HomeMy WebLinkAboutContract 59066-CO3FORT WURTH City of Fort Worth CSC No. 59066-0O3 Change Order Request Project Name: Sanitary Sewer Rehabilitation, Contract 113, Part 3 1 City Sec No.: 59066 Project No.(s): 56002-0600430/0700430-102785-001780 1 DOE No. I N/A I City Proj. No.: 102785 Project Description:) Replacement of Existing Sanitary Sewer Mains and Water Mains on Tierney Rd., South Hampshire Blvd. & various easements Contractor: William J. Schultz, Inc. dba Circle C Construction Company Change Order # 3 Date: 6/25/2025 City Project Mgr. Dena Johnson I City Inspector: John Robinson Phone Number: 817-392-7866 I Phone Number: 817-879-9818 Dept. Original Contract Amount Extras to Date Credits to Date Pending Change Orders (in M&C Process) Contract Cost to Date Amount of Proposed Change Order Revised Contract Amount Original Funds Available for Change Orders Remaining Funds Available for this CO Additional Funding (if necessary) Contract Time Water Sewer Paving Totals (Calendar days) $591,810.15 $2,102,226.65 $604,600.00 $3,206,b6b.61U 300 $0.00 $255.484.00 $0.00 $255.484.00 THIS ONE) AS % OF ORIGINAL CONTRACT 14.84% CHANGE ORDERS to DATE (INCLUDING MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 2516) $4,123,296.00 JUSTIFICATION (REASONS) FOR CHANGE ORDER Change Order No. 3 will primarily provide for water valve and sewer manhole adjustments that were inadvertently omitted at the time the project was advertised for bid, additional pavement markings that are necessary on the project and replacement of pay item quantities that for as -built survey, epoxy manhole liner, and by other than open cut point repair on a project sanitary sewer main were inadvertently deleted from the project to pay for quantity overruns. Staff concurs with the contractor's request for an additional 250 calendar days on the project for the time it took to conduct by other open cut point repair to facilitate pipe enlargement of a project sewer main and the time it took to hand tunnel a project main instead of by cured -in - place pipe as originally proposed. It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order. r Contractor's Company Name Contractor Name Contractor Signature Date William J. Schultz, Inc. dba Circle C Construction Company Teri Skelly r Ins ecto Date Project Mans Date 6/25/25 Director Water Dept) D to _ Construction apervisor Water Dept) Date T.S. 07/02/2025 Wade Miller _ 6/26/25 S io Assistant Cit Attorney Date Assistant City Manager Date o 91l s6ac WW2, 202511, 22 CDT) 07/02/2025 % 07/03/2025 Council Action (if Reouiredi M&C Number 1 25-0647 1 M&C Date Approved j 6/24/2025 OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX FO_ RT' Wo RT H_ City of Fort Worth -� Change Order Additions Project Name I Sanit&Y Sewer Rehabilitation, Contract 113, Part 3 City Sec No.: 1 59066 Project No.(s): 1 560D2-0600430/0700430-102785-001780 I DOE No.1 N/A City Proj. No.: Project i Replacement of Existing Sanitary Sewer Mains and Water Mains on Tierney Rd., South Hampshire Blvd. & various j Description easements J Contractor I William J. Schultz, Inc. dba Circle C Construction Company Change Order: Date: 1 6/25/2025 1 City Project Mgr. I Dena Johnson I City Inspector I John Robinson ADDITIONS ITEM DES IPTION 1 WATER 1SWPPP DEPT Qty Unit I Unit Cost I Total 27 1 > 1 Acre I Water 0.25 LS ] $12,500 $3,125.00 28 1As-Built Survey 1 Water 1 LS $5,000.00 $5,000.00 31 16' Solid Yellow Thermoplastic Hot Applied Spray (HAS) Centerline 1s. Water 500 LF $10.00 $5,000.00 32 1Lane Legend RR ' Water 1 EA $500.00 $500.00 33 Preformed Thermoplastic Contrast Marking - 24" Stop Bars I Water I 22.50 1 LF $15.00 $337.50 34 Preformed Thermoplastic Contrast Marking - 24" Crosswalk j 1 Water I 30.0 1 LF $15.00 $450.00 35 Water Valve Box Adjustment w/ Concrete dollar I Water 3 EA I $2,000,00 $6,000.00 36 Manhole Adjustment W/ Concrete Collar j Water 3 EA $3,500.00 $10,500.00 37 1Painting Curb Addresses I Water 13 I EA $150 $1,950.00 38 ISWPPP> 1 Acre j 1 I Water I 0.25 1 LS i $5.000.001 I I $1,250.00 i i i SEWER I I I I I I I I 23 I anhole Vacuum Testing t Sewer 3 EA 1 $200.001 $600.00 25 IEpoxy Manhole Liner j Sewer 110 I VF 1 $450.001 $49,500.00 26 JEpoxy Structure Liner 1 Sewer 255 1 SF 1 $40.001 $10,200.00 42 Broadcast Seeding j Sewer 1,137 1 SY 1 $8.001 $9,096.00 49 As -Built Survey j Sewer 1 LS $12.500.001 $12,500.00 53 IPipe Enlargement BOTOC Point Repair I Sewer 65 LF $1,500.001 $97,500.00 64 16' Solid Yellow Thermoplastic Hot Applied Spray (HAS) Centerline (s) I Sewer 500 1 LF $10,001 $5,000.00 65 11-ane Legend RR I Sewer 1 I EA $500.00 $500.00 66 Thermoplastic Contrast Marking - 24' Stop Bars Sewer 1 22.50 1 LF 1 $15,00 $337.50 67 Eeformed eformed Thermo-lastic Contrast Marking - 24' Crosswalk Sewer 1 30 1 LF 1 $15.001 $450.00 68 ater Valve Box Adjustment w/ Concrete Lollar I Sewer I 2 1 EA 1 $2,000.001 $4,000.00 69 Manhole Adjustment W/ Concrete Collar j Sewer I 2 1 EA $3,500,00J $7,000.00 70 ainting Curb Addresses I Sewer I 13 I EA $150.0 1 I 6 $1,95D.00 71 1 1 1 SWPPP> 1 Acre j I i I I Sewer 1 I 1 1 I 0,25 ] LS I I I I I 1 $5,000,001 i i I I I i I $1,250,00 I I 1 i i I I I I I I I I I I I I Water 1 I I I 1 $34,112.50 Sewer 1 $199,883.50 Paving 1 Page 1 of 3 Additions Sub Total 1 $233,996.00 F_ CJ�T WORTH City of Fort Worth s Change Order Deletions Project Name Sanitary Sewer Rehabilitation, Contract 113, Part 3 City Sec No.: 59066 Project No.(s): 56002-0600430/0700430-102785-001780 DOE No. I N/A I City Proj, No.: 102785 Project Replacement of Existing Sanitary Sewer Mains and Water Mains on Tierney Rd., South Hampshire Blvd. & various Description easements I J Contractor I William J. Schultz, Inc. dba Circle C Construction Company I Change Order: 3 ! Date 6/25/2025 City Project Mgr. Dena Johnson 1 City Inspector: j John Robinson DELETIONS ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total Water Sewer Paving Deletions Sub Total Page 2 of 3 MIWBE Breakdown for this Change Order MWBE Sub Type of Service Amount for this CO Total $0.00 Previous Change Orders CO# DATE I AMOUNT Total =$000 Page 3 of 3 6/25/2025 CPN 102785 Sanitary Sewer Rehabilitation Contract 113, Part 3 ChanF,e Order 3 Notes Staff has reviewed the requested prices and considers them to be fair and reasonable. City of Fort Worth, Texas Mayor and Council Communication DATE: Tuesday, June 24, 2025 LOG NAME: 60SSRC113P3CO3-CIRCLEC REFERENCE NO.: **M&C 25-0647 SUBJECT: (CD 5, CD 8, and CD 11) Authorize Execution of Change Order No. 3 in the Amount of $233,996.00 to a Contract with William J. Schultz, Inc. dba Circle C Construction Company for the Sanitary Sewer Rehabilitation Contract 113, Part 3 and Adopt Appropriation Ordinance to Effect a Portion of Water's Contribution to the Fiscal Years 2025-2029 Capital Improvements Program RECOMMENDATION: It is recommended that the City Council: 1. Authorize execution of Change Order No. 3 in the amount of $233,996.00 and an additional 250 calendar days to City Secretary No. 59066, a contract with William J. Schultz, Inc. dba Circle C Construction Company for the Sanitary Sewer Rehabilitation Contract 113, Part 3 project for a revised contract amount of $3,788,116.80; and 2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Water and Sewer Capital Projects Fund in the amount of $233,997.00, transferred from available PayGo funds within the Water and Sewer Fund, for the purpose of funding the Sanitary Sewer Rehabilitation Contract 113 project (City Project No. 102785) and to effect a portion of Water's Contribution to the Fiscal Years 2025-2029 Capital Improvement Program. DISCUSSION: On February 14, 2023 by Mayor and Council Communication (M&C) 23-0124, the City Council authorized a construction contract with William J. Schultz, Inc. dba Circle C Construction Company in the amount of $3,298,636.80 for Sanitary Sewer Rehabilitation Contract 113, Part 3 project. The contract was subsequently revised by Change Order No. 1 in the amount of $52,375.00 administratively authorized on October 27, 2023, that originally provided for the point repair of a project sewer main that scheduled for pipe enlargement and Change Order No. 2 in the amount of $203,109.00 authorized by M&C 24-0226 on March 19, 2024 that primarily provided for 20-inch casing by open cut, additional by-pass pumping on the project, manhole shafts and epoxy lines for 5-foot diameter manhole. Change Order No. 3 will primarily provide for water valve and sewer manhole adjustments that were inadvertently omitted at the time the project was advertised for bid, additional pavement markings that are necessary on the project and restoration of pay item quantities for as -built survey, epoxy manhole liner and by other than open cut repair for a project sanitary sewer main that had been inadvertently utilized to pay for quantity overruns. It is the practice of the Water Department to appropriate its CIP plan throughout the Fiscal Year (FY), instead of within the annual budget ordinance, as projects commence, additional funding needs are identified, and to comply with bond covenants. The actions in the M&C will appropriate funds in support of the Water's portion of the City of Fort Worth's Fiscal Years 2025-2029 Capital Improvement Program. Funding is available in the Transfer to Water/Sewer account of the Water and Sewer Fund for the purpose of funding the SS Rehab Contract 113 project within the Water & Sewer Capital Projects Fund. FY2025 - Water PAYGO Appropriations per City Ordinance 27107-09-2024 FY2025 FY2025 YTD PayGo This M&C FY2025 Original Amended Approved Remaining PayGo Adopted (includes any for/Moved to PayGo PayGo council actions Capital Projects Balance subsequent to budget adoption) ,$92,597,771.00 $151,458,196.00 ($59,319,875.00) ($233,997.00)1$91,904,324.00 Note: There may be other pending actions or recently approved actions that are not reflected in the table due to timing. Appropriations for Sanitary Sewer Rehabilitation Contract 113 project are as depicted below: Fund Existing Additional project Total* I Appropriations Appropriations 'W&S Capital Projects Fund 56002 General Capital Projects Fund 30100 $11,212,255.00 � $1,292,045.00 Project Total L$12,504,300.00 $233,997.00 $11,446,252.00 $0.00 $1,292,045.00 $233,997.00 $12,738,297.00 *Numbers rounded for presentation purposes. Business Equity - William J. Schultz, Inc. dba Circle C Construction Co. agrees to maintain its initial M/WBE commitment of 24 percent that it made on the original contract and extend and maintain that same M/WBE commitment of 24 percent to all prior change orders up to and inclusive of this Change Order No. 3. Therefore William J. Schultz, Inc. dba Circle C Construction Company remains in compliance with the City's M/WBE Ordinance and attests to its commitment by its signature on the Acceptance of Previous M/WBE Commitment form executed by an authorized representative of its company. This project is located in COUNCIL DISTRICTS 5, 8 and 11. FISCAL INFORMATION / CERTIFICATION: The Director of Finance certifies that funds are available in the Water & Sewer Fund, and upon approval of the above recommendations and adoption of the attached appropriation ordinance, funds will be available in the W&S Capital Projects Fund, for the SS Rehab Contract 113 project to support the above recommendations and execution of the change order. Prior to any expenditure being incurred, the Water Department has the responsibility of verifying the availability of funds. FUND IDENTIFIERS (FIDs): TO FundlDepartment ccounf Project ctivity� Budget Reference # Amount! I. _ ID � ID �Program Year I (Chartfield 2) I ' FROM Fund Department ccoun Project lProgramActivity Budget I Reference # �mounf ID ID I I Year (Chartfield 2) CERTIFICATIONS: Submitted for Citv Manaqer's Office bv: Jesica McEachern (5804) Originating Department Head: Chris Harder (5020) Additional Information Contact: Dena Johnson (7866) ATTACHMENTS 1. ,?5-102785 (APCF CO3 Final-CC)Adf (CFW Internal) 2. 6OSSRC113P3CO3-CIRCLE C FID Table WCF 04.25.25),xlsx (CFW Internal) 3. 60SSRC113P3CO3-CIRCLEC fund avail docx (CFW Interna►) 4. =SRC113P3CQ3-CIRCLfS&p-df (CFW Internal) 5. _Contract 113 1295 Form,{ (CFW Internal) 6.9RD.APP_60SSRC113P3CO3-CIRCLEC 56002 AO25Q2)-(I).docx (Public) 7. PBS CPN 1027$5.a (CFW Internal) 8. SAM.gov search Circle C Construction CompMy a (CFW Internal) Contract Compliance Manazer By signing I acknowledge that I am the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements. Signature Dena Johnson Name of Employee Project Manager Title v� °FORT�� ° �0 ATTEST: pvo oo =d Jo o 0000,000 p Jannette Goodall City Secretary OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX