HomeMy WebLinkAboutIR 8259 INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 8259
of To the Mayor and Members of the City Council
July 11, 2000
rtx�
�y� Subject: Recent Flooding of Farmer's Branch in White Settlement
On June 13th Mr. Claude Marchioni, a citizen of White Settlement who lives along
Farmers Branch Creek, appeared before the Fort Worth City Council and requested that
Fort Worth work with White Settlement to seek a solution to the flooding problems.
Officials in the City of White Settlement have indicated that past and present
development in the Westpoint area of west Fort Worth has significantly increased the
amount of runoff entering their city. However, previous studies prepared by the United
States Army Corps of Engineers (USACOE) indicate that the flooding conditions along
Farmers Branch Creek are probably much more long standing and are heavily impacted
by the lack of downstream drainage improvements within the City of White Settlement.
Representatives of our Engineering Department and the City Manager's office have
previously met with the current City Manager of White Settlement and his staff to
discuss possible solutions to the flooding problems. Fallowing those discussions the
Fort Worth staff concluded that based on various engineering studies conducted by the
City of White Settlement and USACOE, that several downstream drainage
improvements in White Settlement would provide a level of relief and should be
accomplished.
Following is a brief summary of work that has been performed by USACOE and private
engineering firms pertaining to the Farmers Branch flooding issue. I am providing this
information to you simply as background so you may better understand the nature of the
flooding problems.
Backgound
In 1988 the City of White Settlement contacted the USACOE requesting that they do a
study determining the feasibility of a flood protection project along Farmers Branch. A
study was undertaken by USACOE with findings published in 1990.
The 1990 USACOE report indicated that there were 45 houses in the 2-year floodplain,
79 houses in the 5-year floodplain, 96 in the 10-year floodplain, 159 in the 50-year
floodplain and 187 in the 100-year floodplain in the study area for existing conditions.
USACOE investigated a channelization solution for Farmers Branch that involved
constructing concrete-lined channels on four different segments of the stream. The cost
for these improvements was estimated at $4.5 million with an average annual benefit of
$273,800.
USACOE determined that the proposed improvements would likely create increased
flooding downstream due to increased flows and the restrictions caused by the Carswell
INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 8259
&0—TER�4�a To the Mayor and Members of the City Council
N, July 11, 2000
IF
Page 2 of 3
Subject:
ion Recent Flooding of Farmer's Branch in White Settlement
runway culverts. For these reasons the channelization solution was determined to be
not economically feasible.
USACOE then looked at the feasibility of purchasing and/or relocating homes along
Farmers Branch. As the result of their investigation, USACOE recommended the
relocation of 15 residential structures. These 15 residences were considered the most
severely damaged structures in terms of expected annual flood damage. The cost for
the relocation was estimated at $725,200 with an annual average benefit of $37,900.
According to USACOE the City of White Settlement did not sign a contract with them to
proceed with the buyout plan. It is believed, however, that the City of White Settlement
acted independently and bought several of the structures. In doing so, the City of White
Settlement forfeited USACOE participation in the amount of 75% of the buyout costs.
In 1998, Kimley-Horn and Associates prepared a report for the City of White Settlement
entitled, Farmers Branch Detention Feasibility Study. In their report they reference a
1994 USACOE study. Although we have been unable to obtain a copy of this report at
this time, Staff understands that it is an update of the 1990 report. The 1994 report
recommends the evacuation of 11 structures. The reduction of severely damaged
structures from 15 to 11 is likely the result of the buyout that the City of White
Settlement did without USACOE participation.
The 1998 Kimley-Horn report recommends the construction of detention ponds within
the City of White Settlement and/or the City of Fort Worth to reduce the discharges into
Farmers Branch. The three alternatives presented range in costs between $1.7 and
$4.1M excluding the cost of land acquisition. The Kimley-Horn report acknowledges
that the cost of the least cost detention pond alternative would cost more than two times
the cost of buying out the affected residential structures in the 5-year floodplain. The
report states," If frequent flooding is a concern, a buyout and some improvements to
roadway crossings might be the best solution. If major flooding is the concern, then
detention basins might be the best solution."
While the detention pond alternatives may reduce the magnitude of flooding to the 11
structures noted in the 1994 Corps report it does not remove them from the floodplain.
The recommended improvements would also not bring relief to an additional 79
residences that are located within the 5-year floodplain since the detention basin
alternatives suggested by Kimley-Horn all bypass the 5-year storm discharge directly to
the creek.
ISSUED BY THE CITY MANAGER FORT WORTH,TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 8259
de0TE,9
To the Mayor and Members of the City Council July 11, 2000
Page 3 of 3
1rx
0,- Subject: Recent Flooding of Farmer's Branch in White Settlement
Correspondence material from Kimley-Horn to the City of White Settlement suggests
that the development in the upstream watershed (WestPoint) has led to a 17% increase
in runoff from 1986 to 1996, however the Department of Engineering does not agree
with Kimley-Horns assessments.
Proposed Action
The Fort Worth staff is prepared to work with White Settlement staff if requested and as
appropriate, however the City of Fort Worth should not take the lead in resolving
drainage problems resulting from conditions over which the City of White Settlement
has control.
Attached is a copy of a Fort Worth Star Telegram article that appeared in April of this
year (prior to the recent flooding). The article provides some additional insight as to 'the
City of White Settlement Council's recent actions. If you have any questions concerning
this issue, please feel free to contact me.
Bob Terrell
City Manager
ISSUED BY THE CITY MANAGER FORT WORTH,TEXAS