HomeMy WebLinkAboutContract 50312-A7CSC No. 50312-A7
AMENDMENT No . 7
TO CITY SECRETARY CONTRACT No. 50312
WHEREAS, the City of Fort Worth (CITY) and Freese and Nichols, Inc.,
(ENGINEER) made and entered into City Secretary Contract No. 50312, (the
CONTRACT) which was authorized M&C C-28566 on the 30th day of January, 2018,
in the amount of $3,099,361.00; and
WHEREAS, the CONTRACT was subsequently revised by: Amendment No.l in the
amount of $229,755.00 authorized by M&C C-29067 on March 19th, 2019, Amendment
No.2 in the amount of $366,004.00 authorized by M&C C-29178 on June 25th,
2019, Amendment No.3 in the amount of $211,344.00 authorized by M&C 20-0137
on March 3rd, 2020, Amendment No.4 in the amount of $392,668.00 authorized by
M&C 20-0460 on June 23rd, 2020, Amendment No.5 in the amount of $323,249.00
authorized by M&C 22-0290 on April 12th, 2022 and Amendment No.6 in the amount
of $1,511,941.00 authorized by M&C 24-0844 on September 17, 2024; and
WHEREAS, the CONTRACT involves engineering services for the following
project:
Lake Arlington Lift Station and Force Main, CPN 100995; and
WHEREAS, it has become necessary to execute Amendment No. 7 to the
CONTRACT to include an increased scope of work and revised fee.
NOW THEREFORE, CITY and ENGINEER, acting herein by and through their duly
authorized representatives, enter into the following agreement, which amends
the CONTRACT:
1.
Article I of the CONTRACT is amended to include the additional engineering
services specified in proposal attached hereto and incorporated herein. The
cost to City for the additional design services to be performed by Engineer
totals $99,932.00.
2.
Article II of the CONTRACT is amended to provide for an increase in the
fee to be paid to Engineer for all work and services performed under the
Contract, as amended, so that the total fee paid by the City for all work and
services shall be an amount of $ 6,234,254.00.
3.
All other provisions of the Contract, which are not expressly amended
herein, shall remain in full force and effect.
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
City of Fort Worth, Texas Lake Arlington Lift Station and Force Main
Prof Services Agreement Amendment Template CPN 100995
Revision Date: 12/08/2023
Page 1 of 2
EXECUTED and EFFECTIVE as of the date subscribed by the City's designated
Assistant City Manager.
APPROVED:
City of Fort Worth
i
Jesica McEachern
Assistant City Manager
DATE: 06/04/2025
pO�onp
pONT d �aO
Fo
ATTEST:
a°tat ezae44a
JannettetGoodall
City Secretary
APP/R�O�VAL RECOMME,(NDDED :
Ite
Christopher H rder (May 22, 2025 16:30 CDT)
Christopher Harder, P. E.
Director, Water Department
Contract Compliance Manager:
ENGINEER
Freese & Nichols, Inc.
Nick Lester, P.E
Vice President
DATE: 05/21 /2025
By signing, I acknowledge that I am the person responsible for the
monitoring and administration of this contract, including ensuring all
performance and reporting requirements.
Digitally signed by Bijay Upreti
DIN: C=US,
i@fortworthtexas gov,Bijay Upret GN=Bilay Uprev Reason: I have reviewed this document
Data 2025.05 21 09:5433-05'00'
Bijay Upreti, P.E.
Project Manager
M&C No.#: N/A
APPROVED AS TO FORM AND LEGALITY:
lg� M&C Date: N/A
Douglas Black (May 23, 2025 17:27 CDT)
Douglas W. Black Form 1295: N/A
Sr. Assistant City Attorney
OFFICIAL RECORD
CITY SECRETARY
City of Fort Worth, Texas FT. WORTH, TX Lake Arlington Lift Station and Force Main
Prof Services Agreement Amendment Template CPN 100995
Revision Date: 12/08/2023
Page 2 of 2
801 Cherry Street, Suite 2800 + Fort Worth, Texas 76102 + 817-735-7300 + FAX 817-735-7491 www.freese.com
May 9, 2025
Mr. Bijay Upreti
Project Manager
City of Fort Worth Water Department
100 Fort Worth Trail
Fort Worth, TX 76102
Re: Amendment 7 for the Lake Arlington Lift Station and Force Main (City Project No. 100995)
Dear Mr. Upreti:
Freese and Nichols, Inc. (FNI) is providing this proposal to amend the Engineering Design Services and
Construction Services for the Lake Arlington Lift Station and Force Main (City Project Number 100995).
The following scope and fee includes the costs for additional permitting, archeological survey, resetting
control points for construction staking, and construction representation. FNI records show that this
proposal would serve as Contract Amendment No. 7.
Task 1— Permitting Updates includes an additional archaeological survey and separate USACE PCN for
the bank stabilization at the Village Creek Tributary. The site eroded significantly during the initial
schedule delay and the extents of the stabilization need at the existing aerial crossings increased. The
bank stabilization PCN is being provided separately from the force main to avoid delaying force main
PCN and its construction.
Task 2 — Construction Staking includes resetting the control points for the construction survey which
were lost or removed by others during the schedule delay.
Task 3 —Tunneling General Rep includes bid and construction phase services for to support construction
administration and walk-throughs for tunnel design additions that were made throughout the project.
Those additional design fees did not include bid and construction phase effort.
Task 4 — Includes effort for attendance and exhibits to support the condemnation hearing for parcels 43,
46-47.
[FTW18195] T:\1.02 PM\5-Amendments\Amendment 7 - Additional Construction Effort\Amendment 7 Cover Letter.docx
CPN 100995 Amendment No. 7
Lake Arlington Force Main
May 9, 2025
Page 2 of 2
A summary of the additional costs is shown below:
Item
Task 1- Permitting Updates
Task 2 - Construction Staking
Task 3 -Tunneling General Rep
Task 4 - Condemnation Hearing
Amendment No. 7 Total
"T,4as4-
Fee
$50,312
$39,600
$8,360
$1,660
$99,932
Freese and Nichols, Inc. appreciates this opportunity and we be pleased to meet with you to discuss
these additional services at your convenience.
Original Contract Amount
$ 3,099,361
Amendment No. 1
$ 229,755
Amendment No. 2
$ 366,004
Amendment No. 3
$ 211,344
Amendment No. 4
$ 392,668
Amendment No. 5
$ 323,249
Amendment No. 6
$ 1,511,941
Amendment No. 7
$ 99,932
Contract Amount to Date
$ 6,234,254
Sincerely,
Ivy <
Nicholas Lester, P.E.
Vice President/Principal
Attachments
Level of Effort Summary Spreadsheet
[FTW18195] T:\1.02 PM\5-Amendments\Amendment 7 - Additional Construction Effort\Amendment 7
Cover Letter.docx
Level of Effort Spreadsheet
TASK/HOUR BREAKDOWN
Design Services for
Lake Arlington Force Main - Amendment
7 Summary
City Project No. 100995
Labor (hours
I E�r.pnse
Task No.
Task Description
Tunneling Senior Env Environments
PIC/QC PM APM CAD GIS
Construction
Total Labor Cost
I Subconsultant
Total Expense
Task Sub Total
En in or Scientist I Scientist
e$311
Mana er
Travel
Reproduction
Cost
Rate $303 $264 $228 $2481 $127 $196
$1461 S252
SBEIMWBE Non-SBE
1
Permitting Updates (PCN & UFP)
$ 32,203
I
$ 16,463
$ 48,666
Archaeological Survey
$ -
J $ 16,463
$ 16,463
USACE PCN
64 101
24
$ 32,203
1
$ -
2
Construction Staking
$ -
1 $ 36,000
$ 36,000 $ 36,000
3
Tunneling Construction Rep
$ -
1 $ 7,600
$ 7,600 $ 7,600
4
Condemnation Hearing
6
2
$ 1,660
$ -
$ 1,660
Totals ol ol 61 ol 641 loll ol
261 ol
s 32.203
$ 52.463 $ 7.600 $ -
$ -
$ 60.063
$ 93.926
City of Fort Worth, Texas
Attachment B - Level of Effort Supplement
PMO Official Release Date. 8.09.2012
Project Summary
Total Hours
197
Total Labor
$32,202
Total Expense
$60,063
MBE/SBE Subconsultanl
$52,463
Non-MBE/SBE Subconsult,ni
$7,600
10 % Sub Markup
$6,006
MBE/SBE Participation
52.5%
Total Project Cost
$99,932
1 Of