HomeMy WebLinkAboutContract 61173-FP3-FP3
FORT WORTH.
City Secretary 61173
Contract No.
Date Received 7/31/2025
AT
NOTICE OF PROJECT COMPLETION
(Developer Projects)
The Transportation and Public Works Department upon the recommendation of the Project
Manager has accepted the following project as complete:
Project Name: Summer Crest Phase 2
City Project No.: 103974
Improvement Type(s): ❑x Paving ❑x Drainage ❑x Street Lights ❑x Street Signs
Original Contract Price: $1,885,569.94
Amount of Approved Change Order(s):
Revised Contract Amount:
Total Cost of Work Complete: $1,885,569.94
1&,-= 07/30/2025
Arturo San cen (Jul 30, 202514:47:22 CDT)
Contractor Date
Superintendent
Title
Conatser Construction TX, LP.
Company Name
%Z
07/31/2025
Project Inspector
Date
Motadage
07/31/2025
Project Manager
Date
07/31/2025
CFA Manager
Date
07/31/2025
Lauren Prieur (Ju131, 202514:03 40 CDT)
TPW Director
Date
�_�
07/31/2025
Asst. City Manager
Date
Reason for reroute
OFFICIAL RECORD
Page 1 of 2
CITY SECRETARY
FT. WORTH, TX
Notice of Project Completion
Project Name: Summer Crest Phase 2
City Project No.: 103974
City's Attachments
Final Pay Estimate ❑x
Change Order(s): ❑ Yes ❑x N/A
Contractor's Attachments
Affidavit of Bills Paid
Consent of Surety
Statement of Contract Time
Contract Time: 160 WD Days Charged: 197 WD
Work Start Date: 7/10/2024 Work Complete Date: 5/19/2025
Completed number of Soil Lab Test: 866
Completed number of Water Test: 20
Page 2 of 2
FO TWORTH
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name SUMMER CREST PHASE 2
Contract Limits
Project Type DRAINAGE
City Project Numbers 103974
DOE Number 3974
Estimate Number 1 Payment Number 1
City Secretary Contract Number
Contract Date
For Period Ending 5/19/2025
WD
Project Manager NA
Contractor CONATSER CONSTRUCTION TxLP
5327 WICHITA ST
FORT WORTH, TX 76119
Inspectors G.DEYON / A.TAYLOR
Contract Time 16WD
Days Charged to Date 197
Contract is 100.00 Complete
Friday, June 27, 2025 Page 1 of 5
City Project Numbers 103974 DOE Number 3974
Contract Name SUMMER CREST PHASE 2 Estimate Number I
Contract Limits Payment Number 1
Project Type DRAINAGE For Period Ending 5/19/2025
Project Funding
UNIT III: DRAINAGE IMPROVEMENTS
Item
Description of Items
Estimated Unit
Unit Cost
Estimated
Completed
Completed
No.
Quanity
Total
Quanity
Total
1
33" RCP, CLASS III
587 LF
$120.00
$70,440.00
587
$70,440.00
2
30" RCP, CLASS 111
767 LF
$110.00
$84,370.00
767
$84,370.00
3
24" RCP, CLASS lII
406 LF
$90.00
$36,540.00
406
$36,540.00
4
2 1 " RCP, CLASS lII
158 LF
$85.00
$13,430.00
158
$13,430.00
5
18" RCP, CLASS lII
108 LF
$80.00
$8,640.00
108
$8,640.00
6
4X3 BOX CULVERT
35 LF
$275.00
$9,625.00
35
$9,625.00
7
4X2 BOX CULVERT
109 LF
$255.00
$27,795.00
109
$27,795.00
8
10' CURB INLET
10 EA
$4,200.00
$42,000.00
10
$42,000.00
9
15' CURB INLET
4 EA
$5,200.00
$20,800.00
4
$20,800.00
10
20' CURB INLET
1 EA
$6,200.00
$6,200.00
1
$6,200.00
11
4' STORM JUNCTION BOX
6 EA
$6,000.00
$36,000.00
6
$36,000.00
12
Y STORM JUNCTION BOX
1 EA
$7,000.00
$7,000.00
1
$7,000.00
13
MANHOLE STEPS
23 EA
$250.00
$5,750.00
23
$5,750.00
14
30" SLOPING HEADWALL
1 EA
$4,500.00
$4,500.00
1
$4,500.00
15
2 1 " SLOPING HEADWALL
1 EA
$4,000.00
$4,000.00
1
$4,000.00
16
18" SLOPING HEADWALL
5 EA
$3,500.00
$17,500.00
5
$17,500.00
17
4'X3' SLOPING HEADWALL
1 EA
$7,500.00
$7,500.00
1
$7,500.00
18
4'X2'SLOPINGHEADWALL
2 EA
$7,000.00
$14,000.00
2
$14,000.00
19
6' CONCRETE PILOT CHANNEL
421 LF
$55.00
$23,155.00
421
$23,155.00
20
LARGE STONE RIPRAP, DRY
94 SY
$125.00
$11,750.00
94
$11,750.00
21
TRENCH SAFETY
2174 LF
$1.00
$2,174.00
2174
$2,174.00
Sub -Total of Previous Unit $453,169.00 $453,169.00
-------------
UNIT IV: PAVING IMPROVEMENTS
Item
Description of Items
Estimated Unit
Unit Cost
Estimated
Completed
Completed
No.
Quanity
Total
Quanity
Total
---------------------------------------
1
6" CONC PVMT
19345 SY
$52.00
005,940.00
19345 1,005,940.00
2
4" CONC SIDEWALK
5970 SF
$4.50
$26,865.00
5970
$26,865.00
3
BARRIER FREE RAMP, TYPE P-1
18 EA
$2,000.00
$36,000.00
18
$36,000.00
4
6" LIME TREATMENT
20679.14 SY
$3.50
$72,376.99
20679.14
$72,376.99
5
HYDRATED LIME
310.187 TN
$235.00
$72,893.95
310.187
$72,893.95
Friday, June 27, 2025 Page 2 of 5
City Project Numbers 103974
Contract Name SUMMER CREST PHASE 2
Contract Limits
Project Type PAVING
Project Funding
DOE Number 3974
Estimate Number 1
Payment Number 1
For Period Ending 5/19/2025
6
TRAFFIC CONTROL
2 MO
$1,500.00
$3,000.00
2
$3,000.00
-------------------
Sub -Total of Previous Unit
$1,217,075.94
$1,217,075.94
UNIT V: STREETLIGHTS IMPROVEMENTS
Item
Description of Items
Estimated Unit
Unit Cost
Estimated
Completed
Completed
No.
Quanity
Total
Quanity
Total
1
2" CONDT PVC SCH 80 (T)
1965 LF
$15.00
$29,475.00
1965
$29,475.00
2
FURNISH/INSTALL LED LIGHTING FIXTURE
26 EA
$1,200.00
$31,200.00
26
$31,200.00
(70-WATT ATBO COBRA HEAD)
3
RDWY ILIUM FOUNDATION TY 1,2, AND 4
26 EA
$1,200.00
$31,200.00
26
$31,200.00
4
FURNISH/INSTALL RDWAY ILIUM TY 11 POLE
26 EA
$3,200.00
$83,200.00
26
$83,200.00
5
FURNISH/INSTALL TYPE 33B ARM
26 EA
$400.00
$10,400.00
26
$10,400.00
6
NO 10INSULATED ELEC CONDR
3930 LF
$5.00
$19,650.00
3930
$19,650.00
Sub -Total of Previous Unit
$205,125.00
$205,125.00
UNIT VI: STREET SIGN IMPROVEMENTS
Item Description of Items Estimated Unit Unit Cost Estimated Completed Completed
No. Quanity Total Quanity Total
1 INSTALL ALUM SIGN GROUND MOUNT 12 EA $850.00 $10,200.00 12 $10,200.00
Sub -Total of Previous Unit $10,200.00 $10,200.00
Friday, June 27, 2025 Page 3 of 5
City Project Numbers 103974 DOE Number 3974
Contract Name SUMMER CREST PHASE 2 Estimate Number I
Contract Limits Payment Number 1
Project Type STREET SIGNS For Period Ending 5/19/2025
Project Funding
Contract Information Summary
Original Contract Amount $1,885,569.94
Change Orders
Total Contract Price $1,885,569.94
Total Cost of Work Completed $1,885,569.94
Less % Retained $0.00
Net Earned $1,885,569.94
Earned This Period $1,885,569.94
Retainage This Period $0.00
Less Liquidated Damages
Days @ / Day
LessPavement Deficiency
Less Penalty
Less Previous Payment
Plus Material on Hand Less 15%
Balance Due This Payment
$0.00
$0.00
$0.00
$0.00
$0.00
$1,885,569.94
Friday, June 27, 2025 Page 4 of 5
City Project Numbers 103974
Contract Name SUMMER CREST PHASE 2
Contract Limits
Project Type STREET SIGNS
Project Funding
Project Manager NA
Inspectors G.DEYON / A.TAYLOR
Contractor CONATSER CONSTRUCTION TxLP
5327 WICHITA ST
FORT WORTH, TX 76119
DOE Number 3974
Estimate Number I
Payment Number I
For Period Ending 5/19/2025
City Secretary Contract Number
Contract Date
Contract Time 160 WD
Days Charged to Date 197 WD
Contract is .000000 Complete
CITY OF FORT WORTH
SUMMARY OF CHARGES
Line Fund Account Center Amount Gross Retainage Net
Funded
Total Cost of Work Completed $1,885,569.94
Less % Retained $0.00
Net Earned $1,885,569.94
Earned This Period $1,885,569.94
Retainage This Period $0.00
Less Liquidated Damages
0 Days @ $0.00 / Day
$0.00
LessPavement Deficiency
$0.00
Less Penalty
$0.00
Less Previous Payment
$0.00
Plus Material on Hand Less 15%
$0.00
Balance Due This Payment
$1,885,569.94
Friday, June 27, 2025 Page 5 of 5
FORTWORTH.
M,
TRANSPORTATION AND PUBLIC WORKS
June 24, 2025
Conatser Construction TX, LP
5237 Wichita Street
Fort Worth, Tx 76119
RE: Acceptance Letter
Project Name: Summer Crest Phase 2
Project Type: Water, Sanitary Sewer, Storm Drain, Paving, Street Lights & Signage
City Project No.: 103974
To Whom It May Concern:
On June 24, 2025 a final inspection was made on the subject project. There were no punch list items
identified at that time. The final inspection indicates that the work meets the City of Fort Worth
specifications and is therefore accepted by the City. The warranty period will start on June 24, 2025,
which is the date of the final inspection and will extend of two (2) years in accordance with the Contract
Documents.
If you have any questions concerning this letter of acceptance, please feel free to contact me at
Mosadago Mohammdeen.
Sincerely,
Mosadage Moh wwieen, P. U.
Mosadago Mohammdeen, Project Manager
Andrew Goodman, Program Manager
Cc: Andre Taylor, Inspector
Gary Deyon, Inspection Supervisor
Lorrie Pitts, Senior Inspector
Andrew Goodman, Program Manager
Peloton Land Solutions, Consultant
Conaster Construction, Contractor
SJ Rollning Hills Development, Developer
File
E-Mail: TPW_Acceptance@fortworthtexas.gov
Rev. 08/20/19
AFFIDAVIT
STATE OF TEXAS
COUNTY OF TARRANT
Before me, the undm. igncd authority, a Notary )Public in d* state and county aforesaid,
on this day personally appeared Brock Huggins, President of Conatser Management Croup, Inc.,
general partner of Conatser Construction TX. LP, known to me to be a credible person, who
being by me duly sworn, upon his oath dcpos€d and said:
That all persons, firms, associations, corporations or other organizations furnishing
labor and/or materials have been paid in full.
That the wage scup: established by the City Council in the City of Fort Worth. has
heen paid in full, and
That there are no claims pending for personal injury andlor prcipcoy damages,
On Contract deserihed as:
SUMMER CREST PH. 3H
WATER, SANITARY SEWER, DRAINAGE,
PAVING, & STREET LIGHT IMPROVEMENTS
CPA PRJ # 23-0013
CITY PROJECT # 103974
CITY OF FORT WORTH
STATE OF TEXAS
CONATSER CONSTRUCTION TIC, LP
Brock I lugff
Subscribed and sworn to before rime this 120'day of June, 2025.
KOUA a-Y-J
KATA INE Mss
10r41 KKx, FrAtU F MAI Notmy Pub] is in Warrant County, Texas
w 13349T933
COM4l til[P. 1#-30 -34�#
■
CONSENT OF
SURETY COMPANY
TO FINAL PAYMENT
Conforms with the American Institute of
Architects, AIA Document G707
PROJECT:
Inama, addreSa)5urnrner Crest Phase 38
Fort Worth. TX
TO (Owner)
OWNER
❑
ARCHITECT
❑
CONTRACTOR
❑
SURETY
OTHER
Bond No 0260237
Fo—AMUNS FAMILY JOINT VENTURE AND THE ClrY ARCHITECT'S PROJECT NO: CFA23.0113
OF FORT WORTH CONTRACT FOR.
7201 livnkwq view Dr. Swe 101 Waler, Sanitary Sewer. Drateage, P"Pg, Street Ltghl A Street 8+9ns
fmprovemmnis for Summer Crest Phaso B
L worm Tx 76132 CONTRACT [SATE:
CONTRACTOR: CONATSER CONSTRUCTION TX. L P
I13 irccartianca with the provisions of the Contract between the Owner and the Contractor as indicated nbwe, to
Itwa k%wt arms' irrd addram of Swily Camparrfi
BERKLEY INSURANCE COMPANY
475 Slaam at Road
GMarrmch CT OU30 SURETY COMPANY
OnbOnd0f Irv■ ■uarT A■ma arld IOdnsarr of CMV41,1w1
CONATSER CONSTRUCTION TX. L-P_
532T W Mts St
Fort Woo TX 76119- 035
, CONTRACTOR,
hereby approves of the final payment to the Contractor, and agrees that fnnl payment t0 the Contractor shall not relieve
the Surety Corn piny of any aFits oobliWions to Chafe efion name ■nd edirass or Qwner]
HAWK]NS FAMILY JOINT VENTURE AND T14E CITY OF FORT WORTH
7201 NBwkrns View Or. Suite 101
For Worth TX 76132 , OWNER,
as sc1 Forth in the said Sur-ry Company's bond_
rN WITMESS,W')MPLEOF,
the Surety Company has hereunto set its hand this
Attest; �r►f i��.
(Sea]):
tilt, day of ,tune, 2025
BERKL.EY INSURANCE COMPANY
Surety Company
5ig� of Authorized Representative
Aita,nev-an-Fact
M011. Trio form r to bo mW as a Coftomm doeumreM is AJA 9r]C1jWNT 01OE. CONTRACTOR'S AFFIDAVIT OF PAYMENT OF DEBTS AND CLAWS,
Cvmrrt Edom
ONE PAGE