DEVELOPER -AWARDED -PROJECT CHANGE ORDER,
PROJECT NAME:
Longhorn Estates Phase 1
CHANGE
CONTRACT:
Paving Improvements
ORDER No:
CITY PARTICIPATIONd
YES
CFA #
CFA24-0041
CITY PROJECT#
105087
CITY SECRETARY CONTRACT #
61369
4
FID #
30114-0200431-105087-EO7685
X #
X-27933
FILE #
W-3002
INSPECTOR:
Michael Perkins
Phone No:
682-715-7010
PROJECT MANAGER:
Khal Jaafari
Phone No:
817-392-7872
CONTRACT UNIT
WATER
SEWER
DRAINAGE
PAVING
STREET LIGHTS 1 CONTRACT
Developer
Developer
Developer
DAYS
Cost y}y �pst Developer Cost
� Developer Cost
Cost
Cost
0k1y Cost
ORIGINAL CONTRACT
$2,289,949.98 F1 a49,149.09
$2,739,064.00
$0.00
$4,384,347.00
$6,323,326.70
$606,993.06
'
$D.00
275
EXTRAS TO DATE
$61,160.00 p.00
$8,663.00
50.00
S0.00
$0.00
$44,136.70
$0.00
CREDITS TO DATE
$0.00 ;0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
CONTRACT TO DATE
$2.361,099.98 11,j49,149.69
$2,747,617.00
$0.D0
I $4,394,347.00
$6,323,326.70
$660.129.76
S0.00
275
(AMOUNT OF PROP. CHANGE ORDER
$0.00 $P.00
$0.00
$0.00
$0.00
($20,824,40)
$0.00
$0.00
0
79NA Q�Q RACTAMOUNT
$2,351,099.98 S7.249,149.69
$7,747,617.00
$0.00
$4,384,347.00
$6,302,601.30
$660,129.76
30.00
275
TOT�12EV1� L'ONTRACT AMOUNT PER
UNIT $3,600,249.67
$2.747,617.00
$4,384,347.00
$5,30 501.30
$660.129.76
REVISED COST SHARE
Dev. Cost
$15,435,695.04
TOTAL REVISED CONTRACT
$16,684,844.73
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
Revised: 12-17-2018 Page 1
You are directed to make the following changes in the contract documents:
UNIT IV: PAVING IMPROVEMENTS
CITY BID ITEM
Developer
PAY ITEM 9
9 QUANTITY UNIT
ITEMPISCRJPTIQN CFW Unit Prce
UNIT PRICE Cost City Cost TOTAL
10
3213.0105 152 SY
10 one �m NIA
$66.55 $10.115.60 $0.00 $10,115.60
I 11
3213.0301 (1016) SF
4" Cone Sidewalk NIA
$7.50 (S7.620.00) $0.00 ($7,620.00)
20
3217.0504 310 LF
Preformed Thermoplastic Contrast NIA
$40.00 $12,400.00 $0.00 $12.400.00
Markings - 24" Crosswalk
36
9999.9999 (152) SY
10" Cone Pvmt (Stamped Concrete
N/A
3235.00 (535.720.00) $0.00 ($35.720.00)
Type'B')
TOTAL UNIT IV: PAVING IMPROVEMENTS
($20.824.40) $0.00 ($20.824.40)1
Asterisk(') indicates New Pay
Item
REASONS FOR CHANGE ORDER
Sidewalk revised along Street 17 per landscaping recommendations. Meandering sidewalk constructed outside of the Public R.O.W. will be considered private
infrastructure and maintained by the HOA. Crosswalk
markings added in place of stamped concrete between ADA ramps, stamped concrete Type 'B' placed
before intersections.
RECOMMENDED:
APPROVED:
—
APPROVED:
By: Xf 4 p
_gy.
By:
Name: Michelle Lase
Name: Justin Bosworth
Name: Chad San Juan
Title: Senior Proioct Manager, Pape -Damon Engineers
Title: Assistant Vlce President, D.R. Horton- Texas, Ltd.
Title: Vice President. Glenn Thurman. Inc.
APPROVAL RECOMMENDED:
APPROVED:
APPROVED AS TO FORM AND LEGALITY:
srd��d�PC' 06/11/2025
C-C- 06/18/2025
06/11/2025
By
By:
By.
11
MH
Name: Subv Varuahese
Name: Jesica McEachem
Name: Richard McCracken
Title: Engineering Manager
Title: Assistant Citv Manager
Title: Sr. Assistant City Attorney
RECOMMENDED:
Khal Taclfaf'PE�6/04/2025
Kha[Ja fa P.E.(Juna,202510:25CDT)
By:
Name: Khal Jaafari, P.E.
Title: Professional Engineer
M&C Number: 24-0224
M&C Date Approved: 3/19/2024
ATTEST
v"Qie°°m`AT?pLp4
a
" Contract Compliance Manager (Project Manager):
` A Tsau
°
avog
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, include
ensuring all performance and reporting requirements.
Jannette S. Goodall
City Secretary
[There are NO City Funds associated with this Contract
��