HomeMy WebLinkAboutContract 61573-CO2CSC No. 61573-CO2
FORT WORTH., City of Fort Worth
Change Order Request
Project Name 2024 Sidewalk Improvements Unit Price Construction Contract
Client Project #(s)� Various Projects
Project Description Unit Price Construction Contract for Sidewalk Improvements Projects
Contractor Capko Concrete Structures, LLC Change Order #I 2
City Project Mgr.1 Fanta Kaba City Inspector)
Dept.
Original Contract Amount
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date
Amount of Proposed Change Order
Revised Contract Amount
Original Funds Available for Change Orders
Remaining Funds Available for this CO
Additional Funding (if necessary)
TPW
$1,500,000.00
City Sec # 1 61573
Datel 5/22/2025
N/A
Contract Time
Totals (CD)
$1,500,000.00
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT 0.00%
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%) $1,875,000.00
JUSTIFICATION (REASONS) FOR CHANGE ORDER
Requesting to modify the unit price for item 82: Block Sod Placement, the vendor has confirmed there was a typo in the current contract price. This change order also requests to
modify the bid item number for bid item 54 as there are currently duplicates in the contract. There are additional items needed to construct the following projects: 104218:
Campus Dr and Seminary Dr Sidewalk Improvements and 104219: E Berry and E Seminary Dr Sidewalk Improvements. We have compared the proposed pricing to current on -
call contracts and deem the prices reasonable.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full
(both time and money) for all costs arising out of, or incidental to, the above Change Order. The Project/Program Manager signing below acknowledges that
he/she is the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements.
Contractor's Company Name IContractor (Name) Contract Signature I Dat
Capko concrete structures,llc John j capko IV 05/23/25
Inspector/Inspection Supervisor
Date
Project and Contract Compliance Manager
Date
Fan+a Kaba
05/23/25
Program Manager
Date
Senior Capital Project Officer
Date
05/28/25
—
05/28/25
Date
Director, Contracting Department (Dept)
Date
05/29/25
�--'^—
05/30/25
ity Attorney
Date
AssistW6Qy Manager
Date
�III
x
05/30/25
cwQ�
06/11 /25
ATTEST:
�.. A —
Jannette Goodall, City Secretary
n
FORr �;9dd
00
p<ig oBSp
as°4ni�an54p
Council Action (if required)
M&C Number I I M&C Date Approved
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
FORTWORTH
City of Fort Worth
Change Order Additions
Project Name 2024 Sidewalk Improvements Unit Price Construction Contract
City Sec # 61573
Client Project # Various Projects
I
Contractorl Capko Concrete Structures, LLC
PMI Fanta Kaba
IInspectorl
N/A
Change Order Submittal #
Date 1 5/22/2025
ADDITIONS
DLP I City
Unit Unit Cost I otal
U
SY
$30.2U
$0.001
82 3292.0100 Block Sod Placement
TPW
0
SY
$17.00
$0.001
U
SY
$15.00
$0.001
155 3216.0301 1" Conc Valley Gutter, Kesidenhal
I PW
0
SY
$200.00
$0.001
156 9999.0012 Remove Gravel Driveway
TPW
U
SY
$50.00
$0.001
157 9999.0013 Gravel Driveway
TPW
0
SY
$40.00
$0.001
TF W $0.001
Sub Total Additions $0.001
Change Order Additions Page 2 of 4
Fox� City of Fort Worth
IV,Change Order Deletions
Project Name 1 2024 Sidewalk Improvements Unit Price Construction Contract City Sec # 61573
Client Project # I Various Projects
Contractorl Capko Concrete Structures, LLC I PMI Fanta Kaba I Inspectorl NIA
Change Order Submittal # 0 Dale 1 5/22/2025 1
DELETIONS
ITEM DESCRIPTION DEPT
Oty Unit
Unit Cost
Total 1
b4 3216.0301 I" Conc Valley Gutter, Residential TPW
U SY
$200.0U
$0.001
1-1000
$3,020.00
$0.001
82 3292.0100 Block Sod Placement TPW
1001-2000 SY
$17.00
$0.001
2001+
$15.00
$0.001
TF W $0.001
Sub Total Deletions $0.001
Change Order Deletions Page 3 of 4
M/SBE for this Change Order
M/SBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
c0 # DATE I AMOUNT
11 /20/2024 $0.00
Total I $0.00 I
FQRT WORTH(�,
Routing and Transmittal Slip
Transportation & Public Works
Department
DOCUMENT TITLE: 2024 Sidewalk Improvements Unit Price
Construction Contract — Change Order #2
M&C: 24-0274
Date: 5/22/2025
CPN: Various CSO: 61573 DOC#: I
To: Name
Department
Initials Date Out
1. John J Capko IV
Vendor - signature
05/23/25
2. Ann Estes
TPW - review
AA 05/23/25
3. Fanta Kaba
TPW - signature
PK FK 05/23/25
4. Chad Allen
TPW - signature
C*- 05/28/25
Ch,d5.
Lissette Acevedo
TPW - signature
o�v 05/28/25
6. Patricia Wadsack
TPW - signature
PLVY 05/29/25
7. Lauren Prieur
TPW - signature
JVXF 05/30/25
Lauren Pneu
8. Doug Black
Legal - signature
05/30/25
Douglas Black
9. Jesica McEachern
CMO - signature
CA 06/11 /25
10. Jannette Goodall
CSO - signature
06/12/25
12. TPW Contracts
TPW
DOCUMENTS FOR CITY MANAGER'S SIGNATURE:
All documents received from any
and all City Departments requesting City Manager's signature for approval MUST BE
ROUTED TO THE APPROPRIATE ACM for approval first.
Once the ACM has signed the
routing slip, Jay will review and take the next steps.
NEEDS TO BE NOTARIZED: []YES ®No
RUSH: [—]YES ®No
SAME DAY: ❑YES ®No
NEXT DAY: [—]YES [—]No
ROUTING TO CSO: ®YES ❑No
Action Required:
❑ As Requested
❑ For Your Information
® Signature/Routing and or Recording
❑ Comment
❑ File
❑ Attach Signature, Initial and Notary Tabs
Return To: TPWContractsaFortWorthTexas.2ov at ext. 7233 for pick up when completed.