City of Fort Worth
Change Order Request
Project Name E Long Avenue Bridge Improvements City Sec # l 53886
Client Project #(s)l 101384
Project Description Replacement of bridge deck, including bridge sidewalk, railing and steel members.
Contractorl Ragle, Inc. Change Order#1 4 1 Date
City Project Mgr.l Christian Cardona City Inspectorl
Dept.
Original Contract Amount
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date
Amount of Proposed Change Order
Revised Contract Amount
Original Funds Available for Change Orders
Remaining Funds Available for this CO
Additional Funding (if necessary)
TPW
$6,050,859.05
$1,486,263.16
$7,537,122.21
$0.00
$7,537,122.21
$99,919.44
$0.00
7/22/2025
Eddie Walker
Contract Time
Totals (CD)
$6,050,859.05 40
$1,486,263.16 214
$7,537,122.21 754
$7,537,122.21 754
$99,919.44
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT 24.56%
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%) $7,563,573.81
This change order will add a new bid item to install grouted rock riprap along the southeast embankment of the E Long Avenue Bridge. The recently constructed concrete mow
strip in this area steepened the embankment, increasing the erosion risks. To mitigate these risks, this change order will add a new bid item to install the rock riprap for erosion
protection. A specified remobilization bid item will be added to this change order to allow both the contractor and subcontractor to mobilize the necessary material and
equipment to perform the required work. Additional quantities to the existing bid items for traffic control and block sod will also be added to this change order to provide sufficient
traffic control and to install block sod around the constructed area.
Cost — Staff has verified from previous bid items that the cost for the additional work is fair and reasonable.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full
(both time and money) for all costs arising out of, or incidental to, the above Change Order. The Project/Program Manager signing below acknowledges that
he/she is the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements.
ontractor's Compan Name ontra or a ontract Si nature
Ragle, Inc. Vick Adhikari vc(dd6lkar l u l�,sd ... ,,1 07/28/25
ection Supervisor
Date
07/28/25
Project and ConTleMompliance Manage
Date
07/29/25
Program Manager
Date
Senior Capital Project Officer
Date
08/05/25;
08/05/25
Date
Director, Contracing Department Dept
Date
Pn+naa L. waAsaok
1I,,L (A,;57m5134140CD1
08/05/25
08/05/25
Assistant City Attorney
Date
Assistant City Manager
Date
08/07/25
08/10/25
jam Council Actio
M&C Number N/A M&C Date Approved I N/A
ATTEST: onn
;so °9dA—
Jannette Goodall, City Secretary o�°s ovio
aaIl4an�aa5ap
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
FORT WORTH
—
City of Fort Worth
1j*'
Change Order Additions
Project Name 1 E Long Avenue Bridge Improvements
City Sec # 53886
Client Project # 1 101384
1
Contractorl Ragle, Inc.
I PMI Christian Cardona I
Inspectorl Eddie Walker
l
Change Order Submittal # ®
Date 1 7/22/2025
ADDITIONS
I I EM
UE5(:RIP I IUN
UEP I Uty j
Unit Unit host
I otal 1
32
3292.0100 Block Sod Placement
I PW 1 /2.(l(l(000OC i
SY $B.bU
$1,462.001
43
3471.0001Traffic Control
TPW 0.3000000Ci
MO $13,000.00
$3,900.001
70
3137.0105 Medium Stone Riprap, grouted
TPW 253.00OOOOOQ
SY $168.89
$42,729.171
71
0170.0101 Specified Remobilization
TPW 1.000OOOOCi
EA $6,390.00
$6,390.001
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
l
I
TPW
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
$54,481.171
1
I
I
1
Sub Total Additions
1
1
$54,481.171
Change Order Additions Page 2 of 4
Foxe City of Fort Worth
Change Order Deletions
Project Name I E Long Avenue Bridge Improvements City Sec # 1 53886
Client Project # 1 101384 1
Contractorl Ragle, Inc. IPMI Christian Cardona I Inspectorl Eddie Walker I
Change Order Submittal # ® Date 1 7/22/2025 1
DELETIONS
IIFM UEb(;KIF'I IUN UFF'I UN Unit Unit host total
46 9999.0001 Construction Allowance IPW U. 14000UUU Lb $2UU,000.UU $26,uluum1
47A 9999.0003 Railroad Coordination TPW 0.4413528U LS $60,000.0U $26,481.171
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
T15W $54,481171
1
1
1
1 Sub Total Deletions $54,481.171
Change Order Deletions Page 3 of 4
N/A
M/SBE for this Change Order
M/SBE Sub Type of Service Amount for this CO
N/A N/A
Total $0.00
Previous Change Orders
co # DATE AMOUNT
1 6/27/2022 $900,080.56
2 11 /21 /2023 $60,644.60
3 3/3/2025 $525,538.00
Total I $1,486,263.16
FORT WORTH.
Routing and Transmittal Slip
Transportation & Public Works Department
DOCUMENT TITLE: Change Order #4 - E Long Ave Bridge Improvement
M&C: CPN:
101384 CSO:
53886
DOC#:
Date:
To:
Name
Department
Initials
Date Out
1.
Sophia Flores
TPW - initials
��
07/28/25
2.
Vick Adhikari
Ragle, Inc. - signature
-L14
07/28/25
VA
3.
Eddie Walker
TPW - signature
W,,,,e,
07/28/25
4.
Mike Glover
TPW - signature
M h�a
07/28/25
5.
Christian Cardona
TPW - signature
GG�
07/29/25
6.
Gregory Robbins
TPW - signatures
08/05/25
7.
Mary Hanna
TPW - signature
mF,'
08/05/25
8.
Patricia Wadsack
TPW - signature
pLW
08/05/25
9.
Lauren Prieur
TPW - signaturep
LP
08/05/25
10.
Doug Black
Legal - signature
QR
08/07/25
11.
Jesica McEachern
CMO - signature
Douglas Black
CA
08/10/25
12.
Jannette Goodall
CSO - signature
08/11/25
13.
TPW Contracts
DOCUMENTS FOR CITY MANAGER'S
SIGNATURE: All documents received from any
and all
City Departments requesting City Manager's signature for approval MUST BE
ROUTED TO THE APPROPRIATE
ACM for approval first. Once the ACM has signed the
routing slip, Jay will review and take the next steps.
NEEDS TO BE NOTARIZED: ❑YES ®No
RUSH: ®YES ❑No SAME DAY: ❑YES ❑No NEXT DAY: ❑YES ®No
ROUTING TO CSO: ®YES ❑No
Action Required:
❑ As Requested
❑ For Your Information
® Signature/Routing and or Recording
❑ Comment
❑ File
❑ Attach Signature, Initial and Notary Tabs
Return To: TPWContracts(&,FortWorthTexas.2ov at ext. 7233 for pick up when completed.