HomeMy WebLinkAboutContract 62251-A1CSC No. 62251-A1
AMENDMENT No . 1
TO CITY SECRETARY CONTRACT No. 62251
WHEREAS, the City of Fort Worth (CITY) and RJN Group, Inc. (ENGINEER)
made and entered into City Secretary Contract No. 62251, (the CONTRACT)
which was administratively authorized on the 4th day of November, 2024,
in the amount of $92,062.50 and
WHEREAS, the CONTRACT involves professional services for the following
project:
Citywide Wastewater Collection System Flow Monitoring Maintenance
Contract- FY 2025; and
WHEREAS, it has become necessary to execute Amendment No.1 to the
CONTRACT to include an increased scope of work and revised fee.
NOW THEREFORE, CITY and ENGINEER, acting herein by and through their
duly authorized representatives, enter into the following agreement, which
amends the CONTRACT:
1.
Article I of the CONTRACT is amended to include the additional
professional services specified in proposal attached hereto and
incorporated herein. The cost to City for the additional design services
to be performed by Engineer totals $ 0. 00.
2.
There is no fee increase to Article II of CONTRACT.
3.
All other provisions of the Contract, which are not expressly
amended herein, shall remain in full force and effect.
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
City of Fort Worth, Texas Citywide WW Collection System Flow Monitoring Maint. Contract FY 2025
Prof Services Agreement Amendment Template
Revision Date: 12/08/2023
Page 1 of 2
EXECUTED and EFFECTIVE as of the date subscribed by the City's
designated Assistant City Manager.
APPROVED:
City of Fort Worth
)
Jesica McEachern
Assistant City Manager
DATE: 06/ 18/2025 oangno qO� FON T�Ydd
pro 0Ao
p!`g 9-i0
ATTEST:
((� � ddQn nE4p5ao
Jannette Goodall
City Secretary
APPROVAL RECOMMENDED:
chntOljhel �G d6-
Christopher Harder (Jun 9, 2025 08:30 CDT)
Christopher Harder, P. E.
Director, Water Department
Contract Compliance Manager:
ENGINEER
RJN Group, Inc.
_( .'-&-N
Daniel Jac son, P.E
Senior Vice President
DATE: 5/28/25
By signing, I acknowledge that I am the person responsible for the
monitoring and administration of this contract, including ensuring all
performance and reporting requirements.
John Kasavich, P.E.
Project Manager
APPROVED AS TO FORM AND LEGALITY:
Douglas Black (Jun 9, 202515:44 CDT)
Douglas W. Black
Sr. Assistant City Attorney
M&C No.#: N/A
M&C Date: N/A
Form 1295: N/A OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
City of Fort Worth, Texas Citywide WW Collection System Flow Monitoring Maint. Contract FY 2025
Prof Services Agreement Amendment Template
Revision Date: 12/08/2023
Page 2 of 2
Engineering
Infrastructure for
Tomorrow
April 09, 2025
John Kasavich, P.E.
Engineering Manager
City of Fort Worth Water Department
200 Texas Street
Fort Worth, Texas
www.rjn.com
Subject: Amendment No. 1 Request for General Professional Services for Fort Worth Citywide
Collection System Flow Monitoring Maintenance Contract — FY2024 (City Secretary No.
C-62251)
Mr. Kasavich:
Please find attached our proposed Amendment No. 1 to the existing Citywide Wastewater Collection
System Temporary Flow Metering Project Agreement, City Secretary Contract No. 62251, dated
November 4, 2024, and runs through March 31, 2025. RJN started work immediately upon receiving the
contract.
Amendment No. 1 is seeking to reallocate $33,387.50 of unused funds to better support the FWWD
Staff for this important multi -year City-wide Flow Monitoring Program this fiscal year. New billing items
have been added to support unforeseen tasks that have arisen during the project. This letter provides
justification for this request and briefly summarizes the scope of work anticipated to be performed. The
supporting revised LOE spreadsheet reflecting Add/Deduct Costs is attached for your review. Meter sites
FTW-18, FTW-22, FTW-24, FTW-25, and FTW-26 have had equipment issues for the life of the contract.
This decreases the units for Pay Item 1 and BA#1 by 16 units. The funds from a reduction of just 16 units
will fund the proposed new pay items outlined below as well as extend the contract time for Pay Items 1
and BA#1 through the month of April.
FY 2025 Program Year ()
RJN will continue the field maintenance, data processing, and data hosting of the City's fifteen (15)
current noncontact flow monitors. The prior pay Item #1 and Pay Item BA#1 are included. There are
eight additional pay items included to establish pricing in the event they are needed during the next four
months.
New Pav Items
Flow Meter Removal: Should any equipment need to be removed, the effort associated with that
removal and equipment cleaning will be covered under this pay item.
Equipment Shipping: RJN will package and ship the non -operational equipment to McCrometer for
servicing. It is estimated that the cost of shipping will be $275 per RA.
McCrometer RA: The cost of McCrometer to diagnose the issue with the non -operational equipment.
Any additional cost associated with making the two (2) metering equipment operational is not included
6701 Brentwood Stair Rd, Suite 100W • Fort Worth, Texas 76112 • 817.451.3500
in this Amendment request and will be presented to the City in the event it becomes necessary to fund
through other means.
Flow Meter Installation: In the event that a flow meter needs to be installed the effort associated with
that installation will be covered under this pay item.
Equipment Repair: Pay items 2, 3, 4, and 5 cover repair/replacement costs for known problems. Quotes
from McCrometer have been provided as part of this proposal
Contract Item
Fee
Original Contract Amount
$
92,062.50
Amendment No.1
$
(982.50)
Amended Contract Value
$
91,080.00
Fund Reallocation
$
33,387.50
Meter Site Maintenance
$
11,880.00
Additional Data Management
$
2,850.00
Equipment Repair
$
10,419.74
Flow Meter Removal
$
1,200.00
Shipping Costs
$
550.00
McCrometer RA
$
5,037.76
Flow Meter Installation
$
1,450.00
We appreciate the opportunity to continue working with the City of Fort Worth on this important
project. Please feel free to contact Tristan Nickel at 817-451-3500 if you would like to discuss this
proposal or have any questions.
Sincerely,
Tristan Nickel, PE, AWAM
N. TX/AR Regional Manager
■■ Flow Monitoring Support Services, City of Fort Worth Page 2
Pay Item
Contract Quantity Rate
Pay Item 1: Meter Site Maintenance, as Required
Including Scheduled Calibrations (bi-weekly for the first 60
days and then quarterly thereafter) - Monthly Servicing
Fee [monthly fee per meter, assumed up to 15 NON-
75 $ 990.00
CONTACT (select meter type provided) meters deployed
during a 4 month period (April 2025 to July 2025] (15
units at $1,035 per each per month per contract period
(4 Mos.))
Pay Item BA#1: Additional Data Management, Analysis
and Reporting - Monthly Data Management, Analysis, and
Reporting Fee (monthly fee per meter, up to 20 meters
deployed during a 12 month period) as noted in Section
75 $ 237.50
30.0 "Scope of Work". This is an ADD/DEDUCT item. (15
units at $245 per each per month per contract period
(4 Mos.))
Totals
Available Funds
$ 34,370.00
New Pay Items
IPay Item 1 April: Meter Site Maintenance
12 $ 990.00
Pay Item BA#1 April: Additional Data Management
12 $ 237.50
Pay Item 2: Flodar Repair. (1 unit at $6,536.74 per each)
1 $ 6,536.74
Pay Item 3: Flodar Cable + HUB (1 unit at $628.00 per
1 $ 628.00
each)
Pay Item 4: AV Sensor Assably. (1 unit at $1,984.00 per
1 $ 1,984.00
each)
Pay Item 5: Area Celocity Analyzer Module (1 unit at
1 $ 1,271.00
$1,271.00 per each)
Pay Item 6: Shipping Costs to ship non -operational
equipment to McCrometer for evaluation. (Shipping Costs
2 $ 275.00
estimated at $275 per RA)
Pay Item 7: McCrometer RA, the cost incured from
McCrometer for them to diagnose equipment issues.
2 $ 2,518.88
($2,518.88 per unit for 2 units)
Pay Item 8: Flow Meter Removal, includes cleanup of
2 $ 600.00
meter and sensors. (2 units at $600 per each)
Pay Item 9: Flow Meter installation. (Includes initial site
calibration, coordination with the telemetry service provider,
2 $ 725.00
and a final confirmation inspection within 7 days of
installation) ($725 per unit for 5 unit)
Totals
Contract Balance Remaining
$ 982.50
Contract Fee I Units to Date I Fee to Date
$ 74,250.00 47 $ 46,530.00
$ 17,812.50 47 $ 11,162.50
$ 92,062.50 $ 67,692.50
$ 11, 880.00
$ 2,850.00
$ 6,536.74
$ 628.00
$ 1,984.00
$ 1,271.00
$ 33,387.60
1