HomeMy WebLinkAboutContract 62655-A1CSC No. 62655-Al
AMENDMENT No . 1
TO CITY SECRETARY CONTRACT No. 62655
WHEREAS, the City of Fort Worth (CITY) and ADS, LLC. (ENGINEER) made
and entered into City Secretary Contract No. 62655, (the CONTRACT) which
was administratively authorized on the 21st day of January, 2025, in the
amount of $97,560.00; and
WHEREAS, the CONTRACT involves engineering services for the following
project:
Citywide Wastewater Collection System Flow Monitoring Maintenance
Contract- FY 2025; and
WHEREAS, it has become necessary to execute Amendment No.1 to the
CONTRACT to include an increased scope of work and revised fee.
NOW THEREFORE, CITY and ENGINEER, acting herein by and through their
duly authorized representatives, enter into the following agreement, which
amends the CONTRACT:
1.
Article I of the CONTRACT is amended to include the additional
engineering services specified in proposal attached hereto and incorporated
herein. The cost to City for the additional design services to be performed
by Engineer totals $0.00.
2.
There is no fee increase to Article II of CONTRACT.
3.
All other provisions of the Contract, which are not expressly amended
herein, shall remain in full force and effect.
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
City of Fort Worth, Texas Citywide WW Collection System Flow Monitoring Maint. Contract FY 2025
Prof Services Agreement Amendment Template
Revision Date: 12/08/2023
Page 1 of 2
EXECUTED and EFFECTIVE as of the date subscribed by the City,s
designated Assistant City Manager.
APPROVED:
City of Fort Worth
Jesica McEachern
Assistant City Manager
DATE: 07/11 /2025
4� n4b
l.g
ATTEST:
Jannette Goodall
City Secretary
APPROVAL RECOMMENDED:
CGc�lsto,�G��Y tfa��f��
Christopher Harder (Jul 9, 2025 15:27 CDT)
Christopher Harder, P. E.
Director, Water Department
Contract Compliance Manager:
ENGINEER
ADS, I.
Rodianne Cadet
Region Manager
7/8/25
DATE:
By signing, I acknowledge that I am the person responsible for the
monitoring and administration of this contract, including ensuring all
performance and reporting requirements.
zc��
Ql-a�. � . �--����-ter
John Kasavich, P.E.
Project Manager
M&C No.#: N/A
APPROVED AS TO FORM AND LEGALITY:
M&C Date: N/A
Douglas Black (Jul 10, 2025 12:45 CDT)
Douglas W. Black Form 1295: N/A
Sr. Assistant City Attorney
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
City of Fort Worth, Texas Citywide WW Collection System Flow Monitoring Maint. Contract FY 2025
Prof Services Agreement Amendment Template
Revision Date: 12/08/2023
Page 2 of 2
o ENVIRONMENTAL
SERV/CES°
July 4, 2025
City of Fort Worth
John R. Kasavich, P.E.
Engineering Manager
100 Fort Worth Trail
Fort Worth, TX 76102
11000 Stancliff Road, Suite 100 > Houston, TX 77099
Phone: 281-933-0951
www.adsenv.com
A DIVISION OF ADS LLC
RE: Amendment No. 1 Request for General Professional Services for Citywide Wastewater
Collection System Flow Monitoring Maintenance Contract — FY 2025 (CSC No. 62655)
Mr. Kasavich,
ADS LLC, DBA ADS Environmental Services, is pleased to provide our proposed Amendment No.
1 to the existing Citywide Wastewater Collection System Flow Monitoring Maintenance
Contract — FY 2025, City Secretary Contract No. 62655. This contract is dated January 21, 2025
and currently runs through September 30, 2025.
Amendment No. 1 seeks to reallocate $10,840.00 of unused funds to perform a full technical
field assessment for the following equipment at the City of Fort Worth Village Creek WTP:
- Accusonic Model 8510+ Flow Meter (Serial No. 0006)
- Accusonic Model 7510+ Flow Meter (Serial No. 1596)
The corresponding deliverables that will be provided to the City at the conclusion of the
assessment are as follows:
- Annual Certification Trip Report
- Certificate of Compliance and Operation
This assessment will serve to recertify both flow meters and will be completed no -later -than
July 16, 2025.
The contract amount for the full nine months of comprehensive flow monitoring services under
CSC No. 62655 totals $97,560.00 which equates to approximately $10,840.00 per month. To
accommodate the reallocation of funds outlined above to recertify the Accusonic flow meters
at the Village Creek WTP, ADS LLC proposes to eliminate the comprehensive flow monitoring
services for the ninth and final month (September 2025) for CSC No. 62655 for the ten (10)
contact meters that ADS LLC services. The services that will be eliminated during this time
frame include the following:
- Flow monitoring data management, analysis and reporting.
- On -going flow monitoring network operation, service, maintenance and calibrations.
- Other tasks/task orders (Monitor removals, relocations, installs, etc.).
The comprehensive flow monitoring services for the ten (10) contact meters that ADS LLC
currently services will, therefore, terminate on August 31, 2025 under this Amendment No. 1.
All other terms and conditions of the agreement dated January 21, 2025 shall remain in full
force and effect.
New Pav Items
Accusonic Flow Meter Assessment— Model 8510+: Field assessment and recertification of
Accusonic Model 8510+ Flow Meter (Serial No. 0006) at the Village Creek WTP.
Accusonic Flow Meter Assessment—Model7510+: Field assessment and recertification of
Accusonic Model 7510+ Flow Meter (Serial No. 1596) at the Village Creek WTP.
Contract Item Fee
Original Contract Amount $97,560.00
Amendment No. 1 $0.00
Amended Contract Value $97,560.00
Fund Reallocation $10,840.00
Accusonic Flow Meter Assessment — Model 8510+ $5,420.00
Accusonic Flow Meter Assessment — Model 7510+ $5,420.00
Please see below the Original Contract Pricing Table and the Amendment No. 1 Contract Pricing
Table for reference.
Please let me know if you have any questions or if there is any additional information that we
can provide. Our team is also available for a conference call if needed. I can be reached by
email or at 214-399-4292 should you need to discuss this in more detail.
Regards,
John P. Jenkins
Key Account Manager
ADS Environmental Services
iienkinsl@idexcorp.com
v ENVIRONMENTAL
SERVICES
ORIGINAL CONTRACT PRICING TABLE
CITYWIDE WASTEWATER COLLECTION SYSTEM TEMPORARY FLOW METERING
SCOPE OF SERVICES BID PROSPOSAL
TECHNICAL & FUNCTIONAL REQUIREMENTS: Contractor shall provide all labor, material, supplies and equipment to
perform the required tasks bid
Flow Meterina Services (Contact Meters). - Includes flow meters, installation, calibration,
servicing, removal, data management, flow analysis and reporting, plus redeployment in Bidder's Proposal
accordance with RFP No. 18-xxxx
Bidlist Description Unit of Bid Unit Price Bid Value
Item No. Measure Quantity
Meter Site Maintenance, as Required Including Scheduled Calibrations
1 (bi-weekly for the first 60 days and then quarterly thereafter) - Monthly MO 90
Servicing Fee (monthly fee per meter, assumed up to 10 CONTACT
meters deployed during a 9 month period)
$800.00 $72,000.00
Contact Base Bid Total: $72,000.00
Contact Bid Alternate No. 1
Additional Data Management, Analysis and Reporting - Monthly Data
BA#1 Mangement, Analysis, and Reporting Fee (monthly fee per meter, up to MO 90
10 CONTACT meters deployed during a 9 month period) as noted in
Section 30.0 "Scope of Work". This is an ADD/DEDUCT Item.
$284.00 $25,560.00
Contact Bid Alternate No. 1 Total: $25,560.00
Total Contact Base Bid + Contact Bid Alternate No. 1 = $97,560.00
AMENDMENT NO. 1 CONTRACT PRICING TABLE
CITYWIDE WASTEWATER COLLECTION SYSTEM TEMPORARY FLOW METERING
SCOPE OF SERVICES BID PROSPOSAL
TECHNICAL & FUNCTIONAL REQUIREMENTS: Contractor shall provide all labor, material, supplies and equipment to
perform the required tasks bid
Flow Meterina Services (Contact Meters) - Includes flow meters, installation, calibration,
servicing, removal, data management, flow analysis and reporting, plus redeployment in Bidder's Proposal
accordance with RFP No. 18-xxxx
Bidlist Description Unit of Bid Unit Price Bid Value
Item No. Measure Quantity
Meter Site Maintenance, as Required Including Scheduled Calibrations
(bi-weekly for the first 60 days and then quarterly thereafter) — Monthly
1 Servicing Fee (monthly fee permeter, assumed up to 10 CONTACT MO 80
meters deployed during a 9 month period - Reduced to 8 months for
Amendment No. 1)
Contact Base Bid Total
Contact Bid Alternate No. 1
Additional Data Management, Analysis and Reporting — Monthly Data
Management, Analysis, and Reporting Fee (monthly fee per meter, up to
BA#1 10 CONTACT meters deployed during a 9 month period) as noted in MO 80
Section 30.0 "Scope of Work". This is an ADD/DEDUCT Item. Reduced
to 8 months for Amendment No. 1. $284.00
Contact Bid Alternate No. 1 Total:
Item No.
$800,00 $64,000.00
$64,000.00
Description
New Pay Items
Unit of Bid
Unit Price
Measure Quantity
$22,720.00
$22,720.00
Bid Value
1 Accusonic Flow Meter Assessment - Model 8510+ (Serial No. 0006) Each 1 $5,420.00 $5,420.00
2 Accusonic Flow Meter Assessment - Model 7510+ (Serial No. 1596) Each 1 $5,420.00 $5,420.00
New Pay Items Total: $10,840.00
Total Contact Base Bid + Contact Bid Alternate No. 1 + New Pay Items:I $97,560.00