HomeMy WebLinkAboutContract 61221-FP1-FP1
FORTWORTH.
City Secretary
Contract No. 61221
Date Received 5/12/2025
AT
NOTICE OF PROJECT COMPLETION
(Developer Projects)
The Transportation and Public Works Department upon the recommendation of the Project
Manager has accepted the following project as complete:
Project Name: Crawford Parking Express CFA
City Project No.: 105083
Improvement Type(s): ❑ Paving ❑ Drainage ❑x Street Lights ❑ Traffic Signals
Original Contract Price: $67,687.45
Amount of Approved Change Order(s): $19,769.79
Revised Contract Amount: $87,457.24
Total Cost of Work Complete: $87,457.24
Ericp Digitally signed by Eric tner 05/05/2025
G C i t f 1 e C' Date: 2025.05.05 11:21:15 :15-0-05'00'
Contractor Date
Project Manager
Title
Pavecon LTD
Company Name
,Ed d�V (Mav6,202515:18CDT) 05/06/2025
Project Inspector
Date
Z -&�
05/12/2025
Project Manager
Date
05/12/2025
,a dice Mav12,202508:51CDT)
CFA Manager
Date
A.Z.—
05/12/2025
Lauren Prieur (May 12, 2025 08:52 CDT)
TPW Director
Date
w
05/12/2025
Asst. City Manager
Date
OFFICIAL RECORD
CITY SECRETARY Page 1 of 2
FT. WORTH, TX
Notice of Project Completion
Project Name: Crawford Parking Express CFA
City Project No.: 105083
City's Attachments
Final Pay Estimate ❑x
Change Order(s): ❑x Yes ❑ N/A
Contractor's Attachments
Affidavit of Bills Paid
Consent of Surety
Statement of Contract Time
Contract Time 15 WD
Days Charged: 43 WD
Work Start Date: 12/9/2024 Work Complete Date: 2/21/2025
Completed number of Soil Lab Test: 14
Completed number of Water Test: 0
Page 2 of 2
FORT WORTH
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name 604 CRAWFORD IMPROVEMENTS
Contract Limits
Project Type STREETLIGHTS
City Project Numbers 105083
DOE Number 5083
Estimate Number 1 Payment Number 1 For Period Ending 2/21/2025
WD
City Secretary Contract Number Contract Time 1WD
Contract Date Days Charged to Date 43
Project Manager NA Contract is 100.00 Complete
Contractor PAVECON LTD. CO
3022 ROY ORR BLVD
GRAND PRAIRE, TX 75050
Inspectors E.VELIZ / K.GOINES
Tuesday, March 25, 2025 Page 1 of 4
City Project Numbers 105083 DOE Number 5083
Contract Name 604 CRAWFORD IMPROVEMENTS Estimate Number 1
Contract Limits Payment Number 1
Project Type STREETLIGHTS For Period Ending 2/21/2025
Project Funding
UNIT V: STREET LIGHTING IMPROVEMENTS
Item
Description of Items
Estimated Unit
Unit Cost
Estimated
Completed
Completed
No.
Quanity
Total
Quanity
Total
---------------------------------------
1
2" CONDUIT PVC SCH 80 (CO#1)
190 LF
$100.00
$19,000.00
190
$19,000.00
2
GROUND BOX TYPE B
3 EA
$1,500.00
$4,500.00
3
$4,500.00
3
RDWY ILLUM FOUNDATION TY 7
3 EA
$880.00
$2,640.00
3
$2,640.00
4
FURNISH/INSTALL 10-14' WASHINGTON
3 EA
$8,050.00
$24,150.00
3
$24,150.00
STANDARD LIGHT POLE & FIXTURE LED
5
NO 6INSULATED ELEC CONDR(CO#1)
600 LF
$2.00
$1,200.00
600
$1,200.00
6
TRAFFIC CONTROL
1 MO
$1,000.00
$1,000.00
1
$1,000.00
7
REMOVE SIDEWALK 4" CONC
506 SF
$25.33
$12,816.98
506
$12,816.98
SIDEWALK(CO#1)
8
4" CONC SIDEWALK(CO#1)
559 SF
$31.78
$17,765.02
559
$17,765.02
9
--------------------------------------
SPECIFIED REMOBILIZATION (CO#1)
1 LS
$4,385.24
$4,385.24
1
$4,385.24
Sub-Total of
Previous Unit
$87,457.24
$87,457.24
Tuesday, March 25, 2025 Page 2 of 4
City Project Numbers 105083
Contract Name 604 CRAWFORD IMPROVEMENTS
Contract Limits
Project Type STREETLIGHTS
Project Funding
Contract Information Summary
Original Contract Amount
Chan Orders
Change Order Number 1
Total Contract Price
DOE Number 5083
Estimate Number I
Payment Number I
For Period Ending 2/21/2025
$67,687.45
$19,769.79
$87,457.24
Total Cost of Work Completed $87,457.24
Less % Retained $0.00
Net Earned $87,457.24
Earned This Period $87,457.24
Retainage This Period $0.00
Less Liquidated Damages
Days @ / Day
LessPavement Deficiency
Less Penalty
Less Previous Payment
Plus Material on Hand Less 15%
Balance Due This Payment
$0.00
$0.00
$0.00
$0.00
$0.00
$87,457.24
Tuesday, March 25, 2025 Page 3 of 4
City Project Numbers 105083
Contract Name 604 CRAWFORD IMPROVEMENTS
Contract Limits
Project Type STREETLIGHTS
Project Funding
Project Manager NA
Inspectors E.VELIZ / KGOINES
Contractor PAVECON LTD. CO
3022 ROY ORR BLVD
GRAND PRAIRE, TX 75050
DOE Number 5083
Estimate Number 1
Payment Number 1
For Period Ending 2/21/2025
City Secretary Contract Number
Contract Date
Contract Time 15 WD
Days Charged to Date 43 WD
Contract is .000000 Complete
CITY OF FORT WORTH
SUMMARY OF CHARGES
Line Fund Account Center Amount Gross Retainage Net
Funded
-----------------------------
Total Cost of Work Completed $87,457.24
Less % Retained $0.00
Net Earned $87,457.24
Earned This Period $87,457.24
Retainage This Period $0.00
Less Liquidated Damages
0 Days @ $0.00 / Day
$0.00
LessPavement Deficiency
$0.00
Less Penalty
$0.00
Less Previous Payment
$0.00
Plus Material on Hand Less 15%
$0.00
Balance Due This Payment
$87,457.24
Tuesday, March 25, 2025 Page 4 of 4
PROJECT NAME:
CONTRACT:
CFA #
CITY PROJECT #
FID #
FILE #
INSPECTOR:
PROJECT MANAGER:
DEVELOPER -AWARDED -PROJECT CHANGE ORDER
604 Crawford Parkinq CHANGE
CS-61221 ORDER No:
23-0117 CITY PARTICIPATION: NO
105083
1
30114-0200431-105083-EO7685
K-3203
Kerry Goines
Debbie Willhelm
WATER
Cost
City Cost
ORIGINAL CONTRACT
$0.00
$0.00
EXTRAS TO DATE
CREDITS TO DATE
CONTRACT TO DATE
$0.00
$0.00
AMOUNT OF PROP. CHANGE ORDER
$0.00
$0.00
REVISED CONTRACT AMOUNT
$0.00
$0.00
TOTAL REVISED CONTRACT AMOUNT
PER UNIT
$0.00
REVISED COST SHARE
Dev. Cost:
TOTAL REVISED CONTRACT
Phone No: 817-319-6452 REVIEWED
Phone No: 817-392-2481 By Debbie J. Willhelm at 3:17 pm, Jan 21, 2025
CONTRACT UNIT
SEWER PAVING DRAINAGE STREET LIGHTS CONTRACT
doper Developer Developer Developer DAYS
City Cost Cost City Cost Cost City Cost Cost City Cost
$0.00 $0.00 I $0.00 1 $0.00 $0.00 1 $0.00 1 $67,687.45 $0.00 I 15
$0.00 $0.00 I $0.00 $0.00 $0.00 $0.00 $67,687.45 $0.00 I 15
$0.00 $0.00 I $0.00 $0.00 $0.00 $0.00 $19,769.79 $0.00 I 0
$0.00 $0.00 I $0.00 $0.00 $0.00 $0.00 $87,457.24 $0.00 I 15
$0.00 $0.00 $0.00 $87,457.24
$87,457.24 City Cost: $0.00
$87,457.24
Revised: 10-12-2011 Page 1
You are directed to make the following changes in the contract documents:
UNIT V : Street Light Improvements
CITY BID ITEM
PAY ITEM #
#
QUANTITY
UNIT
ITEM DESCRIPTION
UNIT PRICE
TOTAL
1
2605.3015
15
LF
2" Conduit PVC SCH 80
$
100.00
$ 1,500.00
5
3441.1408
75
LF
NO 6 Insulated Elec Condr
$
2.00
$ 150.00
7
0241.0100
211
SF
Remove Sidewalk
$
25.33
$ 5,344.63
8
3213.0301
264
SF
4" Conc Sidewalk
$
31.78
$ 8,389.92
NEW
170.0101
1
LS
Specified Remobilization
$
4,385.24
$ 4,385.24
TOTAL UNIT V: Street Light Improvements
$ 19,769.79
REASONS FOR CHANGE ORDER Conflict found between existing AT&T underground conduit, which required revised placement of pedestrian poles. Changes corresponding to Plan Revision 1
as shown on Sheet ES1.00 of the construction plans.
NO CITY FUNDS INVOLVED IN THIS CONTRACT. DEVELOPER IS RESPONSIBLE FOR 100% OF THE CHANGE ORDER COST AND NO
REIMBURSEMENT FROM THE CITY WILL BE SOUGHT BY THE DEVELOPER
RECOMMENDED: APPROVED: APPROVED:
Evolving Texas
By: &a-&M David
Name: Chandler Davis. P.E.. CFM
Title: Project Manaoer
Greenstar Development Holdings ll, LLC
By: �{2ccil¢oe/ 6ealxx6e
Name: Michael Polombo
Title: Manaoer
Pavecon, LTD
By: l-'uCi
Name: Eric Lechlitner
Title: Project Manager
Revised: 10-12-2011 Page 2
FORT W0RTH@
TRANSPORTATION AND PUBLIC WORKS
March 14, 2025
Pavecon LTD
3022 Roy Orr Blvd,
Grand Prairie, TX 75050
RE: Acceptance Letter
Project Name: Crawford Parking Express CFA
Project Type: Street Light Improvement
City Project No.: 105083
To Whom It May Concern:
On March 13, 2025 a final inspection was made on the subject project. There were no punch list items
identified at that time. The final inspection indicates that the work meets the City of Fort Worth
specifications and is therefore accepted by the City. The warranty period will start on March 6, 2025,
which is the date of the final inspection and will extend of two (2) years in accordance with the Contract
Documents.
If you have any questions concerning this letter of acceptance, please feel free to contact me at
Andrew.Goodman@fortworthtexas.gov .
Sincerely,
Andrew Goodman, Project Manager
Cc: Kerry. Goi n es@fortworthtexas.gov, Inspector
Michael.Myers@fortworthtexas.gov, Inspection Supervisor
EduardoVeliz@fortworthtexas.gov, Senior Inspector
@fortworthtexas.gov, Program Manager
Samantha@evolingtexas.com, Consultant
elechlitner@pavecon.com, Contractor
michael@gsdre.com, Developer
File
E-Mail: TPW_Acceptance@fortworthtexas.gov
Rev.08/20/19