HomeMy WebLinkAboutIR 8105 INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 8105
`"' TERFO
-y 27, 1998
To the Mayor and Members of the City Council Januar
J.
XA Subject: Status Report on Computer Aided Dispatch (CAD) Project
1973
Introduction
On July 15, 1997, the City Council received IR 8080 regarding the Computer
Aided Dispatch and Mobile Data Computing project for Police, Fire and
MedStar. A presentation was made to the City Council on July 15, 1997
describing the impetus for the project, progress to date, estimates of future
expenses for the project, and a timeline for the next steps of the project.
Impetus for a New System
In March 1994 a fire resulted in the loss of 4 lives. This event precipitated
events that focused attention on the Computer Aided Dispatch (CAD) System.
While the CAD System did not contribute to the loss of lives, it was determined
to be in need of replacement. The City Council in April 1994 directed staff to
pursue this issue. The City subsequently contracted with Public Technology,
Inc. (PTI) for a complete analysis of its public safety systems, which included
the CAD System, PTI issued a report that named a number of reasons for
replacing the existing system. City staff then developed an RFP and
subsequently contracted with The Warner Group, Management Consultants, to
complete a Technology Needs Assessment and to develop a Request for Proposal
for a fully integrated public safety dispatch system, including CAD, Mobile Data
Computing, Automatic Vehicle Location, and workstation/console furniture.
Expected Benefits
1. The existing system needs to be replaced as it is not expandable, nor is it
capable of handling the needs of Police, Fire and MedStar that have
developed over time.
2. The new CAD System will utilize the latest technology that will establish a
solid foundation for future systems, and provide rapid handling of calls for
service. The RFP specifies totally redundant systems with built-in failover
capabilities to keep systems online at all times.
3. The Automatic Vehicle Location System for the Fire Department and
MedStar will enhance the tracking, positioning and dispatching of
emergency response units.
4. The proposed Mobile Data Computing infrastructure will support field-
based reporting, mapping, fingerprint scanning capability, photographic
identification, scanner technology, hazardous material and heads-up
displays. This will allow improvements in processes for Police, Fire and
MedStar.
5. The new console furniture will meet ADA requirements and be
ergonomically engineered for comfort over extended periods of time.
Existing console systems are not ADA compliant.
...........
41, M
n"V
ISSUED BY THE CITY MANAGER F0iii"W'0'k%"TE_,' S
~
INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 8105
RITE
To the Mayor and Members of the City Council January27, 1998
Page 2 of 3
Subject: Status Report on Computer Aided Dispatch (CAD) Project
Outline of Events
1 The proposal submission deadline for the CAD project was extended from
August 14, 1997 to October 16, 1997 in order for the City to receive
complete and comprehensive proposals. The City Council was made aware
of this change in the July 15, 1997 presentation.
2. The RFP was distributed to eighty-one vendors, of which the city received a
total of seven proposals on October 16, 1997.
3. The preliminary analysis of the seven proposals to identify finalists was
performed by the Warner Group (under contract to the City for this project
as previously approved by the City Council) and the CAD Project Team.
They began the analysis on October 20, 1997 and completed it on
December 19, 1997.
4. A short list of two vendors was selected as finalists. A complete
presentation and discussion with the CAD Policy Team followed. The
Policy Team agreed with the short list of selected vendors. They held their
product demonstrations from January 13, 1998 through January 16,
5. The CAD Project Team will complete site visits for each of the finalists to
installed and functioning sites from January 22, 1998 through January
Bid Analysis Process Explained
I. The last round of detailed questions for the finalists were submitted to the
Warner Group on January 8, 1998.
2. The Warner Group will complete their review of the questions and a
detailed economic analysis on February 5, 1998.
3. The Warner Group will present their final recommendation of the most
appropriate vendor on February 6, 1998 to the CAD Project Team.
4. The CAD Project Team will begin their detailed evaluation process on
February 9, 1998 and complete their selection of the most appropriate
vendor by March 6, 1998.
5. The CAD Project Team's final selection will be proposed -to the-CAD Policy
Team for approval during the week of March 9, 1998.
6. The CAD Policy Team will forward their recommendation to the City
Council for approval and funding only after contract negotiations axe
completed which could take from 1-2 months.
The project will be funded from multiple sources. The Police portion of the
project, which is the larger portion of estimated costs, will be bud
..........
ISSUED BY THE CITY MANAGER FORT WORTH,TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 8105
o !91",Q To the Mayor and Members of the City Council January 27, 1998
Page 3 of 3
Ck
1-t Subject:
7873 Status Report on Computer Aided Dispatch (CAD) Project
Crime Control and Prevention District budget. The Fire portion of the project
will be budgeted in the general fund budget process or through certificates of
obligation. The MedStar portion of the project will be budgeted by MedStar, not
the ambulance authority, which is already subsidized by the City of Fort Worth.
The City Council should anticipate that required funding would be split over
this and the following two fiscal years.
No final figures for total project cost are available at this time. Vendors
proposed costs range from slightly lower to tremendously higher than the
original estimates of$11,193,301. However, vendor proposals do not represent
final figures. Vendor negotiations will proceed only after a finalist is selected.
Staff will strive to bring the project in at a cost as close to the originally
estimated budget as possible.
Funding splits, using the original estimated project cost would be:
Police (Crime District) $8,738,955
Fire $1,507,516
Medstax $946,830
Total $11,193,301
These funding splits are based on a pro rata distribution of shared components
though the percentage of incoming calls transferred to Police, Fire and MedStar.
Available statistics for a year show that 78 percent of incoming calls are
transferred to Police, 13 percent to Fire, and 9 Percent to MedStar. All
components that are directly attributable to a single source are included in that
organization's estimated cost. The Crime Control and Prevention District under
this scenario would be able to afford its share of the total project costs.
4ob Terrell
City Manager
j�
FIE",
...........
ISSUED BY THE CITY MANAGER FORT,WORTH,TEXAS