HomeMy WebLinkAboutIR 8147 INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 8147
To the Mayor and Members of the City Council Page 1 of 1
July 28, 1998
Subject:
•'� RECOMMENDED IMPLEMENTATION PLAN FOR 1998
CIP BOND PROGRAM
This report is to provide a recommended Implementation Plan for the 1998 Bond
Program projects. Since the successful passage of the 1998 Bond Election, intensive
efforts have been underway for developing a four-year schedule for initiating or
completing all projects approved by the voters. As you may recall, this spring the City
Council was furnished a preliminary report for consideration, which provided a proposed
schedule for 1998 bond projects. Since that time, staff has sought input from Council
members regarding Council's priorities and preferred timeframes. Staff has attempted to
adjust the Proposed schedule accordingly. At this time, the plan has been finalized and is
submitted for your approval (see attachments).
Based on feedback, some changes were made in the four-year plan, as follows:
Transportation and Public Works:
The Bellaire Drive South arterial project has been accelerated due to citizen interest.
Based on this change, it is anticipated that design will be initiated in year one (1999) and
the project completed in Year Two (2000).
f Parks and Community Services Program:
The Parking Lot Security Lighting project at the Botanic Garden has been accelerated
due to the increased usage of the garden. Based on this change, it is anticipated that
project design will be completed in the first year (1999) and the project will be completed
by the end of the second year of the implementation schedule (year 2000).
Neighborhood Streets:
Information will be presented to Council for their consideration at the July 28`h pre-
Council meeting regarding the Strategy for Neighborhood Street bond projects.
Further information will be provided upon request.
ATTACHMENTS: A-D
tI
I'T ON?
�--- Bob Terrell
City Managers ,
ISSUED BY THE CITY MANAGER FORT WORTH,TEXAS
��
��OMPREHE^`mI , E PROGRAM
l���D7���-��|� IMPLEMENTATION PLAN:1998 ����X��K
^� ��~'��_� ��^"�� ^^,^� ��"�,�^^�` �'=�^�,�` ° ���=�`~��^~^ ~~^"� � �^=.�
IMPROVEMENTS |�����' ����'��
u�~�^ ���� r ^��,����, "�� ��^v�nu� ^ u���^�RAM
�
BONDS Yr I Yc2 Yr3 Y,4
PROGRAM CATEGORY: APPROVED: Uoro4V99 tx,o4/2U0O tbro4/2UU1 tbmw4/2O02
Central City Streets $26,849.000 $5.000,000 88`000.000 $10'800,000 $3.849'000
Drainage $9.060.000 $2,700.000 $3,500,000 $1.600.800 $1.260.000
Bridges $580'000 $300.000 $280.000
Street Lights $1.500.000 $300.000 $400.000 Q400.800 $400.000
Railroad Crossings $300.000 850.000 $100.800 $75.000 $75,000
Small Drainage $2.026.495 $500.000 $600.000 $500.000 $426.495
k4ioo. Conureto $250,000 $70'000 $60^000 $00.008 $60'000
Traffic Signals $1'700.000 $500'000 $500.000 $500.000 $200'000
Intersection Revisions $1.000.000 $V $250.000 $375.000 $375.000
Roadways iuParks $1.800'000 $958`000 $357.000 $i\O.00O $375.000
City Arterials $17.098.000 $2.705.600 $0.033.400 $3.881.400 $4.477'000
Urban Design $3'310.000 $525.000 $1'693.000 01.092.000 $O
Regional Projects $7.200.000 $1'960.702 $325.000 $3.423.300 $1'490.998
Sidewalks %1.826'505 0392.650 $547.950 $547.950 $337.955 �
New Development $5.000.000 $5.000.000 %O $O $O
Conti ngcocy{F"toru $500.000 $500'000
PUBLIC 8VSNTS/CnuvCtr. $20.700.000 $1.700.000 $4.000.008 $5'000.000 $10.000'008
PARKS $)\.DOU.00O $2.764,776 $3.424'833 03'562.807 $2.047.584
LIBRARY $2'700'000 $405.000 $2`295.000 $O $0
F|0G $4.800.000 $2.000.000 $O $0 $2'800`000
TOTAL ALL CATEGORIES $120.000.000 $27.831.728 $32.366.183 $3).|27.457 $28.074.632
PERCENT OFTOTAL: 23% 27% 26% 24%
Aq�
�
ATTACHMENT
MAJOR FACILITIES AND OTHER PROJECTS
FOUR-YEAR IMPLEMENTATION PLAN:1998 CAPITAL
r7l, IMPROVEMENTS PROGRAM
BONDS Yr I Yr 2 Yr 3 Yr 4
APPROVED: thru 4/99 thru 4/2000 thru 4/2001 thru 4/2002
PUBLIC EVENTS
Cowtown Colliseum $700,000 $700,000
Will Rogers Mem.Cntr. $1,000,000 $1,000,000
Total Public Events: $1,700,000 $1,700,000
PARKS AND COMMUNITY SERVICES
SE Community Center $1,495,724 $25,000 $200,000 $1,270,724
All Other PACS Projects $10,304,276 $2,739,776 $3,224,833 $2,292,083 $2,047,584
Total PACS: $11,800,000 $2,764,776 $3,424,833 $3,562,807 $2,047,584
LIBRARY
Summerfields/Park Glen Library $2,700,000 $405,000 $2,295,000
Total Library: $2,700,000 $405,000 $2,295,000
FIRE
Bryant Irvin area Fire Sta. $2,000,000 $500,000 $1,500,000
Alliance Corridor Fire Sta. $1,800,000 $500,000 $1,300,000
Signal Control System $1,000,000 $1,000,000
Total Fire: $4,800,000 $2,000,000 $o $0 $2,800,000
See PACS Detailed Schedule in report.
(I v II if
q
ATTACHMENT B
ARTERIAL AND REGIONAL PROJECTS
FOUR-YEAR IMPLEMENTATION PLAN: 1998 CAPITAL
IMPROVEMENTS BOND PROGRAM
BONDS Yr I Yr 2 Yr 3 Yr 4
APPROVED: thru 4/99 thru 4/2000 thru 4/2001 thru 4/2002
City Arterials $17,098,000 $2,705,600 $6,033,400 $3,881,400 $4,477,600
Basswood $336,000 $784,000
Bellaire Dr.S. $912,000 $2,128,000
Camp Bowie $450,000 $1,050,000
Hemphill/Lamar/Taylor $o $0 $500,000
Henderson Underpass $330,000 $770,000
Jennings Underpass $30,000 $70,000
Main St.Underpass $30,000 $70,000
Lancaster Ave. $150,000 $350,000
Meacham Blvd.* $2,600,000
Remaining projects $1,307,600 $1,961,400 $1,961,400 $1,307,600
Urban Design $3,310,000 $525,000 $1,693,000 $1,092,000 $0
Berry Streetscape $450,000 $1,050,000
Camp Bowie/7th/University $75,000 $175,000
North Main linkage $0 $468,000 $1,092,000
Regional Projects $7,200,000 $1,960,702 $325,000 $3,423,300 $1,490,998
Trinity Blvd. $1,735,702
Vickery Blvd. $100,000 $400,000 $1,365,998
N.University Bridge $128,300
SW Pkwy. $125,000 $125,000 $125,000 $125,000
Bailey's Industrial Drainage $100,000 $100,000 $2,770,000
ATTACHMENT C
PARKS AND COMMUNITY SERVICES
FOUR YEAR IMPLEMENTATION PLAN: 1998 CAPITAL
IMPROVEMENTS PROGRAM
Bonds Yr1 Yr2 Yr3 Yr4
Projects: Project/or Category: Approved: thru 4/1999 thru 4/2000 thru 4/2001 thru 4/2002
20 Playground Renovation $863,576 $863,576 $0 $0 $0
15 Playground safety surfaces $245,700 $245,700 $0 $0 $0
1 Trinity sidewalk replacement $40,000 $6,000 $34,000 $0 $0
1 Harmon Field $300,000 $60,000 $240,000 $0 $0
1 Rolling Hills Soccer Complex $900,000 $180,000 $220,000 $500,000 $0
1 Sycamore Youth Sports Complex $300,000 $0 $300,000 $0 $0
1 Trinity Shelter renovation $50,000 $0 $50,000 $0 $0
1 Trinity Trail replacement $195,000 $65,000 $130,000 $0 $0
4 Replace Athletic Field Lighting $535,000 $229,000 $153,000 $0 $153,000
1 Water Gardens $500,000 $0 $50,000 $450,000 $0
7 Fart Worth Zoo $3,000,000 $150,000 $1,455,000 $655,000 $740,000
1 Bot. Garden Greenhouse Relocation $300,000 $0 $0 $45,000 $255,000
1 Botanic Garden Parking Lot Security
Lighting $150,000 $20,000 $130,000 $0 $0
1 Acoustical improvements: Southside
Comm. Ctr. $20,000 $20,000 $0 $0 $0
1 McLeland $100,000 $0 $0 $15,000 $85,000
1 Trinity Park Security Lighting $20,000 $0 $20,000 $0 $0
1 Southeast CC $1,495,724 $25,000 $200,000 $1,270,724 $0
1 Acquisition: Far North Comm. Park $750,000 $750,000 $0 $0
30 Park Security Lighting $340,000 $0 $113,333 $113,333 $113,334
5 Renovate existing walks and trails $270,000 $40,500 $229,500 $0 $0
1 Bradley Comm. Ctr. Renovation $50,000 $50,000 $0 $0 $0
1 West Community Park Development $200,000 $0 $0 $40,000 $160,000
1 Developing Areas $400,000 $0 $60,000 $155,000 $185,000
1 Lake Como shore improvements $100,000 $0 $0 $15,000 $85,000
1 Boundary fence at Nature Center $125,000 $0 $0 $18,750 $106,250
1 Development: Far North Comm Prk. $200,000 $0 $0 $20
2 h
Develop previously acquired Park ,
sites $100,000 $0 $0 $l ,0 r $�
1f Jr ,,..k}.
Parking Lot Security Lighting A!
r .I
Nature Center $20,000 $0 $0 $ ,0 ' + i�o °lt
2 Additional Park Improvements $50,000 $50,000 $0 $0
2 Additional Park Improvements at
Community Parks $80,000 $10,000 $40,000 $30,000 $0
1 Bridge replacement: Nature Center $100,000 $0 $0 $20,000 $80,000
109 TOTALS: $11,800,000 $2,764,776 $3,424,833 $3,562,807 $2,047,584
7/24/98 10:02 AM ATTACHMENT D
PARKS AND COMMUNITY SERVICES
FOUR YEAR IMPLEMENTATION PLAN: 1998 CAPITAL
IMPROVEMENTS PROGRAM
Bonds YrI Yr2 Yr3 Yr4
Project/or Category: Approved: thru 4/1999 thru 4/2000 thru 4/2001 thru 4/2002
ZOO PROJECTS:
Aquarium $520,000 $0 $260,000 $260,000
Herpetarium $480,000 $0 $240,000 $240,000
Lion Mountain $240,000 $120,000 $120,000
Restrooms $250,000 $50,000 $200,000
Animal Nutrition Complex $1,000,000 $100,000 $900,000 $o
Small Mammal Village $275,000 $0 $35,000 $240,000
Public Picnic Pavillion $235,000 $235,000
TOTAL: $3,000,000 $150,000 $1,455,000 $655,000 $740,000
ROADWAYS in PARKS:
Oakland Lake Park $145,000 $145,000
Rockwood Ballfields $320,000 $320,000
Lincoln Park $60,000 $60,000
Sycamore Park $433,000 $433,000
Trinity Park $357,000 $357,000
Log Cabin Village $55,000 $55,000
Fort Worth Nature Center $55,000 $55,000
Colonial Parkway Bridge $375,000 $375,000
TOTAL: $1,800,000 $958,000 $357,000 $110,000 $375,000
7/24/98 10:02 AM ATTACHMENT D