer warrants that the signer has already paid or will use the funds received
from this final payment to promptly pay in full all of the signer's laborers, subcontractors,
materialmen, and suppliers for all work, materials, equipment, or services provided for or
to the above referenced project up to the date of this waiver and release.
Date 1.20.25
Moss Utilities, LLC
By
President
(Company name)
(Signature)
(Title)
1350 Lakeshore Dr. Ste 160
Coppell, TX 75019
972.243.7674 Phone
Schwob
BUILDING COMPANY, LLC
CONDITIONAL WAIVER AND RELEASE ON FINAL PAYMENT
Project
Self Fort Worth
Job No. 2403
Schwob Bldg Co.
On receipt by the signer of this document of a check from (maker of
check) in the sum of $26208.50 payable to Moss utilities, payee or payees of check) and
when the check has been properly endorsed and has been paid by the bank on which it
is drawn, this document becomes effective to release any mechanic's lien right, any right
arising from a payment bond that complies with a state or federal statute, any common law
payment bond right, any claim for payment, and any rights under any similar ordinance,
rule, or statute related to claim or payment rights for persons in the signer's position that
the signer has on the property of southeastern r g{ t 11AM& at Ft Worth, TX (location)
to the following extent: Site Utilities, . (job description).
This release covers the final payment to the signer for all labor, services,
equipment, or materials furnished to the property or to south easte(pEfreWlMii*er6hom
signer contracted).
Before any recipient of this document relies on this document, the recipient should
verify evidence of payment to the signer.
The signer warrants that the signer has already paid or will use the funds received
from this final payment to promptly pay in full all of the signer's laborers, subcontractors,
materialmen, and suppliers for all work, materials, equipment, or services provided for or
to the above referenced project up to the date of this waiver and release.
Date 1.20.25
Moss Utilities, LLC
By
President
(Company name)
(Signature)
(Title)